SUBPROJECT: IMPROVEMENT AND UPGRADING OF THE CAI LAY- CAO LANH 220kV TRANSMISSION LINE

Size: px
Start display at page:

Download "SUBPROJECT: IMPROVEMENT AND UPGRADING OF THE CAI LAY- CAO LANH 220kV TRANSMISSION LINE"

Transcription

1 Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD Public Disclosure Authorized Public Disclosure Authorized ENVIRONMENTAL MANAGEMENT PLAN PROJECT TRANSMISSION EFFICIENCY PROJECT (TEP) SUBPROJECT: IMPROVEMENT AND UPGRADING OF THE CAI LAY- CAO LANH 220kV TRANSMISSION LINE Public Disclosure Authorized PREPARED BY Power Engineering Consulting Joint Stock Company 3 Ho Chi Minh City, December 2014

2 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" TABLE OF CONTENT 1. INTRODUCTION POLICY, REGULATIONS, AND ADMINISTRATIVE FRAMEWORKS Government Regulations: World Bank Safeguard Policies SUBPROJECT DESCRIPTION Objectives of the Subproject Scope of the subproject Subproject Main Work Volume Main Activities Before and During Construction Subproject implementation schedule and total investment BASIC DATA Geographical location and population... 23_Toc Topography Hydro- meteorological characteristics Situation of land use Basic environmental data Socio-economic status of the subproject area _Toc Protected areas, natural reserves, sensitive areas, cultural heritages, historical monuments, temples and pagodas in the subproject area POTENTIAL IMPACTS MITIGATION MEASURES EMP IMPLEMENTATION ARRANGEMENTS MONITORINGPROGRAM Objectives INSTITUTIONAL DEVELOPMENT ACTIVITIES COST ESTIMATION FOR EMP IMPLEMENTATION PUBLIC CONSULTATION Power Engineering Consulting Joint Stock Company 3 1

3 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" ABBREVIATION APs : Affected persons by the subproject CSC : Construction Supervision Consultant EMP : EMF : Environmental Management Frame EIA : Environmental Impact Assessment EVN : Electricity of Vietnam DONRE : Department of Natural Resources and Environment AP : Affected person GOV : Government Km : Kilometer MONRE : Ministry of Natural Resources and Environment NPT : National Power Transmission Corporation PC : People's Committee PECC3 : Power Engineering Consulting Joint Stock Company 3 PPC : Provincial People Committee PTC4 : Power Transmission Company No.4 SIMC : Safeguard Independent Monitor SPPMB : Southern Power Project Management Board SS : Substation ROW : Right of way RP : Resettlement Plan TEP : T/L : Transmission line WB : World Bank Power Engineering Consulting Joint Stock Company 3 2

4 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" 1. INTRODUCTION The subproject " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" belongs to (TEP). The subproject will go through 21 wards/villages/towns (Cai Lay town, Thanh Hoa commune, Binh Phu commune, Phu An commune - Cai Lay district - Tien Giang province; An Cu commune, Hau Thanh commune, Hoa Khanh commune, Thien Tri commune, My Duc Dong commune, My Duc Tay commune, An Thoi Dong commune, An Thoi Trung commune, Tan Hung commune - Cai Be district - Tien Giang province; My Hiep commune, My Long commune, Binh Hang Tay commune, Binh Hang Trung commune, My Hoi commune, My Tho commune, My Tho town, An Binh commune - Cao Lanh district - Dong Thap province). Subproject Main Components Component 1: Construction of a new transmission line with total length of km including: (1) dismantling and taking back the existing Cai Lay - Cao Lanh single circuit 220kV transmission line (from Cai Lay 220kV substation to the existing tower T142), (2) building the double circuit 220kV transmission line on the ROW of the existing Cai Lay - Cao Lanh single circuit 220kV transmission line with the length of 50.82km, (3) building the new double circuit 220kV transmission line on the new ROW with the length of 6.15km. Construction time for the subproject is estimated about 15 months. Estimated date of construction commencement is in September Component 2: Improving compartments of No.274 and No.275 of the Cai Lay 220 kv substation and compartments of No.271 and No.272 of the Cao Lanh 220 kv substation : these works mainly including installing equipment will be implemented in the existing Cai Lay and Cao Lanh 220 kv stations. To ensure the potential negative impacts are identified and mitigated during the subproject implementation, and in compliance with the policy on environmental assessment of the World Bank (OP/BP 4.01), an (EMP) of the subproject has been prepared in accordance with the guidelines provided in the Environmental and Social Management Framework (ESMF) of the TEP project. The EMP includes the following contents: an introduction, the main legal framework, the subproject description, the environmental background, potential positive and negative impacts, proposed mitigation measures, and implementation arrangements. It also includes an Environmental Codes of Practice (ECOP) prepared for the subproject. The EMP will be incorporated into the bidding documents and construction contracts, as well as a scope for environment quality monitoring. A Resettlement Plan (RP) has also been prepared for the subproject and is presented separately in another safeguard document. According to the Vietnamese Government s regulations on environmental impact assessment (EIA), the subproject has implemented the report on environmental impact assessment for submission to the Ministry of Natural Resources and Environment (MONRE) for appraisal and approval. The EIA report was submitted to MONRE in April, 2014 and is expected to be approved in October, POLICY, REGULATIONS, AND ADMINISTRATIVE FRAMEWORKS 2.1 Government Regulations: The following national laws and regulations are applied for the subproject: Power Engineering Consulting Joint Stock Company 3 3

5 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" - Law on Protection of the Environment No.52/2005/QH11 passed by the National Assembly on November 29, 2005 regulates the obligations of individuals, organizations in protecting environment. - Law on Water Resource No.17/2012/QH13 enacted June 21, Land Law No.45/2013/QH13 dated November 29, 2013 which will take effect on July 1, Construction Law No.16/2003/QH11 dated November 26, Labor Law No.35-L/CTN dated June 23, 1994 with some amendment underdocument No. 84/2007/QH11 by the National Assembly. - The Law on Cultural Heritage No.32/2009/QH12 promulgated on June 18, 2009 about amending and supplementing some articles of the Law on Cultural Heritage No.28/2001/QH10. - Law on Fire Prevention and Fighting No.27/2001/QH10 dated June 29, Law on electricity No.28/2004/QH11 dated December 3, Decree of Government No.80/2006/ND-CP dated August 9, 2006 on guidance for implementation of Law on Protection of the Environment. - Decree of Government No.29/2011/ND-CP dated April 18, 2006 regulating strategic environmental assessment, environmental impact assessment and environment protection commitment. - Decree No.117/2009/ND-CP dated December 31, 2009 on sanction of violations in the field of environmental protection. - Decree No.59/2007/ND-CP dated April 9, 2008 on solid waste management. - Decree No.174/2007/ND-CP dated November 29, 2007 of GOV on environmental protection charges for solid wastes. - Decree No.98/2010/ND-CP of the Government dated September 21,2010 on detailing the implementation of some articles of the Law on Cultural Heritage and the Law amendingand supplementing some articles of Law on cultural heritage. - Decree No.14/2014/ND-CP dated February 26, 2014 detailing the implementation of the Electricity Law on electrical safety; - Circular No.26/2011/TT-BTNMT dated July18, 2011 on guidance for Decree No.29/2011/ND-CP dated April 18, Circular No.12/2011/TT-BTNMT dated April 14, 2011 relating to toxic waste management. - Circular No.03/2010/TT-BCT dated January 1, 2010 on some rules on safe protection of high voltage grids. - Manual of the Electricity of Vietnam No. 2623/CV-EVN - Science Technology and Environment, dated 28/05/2007 on the management and prevention of pollution and exposure to PCBs; - Guidance of EVN No.2623/CV-EVN - KHCN & MT dated May 28, 2007 on the management and prevention of pollution and exposure to PCBs; The main applied National Technical Regulations in the subproject include: Power Engineering Consulting Joint Stock Company 3 4

6 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" - QCVN 05: 2013/BTNMT: National technical regulation on ambient air quality; - QCVN06: 2009/BTNMT - National Technical Regulation on hazardous substances in ambient air; - QCVN08: 2008/BTNMT - National Technical Regulation on surface water quality; - QCVN09: 2008/BTNMT - National Technical Regulation on groundwater quality; - QCVN01: 2009/BYT National technical regulations on drinking water quality; - QCVN02: 2009/BYT National technical regulations on domestic water quality; - QCVN 01:2008/BCT - National Technical Regulation on electrical safety; - QCVN 03:2008/BTNMT - National Technical Regulation on permissible limits of heavy metals in the soilt; - QCVN 07:2009/BTNMT - National Technical Regulation on hazardous waste threshold; - QCVN 40:2011/BTNMT - National Technical Regulation on industrial waste. Standards, National technical regulations on power safety technique: - QCVN QTD 08:2010/BCT Low voltage power technical regulation; - TCVN 5308:1999 Technical safety regulation for construction; - TCVN 4086:1995 Power safety Standard for construction; - TCVN 3147:1990 Safety regulation on loading and unloading works; - TCVN 2292:1978 General requirement on safety for painting work; - TCVN 4244:1986 Safety technical regulation for lifting equipment; - TCVN 5863:1995 Safety requirement during installing and using lifting equipment World Bank Safeguard Policies An environmental and social screening of the subproject was undertaken in line with the OP 4.01 and it showed that the World Bank s policies on Environmental Assessment (OP/BP 4.01), and Involuntary Resettlement (OP/BP 4.12) will be triggered for the subproject. The screening has also resulted in categorizing the subproject as a Category B project. In addition, the Bank s requirements on public consultation and information disclosure will need to be followed. Environmental Assessment (OP/BP 4.01): Environmental Assessment (EA) is an umbrella policy for the Bank s safeguard policies. The overarching objective is to ensure that Bank-financed projects are environmentally sound and sustainable, and that decision-making is improved through appropriate analysis of actions and of their likely environmental impacts. The EA process is intended to identify, avoid and mitigate potential impacts of Bank operations. EA takes into account the natural environment (air, water, and land); human health and safety; social aspects (involuntary resettlement, indigenous peoples, and physical cultural resources); and transboundary and global environmental aspects. EA considers natural and social aspects in an integrated way. This subproject triggers OP 4.01 because it involves the construction and operation of a high-voltage substation and connecting overhead transmission lines, requiring the identification, mitigation and monitoring of potential adverse environmental and social Power Engineering Consulting Joint Stock Company 3 5

7 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" impacts. As required by OP 4.01 and the government EA regulation, the subproject has prepared an Environmental Protection Commitment (EPC) and an EMP that meet the Government s and the World Bank s safeguards requirements. By the TEP appraisal, the subproject EPC and draft EMP were disclosed locally at the subproject sites and at the Bank s InfoShop in Washington DC on January 24, 2014 as required by OP 4.01 and the Bank s policy on access to information.the final subproject final EPC and EMP were disclosed locally at the subproject sites, at the Bank s InfoShop, and the Vietnam Development Information Center on April 18, Involuntary Resettlement (OP/BP 4.12) The Involuntary Resettlement policy seeks to prevent severe long-term hardship, impoverishment, and environmental damage to the affected peoples during involuntary resettlement. OP 4.12 applies whether or not affected persons must move to another location. The Bank describes all these processes and outcomes as involuntary resettlement, or simply resettlement, even when people are not forced to move. Resettlement is involuntary when the government has the right to expropriate land or other assets and when affected people do not have the option to retain the livelihood situation that they have. This policy is triggered because the subproject it would have impacts involving the temporary and permanent involuntary taking of land and the loss of structures and assets associated with the land for the construction of the substation and the associated connecting line. By appraisal, the subproject has prepared and disclosed a RP locally at the subproject sites and at the Bank s InfoShop in Washington DC on January 24, The RP includes the measures to ensure that displaced people are: (i) informed about the options regarding resettlement; (ii) consulted and offered alternative resettlement choices; and (iii) provided with effective compensation and livelihood restoration. World Bank Group Environmental, Health, and Safety Guidelines World Bank-financed projects should also take into account the World Bank Group Environmental, Health, and SafetyGuidelines 1 (known as the "EHS Guidelines"). The EHS Guidelines are technical reference documents with general and industry-specific examples of Good International Industry Practice. The EHS Guidelines contain the performance levels and measures that are normally acceptable to the World Bank Group and are generally considered to be achievable in new facilities at reasonable costs by existing technology. The environmental assessment process may recommend alternative (higher or lower) levels or measures, which, if acceptable to the World Bank, become project- or site-specific requirements. This subproject should to be conforming the Environmental, Health, and Safety Guidelines for Electric Power Transmission and Distribution and General EHS Guidelines. 3. SUBPROJECT DESCRIPTION 3.1. Objectives of the Subproject - Enhancing connection with the 220kV network for the region, ensuring the electricity supply is continuous and safe for the load of the region in any cases. - In case of necessity high transmission capacity will be mobilized between the eastern and western regions of South Vietnam. 1 The EHS Guidelines can be consulted at Power Engineering Consulting Joint Stock Company 3 6

8 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" - Transfering excess capacity from power plants in Nam Song Hau region (including thermal power plants: Ca Mau, O Mon, Long Phu, Kien Luong, etc.) to the Eastern of South Vietnam, serving power supply in a stable condition and long-term for the electrical network of provinces including Dong Thap, Tien Giang, Long An, Ho Chi Minh City and the surrounding areas. - To ensure quality and improve reliability of power supply and reduce power losses on the transmission grid. - Preventing overload for the existing Thot Not - Cao Lanh - Cai Lay 220kV Transmission Line 3.2. Scope of the subproject - Dismantling and taking back the existing Cai Lay - Cao Lanh single circuit 220kv transmission line (from Cai Lay 220kv substation to the existing tower T142); - Building the double circuit 220kv transmission line on the ROW of the existing Cai Lay - Cao Lanh single circuit 220kv transmission line with the length of 50.82km; - Building the new double circuit 220kv transmission line on the new ROW with the length of 6.15km; - Improving compartments of No.274 and No.275 of the Cai Lay 220 kv substation and compartments of No.271 and No.272 of the Cao Lanh 220 kv substation - The areas used for improving compartments: these positions in the existing Cai Lay and Cao Lanh 220 kv stations, so the extension of theses bays will not affect land, trees (permanently or temporarily) of the local people Location of subproject The subproject will go through 21 wards/villages/towns (Cai Lay town, Thanh Hoa commune, Binh Phu commune, Phu An commune - Cai Lay district - Tien Giang province; An Cu commune, Hau Thanh commune, Hoa Khanh commune, Thien Tri commune, My Duc Dong commune, My Duc Tay commune, An Thoi Dong commune, An Thoi Trung commune, Tan Hung commune - Cai Be district - Tien Giang province; My Hiep commune, My Long commune, Binh Hang Tay commune, Binh Hang Trung commune, My Hoi commune, My Tho commune, My Tho town, An Binh commune - Cao Lanh district - Dong Thap province). The subproject will build a new transmission line with total length of km including: (1) dismantling and taking back the existing Cai Lay - Cao Lanh single circuit 220kV transmission line (from Cai Lay 220kV substation to the existing tower T142), (2) building the double circuit 220kV transmission line on the ROW of the existing Cai Lay - Cao Lanh single circuit 220kV transmission line with the length of 50.82km, (3) building the new double circuit 220kV transmission line on the new ROW with the length of 6.15km. Power Engineering Consulting Joint Stock Company 3 7

9 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" Cao Lanh 220kV substation Subproject Cai Lay 220kV substation Figure 1: Location of the Subproject Table 3.1 Description of the routes of transmission line No. Section Length (m) Description G0-G8: Building the double circuit 220kv transmission line on the ROW of the existing Cai Lay - Cao Lanh with the length of 50.82km 1 G0-G m 2 G1 - G1' 1, m From the first point G0 (the existing B1 tower) towards G1 (tower B3). This area terrain is flat, there are many fruit trees as jackfruit, mango, pomelo, longan, coconut. This section is located in Cai Lay town, Cai Lay District, Tien Giang Province. The route crosses two medium voltage transmission lines, and Cai Lay - Cai Be 110kV transmission line, cuts 4 fish ponds, 2 roads paved by concrete plates and 1 asphalt road. The route cuts through one house. There are 4 houses located in the ROW (including the Cai Lay political training center, 1 piggery). At G1 (tower B3) the line turns left with an angle of 8º15'31" and goes straight to G1' (tower No.04). This area terrain is flat, there are many fruit trees like jackfruit, banana, pomelo, longan. This section is located in Cai Lay town, Cai Lay District, Tien Giang Province. Crossing 6 fish ponds and the Cai Lay river (about 60m wide). Crossing 12 roads paved by concrete plates, Provincial Road 868, a road along the Moi canal under construction. Crossing two existing medium-voltage T/Ls and 1 low Power Engineering Consulting Joint Stock Company 3 8

