1 Facility Condition Assessment Report Coast Community College District February 28, 2003

2 INTRODUCTION...2 Table of Contents ASSESSMENT OF EXISTING FACILITIES...4 Background Facilities Summary of Findings CSI Classifications Facility FCI CAPITAL RENEWAL...12 Funding Requirements 10 Year Renewal Projection 20 Year Capital Renewal Forecast CONCLUSIONS...13 COMET ASSESSMENT...14 Level 2 Facilities Assessment Methodology FILTERS...15 Priorities Categories Adverse Effects DEFINITIONS...16 REPORTS...20 Executive Summaries Summary Detail

3 Introduction To help document the need for funding the necessary replacement and upgrading of facilities within California s community college districts and to assist districts in preparing for bond issues, the Foundation for California Community Colleges (FCCC) negotiated a discounted-pricing agreement for facilities condition assessments with. In summer 2001, the FCCC issued a formal Request For Information (RFI) in a public newspaper and subsequently reviewed, considered, and evaluated the respondents experience and quality of work, particularly work with higher education clients. Coast Community College District (CCCD) elected to participate in the joint agreement and contracted with 3D/I to assess and document the facility repair, rehabilitation, modernization requirements relative to the CCCD. Over a period of about two months, a staff of six planning and construction professionals working with the Chancellor s Office performed an Existing Facility Assessment. The following report presents s findings. Orange Coast College Campus Map The Report is organized into the following 4 sections: Introduction Assessment of Existing Facilities Orange Coast College Reports Golden West College Reports Coastline Community College Reports The Assessment of Existing Facilities section reports on the current physical condition of one hundred eleven buildings, totaling approximately 1,363,541 gross square feet. Golden West College Golden West College Campus Map The results of the assessment will provide CCCD with the technical information needed to make informed decisions regarding the disposition of existing facility maintenance funds and the need and cost of a capital improvement program.

4 conducted a visual inspection of one hundred eleven of the existing CCCD facilities to identify the condition and to estimate the cost to perform the necessary repairs and renovations. Existing Facility Assessment Findings The generally accepted range of Facility Condition Index (FCI) for establishing a buildings condition is shown below. This standard has been adopted by the Building Owners and Managers Association, the Council on Education Facilities, and the American University Planners Association, and a number of other national facilities groups. Condition FCI Good 0 to 5% Fair 6 to 10% Poor 10% and above The results of our assessment are summarized in the FCI tables on pages 7 and 8. The estimated initial cost to repair these one hundred eleven facilities totals $81,209,107. The overall FCI rating of 19.45% for the one hundred eleven buildings assessed means that, in general, the facilities are in poor condition despite being generally well maintained. Thirty-five buildings have an FCI less than 10%, the range for good or fair condition. Six buildings have FCI ratings in excess of 50%. When the FCI is greater than 70% the building should be considered for replacement, as opposed to investing the substantial costs to repair a 30 to 40 year old building with systems well beyond their useful lives. A more detailed discussion on the methodology and findings for each of the District buildings is provided in the Assessment of Existing Facilities section of this report.

5 Assessment of Existing Facilities In early 2002, Coast Community College District authorized to perform a district-wide, comprehensive facility condition survey assessment. The costs associated with correcting deficiencies can be identified as follows: Deferred Maintenance maintenance work that has been deferred on a planned or unplanned basis due to lack of funds in the annual budget cycle excluding normal maintenance that has already been scheduled, planned or funded within the current budget cycle. Capital Renewal future renewal requirements for building systems that reach the end of their expected useful life. Fine Arts Gallery, Golden West College The comprehensive facilities assessment performed for CCCD is a detailed visual, non-destructive, inspection of each building. 3D/I s software, COMET Condition Management Estimation Technology is used as the database for recording all deficiencies. The survey assessment is a comprehensive room-by-room inventory of defined key elements and characteristics. The result of the inspection is a populated database that catalogs every deficiency costing over a certain value. In parallel with the FCCC-3D/I agreement for discounted facility condition assessment services, an information technology project referred to as the Facility Utilization, Space Inventory Options Net or FUSION Project is underway. This project will design and deliver a centralized database and software in which the facility condition assessment data will reside and be used and managed by the districts to better manage their real asset portfolio. Approach The assessment teams are comprised of design professionals, typically an architect and an engineer. For each building, the teams collected much of the facility s historical information prior to visiting the facility. This research included a review of existing drawings, meetings with the campus maintenance staff, and a review of previous renovations. The assessment teams then conducted a site visit to verify data already gathered as well as to record additional information found during the inspection. Based on visual observations and discussions with facility occupants and maintenance staff, the assessors determined what deficiencies existed and the general conditions of key building systems. A written description of the facility, including an overview of the facility s construction, building systems and general condition, was then developed.

