Capital Improvement Program Monthly Status Report

Size: px
Start display at page:

Download "Capital Improvement Program Monthly Status Report"

Transcription

1 Districtwide Projects Projects Security Camera Upgrades Digital cameras and software will be installed throughout the District. Delivery Method: Design-Bid-Build Swimming Pool Upgrades Modernization and/or reconstruction of swimming pools at James Lick, Mt. Pleasant, William C. Overfelt, Piedmont Hills, Silver Creek, Santa Teresa and Yerba Buena High Schools. Delivery Method: Design-Build Energy Efficiency Project Energy services contract to implement energy conservation measures whose cost will be outweighed by net savings. Energy conservation measures under investigation include replacement of aging and/or failing mechanical and electrical system and control components, interior and exterior lighting retrofits, expansion of solar photovoltaic clean energy generation, pool heating systems, and other projects that will improve energy efficiency and/or expand clean energy generation. The energy services contract features value-added services, including creation of jobs in the clean energy sector, development of curriculum-enhancing opportunities for students and teachers, and lowering of ongoing operational expenditures. Delivery Method: Energy Services Contract (ESCO) Roof Replacements Replacement of roofs that have reached the end of their service lives, starting with the roofs in the worst condition at James Lick, Mt. Pleasant, and William C. Overfelt High Schools. Delivery Method: Design-Bid-Build Door Replacements Wi-Fi 2 Replacement of exterior doors that have reached the end of their service lives, at Andrew P. Hill, James Lick, Mt. Pleasant, Piedmont Hills, Silver Creek, and William C. Overfelt High Schools. Delivery Method: Design-Bid-Build Expansion of wireless internet access at campuses, including athletic fields and areas that have been limited instructional areas in the past due to the lack of internet access. Infrastructure installed in this project will provide a platform for future projects. Delivery Method: TBD Backend Computer System Upgrade Delivery of a modernized private cloud solution for the District s servers. Servers will be virtualized to provide a lower cost, more energy efficient, more reliable and flexible solution. Delivery Method: TBD

2 Districtwide Projects LEGEND Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Pre-Construction Security Camera Upgrades Swimming Pool Upgrades Energy Efficiency Project Construction Procurement DSA Review Construction Occupancy/Beneficial Use Roof Replacements Door Replacements Wi-Fi 2 Backend Computer System Upgrade subject to change due to factors beyond our control

3 Districtwide Projects Budget Project Funding Sources & Uses Project Measure G (2003) Fund 21 Measure I (2012) Fund 24 Developer Fees Fund 25 School Facilities Fund 35 Total Security Camera Upgrades $3.0 M $1.0 M $1.0 M $5.0 M Swimming Pool Upgrades $2.0 M $10.5 M $12.5 M Energy Efficiency Project $9.1 M $9.1 M Roof Replacements $758 K $758 K Door Replacements $853 K $853 K Wi-Fi 2 $2.4 M $2.4 M Backend Computer System Upgrades $2.5 M $2.5 M Total $12.8 M $18.4 M $1.0 M $1.0 M $33.2 M

4 Districtwide Projects Budget Expenditures Snapshot as of November 30, 2014 Security Camera Upgrades Swimming Pool Upgrades Energy Efficiency Project Roof Replacements Door Replacements Wi-Fi 2 Backend Computer System Upgrade $0 $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000 $14,000,000

5 Districtwide Projects Security Camera Upgrades Construction Manager Swinerton Management & Consulting Engineer The Consulting Group Contractor TBD Swimming Pool Upgrades Construction Manager Swinerton Management & Consulting Design Build Entity: TBD Energy Efficiency Project Construction Manager Swinerton Management & Consulting Energy Services Provider OpTerra Energy Services Roof Replacements Construction Manager Facilities Project Management Architect Skyline Engineering Contractor TBD Door Replacements Construction Manager Facilities Project Management Architect Dreiling Terrones Architecture, Inc. Contractor TBD Wi-Fi 2 Construction Manager Technology staff Engineer Technology staff