10 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Section Length (m) Description voltage T/L. Crossing 9 houses and 1 piggery. There are 41 houses (1 thatched house included) and 1 tomb located in the ROW. At G1' (tower No.04) the line turns left with an angle of 3º21'59" toward G2 (tower No.19). This area terrain is flat, there are many fruit trees as: jackfruit, banana, pomelo, longan, coconut, mango and a little crops such as corn and rice. This section is located in Cai Lay town, Thanh Hoa and Binh Phu communes, Cai Lay District, Tien Giang Province. 3 G1' - G2 5, Crossing 1 fish pond, 4 small channels, 1 large channel (about 35m wide) and 28 ditches. Crossing 10 soil roads, 17 roads paved by concrete plates, 1 asphalt road. Crossing 4 medium-voltage T/Ls and 3 low voltage T/Ls existing, a high voltage branch of the existing Cai Lay - Vinh Long 220kV T/L. Crossing 1 house, 2 tombs, 2 piggeries. There are 17 houses (of which 4 thatched houses, 1 concrete house), 4 piggeries and 1 tomb located in the corridor. At G2 (tower No.19) the line turns left with an angle of 14º43'09 toward G3 (tower No.37). This area is flat, there are many fruit trees as: jackfruit, banana, pomelo, longan, coconut, mango and a little crops such as corn and rice. This segment is located in Phu An commune, Cai Lay district and An Cu commune, Cai Be District, Tien Giang Province. 4 G2 - G3 6, m Crossing 25 small ditches, 10 fish ponds, 4 large channels, the Ba Ton River and the An Cu River (width about 45-60m). Crossing 4 soil roads, 24 roads paved by concrete plates, 1 asphalt road, Provincial Road 869 and Highway 1A. Crossing 4 medium-voltage T/Ls and 5 low voltage T/Ls existing Crossing 2 houses and 3 thatched house, 4 piggeries, 1 barn and 4 tombs. There are 40 houses (of which 5 thatched houses and 3 tileroofed houses), 6 tombs and 4 piggeries located in the ROW. 5 G3 - G4 6, m At G3 (tower No.37), the line turns right with an angle of 18º47'02" toward G4 (tower No.55). This area is flat. The section will go through paddy field Power Engineering Consulting Joint Stock Company 3 9

11 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Section Length (m) Description and fruit trees planting land of orange, banana, grapefruit, longan, lemon, jackfruit. This section goes through the communes including An Cu, Hau Thanh, Hoa Khanh and Thien Tri in Cai Be District, Tien Giang Province. Crossing 3 fish ponds, 16 small ditches, 12 large channels and some major rivers such as the Thong Luu River, the Tra Lot River and the My Thien River (width about 40-80m). Crossing 30 roads paved by concrete plates, 1 intercommune concrete road. Crossing 3 medium-voltage T/Ls and 5 low voltage T/Ls existing Crossing 3 houses, 2 piggeries and 5 tombs. There are 66 houses (of which 2 thatched houses, 1 tileroofed house and 1 concrtete house), 5 tombs and 5 piggeries located in the ROW. At G4 (tower No.55), the line turns left with an angle of 19º35'30" toward G5 (tower No.72). This area is flat. The section will go through paddy field and fruit trees planting land of orange, banana, grapefruit, longan, lemon, jackfruit, mango, guava. This segment goes through 4 communes including Tri Thien, My Duc Dong, My Duc Tay, An Thoi Dong, Cai Be District, Tien Giang Province. G4 - G5 G5 - G6 6, m 8, m Crossing 3 fish ponds, 15 small canals, 10 canals and some large rivers such as the Ong Ve river, the My Duc Tay River, the Rach Mieu River and the Co Co river (width about 30-90m). Crossing 22 roads paved by concrete plates, one 6m wide intercommune asphalt road. Crossing 3 medium-voltage T/Ls and 3 low voltage T/Ls existing Crossing 5 houses, 1 concrete house and 1 piggery. There are 35 houses (of which 4 thatched houses), 3 tombs and 4 piggeries located in the ROW. At G5 (tower No.72), the line turns right with an angle of 29º58'24" toward G6 (tower No.108). This area is flat. The section will go through paddy field and fruit trees planting land of orange, banana, grapefruit, longan, lemon, jackfruit, mango, guava. This section goes through the communes including An Thoi Dong, An Thoi Trung and Tan Hung in Cai Be District, Tien Giang Province. Crossing 38 small ditches, 8 major canals and rivers such as the Bo Gon River, Ruong canal, Chua Ba canal, Mit canal (width about 40-60m). Power Engineering Consulting Joint Stock Company 3 10

12 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Section Length (m) Description G6 - G7 G7 - G8 3, m 12, m Crossing 7 soil roads, 11 intercommune roads paved by concrete plates, 1 concrete road, 1 asphalt road. Crossing 2 medium-voltage T/Ls and 2 low voltage T/Ls existing and the Nha Be - O Mon 500kV transmission line. Crossing 2 houses, 1 tomb and 1 piggery. There are 40 houses and 6 tombs located in the ROW. At G6 (tower No.108), the line turns right with an angle of 29º49'17" toward G7 (tower No.97). This area is flat. The section will go through paddy field and fruit trees planting land of orange, banana, grapefruit, longan, lemon, jackfruit, mango, guava. This segment goes through Tan Hung commune, Cai Be District, Tien Giang province; My Hiep commune and My Long commune in Cao Lanh district, Dong Thap province. The boundary between the two provinces of Dong Thap and Tien Giang is the Cai Lan canal. Crossing 6 canals such as Cai Lan, Ba Du, Ba Luong, Nga Cai Crossing 2 soil roads, 9 intercommune roads paved by concrete plates along the Cai Lan canal. Crossing 1 tomb. There are 19 houses, 2 piggeries and 1 tomb located in the ROW. At G7 (tower No.97), the line turns right with an angle of 10º47'47" toward G8 (tower No.142). This area is flat. The section will go through paddy field and fruit trees planting land of there are many fruit trees such as banana, mango, guava. This segment goes through 4 communes including My Long, Binh Hang Tay, Binh Hang Trung, My Hoi in Cao Lanh district, Dong Thap province. Crossing 9 fish ponds, 21 canals such as Tan Truong, Cai beo and Ong Cung Crossing 3 soil roads, 23 intercommune roads paved by concrete plates and 2 asphalt roads. Crossing 3 medium-voltage T/Ls and 2 low voltage T/Ls existing and the My Tho - Cao Lanh 2 nd 110kV transmission line. Crossing 6 houses, 1 piggery and 2 tombs. There are 37 houses (of which 1 thatched cottage), 3 piggeries and 4 tombs located in the ROW. G8-G13: Building the double circuit 220kv transmission line on the new ROW with the length of 6.15km G8 - G9 1, m At G8 (tower No.142), the line turns right with an angle of 64º02'30" toward G9. This area is flat, mostly rice fields. This segment is still in Power Engineering Consulting Joint Stock Company 3 11

13 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Section Length (m) Description My Hoi commune, Cao Lanh district, Dong Thap province. Crossing 4 irrigation canals with width from 10-42m (including the Duong Luy channel) and 2 small ditches. The route will also cut through 2 roads paved by concrete plates along the canals, cross one single phase mediumvoltage T/L, one 110kV transmission line existing. There is no house in the route. At G9, the line turns left with an angle of 49º25'10" and parallels the existing 110kV transmission line with a distance of 25m towards the Cao Lanh substation. This area is flat, mostly rice fields. This segment goes through My Tho commune and My Tho town in Cao Lanh district, Dong Thap province. G9- G10 1, m Crossing 4 irrigation canals with width from 10-42m (including the Vam Sang channel), 1 ditch and 1 small pond. G10 - G11 G11 - G12 2, m m The route will also cut through 5 roads paved by concrete plates along the canals, cross one single phase mediumvoltage T/L, one 3 phase medium-voltage transmission line and one low-voltage transmission line. G10 is in a rice field. Crossing 7 houses. There are 6 houses and 1 small tomb located in the ROW. At G10, the line turns left with an angle of 41º57'05" and parallels the existing 110kV transmission line with a distance of 119m. This area is flat, mostly rice fields. This segment goes through My Tho town in Cao Lanh district, Dong Thap province. Crossing 1 pond, 5 ditches and 8 irrigation canals with width from 20-40m. The route will also cut through 2 roads paved by concrete plates along the canals, 1 asphalt road, cross two 3 phase medium-voltage transmission lines and one low-voltage transmission line. G11 is in a rice field. Crossing 3 houses. There are 15 houses, 1 thatched house, 1 tile-roofed house and 1 small tomb located in the ROW. At G11, the line turns left with an angle of 37º03'41" and cross the existing 110kV transmission line towards the Cao Lanh substation. This area is flat, mostly rice fields. This segment goes through My Tho town and An Binh commune in Cao Lanh district, Dong Thap province. Crossing 3 canals, 1 ditch and the Can Lo river (about Power Engineering Consulting Joint Stock Company 3 12

14 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Section Length (m) Description 100m wide) The route will also cut through 1 asphalt road and 1 stone road, cross the existing My Thuan - Cao Lanh 110kV transmission line and the existing Thanh Hung - cao Lanh 110kV T/L. G12 is in a lotus pond in An Binh commune, Cao Lanh district, Dong Thap province. Crossing 2 houses, 1 big charnel house and 1 small tomb. There are 6 houses, 1 tomb and 1 piggery located in the ROW. At G12, the line turns left with an angle of 56º10'24" towards tower No.15 and stops here. G12 - G ,m The area has many deep fish ponds, complex terrain. This segment is in An Binh commune, Cao Lanh district, Dong Thap province. There is no house in the ROW. The line cuts through a lotus pond approximate 0.5-2m Subproject Main Work Volume The below table describes items and construction volume of the subproject. Table 3.2 Items and construction volume of the subproject No. Description Unit Volume I. NEW CONSTRUCTION 1 Excavation of foundation pits m 3 116,578 2 Backfilling foundation pits m 3 82,309 3 Concrete grade M100 m Concrete grade M200 m 3 18, Sand cushion m 3 8, Steel in sizes for foundation Ton 2, Anchor bolt in sizes Ton Ground connectors Set Volume of steel for towers Ton 2,963.6 II II.1 ELECTRICAL PART Conductors, insulators and auxiliaries 1 Conductor ACSR300/39 km Connector for conductor unit Repair pipe for conductor pipe Positioning frame for conductor Set 9,324 Power Engineering Consulting Joint Stock Company 3 13

15 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Description Unit Volume 5 Positioning frame for jumper Set Single insulator support string for conductor Set Double insulator support string for conductor Set Double insulator anchor string for conductor Set Insulator support string for jumper of conductor + compensated damper of 100kg II.2 Earth line + auxiliary - Phlox Earth line Phlox 147 km Connector for Earth line Phlox147 Connector 40 3 Repair pipe for Phlox 147 Pipe 12 4 Vibration damper for Phlox 147 Damper Support string for earth line Phlox 147 String Insulator anchor string for earth line Phlox 147 String 33 II.3 Earth line + auxiliary TK 70 (GSW7/16 ) 1 Earth line TK70 (GSW7/16 ) km Connector for Earth line TK 70 (GSW 7/16 ) Connector 9 3 Repair pipe for TK 70 (GSW7/16 ) Pipe 3 4 Vibration damper for TK70 (GSW7/16 ) Damper Support string for earth line TK70 (GSW7/16 ) String 26 6 Insulator anchor string for earth line TK 70 (GSW7/16 ) String 15 II.4 Fiber cable + auxiliary 1 Fiber cable OPGW150 m 48,785 2 Vibration damper for fiber cable OPGW 150 Damper Connector for fiber cable OPGW 150+ bearing frame Box 11 5 Clamp for fiber cable OPGW 150 on the tower Clamp Positioning clamp for Fiber cable OPGW 150 on the tower Clamp 44 7 Support string for fiber cable OPGW 150 with armour rod String String for anchoring fiber cable OPGW 150 String 31 II.5 Fiber cable + auxiliary 1 Fiber cable OPGW70 m 11,270 2 Vibration damper for fiber cable OPGW 70 damper Connector for fiber cable OPGW 70+ bearing frame Box 4 5 Clamp for fiber cable OPGW 70 on the tower Clamp 62 Set 132 Power Engineering Consulting Joint Stock Company 3 14

16 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Description Unit Volume 6 Positioning clamp for Fiber cable OPGW 70 on the tower Clamp 16 7 Support string for fiber cable OPGW 70 with armour rod String 26 8 Anchor string for fiber cable OPGW 70 String 13 III OTHER MATERIALS 1 Ground connector Position River passing sign Position 89 3 Road crossing sign Position 13 4 Number of tower's board Board Warning sign Set Switchboard Set 159 Table 3.3. Volume of new equipment and structures installed - 220kV Bay of the Cai Lay 220kV substation No. Items Specification, use purpose Unit I INSULATOR STRING AND AUXILIARIES Single insulator anchor string for phase separation 2xACSR300 Single insulator support string for phase separation 2xACSR300 Positioning frame for phase separation 2xACSR300 The whole set and auxiliaries for anchoring wire 2xACSR300 The whole set and auxiliaries for supporting wire 2xACSR300 Size of positioning frame 200mm Quanti ty String 12 String 12 Set 90 II 220kV EQUIPMENT Circuit breaker 220kV 2 3 Disconnector, 3 phases, one-sided earth connector Disconnector, 3 phases, duplex earth connector Outdoor type, 245kV, 1600A, 40kA/3s, clamp suitable for wire ACSR 710 Outdoor type, 3 phases, 245kV, 1600A, 40kA/3s, clamp suitable for wire ACSR 710 Outdoor type, 3 phases, 245kV, 1600A, 40kA/3s, clamp suitable for wire ACSR 710 and ACSR 300 Set Set Set Disconnector, 1 phase, without earth connecting blade Outdoor type, 245kV, 1600A, 40kA/3s, clamp suitable for wire ACSR 710 Set 6 5 Current transformer Outdoor type, 1 phase, 245kV, 40kA/3s Ratio: / A Accuracy: 0.5-5P20-5P20-5P20-5P20 Set 6 Power Engineering Consulting Joint Stock Company 3 15

17 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Items Specification, use purpose Unit 6 Capacitive voltage transformer Lightning arrester and lightning counter Post insulator - 220kV - clamp suitable for wire ACSR 710 Conductor and auxiliaries of 220UV - Aluminium conductor steelreinforced - 'T' branch clamp (duplex) - 'T' branch clamp (duplex) Load: 30VA-30VA-30VA-30VA- 30VA clamp suitable for wire ACSR 710 Outdoor type, 1 phase, 245kV Tỷ số: 220kV/ 3 : 110V/ 3 : 10V/ 3 clamp suitable for wireacsrl 710 Outdoor type, 1 phase, 196 kv-20ka. Class3 Outdoor type, 245kV, 10kN, 25mm/kV clamp suitable for wire ACSR 710 ACSR 710 For wire size 2xACSR 400 to ACSR 710 For wire size 2x ACSR ACSR 710 Set Quanti ty 2 2 Set 6 Set m 900 Clamp 18 Clamp 12 - Parallel branch clamp For wire size ACSR ACSR 710 Clamp 4 Table 3.4 Volume of new equipment and structures installed - 220kV Bay of the Cao Lanh 220kV substation No. Items Specification, use purpose Unit I l INSULATOR STRING AND AUXILIARIES - Single insulator support string for phase separation 2xACSR Positioning frame for phase separation 2xACSR300 The whole set and auxiliaries for supporting wire 2xACSR300 Quanti ty String 6 Size of positioning frame 200mm Set 24 II 220kV EQUIPMENT Set l Circuit breaker 220kV, every set includes: -Outdoor type, 245kV,3150A, 40kA/3s Set 2 Clamp of equipment bases For wire size ACSR710 Set 12 2 Disconnector, 3 phases, one-sided earth connector on the right - Outdoor type, 3 phases, 245RV, 1250A, 3 1,5kV/ 1s Set 12 - Clamp of equipment bases For wire size ACSR300 Set 6 - Clamp of equipment bases For wire size ACSR710 Set 6 3 Disconnector, 3 phases, without earth connecting blade Outdoor type, 3 phases, 245RV, 1250A, 3 1.5kV/ 1s Set 1 Power Engineering Consulting Joint Stock Company 3 16

