1 USER S MANU HAKI UNIVERS UMINIUM HAKI AB 2005

2 Important information HAKI s product liability and erection instructions apply only to scaffolds that are entirely composed of components that have been made and supplied by HAKI. HAKI s type examination certificate applies only to scaffolds whose material, dimensions and design accord with those specified in the documentation upon which this certificate is based. HAKI s scaffold systems must not be erected using components of makes other than HAKI or be connected to scaffolds of makes other than HAKI. In such cases, a special study of loadbearing capacity must be carried out. However, HAKI has no objection to the customary addition of scaffold tubes and approved couplers to the scaffold. Adding components from different suppliers may invalidate the insurance cover. For scaffold structures that are not covered by these erection instructions, please contact HAKI s technical department. HAKI reserves the right to make technical modifications on a continual basis. Copyright HAKI AB, 2005 The reproduction of text and pictures/illustrations without HAKI s permission is prohibited. 2

3 BASIC INFORMATION HAKI Universal Aluminium The modular scaffold has been type examined by SP Swedish National Testing and Research Institute in accordance with Ordinance AFS 1990:12 of the Swedish National Board of Occupational Safety and Health Code of Statutes and SS-HD 1000 Certificate no for load class 3 (2.0 kn/m2). Calculations were carried out in accordance with SP Method General data HAKI Universal Aluminium is erected with bay widths of 700, 770, 1050, 1250 or 1655 mm and normally with a bay length of 3050 mm and 2.0 m between lifts. LB or ERB beams can be used both as ledger and transom beams. HAKI decking units or planks are suitable for decking. Marking components except for locks, locking pins, etc. are permanently marked with HAKI s logo and a combination of characters where the last two digits specify the year of manufacture ( S05). Guardrail frames Toeboard Decking Wall tie Standard Ledger beam 2.0 m Single tube beam Base jack 3050 mm 3

4 LIST OF COMPONENTS For steel components, the weights and article numbers apply to hot-dip galvanized products. For other accessories, please see type examination certificates numbers and for HAKI modular scaffolds and also HAKI s erection instructions. Name Art.Nr Code Weight (kg) Base jack BS 5.0 Steel Adjustable mm Standard FSSH Standard joint with spigot FSSH Pockets at same level FSSH Ø 48 mm FSSH FSSH FSSH Locking pin for standard joint Steel Ø 16 mm For reinforcing standard joint in connection with tensile load, e.g. when scaffolding is suspended, when lifting or when scaffolding is used for temporary roof. Ledger beam LB With spring locking catch LB Ø 34 mm LB LB LB LB LB LB Single tube beam ERB With spring locking catch ERB Ø 48 mm ERB ERB ERB ERB ERB ERB ERB

5 LIST OF COMPONENTS Name Art.Nr Code Weight (kg) Guardrail frame SKRD With spring locking catch SKRD SKRD SKRD SKRD SKRD , SKRD SKRD Diagonal brace DS DS Plan brace telescopic HDS 6.3 Wall tie SVF Tie rod SVF Steel Rod Ø 12 mm Tie rod clamp BVF 0.6 Steel Decking unit B=600 mm High hook location Decking Unit 1200x Load class 4 (3,0 kn/m²) Decking Unit 1605x Decking Unit 2450x Decking Unit 3000x B=400 mm Decking Unit 1200x Decking Unit 1605x Decking Unit 2450x Decking Unit 3000x

6 LIST OF COMPONENTS Name Art.Nr Code Weight (kg) Decking unit with trapdoor Decking Unit 2450x See Decking unit Trapdoor Decking Unit 3000x Trapdoor Ladder ST For decking unit with trapdoor plank P 1250x230x P 1655x230x P 2500x230x P 3050x230x Toeboard Toeboard 564x Toeboard 700x Toeboard 1050x Toeboard 1250x Toeboard 1655x Toeboard 1964x Toeboard 2500x Toeboard 3050x Toeboard FL 3300x150x Wood Toeboard clip LF Steel Bracket SK Without spigot for joint to standard SK With spring locking catch Ø 48 mm Bracket with spigot SK With spigot for joint to standard With spring locking catch 6

7 LIST OF COMPONENTS Name Art.Nr Code Weight (kg) Bracket SK With spring locking catch Stairway UTV Stair handrail UTV Guardrail post SRS Steel Guardrail post SSK Steel Jaw width 23 mm Lattice beam FBB Steel Standard adapter FBB Steel Lattice beam FB FB FB

8 ERECTION Before erecting the scaffold, check and flatten out the support surface. The support surface must not be subject to uneven settlement. Its bearing capacity may be improved with the help of sole plates. 1. Set out the material for the base and the first lift along the facade. Place the base jacks about 200 mm out from the facade and at the modular distances that are to be used. If inside brackets are to be used, increase the distance accordingly. The greatest permissible distance between wall and work platform is 300 mm. Always start erection at the point 1. that is situated highest. 2. Erect the first four standards, linking them with the transom and ledger beams. The beams are fitted to the lowest group of pockets on the standards. Check that the beam locks are in the locked position after fitting Fit the SKRD guardrail frames along the scaffold at a level of 1.0 m. Guardrail frames must be fitted in each bay and at each lift level on the outside of the scaffold. Alternatively, fit the vertical diagonal braces. Continue erecting the base of the scaffold bay by bay using base jacks, standards, transoms and ledger beams and guardrail frames. If HAKI UTV stairways are to be used, plan a 3050 mm bay for the ascent. From time to time, check the levels in both the transverse and longitudinal directions using a spirit level and adjust using the swivel base jacks. If there are major differences in levels, adjust each individual standard in relation to the support surface so as to make the beams level.

