1 NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction January 2016 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION Harlan High School

2

3 2010 BOND SAVINGS PROJECTS

4 BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST) Architect Noonan Rittimann Project Architect John Rittimann NISD Project Manager Chris Parker Contractor Bartlett Cocke General Contractor Construction Amount - $25,371, (2010 Bond Savings) Construction Period April 2015 June 30, 2016 (53% Complete) Project Scope New 800 Student Elementary School Concrete superstructure, MEP rough-in, permanent power installation, masonry, structural steel, decking and drywall framing in progress.

5 BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST) (Jan. 7, 2015)

6 BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST)

7 BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST) (Jan. 11, 2016)

8 BENNIE L. COLE ELEMENTARY SCHOOL (VILLAGE at WESTPOINTE EAST)(Dec. 29, 2015)

9 BENNIE L. COLE ELEMENTARY SCHOOL (Future Library) (Dec. 29, 2015)

10 NORTHSIDE SPORTS GYM Architect Marmon Mok Project Architect Monty Howard NISD Project Manager Thomas Curiel Contractor Bartlett Cocke General Contractor Contract Amount $26,326, (2010 Bond Savings) Construction Period May 2015 October 2016 (23% Complete) Project Scope Provide a District-Wide Sports Gymansium at the Farris Complex. Site work, electrical and plumbing rough-ins in progress. Concrete foundation and columns being placed. Precast concrete seating being installed.

11 NORTHSIDE SPORTS GYM Aerial View (December 17, 2015)

12 NORTHSIDE SPORTS GYM Entry Perspective View

13 NORTHSIDE SPORTS GYM Plaza Perspective View

14 NORTHSIDE SPORTS GYM (January 11, 2016)

15 NORTHSIDE SPORTS GYM Seating Perspective View

16 NORTHSIDE SPORTS GYM (January 11, 2016)

17 2014 BOND PROJECTS

18 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Architect Garza Bomberger & Associates Project Architect Roy Lewis NISD Project Manager Jim Berg Contractor Joeris General Contractor GMP - $110,800, Construction Period October 2014 May 2017 (54% Complete) Project Scope New 2800 Student High School Notice to Proceed issued October 8, Site Construction began October 14, Site grading, 1 st,2 nd and 3 rd Floor framing and columns in progress. Underground utilities and Interior CMU walls, drywall framing, electrical, plumbing, and HVAC rough-in in progress. Roof steel erection, roof deck roofing and window installation in progress. Interior painting in progress. Exterior brick veneer in progress.

19 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Aerial (Dec. 22, 2015)

20 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Front Entrance

21 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (Jan. 11, 2016)

22 HARLAN HIGH SCHOOL (CONNECTION BETWEEN MAIN BUILDING and GYMS) (Jan. 11, 2016)

23

24 RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3) Architect O Neill Conrad Oppelt Project Architect Mark Oppelt NISD Project Manager Marilyn Sevedge Contractor Joeris General Contractor Contract Amount - $24,615, Construction Period April 2015 June 30, 2016 (49% Complete) Project Scope New 800 Student Elementary School Steel superstructure and masonry in progress. Plumbing, electrical and mechanical rough-ins in progress, site drainage. Window install in progress. Exterior damp roofing, insulation in progress. Brick starting.

25 RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3) Aerial (Dec. 22, 2015)

26 RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3) Front Entry

27 RANDALL H. FIELDS ELEMENTARY SCHOOL (formerly FM 471 # 3) (Jan. 11, 2016)

28 ADDITIONS AND RENOVATIONS PROJECTS IN PROGRESS

29 ELEMENTARY SCHOOL ISMS (Integrated Security Mgmt System) Consultant Combs Consulting Group NISD Project Manager Charles Pereira Contractor Convergint Technologies Construction Contract Award $13,422, Total Change Orders to Date - $661, Adjusted Construction Contract Amount - $14,084, Total Construction Contract Completed - $13,787, Balance to Finish Construction Contract - $297, Notice to Proceed January 23, 2013 Original Construction Completion May 31, 2014 Revised Construction Completion November 11, 2015 Contract Percentage Completion 98%

30 ELEMENTARY SCHOOL ISMS (Integrated Security Mgmt System) Project Scope Furnish and install all new interior and exterior security surveillance cameras, with access control electrified hardware and security alarm disarm keypads. Connect and integrate the existing intrusion alarm devices, motion sensors and glass break sensors at all existing campuses. 75 Elementary School Campuses have Substantial Completion Certificates. 2 Additional Middle School Campuses have Substantial Completion Certificates. 75 Elementary School Campuses have ISMS software training completed. 2 Additional Middle School Campuses have ISMS software training completed. 75 Elementary campuses have Post Warranty Documents completed. 2 Additional Middle school campuses have Post Warranty Documents completed.