6 Districtwide Projects Backend Computer System Upgrades Construction Manager Technology staff Engineer Technology staff Contractor Not applicable Inspector Not applicable Special Testing & Inspection Not applicable Furniture, Fixtures & Equipment (FF&E) Nexus IS, Inc. Security Camera Upgrades Project-specific supplemental contractor qualification efforts will begin in January. This extra step in qualifying the electrical contractors and camera integrator subcontractors will ensure high quality bidders able to handle a Districtwide, enterprise-level installation of this nature. Swimming Pool Upgrades Proposals for second round of RFP are due in late January, followed by evaluation, and selection of the design-build team whose proposal offers the best value. Energy Efficiency Project OpTerra Energy Services has completed the Program Development work. Energy services contract award is tentatively scheduled to be recommended to the Board of Trustees in March. Roof Replacements Wi-Fi 2 Preparation of construction documents will be completed in February. Bidding for construction will occur in the Spring. There have been significant technology improvements since planning began, resulting in both lower costs and improvements in performance. Construction is expected to be commence Summer Backend Computer System Upgrades Installation is expected to be completed and systems operational by March 1st.

7 Andrew P. Hill High School Projects Budget Projects New Classroom Building 100 New 18,000 sq. ft. building features six visual arts classrooms, two science labs, three general education classrooms. A graciously sized, brightly day lit central circulation corridor with clerestory windows also serves as an informal learning space, art gallery, and event venue. Sited on the southwest corner of campus, the project also provides outdoor learning areas featuring water efficient landscaping along Senter Road, bio-retention areas for sustainable storm water management, and architectural fencing that provides a formal and secure perimeter to the campus, offering a uniform public presence to the community. Delivery Method: Design Bid Build (Multi-Prime) Baseball Field Foul Ball Net Modifications to the baseball field safety features related to the first base line, to prevent foul balls from entering neighboring properties. Delivery Method: Design Bid Build - CUPCCAA Infrastructure Upgrades Irrigation Improvements near Buildings 200 and 300 to address persistent irrigation failures. Storm Drain Improvements at Softball Complex West to address seasonal ponding near the batting cages, the area between the field and adjacent hard courts, and center field. Sanitary Sewer Improvements in and near Building 400, to address recurring stoppages in the line beneath the central courtyard associated with the Boys restroom. Delivery Method: Lease Leaseback and/or Design Bid Build CUPCCAA Courtyard Improvements Modernization of central courtyard, and courtyards between Buildings E and 600 and Buildings B and 500. Project includes demolition of portable classrooms B1-B7 and C4-C7 and installation of utilities for future Concession building with restrooms. Delivery Method: Lease Leaseback Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 LEGEND Pre-Construction New Classroom Building 100 Baseball Field Foul Ball Net Infrastructure: Softball Storm Drain Courtyard Improvements Construction Procurement DSA Review Construction Occupancy/Beneficial Use Infrastructure: Irrigation, Sanitary Sewer subject to change due to factors beyond our control

8 Andrew P. Hill High School Projects Budget Budget Project Funding Sources & Uses Project Measure E (2008) Fund 23 Measure I (2012) Fund 24 Total New Classroom Building 100 $13.8 M $13.8 M Baseball Field Foul Ball Net $80.0 K $80.0 K Infrastructure Upgrades $22.5 K $22.5 K Courtyard Improvements $45.0 K $2.2 M $2.3 M Total $14.0 M $2.2 M $16.2 M Expenditures Snapshot as of November 30, 2014 New Classroom Building 100 Baseball Field Foul Ball Net Infrastructure Upgrades Courtyard Improvements $0 $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000 $14,000,000

9 Andrew P. Hill High School Projects Budget New Classroom Building 100 Construction Manager Blach Construction Architect Cody Anderson Wasney Contractors Beals Martin, Inc. Del Monte Electric Co., Inc. Duran & Venables, Inc. Environmental System, Inc. George E. Masker Painting, Inc. King s Roofing RLH Fire Protection Robert A. Bothman, Inc. Val s Plumbing and Heating, Inc. Inspector Construction Inspection Services (CIS, Inc.) Special Testing & Inspection Bagg Engineers Furniture, Fixtures & Equipment (FF&E>$10,000) A+ Interactive Technologies Contrax Furnishings Virco Mfg. Corporation Baseball Field Foul Ball Net Construction Manager Van Pelt Construction Services Architect Artik Art & Architecture Contractor TBD Infrastructure Upgrades Construction Manager Van Pelt Construction Services Architect Artik Art & Architecture Contractor TBD Courtyard Improvements Construction Manager Van Pelt Construction Services Architect Artik Art & Architecture Contractor TBD