18 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Items Specification, use purpose Unit 4 Disconnector, 1 phase, without earth connecting blade Outdoor type, 1 phase, 245kV, 1250A, 3 l,5kv/ls Quanti ty Set 6 - Clamp of equipment bases For wire size ACSR710 Set 12 - Đầu cosse cho dây nối đất Earth line terminal Current transformer 150mm 2 cái 9 Outdoor type, 1 phase, 245kV; 31,5kA/3s Ratio: / A Accuracy: 0.5-5P20-5P20-5P20-5P20 Load: 30VA-30VA-30VA-30VA- 30VA Set 6 - Bearing Frame Galvanized form steel Set 6 - Clamp of equipment bases For wire size ACSR710 Set 12 Capacitive voltage transformer Outdoor type, l phase, 245kV Ratio: 220kV/ 3:110V/ 3:110V/ 3 - Clamp of equipment bases For wire size ACSR710 Set 6 Post insulator 220kV 8 Conductor and auxiliaries of 220kV - Aluminium conductor steelreinforced - 'T' branch clamp (duplex) - 'T' branch clamp (duplex) Outdoor type, 245kV, 10kN, 25mm/kV For wire size ACSR710 Type ACSR 710 For wire size 2xACSR 710 to ACSR 710 For wire size 2x ACSR ACSR 710 Set Set 6 14 m 500 Clamp!2 Clamp 6 - Mobile ground connecting clamp For wire size ACSR710 Clamp 12 Table 3.5. Volume of materials which will be dismantled and taken back from the existing single circuit T/L (from the existing towers B1 to No.142 ) No. Description Signal Unit Quantity Note I CONSTRUCTION PART I.1 Post part post Vertical support post D220-6T+5 D220-6T+5 post tons/ post 2 Vertical support post D220-5 D220-5 post tons/post 3 Vertical support post D D post tons/post 4 Vertical support post D220-5T D220-5T post tons/post Power Engineering Consulting Joint Stock Company 3 17

19 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Description Signal Unit Quantity Note 5 Vertical support post D220-5T+5 D220-5T+5 post tons/post 6 Transposition post DP220-5 DP220-5 post tons/post 7 Anchor post N220-1 N220-1 post tons/post 8 Anchor post N N post tons/post 9 Anchor post N220-2T+9 N220-2T+9 post tons/post 10 Anchor post N220-3T+14 N220-3T+14 post tons/post 11 Anchor post N220-3T+5 N220-3T+5 post tons/post I.2 Foundation part 1 Destroying the old foundation throats Position 130 4m 3 /foundation 2 Destroying the old reinforced concrete foundations Foundation Foundation of tower D220-6T+5 Foundation m 3 /foundation Foundation of tower D220-5 Foundation m 3 /foundation Foundation of tower N Foundation m 3 /foundation Foundation of tower N220-1 Foundation m 3 /foundation Foundation of tower N220-2T+9 Foundation m 3 /foundation Foundation of tower N220-3T+14 Foundation m 3 /foundation Foundation of tower N220-3T+5 Foundation m 3 /foundation II ELECTRICAL PART II. 1 Conductor 1 Conductor ACSR 795MCM km 156,74 2 Single insulator support string for conductor ACSR 795MCM 3 Single insulator anchor string for conductor ACSR 795MCM 4 Insulator support string for jumper of conductor ACSR 795MCM D15-70 Set 405 N Set 87 DLD15-70 Set porcelain insulators/string 13 porcelain insulators/string 5 Vibration damper for conductor Set 867 II. 2 Earth line 1 Earth line TK70 (GSW 7/16") km 51,4 2 Support string for earth line DCS-70 Set Anchor string for earth line NCS-90 Set 29 4 Vibration damper for earth line Set 323 II. 3 Fiber cable 1 Fiber cable OPGW100 m 521 Power Engineering Consulting Joint Stock Company 3 18

20 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Description Signal Unit Quantity Note 2 Support string for fiber cable OPGW100 DCQ-100 Set 1 3 Anchor string for fiber cable OPGW100 NCQ-100 Set 3 4 Vibration damper for fiber cable OPGW100 Set 3 Table 3.6: Volume of materials which will be dismantled and taken back from the 220kV bay of Cai Lay 220kV substation No. Items Specification, use purpose Unit Quantity I CONDUCTORS, INSULATOR STRINGS AND AUXILIARIES l Conductor ACSR 41Dmm 2 m Single insulator anchor string for conductor ACSR410 3 Single insulator support string for conductor ACSR 410 II EQUIPMENT 220kV String 12 String 12 l Circuit breaker 220kV Outdoor type, 245kV, 1250A, 31,5kA/3s Set 2 2 Disconnector, 3 phases, onesided earth connector 3 Disconnector, 3 phases, duplex earth connector 4 Disconnector, 1 phase without earth connecting blade Outdoor type, 3 pha, 245kV, 1250A, 3 l,5ka/3s Outdoor type, 3 phases, 245kV, 1250A, 3 l,5ka/3s Set 4 Set 2 Outdoor type, 1 phase, 245kV, 1250A. Set 6 5 Current transformer Outdoor type. 1 phase, 245kV; 31.5kA/3s Ratio: / A 6 Lightning arrester and lightning counter Set Outdoor type, 1 phase, 196kV-10kA Set 2 Table 3.7. Volume of materials which will be dismantled and taken back from the 220kV bay of Cao Lanh 220kV substation No. I II Items CONDUCTORS, INSULATOR STRINGS AND AUXILIARIES Specification, use purpose Unit 6 Quantity l Conductor ACSR ACSR 410mm 2 m Single insulator support string for conductor ACSR kV EQUIPMENT String 6 l Circuit breaker 220kV Set 12 Power Engineering Consulting Joint Stock Company 3 19

21 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Items - Clamp of equipment bases 2 Disconnector, 3 phases, one-sided earth connector on the right - Clamp of equipment bases 3 Disconnector, 3 phases without earth connecting blade - Clamp of equipment bases 4 Disconnector, 1 phase without earth connecting blade - Clamp of equipment bases Specification, use purpose 5 Current transformer - Outdoor type, 1 phase, 245kV, 3 l,5ka/3s - Ratio: / A 6 - Capacitive voltage transformer - Clamp of equipment bases 7 Post insulator 220kV - Clamp of equipment bases Unit Quantity Set 12 Set 12 Set 12 Set 6 Set 6 Set Main Activities Before and During Construction Main Activities Before and During Construction The following activities will be implemented before the construction phase: - Compensation and land clearance; - Preparation for materials storages and construction sites. The activities to be implemented during the construction include: - Excavation; - Transportation of construction materials and equipment; - Preparation of mortar, concrete formworks and steel rods; - Installation of steel towers; - Installation of electrical equipments and stringing of the wires; - Experiments and completion work Transportation Material and equipment supply: - Sand, stone, gravel, cement, steel, construction materials will be bought at the local area. - Steel structures: will be processed in HCM city. - The main electrical equipment: will be taken at the warehouse of Project Management Board in Thu Duc District, HCMC. Power Engineering Consulting Joint Stock Company 3 20

22 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" Table 3.8. Supply source of materials and equipment No. Items Unit Source Quantity Transport distance Note 1 Steel for foundation Ton Local area 2, km Domestically processed 2 Galvanized steel Ton -nt- 3, km " 3 Anchor bolt Ton Warehouse of PMB km Imported 4 Earth connector Set " km " 5 Conductor Ton " km " 6 Lightning conductor Ton " km " 7 Fibre optical cable Ton " km " 8 Insulator string and auxiliaries for conductor String " 1, km " 9 Insulator string and auxiliaries for lightning conductor String " km " 10 Insulator string and auxiliaries for fibre optical cable String " km " 11 Positioning frame Set " 9, km " 12 Vibration damper Set " 5, km " Long distance transport - Transportation of materials from the source to the site and along intermediate routes will be done by truck on highways and provincial roads, by barges on the large canal. Loading or unloading materials is done by manual labour or steam-crane of 10 tons; - Steel poles, conductor, lightning conductor, insulators and accessories are transported to temporary facilities along the route; - Local materials are transported directly from the supplier to the construction site. For the positions where trucks cannot move to the construction site, materials will be transported to the location gathering material along the way; - The source of materials and equipment from SPPMB stored in the warehouse of the SPPMB and transported to the station with 30km distances. Intermediate transportation Transport works of materials and equipment from the warehouse to the secondary locations of gathering materials along the provincial roads and intercommune roads by trucks. The average internal transport distance for construction sections is 15 km. Those materials include cement, steel, wire, ceramics, accessories, formworks, steel, etc. Transport road for these sections is type 4. Short distance transport Power Engineering Consulting Joint Stock Company 3 21

23 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" Transportation of materials from secondary locations of gathering materials on roads to the towers' positions by manual labour or manual labour combined with machines. Manual handling All materials and equipment will be transported to the construction site manually. The distance will be determined according to every specific case Employment Temporary construction area placed near to the residential and traffic areas is convenient for transporting and living of the workwers. Number of temporary construction sites will be dependent on the contractor to ensure for the shortest implementation schedule. Directly working Indirectly working Construction Management Board 3.6 Subproject implementation schedule and total investment Subproject implementation schedule 290 persons 35 Persons 25 persons Based on the requirements of power supply and capacity of the subproject owner, the subproject implementation schedule is as follows: No. Content Period 1 Establishing the feasibility study project Quarter 2nd, Approving the feasibility study project Quarter 4th, Establishing and Approving the Engineering design and Total investment estimation. Quarter 1st - quarter 2nd, Establishing and approving the bidding documents Quarter 3rd, Bidding invitation and bidding evaluation Quarter 4th, Measuring land boundary and compensation for clearance of space 7 Building and putting the subproject into service Quarter 1st - Quarter 3rd, 2015 Quarter 4th, Quarter 1st, Implementation planning details of each item are shown in the following table Table 3.9 Implementation Schedule of the subproject No. 1 2 Content Preparation of the construction site : 1 month Building foundations, erecting towers, finishing to stretch cable from G5 to G12: 2 months Month 1-2 Month 3-4 Month 5-6 Month 7-8 Month 9-10 Month Month Power Engineering Consulting Joint Stock Company 3 22

24 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" Building foundations at the positions outside the center line : 7 months Building foundations at the positions on the center line and erecting towers: 5 months) Installing insulation string, stretching cable and lightning conductor (from the Cai Lay 220kV substation to G8): 6 months Dismantling and taking back conductor, insulators, accessories and posts of the single circuit transmission line section 7 Building bay part (replacing equipment and conductor, etc.): 4 months 8 Acceptance and handover Total Investment Total investment is indicated in the table below: Table 3.10 Total capital of the subproject No. Item Total 1 Civil construction cost 504,519,665,000 2 Equipment cost 9,959,206,000 3 Compensation cost 67,402,690,000 4 Project management cost 6,897,618,000 5 Consultancy cost 25,495,179,000 6 Other cost 62,571,569,000 7 Contingency 181,171,593, BASIC DATA 4.1. Geographical location and population Total project cost 858,017,520,000 The subproject has a length of 56.97km including the first part which will be built on Cai Lay district is 9,698m long, and the second with 26,333m length in Cai Be district and the third with 20,939m length is in Cao Lanh district. Power Engineering Consulting Joint Stock Company 3 23

25 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" Geographical location and population of the two provinces are as follows: Tien Giang Province Tien Giang is a coastal province of the Mekong Delta in Southern Vietnam, with a large area belonging to My Tho province earlier. However, the entire area of Tien Giang province today belonged to My Tho province including Go Cong town in the past. Tien Giang province is in the Mekong River delta and also is the major economic region of Southern Vietnam, 70 km from Ho Chi Minh City to the south and 90 km from Can Tho city to the north. Tien Giang province is located in 10 26' N ' E. It borders Long An province in the north, Dong Thap province in the west, Ben Tre and Vinh Long in the south, Ho Chi Minh City in the north east, the East Sea in the southeast. Tien Giang province has been planned by the Government as one of the 8 key economic provinces in the southern. Tien Giang province comprises 11 administrative units including 1 city (My Tho), 2 towns (Go Cong, Cai Lay) and 8 districts (Cai Be, Go Cong Dong, Go Cong Tay, Cho Gao, Chau Thanh, Tan Phuoc, Cai Lay, Tan Phu Dong). Dong Thap Province Dong Thap province is one of 13 provinces in the the Mekong Delta, it has two large rivers flowing through the province including the Tien river with 114 km length and the Hau river with 30km length. Regarding geographical boundaries, Dong Thap province borders Cambodia with the length of 48.7km in the north, Vinh Long and Can Tho in the south, An Giang Province in the west, Long An and Tien Giang in the east. Total natural area of Dong Thap is 3, km2, equipvalent to 8.17% of the Mekong Delta area and 0.99% of the country area. Maximum length from north to south is 96km and the largest width from east to west is 84km. The population of Dong Thap Province was million in 2011, equivalent to 1.95% of the country's population and 9.5% of the Mekong Delta's population. Dong Thap province is divided into twelve administrative units including: 1 city (Cao Lanh), 2 towns (Sa Dec and Hong Ngu) and 9 districts comprising: Tan Hong, Hong Ngu, Tam Nong, Thanh Binh, Thap Muoi, Cao Lanh, Lap Vo, Lai Vung Chau Thanh. The whole province has 119 communes, 9 towns and 17 wards Topography Tien Giang Province The topography of Tien Giang Province is flat, with slope lower than 1% and elevation varies from 0 meters to 1.6 meters above sea level, the common elevation is from 0.8m to 1.1m. In general, the whole area's slope direction is not clear, however there are sub-areas with low-lying terrain or hills higher than the general terrain, besides there are many dunes in bow shape with the popular elevation from 0.9 to 1.1m standing out above the surrounding plains. Land of the province is largely neutral alluvial soil, less acidic along the Tien River accounting for about 53% of the provincial area. Tien Giang province has convenient source Power Engineering Consulting Joint Stock Company 3 24

26 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" of fresh water which has been put to use for a long time, the paddy fields with high productivity and intensive orchards have been formed in the province; the remaining land area comprises: 19.4% is aluminum soil and 14.6% is saline alluvial soil. Dong Thap Province The terrain of Dong Thap Province is relatively flat with common elevation from 1 to 2m above sea level. The topography is divided into two major regions: one in the north of the Tien River and the other in the south of the Tien River. Dong Thap Province benefits from a large river (the Tien River), channel and spring system, frequently silt-aggraded soil, and permanently fresh and non-saline water source Hydro- meteorological characteristics Tien Giang and Dong Thap provinces are located in the tropical climate zone. In a year, there are two distinct seasons: rainy season from May to November, dry season from December to April of the following year. Due to the provinces' topography lying in the Mekong Delta and being crossed by the Tien river and Hau River so they are greatly affected by these two rivers. The hydrologic regime is divided into 2 seasons: exhausted season from December to June of the following year and flood season from July to November. Air temperature ( o C) + Average temperature + Highest temperature + Lowest temperature Table 4.1. Climatic conditions in the subproject area Meteorological factors Air humidity (%) + Average relative humidity + Minimum average relative humidity Rainfall (mm) + Average annual rainfall + Highest daily rainfall + Total number of rainy days per year My Tho meteorological station (Tien Giang) Cao Lanh meteorological station (Dong Thap) Total number of sunshine hours per year Total number of foggy days per year Average annual cloud cover (tenth of the sky cover) Total number of thunder days per year Density of lightning in the project area (times/km 2 /year) Air temperature: Air temperature does not vary much between months in a year. Table 4.2. Average annual air temperature Power Engineering Consulting Joint Stock Company 3 25

27 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" Province/City Min Max Mean Tien Giang C (January) 28.1 o C (April) 26.3 o C Dong Thap 25.4 o C (January) 28.6 o C (April) 27.1 o C Air humidity: In the rainy months humidity is high and in the dry season humidity is reduced but the humidity difference between months is not significant. Table 4.3. Average annual humidity Province/City Min Max Mean Tien Giang 77.3%(March) 87.3% (September) 83% Dong Thap 77.7% (March) 86.5% (July) 82.8% Rainfall: rainfall in the rainy season accounts for about 75% total annual rainfall. Rainfall is distributed evenly in this region. Table 4.4. Average Annual rainfall Province/City Total number of rainny days Average Annual rainfall Tien Giang 152 days 1,663mm Dong Thap 129 days 1,398mm Solar radiation: solar radiation is measured based on the number of sunny hours. Table 4.5. Total number of sunny hours per year Province/City Min Max Mean Tien Giang Dong Thap 162 hours (September) 179 hours (September) 289 hours (March) 2532 hours 282 hours (March) 2688 hours Wind: Table 4.6. Wind velocity Province/City Max Average Wind pressure Tien Giang 31 m/s 1.6 m/s. Wo=65 dan/m 2 Dong Thap 31 m/s 1.6 m/s Wo=65 dan/m 2 Storm: This region has not directly influenced by storms Thunder: Table 4.7. Total of number of thunder days Province/City Average number of thunder Density of lightning Power Engineering Consulting Joint Stock Company 3 26