31

32 RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Jim Berg Contractor D.L. Bandy Contract Amount - $4,782, Construction Period May 15, 2015 August 1, 2016 (46% Complete) Project Scope New Science Classroom Addition and Renovation. Site work and underground site utilities in progress. Exterior and interior CMU walls completed. Plumbing, electrical and HVAC rough-in in progress. Window install in progress. Brick veneer in progress. Interior painting in progress.

33 RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (Perspective)

34 RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (Front Entry Final Scheme)

35 RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (1 st Floor Plan)

36 RUDDER MIDDLE SCHOOL - SCIENCE LAB ADDITION (2 nd Floor Plan)

37 RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (January 8, 2016)

38 LUNA MIDDLE SCHOOL CLASSROOM ADDITION Architect Garza Bomberger & Associates Project Architect Roy Lewis NISD Project Manager Thomas Curiel Contractor Guido Brothers Construction Contract Amount - $3,198, Construction Period June 2015 June 2016 (32% Complete) Project Scope New Classroom Addition Pilot holes drilled for addition foundation. Piers are completed. Plumbing rough-in underway. Foundation columns completed.

39 LUNA MIDDLE SCHOOL CLASSROOM ADDITION (Site Plan)

40 LUNA MIDDLE SCHOOL CLASSROOM ADDITION (1 st Floor Plan)

41 LUNA MIDDLE SCHOOL CLASSROOM ADDITION (2 nd Floor Plan)

42 LUNA MIDDLE SCHOOL CLASSROOM ADDITION (Elevation)

43 LUNA MIDDLE SCHOOL CLASSROOM ADDITION (January 11, 2016)

44 2014 BOND PROJECTS IN BID/DESIGN PHASES

45

46 KALLISON RANCH #2 ES (ELLISON ES PROTOTYPE) Architect Garza Bomberger Project Architect Roy Lewis NISD Project Manager Marilyn Sevedge Contractor Guido Construction Construction Budget - $22,500, Tentative Construction Period May 7, 2016 May 26, 2017 Project Scope Construction of an 800 Student Elementary School

47 KALLISON RANCH #2 ES - (Ellison ES Prototype) Front Entrance

48 CHILD NUTRITION WAREHOUSE - Warehouse Renovation Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $3,000, Tentative Construction Period April 4, 2016 October, 2016 Project Scope Warehouse Renovation

49 CHILD NUTRITION WAREHOUSE - Warehouse Renovation (Aerial View)

50 ALLEN ES CLASSROOM - ADDITION/ADA/WINDOW UPGRADES Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Chris Parker Contractor TBD Construction Budget - $6,230, Tentative Construction Period March 7, 2016 November 7, 2016 Project Scope Classroom Addition/ADA/Window Upgrades Proposals in progress.

51 ALLEN ES CLASSROOM - (Rendering of Site and Floor Plans)

52 ALLEN ES CLASSROOM - (Rendering of Floor Plan, Elevation and Perspectives)

53 HOLMES HS FINE ARTS - UPGRADE Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager James Berg Contractor TBD Construction Budget - $14,000, Tentative Construction Period TBD Project Scope Fine Arts Building Replacement

54 THORNTON ES - MUSIC ROOM ADDITION Architect Pfluger Architects Project Architect Carr Hornbuckle NISD Project Manager James Berg Contractor TBD Construction Budget - $300, Tentative Construction Period June 6, 2016 August 5, 2016 Project Scope Music Room Addition

55 THORNTON ES - MUSIC ROOM ADDITION (Rendering of Site Plan)

56 THORNTON ES - MUSIC ROOM ADDITION (Rendering of Music Room Addition)

57 ZACHRY MS BUS CANOPY MODIFICATIONS Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Jim Berg Contractor TBD Construction Budget - $1,100, Tentative Construction Period February 8, 2016 July 1, 2016 Project Scope Proposal Evaluations in Progress Board approval recommendation scheduled for January.

58 ALE Upgrades at CLARK HS, JAY HS & PEASE MS & ESPARZA ES Library Addition Architect O Connell Robertson Project Architect Chris Narendorf NISD Project Manager Chris Parker Contractor TBD Construction Budget - $1,125, and $880, Tentative Construction Period March 4, 2016 August 5, 2016 Project Scope Upgrades of Existing ALE Classrooms and Library Addition for Esparza ES Bid Drawings To Be Issued in January.

59 GLENOAKS ELEMENTARY - Administration Upgrades Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $3,750, Tentative Construction Period March 14, 2016 March 3, 2017 Project Scope Administration Upgrades

60 GLENOAKS ELEMENTARY - (Rendering of Front Elevation)

61 CODY ES & LEON VALLEY ELEMENTARY - (CAFE & KITCHEN RENOVATIONS) Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Tom Curiel Contractor TBD Construction Budget - $3,500, Tentative Construction Period February 15, 2016 August 8, 2016 Project Scope Renovations to Cafeteria and Kitchen Proposals in Progress.