10 Andrew P. Hill High School Projects Budget New Classroom Building 100 Building construction is complete. Classroom furniture was delivered and installed. Landscape and irrigation construction work continues around the perimeter of the building, and will be completed in January. Classes will begin in the new building when the students return from Winter Break in late February. Courtyard Improvements, Infrastructure Upgrades, and Baseball Field Foul Ball Net Design kick-off meeting, including District staff, school administration, architect and construction manager, was held to discuss communication protocols, initial programming concepts and project schedules.

11 Independence High School Projects Performing Arts Center Building F Modernization Expansion of lobby featuring enhanced ticketing and restroom areas, accessibility upgrades, new Theater seating and audio/visual systems, new stage curtains and flooring. A modernized dance studio includes new flooring; other modernized areas include dressing rooms, makeup areas, props storage, shop, catwalks, and offices. The entire building receives updated heating/ventilation/air conditioning systems, electrical, fire alarm, communications, and security systems, along with new roofing. Delivery Method: Lease Leaseback Building B Bicentennial Hall Modernization Modernization repurposes the building for the Visual Arts academic program, featuring six visual arts classrooms, modernization of roofing, mechanical, electrical, communications, fire alarm, and security systems. The project also repairs damaged caused by a fire. Delivery Method: Lease Leaseback Site & Infrastructure Improvements Streetscape enhancements along Jackson Avenue, including a new marquee, banners, way finding signage, and upgraded landscaping. Infrastructure improvements include exterior lighting upgrades, asphalt improvements, storm drain upgrades, and exterior painting. Delivery Method: Lease Leaseback Independence / Independence Adult Center (IAC) Alternative Education Facility Upgrade Minor and major modernization work in Buildings B, G, H, K, L to accommodate alternative education programs. Modernization of Building J to house Post Senior program. Modernization of IAC Building 100 to house Administration. A new mini-campus for Pegasus High School at IAC. Project includes a Portable Village for temporary housing. Delivery Method: IH Portable Village: Design-Bid-Build; IAC Building 100 Modernization: Design-Bid-Build; balance: Lease Leaseback Gym Sound System Replacement Installation of upgraded Gymnasium sound system Delivery Method: Design-Bid-Build

12 Independence High School LEGEND Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Pre-Construction Performing Arts Center Building F Modernization Building B Bicentennial Hall Modernization Site & Infrastructure Improvements Building 100 Modernization (IAC) Construction Procurement DSA Review Construction Occupancy/Beneficial Use New Building 1000 (Pegasus High School) Building J Modernization (IH Post Senior program) Buildings G, H, K, and L Modernization Portable Village (IH) subject to change due to factors beyond our control

13 Independence High School Budget Project Funding Sources & Uses Project Measure G (2003) Fund 21 Measure E (2008) Fund 23 Measure I (2012) Fund 24 Developer Fees Fund 25 Insurance Fund 67 Total Performing Arts Center Building F Modernization $10.3M $1.2 M $11.5 M Building B Bicentennial Hall Modernization $1.3 M $2.5 M $3.8 M Site & Infrastructure Improvements $554 K $2.1 M $2.6 M Alternative Education Facility Upgrades $16.7 M $3.7M $3.0 M $23.4 M Gym Sound System Replacement $35 K $35 K Total $554 K $27.0 M $8.4 M $3.0 M $2.5 M $41.4 M Expenditures Snapshot as of November 30, 2014 Performing Arts Center Building F Modernization Building B Bicentennial Hall Modernization Site & Infrastructure Improvements Independence / Independence Adult Center (IAC) Alternative Education Facility Upgrade Gym Sound System Replacement $0 $5,000,000 $10,000,000 $15,000,000 $20,000,000 $25,000,000