9 ERECTION 4. Fit the transom and ledger beams for the second lift 2.0 m above the beams that were fitted first. Fit HAKI decking units to the transom beams. Don t forget to lock the decking. Fit the second set of 3000 or 2000 mm standards. Install SKRD guardrail frames for the second lift and fit the toeboards with the aid of the toeboard clips. Don t forget the end guardrails Fit the transom and ledger beams for the third lift and then decking, guardrails and toeboards. Don t forget to lock the beams and decking. Anchor the scaffold at a height of approximately 4.8 m using tie rods and clamps. Check that the fixings in the facade can carry the forces involved Continue erecting the subsequent lifts as described above. Use approved lifting aids for transport of the material. If steel/aluminium planks are used, these should be locked in the outer bays. The planks otherwise lock each other. When decking using scaffold boards, these must be provided with yokes if the span exceeds 2.5 m. Dismantling is done in the reverse order. Scaffolding material must not be thrown down from the scaffold. 9

10 External stairways ERECTION There are two options for external stairways: the HAKI UTV of steel and the HAKI UTV of aluminium. Both options are fitted in a similar manner The UTV stairway is fitted in an external bay using ERB 720 and LB/ERB 3000 beams. The stairway is usually built into the scaffold proper. Alternatively, the stair tower is erected using separate standards. Set out the base jacks and erect the standards. Fit the ERB 720 and LB/ERB beams into the lowest group of pockets. Fit the transom beams for the second lift too. At other levels, the handrails replace the ledger beams. 8. Fit the hooks of the UTV stairway over the tubes of the transom beams and lock the stairs using the locking device. Fit the handrail at the 1.0 m level and provide the top end with SKRD 720 guardrail frames. Fit the next set of standards, transom beams, stairs, handrail and guardrail frames Continue erection up to the desired height. At the top level, an ERB 3000 beam is fitted externally in the scaffold. An SSK 1000 guardrail post is fitted on the beam so that an SKRD 2450 guardrail frame can be fitted between post and standard. Alternatively, an LB 3000 beam can be combined with an SRS 1000 guardrail post. The guardrail frame provides fall protection at the top level of the scaffold. At other levels, the next stairway provides sufficient protection.

11 LOADING CONDITIONS Base jacks The scaffold is erected on base jacks of type BS, which are adjustable between 55 and 570 mm. This means that it is always possible to adjust the standards so as to make the beams level. Standards Standards of length 3000 or 2000 mm are normally used in the scaffold. When FSSH 2000 standards are used throughout the scaffold, the permissible construction height is reduced by 6.0 m. Standards shorter than 2000 mm may only be used as landing standards. Beams The scaffold is erected using LB or ERB beams as ledger and/or transom beams with 2.0 m between the lifts. Each lift must be provided with beams on both the inside and outside. The bottom lift must always be placed at the lowest possible level. Guardrails Decked lifts must be provided with guardrail frames or double guardrails and toeboards if the drop is 2.0 m or more. Access ways must be provided with double handrails. Decking HAKI decking units are used for decking. These units are available in lengths of 1200, 1605, 2450 and 3000 mm with widths of 600 and 400 mm. Alternatively, HAKI aluminium or steel planks may be used. These are available in all modular dimensions and in widths of 230 or 170 mm. Other options are wooden gratings in lengths of 1950 or 1400 mm and of width 485 mm. The wooden gratings are placed across the ledger beams of the scaffold. Decking may also be done using 195 x 50 mm scaffold planks, class K24. Headroom When using ERB beams and HAKI decking units, the headroom is 1910 mm. Using aluminium/steel planks, the headroom is more than 1910 mm. Brackets Brackets can be placed at the five highest lift levels of the erected scaffold. Each level at which a bracket is fitted must be provided with a wall tie. Load classes for brackets apply provided that the brackets are fitted in a bay of length max mm and in connection with decking of weight 16 kg/m2. In the specified weight classes, no consideration has been paid to the bearing capacity of the decking. Using HAKI decking units, max. load class 4 applies. Bracket SK 230 SK 460 SK 1200 Load class

12 LOADING CONDITIONS Bracing and tying-in Bracing with vertical diagonal braces and tying-in Bracing with SKRD guardrail frames and tying-in Vertical diagonal bracing between the outside standards must be installed in every 5th bay and always in the end bays. SKRD guardrail frames can replace vertical diagonal braces, but must then be fitted in each bay and at every lift level, including the bottom level. PLEASE NOTE when bracing with SKRD guardrail frames, the permissible loads on standards are reduced. See table on page 13. Plan braces must be fitted in every 5th bay and always in the end bays at every 12th metre in height. Each inside standard must be tied to the facade or equivalent at every 4th metre in height in conjunction with the node between standard and beam. The lowest tie must be fitted no more than about 4.8 m above ground level. There must be ties that can carry horizontal forces on at least every 6th pair of standards along the scaffold and at every level of ties. In addition, we recommend that the scaffold always be anchored as high up as possible. Where a scaffold is contained, the number of ties must be increased to take account of wind load. See instructions for the containment in question. 12

13 LOADING CONDITIONS Permissible loads on standards When calculating permissible construction heights for the scaffold, the following permissible loads on standards can be applied for different combinations of lift height and vertical distances between ties. Lift height Vertical distance between ties Permissible load on standard Permissible load on standard SKRD* [m] [m] [kn] [kn] * Scaffold braced with SKRD guardrail frames 1 kn = 100 kp 13

14 Permissible construction heights The table applies to HAKI Universal Aluminium with bay lengths 3050 mm, lift heights 2.0 m, bracing using vertical diagonal braces and different vertical distances between ties. PLEASE NOTE when bracing with SKRD guardrail frames, the permissible loads on standards are reduced. Work must not be carried out on more than one lift at a time. Decking has been calculated at 16 kg/m². LOADING CONDITIONS SS-HD 1000 recommends a bay width of at least 1.0 m for load classes 4, 5 and 6. Other bay lengths, bay widths and decking alternatives will have an effect on the permissible construction height. Please contact HAKI s technical department in these cases. Vertical distance between ties [m] Bay width [mm] Number of decked lifts Load class/ Permissible load [kn/m 2 ] kn = 100 kp 14

15 LOADING CONDITIONS Permissible loads on beams Permissible loads on beams installed in HAKI standards. Beam type Permissible load q [kn/m] Permissible distributed load Q [kn] Permissible centrepoint loads P [kn] Permissible centrepoint loads P3 [kn] Permissible point loads P4 [kn] LB LB LB LB ERB ERB ERB ERB ERB ERB ERB ERB kn = 100 kp 15

16 LOADING CONDITIONS Permissible load classes for different beam combinations The tables apply to HAKI Universal Aluminium LB or ERB beams for varying bay sizes, decking of weight 16.5 kg/m² and unilateral or bilateral loading. In the specified load classes, no consideration has been paid to the bearing capacity of the decking. Permissible load classes for LB beam for unilateral loading a [mm] LB 1605 LB 1914 LB 2450 LB Permissible load classes for ERB beam for unilateral loading a [mm] ERB ERB 1000 ERB 1200 ERB 1605 ERB 1914 ERB 2450 ERB Loaded beam Loaded beam a a Wide scaffold Facade scaffold 16

17 LOADING CONDITIONS Permissible load classes for LB beam for bilateral loading a [mm] LB 1605 LB 1914 LB 2450 LB Permissible load classes for ERB beam for bilateral loading a [mm] ERB ERB 1000 ERB 1200 ERB 1605 ERB 1914 ERB 2450 ERB Loaded beam Loaded beam a a a a Wide scaffold Facade scaffold 17

