Work Order (Bid Form) UPPER EAST TENNESSEE HUMAN DEVELOPMENT AGENCY

Size: px
Start display at page:

Download "Work Order (Bid Form) UPPER EAST TENNESSEE HUMAN DEVELOPMENT AGENCY"

Transcription

1 UPPER EAST TENNESSEE HUMAN DEVELOPMENT AGENCY WORK ORDER INFORMATION Work Order Type: Weatherization Audit Name: 18018UE10237 CLIENT INFORMATION Address: MOUNTAIN CITY, TN AGENCY INFORMATION Agency: UETHDA Agency Phone: (423) Address: 301 Louis Street Fax: (423) Kingsport, TN Address: Company Name & License Number: Contractor's Signature: COMMENT 370 SQ. FT. MOBILE HOME MANUFACTURED IN A 290 SQ. FT. ADDITION WAS BUILT IN THERE IS A METAL ROOF RETRO-FIT OVER THE ENTIRE STRUCTURE. ALL WORK TO BE DONE IN ACCORDANCE WITH THE TENNESSEE STANDARD WORK SPECIFICATIONS AS ADOPTED BY THE TENNESSEE HOUSING DEVELOPEMANT AGENCY. CONTRACTOR IS RESPONSIBLE TO VERIFY DIMENSIONS AND SCOPE OF WORK PRIOR TO BID. SURVEY ON 4/7/2016 BY RON CARLISLE (423) INITIAL BLOWER DOOR 1924@-50 POST WORK TARGET MUST BE REACHED OR EXCEEDED CERTIFIED FIRM/RENOVATOR REQUIRED Page 1 of 13

2 Measures Measure 1 Wall Fiberglass Batt Comment INSULATE EXTERIOR THE WALLS OF THE MOBILE HOME- REMOVE AND REPLACE THE VINYL SIDING AS NEEDED TO COMLETE MEASURE. INSULATION CAN BE BATT OR BLOWN, BUT MUST BE FIBERGLASS MATERIAL. THE WALL STUDS ARE 2" X 3" 1 Insulation Wall Insulation -Faced SqFt Batt - R-13 Wall Insulation -Faced SqFt Batt - R-13 Measure Sub : Sub : Page 2 of 13

3 Measure 2 Belly Fiberglass Loose [Addition] Comment INSULATE THE ADDITION FLOOR FROM UNDERNEATH- SUPPORT THE INSULATION WITH A BELLY MEMBRANE. INSULATE THE AREA THAT IS ACCESSABLE- PART OF THE ADDITION HAS LOW CLEARANCE MAKING IT INACCESSABLE. 1 Insulation Floor Insulation - Bag 6 Fbergls,Blwn Floor Insulation - Bag 6 Fbergls,Blwn Measure Sub : Sub : Measure 3 Roof Fiberglass Loose Comment INSTALL FIBERGLASS INSULATTION IN THE MOBILE HOME ROOF- REACHABLE THROUGH THE PORCH CEILING ACCESS. CUT HOLES IN THE ROOF AS NEEDED TO FILL THE CAVITY AND PATCH THE HOLES AFTER INSULATING. THE ROOF IS UNDER A METAL ROOF ABOVE BUT SHOULD BE WATER TIGHT UPON COMPLETION. 1 Insulation Roof Insulation - Bag 12 Fbergls,Blwn Roof Insulation - Bag 12 Fbergls,Blwn Measure Sub : Sub : Page 3 of 13

4 Measure 4 Roof Fiberglass Loose [Addition] Comment BLOW 12" OF FIBERGLASS INSULATION OVER THE ADDITION- INSTALL A DAM (18' X 16") TO KEEP INSULATON FROM SPILLING INTO THE PORCH AREA. ADD INSULATION ABOVE THE MOBILE HOME ALSO. TOTAL AREA IS 660 SQ. FT. 1 Insulation Roof Insulation - Bag 5 Fbergls,Blwn Roof Insulation - Bag 5 Fbergls,Blwn Measure Sub : Sub : Measure 5 DWH Pipe Insulation Comment Insulate the first 6 feet of hot and cold water pipe from water heater. Both hot and cold water pipes should be insulated to R-3 for first 6ft.Cover elbows, unions, and other fittings sized to fit snug on pipe. 1 Insulation DWH Pipe Insulation Each 1 DWH Pipe Insulation Each 1 Measure Sub : Sub : Page 4 of 13

5 Measure 6 DWH Tank Insulation Comment AS PER THE TN SWS- Wrap the 20 Gallon Electric Water Heater Located UNDER THE KITCHEN COUNTER With R-10 or Better Insulation. Secure With Tape And Zip Ties. Bubble Wrap Insulation is NOT Allowed. Refer to the THDA Standard Work Specifications. 1 Insulation DWH Tank Insulation Each 1 DWH Tank Insulation Each 1 Measure Sub : Sub : Page 5 of 13

