PROJECT STATUS TOTAL MAN HOURS FROM 11/20 THRU 12/14 PERCENT COMPLETE 18% OVERALL PROJECT 24% LOWER SCHOOL 31% PLAYGROUND 17% PARKING LOT

Size: px
Start display at page:

Download "PROJECT STATUS TOTAL MAN HOURS FROM 11/20 THRU 12/14 PERCENT COMPLETE 18% OVERALL PROJECT 24% LOWER SCHOOL 31% PLAYGROUND 17% PARKING LOT"

Transcription

1

2 PROJECT STATUS PERCENT COMPLETE 8% OVERALL PROJECT 24% LOWER SCHOOL 3% PLAYGROUND 7% PARKING LOT TOTAL MAN HOURS FROM /20 THRU 2/4 7 COMPANIES 8 TOTAL WORKERS 4,623 TOTAL HOURS WORKED 2 WEATHER DAYS

3

4 HIGHLIGHTS / ONGOING ACTIVITIES LOWER SCHOOL MASONRY WALLS PLUMBING WALL ROUGH-IN ELECTRICAL WALL ROUGH-IN MECHANICAL WALL ROUGH-IN THERMOSTATS GYMNASIUM PLUMBING IN SLAB ELECTRICAL IN SLAB MASONRY AT THE STAGE POUR LOBBY AND GYM BUILDING

5 HIGHLIGHTS / ONGOING ACTIVITIES PLAYGROUND GRADING STORM WATER RETAINING WALL PARKING LOT GRADING OPERATIONS 30,000 YD. OF DIRT TO MOVE FROM BORROW AREA TO PARKING LOT

6 UPCOMING MILESTONES CLASSROOM BUILDING ST FLOOR MASONRY WALLS GYMNASIUM FOUNDATIONS ELECTRICAL IN SLAB PLUMBING IN SLAB POUR SLAB 2/2/7 PLAYGROUND GRADING STORM WATER

7 CLASSROOM FOUNDATION PLUMBING WALL ROUGH-IN

8 CLASSROOM FOUNDATION ELECTRICAL IN SLAB

9 CLASSROOM FOUNDATION STRUCTURAL STEEL COLUMNS

10 CLASSROOM FOUNDATION ST FLOOR MASONRY WALLS

11 CLASSROOM FOUNDATION SLAB PREP

12 CLASSROOM FOUNDATION EARLY MORNING SLAB POUR

13 GYMNASIUM FOUNDATION FOOTING PREP

14 PLAYGROUND GRADING OPERATIONS

15 PICTURE OF THE WEEK,000 SF CONCRETE POUR

16 OAC Meeting Mountain Island Charter New Lower School November 30, 207 :30pm at Mountain Island Charter School AGENDA Construction Schedule. Week of /30 to 2/4 2. Two week look ahead a Lower School i Masonry walls ii Plumbing in slab at food service area iii Electrical in slab at food service area iv Pour another half of the classroom building v Door frames vi Mockup panel for review and approval vii Early steel installation b Playground i Temporary drive ii Stake clearing limits iii Clearing & grubbing iv Sediment and erosion control measures v Submit retaining wall design to the Gaston County c Gymnasium i Plumbing in slab ii Electrical in slab iii Masonry at the stage iv Pour lobby and gym building v Sleeves for the volleyball court Design Schedule. Large and small parking a Site plan design (submit 2/8) 2. Playground a site plan (not required to submit) b Send zoning a copy of plans and S&E plan 3. Bridge Design a Structural design (submitted to EOR 0/6) Approved b Gaston County (resubmit 2/8) 4. Off-Site (Baseball/Softball) a Board of Adjustments meeting (2/7). Track & Field, Soccer a Track & Field site plan (submit 2/9/8) b Architectural, structural, and electrical (submit 2/9/8) 6. Admin Conversion (dance/music) a Building, mechanical, electrical, and plumbing (submit 2/9/8) b Site plan (submit 2/9/8)

17 Owner Items. Board of adjustments planning meeting scheduled for December, 207 at 0am. Cost Control Meeting Date Next meeting: December :30pm Location: Construction Trailer Subject: Bi-weekly OAC Meeting Attendance Kelly Pledger MICS Justin Matthews MICS Shannon Russell MICS David Ashburn MICS Tyrone Harmon RJL

