Current Construction Projects in Progress. Thru January 31, 2016

Size: px
Start display at page:

Download "Current Construction Projects in Progress. Thru January 31, 2016"

Transcription

1 Current Construction Projects in Progress Thru January 31, 2016

2 Orange Ave Pump Station Improvements Before After Project consist of the removal of the existing pumps, housing and piping. Remove and replace wet well top. Repair the interior wall and resurface with spectra shield spray on liner. Construct new submersible pumps, piping and control panel. a. Project bid September 25, 2015 and awarded to Grimes Utilities, Inc. by Town Council on October 6, b. Project completion date January 21, 2016.

3 Milwaukee Ave Pump Station Improvements Existing Contract scope of work to include but not limited to the removal of existing suction lift pumps, housing and piping. Remove and replace wet well concrete top. Clean inside wet well walls and repair with a spectra shield spray on liner. Construct new submersible pumps and piping. Upgrade pump out connection and construct new control panel. Construct new electrical wiring. a. Project bid November 20, 2015 and awarded to Grimes Utilities, Inc. by Town Council on December 1, b. Project start January 29, c. Anticipated substantial completion date April 28, 2016.

4 Gabriel Dr and Chablis Ct W. Water Main and Roadway Improvements Roadway Reconstruction Work Order is for Professional Engineering Services in connection with the Towns efforts to upgrade the water utility and improve the drainage and roadway on Gabriel Drive and Chablis Court W. Project will replace approximately 3000 linear feet of existing asbestos cement water main with new 6-inch PVC water main, replace existing services with new services, replace existing fire hydrants, mill and resurface asphalt, remove and replace curb and gutter and driveways. Install groundwater control underdrain where determined by the geological soil report. a. Project Complete.

5 Floyd Circle Utility and Drainage Improvements Sanitary Sewer Roadway Reconstruction Work will consist of the construction of approximately 1,656 LF of 6 PVC water main with new services and fire hydrants; removal and replacement of approximately LF of 8 gravity sewer, sewer laterals and manholes. Reconstruct roadway with new curb and gutter, lime rock base, asphalt, sidewalk and driveway replacement. Installation of a new storm water system with pipe and structures and all other site work per design plans. a. Council approved contract on July 21, 2015 in the amount of $509, b. Pre-construction August 20, c. Water and sewer 85% complete. d. Roadway reconstruction 25% complete. e. Anticipated substantial completion date per contract February 28, 2016.

6 Plainfield Ave Utility and Roadway Improvements Storm and Utility Installation Work will consist of the re-construction of approximately 7200 LF of roadway; curb & gutter, partial sidewalk and driveways. Install new 16 PVC water main; valves, water services and fire hydrants from Wells Rd to Kingsley Ave. New 12 gravity sewer main, manholes and service laterals from Wells Rd to Ash St. Partial storm drain installation and replacement of existing from Wells Rd to Kingsley Ave. a. Council approved contract on August 4, 2015 to RB Baker Construction in the amount of $3,287, for Opt#1. b. Notice of Award issued August 14, c. Storm drainage and water main installation to begin November 30, d. Clearing and grubbing complete. e. Storm drainage and water main installation in progress from Wells Rd to Loring Ave. f. Anticipated completion date is October 2016.

7 OPAA Sidewalk and Bleacher Slab Improvements New bleacher slab and sidewalk Work will consist of installing new 5 ft sidewalk and bleacher slabs to accommodate the new bleacher units with framed canvas covers. a. Purchase order issued to Sauer Concrete and Tractor, Inc. on October 15, b. Work began on November 4, c. Concrete sidewalk and bleacher slabs complete. d. Bleacher covers to be installed by April 2016.

8 Carriage House Improvements at Clarke Park Before After Work will consist the demolition of the existing footer and reconstruct new concrete footer. Replace existing wall studs, wood siding (partial), barn doors and repaint. a. Project Complete. If you have any questions please contact Russell Grimes, Capital Projects Manager at or