18 Lattice beams LOADING CONDITIONS Access ways Access is usually provided by means of HAKI UTV stairways that are fitted to the outside of the scaffold using components designed for this purpose. Alternatively, a HAKI tower scaffold may be used, see type examination certificate Ascent via ladders may be arranged by means of HAKI decking units with trapdoors and ladders, or HAKI STV ladders. Lattice beams of steel FBB 6050 steel lattice beams are designed to allow the scaffold to continue to be erected across a span equivalent to two 3050 mm bays. When installing the lattice beams, it is very important to brace these against lateral movement by fitting a beam to the fixings in the middle of the lattice beams. Steel lattice beams are fitted to the standards of the scaffold by hooking them over two groups of pockets. The FBB standard adapter is used to continue erecting. Lattice beam of steel Lattice beams of aluminium Aluminium lattice beams are fitted in pairs on the inside and outside of the scaffold. Both the top and bottom tubes must be fixed to the standards using KV 48x48 swivel couplers. The height of the lattice beams is 450 mm. Permissible loads on lattice beams Lattice beam of aluminium Lattice beam Permissible load q [kn/m] Permissible distributed load Q [kn] 18 Permissible centre-point load P [kn] Permissible point loads P3 [kn] Steel FBB Aluminium FB FB FB kn = 100 kp

19

20 HAKI INT P Published by Holmbergs in Malmö SAFETY SHECKLIST 1. Supporting surface checked with regard to bearing capacity 2. Distance to wall or similar as short as possible 3. Scaffold aligned correctly horizontally and vertically 4. Components correctly fitted and locked 5. Bracing correctly done 6. Anchoring with right number and placing of ties 7. Decking correctly done 8. Guardrail with toeboard if drop is two metres or more 9. Suitable means of access to scaffold 10. Scaffold erected for correct class of load HAKI AB is ISO 9001:2000 certified HAKI AB SE Sibbhult, Sweden Tel Fax

USER S MANUAL HAKI CONTINENTAL

USER S MANUAL HAKI CONTINENTAL USER S MANUAL HAKI CONTINENTAL HAKI AB 2003 HAKI User s Manual and product liability applies only to scaffolding containing components manufactured and supplied by HAKI. Building scaffolding using components

More information

USER S MANUAL HAKI UNIVERSAL

USER S MANUAL HAKI UNIVERSAL USER S MANUAL HAKI UNIVERSAL Suspended scaffolding HAKI AB 2012 Important information HAKI s product liability and erection instructions apply only to scaffolds that are entirely composed of components

More information

USER S MANUAL HAKI STAIR TOWER

USER S MANUAL HAKI STAIR TOWER USER S MANUAL HAKI STAIR TOWER HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made and supplied

More information

USER S MANUAL HAKI COMPACT STAIR TOWER

USER S MANUAL HAKI COMPACT STAIR TOWER USER S MANUAL HAKI COMPACT STAIR TOWER HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made

More information

USER S MANUAL HAKI PUBLIC ACCESS STAIR

USER S MANUAL HAKI PUBLIC ACCESS STAIR USER S MANUAL HAKI PUBLIC ACCESS STAIR HAKI AB 2017 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made

More information

USER S MANUAL. HAKI Loading Tower

USER S MANUAL. HAKI Loading Tower USER S MANUAL HAKI Loading Tower HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made and

More information

USER S MANUAL HAKI COMPACT STAIR TOWER

USER S MANUAL HAKI COMPACT STAIR TOWER USER S MANUAL HAKI COMPACT STAIR TOWER HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made

More information

USER S MANUAL HAKI PUBLIC ACCESS STAIR

USER S MANUAL HAKI PUBLIC ACCESS STAIR USER S MANUAL HAKI PUBLIC ACCESS STAIR HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made

More information

USER S manual HAKI UNIVERSAL. International version

USER S manual HAKI UNIVERSAL. International version USER S manual HAKI UNIVERSAL International version HAKI AB 2014 Important information HAKI s product liability and erection instructions apply only to scaffolds that are entirely composed of components

More information

USER S MANUAL HAKI UNIVERSAL

USER S MANUAL HAKI UNIVERSAL USER S MANUAL HAKI UNIVERSAL International version HAKI AB 2015 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have

More information

USER S Manual. HAKI Bridge System (HBS)

USER S Manual. HAKI Bridge System (HBS) USER S Manual HAKI Bridge System (HBS) HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made

More information

Modular Scaffolding MEKA 48

Modular Scaffolding MEKA 48 Modular Scaffolding MEKA 48 MODULAR SCAFFOLDING MEKA 48 MODULAR SCAFFOLDING The Modular Scaffolding MEKA 48 is designed to adapt to the most complex scaffold structures. Its versatility offers a wide range

More information

Modular Scaffold MEKA 48

Modular Scaffold MEKA 48 Modular Scaffold MEKA 48 Imperial units NA MODULAR SCAFFOLD MEKA 48 MODULAR SCAFFOLD The Modular Scaffold MEKA 48 is designed to adapt to the most complex scaffold structures. Its versatility offers a

More information

ASSEMBLY.

ASSEMBLY. ASSEMBLY www.proscaf.com ASSEMBLY SECTION Points to Consider These assembly instructions are generic and may not apply to all applications. If you have questions regarding specific applications contact

More information

scaffoldings/ coverings

scaffoldings/ coverings scaffoldings/ coverings 198 MDS 222 temporary covers Scaffoldings / Coverings 197 SCAFFOLDINGS / COVERINGS MDS MDS multidirectional scaffolding The MDS multidirectional scaffolding is the modern solution

More information

BRIO Modular scaffolding

BRIO Modular scaffolding BRIO Modular scaffolding // Versatile and multifunctional // Table of content Features Benefits Solutions Basic components 2 4 6 13 // Features BRIO Modular Scaffolding covers the different configurations

More information

modular scaffolding R+

modular scaffolding R+ modular scaffolding R+ 1. Stand 6. Transverse U-transom Stand is the main element of modular scaffolding. Made of 48.2x3.2 mm steel pipe. Every 0,5m on the whole stand length are installed steel plates

More information

Multidirectional_scaffolding MP

Multidirectional_scaffolding MP Multidirectional_scaffolding MP 162 Company Projects Products Scaffoldings and Coverings MP MULTIDIRECTIONAL SCAFFOLDING The MP multidirectional system is the modern solution that reflects in an industrialized

More information

K stage System Scaffold

K stage System Scaffold K stage System Scaffold Product Manual Coronet Group Suzhou Co.,Lt Email : Coronet@coronet scaffold.com TEL :+86 512 85557000 400 770 9995 FAX :+86 512 85557111 Addres:#1505 SIFC,SIP,SUZHOU,CHINA Coronet

More information

Uniscaff User Guide. Uniscaff. George Roberts Total Reliability of Supply. George Roberts Total Reliability of Supply

Uniscaff User Guide. Uniscaff.   George Roberts Total Reliability of Supply. George Roberts Total Reliability of Supply George Roberts Total Reliability of Supply User Guide George Roberts Total Reliability of Supply www.scaffoldingsales.co.uk Tubes Scaffold Staircases Beams Formwork Fencing K-Lok User Guide Contents Introduction

More information

Note. Floor beams can also be made from wooden beams put through the holes in the longitudinal beam and boards nailed to it.