6 Background Since its founding in 1947, the Coast Community College District has enjoyed a reputation as one of the leading community college districts in the United States. Coast Community College District plays an important role in the community by responding to the needs of a changing and increasingly diverse population. The California Community Colleges Chancellor s Office encouraged districts within the CCC System to take advantage of the discounted assessment service to generate an unbiased appraisal of the school s physical conditions and to obtain recommendations for building system replacement based on priorities and expected useful life. Facilities One of the findings of the assessment process is the determination of the Facility Condition Index, or FCI. The FCI is a ratio of the estimated cost to repair the identified deficiencies divided by the estimated replacement value of the facility. It describes the relative state of physical condition of a building (or its components, or a group of buildings) against a cost model of the original building as if it were at the beginning of its useful life, fully renewed to today s standards. Condition FCI Good 0 to 5% Fair 6 to 10% Poor 10% and above Summary of Findings The costs presented below are a summary of the findings of the assessment for the current deficiencies. The costs do include soft costs associated with a rehabilitation project. These costs can change based on the packaging of repair and renovation projects. Campus Estimated Repair Cost Gross Square Feet FCI % Replacement Cost Coast CCD $81,209,107 1,363, % $417,479,888 Hard Cost $60,378,484 $310,393,792 Soft Cost $20,830,623 $107,086,096 Based on current industry standards, the campus FCI indicates the facilities are in poor condition.

7 Building System Classifications The following chart gives a breakdown of the recorded deficiencies by their respective building systems for the entire campus. Estimate by Building System - Coast CCD $2,740,213 $2,814,714 $2,959,730 $3,105,385 $444,007 $542,942 $566,688 $797,743 $1,027,543 $1,137,392 $1,493,217 $2,160,609 $1,683,728 $19,995,384 $4,534,899 $4,566,825 $18,150,389 $12,856,421 Mechanical Electrical Plumbing Furniture/Shelving IntFloor Fire Protection IntCeil IntFinish IntDoor Interior Construction Exterior Closure Conveying Special Constructio IntPart Cooling Exterior Walls Special Electrical Various In general, the majority of the costs identified in the assessment are for mechanical and electrical systems. Within mechanical systems, most costs are for adding or replacing chillers, boilers, and associated components such as air handlers and ductwork. The majority of the electrical system costs are for replacing lighting fixtures and providing additional capacity to the main service and branch circuits.

8 Facility FCI by Type Structure The following is a list of the campus facilities grouped by building number displaying the Current Repair Cost, Replacement Cost and FCI. Facility Gross SQ FT Yr Built Repair Cost Replacement Cost FCI Coast CCD Totals 1,363,541 81,209, ,479, % Coastline Community College 98,770 1,154,464 27,073, % 401 GG Higher Ed Ctr. 48, ,105 13,039, % 900 College Center 50, ,052,359 14,033, % Golden West College 600,270 37,290, ,704, % 01 Math Science 44, ,615,900 13,569, % 02 Forum One 11, ,981 3,503, % 03 Bus Soc Sci 15, ,466 4,822, % 04 Admissions/Records/Counsel 39, ,841 12,433, % 04A Administration 18, ,811 5,897, % 05 Communication 8, ,462 2,376, % 06 Music 14, ,191,850 4,455, % 07 Library M/M Center 58, ,026,172 18,133, % 08 Fine Arts Gallery 9, ,348 2,906, % 08A Fine Arts Bldg. (New) 31, ,447,720 9,533, % 10 Men's Phys Ed 16, ,109,494 5,235, % 11 Women's Phys Ed 8, ,032 2,821, % 12 Community Center 5, ,062 1,752, % 13 Corporation Yard 12, ,256 1,723, % 14 Trade-Indust. (Auto/Diesel) 31, ,214,244 8,799, % 15 Health Science 18, ,807,726 5,453, % 16 Cosmetology 12, ,395,166 3,591, % 17 Tele-Comm+Forum II 16, ,820 4,972, % 18 PE-Rec 44, ,898,888 15,406, % 19 Technology 25, ,216,848 7,922, % 20 Community Theater 27, ,373,674 7,973, % 21 Humanities 39, ,320,454 12,278, % 23 Trade-Industry 2 23, ,351,966 7,016, % 24 Child Care Center 5, , , % 25 Health Center 4, , , % 26 Criminal Justice-Trn- 11, ,617 3,397, % 26A Crim. Justice Trg. Annex 1, , % 27 Rehabilitation Center 1, , , % 28 Security 1, , , % 91 College Store 9A 7, ,556 2,166, % 92 College Center 9B 15, ,921,163 4,669, % Load Center A-Old M/S 1, ,564 1,785, % Load Center B-Forum 1 1, ,768 1,785, % Load Center C-Admission 1, ,116 1,785, % Load Center D - Library 1, ,243 1,801, % Load Center E-Std. (Coll.) Ct. 1, ,068 1,785, % Load Center G-Cosmetology 1, , , % Load Center H-F.A./Music 1, ,858 2,678, % Load Center J-Rec. Ed. 1, , , % Load Center K-Rec. Ed. 1, ,847 1,785, % Load Center L-Technology 1, ,879 1,785, % Load Center P-New M/S 1, ,402 1,785, % Load Center R-KOCE 1, ,530 1,785, % Load Center S-F.A. (New) , , % Load Center T-Health Scn. 1, ,571 1,785, % Load Center V-Admin. 1, , , %