28 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" days Tien Giang 64.1 days 12.1 times/km 2 /year Dong Thap 87 days 14.7 times/km 2 /year 4.4. Situation of land use Tien Giang Province : Total natural land area of Tien Giang is 2, km². The structure of land use in Tien Giang province is as follows: agricultural land: km 2 (accounting for 76.69%), forest land: km 2 (accounting for 3.49%), specialized land: 15,887 km 2 (accounting for 6.71%), residential land: km 2 (accounting for 3.23%) and unused land: km 2, rivers, streams, rock mountain (accounting for 9.87%). Dong Thap province: Total natural land area of Dong Thap is 3, km². Structure of land use in Dong Thap province is as follows: agricultural land: 2, km 2 (accounting for 77.01%); forest land: km 2 (accounting for 4.42%); specialized land: km 2 (accounting for 6.62%); residential land: km 2 (accounting for 4.82%) and unused land: km 2 ; rivers, streams, rock mountain (accounting for 7.13%) Basic environmental data Quality of air and noise To assess the quality of the environment in the project area, Power Engineering Consultant Joint Stock Company 3 cooperated with Sac Ky Hai Dang Science - Technology Services Joint Stock Company to conduct measurement and analysis of environmental parameters of water and air at 05 locations along the line of the subproject on May 21st, The selected measurement locations are the locations where the air quality is easily affected due to construction of subproject and near residential areas. The measured parameters comprise noise, dust, SO 2, NO 2, CO. No. Symbol Sampling date (dd/mm/yyyy) Table 4.1 Sampling locations of air and noise Description of sampling locations Coordinate (X, Y) 01 K1 21/5/ K2 21/5/ K3 21/5/ K4 21/5/2014 Provincial road 868, Cai Lay town, Cai Lay county town Tien Giang province Tra Lot Bridge National Highway 1A, Hoa Khanh commune, Cai Be District, Tien Giang Province Co Co Bridge, An Thai Dong commune, Cai Be District, Tien Giang Province Cai Say Bridge - National Highway 30, Binh Hang Tay commune, Cao Lanh district, Dong Thap province 1,150,952.,57 540,036.,66 1,146,270.,20 529,260.,72 1,142,456.,63 517,645.,00 1,144,336.,30 504,925.,87 05 K5 21/5/2014 Can Lo Bridge - National 1,155,189.,87 492,427.,62 Power Engineering Consulting Joint Stock Company 3 27

29 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Symbol Sampling date (dd/mm/yyyy) Description of sampling locations Coordinate (X, Y) Highway 30, An Binh commune, Cao Lanh district, Dong Thap province Position Table 4.2 The results of analysis of ambient air quality in the project area Dust (mg/m 3 ) SO 2 (mg/m 3 ) NO 2 (mg/m 3 ) CO (mg/m 3 ) Noise (dba) K K K K K Test method TCVN TCVN TCVN TCN Acoumeter QCVN 05:2013/BTNMT QCVN 26:2010/BTNMT Note: - QCVN 05:2013/BTNMT - National technical regulation on ambient air quality; - QCVN 26:2010/BTNMT: National technical regulation on noise. Remark: From the analysis results of 05 points measured in the project area (along the transmission line), noise levels at the measurement points reached QCVN 26: 2010/BTNMT; air quality (SO 2, NO 2, CO and dust) at the measurement points reached QCVN 05: 2013/BTNMT. The above result showed that the quality of air and noise in the region is still good. Surface water quality To assess the quality of the surface water in the project area, Power Engineering Consultant Joint Stock Company 3 cooperated with Sac Ky Hai Dang Science - Technology Services Joint Stock Company to conduct measurement and analysis of environmental parameters of water samples at 05 locations along the line of the subproject on May 21st, The selected measurement locations are the locations where the surface water quality is easily affected due to construction of subproject. The measured parameters comprise ph, TSS, BOD 5, COD, nitrate (NO 3 - ) (based on N), phosphate (PO 4 3-) (based on P) and total coliform.. Table 4.3: Sampling positions of surface water No. Symbol Sampling date (dd/mm/yyyy) Description of sampling locations Coordinate (X, Y) 1 N1 21/5/2014 Cai Lay river, Cai Lay town, Cai Lay county town Tien Giang 1,150, , Power Engineering Consulting Joint Stock Company 3 28

30 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" No. Symbol Sampling date (dd/mm/yyyy) 2 N2 21/5/ N3 21/5/ N4 21/5/ N5 21/5/2014 Description of sampling locations Coordinate (X, Y) province Hoa Khanh river - Tra Lot Bridge, Hoa Khanh commune, Cai Be District, Tien Giang Province Co Co river, An Thai Dong commune, Cai Be District, Tien Giang Province Cai Say Canal - Binh Hang Tay commune, Cao Lanh district, Dong Thap province Can Lo river - National Highway 30, An Binh commune, Cao Lanh district, Dong Thap province 1,147, , ,142, , ,146, , ,154, , Power Engineering Consulting Joint Stock Company 3 29

31 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" Table 4.4 The results of analysis of surface water quality in the project area No. Parameter Test method Unit 1 ph 2 BOD 5 (20 o C) Total suspended solid (TSS) Nitrat (NO 3 - ) (based on N) Phosphat (PO 4 3- ) (based on P) 6 Total Coliform Note: TCVN 6492:2011 SMEWW 5210 B:2005 SMEWW 2540 D:2005 SMEWW 4500 :2005 SMEWW 4500 :2005 TCVN : 1996 Result N1 N2 N3 N4 N5 QCVN 08:2008/ BTNMT Column B mg/l mg/l mg/l mg/l MPN/ 100 ml 1, ,300 1,400 2,100 7,500 - QCVN 08:2008/BTNMT: National technical regulation on surface water quality; column B1: used for irrigation purposes or other uses which require similar water quality or other purposes used as type B2. Remark: Comparison of analytical results of surface water quality with QCVN 08: 2008/BTNMT column B1 showed that most of the parameters reached the allowable standards of the regulation, except parameters including phosphates (PO 4 3- ) (at 3 locations) and BOD 5 (at 5 locations) which are higher than the standards. Thus, the quality of the surface water in the project area is slightly polluted Socio-economic status of the subproject area Economy - Tien Giang province Tien Giang province is in the Mekong River delta and also is in the major economic region of Southern Vietnam, 70 km from Ho Chi Minh City to the south and 90 km from Can Tho city to the north. On the administrative boundaries, it borders Long An province in the north, the East Sea in the east, Dong Thap province in the west and Ben Tre in the south. Total natural area of Tien Giang Province is 2, km 2, equipvalent to 6% of the Mekong Delta area, 8.1% of the major economic region area in South Vietnam and 0.7% of the country area. The population of Tien Giang province is 1,682,600 persons equivalent to 1.39% of the country's population and 6.97% of the Mekong Delta's population. About administrative regions, Tien Giang Province has 01 city (My Tho city); 01 town (Go Cong town) and 08 districts including: Cai Be, Cai Lay, Chau Thanh, Cho Gao, Go Power Engineering Consulting Joint Stock Company 3 30

32 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" Cong Dong and Go Cong Tay and Tan Phu Dong, Tan Phuoc. Rate of Economic growth (based on GDP) in Tien Giang province averaged 9.2% in the period Industrial areas always have high growth rate, average 15.4%/year in the period The economic structure of the province has shifted in a positive direction: reducing the proportion of agricultural and fishery products and increasing the proportion of services, industry - construction. In 2012, in the GDP, industry - construction accounted for 38.88% and services accounted for 42.1%. Based on the actual data, income per capita increased from 314 USD in 2000 to 724 USD in 2005 and 2,214 USD in Dong Thap province is one of 13 provinces in the the Mekong Delta, it has two large rivers flowing through the province including the Tien river with 114 km length and the Hau river with 30km length. Regarding geographical boundaries, Dong Thap province borders Cambodia with the length of 48.7km in the north, Vinh Long and Can Tho in the south, An Giang Province in the west, Long An and Tien Giang in the east. Total natural area of Dong Thap is 3, km2, equipvalent to 8.17% of the Mekong Delta area and 0.99% of the country area. Maximum length from north to south is 96km and the largest width from east to west is 84km. The population of Dong Thap Province was million in 2011, equivalent to 1.95% of the country's population and 9.5% of the Mekong Delta's population. About administrative regions, Dong Thap province is divided into twelve administrative units including: 1 city (Cao Lanh), 2 towns (Sa Dec and Hong Ngu) and 9 districts comprising: Tan Hong, Hong Ngu, Tam Nong, Thanh Binh, Thap Muoi, Cao Lanh, Lap Vo, Lai Vung Chau Thanh. The whole province has 119 communes, 9 towns and 17 wards. Rate of Economic growth (based on GDP) in Dong Thap province averaged 13.4% in the period Rate of Economic growth of GDP averaged 9.7% in The economic structure of the province has shifted in the right direction: before 2010, agriculture - forestry - fishery reached 41.0%, industry - construction: 27.0%, trade - service: 32.0% ( objectives of 5 year plan, until 2010, the above rates on the order are 40.5%, 28.8%, 30.7%). Based on the actual data, income per capita increased from 406 USD in 2005 to 1,180 USD in Society The results of survey and investigation on the socio-economic situation in the communes in the subproject area in May 2014 are shown as follows: - Average number of persons in a HH 4.30 persons/hh + Man % + Woman % - Age groups Power Engineering Consulting Joint Stock Company 3 31

33 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" yrs % yrs % + Above 60 yrs 1.59 % - Heads of HH + Man % + Woman 6.50 % - Income (annually average income) 85,260,228 VND/HH/year - Average annual expenses 74,400,000 VND/HH/year Healthcare In every district in the subproject area, there is 1 hospital at the center of district and 1 healthcare station in every commune. The commune healthcare station usually takes care of minor illnesses and childbirth for women in the commune. District hospitals can cure and treat more serious diseases and do activities to protect public health. However, health care for workers and the poor has not been guaranteed due to the lack of necessary medical equipment. Income Main sources of income: + Farming 12.12% + Wage-earner 53.18% + Housewifery 11.35% + Others 11.33% It is difficult to specify exactly source of income and income, since many HHs have no source of main income and many affected households do not have stable sources of income. Many households have multiple sources of income and their income sources vary with fluctuations in harvests and prices of crops. Average income The socio-economic survey in the subproject area showed that the average income in the project areas is around 85,260,228 VND/HH/year Protected areas, natural reserves, sensitive areas, cultural heritages, historical monuments, temples and pagodas in the subproject area There is no protected area, natural reserve, sensitive area, cultural heritage or historical monument in the subproject area. Power Engineering Consulting Joint Stock Company 3 32

34 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" TBA 220kV Cao Lãnh Tiễu dự án TBA 220kV Cai Lậy Figure 4.1. Existing and proposed protected areas around the subproject area 5. POTENTIAL IMPACTS The subproject would contribute to meeting the demand load in Tien Giang, Dong Thapand adjacent area and thereby bring about significant socioeconomic benefit. Apart from such benefits, the subproject may also result in environmental and socioeconomic impacts which are adverse to the local conditions. The environmental screening of the subproject indicates that it is eligible for financing considering that the subproject would not involve possible high risk and would not create any potential adverse impacts on (a) critical natural habitats and/or protected area including proposed protected areas; (b) loss or damage to physical cultural resources, including sites having archeological (prehistoric), paleontological, historical, religious, cultural and unique natural values; and (c) water regime, particularly water flow and water quality. Power Engineering Consulting Joint Stock Company 3 33

35 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" The implementation of the subproject would mainly cause land acquisition, increased dust generation, air pollution, domestic waste, and health and safety issues due to construction activities and electrical magnetic field. However, these impacts are not significant, temporary, localized impacts with available mitigation measures. In addition, the subproject will relocate 6 graves, so OP 4.01, OP 4.11 and OP 4.12 are triggered for this subproject. Screening for assessment of eligible of the subproject location are identified in table 5.1 The potential negative impacts of the subproject are identified in table 5.2 and could be minimized by applying the proposed mitigation measures developed for the subproject which are described in Table 5.3. Table 5.1. Environmental rapid assessment checklist of the subproject Screening Question Yes No 1. Subproject's sitting: Is the Subproject site adjacent to or within any of the following environmental sensitive areas? - Cultural heritages x - Protected areas such as National Parks, Nature Reserves, Bioconservation areas, bird yards, mangrove forest etc. - Wetlands x - Forests x - Estuaries x - Buffer zone of Protected areas x - Rivers and reservoirs x - Channel, ditch x 2. Potential environmental impacts Will the Subproject cause: Encroachment on historical/cultural areas Encroachment on critical ecosystem (e.g. sensitive or protected area, national park, nature reserve etc...) Disfiguration of landscape and increase waste generation Removal of vegetation cover or cut down of trees resulted from clearance along ROW? Change of surface water quality or water flows - Increase water turbidity due to run- off and erosion x x - Waste water from camping sites is directly discharged to the surface water resources or not? - Construction waste is directly discharged to the surface water or not? x Increase the dust level? Increase noise and/or vibration? Permanent land acquisition x x x x x x x x x Power Engineering Consulting Joint Stock Company 3 34

36 Subproject of " Improvement and Upgrading of the Cai Lay - Cao Lanh 220kV transmission line" Temporary land acquisition Land in ROW Screening Question Yes No Is there any risk of disease dissemination from construction workers to the local peoples (and vice versa)? Is there any potential for conflict between construction workers and local peoples (and vice versa)? Are explosive and hazardous chemicals used within the Subproject? In the past, there was any accident incurred due to landmines or explosive materials remaining from the war? Will Subproject's construction cause disturbance to the transportation in the Subproject's site? Subproject's construction will cause any damage to the existing local roads, bridges or other rural infrastructures? Will soil excavation during Subproject's construction cause soil erosion? Will Subproject need to open new access roads? Will Subproject cause fragmentation of habitat of flora and fauna? Will Subproject cause impact on air quality? Will Subproject cause accident risks for workers and community during construction phase? Will Subproject cause risk to safety and human health (electric and magnetic fields, electric shock etc.)? Conclusion: The implementation of the subproject would mainly cause land acquisition, increased dust generation, air pollution, and domestic waste. However, these impacts are not significant, temporary, and localized, and can be mitigated available mitigation measures. Only OP 4.01 and OP 4.12 are triggered for this subproject. Therefore, the subproject is eligible for funding by the World Bank. x x x x x x x x x x x x x x Power Engineering Consulting Joint Stock Company 3 35

37 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" Table 5.2. Potential impacts of the subproject No Impact Magnitude Duration Description of the impacts Evaluation of impacts Pre-construction phase 1 Permanent and temporary land acquisition 2 Impact on Subproject affected household 3 Loss of vegetation due to land clearance for ROWs Medium Medium Short and Long Long term - Total permanent land acquisition of the project is land for foundations of the transmission line, this is 25,203 m 2. - Land in the ROWs is 704,848 m 2. This land will not be acquired but trees higher than 4 m can not planted. - Total temporary land acquisition is 43,000 m 2. This land is mainly used for rice and dry crop cultivation. - Total number of HHs affected by the Project is 712 HHs; - Affected types: land lost for foundation; having house within ROWs; loss of trees and crops, rice; trees will be damaged during cable pulling; change type of trees within ROWs etc. - There are 396 structures within ROWs (including pig sheds, kitchens, warehouses etc.) These structures are not required to be removed, but some modification, repairing are required to meet technical requirements such as roofs and walls need to be made from nonflammable materials; metal parts need to be grounded; structures should not block access to maintain ROWs, high voltage transmission line etc; - No HH needs to be resettled; - Subproject owner will develop and implement Compensation plan. Medium Long - Areas that transmission line will overpass mainly rice fields, gardens for fruit trees. Besides rice field, number of trees to be cut for acquisition land is 8,282 trees in Tan Uyen district; 1,538 trees in Thuan An town. Names of cut trees are: jackfruit, longan, acerola, tamarind, mango, bamboo, - These trees mainly have economic value; ecological value of these trees is not high. Medium and mitigable Medium Medium Power Engineering Consulting Joint Stock Company 3 36

38 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No Impact Magnitude Duration Description of the impacts Evaluation of impacts 4 Health risk due to chemical hazard None None - No hazardous chemical will be used for the Subproject. Since 1995, EVN does not allow to buy equipment containing PCB. Therefore there will not be PCBs containing equipment used for the Subproject; - Non of Subproject component is replacement or removal of old equipment so there will be no risk of encountering of PCB equipment; - Subproject will not use chemicals or explosives; None 5 Impact on historical and cultural properties None None - There are no historical and cultural resources near and inside the Subproject area None 6 Health risks caused by Unexploded Ordnance (UXOs) Medium Short The implementation of the construction of transmission lines in the area of types of UXOs left from the war could lead to serious consequences, dangerous to human life and property of the workers and people local, adversely affect the environmental quality of the area. Before commencing construction activities, the project will deal with specialized military units to perform leakage find mines and explosives in the area all nail column, the total area of demining, animals explosion in the project area is 39,248 m 2. Therefore, the risk of accident due to residual mine is low High Construction phase 7 Surface water contamination. Medium Short - The surface water can be more turbid due to soil residues, particles generated from excavation of poles foundations. These particles flow into rivers, streams, lakes, ponds. - The subproject crosses the ditchabout 8.5m length (section G6-G7 in Thuan An town). These are source of surface water that might be more turbid in rainy season due to washing out of subproject s construction materials, excavated soil. - Though the transmission line will cross the ditch but foundations are designed about m far from ditch shores. Hence soil Medium Mitigable and Power Engineering Consulting Joint Stock Company 3 37