Note. Floor beams can also be made from wooden beams put through the holes in the longitudinal beam and boards nailed to it. Assembly instructions for HAKI IV These assembly instructions are designed for the construction of sectional HAKI IV scaffolding approved in accordance with the technical standards TP 73-05-60/020/83.

More information

BRIO Modular scaffolding

BRIO Modular scaffolding BRIO Modular scaffolding // Versatile and multifunctional // Table of content Features Benefits Solutions Basic components 2 4 6 13 // Features BRIO Modular Scaffolding covers the different configurations

More information

ALBLItZ 70 S INSTRUCTION FOR ERECTION AND USE

ALBLItZ 70 S INSTRUCTION FOR ERECTION AND USE ALBLItZ 70 S INSTRUCTION FOR ERECTION AND USE Approval No. Z-8.1-864 Standard Version (as of ) C O N T E N T S 1. General...1 2. Erecting the scaffold...3 2.1 General requirements...3 2.2 Erecting the

More information

QUICK ALLY SCAFFOLD SPECIFICATIONS Standards: 1.0 m, 1.5 m, 2.0 m, 2.5 m, 3.0 m, 4.0 m. Ledgers: 0.5 m, 0.7 m, 1.2 m, 1.8 m, 2.4 m, 3.0 m. Polypropylene platforms: 0.7 m, 1.2 m, 1.8 m, 2.4 m, 3.0 m. Also

More information

Erection manual. Tube-Lock Concept. van Thiel United b.v Page: 1 of 15

Erection manual. Tube-Lock Concept. van Thiel United b.v Page: 1 of 15 Erection manual Tube-Lock Concept 2013-02 Page: 1 of 15 Contents Subject Page Illustration of Tube-Lock Concept 3 Parts of Tube-Lock concept 4 Legislation 5 Erecting a Tube-Lock Concept scaffold 6 Technical

More information

HAKI AB, Sibbhult, Sweden

HAKI AB, Sibbhult, Sweden HAKI AB, Sibbhult, Sweden www.haki.com The HAKI Group HAKI is a manufacturer of system scaffold and weather protection solutions. HAKI temporary work-places ensure the highest standard in safety whilst

More information

BoSS Clima USER GUIDE. Mobile Aluminium Tower with Climbing Frame 1450/850. 3T - Through the Trapdoor Method

BoSS Clima USER GUIDE. Mobile Aluminium Tower with Climbing Frame 1450/850. 3T - Through the Trapdoor Method BoSS Clima Mobile Aluminium Tower with Climbing Frame 1450/850 3T - Through the Trapdoor Method USER GUIDE Edition April 2009 Safety First Mobile Towers - 3T Method INTRODUCTION Please read this guide

More information

Sales Hire Erections

Sales Hire Erections LTD www.scafhire.ie Sales Hire Erections Scaffolding Specialists Company History Since its modest inception in 1980 Scafhire Ltd has progressed to a position of very high prominecnce and respectability

More information

distribution Modular Scaffolding

distribution Modular Scaffolding Modular Scaffolding Modular scaffolding PDM Universal scaffolding system plettac-pl PDM Application A characteristic feature of plettac PDM system is the use of wedge joint which provides quick and safe

More information

CLIMA AGR. Mobile Aluminium Tower with Climbing Frames 1450/850 Camlock Advanced Guardrail USER GUIDE

CLIMA AGR. Mobile Aluminium Tower with Climbing Frames 1450/850 Camlock Advanced Guardrail USER GUIDE CLIMA AGR Mobile Aluminium Tower with Climbing Frames 1450/850 Camlock Advanced Guardrail USER GUIDE Contents Safety First Safety Checklist Quantity Schedules Assembly and Dismantling Procedure Toe Boards

More information

MOBILE ACCESS TOWER INSTRUCTION MANUAL SHALLOW BRACE. Incorporating the 3T method of assembly

MOBILE ACCESS TOWER INSTRUCTION MANUAL SHALLOW BRACE. Incorporating the 3T method of assembly MOBILE ACCESS TOWER Incorporating the 3T method of assembly SHALLOW BRACE INSTRUCTION MANUAL 2 INTRODUCTION This instruction manual contains all the information required to correctly assemble the OCTO

More information

PERI UP Easy * The lightweight and fast frame scaffold for safe working on facades

PERI UP Easy * The lightweight and fast frame scaffold for safe working on facades PERI UP Easy * The lightweight and fast frame scaffold for safe working on facades Product Brochure * If approval is required for the scaffolding system PERI UP Easy to be placed on the market in a country,

More information

STABILO. System Parts Facade Scaffold. Vertical Frame (Steel) Vertical Frame (Aluminium) Vertical Frame. Vertical Frame (Aluminium) (Steel)

STABILO. System Parts Facade Scaffold. Vertical Frame (Steel) Vertical Frame (Aluminium) Vertical Frame. Vertical Frame (Aluminium) (Steel) STABILO STABILO ø 48.3 x 4.0 mm Weight kg 6,0 14,0 19,0 Art.-No. 700193 700186 700179 Vario Equipped with exchangeable stabilizer Weight kg 3,5 6,0 8,0 Art.-No. 700223 700216 700209 Vario ø 48.3 x 4.0

More information

USER S MANUAL 750. wit h HAKI Trak Sheet ing Roll-Out Met hod

USER S MANUAL 750. wit h HAKI Trak Sheet ing Roll-Out Met hod USER S MANUAL 750 wit h HAKI Trak Sheet ing Roll-Out Met hod HAKI AB 2015 Important information HAKI s product liability and user s manuals apply only to structures that are entirely composed of components

More information

Since it was established in 1989, with a small manufacturing base in Qwa Qwa, Uni-Span has grown to become one

Since it was established in 1989, with a small manufacturing base in Qwa Qwa, Uni-Span has grown to become one access scaffolding Since it was established in 1989, with a small manufacturing base in Qwa Qwa, Uni-Span has grown to become one of the major players in the scaffolding and formwork industry in South