9 Facility FCI by Type Structure - Continued Facility Gross SQ FT Yr Built Repair Cost Replacement Cost FCI Orange Coast College 664,501 42,763, ,702, % 001 Administration 13, ,597 4,244, % 002 Auditorium 28, ,212,194 8,416, % 003 Music 4, ,511 1,266, % 004 Music 7, ,574 2,174, % 005 Fine Arts 16, ,348 4,546, % 007 Counseling Admissions 13, ,170,877 4,040, % 008 Counseling Admissions 5, ,729 1,586, % 009 Counseling Admissions 5, ,850 1,643, % 010 Special Services 7, ,555 2,293, % 011 Faculty House 2, , , % 012 Business Education 6, ,404 1,881, % 013 Business Education 4, ,769 1,354, % 014 Business Education 8, ,619 2,396, % 035 Science 6, ,631 1,877, % 036 Science 10, ,214,028 3,143, % 037 Reprographic Ct 6, ,499 1,979, % 038 Science , , % 039 Science 1, , , % 040 Science Hall 10, ,631,472 2,960, % 041 Science Lecture Hall 1&2 4, ,257 1,480, % 042 Ctr Applied Science 33, ,868,808 9,871, % 043 Consumer Health Sci 1, , , % 044 Taco Bell E 2, , , % 047 Skill Center 15, ,638 4,511, % 048 Skill Center 8, ,859 2,424, % 049 Allied Health 2, , , % 050 Health Science 3, ,177 1,042, % 064 Horticulture 3, , , % 069 Chemistry 33, ,330 9,772, % 070 Literature-Language 23, ,090 6,958, % 071 Home Economics 6, ,668 1,875, % 072 Home Economics 10, ,116,599 3,107, % 073 Computing Center 15, ,042,047 4,452, % 080 Social Sciences 12, ,111,486 3,623, % 081 Forum 9, ,406,170 2,658, % 082 Sports Medicine Lab 6, ,925 1,695, % 083 Bookstore 8, ,406 2,534, % 085 Snack Bar East 1, , , % 086 Student Center 26, ,043,927 7,647, % 089 Student Health Ct 12, ,263 3,406, % 090 Physical Ed Bus Off ,727 86, % 091 Gymnasium 28, ,149,736 9,196, % 092 Women's Shower/Locker 7, ,012,246 2,446, % 096 Men's Shower/Locker 12, ,326,818 3,973, % 097 Indoor Handball Courts 7, ,497 2,272, % 110 Field House 9, ,084,881 2,915, % 114 Technology Ctr 47, ,956 12,932, % 115 Technology Ctr A 7, ,665 2,070, % 116 Technology Ctr B 1, , , % 138 Sailing Center 10, ,041 3,142, % 139 Strength Lab 3, , , % 144 Bookstore Warehouse 3, , , % 146 Early Child Lab Sch 6, ,451 1,809, % 147 Public Safety 2, , , % 149 Community Educates 3, , , % 150 Counseling Adm Anx 3, , , % 152 Children's Center 12, ,162 3,773, % 153 Children Ctr Art ,023 65, % 155 Maint & Oper 19, ,920 5,625, % 156 Art Annex 10, ,777 2,938, % 157 Weight Lab 2, , , % 158 Art Center 57, ,161 16,607, % 172 Middle Col High School 2, , , %