62 2016 SECURITY LOBBIES - LOCKE HILL ES, THORNTON ES, CARLOS COON ES, LEON VALLEY ES, POWELL ES, MICHAEL ES, MARY HULL ES AND CABLE ES Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $480, Tentative Construction Period February 1, 2016 August 1, 2016 Project Scope New Security Lobby for (10) Elementary Schools

63 NORTHSIDE ACTIVITY CENTER RENOVATIONS Architect Richard Sanchez Architects, Inc. Project Architect Richard Sanchez NISD Project Manager Thomas Curiel Contractor TBD Construction Budget - TBD Tentative Construction Period April 4, 2016 March 1, 2017 Project Scope Addition Program Phase

64 PAUL TAYLOR FIELD HOUSE RENOVATIONS Architect Garza Bomberger Architects Project Architect Roy Lewis NISD Project Manager Thomas Curiel Contractor TBD Construction Budget - TBD Tentative Construction Period April 2016 November 2016 Project Scope ADA Interior/Exterior Renovations Schematic Design Phase

65

66 2016 GROWTH & IMPROVEMENT

67 HARDIN SOCCER COMPLEX - UPGRADES Architect Nextgen Architects Project Architect Joel Hernandez NISD Project Manager Chris Parker Contractor TBD Construction Budget - TBD Tentative Construction Period February 1, 2016 July 5, 2016 Project Scope Replacement of existing ticket collection, concessions and officials trailer with a building. Contractor evaluation complete. Board approval recommendation scheduled for January.

68 2016 ATHLETIC AREA UPGRADES (JAY HS, CLARK HS, JONES MS & ROSS MS) Architect Nextgen Architects Project Architect Joel Hernandez NISD Project Manager Chris Parker Contractor TBD Construction Budget - TBD Tentative Construction Period May 30, 2016 August 8, 2016 Project Scope Installation of Athletic Storage Units and Interior Renovations. Site Verifications in progress. CDs in progress.

69 2016 CTE RENOVATIONS - (CLARK HS HOLMES HS, & TAFT HS) Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Jim Berg Contractor TBD Construction Period TBD Tentative Construction Period May 2, 2016 August 12, 2016 Project Scope Renovations to Cosmetology at Holmes and Taft, Health Science Technology at Clark, Residential Kitchen at Clark and Engineering Lab at Taft HS.

70 ROOFING PROJECTS

71 BOONE ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Raba Kistner Contractor TBD Budget $365, Construction Period June August 2016 Project Scope Roof Repair & Waterproofing

72 CABLE ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Austech Engineering Contractor TBD Budget $160, Construction Period June August 2016 Project Scope Roof Repairs & Waterproofing

73 HOWSMAN ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Raba Kistner Contractor TBD Budget $740, Construction Period June August 2016 Project Scope Roof Replacement & Waterproofing

74 ANSON JONES MIDDLE SCHOOL ROOFING PROJECT Roofing Consultant Hollon + Cannon Contractor TBD Budget $165, Construction Period June August 2016 Project Scope Roof Repair & Waterproofing 65% Review

75 LEWIS ELEMENTARY SCHOOL - ROOFING PROJECT Roofing Consultant Austech Contractor TBD Budget $200, Construction Period June August 2016 Project Scope Roof Repair & Waterproofing

76 LINTON ELEMENTARY SCHOOL - ROOFING PROJECT Roofing Consultant Raba Kistner Contractor TBD Budget $180, Construction Period June August 2016 Project Scope Roof Repair & Waterproofing

77 MARY HULL ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Hollon + Cannon Contractor TBD Budget $70, Construction Period June August 2016 Project Scope Roof Replacement & Waterproofing 65% Review

78 MAY ELEMENTARY SCHOOL - ROOFING PROJECT Roofing Consultant Hollon + Cannon Contractor TBD Budget $2,175, Construction Period June October 2016 Project Scope Roof Replacement & Waterproofing Board Approval Scheduled for January 19, 2016

79 TAFT HIGH SCHOOL ROOFING PROJECT Roofing Consultant Hollon + Cannon Contractor TBD Budget $1,885, Construction Period June December 2016 Project Scope Roof Replacement & Waterproofing Board Approval Scheduled for January 19, 2016

80 PAUL TAYLOR FIELD HOUSE ROOFING PROJECT Roofing Consultant Hollon + Cannon Contractor TBD Budget $525, Construction Period June August 2016 Project Scope Roof Replacement & Waterproofing Board Approval Scheduled for January 19, 2016

81 VILLARREAL ELEMENTARY SCHOOL ROOFING PROJECT Roofing Consultant Austech Contractor TBD Budget $110, Construction Period June August 2016 Project Scope Roof Repair & Waterproofing