More information

modular scaffolding R+

modular scaffolding R+ modular scaffolding R+ 1. Stand 6. Transverse U-transom Stand is the main element of modular scaffolding. Made of 48.2x3.2 mm steel pipe. Every 0,5m on the whole stand length are installed steel plates

More information

USER S GUIDE for HAKITEC 750. TEMPORARY ROOF with HAKI Trak Sheeting ( Hand-Built )

USER S GUIDE for HAKITEC 750. TEMPORARY ROOF with HAKI Trak Sheeting ( Hand-Built ) USER S GUIDE for HAKITEC 750 TEMPORARY ROOF with HAKI Trak Sheeting ( Hand-Built ) HAKI LTD 2007 INTRODUCTION Temporary roof structures are by their very nature amongst the most difficult and demanding

More information

Mobile Towers - 3T Method

Mobile Towers - 3T Method Safety First Safety First INTRODUCTION SAFE USE Mobile Towers - 3T Method Please read this guide carefully. Please note that diagrams are for illustrative purposes only. User guides are also available

More information

LADDERSPAN 3T USER GUIDE. Mobile Aluminium Tower 1450/850 Ladderspan. 3T - Through the Trapdoor Method

LADDERSPAN 3T USER GUIDE. Mobile Aluminium Tower 1450/850 Ladderspan. 3T - Through the Trapdoor Method LADDERSPAN 3T Mobile Aluminium Tower 1450/850 Ladderspan 3T - Through the Trapdoor Method USER GUIDE Safety First Mobile Towers - 3T Method INTRODUCTION Please read this user guide carefully. Please note

More information

ROOM-MATE. 3T - Through the Trapdoor USER GUIDE

ROOM-MATE. 3T - Through the Trapdoor USER GUIDE ROOM-MATE 3T - Through the Trapdoor USER GUIDE Safety First Introduction Please read this user guide carefully. Please note that diagrams are for illustrative purposes only. User guides are also available

More information

CLIMA 3T. Mobile Aluminium Tower with Climbing Frame 1450/850 3T - Through the Trapdoor Method USER GUIDE

CLIMA 3T. Mobile Aluminium Tower with Climbing Frame 1450/850 3T - Through the Trapdoor Method USER GUIDE CLIMA 3T Mobile Aluminium Tower with Climbing Frame 1450/850 3T - Through the Trapdoor Method USER GUIDE Safety First Mobile Towers - 3T Method INTRODUCTION Please read this Userguide carefully. Please

More information

user s guide for ( Hand-Built )

user s guide for ( Hand-Built ) user s guide for hakitec 750 MONOPITCHED TEMPORARY ROOF with HAKI Trak Sheeting ( Hand-Built ) HAKI LTD 2011 INTRODUCTION Temporary roof structures are by their very nature amongst the most difficult and

More information

Industrial Aluminium Towers

Industrial Aluminium Towers Industrial Aluminium Towers SINGLE WIDTH LADDERSPAN & VERTICAL LADDER ERECTION MANUAL TO BS-EN 1004-2004 Using 2 rung frames (Recommended) Using guardrail frames HORIZONTAL BRACE 1.8m (2040) 2.7m (2041)

More information

BoSS Room-Mate. 3T - Through the Trap Method

BoSS Room-Mate. 3T - Through the Trap Method BoSS Room-Mate 3T - Through the Trap Method User Guide Edition 2: 2010 Safety First Mobile Towers - 3T Method INTRODUCTION Please read this guide carefully. Please note that diagrams are for illustrative

More information

LADDERSPAN AGR. BoSS Camlock Advance Guardrail Mobile Aluminium Tower 1450/850 Frames USER GUIDE

LADDERSPAN AGR. BoSS Camlock Advance Guardrail Mobile Aluminium Tower 1450/850 Frames USER GUIDE LADDERSPAN AGR BoSS Camlock Advance Guardrail Mobile Aluminium Tower 1450/850 Frames USER GUIDE Contents Safety First Safety Checklist Quantity Schedules Assembly and Dismantling Procedure Toe Boards Stabilisers

More information

BoSS. Mobile Aluminium Tower 1450/850 Ladderspan. 3T - Through the Trapdoor Method

BoSS. Mobile Aluminium Tower 1450/850 Ladderspan. 3T - Through the Trapdoor Method BoSS Mobile Aluminium Tower 1450/850 Ladderspan 3T - Through the Trapdoor Method USER GUIDE Edition November 2011 Safety First Mobile Towers - 3T Method INTRODUCTION Please read this guide carefully. Please

More information

Safety First Mobile Towers - 3T Method INTRODUCTION

Safety First Mobile Towers - 3T Method INTRODUCTION Safety First Mobile Towers - 3T Method INTRODUCTION Safety First SAFE USE BoSS Mobile Aluminium Tower 1450/850 Ladderspan 3T - Through the Trapdoor Method Please read this guide carefully. Please note

More information

Contents 2017 VR ACCESS SOLUTIONS ALL RIGHTS RESERVED.

Contents 2017 VR ACCESS SOLUTIONS ALL RIGHTS RESERVED. Issue 1 February 2017 Contents Introduction... 1 NASC Compliance... 2 Safety Information... 3 Component Details... 4 Component Load Capacities... 7 Deck Arrangements... 9 Bracing and Tying... 11 Safe Working

More information

Industrial Aluminium Towers

Industrial Aluminium Towers Industrial Aluminium Towers SINGLE WIDTH LADDERSPAN & VERTICAL LADDER ERECTION MANUAL HORIZONTAL BRACE 1.8m (2040) 2.7m (2041) REVISED EDITION TOE BOARD 1.8m (2065) 2.7m (2067) LADDERSPAN TRAP PLATFORM

More information

COMPONENT SCHEDULE SINGLE WIDTH SPAN TOWERS WITH LADDER FRAMES TO BSEN RUNG STARTER FRAMES

COMPONENT SCHEDULE SINGLE WIDTH SPAN TOWERS WITH LADDER FRAMES TO BSEN RUNG STARTER FRAMES COMPONENT SCHEDULE SINGLE WIDTH SPAN TOWERS WITH LADDER S TO BSEN 1004-2004 STARTER S PLATFORM HEIGHT METRIC 2.4 2.9 3.4 3.9 4.4 4.9 5.4 5.9 6.4 6.9 7.4 7.9 DESCRIPTION IMPERIAL 7 10 9 6 11 2 12 10 14