10 It is accepted practice within the field of professional property management to consider replacement rather than repair of an asset when the FCI for that facility is in the range of 60 70% or higher. For facilities with an FCI in or near this range, the master planning process should carefully weigh issues such as: Student population (current versus planned) of the school in question The condition of the existing foundations and superstructures. The need for additional space, i.e., new construction. The appropriateness of the location of current assets. Provided in this report are cost estimates to renovate the facilities and eliminate the identified deficiencies. Please note that these estimates reflect incorporating current building standards, codes, and livability issues into the renovation. The cost estimates do not reflect upgrades to: Forum Building, Orange Coast College the architectural program e.g., additional square footage for another educational mission; finishes e.g., terrazzo tile in lieu of concrete; and/or systems replacement of a 200 Amp electrical service with a 300 Amp service, which may in fact be more applicable for today s educational mission/program but would require further engineering and study to determine the appropriate service for today s learning environment.

11 Capital Renewal Funding Requirements 10 Year Renewal Projection The following chart illustrates the 10-year total funding requirements for the Coast Community College District for three (3) funding scenarios. It shows the combined funding needed for correcting the assessed deficiencies and the predicted capital renewal requirements. Using this chart, we can query: How much funding is required to maintain the current FCI? What level of funding is required to achieve an FCI of 10%? What level of funding is required to achieve an FCI of 5% Future Facility Funding vs FCI for Coast CCD $35,000,000 Current FCI = 19.45% 20.0% $30,000,000 $25,000, % 16.0% 14.0% $20,000,000 $15,000, % 10.0% 8.0% $10,000,000 $5,000, % 4.0% 2.0% $0 0.0% Year Funding Plan 1 FCI% Progress 1 Funding Plan 2 FCI% Progress 2 Funding Plan 3 FCI% Progress 3 Funding Plan Total Red $7.1 M $9.2 M $10.0 M $7.3 M $1.9 M $6.8 M $6.6 M $1.2 M $2.0 M $9.9 M $62.0 M Blue $9.8 M $12.0 M $12.9 M $10.2 M $4.9 M $9.9 M $9.8 M $4.5 M $5.3 M $13.3 M $92.3 M Green $10.6 M $12.8 M $13.7 M $11.1 M $5.8 M $10.8 M $10.7 M $5.5 M $6.4 M $14.4 M $101.7 M

12 Three scenarios are shown: Current FCI: Keep the current FCI Stable (Red) The red line assumes no spending in the current year (2003) for current deficiencies. Capital renewal costs, as shown, over the next 10 years would be required to maintain the current FCI. The total to keep the FCI stable is approximately $62 million. Required funding: Reduce the FCI to 10% (Blue) The green line assumes no spending in the current year (2003) for all current deficiencies. It assumes a consistent level of funds for the next 10 years to buy-down the current deficiencies and additional funding for capital renewal items to achieve an FCI of 10%. (Minimal standard as published by APPA.) The total to reduce the FCI to 10% is approximately $92.3 million. Required funding: Reduce the FCI to 5% (Green) The blue line assumes no spending in the current year (2003) for all current deficiencies. It assumes a consistent level of funds for the next 10 years to buy-down the current deficiencies and additional funding for capital renewal items to achieve an FCI of 5%. The total to reduce the FCI to 5% is approximately $101.7 million.

13 20 Year Capital Renewal Forecast The cost models for each building give us a method to predict future needs for capital renewal. Each model allows us to assess the remaining life of each of the main systems in the building and to enter the expected time of replacement of such systems. Although each model is only a rough approximation for one building, over a larger sample size use of these cost models produces a reliable estimate of the yearly cost to replace building systems. This chart illustrates a 20-year projection of capital renewal funding requirements, excluding current deficiencies for the entire district. Facility Renewal Forecast for Coast CCD $45,000,000 $40,000,000 $35,000,000 $30,000,000 $25,000,000 $20,000,000 $15,000,000 $10,000,000 $5,000,000 $0 Year Coast CCD

14 Conclusions The overall FCI of the facilities in the Coast Community College District is 19.45%, typical of what we find for facilities of similar age and function across the nation. While this is a poor FCI (as defined by the APPA) the facilities are generally well maintained. The majority of the deferred maintenance requirements are of the type that can be renewed without demolition of the facility. (e.g., mechanical and electrical systems, wall and floor finishes, and exterior doors and windows.) Not all facilities should be renovated; however, renovation should remain an option as the planners consider educational master plans, new buildings, high growth areas, population, etc.

