HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

Size: px
Start display at page:

Download "HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District"

Transcription

1 HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update

2 PROGRESS UPDATE Rien Construction (General Contractor) Placed rebar, anchor bolts and concrete for footings and piers for areas A and D Graded, placed the stone base, vapor barrier and wire mesh for the slab on grade in area C and in the gym Placed subgrade insulation around perimeter walls at the connector and backfilled with stone Excavated and placed concrete footings and the elevator pit slab and sump pit Set door frames on the first and second floor of area B and at the gym and locker rooms Grouted under steel columns in area C Started demolition of the cafeteria vestibule and stone panels on the south side of the existing building Etzel Masonry (Masonry Subcontractor) Laid CMU backup for the mechanical room Continued laying split face block on areas B & C, the gym locker rooms, the mechanical room and the gym Sprayed air barrier on the block walls around the gym and area B Laid brick veneer on the gym and at the stairwells for areas B and C Laid CMU walls for the locker rooms, gym chases and elevator shaft Ferguson-Steel (Steel Erection Subcontractor) Installed columns, beams and roof joists for the first floor of area C Installed joists, bracing and acoustical decking for the gym Started installing beams and decking for the gym locker rooms and the rest of area D Emerick Masonry (Concrete Subcontractor) Placed and finished the concrete slab on grade for area C and the gym Grafton Construction (Interiors Subcontractor) Installed wall framing for the first and second floors of area B and started installing exterior wall framing for area C Installed sheathing, insulation and plywood for the exterior walls on area B and started installing sheathing on area C Installed wood blocking around the window openings on area B SRI Roofing (Roofing Subcontractor) Installed substrate boards, insulation, cover boards and EPDM roofing on area B, the gym and area C Boak & Sons (Spray Foam Insulation Subcontractor) Started spraying foam insulation for the exterior walls on the first floor of area B Merit Electrical Group (Electrical Contractor) Installed conduit, MC cable and boxes in the basement of area C and the first and second floors of area B Installed underground conduits in the mechanical room, gym and area C Worked with the masons to install conduit and junction boxes in masonry walls Installed temporary lighting on the first and second floors of area B and in the gym Vrabel Plumbing (Plumbing Contractor) Installed carriers, waste and vent piping for areas B and C and the gym locker rooms Installed domestic water lines for areas B and C Installed roof drains and rain water conductor piping for areas B and C Excavated and installed underground sanitary piping for the restrooms on the north side of the gym

3 Lugaila Mechanical (HVAC Contractor) Mobilized office trailer, storage trailers and stocked materials Installed hangers and hot water supply and return piping for terminal boxes in area B. Assisted Hranec with placing and leveling curbs for roof top units Hranec Sheet Metal (Sheet Metal Subcontractor) Continued hanging ductwork on the first and second floors of area B Installed curbs for roof top equipment on areas B and C and the gym Installed return air ductwork for the gym Contractor Rien Construction Co. Lugaila Mechanical PAYMENT APPLICATION SUMMARY Vrabel Plumbing Co. Merit Electrical Group William T. Spaeder Co. Commercial Appliance Contracts Northeast Interior Systems Canfield Development WorkSpace Solutions Construction Contract General Construction HVAC Construction Plumbing Construction Electrical Construction Fire Protection Construction Food Service Construction Architectural Casework Construction Asbestos Abatement Construction Maker Space Equipment All Contracts Total Billed $4,236, $341, $1,064, $509, $0.00 $241, $8, $14, $0.00 $6,416, Original Contract Sum $17,374, $3,752, $2,681, $4,555, $315, $459, $1,261, $247, $117, $30,766, Change Order 1 $0.00 $ Change Order Total $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $ $0.00 $ Contract Sum to Date $17,374, $3,752, $2,681, $4,555, $315, $459, $1,261, $248, $117, $30,766, Balance to Finish $13,138, $3,411, $1,617, $4,045, $315, $218, $1,253, $234, $117, $24,349, Percent Complete 24.38% 9.10% 39.70% 11.18% 0.00% 52.56% 0.68% 5.81% 0.00% 20.86% May-18 $344, $29, $12, $387, Jun-18 $177, $76, $186, $109, $1, $552, Jul-18 $417, $232, $112, $4, $767, Aug-18 $784, $57, $151, $134, $213, $1,340, Sep-18 $589, $86, $93, $54, $12, $836, Oct-18 $1,922, $121, $369, $98, $11, $8, $2,533,003.41