More information

PERI PD 8 The cost-effective shoring for slab tables and high loads

PERI PD 8 The cost-effective shoring for slab tables and high loads PERI PD 8 The cost-effective shoring for slab tables and high loads Edition 06/2010 PERI GmbH Formwork Scaffolding Engineering P.O. Box 1264 89259 Weissenhorn Germany Tel +49 (0)7309.950-0 Fax +49 (0)7309.951-0

More information

There s no bad weather

There s no bad weather There s no bad weather HAKITEC protects your site against bad weather! Rain and snow. Cold and wind. There s no bad weather. HAKITEC protects your site and makes your work more profitable! Today, it is

More information

Industrial Aluminium Towers

Industrial Aluminium Towers Industrial Aluminium Towers SINGLE WIDTH LADDERSPAN & VERTICAL LADDER ASSEMBLY GUIDE TO BS-EN 1004-2004 Using 2 rung frames (Recommended) Using Guardrail frames HORIZONTAL BRACE 1.8m (2040) 2.7m (2041)

More information

Allround Scaffolding

Allround Scaffolding .. Allround Scaffolding I n g e n i o u s. S t r o n g. L i m i t l e s s. Faster. Stronger. Safer. More Profitable. Introduction Layher s Allround scaffolding makes an ideal propping system: being both

More information

CLIMA 3T. Mobile Aluminium Tower with Climbing Frame 1450/850 3T - Through the Trapdoor Method USER GUIDE

CLIMA 3T. Mobile Aluminium Tower with Climbing Frame 1450/850 3T - Through the Trapdoor Method USER GUIDE CLIMA 3T Mobile Aluminium Tower with Climbing Frame 1450/850 3T - Through the Trapdoor Method USER GUIDE Safety First Mobile Towers - 3T Method Introduction Please read this user guide carefully. Please

More information

This User Guide provides you with step by step instructions to ensure your system is erected easily and safely.

This User Guide provides you with step by step instructions to ensure your system is erected easily and safely. INTRODUCTION Please read this guide carefully. Please note that diagrams are for illustrative purposes only. Trade King 730 mobile aluminium towers are light-weight scaffold towers used throughout the

More information

Safety First Mobile Towers - 3T Method INTRODUCTION

Safety First Mobile Towers - 3T Method INTRODUCTION BoSS Room-Mate 3T - Through the Trap Method Safety First Mobile Towers - 3T Method INTRODUCTION Please read this guide carefully. Please note that diagrams are for illustrative purposes only. User guides

More information

2017 RING SYSTEM TECHNICAL MANUAL HIRE ONLY UNITED KINGDOM

2017 RING SYSTEM TECHNICAL MANUAL HIRE ONLY UNITED KINGDOM 2017 TECHNICAL MANUAL HIRE ONLY UNITED KINGDOM Table of Contents INTRODUCTION... 3 INTRODUCTION TO AT-PAC... 3 QUALITY FACTORS... 4 DESIGNATION OF... 4 COMPONENT SAFE WORKING LOAD CAPACITIES... 5 NODE

More information

Safety First Mobile Towers - 3T Method INTRODUCTION. Please read this guide carefully. Please note that diagrams are for illustrative purposes only.

Safety First Mobile Towers - 3T Method INTRODUCTION. Please read this guide carefully. Please note that diagrams are for illustrative purposes only. BoSS Mobile Aluminium Tower 0/80 Ladderspan T - Through the Trapdoor Method Safety First Mobile Towers - T Method INTRODUCTION Please read this guide carefully. Please note that diagrams are for illustrative

More information

SIDE CANTILEVER TOWER SCAFFOLD. 3T - Through the Trapdoor Method USER GUIDE

SIDE CANTILEVER TOWER SCAFFOLD. 3T - Through the Trapdoor Method USER GUIDE SIDE CANTILEVER TOWER SCAFFOLD 3T - Through the Trapdoor Method USER GUIDE Contents Safety First Component Diagram Component Quantity & Safety Data Schedule Build Method Pre-use Safety Inspection Checklist

More information

Instructions for erection and use of the RUX-SUPER 65 Rapid-Erection Scaffolding. - Standard Design - Rapid-Erection Scaffolding RUX-SUPER 65

Instructions for erection and use of the RUX-SUPER 65 Rapid-Erection Scaffolding. - Standard Design - Rapid-Erection Scaffolding RUX-SUPER 65 Rapid-Erection Scaffolding RUX-SUPER 65 Instructions for erection and use of the RUX-SUPER 65 Rapid-Erection Scaffolding - Standard Design - Status: January 2007 Attention! Any instructions for erection

More information

Generation Hop up brackets to be removed and boards moved to lift above.

Generation Hop up brackets to be removed and boards moved to lift above. Denotes Ladder for Access from 2nd Lift to Extenda Bracket Generation Hop up brackets to be installed to manufacturer's instructions. Installed at 1200mm c/c max & 1050mm down from top of wall section.

More information

PRODUCT MANUAL

PRODUCT MANUAL toronto 2800 Skymark Ave, Ste, 203 Mississauga, ON L4W 5A6 [T] 416 783 70 Edmonton 12900-148TH Street, Edmonton, AB T5L 2H8 [T] 780 747 1670 hamilton 1620 Claybar Road, Ancaster, ON L9G 3L4 [T] 905 692

More information

PROFESSIONAL ROLLING TOWER SYSTEMS

PROFESSIONAL ROLLING TOWER SYSTEMS Relax. It s an Altrex. ROLLING TOWER SYSTEMS Rolling tower Folding frame Relax. It s an Altrex. Working at height has several risks. Choosing Altrex is choosing safety, quality and durability. Altrex access

More information

COLD DEFORMATION: A STRONGER ALTERNATIVE

COLD DEFORMATION: A STRONGER ALTERNATIVE COLD DEFORMATION: A STRONGER ALTERNATIVE LOAD TEST: ALUFASE Vs WELDING Load (Tons) / Deformation (mm) 7 6 The cold deformation system has been proven to be 3 times stronger than the traditional welding

More information

Industrial Aluminium Towers

Industrial Aluminium Towers HORIZONTAL 1.8m (2040) 2.7m (2041) TOE BOARD 1.8m (2066) 2.7m (2068) Industrial Aluminium Towers DOUBLE WIDTH SPAN & VERTICAL ASSEMBLY GUIDE TO BS-EN 1004-2004 Using the 3T (Through the Trap ) Assembly

More information

Mobile Tower 3T Method (Through The Trapdoor) Please read this guide carefully. Please note that diagrams are for illustrative purposes only.