14 Independence High School Performing Arts Center Building F Modernization Construction Manager Van Pelt Construction Services Inspector Construction Inspection Services (CIS, Inc.) Architect Cody Anderson Wasney Architects Special Testing & Inspection Construction Testing Services Lease Leaseback Developer McCarthy Building Companies, Inc. Furniture, Fixtures & Equipment (FF&E) Musson Theatrical Building B Bicentennial Hall Modernization Construction Manager Van Pelt Construction Services Architect Cody Anderson Wasney Architects Lease Leaseback Developer McCarthy Building Companies, Inc. Site & Infrastructure Improvements Construction Manager Van Pelt Construction Services Architect Cody Anderson Wasney Architects Lease Leaseback Developer McCarthy Building Companies, Inc Independence / Independence Adult Education Center (IAC) Alternative Education Facility Upgrade Construction Manager Van Pelt Construction Services Architect Dreiling Terrones Architecture, Inc. Lease Leaseback Developer TBD Gym Sound System Replacement Construction Manager Facilities Project Management Architect Salas O Brien, Inc. Contractor TBD

15 Independence High School Performing Arts Building F Modernization Construction is underway and proceeding as planned. Building B Bicentennial Hall Modernization Design is underway. Site & Infrastructure Improvements 90% of the schematic design phase is complete. Independence / Independence Adult Education Center (IAC) Alternative Education Facility Upgrade Architectural and construction management services contract awards will be recommended to the Board of Trustees in January.

16 James Lick High School Projects Building 900 Student Center & Quad Modernization Modernization of Building 900 and the adjacent quad will create campus facilities to support James Lick s transformation into a New Tech High School. The Student Center will fulfill several campus objectives such as providing an environment where events can be staged, and where students can gather informally outside of the classroom. The indoor/outdoor experience will provide space for varied functions and groups and will need to maintain a comfortable scale in all configurations. It will support dining areas, student activities, and presentations. Semi-public functions such as student lounges and meeting spaces will also be part of the open plan. The site s unique proximities allow an inviting transition of unobstructed flow of indoor/outdoor spaces providing a seamless experience to/from the student center, food service, the Comet Building, conference rooms, and outdoor seating under shade. Delivery Method: Lease Leaseback Classroom Modernization Modernization of classrooms to convert room layouts into open studio environments that will support James Lick s transformation into a New Tech High School. New classroom furniture will allow for mobility and quick reconfiguration of learning spaces, including mobile smart boards and mobile white board screens that act as dividers and idea space. The creation of smaller gathering spaces within the open classrooms will provide opportunities for small group learning. The campus wide implementation will also provide casual student areas outside of classroom space for small and large groups and a space for public proclamation and performance. Phase 1, completed August 2014, created 8 integrated classrooms. Phase 2 will create two additional integrated classrooms in August Phase 3 will complete the classroom modernization scope. Delivery Method: Design-Bid-Build; Lease Leaseback Storm Drain & Sanitary Sewer Infrastructure Improvements Upgrade of storm drain system between Buildings , , in the Quad bounded by Modernization of central courtyard, and courtyards between Buildings E and 600 and Buildings B and 500. Fill and grade northwest side of Baseball field to eliminate flooding, or provide new storm drain inlet; similar for south end of softball field. Upgrade sanitary sewer between Administration and Building 100. Replace underground infrastructure below pavements demolished as part of Quad Modernization. Delivery Method: Design-Bid-Build White Road Street Lighting Upgrade Public/Public/Public partnership project between East Side, City of San Jose, and Santa Clara County to upgrade street lighting along White Road between Alum Rock and Gay Avenues. Project includes installation of 21 new energy efficient, white LED lights and the conversion of 12 existing yellow lights to LED s. The additional lights will improve night time appearance and safety. City of San Jose s responsibilities include managing the project and funding ongoing street light energy and maintenance. The project is estimated to cost $320,000, and features a commensurate cost sharing arrangement.