39 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No Impact Magnitude Duration Description of the impacts Evaluation of impacts 8 Noise and vibration excavation and damming are carried out far from these shores, therefore potential risks on land slides from these shores are not high. At the sites near fishponds, the subproject foundations will construct far from ponds (above 50 m). From the foundation sites to fish ponds are trees, rice fields so potential for debris washed out from subproject excavation to these ponds is also low. - Topography of subproject site is plain with good vegetation cover. - Subproject sites near surface water bodies are also plain so potential for soil erosion, material washing out is low. - Excavation is planned to do in dry season. Excesses soil will be reused to fill in the poles foundations. Thus there will be no soil, rock left after the subproject construction. - No tower will be constructed in ditch. - Thus the impact on surface water pollution in the subproject area is assessed as medium and can be mitigated. Medium Short - Noise and vibration are caused by: equipment, material transportation, subproject's vehicles, pole's erection and cable's pulling, generators (if there are any) - Most part of the 220 kv line is designed to be far from residential areas as well as the concentration of human activities such as towns and townships. Main part of the transmission line will be far from residential areas. - The main work will be done manually or by small scale machines. Duration of construction for each site at pole s foundation is short from 2 or 3 days for foundation excavation, 5 days for pouring concrete, 2 or 3 days for cable pulling. Noise and vibration (if there is any) will be caused only during very short period of time in each foundation position; - Owing to these mentioned reasons, the noise and vibration impact caused by the subproject is considered as medium. Medium and mitigable Power Engineering Consulting Joint Stock Company 3 38

40 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No Impact Magnitude Duration Description of the impacts Evaluation of impacts 9 Soil erosion Minor Short - The subproject area s terrain is generally flat. - The vegetation cover of subproject area at the present is relatively good: rice paddy, garden with mixed trees, fruit trees etc - Excavation is planned to carry out in dry season; - Regarding soil erosion, the impact is considered as small due to the small scale of related activities, short duration and the affected area is small. 10 Air pollution Medium Short - Dust generated from soil excavation, especially during dry seasons. - Dust generated by the transportation of supplies and equipment during the subproject construction. The transportation of raw materials, construction materials and equipments for the subproject is relatively significant. It also causes dust and air pollution. 11 Agricultural production due to temporary acquisition of productive land 12 Traffic disturbance in roads and water ways Medium Medium - Some of productive land will be mobilized for construction purpose in a short period of time. - Total amount of acquired cultivated land is 48,000 m 2 in Tan Uyen district and is 104,400 m 2 in Thuan An town. - Construction duration of the subproject is about 12 months (the next 3 months are used for installation of equipment and accessories). Therefore the temporary acquisition of productive land will only cause damages in a season or maximum 02 seasons of producing - Subproject owner has planned and will implement the compensation for the land acquisition. Medium Short - Transportation of material and equipment, soil excavation and cable pulling activities will disturb the normal traffic in the areas during short period of time; - In open areas, the transportation of construction materials is generally easy due to relatively developed traffic system in the subproject area; - Conditions for transportation of material and equipment are generally convenient. The system of provincial and inter-district road is Minor and mitigable Medium and mitigable Medium Medium and Mitigable Power Engineering Consulting Joint Stock Company 3 39

41 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No Impact Magnitude Duration Description of the impacts Evaluation of impacts 13 Degradation of the existing rural roads, pavement of rice fields. 14 Solid waste generated from soil excavation 15 Wastes from dismantling the existing 220kV Cai Lay - Cao Lanh T/L relatively good. Walking trails in the area of agricultural land, orchards are generally well developed. - The transportation of construction materials and equipments for the subproject will not exceed the capacity of the existing traffic flow in the area. Small Short - Transportation of construction materials with high frequency may cause damage to the existing rural roads; - Raw materials are transported by trucks along the inter-provincial and inter-district roads. At the foundations far from roads, materials are moved manually to construction positions. Therefore, the frequency of transport just increases very little on the soil roads with not good quality so subproject activities will not cause serious impacts on these roads. - Currently, the local government and people supervise the management of rural roads relatively well. Large load transportations are not allowed to run through roads whose quality is not good enough. - This is also an issue that the contractors have to comply and thoroughly transporting options to avoid rural road degradation. Small Short Excess soil and materials will be used for poles foundations filling. The volume of excess soil is often not enough for foundations, sometimes it has to purchase and transport from other places. Therefore it could be said that impact is in minor level. Small Short The process of dismantling the 144 columns of the existing Cai Lay - Cao Lanh single circuit 220kv will incurred: steel columns. - Steel nails recovered from 14 existing positions coincide with the new foundation. - Conductors, insulators and accessories chain of the existing 220kV line. The solid waste (steel, wire, string insulators,...) are still valid and can Minor Minor Power Engineering Consulting Joint Stock Company 3 40

42 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No Impact Magnitude Duration Description of the impacts Evaluation of impacts 16 Cause water flow block due to landslide during construction of foundations near irrigation canal make use of other power transmission projects. Because it will be transported to the warehouse of the project management unit to take advantage when bidding requirements or liquidation. Medium Short - Construction of foundation near irrigation canals might cause landslide of shores. It will block water flow in ditch. - Usually, foundation are designed to be far from ditch; - In case foundations must be located near ditch, shores of ditch will be strengthened by wooden poles to protect shores and avoid landslide as well as soil erosion. Minor Mitigable and 17 Environmental impacts caused by construction workers at camping sites 18 Conflict between construction Medium Short - Working duration is expected to last in 15 months, from that civil work such as soil excavation, tower erection, cable pulling will last for about 12 months. Other 3 months are use for installation of equipment and accessories; - It is estimated that 1 groups of workers to carry out the subproject, each group are about 74 people. - The camping sites include warehouses, open storage areas, temporary housing for workers; - Worker will use toilet and bath facilities with host families or additionally constructed for convenience. - Camping sites will dispose solid waste that can cause environmental pollution. - Almost workers will be local people, only a small number of workers needs to stay in the camps. - Thus the impact is considered as medium and mitigable. Small Short - The conflict between workers and local people might occur due to differences on income, culture and attitude; - Subproject is carried out in well developed areas and quite crowded Medium and Mitigable Minor Power Engineering Consulting Joint Stock Company 3 41

43 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No Impact Magnitude Duration Description of the impacts Evaluation of impacts workers and local people 19 Health and safety 20 Interruption of utility services Operation phase 21 Development and poverty alleviation 22 ROW violation Small or None places; the number of workers is not considerable in comparison with local people. - Stay duration of workers in each site is short (12 months) therefore this impact is insignificant. Medium Short - Accidents might happen during construction if the safety issues are not well considered. - Accidents might occur during foundation excavation, pole erecting and cable pulling. - Accidents might happen to the workers or local people living around the subproject area Small Short - Installation of transmission line requires power interruption to some areas. -Because of power interruption, some services which depend on power supply are interrupted too. Large Long - Subproject actively supports for the development of the area; There are many industrial activities in Tien Giang, Dong Thapprovince such as food processing, rice husking etc. so stable electricity supply will bring great support to provincial economics; - Increase the quality of life for local residents due to sufficiency and stability of power supply. Long - Trees within ROW could grow higher than 4m caused unsafely to transmission lines; - People might accidentally or intentionally violate ROW such as building houses with ROW; hanging antennas, or some kinds of poles which are higher than 4m; planting tree higher than 4m within ROW, etc. 23 Electromagnetic None None - The transmission line is designed according to existing technical specification; electromagnetic field will not exceed permissible value Medium and Mitigable Small Major positive Mitigable None Power Engineering Consulting Joint Stock Company 3 42

44 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No Impact Magnitude Duration Description of the impacts Evaluation of impacts field 24 Impact crossed the road traffic 25 Impact crossed the waterway traffic 26 Oil hazardous waste contamination Small or None Small or None Long Long (5kV/m). - When the power line is designed according to technical standards, the electromagnetic field in the ROW is always lower than 5 kv/m for power line with voltage under 220 kv. - At this electromagnetic field level, there will not be effect of electromagnetic field on human health The Project will crossove with Provincial Road 868, 869, Highway 1A and the other rural roads, if not properly designed regulation will affect the operation of traffic The Project will crossove with river: Cai Lay, Ba Ton, An Cu, Thong Luu, Tra Lot, My Thien, Ong Ve, My Duc Tay, Rach Mien, Co Co, Bo Gon, Muong Khai, Ba Mieng, Can Lo,..., if not properly designed regulation will affect the operation of traffic. When the transmission line goes into operation, there could have potential risks affecting the operation of travelling ships in the section crossing rivers. However, the process of design and construction for the transmission line was complied with Decree No.14/2014/ND-CP dated February 26, 2014 on the clearance of the transmission line and Document No. 617/CCDTNDPN-KT on October 27, 2010 of Southern Internal Waterway Department on the clearance height for navigability. Warning boards are attached on the transmission line section crossing the river as prescribed and regularly checked during the operation phase, so risks affecting the operation of travelling ships are small and can be controlled. Small Long - No PCBs containing oil will be used during the subproject s construction and operation; - During subproject operation, some chemical will be used such as accumulators, batteries, dielectric oil, lubricants etc. These equipment and chemicals will be registered and managed as regulated by Circular 12/2011/TT-BTNMT dated 14/4/2011 on Management of hazardous wastes. These practices are applied for all other substations of EVN No impact Power Engineering Consulting Joint Stock Company 3 43

45 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No Impact Magnitude Duration Description of the impacts Evaluation of impacts 6. MITIGATION MEASURES and will apply for Subproject as well. Power Engineering Consulting Joint Stock Company 3 44

46 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" Table 6.1. Mitigation measures No. Impacts Mitigation measures applied for the impact 1 Impacts to vegetation cover and ecological resources General mitigation measures according to ECOP Construction phase - The Contractor shall prepare a Clearance, Re-vegetation and Restoration Management Plan for prior approval by the Construction Engineer, following relevant regulations. The Clearance Plan shall be approved by Construction Supervision Consultant and followed strictly by contractor. Areas to be cleared should be minimized as much as possible. - The Contractor shall remove topsoil from all areas where topsoil will be impacted on by rehabilitation activities, including temporary activities such as storage and stockpiling, etc; the stripped topsoil shall be stockpiled in areas agreed with the Construction Supervision Consultant for later use in re-vegetation and shall be adequately protected. - The application of chemicals for vegetation clearing is not permitted. - Prohibit cutting of any tree unless explicitly authorized in the vegetation clearing plan. - When needed, erect temporary protective fencing to efficiently protect the preserved trees before commencement of any works within the site. - No area of potential importance as an ecological resource should be disturbed unless there is prior authorization from CSC, who should consult with PMUs, and the relevant local authorities. This could include areas of breeding or feeding of birds or animals, fish spawning areas, or any area that is protected as a green space. - Work with local authorities to well prepare construction schedule to avoid harvesting time. 2. Impacts of dust - The Contractor is responsible for ensuring compliance with relevant Vietnamese legislation with respect to ambient air quality. - The Contractor shall ensure that dust generation is mitigated and will not annoy local people and implement measures to control dust concentration in order to maintain safe working place and minimize disturbance to surrounding residences/houses. - Material loads shall be suitably secured during transportation to prevent the scattering of soil, sand, materials or dust. - Exposed soil and material stockpiles shall be protected against wind erosion and the location of stockpiles shall take into consideration the prevailing wind directions and locations of sensitive receptors Responsible for Implementation Contractor Contractor Power Engineering Consulting Joint Stock Company 3 45

47 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts Mitigation measures applied for the impact - Dust masks should be used where dust levels are excessive. 3 Air pollution - All vehicles must comply with Vietnamese regulations controlling allowable emission limits of exhaust gases. - Vehicles in Vietnam must undergo a regular emissions check and get certified named: Certificate of conformity from inspection of quality, technical safety and environmental protection following Decision No. 35/2005/QD-BGTVT; - There should be no burning of waste or construction materials (for example: asphalt, etc.) on site. 4 Noise and vibration - The contractor is responsible for compliance with the relevant Vietnamese legislation with respect to noise and vibration. - All vehicles must have appropriate Certificate of conformity from inspection of quality, technical safety and environmental protection following Decision No. 35/2005/QD-BGTVT; to avoid exceeding noise emission from poorly maintained machines. When needed, measures to reduce noise to acceptable levels must be implemented and could include silencers, mufflers, acoustically dampened panels or placement of noisy machines in acoustically protected areas. - Avoiding or minimizing transportation through or processing material in community areas (like concrete mixing). 5 Water pollution - The Contractor must be responsible for compliance with the relevant Vietnamese legislation relevant to wastewater discharges into watercourses. - Portable or constructed hygienic toilets must be provided on site for construction workers. Wastewater from toilets as well as kitchens, showers, sinks, etc. shall be discharged into a conservancy tank for removal from the site or discharged into municipal sewerage systems; there should be no direct discharges to any water body. - Wastewater over standards set by relevant Vietnam technical standards/regulations must be collected in a conservancy tank and removed from site by licensed waste collectors. - Implement measure to collect, redirect or block municipal wastewater disposed from surrounding houses to properly dispose and ensure that local blocking or flooding are minimized - Before construction, all necessary wastewater disposals permits/licenses and/or wastewater disposal contract have been obtained. Responsible for Implementation Contractor Contractor Contractor Power Engineering Consulting Joint Stock Company 3 46

48 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts Mitigation measures applied for the impact - At completion of construction works, wastewater collection tanks and septic tanks shall be safely disposed or effectively sealed off. 6 Solid waste - Before construction, a solid waste control procedure (storage, provision of bins, site clean-up schedule, bin clean-out schedule, etc.) must be prepared by Contractors and it must be carefully followed during construction activities. - Before construction, all necessary waste disposal permits or licenses must be obtained. - Measures shall be taken to reduce the potential for litter and negligent behavior with regard to the disposal of all refuse. At all places of work, the Contractor shall provide litter bins, containers and refuse collection facilities. - Solid waste may be temporarily stored on site in a designated area approved by the Construction Supervision Consultant and relevant local authorities prior to collection and disposal through a licensed waste collector, for example, URENCO in urban areas or local environment and sanitation companies. - Waste storage containers shall be covered, tip-proof, weatherproof and scavenger proof. - No burning, on-site burying or dumping of solid waste shall occur. - Recyclable materials such as wooden plates for trench works, steel, scaffolding material, site holding, packaging material, etc shall be collected and separated on-site from other waste sources for reuse, for use as fill, or for sale. - If not removed off site, solid waste or construction debris shall be disposed of only at sites identified and approved by the Construction Supervision Consultant and included in the solid waste plan. Under no circumstances shall the contractor dispose of any material in environmentally sensitive areas, such as in areas of natural habitat or in watercourses. 7 Chemicals or hazardous wastes - Chemical waste of any kind shall be disposed of at an approved appropriate landfill site and in accordance with local legislative requirements. The Contractor shall obtain needed disposal certificates. - The removal of asbestos-containing materials or other toxic substances shall be performed and disposed of by specially trained and certified workers. - Used oil and grease shall be removed from site and sold to an approved used oil recycling company. - Used oil, lubricants, cleaning materials, etc. from the maintenance of vehicles and machinery shall be collected in holding tanks and removed from site by a specialized oil recycling Responsible for Implementation Contractor Contractor Power Engineering Consulting Joint Stock Company 3 47

49 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts Mitigation measures applied for the impact 8 Traffic management company for disposal at an approved hazardous waste site. - Used oil or oil-contaminated materials that could potentially contain PCBs shall be securely stored to avoid any leakage or affecting workers. The local DONRE must be contacted for further guidance. - Unused or rejected tar or bituminous products shall be returned to the supplier s production plant. - Relevant agencies shall be promptly informed of any accidental spill or incident. - Store chemicals appropriately and with appropriate labeling. - Appropriate communication and training programs should be put in place to prepare workers to recognize and respond to workplace chemical hazards. - Prepare and initiate a remedial action following any spill or incident. In this case, the contractor shall provide a report explaining the reasons for the spill or incident, remedial action taken, consequences/damage from the spill, and proposed corrective actions. - Before construction, carry out consultations with local government and community and with traffic police. - Significant increases in number of vehicle trips must be included in a construction plan before approved. Routings, especially of heavy vehicles, need to take into account sensitive sites such as schools, hospitals, and markets. - Installation of lighting at night must be done if this is necessary to ensure safe traffic circulation. - Place signs around the construction areas to facilitate traffic movement, provide directions to various components of the works, and provide safety advice and warning. - Employing safe traffic control measures, including road/rivers/canal signs and flag persons to warn of dangerous conditions - Avoid material transportation for construction during rush hour. - Passageways for pedestrians and vehicles within and outside construction areas should be segregated and provide for easy, safe, and appropriate access. Signpost shall be installed appropriately in both water-ways and roads where necessary. - For water way transportation on river: working with local authorities responsible for river s transportation management, inform them on arrangement of cable pulling through the rivers (at Responsible for Implementation Contractor implement, Project owner supervise and facilitate implementation Power Engineering Consulting Joint Stock Company 3 48