Mobile Tower 3T Method (Through The Trapdoor) Please read this guide carefully. Please note that diagrams are for illustrative purposes only. Mobile Tower 3T Method (Through The Trapdoor) INTRODUCTION Please read this guide carefully. Please note that diagrams are for illustrative purposes only. LOYAL mobile aluminium towers are light-weight

More information

3T - Through The Trapdoor Method

3T - Through The Trapdoor Method ALTO MEDIUM DUTY STAIRWELL TOWER Aluminium Access Tower ISSUE 3 Instruction Manual EN 1298-IM-EN The ALTO MD Stairwell Tower 3T - Through The Trapdoor Method Lakeside Industries Ltd www.altoaccess.com

More information

Universal Panels & Accessories

Universal Panels & Accessories Universal Panels & Accessories Erection Procedures INTRODUCTION Use common sense when working with Scaffold Your Safety is our #1 Concern Universal Scaffolds are designed with your safety in mind every

More information

PLETTAC METRIX COMPONENT CAPACITIES. Providing quality products and services at a competitive price.

PLETTAC METRIX COMPONENT CAPACITIES. Providing quality products and services at a competitive price. PLETTAC METRIX COMPONENT CAPACITIES Providing quality products and services at a competitive price. Valid Only For Genuine Equipment COMPONENT CAPACITIES COMPONENT CAPACITIES Loads given in this document

More information

AGR TOWER. Standard Features include. Tower Assembly Training Available

AGR TOWER. Standard Features include. Tower Assembly Training Available AGR TOWER The Euro Tamper Proof Advanced Guardrail is another solution to safe tower assembly. The ergonomic design lends itself to quick easy assembly and provides collective fall prevention before the

More information

BASIC SCAFFOLDING KNOWLEDGE QUESTIONS

BASIC SCAFFOLDING KNOWLEDGE QUESTIONS Garnsworthy Square 46, 62 & 64 Garnsworthy St Springvale rth Victoria 3171 Updated on 22/02/08 STC105 Name BASIC SCAFFOLDING KNOWLEDGE QUESTIONS THE PROFESSIONAL Scaffold Tools Scaffold Belts Couplers

More information

Allround Scaffolding. Propping Technical Brochure. The universal system for everyday and engineered scaffolding solutions

Allround Scaffolding. Propping Technical Brochure. The universal system for everyday and engineered scaffolding solutions Propping Technical Brochure The universal system for everyday and engineered scaffolding solutions made of galvanised steel or aluminium General construction approval Z-8.22-64 Quality management certified

More information

BoSS Climalite Camera and lighting tower

BoSS Climalite Camera and lighting tower Contents Safety First Safety First Quantity Schedules Toeboard 2 9 13 33 INTRODUCTION Please read this guide carefully. Please note that diagrams are for illustrative purposes only. User guides are also

More information

RINGLOCK Introduction Ringlock is world most widely used scaffold system. It is a fully galvanized multi purpose steel scaffold system suitable for pr

RINGLOCK Introduction Ringlock is world most widely used scaffold system. It is a fully galvanized multi purpose steel scaffold system suitable for pr RINGLOCK ACCESS SCAFFOLD SYSTEM 9 RINGLOCK Introduction Ringlock is world most widely used scaffold system. It is a fully galvanized multi purpose steel scaffold system suitable for providing general access

More information

MiniMax USER GUIDE. Mobile Aluminium Trade Quality Access Tower System. 3T - Through The Trapdoor Method

MiniMax USER GUIDE. Mobile Aluminium Trade Quality Access Tower System. 3T - Through The Trapdoor Method MiniMax Mobile Aluminium Trade Quality Access Tower System 3T - Through The Trapdoor Method USER GUIDE Contents Safety First Component Diagram Component Quantity & Safety Data Schedule Build Method Pre-use

More information

INSTRUCTIONmanual. BoSS COMPACT SIDE CANTILEVER TOWER SCAFFOLD 3T Method - Through the Trap Door

INSTRUCTIONmanual. BoSS COMPACT SIDE CANTILEVER TOWER SCAFFOLD 3T Method - Through the Trap Door INSTRUCTIONmanual BoSS COMPACT SIDE CANTILEVER TOWER SCAFFOLD 3T Method - Through the Trap Door Drawn: 26/02/2018 Issue: E Page: 2 OF 21 CONTENTS Safety First Component Diagram Component Quantities & Safety

More information

3T - Through The Trapdoor Method

3T - Through The Trapdoor Method ALTO HEAVY DUTY SINGLE WIDTH LADDERSPAN TOWER Mobile Aluminium Access Tower ISSUE 5 Instruction Manual EN 1298-IM-EN The ALTO HD Ladderspan Tower is certified to BS EN 1004:2004 3T - Through The Trapdoor

More information

Assembly and Usage Instructions Z 600 S-PLUS mobile scaffold tower with stabilisers Z 600 S-PLUS folding scaffold unit COMPACT

Assembly and Usage Instructions Z 600 S-PLUS mobile scaffold tower with stabilisers Z 600 S-PLUS folding scaffold unit COMPACT 09/2016 No. 291358 en Assembly and Usage Instructions Z 600 S-PLUS mobile scaffold tower with stabilisers Z 600 S-PLUS folding scaffold unit COMPACT 2 Contents en 1 General information... 4 1.1 Introduction...4

More information

RAPID Column Formwork For the highest requirements on concrete surfaces and edge formation. Product Brochure Issue 10/2017

RAPID Column Formwork For the highest requirements on concrete surfaces and edge formation. Product Brochure Issue 10/2017 For the highest requirements on concrete surfaces and edge formation Product Brochure Issue 10/2017 Content System advantages 5 For the highest requirements on concrete surfaces and edge formation 8 For

More information

Allround Scaffolding. Layher Allround Bridging System Instructions for Assembly and Use. Modular truss system for wide spans

Allround Scaffolding. Layher Allround Bridging System Instructions for Assembly and Use. Modular truss system for wide spans Layher Allround Bridging System Instructions for Assembly and Use Modular truss system for wide spans Certification according to DIN ISO 9001/EN 29 001 by TÜV-CERT Allround Scaffolding } CONTENT 1. Introduction...3

More information

Allround Scaffolding System

Allround Scaffolding System Quality management certified according to ISO 9001:2008 by German TÜV-CERT L i m i t l e s s. S t r o n g. 8116.221 I n g e n i o u s. Catalogue Edition 01.04.2012 Allround Scaffolding System Layher Allround

More information

TAKING YOU TO NEW HEIGHTS IN SAFETY...