4 PROGRESS PHOTOS: Concrete slab on grade for the gym locker rooms Steel and joist erection for area C

5 Underground electric installation under the main office area Mechanical equipment curbs on area B

6 Roof drain installation on area B Roofing installation on area B

7 Area D storage room concrete slab on grade Area C concrete slab on grade in the stairwells

8 Underground plumbing and the stone base was placed in area C Exterior wall studs started in area B

9 Block was placed for the elevator pit/shaft Vapor barrier and wire mesh were placed for the area C slab on grade

10 Roof joists and bracing were installed for the gym CMU was laid for the gym locker rooms

11 Plumbing carriers, waste and vent piping were installed in area B Underground sanitary piping was installed for the restrooms outside the gym

12 Ductwork installation continued in area B The concrete slab on grade was placed and finished for area C

13 Exterior wall framing and roofing started for area C Stone base was placed for the gym floor

14 Air barrier was applied to the gym walls and the brick fascia was laid Sheathing, insulation and plywood were installed on the exterior walls for area B

15 Split face block and brick was laid for the exterior gym walls Concrete slab on grade was placed and finished for the gym

16 Steel erection continued for area D CMU backup and split face block were laid for the mechanical room

17 Demo of the stone panels and vestibules on the south side of the existing building Roofing being installed on area C

18 View of area C Plumbing rough-ins in the gym locker rooms

19 Gym locker room showers Area C plumbing toilet room rough-ins

20 Area C stair structure installed Area B first floor progress

21 Spray foam insulation on the exterior walls in area B 1 st floor Area B second floor progress

22 Area C progress CMU installation for the elevator shaft

23 The connector for areas B and C Plywood and weather barrier installation on area B

24 The west side of area C The west side of area B

25 North and west sides of area B South side of area C and the west side of the gym and locker rooms

26

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek

Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015 Arbor Heights Elementary School

More information

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

Update on FCPS Construction/Renovation Projects. November 2015

Update on FCPS Construction/Renovation Projects. November 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

Schedule of Values Cruise Terminal 2 Expansion

Schedule of Values Cruise Terminal 2 Expansion Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Update on FCPS Construction/Renovation Projects. December 2015

Update on FCPS Construction/Renovation Projects. December 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Project Manual Index of Specifications Shenandoah Schools Concession Building

Project Manual Index of Specifications Shenandoah Schools Concession Building INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions

More information

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST Village of Vernon Hills Community Development Department - Building Division 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http://www.vernonhills.org INSPECTION TIMING

More information

City of Rohnert Park Building Department Inspection Descriptions

City of Rohnert Park Building Department Inspection Descriptions 200 SITE REVIEW: Prior to a permit being issued the Fire / Building Department is authorized to examine existing buildings, structures, and site for which an application has been filed. 201 PRECONSTRUCTION

More information

TABLE OF CONTENTS Public Safety Building

TABLE OF CONTENTS Public Safety Building DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary

More information

Update on FCPS Construction/Renovation Projects. July 2016

Update on FCPS Construction/Renovation Projects. July 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School

More information

Technical Assignment 2

Technical Assignment 2 Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive

More information

FIELD COPY ATTACHMENT

FIELD COPY ATTACHMENT FIELD COPY ATTACHMENT The released plans for the project must be on site and available to the inspectors at all times. No inspection will be done without the released field plans. If you have any questions,

More information

APPLICATION AND CERTIFICATE FOR PAYMENT

APPLICATION AND CERTIFICATE FOR PAYMENT AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in

More information

ADDENDUM 2 - JULY 14, 2015

ADDENDUM 2 - JULY 14, 2015 7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Update on FCPS Construction/Renovation Projects. September 2015

Update on FCPS Construction/Renovation Projects. September 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION Section 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Invitation

More information

INSPECTION REQUIREMENTS Page 1 of 5. JOB SITE ADDRESS posted during entire construction process.