15 Facilities Assessment Methodology COMET Assessments Condition Management Estimation Technology Facility Management Software The basic level of surveys to be performed within the CCC System is referred to as Level 1 or Level 2 assessments. A Level 1 (L-1) assessment is a mathematical model of a facility s component building systems, which is used to determine their conditions based on the components planned life cycles. It is a strategic tool for programming and budgeting capital renewal costs; a macro view of facility status. A Level 2 (L-2) assessment is a detailed physical survey of the condition of existing facilities wherein the assessors document hundreds or thousands of current deficiencies. These deficiencies are added to the L-1 component building system life cycles to determine a comprehensive facility evaluation of both current deficiencies and future renewal costs. It is a tool for facility managers to identify specific deferred maintenance and capital renewal items to repair or replace. The majority of the facility condition assessment being performed by 3D/I, for Districts within the California Community College System, are Level 2 assessments. For this type of assessment, data is collected from a review of as-built drawings and other current documents as well as a complete but nondestructive visual inspection of facilities. Typical areas of buildings that are investigated include roofs, mechanical rooms, and exterior support areas extending to 5 feet from the building. Coastline Community College The first phase of an L-2 assessment is the review of the floor plans of each facility to be assessed. Next a hierarchical structure (a tree or parent/child relationship) that captures the facilities and all interior rooms and spaces is designed in the COMET software. The tree structure provides the assessor a road map of the building and the lowest level of the tree structure is where the deficiencies are recorded. The next step is developing cost models for the life cycles of building systems. This includes reviewing existing documents to determine types, ages, and components of the buildings, and the dates and scope of any recent renovations. 3D/I s cost models are based on RS Means building material estimates and the Business Owners and Managers Association (BOMA) estimated useful life of building components. However, COMET can be customized to reflect individual client s project or O&M cost histories and to account for particular environmental or operational conditions such as excessive moisture and heat or continuous operation. Also considered are preventative maintenance efforts, since they can often significantly affect the number of years a system can remain in operation.

16 Priorities Filters Each deficiency is assigned a Priority as described below. Priority 1: Directly Affects the Educational Mission Systems or elements within systems that should be repaired or replaced to mitigate issues that prevent the educational mission of the facility. Priority 2: Indirectly Affects the Educational Mission - Systems or elements within systems that should be replaced or repaired to maintain the educational mission of the facility or mitigate additional damage to the facility. Priority 3: Beyond Expected Useful Life Systems or elements within systems that should be replaced or repaired to maintain the mission of the facility but potentially have some life left. Priority 4: Finishes and Improvements Systems or elements within systems that should be replaced or repaired or upgraded that have minimal impact on the educational mission of the facility. Categories Each deficiency is classified into one of the following categories. Life Safety Code Compliance Building Code Compliance Accessibility Code Compliance Capital Renewal Deferred Maintenance Energy Efficiency Improvement Hazmat Adverse Effects Each deficiency is assigned one of the following risk potentials. Campus / Facility Closure Safety Hazard Disruption of Program Code Violation Greater Future Damage / Cost Inconvenience Potential / Future Damage / Cost

17 City Index Definitions The R.S. Means data used to develop the cost models is a national average. As such, we modified the costs using a standard index published by the R.S. Means Corporation. Facility Condition Index (FCI) The FCI represents the relative physical condition of facilities. The FCI measures the estimated cost of the recommended improvements and compares that to the replacement cost of the facility. The total cost of repairs divided by the facility replacement cost is the FCI. A higher FCI indicates a facility in worse shape. For example, if a building has a replacement value of $1,000,000 and has $100,000 of existing deficiencies, the FCI is $100,000/$1,000,000 or The generally accept rule of thumb in building condition assessments is: Condition FCI Good 0 to 5% Fair 6 to 10% Poor 10% and above Associated Students Bookstore, Orange Coast College Facility Systems Conveying: Elevators Electrical includes alarms and communications, lighting, power, service and distribution. Excavation includes any digging for underground access or removal of soil. Exterior Closure includes exterior doors, trim, caulking, etc. Exterior Walls includes refinishing and painting exterior surfaces and materials. Fire Sprinkler includes fire protection systems. Foundations include work to repair footings or level slabs, etc. Heating & Cooling System includes boilers, cooling, HVAC piping, insulation, mechanical components like pumps and controls. Interior construction includes ceiling finishes, flooring finishes, interior doors, stairs, wall finishes and walls. Plumbing includes potable and sanitary piping and plumbing fixtures. Roof includes all components of a roofing system including the deck, insulation, membrane, and any special work such as gutters or repairing flashing, etc. Slab on Grade includes any repairs, removal, or replacement after other work is done.