17 James Lick High School Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Building 900 Student Center & Quad Modernization Classroom Modernization Phase 2 Classroom Modernization Phase 3 Storm Drain & Sanitary Sewer Infrastructure Improvements White Road Street Lighting Upgrade subject to change due to factors beyond our control LEGEND Pre-Construction Construction Procurement DSA Review Construction Occupancy/Beneficial Use

18 James Lick High School Budget Project Funding Sources & Uses Project Measure E (2008) Fund 23 Measure I (2012) Fund 24 School Facilities Fund 35 Total Building 900 Student Center & Quad Modernization $6.5 M $2.3 M $8.8 M Classroom Modernization $2.2 M $2.2 M Storm Drain & Sanitary Sewer Infrastructure Improvements $50 K $50 K White Road Street Lighting Upgrade $102 K $102 K Total $6.5 M $4.6 M $102 K $11.2 M Expenditures Snapshot as of November 30, 2014 Building 900 Student Center & Quad Modernization Classroom Modernization Storm Drain & Sanitary Sewer Infrastructure Improvements White Road Street Lighting Upgrade $0 $1,000,000 $2,000,000 $3,000,000 $4,000,000 $5,000,000 $6,000,000 $7,000,000 $8,000,000 $9,000,000 $10,000,000

19 James Lick High School Building 900 Student Center & Quad Modernization Construction Manager TBD Architect TBD Lease Leaseback Developer TBD Classroom Modernization Construction Manager TBD Architect TBD Lease Leaseback Developer TBD Storm Drain & Sanitary Sewer Infrastructure Improvements Construction Manager TBD Architect TBD Lease Leaseback Developer TBD White Road Street Lighting Upgrade Lead Partnering Agency City of San Jose Partnering Agency Santa Clara County Inspector Not applicable Special Testing & Inspection Not applicable Furniture, Fixtures & Equipment (FF&E) Not applicable

20 James Lick High School Building 900 Student Center & Quad Modernization RFPs for construction management services and architectural services will be issued in early Classroom Modernization RFPs for construction management services and architectural services will be issued in early Storm Drain & Sanitary Sewer Infrastructure Improvements RFPs for construction management services and architectural services will be issued in early White Road Street Lighting Upgrade City of San Jose awarded a construction contract in late Construction field work will begin in January.

21 William C. Overfelt High School Projects Building J (L) Modernization Modernization scope includes development of a home living studio space as an independent living lab, maximizing natural light into classrooms via new windows, new roof, and upgrades to mechanical, electrical, communications, fire alarm and security systems. Building J will be re-designated as Building L upon post-construction re-occupancy. Delivery Method: Design-Bid-Build Site & Infrastructure Improvements Exterior Lighting, Sanitary Sewer, and Irrigation System improvements Delivery Method: Design-Bid-Build Child Care Center Building N Play Yard Shade Canopy New canopy to provide shade in the play yard Delivery Method: Design-Bid-Build Varsity Baseball Field Upgrade Removal of east-west swale between third base line and outfield; general field renovation. Delivery Method: Design-Bid-Build Stadium Sound System Upgrade Upgrade to Stadium sound system Delivery Method: Design-Bid-Build Stadium Drinking Fountain Replacement Installation of replacement drinking fountain, near Stadium entrance. Project will result in a water line sized for a potential future Concession Stand with restrooms. Delivery Method: Design-Bid-Build

22 William C. Overfelt High School LEGEND Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Pre-Construction Building J (L) Modernization Site & Infrastructure Improvements Child Care Center Building N Play Yard Shade Canopy Construction Procurement DSA Review Construction Occupancy/Beneficial Use Varsity Baseball Field Upgrade Stadium Sound System Upgrade Stadium Drinking Fountain Replacement subject to change due to factors beyond our control

23 William C. Overfelt High School Budget Project Funding Sources & Uses Project Measure G (2003) Fund 21 Measure E (2008) Fund 23 Measure I (2012) Fund 24 Total Building J (L) Modernization $3.5 M $3.5 M Site & Infrastructure Improvements $120 K $120 K Child Care Center Building N Play Yard Shade Canopy Varsity Baseball Field Upgrade $100 K $31 K $31 K $100 K Stadium Sound System Upgrade $110 K $110 K Stadium Drinking Fountain Replacement $45 K $45 K Total $100 K $3.6 M $230 K $3.9 M Building J (L) Modernization Expenditures Snapshot as of November 30, 2014 Site & Infrastructure Improvements Child Care Center Building N Play Yard Shade Canopy Varsity Baseball Field Upgrade Stadium Sound System Upgrade Stadium Drinking Fountain Replacement $0 $500,000 $1,000,000 $1,500,000 $2,000,000 $2,500,000 $3,000,000 $3,500,000 $4,000,000 $4,500,000 $5,000,000

