Renovation Progress. July 2-6, Week 39

Size: px
Start display at page:

Download "Renovation Progress. July 2-6, Week 39"

Transcription

1 Renovation Progress July 2-6, 2012 Week 39

2 Jul 2 Plaster mud applied to upper section of walls along 1 st Ottilia hallway

3 Jul 2 Markings indicate the location of kitchen fire extinguisher boxes

4 Jul 2 Plumbers collecting their supplies at the new BSRC restrooms in the dining area

5 Jul 2 Too much rain in the passing shower chases the brick masons home for the rest of the day

6 Jul 3 1 st Ottilia main entrances get plastered

7 Jul 3 Ductwork insulation in kitchen area begins

8 Jul 3 The final rows of brick are being set in place on the Ottilia tower

9 Jul 3 Digging up the area for the new south Ottilia driveway begins; topsoil is being saved for reuse

10 Jul 3 Rerouting the BSRC walkway from one side of the flagpole to another

11 Jul 3 Green markings indicate the placement of new towel racks in Ottilia bathrooms

12 Jul 3 Cable company and electrical progress in 2 nd Ottilia

13 Jul 3 Door handle installation progresses down 2 nd Ottilia

14 Jul 3 Painters putting second coat of china white paint in bathrooms

15 Jul 3 HVAC and electrical work in the Ottilia tower (2 nd floor entryway)

16 Jul 3 Holes cut for plumbing in new restroom underneath the Ottilia staircase

17 Jul 3 Ottilia tower brickwork is completed (except for cleaning)

18 Jul 5 Metal roofers arrive bright and early to finish topping off the Ottilia tower while scaffolding is still in place

19 Jul 5 Dirt scraping and leveling continues on the south end of Ottilia Hall; wooden ramp provided for handicap access to the Retreat Center

20 Jul 5 Masons build up columns around the steel supports along the east wall of the private retreatant area

21 Jul 5 Furring strip installation in 1 st Ottilia elevator entrance area is being completed, then the crew will move to the Infirmary laundry and staff restroom under the Ottilia staircase

22 Jul 5 Plumbers begin their work at the BSRC dining area restrooms

23 Jul 5 The new Sisters serving area has been tagged for proper electrical and plumbing

24 Jul 5 Even the arriving hardware, like these boxes of door hinges, feel the challenge of getting up the stairs these days

25 Jul 5 More plaster progress on 1 st Ottilia

26 Jul 5 More above-ceiling work in the Infirmary getting the ceiling fans installed

27 Jul 5 Overhead view of driveway leveling

28 Jul 5 More freshly painted China White bedrooms on 2 nd Ottilia

29 Jul 3 Sewer system supplies and access containers arrive

30 Jul 5 Plumbing from BSRC dining area restrooms pokes through the lower level s ceiling

31 Jul 5 Rainwater draining supplies

32 Jul 5 Masonry progress on the east-facing columns

33 Jul 6 Brick masons more their supplies and activity to the north side of the building new the Private Retreatant area entrance

34 Jul 6 Piles of supplies from the newly-arrived to last spring s leftovers

35 Jul 6 Wooden stakes in the ground mark the placement on new manholes for the sewer system

36 Jul 6 Down at the creek between the monastery and Benedictine Manor workers begin to access the existing sewer system

37 Jul 6 Metal framework completed in and around the new Infirmary staff restroom

38 Jul 6 1 st Ottilia hallway sanding and application of second coat of plaster mud

39 Jul 6 More mud application and sanding in Infirmary bedrooms

40 Jul 6 Infirmary bathroom tile work

41 Jul 6 More ceiling fan installation in the Infirmary

42 Jul 6 Insulation of ductwork in the kitchen area continues

43 Jul 6 Got gutters? The Ottilia tower is getting them and a downspout, too

44 Jul 6 Roll Tide?? For bathrooms in Ottilia with no wall space to hang a dispenser a variety of options are being considered, communally of course

45 Jul 6 Masons working where the stairs to the north porch will be

46 Jul 6 Two pipes in the ground and covered over for the weekend; a run-off barrier is set up in case a heavy rain tries to wash away loose topsoil

47 Jul 6 Plumbing progress for the BSRC dining area restrooms

48 Jul 6 BSRC Dining Room cleaned up for the weekend

49 Jul 6 Outdoor stairwell foundation with water drainage piped through the area

50 Jul 6 With the below ground brickwork completed and water drainage set in place, the trench along the northeast corner of the Private Retreatant area is covered over with dirt; Golden engineer works with the masons to ensure correct measurements and leveling lines

51 Drainage is ready for the crew installing the sewer line to make it to the top of the hill

52 Happy are you who fear the LORD, who walk in God s ways! Ps 128:1