18 ID Task Mode Task Name Duration Start Finish 2 Lower School Building days Tue 0/3/7 Wed 8/22/8 Classrooms 22 STRUCTURE 9 days Tue 0/3/7 Wed 4/8/8 28 Prep & pour slab on grade A 4 days Mon /27/7 Thu /30/7 29 Slab cure A 4 days Fri 2//7 Wed 2/6/7 3 Plumbing & electrical slab B days Mon /27/7 Fri 2//7 32 Masonry Foundation B days Wed /22/7 Thu /30/7 33 Prep & pour slab on grade B 4 days Mon 2/4/7 Thu 2/7/7 34 Slab cure B days Fri 2/8/7 Thu 2/4/7 3 Erect early steel at Area 3 days Thu 2/7/7 Mon 2//7 A 36 Masonry walls st floor 2 days Thu 2/7/7 Thu //8 A 94 Lower School Building - 90 days Tue /2/7 Thu 8/6/8 Gymnasium 9 Footings 8 days Tue /2/7 Mon 2/4/7 96 Block Foundation 2 days Tue 2//7 Wed 2/6/7 97 Plumbing & electrical 4 days Thu 2/7/7 Tue 2/2/7 Slab 98 Slab prep & pour 3 days Tue 2/2/7 Thu 2/4/7 st Quarter Nov Dec Jan Prep & pour slab on grade A Slab cure A Plumbing & electrical slab B Masonry Foundation B Footings Prep & pour slab on grade B Slab cure B Erect early steel at Area A Block Foundation Plumbing & electrical Slab Slab prep & pour Masonry walls st floor A Project: Construction schedule Date: Wed /29/7 Task Split Milestone Summary Project Summary Manual Task Page