TAKING YOU TO NEW HEIGHTS IN SAFETY... limited one bay cuplok Stair Unit user guide One Bay Stair Tower used in conjunction with Cuplok System Scaffolding and designed to conform to all current British and European Standards. With only five

More information

TRAD HIRE & SALES SCAFFOLDING SUPPLIER USER GUIDE PLETTAC METRIX FOCUSSED ON SERVICE

TRAD HIRE & SALES SCAFFOLDING SUPPLIER USER GUIDE PLETTAC METRIX FOCUSSED ON SERVICE TRAD HIRE & SALES SCAFFOLDING SUPPLIER PLETTAC USER GUIDE FOCUSSED ON SERVICE DISCLAIMER: Whilst TRAD Hire & Sales Ltd and the author have made every reasonable effort to ensure that the information contained

More information

BoSS SOLO 700. One Man Aluminium Tower EN /4 EN1298-IM-EN 3T - Through the Trap Door USER GUIDE

BoSS SOLO 700. One Man Aluminium Tower EN /4 EN1298-IM-EN 3T - Through the Trap Door USER GUIDE BoSS SOLO 700 One Man Aluminium Tower EN1004-3-4/4 EN1298-IM-EN 3T - Through the Trap Door USER GUIDE Edition August 2013 Contents Safety First 2 Component Diagram 7 Quantity Schedules 9 Stabalisers 10

More information

PROPERTY OF JUMBO STILLADS A/S

PROPERTY OF JUMBO STILLADS A/S PROPERTY OF PROPERTY OF PROPERTY OF PROPERTY OF CERTIFICATE EXAMINATION CERTIFICATE No. 35 37 02 Tower scaffolds Holder/Manufacturer/Supplier JUMBO Stillads A/S, Staalvej 9-23, DK-6000 Kolding, Denmark

More information

DEPAUL UNIVERSITY. Scaffolding Program. Environmental Health & Safety. April 2017

DEPAUL UNIVERSITY. Scaffolding Program. Environmental Health & Safety. April 2017 DEPAUL UNIVERSITY Scaffolding Program Environmental Health & Safety April 2017 1 TABLE OF CONTENTS SECTION PAGE NO. 1.0 PURPOSE 2 2.0 SCOPE 2 3.0 SCAFFOLDING ERECTOR 2 4.0 GENERAL 2 5.0 WOOD SCAFFOLDING

More information

PLETTAC METRIX USER GUIDE

PLETTAC METRIX USER GUIDE PLETTAC USER GUIDE Providing quality products and services at a competitive price. Valid Only For Genuine Equipment DISCLAIMER: Whilst TRAD Hire & Sales Ltd and the author have made every reasonable effort

More information

SpeedyScaf System. Layher SpeedyScaf System. Catalogue Edition Quality management certified according to ISO 9001:2008 by German TÜV-CERT

SpeedyScaf System. Layher SpeedyScaf System. Catalogue Edition Quality management certified according to ISO 9001:2008 by German TÜV-CERT C o m p l e t e. Quality management certified according to ISO 9001:2008 by German TÜV-CERT S a f e. 8102.253 Q u i c k. Catalogue Edition 01.04.2012 SpeedyScaf System Layher SpeedyScaf System u Contents

More information

Layher. Aluminium Rolling Towers. Layher SuperKlaxTower. Instructions for Assembly and Use

Layher. Aluminium Rolling Towers. Layher SuperKlaxTower. Instructions for Assembly and Use Mobile access and working towers in accordance with: HD 1004; DIN 4422, Part 1 (Version 8/92) Working platform 2.8 x 2.8 m and 2.8 x 1.95 m Max. working height: in closed rooms 13.95 m, outdoors 10.0 m

More information

TAKING YOU TO NEW HEIGHTS IN SAFETY... kwikstage

TAKING YOU TO NEW HEIGHTS IN SAFETY... kwikstage limited one bay kwikstage stair unit user guide One Bay Stair Tower used in conjunction with Kwikstage System Scaffolding and designed to conform to all current British and European Standards. With only

More information

Rosette Modular Scaffolding System

Rosette Modular Scaffolding System Rosette Modular Scaffolding System The rosette modular security scaffolding system to be used in facades, has been produced in accordance with the structural design conditions stated by the following applicable

More information

Span 300 Manual. DESIGNATION EN1004 CEN 1298 IM - en. CEN designation of this instruction manual EN 1298 IM en

Span 300 Manual. DESIGNATION EN1004 CEN 1298 IM - en. CEN designation of this instruction manual EN 1298 IM en Span 300 Manual DESIGNATION EN1004 CEN 1298 IM - en CEN designation of this instruction manual EN 1298 IM en WARNING NEVER STAND ON AN UNGUARDED PLATFORM SAFE WORKING LOADS AND WORKING HEIGHTS The safe

More information

Inspect components prior to erection. Inspect tower prior to use. Castors locked and legs correctly adjusted. Stabilisers fitted as specified

Inspect components prior to erection. Inspect tower prior to use. Castors locked and legs correctly adjusted. Stabilisers fitted as specified Introduction This Guide is designed to provide you with step bystep instructions to ensure that your system is erected with themaximum of ease and safety. Before assembly, please read thesafety notes.

More information

Construction Safety Education Forum. 6 March Scaffolding. Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT

Construction Safety Education Forum. 6 March Scaffolding. Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT Construction Safety Education Forum 6 March 2013 Scaffolding Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT SRWSD in confidence 1 Presentation Outline Introduction

More information

2017 AT-PAC RINGLOCK SAFETY MANUAL & USER GUIDES UNITED KINGDOM

2017 AT-PAC RINGLOCK SAFETY MANUAL & USER GUIDES UNITED KINGDOM 2017 AT-PAC RINGLOCK SAFETY MANUAL & USER GUIDES UNITED KINGDOM Table of Contents INTRODUCTION... 4 RINGLOCK QUALITY FACTORS... 5 DESIGNATION OF RINGLOCK... 5 SAFETY GUIDELINES AND SAFE USE... 6 NEVER...

More information

GENERAL SAFETY RULES DOUBLE WIDTH 232 (NARROW RUNG) 3T INSTRUCTION MANUAL DISMANTLING NOTES: The 232 Tower Approved to the requirements of BS EN 1004

GENERAL SAFETY RULES DOUBLE WIDTH 232 (NARROW RUNG) 3T INSTRUCTION MANUAL DISMANTLING NOTES: The 232 Tower Approved to the requirements of BS EN 1004 GENERAL SAFETY RULES DOUBLE WIDTH 232 (NARROW RUNG) 3T INSTRUCTION MANUAL The 232 Tower Approved to the requirements of BS EN 1004 MAX SAFE WORKING LOAD FOR STRUCTURE: 750KG MAX SAFE WORKING LOAD FOR PLATFORM: