Construction Update Report #3

Size: px
Start display at page:

Download "Construction Update Report #3"

Transcription

1 World Children s Fund Mama Kevina Comprehensive Secondary School Construction Update Report #3 UGANDA June, 2014 Real Medicine Foundation National Blvd, Suite 234 Los Angeles, CA (310)

2 New Construction Project funded by World Children s Fund: We were very excited to announce in mid-2013, that World Children s Fund agreed to fund the construction of four new buildings, which will substantially increase the capacity of the school to attract more paying students to help subsidize the non-paying students and move closer to becoming a sustainable school. The funds will go towards the construction of new girls and boys dormitory buildings, a dining hall, and finishing the ground floor of a new office/classroom block. Construction began in December This brings the partnership between WCF, RMF and Mama Kevina to a new level, and promises to make the school a model program for the area. Construction Project Works/ Scope: Completion of the Classroom block using part of existing building Construction of a new Dining Hall Construction of a new Dormitory block for Girls Construction of new Dormitory block for Boys Contractor MMK Engineering Limited, P.O. Box 508 Kampala- Uganda. Update as of June 11, 2014 Real Medicine Foundation hired a Building/Structural Engineer, Odongo Richard Sikola, as an Independent Consultant to monitor the progress and quality of the work completed by MMK Engineering. Each release of funds to the Construction company is contingent upon the approval of RMF s Engineering Consultant. Time extension Due to ongoing negotations with the school management/administration concerning project, RMF had halted payments temporarily until resolving the situation. Payments were begun again in late May and work has continued giving the Contractor a time extension of 45 calendar days. Meanwhile the Contractor has been instructed to submit to the client a revised work program Status of the Contract Time: Progress Equipment and Tools. Date of Contract Signing 17 th October 2013 Date of site possession 27 th December 2013 Original Contract Duration Four Months (16 weeks) Revised Contract Duration Five and half months (22 weeks) Commencement date 02 nd January 2014 Original Completion Date 03 rd May 2014 Revised Completion date 17 th July 2014 Defect Liability period Six weeks Projected Date of Hand over 17 th August 2014 The following equipment/ tools have been mobilized by the contractor to site for the works execution 2

3 S/no Item Description Quantity Remarks 1 Tipper trucks Concrete Mixer.75m Concrete Vibration Water pump Jumping Compactor Hand Tools Assorted Personnel The following personnel have been mobilized to site. S/no Title No Remarks 1 Project Director 01 Owor Mike A 2 Site Manager 01 Magara Bernard 3 Site Engineer 01 Oporu Paul P. 4 Site Foremen 04 Owor Jacob 5 Masons 35 Recho Nadundu 6 Carpenters 07 Ochieng Chrisopher 7 Steel benders 05 8 Unskilled 65 Material mobilization S/No Description Unit Quantity Last month This month Total 1 Concrete blocks No 2, Clay Bricks No 87,500 43, ,800 3

4 3 Coarse Sand trips Aggregates Tons Hard core Trips Eucalyptus poles 1,505 1,505 7 Timber (100*50) (150*50) (230*25) (300*25) (75*25) Pce Cement Bags 2, ,989 9 Steel Y16 Y12 R10 R 8/ Max pan No 2,370 2, Pre-painted sheets 7.7m length 5.5m length Ridges Valley gutters Construction Completion Percentages as of June 11 th, 2014: S/NO Description Physical Progress Achievement % Class room block Roof Slab level 75% 4

5 3.4.2 Multipurpose Dining hall A waits approval of change in roof design 70% Dormitory for boys Partially under use 98% Dormitory for Girls Already under use 100% Current Engineering/Construction Activities per building: Completion of an existing ground floor of the classroom block Construction of Multipurpose dining hall. Construction of dormitory block for Girls. Construction of walls using approved Concrete block of specified compressive strength. Construction of Reinforced concrete beam and columns Solid Reinforced Concrete slab on the balcony/ walkway Concrete slab laid on Maxpan Installation of doors and windows at all openings Internal finishes and decorations External rendering and paintings to match existing structures Electrical installation and internal wiring Construction of stairway case Construction of the Splash apron all round including drainage channels. Setting out and excavations Concrete works and walling using approved clay fired bricks Steel fixing and shuttering Construction of timber roof truss Covering using pre painted gauge 26 iron sheets green colour Closing all openings with half solid doors and double opening glass windows Internal and external finishing including decorations Construction of splash apron and drainage channels Electrical installation and wiring Setting out and excavations Concrete works and walling using approved clay fired bricks Steel fixing and shuttering Construction of timber roof truss Covering using pre painted gauge 26 iron sheets green colour Closing all openings with half solid doors and double opening glass windows Internal and external finishing including decorations Construction of splash apron and drainage channels Electrical installation and wiring (Works 100% completed) 5

6 Construction of dormitory block for boys. Setting out and excavations Concrete works and walling using approved clay fired bricks Steel fixing and shuttering Construction of timber roof truss Covering using pre painted gauge 26 iron sheets green colour Closing all openings with half solid doors and double opening glass windows Internal and external finishing including decorations Construction of splash apron and drainage channels Electrical installation and wiring (Works 98% Completed) Quality Control All materials used on site for permanent works comply with the contract specification per the Independent Engineer Consultant hired by RMF. Construction Challenges encountered and addressed: Description Action Taken Classroom block The plinth walls, columns and some sections of the slab had developed major cracks a sign of structural failures Multipurpose Dining Hall Contractor instructed to demolish all failed sections and make good. A new ground beam was introduces where the plinth wall had shown structural failures According to the Site plan the structures crosses over the football pitch and walkway to the boys dormitory Design change of Roof structure from timber to steel is under consideration by the Client Relocated in an orientation line with the existing laboratory block The span of the Building is large and it would require double truss to support the roof. In turn this would over load the structure thus the Change to a light weight material The Contractor is under instruction to proceed with the original roof plan of timber truss. Boys Dormitory Formally L Shaped Gable roof type Ground level matching with Shape changed to straight Single hip and double gable to match High headroom and above the existing structure 6

7 existing block. No provision for future upgrading Girls Dormitory Reinforced beam and column introduced in preparation for future development into stored structures. Gable roof type Ground level matching with existing block. No provision for future upgrading Single hip and double gable to match High headroom and above the existing structure Reinforced beam and column introduced in preparation for future development into stored structures. June Project Photos: Classroom block under constructions Girls dorm under construction Boy s dorm completed 7

8 Quality Control sifting of concrete aggregate Multipurpose Dining hall Ready for roofing Front view of classroom block building under construction 8