18 Special Construction includes chalk and tack boards, seating, etc. Structural includes framing system, columns, beams, and slabs. Superstructure includes the exterior walls. Windows includes repair or replacement of window units. Structural: superstructure (columns, beams, footings, foundations, slab-on-grade, etc) Facility Replacement Cost This represents the derived expense to rebuild the existing facilities in a manner representing the desired construction. The replacement cost is determined by multiplying the gross area of the facility by the estimated cost per square foot cost value associated with the pertinent cost model. Renewal Premiums The costs developed in the models are typical of new construction. When a renovation project is undertaken, certain additional costs are incurred for some systems because of demolition and difficulty. For other systems, not all items in the assembly are replaced. In these instances the reduction in work overcompensates for the demolition costs, and a lower cost is incurred. The table below details our strategy for this issue by system group. System Name Life (yrs) % Renewal Conveying 25 75% Electrical 30 90% Exterior Closure % Exterior Walls % Fire Protection 25 95% Foundations % IntCeil % IntDoor % IntFinish % IntFloor % IntPart % Mechanical 30 90% Plumbing 30 90% Roof Deck % Roofing % RoofOpSp % Special Construction % Special Electrical 10 90% Stairs % Structural % Structural walls % Windows %

19 Hard and Soft Costs Hard Costs include the installing contractors cost (RS Means data), site work, the contractor s general conditions, the general contractors overhead and profit and an amount for construction contingency. Soft costs are additional costs, which are necessary to accomplish the work, but are not directly attributable to the general contractor or the deficient system. Soft costs vary by user but can include design fees; specialized investigations such as geotechnical, environmental, or hazardous material; program management fees; and various administrative fees. The soft costs used in this assessment are as follows: New Construction Cost Breakdown for Cost Models Description Percentage Hard Cost 1. Total Subcontractor/Specialty Costs R.S. Means Assembly price 2. Site Work 12.0% of 1 3. Area Location Factor 8.0% of 1 4. General Conditions 15.0% of (1+2+3) 5. Contractor Overhead and Profit 10.0% of ( ) 6. Construction Contingency 5% of ( ) 7. General Contract Soft Cost 8. Architecture & Engineering 15.0% of General Contract 9. Plan Check/Permits/Fees 2.0% of General Contract 10. Hazardous Materials 0.5% of General Contract 11. Materials Testing & Inspection 2.0% of General Contract 12. Bonds & Insurance 2.0% of General Contract 13. Temporary Storage and Relocation 1.0% of General Contract 14. Furniture & Equipment 7.0% of General Contract 15. Construction Management 5.0% of General Contract

20 Renovation Cost Breakdown for deficiencies pricing Hard Cost Description Percentage 1. Total Subcontractor/Specialty Costs R.S. Means per unit price 2. General Conditions 15.0% of 1 3. Contractor Overhead and Profit 10.0% of (1+2) 4. Construction Contingency 15% of (1+2+3) 5. General Contract Soft Cost 6. Architecture & Engineering 15.0% of General Contract 7. Plan Check/Permits/Fees 2.0% of General Contract 8. Hazardous Materials 3.0% of General Contract 9. Materials Testing & Inspection 2.0% of General Contract 10. Bonds & Insurance 2.0% of General Contract 11. Temporary Storage and Relocation 1.0% of General Contract 12. Furniture & Equipment 7.0% of General Contract 13. Construction Management 5.0% of General Contract It is important to note that these costs may vary once plans for executing the work are created. If variations do occur over time, the data in COMET can be easily updated to reflect the changing costs.