19 LEGEND: FFE = EOS = FOB = FOV = FOM = FOC = FD = TCX = CP * MF-* L* V* - 2 2' - 4" 3' - 4" 0' - 0" ' - 7 /8" 4' - 4 3/8" 3' - 2" 0' - 0" 9' - 4" 6' - 0" 3' - 2" 2' - /8" 2' - 6" ' - 8" 6' - 9" 3' - 3/8" 9' - /8" ' - 0" 7' - 4 3/8" ' - 7 /8" 4 # S-30 2MP2A 6' - 3 7/8" 3' - 4" 4 S-30 A 0' - 0" 2MP2A 2MP3A 2MP3A 2MP2A S-30 INDICATES SPREAD FOOTING (SEE SCHEDULE ON SHEET S-60) SHELBY 20 S. Washington St., Suite 200 Shelby, NC / W. Morehead St., Suite 24 Charlotte, NC / RALEIGH 63 Falls of Neuse, Suite 204 Raleigh, NC / LEXINGTON 070 S. Lake Dr., Suite J Lexington, SC / CHARLOTTE 2MP2A 2MP3A FINISHED FLOOR ELEVATION EDGE OF SLAB FACE OF BUILDING FACE OF BRICK VENEER FACE OF CMU MASONRY FACE OF CONCRETE FLOOR DRAIN (COORDINATE WITH PLUMB'G AND ARCH. DWGS.) TOP CHORD EXTENSION INDICATES CONCRETE PIER INDICATES MOMENT FRAME (SEE MOMENT FRAME ELEVATIONS) INDICATES LINTEL (SEE SCHEDULE ON SHEET S-60) INDICATES BRICK LINTEL (SEE SCHEDULE ON SHEET S-60) 2MP3A S-30 FOUNDATION & SLAB PLAN NOTES: 2MP2A B 2MP2A 2MP2A. TOP OF FOOTING ELEVATIONS GIVEN THUS (-*'-*") ARE IN REFERENCE TO FINISHED FLOOR ELEVATION = ' 2. TYPICAL EXTERIOR WALL TOP OF FOOTING ELEVATION IS (-2'-0") BELOW REFERENCE FINISHED FLOOR ELEVATION, U.N.O. 3. TYPICAL INTERIOR WALL TOP OF FOOTING ELEVATION IS (-2'-0") BELOW REFERENCE FINISHED FLOOR ELEVATION, U.N.O. 4. SEE /S-02 FOR TYPICAL MASONRY DETAILS. COORDINATE ALL DIMENSIONS WITH THE ARCHITECTURAL DRAWINGS. 6. SEE THE ARCHITECTURAL DRAWINGS FOR DIMENSIONS NOT SHOWN. 7. COORDINATE MASONRY WALL LOCATIONS AND OPENINGS WITH THE ARCHITECTURAL DRAWINGS 8. FINISH SURFACE OF SLAB-ON-GRADE PER PROJECT SPECIFICATIONS AND ARCHITECTURAL DRAWINGS. 9. LOCATE SLAB JOINTS PER PLAN, SEE /S-0 AND 2/S-0 3' - 4" UP UP S-30 S-30 S-30 S-30 S-30 S-30 S-30 S INDICATES CMU MASONRY PIER (SEE 3/S02 FOR DETAILS) *MP* 0' - 0" C S-30 S-30. D INDICATES CMU CONTROL JOINT *MP* G.C. COORDINATE ADDITIONAL MASONRY CONTROL JOINTS WITH THE ARCH. DWGS AND TYPICAL MASONRY DETAILS 2/S02. MAX SPACING B/T CONTROL JOINTS IS 24'-0" 6 S-30 S-30 3' - 2" F.D. SLOPE SLAB TO DRAIN (TYP.) F.D. S-30 S-30 6 S-30 S-30 SLAB-ON-GRADE 4" CONCRETE SLAB-ON-GRADE W/ 6X6-W.4XW.4 WWF VAPOR BARRIER PER SPECIFICATION 4" DRAINAGE COURSE 7 2MP4A S-30 ELEVATOR PIT (SEE 8/S-30 & 9/S-30) S-30 S-30 S-30 SLAB-ON-GRADE 4" CONCRETE SLAB-ON-GRADE W/ 6X6-W.4XW.4 WWF VAPOR BARRIER PER SPECIFICATION 4" DRAINAGE COURSE STEP 20" INDICATES SLAB CONTROL JOINTS, SEE & 2/S-0 S-30 F.D. F.D. 2MPA 6 S-30 STEP 20" 2MP4A 2MP6A 2MP4A 2MP4A T/FTG. EL. = (-2'-0") 2MP4A 2MP4A 7 S-30 S-30 S-30 F 3 8/ A RP ENGINEERING, INC. CONSULTING ENGINEERS S-30 S-30 S EAST FRANKLIN STREET, SUITE A PO BOX 87 MONROE NC 28 (704) NC COA C2424 F.D. S-30 S-30 F F All IDEAS, DESIGNS, DRAWINGS, AND SPECIFICATIONS SHOWN THERON ARE THE PROPERTY OF ARP ENGINEERING INC. ALL RIGHTS RESERVED INCLUDING RIGHTS OF REPRODUCTION. THIS DRAWING MUST NOT BE REPRODUCED OR COPIED IN WHOLE OR IN PART WITHOUT THE EXPRESS WRITTEN PERMISSION OF ARP ENGINEERING INC. H 6 S-30 S-30 UP 8' - 3 7/8" S-30 UP COPYRIGHT 207, ARP ENGINEERING, INC. S-30 REVISIONS 6 8MPA S-30 NO. 2 F.D. F6 F6 F6 6' - 3 7/8" K 2MP2A 7 2MP2A S-30 2' - 0 /8" L F F S-30 9/4/207 0:0:24 AM S-20 FOUNDATION PLAN - AREA A /8" = '-0" MP2A S-30 2MP3A 2MP3A 2MP2A 4 DATE 8/3/7 9/8/7 2MP2A S-30 Footing Phasing Legend CD PROJECT PHASE S-30 Description 6 CD Revisions Plan Review Comments S-30 DESCRIPTION 2MP2A 706 BOOMERANG DESIGN PROJECT NUMBER INDICATES SLAB CONTROL JOINTS, SEE & 2/S-0 MATCH LINE SLAB-ON-GRADE 4" CONCRETE SLAB-ON-GRADE W/ 6X6-W.4XW.4 WWF VAPOR BARRIER PER SPECIFICATION 4" DRAINAGE COURSE 2MP3A MATCH LINE S-30 2MP2A 2MP2A 2MP3A X F6 J 7 / F S-30 MOUNTAIN ISLAND CHARTER SCHOOL NEW LOWER SCHOOL PROJECT TITLE 2MPA 3' - 0 /4" 6 UP 2 6 SLAB-ON-GRADE 4" CONCRETE SLAB-ON-GRADE W/ 6X6-W.4XW.4 WWF VAPOR BARRIER PER SPECIFICATION 4" DRAINAGE COURSE G INDICATES SLAB CONTROL JOINTS, SEE & 2/S-0 STEP 6" STEP 6" F T/FTG. EL. = (-2'-0") S-30 (-'-0") STEP 20" 0' - 0" STEP 20" (-2'-0") 2MP4A 6 S-30 2MP2A 7 2MP4A S-30 2MP4A S-30 STEP 6" STEP 6" 37' - 9 /8" S-30 2MP4A 2MPA 2MP2A INDICATES SLAB CONTROL JOINTS, SEE & 2/S-0 2MP4A T/FTG. EL. = (-2'-0") 2MP4A 2MP4A ' - 7 /8" E S-30 2MP4A 7 DRAWING RELEASE DATE A Phase B Phase FOUNDATION PLAN AREA A Gymnasium Phase SHEET TITLE S-20 SHEET