INSPECTION REQUIREMENTS Page 1 of 5. JOB SITE ADDRESS posted during entire construction process. INSPECTION REQUIREMENTS Page 1 of 5 JOB SITE ADDRESS posted during entire construction process. JOB PLACARD POSTED IN PLAIN SIGHT: GREEN Placard - Building, ORANGE Placard Electrical, BLUE Placard - HVAC,

More information

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule Christopher Glinski Construction Management AE Senior Thesis Appendix B Project Summary /Detailed Schedule 74 Task Name ation 1 Project 546 days Mon 5/3/04 Mon 6/26/06 29 Design 243 days Mon 5/3/04 Fri

More information

Dr. David R. Riley October 30, 2006 TABLE OF CONTENTS. Executive Summary.1. Detailed Project Schedule Site Layout Planning 4

Dr. David R. Riley October 30, 2006 TABLE OF CONTENTS. Executive Summary.1. Detailed Project Schedule Site Layout Planning 4 Dr. David R. Riley October 30, 2006 TABLE OF CONTENTS Executive Summary.1 Detailed Project Schedule..2 3 Site Layout Planning 4 Assemblies Estimate 5 Detailed Structural Estimate..6 7 General Conditions

More information

Two complete sets of plans that are legible and drawn to conventional scale are required to be submitted with the Building Permit Application Form.

Two complete sets of plans that are legible and drawn to conventional scale are required to be submitted with the Building Permit Application Form. The Homeowner s Building Application Checklist for Constructing a Residential Accessory Building This checklist provides homeowners a summary of the Building Permit submission requirements for constructing

More information

Update on FCPS Construction/Renovation Projects. August 2015

Update on FCPS Construction/Renovation Projects. August 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 18810» Total Man Hours on Project 395795» Crafts On Project This Week: 22» OSHA Recordable Rate: 0 July 31, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND CONDOMINIUMS

THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND CONDOMINIUMS THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE II RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING

More information

Capital Projects Progress Report. January Presented by

Capital Projects Progress Report. January Presented by Capital Projects Progress Report January 2019 Presented by February 8, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York 14428

More information

Division 00 Procurement and Contracting Requirements

Division 00 Procurement and Contracting Requirements SECTION 00 01 10 TABLE OF CONTENTS Division SECTION NO. VOLUME ONE Title SECTION TITLE Division 00 Procurement and Contracting Requirements 00 11 00 Invitation to Bidders 00 21 00 Instructions to Bidders

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report September 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2) Inspection of Fabricators (1704.2) Furnish inspection reports (1704.2.1) - Fabricators that have not been approved Provide a Certificate of Compliance (1704.2.2) - Approved Fabricators Steel Construction

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 13462» Total Man Hours on Project: 268272» Crafts On Project This Week: 17» OSHA Recordable Rate: 0 June 5, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...

More information

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested. Purpose 355 West Queens Road Single Family New Construction Required Inspection Stages Master Requirement GEN 110 Building Department: 604-990-2480, building@dnv.org, fax: 604-984-9683 The following procedure

More information

4.1.3 Project Manual

4.1.3 Project Manual 4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01

More information

The Homeowner s Building Application Checklist for Constructing a Residential Addition

The Homeowner s Building Application Checklist for Constructing a Residential Addition The Homeowner s Building Application Checklist for Constructing a Residential Addition This checklist provides homeowners a summary of the Building Permit submission requirements for constructing a residential

More information

The better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs

The better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs November 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements....................................

More information

The Inspection Process. Waxhaw N.C.