School Assessment Report

School Assessment Report School Assessment Report School: KIPP Vision Report: Dec 15, 14 Condition Assessment: Suitability Assessment: Generated: 12/15/14 12:33:33 PM Final School Assessment Report - Charter Schools, KIPP Vision

More information

School Assessment Report

School Assessment Report School Assessment Report School: Humphries Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:35:17 AM FOR OFFICIAL USE ONLY Final School Assessment

More information

School Assessment Report

School Assessment Report School Assessment Report School: Sutton Middle School (Powers Ferry) Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:32:59 AM FOR OFFICIAL USE ONLY Final School

More information

Semi-Annual Report. January 1, 2012 June 30, 2012

Semi-Annual Report. January 1, 2012 June 30, 2012 Semi-Annual Report January 1, 2012 June 30, 2012 G.O. Bond Project Status As of June 30, 2012 Completed OCC Soccer Fields GWC Library/Classroom Improvements OCC South Campus Utilities Upgrade GWC Student

More information

School Assessment Report

School Assessment Report School Assessment Report School: Morningside Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:29:07 AM FOR OFFICIAL USE ONLY Final School Assessment

More information

School Assessment Report

School Assessment Report School Assessment Report School: Carver High School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:37:23 AM FOR OFFICIAL USE ONLY Final School Assessment Report

More information

DeKalb County School District/Stadiums Avondale Stadium Final School Assessment Report May 20, 2016

DeKalb County School District/Stadiums Avondale Stadium Final School Assessment Report May 20, 2016 DeKalb County School District/Stadiums Avondale Stadium Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition Summary

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

LEWIS ELEMENTARY SCHOOL

LEWIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

MAURY ELEMENTARY SCHOOL

MAURY ELEMENTARY SCHOOL INITIAL YEAR BUILT 1886 BUILDING AREA 46,800 SF CURRENT PROGRAM CAPACITY 276 ENROLLMENT 2008 238 WARD 6 PROPOSED PROGRAM CAPACITY 325 Site Plan MAURY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

School Assessment Report

School Assessment Report School Assessment Report School: Morningside Elementary School Report: Dec 15, 2014 Condition Assessment: Suitability Assessment: Generated: 12/15/2014 12:11:31 PM FOR OFFICIAL USE ONLY Final School Assessment

More information

July 1 September 30, 2008

July 1 September 30, 2008 July 1 September 30, 2008 1 G.O. Bond Project Status As of September 30, 2008 Completed OCC Soccer Fields GWC Library/Classroom Improvements OCC South Campus Utilities Upgrade GWC Student Center Remodel

More information

Facilities Feasibility Study Frederick Douglass HS Condition Assessment

Facilities Feasibility Study Frederick Douglass HS Condition Assessment Summary of Findings The Frederick Douglass HS Facility located at 2301 Gwynns Falls Parkway in Baltimore, Maryland, was built in 1927. It comprises 194,249 gross square feet. The total current deficiencies

More information

NALLE ELEMENTARY SCHOOL

NALLE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

DeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016

DeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016 DeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

SEATON ELEMENTARY SCHOOL

SEATON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

BARNARD ELEMENTARY SCHOOL

BARNARD ELEMENTARY SCHOOL INITIAL YEAR BUILT 2002 BUILDING AREA 67,000 SF CURRENT PROGRAM CAPACITY 520 ENROLLMENT 2008 329 WARD 4 PROPOSED PROGRAM CAPACITY 450 Site Plan BARNARD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

BALLOU SENIOR HIGH SCHOOL

BALLOU SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 X DATE: March 27-29, 2018 ****************************************************************************** SUBJECT USD North Commons Renovation

More information

NOYES EDUCATION CAMPUS

NOYES EDUCATION CAMPUS INITIAL YEAR BUILT 1930 BUILDING AREA 49,700 SF CURRENT PROGRAM CAPACITY 321 ENROLLMENT 2008 337 WARD 5 PROPOSED PROGRAM CAPACITY 450 Site Plan NOYES - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-8

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

STUART-HOBSON MIDDLE SCHOOL

STUART-HOBSON MIDDLE SCHOOL INITIAL YEAR BUILT 1927 BUILDING AREA 105,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 399 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan STUART-HOBSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

RESIDENTIAL CONSTRUCTION PERMIT FEES

RESIDENTIAL CONSTRUCTION PERMIT FEES RESIDENTIAL CONSTRUCTION PERMIT FEES R-1 Building Permit: One- or Two-Family New Construction (Complete Permit Packet) Combination permit to include Building, Electrical, Mechanical, Plumbing (to include

