1 SCHEDULE OF CONDITION Buckinghamshire Marketing by:

2 CONTENTS SCHEDULE OF CONDITION Elevations page 4 Internal Rooms page 10 GROUND FLOOR FIRST FLOOR Other Matters page 28 FIRE REGULATIONS DISABILITY AND DISCRIMINATIONS ACT ASBESTOS REGISTER Limitations page 30 Signature Document page 31&32 2

3 Address: Prospective Tenant: Repairing Covenant, Redecorating Covenant, Reinstatement and Statutory Regulation Covenant Yield Up Clause: Buckinghamshire Mrs X We have not seen a copy of the lease and we have therefore assumed the property has a full repairing and insuring covenant or will have under the proposed lease. We have assumed it is a standard lease with no unusual or onerous clauses. Your Legal Adviser should confirm this and advise us of any unusual or onerous clauses immediately. Photographs: We typically take approximately 100 photographs during the course of a Schedule of Condition. We reserve the right to produce these photographs to establish the condition of the property over and above the ones included in the report. Orientation: All directions are taken as if viewing the property from the front. The Schedule of Condition offers a detailed description of the condition of the property on the day of inspection. We have not carried out formal investigations by phone or otherwise with Local Authorities or other statutory bodies. The Schedule of Condition is to be read in conjunction with the Property Report. 3

4 ELEVATIONS All directions given as you face the property. Under the terms of most Leases there is a redecoration covenant requiring redecoration on termination of the Lease we assume this will take place or appropriate agreed monetary compensation in lieu of this to the new tenants. 4

5 FRONT ELEVATION DESCRIPTION CONDITION ACTION REQUIRED Roofs: Profile pre-finished sheeting Weathered. It is usually a condition of the lease that it is redecorated every x number of years and redecorated on the termination of the lease. In this case we can see no decoration has been carried out whatsoever. Gutters and Downpipes: Box gutters and internal downpipes Walls: There is a collection of water and leaf waste, etc within the box gutter and we can see damp staining to the ceilings beneath. We believe this is a design defect and should be excluded from the lease.. Profile pre-finished sheeting As above redecoration is usually a condition of the lease. Detailing: Single glazed windows Double entrance door Require cleaning and painting. Please see our comments with regards to typical lease terms. 5

6 REAR ELEVATION DESCRIPTION CONDITION ACTION REQUIRED Roofs: Profile pre-finished sheeting Rear roof Roof: Water sitting around rear of flue Tar staining indicate roof has been repaired recently Poor quality repairs, deterioration to fascia and deterioration around central linear roof light Staining to profile metal sheeting Staining to the ends of the profile metal and also to the expansion joints Close up view 6

7 Gutters and Downpipes: Box gutters and internal downpipes Sludge sitting in box gutter to rear of roof Walls: Profile pre-finished sheeting Windows and Doors: Roller shutter loading bay doors Generally overgrown to rear area Damaged and damp stained Repair, prepare and Fire exit Damp staining visible to rear roller shutter doors Marked Repair, prepare and General marking to rear fire exit Base needs cleaning and redecorating 7

8 INTERNAL All directions given as you face the property. Under the terms of most Leases there is a redecoration covenant requiring redecoration on termination of the Lease we assume this will take place or appropriate agreed monetary compensation in lieu of this to the new tenants. 8

9 GROUND FLOOR 9

10 Entrance Lobby and staircase Ceilings: DESCRIPTION CONDITION ACTION REQUIRED High ceiling with suspended ceiling tile finish Staining and tiles slightly displaced indicating water leak to front left hand corner (likely to relate to box gutter that we have seen on the roof) all directions given as you face the property Repair leak and replace ceiling tile Above suspended ceiling in stairs/landing Walls: Painted blockwork Radiators to right hand side and rear Not recently painted Repair, prepare and 10

11 Floors: Carpet tiles Clean and/or replace Staircase: Metal staircase with a half landing finished with carpet Clean and/or replace carpet Detailing Single glazed windows 11

12 Office to Right Hand Side Ceilings: DESCRIPTION CONDITION ACTION REQUIRED Plaster onto concrete (assumed) Hairline cracking to front Repair, prepare and Walls: Painted blockwork Marked and old fixing points to right hand wall Clean, repair, prepare and Skirting Internal radiator on right hand side of entrance lobby area (all directions given as you face front of property) Marked Marks to walls Clean, repair, prepare and Testing for rising damp 12

13 Floors: Carpet tiles Average Detailing: Single glazed metal windows with glazed venting system on front Door Average Marked Repair, prepare and Clean and repair 13

14 Single Internal WC (off reception area) Ceilings: DESCRIPTION CONDITION ACTION REQUIRED Painted concrete It would benefit from redecoration. Repair, prepare and Walls: Painted blockwork Splash back tiles 100mm square, 5 high Floors: Thermoplastic tiles Marked and old fixings points Repair, prepare and Clean or replace Sanitary Ware: One wash hand basin and one WC Detailing: Deep clean Door Marked Repair, prepare and 14

15 Access Corridor to WCs DESCRIPTION CONDITION ACTION REQUIRED Ceilings: Painted concrete Walls: Painted blockwork Floors: Thermoplastic tiles Marked Marked and old fixings points Repair, prepare and Repair, prepare and Clean or replace Detailing: Door Marked Repair, prepare and 15

16 Ladies WC DESCRIPTION CONDITION ACTION REQUIRED Ceilings: Painted concrete Marked Repair, prepare and Walls: Painted blockwork Splash back tiles Partitions formed in a faced particleboard (generically known as Conti board) Single panel internal radiator Floors: Thermoplastic tiles Manhole to centre Painted concrete ceiling Marked and old fixings points Note: the drains have not been tested Repair, prepare and Clean Clean and redecorate Clean or replace 16

17 Sanitary Ware: Two wash hand basin and two WCs Detailing: High level windows Door Dirty Marked Clean and Repair, prepare and 17

18 Lobby to Gents WC (Note: lights not working, survey carried out without light) Ceilings: Painted concrete Walls: DESCRIPTION CONDITION ACTION REQUIRED Painted blockwork Floors: Thermoplastic Marked Clean/replace Detailing: Doors Marked Clean, repair, prepare and 18

19 Gents WC Ceilings: DESCRIPTION CONDITION ACTION REQUIRED Painted concrete Marked Repair, prepare and Walls: Painted blockwork Partitions formed in a faced particleboard known as conti board Marked Repair, prepare and redecorate Internal radiator Floors: Vinyl Marked Clean/replace Sanitary Ware: Two WCs, two wash hand basins and one urinal Detailing: High level windows Doors Marked Dirty Clean Clean. Repair, prepare and 19

20 Workshop Area (double storey height located to the rear) DESCRIPTION CONDITION ACTION REQUIRED Structural frame: Metal portal structural frame Not redecorated as required by a standard full repairing and insuring lease. Some possible rusting visible. Ceilings: Cladding panels Replacement cladding panel to left hand corner (all directions given as you face front of property) Replaced panel indicates that dampness is getting in through the rear box gutter which is in line with what we saw with water sitting in the box gutter. Repair leak, repair, prepare and Dampness visible coming inside from linear roof light Left hand side cracking at high level 20

21 Rear wall: Formed in panels at high level and painted blockwork at low level and roller shutter door. Panels at high level, some are marked, general cleaning required. Blockwork at low level which needs to be redecorated, particularly marked behind the boiler. Clean panels. Repaint walls including floor paint at lower end. Panels to front wall need securing Possible asbestos to flue on rear wall Asbestos register required. Roller shutter door Fire exit door Dividing wall between the workshop and the offices: Impact damage marks Marked Make good. Make good and 21

22 Left hand wall: Painted blockwork Left hand wall Right hand wall: Painted blockwork with old fixing points Right hand wall - Painted blockwork with old fixing points and some decoration left on it. Dust on ledge area. Staining at the base with floor paint. Not decorated at the end of the lease. Redecorate. Floors: Painted concrete Clean, repair, prepare and redecorate Floor Floor paint gone on walls Services: 3 heaters including Ideal E-type heater Earth test 22

23 Wash Up Area Ceilings: DESCRIPTION CONDITION ACTION REQUIRED Painted concrete Marked Repair, prepare and redecorate Walls: Painted blockwork Heavily marked Repair, prepare and Floors: Painted concrete Sanitary Ware: Belfast sink Damaged paintwork just outside wash up area Average Heavily marked Cold tap not working Deep clean or replace 23

24 Internal Room (Store/Kitchenette) off workshop area Ceilings: Painted concrete Walls: DESCRIPTION CONDITION ACTION REQUIRED Painted blockwork Average Remove bench, make good fixings and Floors: Painted concrete Services: See Services section Electrics Boiler: un-insulated 24

25 FIRST FLOOR Under the terms of most Leases there is a redecoration covenant requiring redecoration on termination of the Lease we assume this will take place or appropriate agreed monetary compensation in lieu of this to the new tenants. 25