50 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts Mitigation measures applied for the impact 9 Interruption to utility services 10 Restoration of affected areas least 5 days in advance) so that people attending transportation in this section of river has informed when their transportation can be affected. - Planned and unplanned interruptions to water, gas, power, internet services: the Contractor must undertake prior consultation and contingency planning with local authorities about the consequences of a particular service failure or disconnection. - Coordinate with relevant utility providers to establish appropriate construction schedules. - Provide information to affected households on working schedules as well as planned disruptions (at least 5 days in advance) - Interruptions of water supply to agricultural areas must also be avoided. - The contractor should ensure alternative water supply to affected residents in the event of disruptions lasting more than one day. - Any damages to existing utility systems of cable shall be reported to authorities and repaired as soon as possible. - Temporary acquired areas to make warehouse, cable pulling site, etc. are used for a short period of time, site facilities, workers camps, stockpiles areas, working platforms and any areas temporarily occupied during construction of the project works shall be restored using landscaping, adequate drainage and re-vegetation. - Start re-vegetation at the earliest opportunity. Appropriate local native species of vegetation shall be selected for the planting and restoration of the natural landforms. - Spoil heaps and excavated slopes shall be re-profiled to stable batters, and grassed to prevent erosion; - All affected areas shall be landscaped and any necessary remedial works shall be undertaken without delay. These works may be green-spacing, roads, bridges and other works to original existing etc. - Trees shall be planted at exposed land and on slopes to prevent or reduce land collapse and keep stability of slopes. - Soil contaminated with chemicals or hazardous substances shall be removed and transported and buried in waste disposal areas in accordance with regulations; - Restore all damaged road and bridges caused by subproject activities. Responsible for Implementation Contractor Contractor 11 Worker and - Contractor shall comply with all Vietnamese regulations regarding worker safety. Contractor Power Engineering Consulting Joint Stock Company 3 49

51 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts Mitigation measures applied for the impact public Safety 12 Communication with local communities about subproject environmental issues - Prepare and implement action plan to cope with risk and emergency. - Preparation of emergency aid service at construction site. - Training workers on occupational safety regulations - Ensure that ear pieces are provided to and used by workers who must use noisy machines such as piling, explosion, mixing, etc., for noise control and workers protection. - During demolition of existing infrastructure, workers and the general public must be protected from falling debris by measures such as chutes, traffic control, and use of restricted access zones; - Install fences, barriers, dangerous warning/prohibition site around the construction area which showing potential danger to public people; - The contractor shall provide safety measures as installation of fences, barriers warning signs, lighting system against traffic accidents as well as other risk to people and sensitive areas. - Cost estimates for the implementation of demining about d. - Maintain open communications with the local government and concerned communities; the contractor shall coordinate with local authorities (leaders of local wards or communes, leader of villages) for agreed schedules of construction activities at areas nearby sensitive places or at sensitive times (e.g., religious festival days) - Copies in Vietnamese of these ECOPs and of other relevant environmental safeguard documents shall be made available to local communities and to workers at the site. - Reduced playground space, loss of playing fields and car parking: The loss of amenities during the construction process is often an unavoidable source of inconvenience to users in sensitive areas. However, early consultation with those affected, provides the opportunity to investigate and implement alternatives - Disseminate subproject information to affected parties (for example local authority, enterprises and affected households, etc) through community meetings before construction commencement; - Provide a community relations contact from whom interested parties can receive information on site activities, subproject status and subproject implementation results; - Provide all information, especially technical findings, in a language that is understandable to the general public and in a form of useful to interested citizens and elected officials through the preparation of fact sheets and news release, when major findings become available during Responsible for Implementation Contractor in coordination with Project owner Power Engineering Consulting Joint Stock Company 3 50

52 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts Mitigation measures applied for the impact 13 Workforce, camp and site management 14 Chance finding procedures in case of foundingobjects with historical or cultural values project phase; - Monitor community concerns and information requirements as the project progresses; - Respond to telephone inquiries and written correspondence in a timely and accurate manner; - Inform local residents about construction and work schedules, interruption of services, traffic detour routes and provisional bus routes, blasting and demolition, as appropriate; - Provide technical documents and drawings to PC s community, especially a sketch of the construction area and the EMP of the construction site; - Notification boards shall be erected at all construction sites providing information about the subproject, as well as contact information about the site managers, environmental staff, health and safety staff, telephone numbers and other contact information so that any affected people can have the channel to voice their concerns and suggestions. - Worker camps will be located at least 200 m away from schools and health care centers and not be located on steep slopes. The workforce shall be provided with safe, suitable and comfortable accommodations and safe portable water. They have to be maintained in clean and sanitary conditions. - Site offices, camps, mixing stations, and workshops shall be located NOT within 100m from any water courses, 500 meters of existing residential area. - Engineers and workers shall register their temporary residence with the local authority. - Allocate officer to be the Contractor s Workplace Safety and Environment Officer responsible for environmental and safety issues including training for workers. - Septic tank toilets must be provided at all construction camp areas where there will be concentration of labor. - First aid boxes shall be provided in each construction camp site. If the Contractor discovers archeological sites, historical sites, remains and objects, including graveyards and/or individual graves during excavation or construction, the Contractor shall: - Stop the construction activities in the area of the chance find; - Delineate the discovered site or area; - Secure the site to prevent any damage or loss of removable objects. In cases of removable antiquities or sensitive remains, a night guard shall be arranged until the responsible local authorities or the Department of Culture and Information takes over; Responsible for Implementation Contractor Contractor in coordination with Project owner and relevant local authorities Power Engineering Consulting Joint Stock Company 3 51

53 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts Mitigation measures applied for the impact 15 HHs affected by land acquisition, loss of trees, crops - Notify the Construction Supervision Consultant who in turn will notify responsible local or national authorities in charge of the Cultural Property of Viet Nam (within 24 hours or less); - Relevant local or national authorities would be in charge of protecting and preserving the site before deciding on subsequent appropriate procedures. This would require a preliminary evaluation of the findings to be performed. The significance and importance of the findings should be assessed according to the various criteria relevant to cultural heritage; those include the aesthetic, historic, scientific or research, social and economic values; - Decisions on how to handle the finding shall be taken by the responsible authorities. This could include changes in the layout (such as when finding an irremovable remain of cultural or archeological importance) conservation, preservation, restoration and salvage; - If the cultural sites and/or relics are of high value and site preservation is recommended by the professionals and required by the cultural relics authority, the subproject s Owner will need to make necessary design changes to accommodate the request and preserve the site; - Decisions concerning the management of the finding shall be communicated in writing by relevant authorities; - Construction works could resume only after permission is granted from the responsible local authorities concerning safeguard of the heritage. Specific Mitigation Measures Applied for the Sub-project during Construction Phase - Careful site survey, consult with local peoples for optimum route selection, substation location; - Inform affected HHs on land temporarily and permanently acquired - Proper compensation for land acquisition for affected HHs. Estimated cost of compensation for subproject is 1,735bill. VND. - The subproject owner shall prepare and carry out the compensation plan according to Vietnamese and the WB Regulations in accordance with the RPF of the TEP Project and RP of the subproject. - Select pole s foundation locations properly to minimize impacts on land, rice field, or garden losses of local people; Pole locations should be arranged properly in local people land so that affected households can still use the remaining part of their land comfortably. - Simple scaffolds will be created when pulling cables overpass rice fields, gardens to avoid Responsible for Implementation -Design Consultant; - Project owner coordinates with local authorities. Power Engineering Consulting Joint Stock Company 3 52

54 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts Mitigation measures applied for the impact 16 Soil erosion at irrigation ditch s embankments 17 Improving house located in ROW 18 Impacts by construction activities of the transmission line section passing rivers damages to the rice fields and trees. - Create dyke, barriers to avoid erosion and landslide; When foundations are ditch need to be strengthened by wooden poles to avoid landslide and soil erosion; - Excavating, earth-moving and ground leveling activities will be scheduled to dry season, after harvest time and implemented in the shortest duration of time. - Restore the ground at construction sites after poles erection. - Implementation renovate and comfortable place for housing and work in a safe corridor. According to the preliminary investigation, of the need renovated and earth connector of roof are 396 units (including 295 units in the province of Tien Giang and Dong Thap Province 101 units) and 37 cattle sheds. - Implementation grounding for metallic structures in the earthing corridor to avoid induction stipulated in Circular 03/2010 / TT-BCT dated 22/01/2010 (earthing corridor width of 60m from the outer edge of the second wire side).according to preliminary investigation results, the total number of houses and buildings with metal structures need grounding in the corridor to address is 709 units (including 522 units of 187 Tien Giang and Dong Thap province basis). - The total cost of renovation, the grounding is d - Arrange the construction schedule for pile foundations for the shortest period. - Stretching wire passing rivers: + Preparation of stretching wire will be done carefully. + Logically arrange the schedule for stretching wire, avoid implementation during the rush hours when there are many ships, boats travelling. + Only stretching wire when there is agreement of the waterway management board, presence of the representative and the exact time according to the agreement. + Inform them on arrangement of cable pulling through the rivers (at least 5 days in advance) so that people attending transportation in this section of rivers has informed when their transportation can be affected. + At first, gather simultaneously materials, construction machinery, vehicles and instruments, then introduce the team's workers about design, distance of crossing river and content about the construction process, perform division of responsibilities among team members. Proceed agreement on convention signals and communication between construction workers working in Responsible for Implementation - Construction contractor Contractor in coordination with Project owner Contractor in coordination with Project owner Power Engineering Consulting Joint Stock Company 3 53

55 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts Mitigation measures applied for the impact 19 Safety measures applied for houses in the ROW different locations. + Signing the lease of vehicles on the river, preparing the river flow and test the ability of docking of river tugs or canoes. + Building scaffolds to pass or removing temporarily works which hinder spreading and stretching wire. + Spreading wire across the river using tugs, putting wire on rafts or floats. + If there is no a tree trunk or rock on the riverbed, then wire will be dropped into the water to be spreaded, if spreading wire by this method wire will be stretched after spreading completion. Mitigation Measures for Operation Phase Upgrade these houses to meet requirements for safe being in the ROW by the following measures: - Change corrugated roof by leaf roof; - Change corrugated walls by wooden walls; - Create earth connection of roofs and walls of these houses. 20 ROW protection - Comply with Decree 106/2005/ND-CP dated 17/8/2011 on the protection of high-voltage power grid corridor; Decree 81/2009/ND-CP dated 12/10/2009 on safety protection for high voltage power network; - Carry out regular supervision of ROWs protection. 21 Electromagnetic field and safety issues of the power line - Prepare leaflet on information on electromagnetic field and safety issues for the 220 kv power line under TEP project; - Distribute the leaflet to people in subproject areas. Responsible for Implementation - Design Consultant; - Sub-project owner - Southern High Voltage Power Network Designed consultant High Voltage Power Network Company 22 An air traffic Installation of signal lights in the office over 50m in height. - Design Consultant; - Sub-project owner 23 Impact to - Design and construction of transmission line have to comply with Decree No.14/2014/ND- Designed Power Engineering Consulting Joint Stock Company 3 54

56 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts Mitigation measures applied for the impact activities of ship due to the transmission line section passing rivers CP on February 26, 2014 on clearance of the transmission line and Document No.617/CCDTNDPN-KT on October 27, 2010 of the Southern internal waterway Branch on clearance height for ships travelling.. - Attach warning boards according to the regulations. Frequently inspecting the transmission line, specially the section passing river during operation phase. Responsible for Implementation consultant High Voltage Power Network Company Power Engineering Consulting Joint Stock Company 3 55

57 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" 7. EMP IMPLEMENTATION ARRANGEMENTS Proper environmental management during construction requires the involvement of several stakeholders and agencies, each with different roles and responsibilities including NPT, SPPMB, DONREs (Provincial Department of Natural Resources and Environment) of Tien Giang, Dong Thap province, the Contractors, the Construction Supervision Consultant, and local communities. To ensure effective implementation of the EMP, the following actions will be carried out during the implementation of the subproject: a)during thedetailed designandtenderdocumentation making - During the detailed design of technical specifications and preparation of bidding contract documents for each contract, the technical design consultant will incorporate into these bidding and contractual documents the parts of the EMP specific to that contract, as well as the specific measures identified in the EMP. - In preparing the bidding and contract documents, make an effort to ensure that the contractors are aware of the safeguard obligation and commit to comply. The environmental specifications to be included in the bidding and contractual documents are included in Annex 1. b) During the course of preconstruction and construction SPPMB will assign the Construction Supervising Consultant (CSC) and/or field engineer to be responsible for supervision of safeguard performance of contractor on a daily basis. A generic Terms of Reference (TOR) is provided in Annex2. CSC and/or field engineers will carry out, but not limited to, the following tasks: - Before the commencement of the construction, confirm that all compensation for land and facilities are provided and relocation and/or land acquisition/donation has been completed. - Review and approve Site (SEMP) to be prepared by contractor before the commencement of the construction. - Closely supervise the implementation of the EMP throughout the construction period. - Confirm the compliance with the agreed environmental plan and inspect any damages incurred by the contractor. If necessary, prepare an order to compensate/restore the construction sites as specified in the contracts. Contractor safeguard performance will be included in the subproject progress report. The role and responsibilities of relevant parties in the implementation of EMP are described in the following table: Power Engineering Consulting Joint Stock Company 3 56

58 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" Table 7.1. Arrangement for EMP implementation Community/ agencies Project Implementing Agency: NPT Project Implementing Agency: SPPMB Project Implementing Agency: PTC4 Environmental Units EUs (EU) under SPPMB and PTC4 Responsibilities - NPT will be responsible for overseeing the project implementation including ESMF implementation and environmental performance of the project. - The SPPMB will be responsible for monitoring the subproject implementation, including environmental compliance of the project. PMB will have the final responsibility for ESMF implementation and environmental performance of the subproject during the construction phase. - The SPPMB is responsible for fostering effective coordination and cooperation between contractor, local authorities, and local communities during construction phase. PMB will be assisted by the environmental staff, and CSC/or field engineer. - Specifically SPPMB will: i) closely coordinate with local authorities in the participation of the community during subproject preparation and implementation; ii) monitor and supervise EMP implementation including incorporation of EMP into the detailed technical designs and bidding and contractual documents; iii) ensure that an environmental management system is set up and functions properly; iv) be in charge of reporting on EMP implementation to NPT and the World Bank. - In order to be effective in the implementation process, SPPMB will establish an Environmental Unit with at least an environmental staff to help with the environmental aspects of the project. - The PTC4 will be responsible for monitoring the subproject implementation, including environmental compliance of the project. PMB will have the final responsibility for ESMF implementation and environmental performance of the subproject during the operation phase. - In order to be effective in the implementation process, PTC4 will establish an Environmental Unit with at least an environmental staff to help with the environmental aspects of the project. - The EUs is responsible for monitoring the implementation of WB s environmental safeguard policies in all stages and process of the subproject. Specifically, this unit will be responsible for: i) reviewing the subproject EIAs and EMPs prepared by consultants to ensure that they follow the project ESMF and meet the government and the Bank requirements; ii) helping SPPMB and PTC4 incorporate EMPs into the detailed technical designs and civil works bidding and contractual documents; iii) helping SPPMB and PTC4 incorporate responsibilities for EMP monitoring and supervision into the TORs, bidding and contractual documents for CSC; iv) providing relevant inputs to the consultant selection process; v) reviewing reports submitted by the CSC; vi) conducting periodic site checks; vii) advising SPPMB and PTC4 on solutions to environmental issues of the project; and viii) preparing environmental performance section on the progress and review reports to be submitted to NPT, the Bank, and the local Power Engineering Consulting Joint Stock Company 3 57