20 LEGEND: FFE = FINISHED FLOOR ELEVATION EOS = EDGE OF SLAB FOB = FACE OF BUILDING FOV = FACE OF BRICK VENEER FOM = FACE OF CMU MASONRY FOC = FACE OF CONCRETE FD = FLOOR DRAIN (COORDINATE WITH PLUMB'G AND ARCH. DWGS.) TCX = TOP CHORD EXTENSION CP * - INDICATES CONCRETE PIER MF-* - INDICATES MOMENT FRAME (SEE MOMENT FRAME ELEVATIONS) L* - INDICATES LINTEL (SEE SCHEDULE ON SHEET S-60) V* - INDICATES BRICK LINTEL (SEE SCHEDULE ON SHEET S-60) # INDICATES SPREAD FOOTING (SEE SCHEDULE ON SHEET S-60) SHELBY 20 S. Washington St., Suite 200 Shelby, NC / RALEIGH 63 Falls of Neuse, Suite 204 Raleigh, NC / CHARLOTTE 230 W. Morehead St., Suite 24 Charlotte, NC / LEXINGTON 070 S. Lake Dr., Suite J Lexington, SC / g 2g 3g 4g g 6g FOUNDATION & SLAB PLAN NOTES:. TOP OF FOOTING ELEVATIONS GIVEN THUS (-*'-*") ARE IN REFERENCE TO FINISHED FLOOR ELEVATION = ' 2. TYPICAL EXTERIOR WALL TOP OF FOOTING ELEVATION IS (-2'-0") BELOW REFERENCE FINISHED FLOOR ELEVATION, U.N.O. K L M Ag Bg Cg Dg Eg 04' - 8" 2' - 0 /8" 2' - 4" ' - 4" 23' - 4" ' - 4" 2' - 4" ' - 3 /8" 29' - 4 3/4" F6 S-403 F6 F6 3 S-403 S-403 F6 F6 S-403 MATCH LINE S-30 RAMP DOWN RAMP DOWN SIM 2 S-30 S-30 (+'-2 3/4") 2MP2A 2MP3A 2MP3A SLAB-ON-GRADE 4" CONCRETE SLAB-ON-GRADE W/ 6X6-W.4XW.4 WWF VAPOR BARRIER PER SPECIFICATION 4" DRAINAGE COURSE (-0'-2 /4") 7 S-30 SLAB-ON-GRADE (GYM) 4" CONCRETE SLAB-ON-GRADE W/ 6X6-W.4XW.4 WWF VAPOR BARRIER PER SPECIFICATION 4" DRAINAGE COURSE GYM SLAB NOTES:. DEPRESS SLAB IN THE GYMNASIUM FOR WOOD FLOORING. 2. COORDINATE THE DEPTH OF DEPRESSION WITH APPROVED SHOP DRAWINGS AND ENSURE A LEVEL FINISH WITH ADJACENT FINISHED FLOOR SURFACES. 3. COORDINATE EXTENTS WITH THE ARCH. DRAWINGS. INDICATES SLAB CONTROL JOINTS, SEE & 2/S-0 INDICATES SLAB CONTROL JOINTS, SEE & 2/S-0 F F6 F (+0'-0") (+0'-0") 0 S-30 RAMP DOWN 2 S-30 3 S F9 F9 F8 F8 F9 2MP2A F F F F F 0' - 0" S-30 THICKEN SLAB 30"x30" B/N P.E.M.B. COLUMNS AND 30"x60" B/N PORTAL FRAMES #7 HAIRPINS (TYP. WHERE SHOWN) F9 #7 HAIRPINS (TYP. WHERE SHOWN) F9 F8 F8 F9 0' - 0" MATCH LINE S-30 F 2 S S S TYPICAL INTERIOR WALL TOP OF FOOTING ELEVATION IS (-2'-0") BELOW REFERENCE FINISHED FLOOR ELEVATION, U.N.O. 4. SEE /S-02 FOR TYPICAL MASONRY DETAILS. COORDINATE ALL DIMENSIONS WITH THE ARCHITECTURAL DRAWINGS. Footing Phasing Legend 6. SEE THE ARCHITECTURAL DRAWINGS FOR DIMENSIONS NOT SHOWN. 7. COORDINATE MASONRY WALL LOCATIONS AND OPENINGS WITH THE ARCHITECTURAL DRAWINGS Description 8. FINISH SURFACE OF SLAB-ON-GRADE PER PROJECT SPECIFICATIONS AND ARCHITECTURAL DRAWINGS. 9. LOCATE SLAB JOINTS PER PLAN, SEE /S-0 AND 2/S-0 0. INDICATES CMU MASONRY PIER (SEE 3/S02 FOR DETAILS) A Phase *MP*. INDICATES CMU CONTROL JOINT *MP* G.C. COORDINATE ADDITIONAL MASONRY CONTROL JOINTS WITH THE B Phase ARCH. DWGS AND TYPICAL MASONRY DETAILS 2/S02. MAX SPACING B/T CONTROL JOINTS IS 24'-0" Gymnasium Phase MOUNTAIN ISLAND CHARTER SCHOOL NEW LOWER SCHOOL ARP REVISIONS ENGINEERING, INC. CONSULTING ENGINEERS 202 EAST FRANKLIN STREET, SUITE A PO BOX 87 MONROE NC 28 (704) NC COA C2424 X PROJECT TITLE All IDEAS, DESIGNS, DRAWINGS, AND SPECIFICATIONS SHOWN THERON ARE THE PROPERTY OF ARP ENGINEERING INC. ALL RIGHTS RESERVED INCLUDING RIGHTS OF REPRODUCTION. THIS DRAWING MUST NOT BE REPRODUCED OR COPIED IN WHOLE OR IN PART WITHOUT THE EXPRESS WRITTEN PERMISSION OF ARP ENGINEERING INC. COPYRIGHT 207, ARP ENGINEERING, INC. NO. DATE DESCRIPTION 8/3/7 Fg 8/3/7 CD Revisions 2 9/8/7 Plan Review Comments F6 SL S-403 F9 F F 2 F S-403 F9 24' - " 7' - 7 /4" 7' - 6" 7' - 6" 7' - 7" 94' - 3 /4" CD PROJECT PHASE g 2g 3g 4g g 6g 706 BOOMERANG DESIGN PROJECT NUMBER FOUNDATION PLAN - AREA B DRAWING RELEASE DATE S-202 /8" = '-0" 9/4/207 0:0:24 AM FOUNDATION PLAN - AREA B SHEET TITLE S-202 SHEET