6 Measure 7 Glass Storm Windows [Addition] 10 Comment Storm Windows should be sized correctly and fit tightly in the opening. Caulk storm windows around the frame except for weep holes at the bottom that must not be sealed. If weep holes are not manufactured into the storm they should be drilled. Refer to house diagram with window sizes. Responsibility of contractor to verify measurements in the field before ordering window 1 Windows Glass storm windows SqFt 9.5 Glass storm windows SqFt Other Glass storm windows Each 1 Measure Sub : Sub : Page 6 of 13

7 Measure 8 Glass Storm Windows [Addition] 9 Comment Storm Windows should be sized correctly and fit tightly in the opening. Caulk storm windows around the frame except for weep holes at the bottom that must not be sealed. If weep holes are not manufactured into the storm they should be drilled. Refer to house diagram with window sizes. Responsibility of contractor to verify measurements in the field before ordering window 1 Windows Glass storm windows SqFt 9.5 Glass storm windows SqFt Other Glass storm windows Each 1 Measure Sub : Sub : Page 7 of 13

8 Measure 9 Glass Storm Windows [Addition] 8 Comment Storm Windows should be sized correctly and fit tightly in the opening. Caulk storm windows around the frame except for weep holes at the bottom that must not be sealed. If weep holes are not manufactured into the storm they should be drilled. Refer to house diagram with window sizes. Responsibility of contractor to verify measurements in the field before ordering window 1 Windows Glass storm windows SqFt Glass storm windows SqFt Other Glass storm windows Each 1 Measure Sub : Sub : Page 8 of 13

9 Measure 10 Glass Storm Windows [Addition] 7 Comment Storm Windows should be sized correctly and fit tightly in the opening. Caulk storm windows around the frame except for weep holes at the bottom that must not be sealed. If weep holes are not manufactured into the storm they should be drilled. Refer to house diagram with window sizes. Responsibility of contractor to verify measurements in the field before ordering window 1 Windows Glass storm windows SqFt Glass storm windows SqFt Other Glass storm windows Each 1 Measure Sub : Sub : Page 9 of 13

10 Measure 11 Glass Storm Windows 6 Comment Storm Windows should be sized correctly and fit tightly in the opening. Caulk storm windows around the frame except for weep holes at the bottom that must not be sealed. If weep holes are not manufactured into the storm they should be drilled. Refer to house diagram with window sizes. Responsibility of contractor to verify measurements in the field before ordering window 1 Windows Glass storm windows SqFt Glass storm windows SqFt Other Glass storm windows Each 1 Measure Sub : Sub : Page 10 of 13

11 Measure 12 Glass Storm Windows 4 Comment Storm Windows should be sized correctly and fit tightly in the opening. Caulk storm windows around the frame except for weep holes at the bottom that must not be sealed. If weep holes are not manufactured into the storm they should be drilled. Refer to house diagram with window sizes. Responsibility of contractor to verify measurements in the field before ordering window 1 Windows Glass storm windows SqFt Glass storm windows SqFt Other Glass storm windows Each 1 Measure Sub : Sub : Measure 13 CO Monitor is Needed Comment INSTALL A BATTERY OPERATED CO MONITOR 1 Health and Safety CO monitor Each 1 Labor Each 1 Measure Sub : Sub : Page 11 of 13

12 Measure 14 Install Bathroom Exhaust Fan Comment INSTALL A NEW TWO SPEED ASHRAE COMPLIANT BATH FAN, COMPLETE WITH NEW WIRING. VENT TO THE OUTSIDE WITH A DAMPER AND TRIM KIT. SET FOR 30 CFM CONTINUOUS EXHAUST 1 Health and Safety Bathroom exhaust fan Each 1 Labor Hour 1 Measure Sub : Sub : Measure 15 PressureRelief Piping Needed Comment INSTALL A PRESSURE RELIEF PIPE EXTENSION AS PER TN SWS 1 Health and Safety Pressure relief piping Each 1 Labor Each 1 Measure Sub : Sub : Page 12 of 13

13 Measure 16 REPLACE THE EXISTING WINDOW AIR CONDITIONER UNIT Comment REMOVE AND REPLACE THE EXISITNG WINDOW AIR CONDITIONER UNIT WITH A NEW ENERGY STAR WINDOW AIR CONDITIONER/HEAT PUMP -110 VOLT, 12 KBTU 10 Unspecified Misc Material Each 1 11 Labor LABOR Hour Measure Sub : Sub : Work Order Grand : Grand : Page 13 of 13