1 City of Taunton to Contract Documents for Main Lift Pumping Station Foundation CWSRF No The following changes and additional information are hereby made part of the Contract Documents. Addendum 2 consists of the information provided below and the following documents: Attachment 1 - Verification of Receipt Attachment 2 Filed Sub-bid Results Attachment 3 Contractor Questions Attachment 4 Revised Contract Drawings Project Takers List (as of 11/2/2018) Waterline Industries G.V.W. Incorporated P. Gioioso & Sons, Inc. Biszko Building Systems, Inc. Superior Gunite Dodge Docs Beacon Waterproofing WES Construction Corp. Projectdog The Blue Book Building & Construction Network Armani Restoration Methuen Construction Construct Connect Commercial Masonry Weston & Sampson Quinn Bros. of Essex, Inc. WM Schultz Construction Chapman Waterproofing Company LMH Civil Construction, LLC Folan Waterproofing & Construction Co., Inc. Hart Engineering Corp. John W. Egan Co., Inc. Drawings 1. Sheet No. S-10. o Delete sheet S-10 in its entirety and insert the revised sheet S-10 in Attachment 4 2. Sheet No. S-11 o Delete sheet S-11 in its entirety and insert the revised sheet S-11 in Attachment 4 Page 1 of 6

2 ATTACHMENT 1 Verification of Receipt Page 2 of 6

3 City of Taunton to Contract Documents for Main Lift Pumping Station Foundation CWSRF No Verification of Receipt Please Sign, Date, and this form to at BETA Group, Inc. Upon Receipt Receipt of is hereby acknowledged: this day of, 20. By: Title: Company Name: Addendum No. 1 Attachment 1

4 ATTACHMENT 2 Filed Sub-bid Results Page 3 of 6

5 City of Taunton, MA Department of Public Works Main Lift Sewer Pumping Station Foundation Contract No. S , CWSRF No Filed Sub-bid Bid Tabulation -- October 30, 2018 Category: Miscellaneous Metals Contractor Bid Amount DCAMM Update Statement D/WBE - D/MBE Bid Bond Acknowledge Addendum 1 L & L Contracting, Inc. $270, Yes D/WBE Yes Yes No Restricted Quinn Bros. of Essex, Inc. $274, Yes No Yes Yes Yes (1) 1: Quinn Bros.'s bid may be used by any general bidder except Seaver Construction, Inc. and GTC Construction Management, Inc. FILED SUB-BID RESULTS

6 City of Taunton, MA Department of Public Works Main Lift Sewer Pumping Station Foundation Contract No. S , CWSRF No Filed Sub-bid Bid Tabulation -- October 30, 2018 Category: Waterproofing, Dampproofing, and Caulking Contractor Bid Amount DCAMM Update Statement D/WBE - D/MBE Bid Bond Acknowledge Addendum 1 Restricted Beacon Waterproofing & Restoration $108, Yes No Yes Yes Yes (1) Folan Waterproofing & Construction Co., Inc. $162, Yes D/WBE Yes Yes No Chapman Waterproofing Co. $178, Yes No Yes Yes No Armani Restoration, Inc. $207, Yes No Yes Yes No 1: Beacon's bid may be used by any general bidder except GVW and G+R FILED SUB-BID RESULTS

7 ATTACHMENT 3 Contractor Questions Page 4 of 6

8 CONTRACTOR QUESTIONS & RESPONSES 1. Question: I noticed that on the Addendum No. 1 the plan holders say Biszko Contracting, that is incorrect. It should say Biszko Building Systems, Inc. Is there any way we can change that? - Response: The takers list has been updated as requested. Page 5 of 6

9 ATTACHMENT 4 Revised Contract Drawings Page 6 of 6

10 PREPARED BY REGISTERED PROFESSIONAL SUBCONSULTANT PROJECT Main Lift 2 Pump Station Taunton, MA TITLE 10/31/2018 3:08 PM J:\TAUNTON\MAIN LIFT PUMP STATION\AUTOCAD\DRAWINGFILES\STRUCTURAL\ADDENDUM2\S-10\5530_SR10.DWG (BETA STB BW.STB) 1 2 NO. REVISIONS DRAWN BY: DW DESIGNED BY: TW CHECKED BY: MG ISSUE DATE: BETA JOB NO.: 5530 SCALE UNLESS OTHERWISE NOTED OR CHANGED BY REPRODUCTION SHEET NO. Sections (2 of 3) 1 CONST. JOINT ADDITION 10/ SLOPED CONCRETE FILL 10/2018 OCTOBER 2018 AS SHOWN S-10 DATE

11 PREPARED BY REGISTERED PROFESSIONAL SUBCONSULTANT PROJECT Main Lift Pump Station Taunton, MA TITLE 10/31/2018 3:06 PM J:\TAUNTON\MAIN LIFT PUMP STATION\AUTOCAD\DRAWINGFILES\STRUCTURAL\ADDENDUM2\S-11\5530_SR11.DWG (BETA STB BW.STB) 1 2 NO. REVISIONS DRAWN BY: BN DESIGNED BY: TW CHECKED BY: MG ISSUE DATE: BETA JOB NO.: 5530 SCALE UNLESS OTHERWISE NOTED OR CHANGED BY REPRODUCTION SHEET NO. Sections (3 of 3) 1 CONST. JOINT ADDITION 10/ SLOPED CONCRETE FILL 10/2018 OCTOBER 2018 AS SHOWN S-11 DATE