21 OAC Meeting Mountain Island Charter New Lower School December 4, 207 :30pm at Mountain Island Charter School AGENDA Construction Schedule. Week of 2/4 to /4 2. Three week look ahead a Lower School i Masonry walls ii Plumbing wall rough-in iii Electrical wall rough-in iv Mechanical wall rough-in thermostats b Gymnasium i Plumbing in slab ii Electrical in slab iii Masonry at the stage iv Pour lobby and gym building 2/2 c Playground i Sediment and erosion control measures ii Grading iii Storm water iv Retaining wall v Bury 2,000 yd. of unsuitable soils from playground area vi Bridge permit resubmittal for Gaston County d Parking Lot i Grading operations 30,000 yd. of dirt to move from future track to parking lot Design Schedule. Large and small parking a Site plan design (submit 2/8) 2. Playground a site plan (Zoning and Building request plans for review) b Send zoning a copy of plans and S&E plan 3. Bridge Design a Structural design (submitted to EOR 0/6) Approved b Gaston County (resubmit 2/) 4. Off-Site (Baseball/Softball) (Submit /29/8) a Erosion control plan b Site plan Submitted to zoning c Grading plan d Driveway permit NCDOT e Building plan & lighting design f Duke Energy ( or 3 Phase power for lighting). Track & Field, Soccer a Track & Field site plan (submit 2/9/8) b Architectural, structural, and electrical (submit 2/9/8) 6. Admin Conversion (dance/music)