The Inspection Process. Waxhaw N.C. The Inspection Process In Waxhaw N.C. This information is provided by the Waxhaw Enforcement Division to assist you in the progression of your project. Nothing in this document should be considered "Code"

More information

Nassau County Building Department

Nassau County Building Department July 6, 2018 Nassau County Building Department Inspection Types ALL INSPECTION REQUESTS ARE REQUIRED TO BE INITIATED BY THE PERMIT HOLDER, ALL INSPECTION REQUESTS SHALL SUPPLY THE PERMIT NUMBER FOR EACH

More information

NAAHB Workgroup Index General Ledger Account

NAAHB Workgroup Index General Ledger Account NAAHB Workgroup Index General Ledger Account 1000 Series Preparation/Preliminaries 1000 Permits/Fees 1010 Building Permits 1020 HBA Assessments 1030 Warranty Fees 1100 Architectural/Engineering 1110 Blue

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6 PROJECT MANUAL for: FRANKLIN VILLAGE APARTMENTS Building I Morristown, NJ 07960 Block: 3901 Lots: 4,5,6 Owner: Atlantic Health Investment Corp. 200 American Road Morris Plains, NJ 07950 Architect NETTA

More information

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB CONSTRUCTION COST BREAKDOWN Property Owner s Name or Borrowers Name Brief Description of Project John Homeowner Build single family residence Property Address Property City Property Zip Code 4625 Jillbarr

More information

City Of Mendota Construction Procedures

City Of Mendota Construction Procedures City Of Mendota Construction Procedures Building Permit Application: A permit shall be obtained prior to commencing work of any type. Failure to do so may result in doubling the permit fees. At the time

More information

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS Watercrest - Sand Hill - Columbia, SC 00 0110-1 TABLE OF CONTENTS DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS INTRODUCTORY INFORMATION Document 00 0101 Document 00 0110 Project Title Page CONTRACTING

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

City of Westerville Guide to Commercial Inspections

City of Westerville Guide to Commercial Inspections City of Westerville Guide to Commercial Inspections FOOTINGS - After the excavation, with the form work and any required reinforcing steel in place. All footings shall have loose soil removed, reinforcing

More information

Section 4 - Design and Construction Overview

Section 4 - Design and Construction Overview Section 4 - Design and Construction Overview 4-1 Building Architecture/Enclosure The Pearland Recreation Center and Natatorium houses a recreation center and natatorium as shown in Figures 4-1.1 First

More information

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders

More information

BuildingAdvisor.com Estimating Checklist

BuildingAdvisor.com Estimating Checklist BuildingAdvisor.com Estimating Checklist GENERAL REQUIREMENTS Plans and specifications Plan review Permits: Zoning, building, environmental, other Survey Impact fee Administrative costs Financing costs

More information

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16 New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16 Date: March 1, 2010 From: Gary Claar Engineering Services 355-1660 Gary.Claar@NationwideChildrens.org More and more

More information

Module number 3 provides an on-line, self-paced training seminar on chapter 4, foundations and chapter 5, floors from the residential code of ohio.

Module number 3 provides an on-line, self-paced training seminar on chapter 4, foundations and chapter 5, floors from the residential code of ohio. Module number 3 provides an on-line, self-paced training seminar on chapter 4, foundations and chapter 5, floors from the residential code of ohio. 1 This chapter sets forth the prescriptive requirements

More information

STATEMENT OF SPECIAL INSPECTION FORM

STATEMENT OF SPECIAL INSPECTION FORM Project Title: Permit #: Project Address: STATEMENT OF SPECIAL INSPECTION FORM This Statement of Special Inspections is submitted in fulfillment of the requirements of CBC Sections 1704 and 1705. Special

More information

Building Systems and Design Elements included in SliDeRulE

Building Systems and Design Elements included in SliDeRulE Building Systems and Design Elements included in SliDeRulE No. System Subsystem Design Element 1.1.1 Foundation Deep Foundation Steel H-pile 1.1.2 Foundation Deep Foundation Steel pipe pile 1.1.3 Foundation

More information

BUILDING PERMIT APPLICATION CITY OF SIDNEY BUILDING INSPECTION DEPARTMENT

BUILDING PERMIT APPLICATION CITY OF SIDNEY BUILDING INSPECTION DEPARTMENT BUILDING PERMIT APPLICATION CITY OF SIDNEY BUILDING INSPECTION DEPARTMENT APPLICATION REQUESTED (check all that apply) Is this currently a: Permit # Addition-square footage Single Family Detached Permit