26 Open Plan Office DESCRIPTION CONDITION ACTION REQUIRED Ceilings: Suspended ceiling with square ceiling grid tiles with category two style lighting Two areas of water staining visible to the tiles to the front of property, one to the middle and one to the left hand side (all directions given as you face the property) Replace damaged and stained ceiling tiles once the roof and guttering is made watertight. As mentioned we believe this to be a design defect. Water damaged ceiling tiles Looking above suspended ceiling Rusting visible to box gutter 26

27 Walls: Painted blockwork below and blockwork above Dampness visible to steel portal frame. Clean, repair, prepare and Raking crack front left hand corner Floors: Painted blockwork and parts of ceiling tile on the floor. Painted blockwork hasn t been painted in accordance with most full repairing and insuring lease requirements to paint at the end of the lease and it doesn t look to have been painted during the lease. Carpet tiles Average Clean Detailing: Windows Clean 27

28 OTHER MATTERS SERVICES Electrics All electrics need to be tested by an NICEIC approved electrician or equivalent to Institute of Electrical Engineers (IEE) standard. Fuel Gas/Oil The respective safety standards to be applied and most full repairing and insuring leases require a test certificate. All services to Gas Safe Standard or equivalent. FIRE REGULATIONS Normally it is a requirement of any Lease or Tenancy agreement that current fire regulations are adhered to and that a service contract is in place. This is how the property should be left. ACTION REQUIRED: You should have a suitable Fire Safety Notice from the outgoing tenant/landlord. You should have a suitable Fire Safety Notice from the outgoing tenant/landlord. DISABILITY DISCRIMINATION ACT You should be aware that it is now a requirement to give reasonable access to the disabled and make reasonable amendments to the property as is necessary to accommodate them. It is a condition of all the leases that we have seen to meet this requirement. ACTION REQUIRED: You should ask to see if a report has been carried out in line with the Disabilities Act highlighting areas that can be improved or have been improved. 28

29 ASBESTOS REGISTER In a property of this age there may well be some asbestos. This was commonly used post war until it was banned only in the last ten or so years, although it is rumoured that it was still used after this point in time. It is now a requirement for any public building to have an asbestos register, indicating whether there is or is not asbestos and if so where it is. ACTION REQUIRED: An Asbestos Register should be provided by the outgoing tenant/landlord. You should note that work involving products containing asbestos is covered by Health and Safety legislation and you are recommended to seek the advice of the Local Authority Environmental Health Officer before proceeding with any such work. We are not asbestos surveyors. 29

30 LIMITATIONS As per our original Terms of Engagement, we would remind you specifically that: We have not inspected parts of the structure that were covered, unexposed or inaccessible during our inspection. We therefore cannot confirm that such parts are free from defect, structural or otherwise. We have not determined whether any hazardous materials such as high alumina cement, calcium chloride, asbestos etc have been used in the construction. Our report is for the use of the party to whom it is addressed above and no responsibility is accepted under the Third Parties Act or for any third parties who use this report in whole or in part. We have not carried out a comprehensive test of any electrical, mechanical or drainage services. We therefore cannot confirm that they are operational and in good condition. If you wish us to arrange tests please advise. We have not carried out or arranged for specialists to undertake any reports, for example an environmental report or an audit report upon the property. We are therefore unable to advise whether any contaminated or other adverse environmental issues affect the site. The Schedule of Condition has been prepared following an inspection. This report does not constitute a Structural Survey (now known as a Building Survey). 30

31 Signature Document in Relation to XXX St, XXX Town, Buckinghamshire Schedule of Condition This signature document represents page 31 and 32 of a 32 page Schedule of Condition relating to: XXX St, XXX Town, Buckinghamshire You should ensure your Legal Advisor gets this document signed by the relevant parties and agreed prior to legal commitment to purchase. Delete/amend as you require. Lessees Representative We verify that this is a true and accurate record of the condition of: XXX St, XXX Town, Buckinghamshire Signed:

32 Lessee Mrs X has seen and forwarded this document on by recorded delivery on.... to the owners/landlords or their legal representatives in relation to the proposed Lease. Signed:... Mrs X Dated: Landlords Representative (delete as applicable) Print Name:.... for and on behalf of..... has inspected and read the Schedule of Condition for an on behalf of. and accepts that it is a true and accurate record. Signed: Dated:. For and on Behalf of:..... I have the authority to sign this document on behalf of the aforementioned company. 32