22 a Building, mechanical, electrical, and plumbing (submit 2/9/8) b Site plan (submit 2/9/8) Owner Items. Small parking lot (entire lot is built on unsuitable soils) a. Keep light vehicle traffic only b. Bridge unsuitable soils with geotextile fabric and stone 2. Playground a. Temporary road access ends March 3, 208 b. All big deliveries in before March 3 date or need to discuss with Duke Energy for an extension for access Cost Control Meeting Date Next meeting: January :30pm Location: Construction Trailer Subject: Bi-weekly OAC Meeting Attendance Justin Matthews MICS Kelly Pledger MICS Greg Snelson MICS Tyrone Harmon RJL John Johnson RJL

23 ID Task Mode Task Name Duration Start Finish 2 Lower School Building days Tue 0/3/7 Mon 8/20/8 Classrooms 22 STRUCTURE 02 days Tue 0/3/7 Mon 3/26/8 34 Slab cure B days Fri 2/8/7 Thu 2/4/7 3 Erect early steel at Area 3 days Mon 2//7 Wed 2/3/7 A 36 Masonry walls st floor 2 days Tue 2//7 Tue /9/8 A 37 Masonry walls st floor 20 days Wed /0/8 Tue 2/6/8 B 38 2nd Floor Steel A 2 days Wed /0/8 Thu /2/8 9 Lower School Building - 83 days Mon 2/4/7 Thu 8/6/8 Gymnasium 97 Block Foundation 3 days Mon 2//7 Wed 2/3/7 98 Plumbing & electrical 4 days Tue 2/2/7 Fri 2//7 Slab 99 Slab prep & pour 3 days Fri 2//7 Tue 2/9/7 00 Pour ramps 2 days Tue 2/26/7 Wed 2/27/7 22 Playground 9 days Fri /7/7 Mon 2/2/8 27 Retaining wall days Mon 2//7 Fri 2//7 28 Finish grade days Mon 2/8/7 Fri 2/22/7 29 Bridge 20 days Mon 2/8/7 Mon //8 30 Playground equipment 30 days Tue 2/26/7 Mon 2//8 36 Large Parking Lot 76 days Mon 2/4/7 Tue 3/20/8 37 Import Soil 37 days Mon 2/4/7 Wed /24/8 48 Baseball/Softball Field 90 days Mon //8 Fri /4/8 49 Build 90 days Mon //8 Fri /4/8 January 2/0 2/7 2/24 2/3 /7 Slab cure B Erect early steel at Area A Block Foundation Plumbing & electrical Slab Slab prep & pour Retaining wall Finish grade Pour ramps Mason Project: Construction schedule Date: Wed 2/3/7 Task Split Milestone Summary Project Summary Manual Task Page