59 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" Community/ agencies authorities if requested. Responsibilities Construction Supervision Consultant (CSC) and/or Field Engineer Contractor Local community Mass organizations - The CSC will be responsible for routine supervising and monitoring all construction activities and for ensuring that Contractors comply with the requirements of the contracts and the EMP. The CSC shall engage sufficient number of qualified staff (e.g. Environmental Engineers) with adequate knowledge on environmental protection and construction project management to perform the required duties and to supervise the Contractor s performance. - The CSC also assists SPPMB in reporting and maintaining close coordination with the local community. - Based on the approved EMP and environmental specifications/requirements in the bidding and contractual documents, the Contractor is responsible for establishing a site-specific EMP for each construction site area, submit the plan to the SPPMB and CSC for review and approval before commencement of construction. In addition, it is required that the Contractor get all permissions for construction (traffic control and diversion, excavation, labor safety, etc. before civil works) following current regulations. - The contractor is required to appoint a competent individual as the contractor s on-site Safety and Environment Officer (SEO) who will be responsible for monitoring the contractor s compliance with the EMP requirements and the environmental specifications. - Take actions to mitigate all potential negative impacts in line with the objective described in the EMP. - Actively communicate with local residents and take actions to prevent disturbance during construction. - Ensure that all staff and workers understand the procedure and their tasks in the environmental management program. - Report to the SPPMB on any difficulties and their solutions. - Report to local authority and PMB if environmental accidents occur and coordinate with agencies and keys stakeholders to resolve these issues. - Community: According to Vietnamese practice, the community has the right and responsibility to routinely monitor environmental performance during construction to ensure that their rights and safety are adequately protected and that the mitigation measures are effectively implemented by contractors and the SPPMB. In case of unexpected problems, they will report to CSC/PMB. - These organizations could play a role as a bridge between the PPC/DPC, communities, contractors, and SPPMB by assisting in community monitoring. - Mobilizing communities participation in the subproject, providing training to communities. Power Engineering Consulting Joint Stock Company 3 58

60 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" Community/ agencies Province and District People s Committees (PPCs/DPCs), Provincial DONRE Responsibilities - Participating in solving environmental problems if any. - Oversee implementation of subprojects under recommendations of DONRE and SPPMB to ensure compliance of Government policy and regulations. - DONRE is responsible for monitoring the compliance with the Government environmental requirements. The safeguard performance will be included in the subproject and Project progress reports. SPMB with assistance from the CSC will include safeguard performance at subproject level to SPMB periodically. At the project level, NPT will prepare safeguard performance report twice per year for submission to the World Bank describing the Project progress and compliance with the ESMF and other safeguard requirements.the reporting requirement is described in Table 7.2 below. Table 7.2. Reporting Procedures Report Prepared by Submitted to Frequency of Reporting 1 Contractor to the Employer 2 Construction Supervision consultant (CSC) SPMB SPMB Once before construction commences and monthly thereafter Weekly and monthly 3 Community Monitoring SPMB When there are complaints 4 PMBs NPT 6 months per time 5 NPT WB 6 months per time SPMB report on environmental performance/compliance of the subproject should be included in the progress report submitted to the NPT before each project implementation support mission and must include sufficient information on: i) preparation and disclosures of environmental safeguards instruments for subprojects; ii) incorporation of new subproject EMPs in the bidding and contractual documents; iii) monitoring and supervision of EMP implementation by the contractor, the construction supervision engineer, and the SPMB; iv) any challenges in safeguard implementation, solutions, and lessons learned 8. MONITORINGPROGRAM 8.1.Objectives It is essential to design the monitoring program and monitoring frequency appropriately to Power Engineering Consulting Joint Stock Company 3 59

61 Subpoject of " Improvement and upgrading the Cai Lay - Cao Lanh 220 kv transmission line" be able to demonstrate both the overall performance of the subproject works as well as the shortterm impact due to peak construction activities. More specifically, as the integral and critical part of the EMP, the environmental monitoring program should have the following objectives: - Determine the actual extent of the impacts. - Control impacts thatare generated from construction process and mentioned in the EMP. - Check and supervise implementation of environmental protection solutions during construction based on EMP. - Suggest mitigation measures in case of unexpected impacts. - Suggest to the related parties to coordinate with central and local environmental organizations to solve any pending issues that might arise relating to environmental protection under the scope of the subproject. - Assess the effect of mitigation measures in pre-construction, construction and operation stages and recommend for improvement. The environmental monitoring plan is presented in table 8.1 below: Power Engineering Consulting Joint Stock Company 3 60

62 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" Table 8.1. Environmental monitoring table No. Impacts 1 Vegetation cover clearance or cutting down trees 2 Dust, air pollution Parameter to be monitored -Clearance technique - Disposal of cut-down trees. Tightness of truck bottom and whether sand/soil on trucks are covered properly Check the uncoveredspoils 3 Noise Noise level generated from construction plants and activities, Time of the day when materials/equipment are unloaded or construction is going on 4 Water pollution Wastewater collection and treatment systems Where to monitor - At substation area and along the transmission line - In a centralized place for processing. Along transportation the route and nearest house At localized soil positions and discrete stockpiles At nearest house, community centre along the route Along ROW and nearby How is the parameter to be monitored A. The construction phase Observation Observation Listen and interview Noise measuring equipment (dba) When is the parameter to be monitored/frequency of measurements or continuous -From beginning to the last moment. Before departure of filled trucks, in hot, dry and windy days While construction activities is generating high noise level /when there are complaints Cost Included in construction cost Included in construction cost -ditto- Responsibility -Contractor -Construction supervising consultant Contractors Supervisor of SPPMB Contractors Supervisor of SPPMB Observation Three- monthly -ditto- Contractors Supervisor of Power Engineering Consulting Joint Stock Company 3 61

63 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts 5 Drainage, sedimentation and erosion 6 Management solid waste 7 Management hazardous waste Parameter to be monitored Criterias of wastewater such as: ph, BOD, COD, TSS, Total N, Coliform. Drainage, sedimentation traps Level of vegetation clearance Slope Procedure and facilities to control solid waste Category solidwaste; and collection and treatment methods Concrete mixing work Quality of lavatories Solid waste at construction site Level of oil leakage at land surface of subproject area Collection and risks treatment methods Warning boards for dangerous waste storage Where to monitor water sources Drainage along ROW, nearby water sources and slops within subproject areas Camps and waste disposal site Within subproject area How is the parameter to be monitored Observation Observation Observation When is the parameter to be monitored/frequency of measurements or continuous During and after heavy rain Weekly and before work acceptance Monthly during construction phase Cost -ditto- -ditto- -ditto- Responsibility SPPMB Contractors Supervisor of SPPMB Contractors Supervisor of SPPMB Contractors Supervisor of SPPMB 8 Disruption of Technical and scope of Along ROW Observation Weekly in the first month, -ditto- Contractors Power Engineering Consulting Joint Stock Company 3 62

64 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts vegetative cover 9 Effects on rural traffic 10 Disruption road and water transportation 11 Disruption of utility services 12 Management dredged Parameter to be monitored clearance Treatment process trees after clearance Road surface condition and traffic density Quantity, loads and intensity of subproject vehicles/construction plants used Installing warning boards systems, etc Scaffold work when stringing and wire Method of construction at sections of cross connection in comparison with those mentioned in bidding documnents Water way transportation Line and conduit systems of services Effects due to disruption of utility services Position of disposal sites Where to monitor At disposal sites Along transportation route At sections of cross connection of the line and roads, channels Where are complaints Atdisposal sites How is the parameter to be monitored Listen and interview local people Listen and interview local people Observation and interview local authorities and APs When is the parameter to be monitored/frequency of measurements or continuous then monthly Weekly when materials and equipment are mobilized to the site intensively, then monthly When stringing and wire at section of cross connection Cost -ditto- -ditto- Responsibility Supervisor of SPPMB Contractors Supervisor of SPPMB and communities Contractors Supervisor of SPPMB There are complaints -ditto- Contractors Supervisor of SPPMB Observation Duringearthworkingperiod -ditto- Contractors Supervisor of Power Engineering Consulting Joint Stock Company 3 63

65 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts materials Parameter to be monitored Where to monitor How is the parameter to be monitored When is the parameter to be monitored/frequency of measurements or continuous Cost Responsibility SPPMB 13 Conflict between workers and local people Level of conflict occurred between workers and local people Resident of workers impact on lives and activities habits of the local people Conflicts occurred during resident of workers, solutions and responsibilites of constructors and owner At concentrated labors Where are complaints Interview local authorities, workers and APs There are complaints -ditto- Supervisor of SPPMB 14 Restoration of affected areas Landscape and drainage exchange Types of new plants Physico-mechanical soil criterias Level of damage of road systems in comparison with their existing conditions before construction Along ROW Taking photos existing area before commencement Observation, inspection and interview local authorities and people about difference between before and after construction phase Before and after construction There are complaints -ditto- Supervisor of SPPMB, local authorities and relevant agencies Power Engineering Consulting Joint Stock Company 3 64

66 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" No. Impacts Parameter to be monitored 15 Safety Briefing on workplace safety regulations, availability of first aid kits, storage of danger materials, warning signboards, etc. 16 Communication with local communities 1 Electric and Magnetic Field 2 ROW Clearance Level of information which local authorities and APs received about progress schedule Public information boards Electric and Magnetic Field Intensity Types of cutting and height of trees within ROW Clearing technique Disposal of cut vegetation Trees cut down within ROW Where to monitor At the unfinished pole foundation, wire installation along road Along ROW At house nearest to ROW Along ROW At disposal site How is the parameter to be monitored Observation, interview, check site log book Observation, interview local authorities and people B. The operation phase Electromagneticmeter Observation When is the parameter to be monitored/frequency of measurements or continuous Cost Responsibility During construction phase -ditto- Constructors When public consultant meeting take place There are complaints There are report/complaints about noise impacts Every three months or if there are complaints -ditto- Included in operationcos t -ditto- Supervisor of SPPMB Communities PTC4 PTC4 Power Engineering Consulting Joint Stock Company 3 65

67 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" Table 8.2.Costestimationforenvironmentmonitoring No. Item Unit cost Amount Total 1 SupervisionbyContractor - - Includedin constructioncost 2 Environmental supervisionof SPPMB 1manmonth/project 1project Includedin managementcost 3 Environmental supervisionofptc4 1manmonth/project 1project Includedin operationcost TOTAL 50,000,000 VND 9. INSTITUTIONAL DEVELOPMENT ACTIVITIES The following is capacity -buiding plan for implementing EMP - Electricity of Vietnam s training program: internal training courses on how to monitor EMP in site and how to report environmental results as part of quarterly and annual subproject reports. The program also trains mitigation measures for unexpected environmental impacts which different from forecasts mentioned in EMP. - NPT s training program: + Safety training: regular training on safety issues related to safety and the distribution network maintenance. + Monitoring and reporting of environmental management plan for stakeholders of the Subproject's district or communes:the training will give guidance to the local stakeholders about the participation of local peoples during implementation of EMP. + Training for environmental and hazardous waste management. Table 9.2. Cost estimation for capacity building plan No. Training Amount (VND) 1 Yearly training courses of EVN for all affiliates 2 Conference for sharing experience for preparing EIA and carrying our EMP A. Construction phase Included in operation cost of EVN. SPPMB shall pay for living, transportation, etc. for their staffs who participate 3 people of SPPMB shall participate: 3 people 2 days VND5,000,000/person = VND30,000,000 Included in operation cost of EVN 2 people 2 days VND5,000,000/person =VND20,000,000 3 Training course for EMP implement 2 people of SPPMB shall participate: 2 people 2 days VND5,000,000/person =VND20,000,000 Amount in construction phase VND70,000,000 Power Engineering Consulting Joint Stock Company 3 66

68 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" 4 Training course of NPT for work safety B. Operation phase Included in operation cost of SPPMB 8 people x 1 day VND1,000,000/person 20 years of subproject life = VND 160,000,000 Total amount for subproject life VND 230,000,000 Note: Training courses are carried out for all subprojects. The above cost is estimated for the Cai Lay - Cao Lanh 220kV transmission line subproject. 10. COST ESTIMATION FOR EMP IMPLEMENTATION Table SummaryofcostestimationforimplementationofEMP No. Items Implementation cost (VND) 1 Cost for information dissemination Construction phase 2 Mitigation measures Included in contract with construction contractors 3 Supervision cost for environmental supervisor of SPPMB 4 Supervision cost for CSC 5 Supervision cost for environmental supervisor of PTC4 6 Capacity building (training cost) 5,000,000 Included in management cost of the subproject 100,000, ,000,000 Operation phase Included in yearly operation cost Included in operation cost of subthe project 7 Contingency cost Included in contingency cost of approved total estimate cost for the subproject s implementation TOTAL 11. PUBLIC CONSULTATION 335,000,000 VND Public consultants are carried out by sending summary document of the subproject and organized community meetings. This summary document was described subproject s components, resettlement policy, frequently asked questions of AHs, prevented methods for risk of shock and protect measures for the ROW, potential impacts and minimized methods, etc. PECC3 held community meetings at People s Committee of affected communes in Oct Participant components who invited to the public consultation meeting consist of representatives of subproject affected households, local authorities, Fatherland Front Committee and local mass organizations (Women Union, Farmers Associations, etc.) In the consultation meetings, representatives of the subproject owner as the consultant presented some major issues as follows: Power Engineering Consulting Joint Stock Company 3 67

69 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" Introduction of the subproject and implementation schedule. Impacts on land, houses, structures, trees; mitigation measures for land acquisition; principles and policy of compensation; the grievance procedure. Impacts on air quality, noise, water quality, socio-economic activities and mitigation measures. In the community meetings, AHs queries on RP related issues such as entitlement, compensation, etc., will be answered and recorded by representatives of the subproject owner; and updated in the RP. No. Location/Date (dd/mm/yy)/ Participants 1 Location: People s Committee of Cai Lay District Date: 10/02/2013 Participants: 37 persons 2 Location: People s Committee of Thanh Hoa commune Date: 10/06/2013 Participants: 21 persons 3 Location: People s Committee of Binh Phu commune Date: 10/03/2013 Participants: 25 persons 4 Location: People s Committee of Phu An commune Date: 10/10/2013 Participants: 27 persons 5 Location: People s Committee of An Cu commune Date: 10/08/2013 Participants: 45 persons Table 11.1.Public consultation Method of public consultation Meeting Meeting Meeting Meeting Meeting Summary of issues discussed and opinions Social and resettlement issue: - During the construction phase to ensure sector regulations, does not affect the surrounding environment. - During construction, if there is damage to property, plant, crops must agreements and compensation with local people. - Before starting to notice people. Social and resettlement issue: - During the construction avoid affecting people. - Compensation for people according to negotiated price. Social and resettlement issue: During the construction process, if the occurrence of environmental problems, the SPPMB is responsible to fix any problem. Social and resettlement issue: - The project owner must be adequate compensation for the affected households. - The project owner must comply with the law on compensation - Support - resettlement. Social and resettlement issue: - The project owner must compensate land, house affected by the project in accordance with the provisions of law. - The project owner must support the affected households in the relocation process 6 Location: People s Meeting Social and resettlement issue: Power Engineering Consulting Joint Stock Company 3 68

70 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" No. Location/Date (dd/mm/yy)/ Participants Committee of Hau Thanh commune Date: 10/14/2013 Participants: 27 người 7 Location: People s Committee of Hoa Khanh commune Date: 10/07/2013 Participants: 27 persons 8 Location People s Committee of Thien Tri commune Date: 10/09/2013 Participants: 16 persons 9 Location People s Committee of My Duc Dong commune Date: 10/15/2013 Participants: 20 persons 10 Location People s Committee of My Duc Tay commune Date: 10/13/2013 Participants: 18 persons 11 Location People s Committee of An Thai Dong commune Date: 10/20/2013 Participants: 19 persons 12 Location People s Committee of An Thai Trung commune Date: 10/20/2013 Participants: 20 persons 13 Location People s Committee of Tan Hung commune Date: 11/05/2013 Method of public consultation Meeting Meeting Meeting Meeting Meeting Meeting Meeting Summary of issues discussed and opinions - Suggest to the project owner are going to meet to compensation of cost. - The project owner must satisfy the law, fair compensation for affected households. Social and resettlement issue: - The house under safety corridors don't built new. - Ensure the safety of electromagnetic fields. Social and resettlement issue:. Prior to the construction, the construction units must coordinate with the commune to let people know. Social and resettlement issue:. - There compensation expense for people fit before construction. - Ensure proper compensation for people Social and resettlement issue:. - The project owner must ensure the safety of electromagnetic fields. - The project owner must compensate and support for families affected by strict laws. - The project owner shall disclose the compensation to the affected households are known. Social and resettlement issue:. - The project owner must be public compensation and land prices for the affected households. - The project owner must comply with laws and regulations in the construction + operation. Social and resettlement issue:. - Compensation for trees, crops and property of the people for satisfactory. - Ensure the safety of electromagnetic fields. Social and resettlement issue:. - Due to the project area are mainly rice and vegetables should investors be compensated and supported in accordance with the law, Power Engineering Consulting Joint Stock Company 3 69