More information

KU West Campus LEEP II High Bay Facility Project # , A (c)

KU West Campus LEEP II High Bay Facility Project # , A (c) Number Revision Title Rev Date Discipline Bulletin Drawings B-West Structural Category S051 0 General Notes - Sheet 1 7/31/13 Structural Bid Package B- West Campus S052 0 General Notes - Sheet 2 7/31/13

More information

Safety Update Crossing study is in final review stages. Facilities Update Construction Progress

Safety Update Crossing study is in final review stages. Facilities Update Construction Progress Major Projects Update September 2017 Prepared by Business and Operations September 11, 2017 Transportation Update As of 9/6/17 we have 4,803 students registered for busing, up 643 from last month s update.

More information

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017 Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.

More information

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary

More information

MITTERSILL WARMING HUT

MITTERSILL WARMING HUT STATE OF NEW HAMPSHIRE DEPARTMENT OF RESOURCES AND ECONOMIC DEVELOPMENT DIVISION OF PARKS AND RECREATION PROJECT #: CAP 1786 FRANCONIA NOTCH STATE PARK FRANCONIA, NEW HAMPSHIRE DRAWING LIST: COVER SHEET

More information

Project Estimate Summary

Project Estimate Summary Project Estimate Summary Project Cost Evaluation Table 4 shows the Construction Cost, CC/SF, Total Cost, TC/SF, the Building Systems Cost, and Building Systems Cost/SF based on the budget for. Table 4

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior

More information

Cost and Methods Analysis

Cost and Methods Analysis Technical Assignment 2 Cost and Methods Analysis Cathy Neiderer Pasadena Elementary School Technical Assignment 2 Table of Contents Executive Summary... 3 Detailed Project Schedule... 4 Site Layout Planning...

More information

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION

More information

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 25 26 27 28 29 30 3 32 33 34 35 36 37 38 39 40 4 42 43 44 45 46 DIVISION 02 EXISTING CONDITIONS Demolition; Removal & Disposal: CMU Partitions AD Quan UM

More information

PAULDING COLLEGE & CAREER ACADEMY

PAULDING COLLEGE & CAREER ACADEMY PAULDING COLLEGE & CAREER ACADEMY 000110 OF THE PROJECT MANUAL FOR THE CONSTRUCTION OF: PAULDING COLLEGE & CAREER ACADEMY DALLAS, GEORGIA DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000101 TITLE

More information

Office of Design & Construction State University Plaza Albany, New York

Office of Design & Construction State University Plaza Albany, New York Instructions: Consultant should meet with the Campus and Fund at the work area(s) prior to completing this Checklist. At least two (2) meetings are required, one prior to Schematic Phase submission and

More information

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco

More information

1 AND 2 FAMILY DWELLING REQUIREMENTS

1 AND 2 FAMILY DWELLING REQUIREMENTS PLAN REQUIREMENTS: 1 AND 2 FAMILY DWELLING REQUIREMENTS All residential plans including additions and attached garages shall be designed to the current edition of the International Residential Code. Plans

More information

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Project Status September Report 15, 2009 #13 April 27, 2012 TABLE OF CONTENTS SECTION 1: PROJECT SUMMARY SECTION 2: OVERALL PROJECT SCHEUDLE

More information

STATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION SKI PATROL HUT PROJECT #: CAP 1804

STATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION SKI PATROL HUT PROJECT #: CAP 1804 STATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION PROJECT #: CAP 1804 FRANCONIA NOTCH STATE PARK FRANCONIA, NEW HAMPSHIRE BID SET 8/4/2017 DRAWING LIST:

More information

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After Contents 1 Program Outline Gymnasium Restrooms Storage rooms IDF 2 Finish Outline Walls Flooring Ceiling Roof 3 MEP Outline Plumbing Mechanical Electrical 4 Communication and Security Guideline Communication

More information

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Franklin County Septic & Zoning permit application: A septic and zoning permit is required for residential or commercial