24 ID Task Mode Task Name Duration Start Finish 33 Prep & pour slab on 4 days Mon 2/4/7 Thu 2/7/7 grade B 34 Slab cure B days Fri 2/8/7 Thu 2/4/7 3 Erect early steel at Area 3 days Thu 2/7/7 Mon 2//7 A 36 Masonry walls st floor 2 days Thu 2/7/7 Thu //8 A 37 Masonry walls st floor 20 days Fri /2/8 Thu 2/8/8 B 38 2nd Floor Steel A 2 days Fri /2/8 Mon /29/8 39 2nd floor prep & pour A 4 days Tue /30/8 Fri 2/2/8 40 2nd floor slab cure A days Mon 2//8 Fri 2/9/8 4 Masonry walls 2nd floor 20 days Mon 2/2/8 Fri 3/9/8 A 42 2nd Floor Steel B 0 days Fri 2/9/8 Thu 2/22/8 43 2nd floor prep & pour B 4 days Fri 2/23/8 Wed 2/28/8 44 2nd floor slab cure B days Thu 3//8 Wed 3/7/8 4 Masonry walls 2nd floor 0 days Thu 3/8/8 Wed 3/2/8 B 46 Roof steel A 0 days Mon 3/2/8 Fri 3/23/8 47 Roof steel B 8 days Mon 3/9/8 Wed 3/28/8 48 Roofing days Thu 3/29/8 Wed 4/8/8 49 EXTERIOR 32 days Mon 2/2/8 Tue 8/4/8 0 Roof leaders and grade 20 days Mon 2/2/8 Fri 3/9/8 around building Air barrier 0 days Wed 3/2/8 Tue 4/3/8 2 Brick/stone veneer 20 days Wed 3/28/8 Tue 4/24/8 3 Install storefront frames days Wed 4/4/8 Tue 4/24/8 & glass 4 EIFS 30 days Wed 4//8 Tue /22/8 Canopy bases days Wed /23/8 Tue 6/2/8 6 Sidewalks days Wed 6/3/8 Tue 7/3/8 7 Complete Canopy days Wed 7/4/8 Tue 7/24/8 8 Asphalt days Wed 7/4/8 Tue 7/24/8 9 Landscaping days Wed 7/2/8 Tue 8/4/8 60 INTERIOR 29 days Fri 2/23/8 Wed 8/22/8 6 Interior Framing (st days Fri 2/23/8 Thu 3//8 floor) 62 PME wall rough (st 2 days Fri 3/6/8 Thu 4/9/8 floor) 63 PME overheads (st floor) 20 days Fri 4/20/8 Thu /7/8 ter 3rd Quarter 4th Quarter st Quarter 2nd Quarter 3rd Quarter 4th Quarter May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Prep & pour slab on grade B Slab cure B Erect early steel at Area A Masonry walls st floor A Masonry walls st floor B 2nd Floor Steel A 2nd floor prep & pour A 2nd floor slab cure A Masonry walls 2nd floor A 2nd Floor Steel B 2nd floor prep & pour B 2nd floor slab cure B Masonry walls 2nd floor B Roof steel A Roof steel B Roofing Roof leaders and grade around building Air barrier Brick/stone veneer Install storefront frames & glass EIFS Interior Framing (st floor) Canopy bases Sidewalks PME wall rough (st floor) Complete Canopy Asphalt PME overheads (st floor) Landscaping Project: Construction schedule Date: Tue /28/7 Task Split Milestone Summary Project Summary Manual Task Page 2

25 ID Task Mode Task Name Duration Start Finish 64 Interior Framing (2nd days Thu 3/29/8 Wed 4/8/8 floor) 6 PME wall rough (2nd 20 days Thu 4/9/8 Wed /6/8 floor) 66 PME overheads (2nd 2 days Thu /7/8 Wed 6/20/8 floor) 67 Insulation (st floor) 3 days Fri 4/20/8 Tue 4/24/8 68 Insulation (2nd floor) 3 days Thu /7/8 Mon /2/8 69 Hang and finish walls 0 days Wed 4/2/8 Tue /8/8 (st floor) 70 Hang and finish walls 0 days Tue /22/8 Mon 6/4/8 (2nd floor) 7 Prime (st floor) 0 days Wed /9/8 Tue /22/8 72 Prime (2nd floor) days Tue 6//8 Mon 6//8 73 Install ceiling grid (st days Wed /23/8 Tue 6/2/8 floor) 74 Install ceiling grid (2nd days Thu 6/2/8 Wed 7//8 floor) 7 Lighting Install (st 8 days Mon /28/8 Wed 6/6/8 floor) 76 Lighting Install (2nd 8 days Tue 6/26/8 Thu 7//8 floor) 77 Polished & sealed days Thu 6/7/8 Wed 6/3/8 concrete (st floor) 78 Polished & sealed concrete (2nd floor) days Fri 7/6/8 Thu 7/2/8 79 Temp Power Inspection day Fri 7/6/8 Fri 7/6/8 80 Temp Power 2 days Mon 7/9/8 Tue 7/0/8 8 HVAC Start-up & Bld days Wed 7//8 Tue 7/7/8 Conditioning 82 Flooring days Wed 7/8/8 Tue 8/7/8 83 Elevator Install 8 days Wed 7//8 Fri 7/20/8 84 Casework Install 0 days Wed 7/8/8 Tue 7/3/8 8 Paint Final days Wed 8//8 Tue 8/2/8 86 PME Trims (st floor) 2 days Thu 6/4/8 Wed 7/8/8 87 PME Trims (2nd floor) 20 days Fri 7/3/8 Thu 8/9/8 88 Install Doors & Hdwr 0 days Wed 8/8/8 Tue 8/2/8 89 PM&E Final Inspections days Fri 8/0/8 Thu 8/6/8 90 Building Final Inspection day Fri 8/7/8 Fri 8/7/8 ter 3rd Quarter 4th Quarter st Quarter 2nd Quarter 3rd Quarter 4th Quarter May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Interior Framing (2nd floor) PME wall rough (2nd floor) Insulation (st floor) PME overheads (2nd floor) Insulation (2nd floor) Hang and finish walls (st floor) Hang and finish walls (2nd floor) Prime (st floor) Prime (2nd floor) Install ceiling grid (st floor) Install ceiling grid (2nd floor) Lighting Install (st floor) Lighting Install (2nd floor) Polished & sealed concrete (st floor) Polished & sealed concrete (2nd floo Temp Power Inspection Temp Power HVAC Start-up & Bld Conditioning Flooring Elevator Install Casework Install Paint Final PME Trims (st floor) PME Trims (2nd floor) Install Doors & Hdwr PM&E Final Inspections Building Final Inspection 9 Owner Punch Walk day Wed 8/22/8 Wed 8/22/8 92 Owner Punch Walk Project: Construction schedule Date: Tue /28/7 Task Split Milestone Summary Project Summary Manual Task Page 3