71 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" No. Location/Date (dd/mm/yy)/ Participants Method of public consultation Summary of issues discussed and opinions Participants: 24 persons sufficient to ensure the life of people. - The project must comply with laws and regulations in the process of construction and operation of the project. 14 Location People s Committee of My Hiep commune Date: 11/12/2013 Participants: 12 persons 15 Location People s Committee of My Long commune Date: 11/06/2013 Participants: 18 persons Meeting Meeting Social and resettlement issue:. In the process of implementing the project in the commune, the company proposed to fully implement the provisions on electrical safety, must also agree on the crop damage during project implementation Social and resettlement issue:. - The project owner must compensate for example, support to farmers in accordance with applicable laws and regulations. - The project owner must be public compensation rates in accordance with regulations. 16 Location People s Committee of Binh Hang Tay commune Date: 11/14/2013 Participants: 10 persons 17 Location People s Committee of Binh Hang Trung commune Date: 11/18/2013 Participants: 22 persons 18 Location People s Committee of My Hoi commune Date: 11/03/2013 Participants: 18 persons 19 Location People s Committee of My Tho commune Date: 11/13/2013 Participants: 10 persons Meeting Meeting Meeting Meeting Social and resettlement issue:. Before the construction should coordinate with the local survey. Social and resettlement issue:. Agree with content construction projects, but in the process of construction policies should be compensated for if people have damage fruit or assets. Social and resettlement issue:. - Compensation adequate housing, crops, land affected households. - Allow people to continue farming. Social and resettlement issue:. - The project owner must be adequately compensated for the people. - During the process of construction, if the damage of crops farmers, the project owner must pay compensation. 20 Location People s Committee of My Tho District Date: 11/24/2013 Participants: 08 persons Meeting Social and resettlement issue:. - The project must be public information about prices compensation for affected households is known. Power Engineering Consulting Joint Stock Company 3 70

72 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" No. Location/Date (dd/mm/yy)/ Participants 21 Location People s Committee of My Tho commune Date: 11/25/2013 Participants: 10 persons Method of public consultation Meeting Summary of issues discussed and opinions - Investors must comply with the legal provisions on compensation and assistance to farmers Social and resettlement issue:. - Work closely with local authorities during the compensation and land clearance. - Unit cost of compensation projects must be reviewed to ensure that people can stabilize their life and production. Power Engineering Consulting Joint Stock Company 3 71

73 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" Annex 1: Environmental Specifications for the Contractor The environmental management requirements in construction of the subproject have been established and presented clearly in the EMP (indicate the specific section of the EMP here). The Contractor need to carefully read and fully understand all requirements included in the contractor s bid: (Insert the name of the Civil Works Package here) of the subproject. I. Overview In order to avoid negative effects into the environment and local community, as well as minimizing damaging impacts to the environment during the construction and operation stages of the resettlement sites, Contractor and workers are required to observe the mitigation measures as mentioned below: - for the Project. - The technical specifications, procedures and the most popular practices are presented in this annex. II. Overall requirements of Contractor for environmental management Contractor need, in in line with the requirements of the EMP, to include, but not limited the following responsibilities: - Be in compliance with the current national legal regulations on environmental management. - Work in scope of requirements in the contract and the conditions in the bidding documents. - Assign the representative of the construction team to participate in the site inspection operations by the PMB, CSC or the DONRE as well as implement all corrective actions to overcome the environmental issues as guidance provided by the Construction Supervision Consultant (CSC). - Provide and update information for PMB about any activities, assignments that can contribute or continue to cause the significant harmful impacts into the environment. - In case of instruction by the CSC and PMB, the Contractor must stop the construction activities that causes adverse impacts, also propose and conduct the environmental remedial actions and implementation other construction methods (if required) to minimize the negative environmental impacts. - Establish and maintain an Environmental and Safety Unit, which consists of Construction team leader or Vice- team leader and Safety and Environmental Officer (SEO) with the purpose of receiving and dealing with the complaints, objections, argument and displeased of the local community caused by the construction operation. SEO is responsible to record all of complaints, resolve methods and results into the complained register. The register need to keep at the construction office and available for review by the supervision engineer and PMB. III. Responsibilities of Contractor in EMP implementation: The construction Contractor has responsibility in compliance with the technical specifications of the EMP, (name of the subproject to be inserted here) and national environmental management regulations, including but not limited the following items: Annex 3 1/2

74 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" i) The mitigation measures presented in relevant section of the EMP(indicate the specific section of the EMP here) and prepare budget for implementing the mitigation measures. ii) Based on EMP, Contractor developed a detail Site for addressing the construction related impacts. The SEMP includes the following components: - Management Plan for worker camps. - Management Plan of the overall construction operation. - Plan for management and storage of construction materials (including the dangerously chemicals) - Solid waste and waste water management plan (including construction and household waste) - Plan for management and mitigation of noise and dust. - Plan for management and mitigation of impacts to vegetation and wild animals. - Plan for environmental landscape restoration - Healthy and safety ensuring plan at the construction. - Erosion and soil aggrandizement controlling plan. - Safety plan during the construction stage and training for workers about environmental management and community relations. - Rules and regulations about living activities of staffs and workers at the construction sites. - Emergency Problem Treatment Plan. - Management and Monitoring Plan for Report Process. The detail measure of plan need to satisfy the following requirements: to implement the particular mitigation measures: who implement (people, team, etc), how to implement (labours, machines, equipment, etc.) and the cost. This plan shall be completed and submitted to the CSC for review and approval before start of the construction. The Contractor will: a) ensure that at least one supervisor is available in compliance with EMP before and during the construction time. b) ensure that all of the construction activities will be approved in document of the relevant authorities. c) ensure that all of staff and workers understand through their process and duties. d) be in compliance with requirements about the environmental management monitoring and reporting in EMP and inform to PMB about the difficulties and solutions. e) Inform to the local authority and PMB in case of environmental problems and coordinate with the relevant institutions and stakeholders for resolving. IV. Safety and Environmental Officer of Contractor: Each contractor will nominate a Safety and Environmental Officer (SEO) to work full-time at the construction site. Requirements for a SEO include an undergraduate degree in Environmental Major, at least 3 years of working experience in environmental management, training and monitoring at the infrastructure construction project. Additionally, SEO should have a good knowledge about Vietnamese Environmental Legal Regulations and has Annex 3 2/2

75 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" participated to the labor safety and sanitation training class that organized by Department of Labour- Invalids and Social Affairs and have the labor safety and sanitation certificate. SEO have the responsibilities for implementing and managing EMP of Contractor. Tasks of SEO will include, but not limit the following activities: i) Training and developing environmental awareness for workers of Contractor within 2 weeks after the contractor is mobilized. The training is repeating every six months. The additional trainings will be implemented under the guidance of Environmental Supervision Engineer. ii) iii) iv) Conduct the internal environmental monitoring at the site to check the construction activity implementation of contractors, equipment and implementation methods to manage the environmental pollution and evaluate the efficiency of the mitigation measures into the environmental impacts. Internal monitoring the implementation of environmental mitigation measures and in compliance of contractors with the environmental protection measures to prevent and control pollution; the committed requirements in the contract; guidelines of the contractor(s) on environmental improvement, environmental awareness and also proactive measures to prevent pollution. Conduct an investigation and propose the mitigation measures for the contractor(s) in case of incompliance/ infringe the EMP; monitoring and implementing the environmental mitigation measures. v) Evaluate the success of the EMP implementation to estimate effectively the cost and adequacy of the implemented mitigation measures. vi) Survey after receiving the complaint, thence evaluate and select the corrective actions. vii) Conduct the additional monitoring activities, based on the concrete guidelines of the monitoring engineer and/ or PMB; and viii) Contact and implement all activities under the co-ordination or guidance of the Contractor Leader, Environmental Supervision Engineer, Supervision Engineer, PMB, representatives of the provincial environmental management offices, local authority about all of environmental problems if necessary. ix) Establish the regularly reports for the environmental implementation of the civil works package. x) All of the internal monitoring as well as other activities of SEO should be documented and updated frequently in the environmental implementation monitoring diary of Contractor. This diary is used for normally checking by the CSC to evaluate the effectiveness of mitigation and the work of SEO. V. Monitoring the environmental implementation of Contractor: The PMB will sign a contract with the Consultant to carry out the task of CSC. The CSC will apply the environmental and monitoring activities of the package as indicated in Appendix 2. The environmental monitoring engineer of construction/execution monitoring Consultant is responsible to monitor daily the implementation of measures, in order to minimize environmental impact and safety of the Contractor. The construction monitoring Consultant will carry out the following main tasks: Annex 3 3/2

76 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" Before the construction stage, make sure that all of the compensation process for land, works on land and relocation and/ or recovery/ donation of land as well as the clearance of landmines and UXO have been completed. Review and approve the SEMP for implementing the EMP by Contractor before the construction operation. During the construction process, monitoring closely the compliance with implementing of the environmental and safety mitigation measures. Confirm the compliance with the EMP of Contractor and check any negative effect or damage caused by the contractor. If necessary, establish a request statement for contractor to compensate/ restore the construction site, as provided in the contract. The implementation of environmental management issues of the Contractor shall be mentioned in the progress report of the subprojects. VI. Compliance Framework: a) The contractors are not allowed to implement the construction activities, including preparation of construction within the project scope in advance the detail SEMP for implementation of the EMP are reviewed and approved by the construction supervision consultant and environmental official of the Client. b) The PMB is mandatory to ensure that the Contractor in compliance with the contract provision including compliance with EMP and the detail implementation plan of EMP. In case of incompliance with EMP, Client will require the Contractor to bring out the suitable measures. c) In order to ensure in compliance with the environmental standards of the sub- project, PMB is allowed to hire the third party to solve the problems in case the Contractor could not implement the remedies on time, leading to the negative effects into the environment, as follow: - For small infringements (such as minor impact/ damage, temporary and repairable), PMB or the representative of PMB (the CSC) will notify the Contractor to correct the problems as required in the EMP within 48 hours after receiving the official report. If the mistakes are satisfactorily repaired during that time, no more action should be undertaken. Supervision consultants have the right to extend more 24 hours in the limited time for recovery, under the conditions that the Contractor has implemented activities but not completed the prescribed time, due to irresistible conditions that mentioned in the contract. - For major violations, it is required about 72 hours for repairing, the PMB through the CSC will announce the violation and require the Contractor to rectify the problems within the prescribed time by their budget. If the Contractor fails to complete corrective work according to the specified time, they will be punished by financial punishment (cost punishment is calculated by the cost of remedying damage) - According to the evaluation of the CSC, if the Contractor fails to resolve the problems in environmental management or the contractor conduct reparing unsatisfactorily within the specified period of time (48 hours or 72 hours), the investors have the capacity to arrange for another contractor (third-party) to Annex 3 4/2

77 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" implement the suitable measures and deduct money for this task from the contract with the contractor in the next payment. Annex 3 5/2

78 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" ANNEX 2: TOR FOR CONSTRUCTION SUPERVISION CONSULTANT (CSC) General In order to prevent harm and nuisances on local communities, and to minimize the impacts on the environment during the construction of the civil works under the TEP Project, Environmental Code of Practices (ECOPs) and subproject EMP (if available) have been prepared and should be adhered to the Contractors and his employees. The Construction Supervision Consultant is to provide professional technical services ( the Services ) to help ensure effective implementation of the ECOP and subproject EMPs. Scope of Services: The general services to be provided by the CSC are to inspect, monitor the construction activities to ensure that mitigation measures adopted in the ECOPs/EMP are properly implemented, and that the negative environmental impacts of the subproject are minimized. On behalf of the Project Management Board (SPPMB), the CSC will conduct the following tasks: - Conduct regular site inspections; - Review the status of implementation of environmental protection measures against the EMP and contract documents; - Review the effectiveness of environmental mitigation measures and subproject environmental performance; - As needed, review the environmental acceptability of the construction methodology (both temporary and permanent works), relevant design plans and submissions. Where necessary, the CSC shall seek and recommend the least environmental impact alternative in consultation with the designer, the Contractor(s), and SPPMB; - Verify the investigation results of any non-compliance of the environmental quality performance and the effectiveness of corrective measures; and - Review and approve Site (SEMP) to be prepared by contractor before the commencement of the construction; - Instruct the Contractor(s) to take remedial actions within a specified timeframe, and carry out additional monitoring, if required, according to the contractual requirements and procedures in the event of non-compliances or complaints; - Instruct the Contractor(s) to take actions to reduce impacts and follow the required EMP procedures in case of non-compliance/discrepancies identified; - Instruct the Contractor(s) to stop activities which generate adverse impacts, and/or when the Contractor(s) fails to implement the EMP requirements/remedial actions. - For contracts that Site (SEMP) are required, the CSC shall provide the final review and recommend clearance of all Site Environmental plans which may affect the environment. These include, but are not limited to: dredging areas, borrow pits and disposal sites, worker s camp plans. The CSC will review and approve the SEMP presented by the Contractors. Where these plans are found not to comply with the EMP, EIA or ARP, the CSC shall work with the SPPMB and Contractor to establish a suitable measure or remediation. Annex 3 6/2

79 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" - Addressing Complaints: Complaints will be received by the Contractor s Site Office from local residents with regard to environmental infractions such as noise, dust, traffic safety, etc. The Contractor s Chief Engineer or his deputy, and the CSC shall be responsible for processing, addressing or reaching solutions for complaints brought to them. The CSC shall be provided with a copy of these complaints and shall confirm that they are properly addressed by the Contractors in the same manner as incidents identified during site inspections. - Certification for Monthly Payments: The CSC shall confirm the monthly payments for environmentally related activities implemented by the Contractor. - Reporting: the CSC shall prepare the following written reports: Bi-weekly report of non-compliance issues Summary monthly report covering key issues and findings from reviewing and supervision activities At the end of the subproject the CSC shall prepare a final report summarizing the key findings from their work, the number of infringements, resolutions, etc. as well as advice and guidance for how such assignments should be conducted in the future. Annex 3 7/2

80 Subpoject of " Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" Environmental Management plan No. Full Name Job Tile Position of EMP report 1 Do TrungKien Master of environment 2 Le Thi Ngoc Xuan Bachelor of Environmental engineer 3 Do QuangLinh Bachelor of Environmental engineer 4 Nguyen Minh Hieu Bachelor of Environmental engineer ANNEX 3: LIST OF MEMBERS PERFORMED THIS EMP REPORT Leader Responsibility for performance Assigned tasks 12 years 9years Member s experience Responsibility for preparing the reports of Environmental Impact Assessment (EIA), Resettlement Plan (RP), Environment Management Plan (EMP) and Ethnic Minority Development Plan (EMDP) for many power projects carried out by PECC3 Specialized education - Mike 11 software for estimate runoff in hydropower projects -EVN, Reformation framework of WB on minority ethnics - OP/BP WB, Designing maps for environmental impact assessment -EVN, Environmental management for thermal power plants project - ADB, RP/EMDP for substation and transmission line projects loaning from WB -EVN, Reformation framework of WB on minority ethnics - OP/BP WB, Environmental management plan for hydropower projects ADB, WB Safeguard Policies WB, Framework for DEP- WB, 2011 Participant 6years - Environmental Impact Assessment and Resettlement Plan -WB, 2007 Participant 6years - Environmental Impact Assessment and Resettlement Plan -WB, 2007 Annex 4 1

81 Subproject of "Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" ANNEX 4: LAYOUT OF SUBPROJECT LOCATION Annex 5 1

82 Subpoject of "Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line"

83 Subpoject of "Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" ANNEX 5: PHOTOS AND RELEVANT MAP

84 Subpoject of "Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" Picture PL5.1: The existing tower B1 of Cai Lay - Cao Lanh 220kV T/L Picture PL5.2: The existing tower B2 and B3 of Cai Lay - Cao Lanh 220kV T/L Picture PL5.3: The existing tower B34 of Cai Lay - Cao Lanh 220kV T/L

85 Subpoject of "Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" Picture PL5.4: The existing tower B37 of Cai Lay - Cao Lanh 220kV T/L Picture PL5.5: Place crossover with 500kV Nha Mon -O Mon T/L Vị trí G8 Picture PL5.6: Place G8 located on farmland from existing tower T141 about 50m

86 Subpoject of "Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" Vị tríg10 Vị trí G11 Picture PL5.7: Vị trí G10 xây dựng mới nằm trên đất ruộng Picture PL5.8: Place G10 new construction located on farmland Vị trí G13 T15 hiện hữu Picture PL5.9: Place crossover with 110kV My Thuan - Cao Lanh T/L Picture PL5.10: G13 coincides with the existing tower 15

87 Subpoject of "Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line" PHỤ LỤC 6: APPROVAL DECISION EIA REPORT

88 Subpoject of "Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line"

89 Subpoject of "Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line"

90 Subpoject of "Improvement and upgrading of the Cai Lay - Cao Lanh 220 kv transmission line"