24 William C. Overfelt High School Building J (L) Modernization Construction Manager Van Pelt Construction Services Architect FMPO Inc. Contractor TBD Site & Infrastructure Improvements Construction Manager Van Pelt Construction Services Architect TBD Contractor TBD Child Care Center Building N Play Yard Shade Canopy Construction Manager Van Pelt Construction Services Architect TBD Contractor TBD Varsity Baseball Field Upgrade Construction Manager Van Pelt Construction Services Architect TBD Contractor TBD Stadium Sound System Upgrade Construction Manager Facilities Project Management Engineer Salas O Brien Contractor TBD Stadium Drinking Fountain Replacement Construction Manager Facilities Project Management Architect Facilities staff Contractor TBD

25 William C. Overfelt High School Building J (L) Modernization 90% of Design phase is complete. Architect is incorporating District s comments into design and preparing for DSA submission. CM is coordinating with site administration on occupant relocation strategy during construction. Site & Infrastructure Improvements 60% of preconstruction phase is complete. Child Care Center Building N Play Yard Shade Canopy Shade structure piggyback contract is Board approved. CM is seeking architectural service proposals. Varsity Baseball Field Upgrade Scoping, design and procurement activities for CUPCCAA bid process are underway; construction is scheduled to occur after the baseball season. Stadium Sound System Upgrade Construction bid documents are in development. Stadium Drinking Fountain Replacement Construction bid documents are in development.

26 Yerba Buena High School Projects Building 100 Student Union and Quad Modernization Demolition of part or all of existing Building 100, which has reached the end of its useful life. The Student Union will include a dining commons that can also be used for assemblies or other functions, academic spaces to support project-based learning, STEM classrooms, Learning/Media Center, student support and academic counseling service areas, ASB spaces, school bank, staff support spaces including copy/mail/supply center, a student/parent center, administrative offices, and a micro-fitness center. Project also includes modernization of adjacent campus quadrangle - approximately 10,000 sq. ft of landscape/hardscape - to integrate interior and exterior spaces and allow for program spaces and activities to flow seamlessly. Delivery Method: Design-Build Building 500 Theater Eaves Repair The eaves around the Theater are showing deterioration due to sun and rain exposure. The intent is to mitigate further deterioration for a 5 year period, to prevent structural compromise and to create an acceptable aesthetic outcome for this prominent building in the center of campus. Delivery Method: Design Bid Build (CUPCCAA) Infrastructure Improvements Sanitary Sewer, Storm Drain and Irrigation Improvements to address recurring stoppages in the lines beneath the campus quad, and in the line downstream from the Gymnasium locker rooms. Asphalt Repair at parking lots. Delivery Method: Design-Build and Design Bid Build (CUPCCAA) Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Student Union and Quad Modernization Building 500 Theater Eaves Repair Infrastructure Improvements subject to change due to factors beyond our control LEGEND Pre-Construction Construction Procurement DSA Review Construction Occupancy/Beneficial Use

27 Yerba Buena High School Budget Project Funding Sources & Uses Measure G (2003) Measure E (2008) Measure I (2012) School Facilities Project Fund 23 Fund 23 Fund 24 Fund 35 Total Building 100 Student Union and Modernization Quad $4.9 M $8.4 M $2.0 M $15.3 M Building 500 Theater Eaves Repair $100 K $100 K Infrastructure Improvements $212 K $212 K Total $100 K $4.9 M $8.6 M $2.0 M $15.6M Expenditures Snapshot as November 30, 2014 Building 100 Student Union and Quad Modernization Building 500 Theater Eaves Repair Infrastructure Improvements $0 $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000 $14,000,000 $16,000,000 $18,000,000

28 Yerba Buena High School Student Union and Quad Modernization Construction Manager and Design-Build Criteria Docs Kitchell CEM Design-Builder TBD Building 500 Theater Eaves Repair Construction Manager Kitchell CEM Architect TBD Contractor TBD Infrastructure Improvements Construction Manager Kitchell CEM Architect TBD Design-Builder TBD Student Union and Quad Modernization Design Build Entity (DBE) qualification phase is in process, to short-list 3 DBEs who will provide proposals to design and construct the project.