More information

CITY OF OAK CREEK SINGLE FAMILY & TWO-FAMILY CONSTRUCTION/PERMIT REQUIREMENTS

CITY OF OAK CREEK SINGLE FAMILY & TWO-FAMILY CONSTRUCTION/PERMIT REQUIREMENTS CITY OF OAK CREEK SINGLE FAMILY & TWO-FAMILY CONSTRUCTION/PERMIT REQUIREMENTS Update April 29, 2013 12 Permit application forms and contact information can be found on our website under Inspection Department

More information

Fleet Elementary School

Fleet Elementary School Fleet Elementary School Community Newsletter (January 2019) This is the January update on the status and progress of construction for the project. All monthly updates will also be posted to the project

More information

WORK AND PROJECT REQUIREMENTS

WORK AND PROJECT REQUIREMENTS WORK AND PROJECT REQUIREMENTS BID PACKAGE 3A SITE CONCRETE & CONCRETE TURNKEY CRABAPPLE MIDDLE SCHOOL REPLACEMENT April 26, 2018 EXHIBIT B CONSTRUCTION DOCUMENTS AND SPECIFICATIONS shall be acknowledged

More information

Residential Construction Minimum Required Inspections

Residential Construction Minimum Required Inspections Residential Construction Minimum Required Inspections The permit which you have been issued gives authority for work to commence. The stamped, approved plans, returned with this permit, shall be retained

More information

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD MARCH 2018 2016 BOND & TIF PROJECT UPDATE Grapevine-Colleyville ISD GHS Agricultural Sciences Building Renovation Multipurpose Activity Centers Additions and Renovations to TES and GMS Cannon Elementary

More information

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements % 8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior

More information

Building Architecture

Building Architecture The front of the building consists of the three story town homes with facades to remain, as well as one leg of the condominium tower that reaches the street. The main condo portion of the building is L

More information

CSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

CSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 01 Project Title Page 00 01 10 Table of Contents 00 01 15 List of Drawing Sheets 00 21

More information

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS AIA General Conditions... GC-1 to GC-44 Amendments to General Conditions... AM-1 to AM-2 Supplements to General Conditions... SU-1 to SU-7 00200 Instructions To Bidders... 1 3 00201 Contractor s Bidding

More information

ACCESSORY BUILDING. Building Permit Requirements: (must be completed before submitting application)

ACCESSORY BUILDING. Building Permit Requirements: (must be completed before submitting application) ACCESSORY BUILDING Before your application can be deemed complete and ready for processing you will need the following: (Please hand in entire application package including this cover sheet) Zoning- check

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Executive Summary:, located in Pigeon Forge, Tennessee, is designed as a multifunctional space and

More information

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 9086» Total Man Hours on Project: 188636» Crafts On Project This Week: 13» OSHA Recordable Rate: 0 April 24, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES» Continued

More information

GENERAL BUILDING CODE AND ZONING REQUIREMENTS: Post and spread footings shall be designed and constructed below the minimum frost depth of 42 inches

GENERAL BUILDING CODE AND ZONING REQUIREMENTS: Post and spread footings shall be designed and constructed below the minimum frost depth of 42 inches GENERAL BUILDING CODE AND ZONING REQUIREMENTS: Post and spread footings shall be designed and constructed below the minimum frost depth of 42 inches and shall be sized to carry the applicable roof and

More information

Boyden Library Board of Trustees Minutes of Monthly Meeting Monday, August 20, 2012

Boyden Library Board of Trustees Minutes of Monthly Meeting Monday, August 20, 2012 Boyden Library Board of Trustees Minutes of Monthly Meeting Monday, August 20, 2012 6:36 pm Welcome and call to order: Jeff Lovely. Attendees: Trustees Jeff Lovely, Janet Pineault, Fran Spillane, Kevin

More information

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Project Status September Report 15, 2009 #15 June 27, 2012 TABLE OF CONTENTS SECTION 1: PROJECT SUMMARY SECTION 2: OVERALL PROJECT SCHEUDLE

More information