26 ID Task Mode Task Name Duration Start Finish 93 Lower School Building - 90 days Tue /2/7 Thu 8/6/8 Gymnasium 94 Footings 3 days Tue /2/7 Mon /27/7 9 Block Foundation 2 days Tue /28/7 Wed /29/7 96 Plumbing & electrical 4 days Thu /30/7 Tue 2//7 Slab 97 Slab prep & pour 3 days Tue 2//7 Thu 2/7/7 98 PEMB Steel 20 days Mon //8 Fri 2/9/8 99 PEMB roof & walls 0 days Mon 2/2/8 Fri 2/23/8 00 Interior framing days Mon 2/26/8 Fri 3/6/8 0 PME wall rough days Mon 3/9/8 Fri 4/6/8 02 PME overhead 20 days Mon 4/9/8 Fri /4/8 03 Insulation 4 days Mon 4/9/8 Thu 4/2/8 04 Hang & finish walls 0 days Fri 4/3/8 Thu 4/26/8 0 Prime paint 0 days Fri 4/27/8 Thu /0/8 06 Ceiling grid 4 days Fri //8 Wed /6/8 07 Lighting install days Thu /7/8 Wed 6/6/8 08 Install Doors & Hdwr 3 days Thu 6/7/8 Mon 6//8 09 Locker install 2 days Tue 6/2/8 Wed 6/3/8 0 Paint Final 0 days Thu 6/4/8 Wed 6/27/8 Install BB goals days Thu 6/28/8 Wed 7/4/8 2 PME Trims 0 days Thu 6/28/8 Wed 7//8 3 Install gym floor 0 days Thu 7/2/8 Wed 7/2/8 4 Install bleachers 6 days Thu 7/26/8 Thu 8/2/8 Finish Gym Floor & Stripe 0 days Fri 8/3/8 Thu 8/6/8 6 PM&E Final Inspections 3 days Thu 7/9/8 Mon 7/23/8 ter 3rd Quarter 4th Quarter st Quarter 2nd Quarter 3rd Quarter 4th Quarter May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Footings Block Foundation Plumbing & electrical Slab Slab prep & pour PEMB Steel PEMB roof & walls Interior framing PME wall rough Insulation PME overhead Hang & finish walls Prime paint Ceiling grid Lighting install Install Doors & Hdwr Locker install Paint Final Install BB goals PME Trims Install gym floor Install bleachers Finish Gym Floor & Stripe PM&E Final Inspections 7 Building Final Inspection day Tue 7/24/8 Tue 7/24/8 Building Final Inspection Project: Construction schedule Date: Tue /28/7 Task Split Milestone Summary Project Summary Manual Task Page 4