More information

Hatton Drive Warehouse

Hatton Drive Warehouse DeKalb County School District/Leased/Charter Hatton Drive Warehouse Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 3 School Condition

More information

Facility Condition Assessment

Facility Condition Assessment Citywide Facility Condition Assessment Report of Facility Condition Assessment For City of Manhattan Beach 1600 Marine Avenue, Manhattan Beach, CA September 4, 2013 (Rev A) Provided By: Faithful+Gould,

More information

WILKINSON ELEMENTARY SCHOOL

WILKINSON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1976 BUILDING AREA 144,900 SF CURRENT PROGRAM CAPACITY 508 ENROLLMENT 2008 451 WARD 8 PROPOSED PROGRAM CAPACITY 600 Site Plan WILKINSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

School Assessment Report

School Assessment Report School Assessment Report School: Cascade Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:37:55 AM FOR OFFICIAL USE ONLY Final School Assessment

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

POWELL ELEMENTARY SCHOOL

POWELL ELEMENTARY SCHOOL INITIAL YEAR BUILT 1925 BUILDING AREA 38,500 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 319 WARD 4 PROPOSED PROGRAM CAPACITY 325 Site Plan POWELL - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-3

More information

LASALLE - BACKUS EDUCATION CAMPUS

LASALLE - BACKUS EDUCATION CAMPUS INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

CENTENNIAL SCHOOL DISTRICT

CENTENNIAL SCHOOL DISTRICT CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites

More information

Architectural Services Consultant Registration Form

Architectural Services Consultant Registration Form Architectural Services Consultant Registration Form Send three copies of the completed registration form to: San Bernardino Community College District, Facilities Project Management, Attn: Scott Stark,

More information

QUARTERLY REPORT. (July 1, 2013 September 30, 2013) December 18, 2013

QUARTERLY REPORT. (July 1, 2013 September 30, 2013) December 18, 2013 QUARTERLY REPORT (July 1, 2013 September 30, 2013) December 18, 2013 Closed CCC NBLC Lease Revenue Bond Retirement Completed DIST Help Desk Software OCC Gym Acoustic Retrofit OCC Large Lecture Hall Seating

More information

SAVE YOURSELF TIME AND MONEY! PLEASE READ THE FOLLOWING INFORMATION:

SAVE YOURSELF TIME AND MONEY! PLEASE READ THE FOLLOWING INFORMATION: TOWN OF SURFSIDE BEACH, SC SUBSTANTIAL IMPROVEMENT NOTICE TO PROPERTY OWNERS Rebuilding your Home or Non-residential structure after the storm? Adding on, renovating, or remodeling your home or business?

More information

Deferred Maintenance Plan

Deferred Maintenance Plan Deferred Maintenance Plan 2012-2015 1/5/2012 1 Table of Contents Title Page Introduction 3 Wallace Hall Deferred Maintenance 4 Wallace Hall Building Assessment 6 Wilson Hall Deferred Maintenance 7 Wilson

More information

0B MAGNOLIA HALL. Scale: 1:110. Date: Feb Time: 7:40 pm. User: brady. 10 ft

0B MAGNOLIA HALL. Scale: 1:110. Date: Feb Time: 7:40 pm. User: brady. 10 ft 0B 2 m 1:110 7:40 pm. 01 5 m 1:230 7:38 pm. 02 5 m 1:230 7:38 pm. 03 5 m 1:230 7:45 pm. Facility Profile ( FP-1 ) City: State: Country: Address: Stories: Attic: Basement: Glassboro New Jersey United States

More information

Former Truancy Center

Former Truancy Center DeKalb County School District/Vacant Former Truancy Center Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 3 School Condition Summary

More information

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested. Purpose 355 West Queens Road Single Family New Construction Required Inspection Stages Master Requirement GEN 110 Building Department: 604-990-2480, building@dnv.org, fax: 604-984-9683 The following procedure

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

INDOOR HEALTH ISSUES

INDOOR HEALTH ISSUES HUMAN SYSTEMS SKIN BONES NERVES HEART LUNGS VESSELS INDOOR ENVIRONMENT PRODUCTIVE WORK ENERGY WATER HUMAN SYSTEMS WASTE WASTE INDOOR HEALTH ISSUES The effect of building health on the humans and human

More information

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923 INITIAL YEAR BUILT 1923 BUILDING AREA 288,800 SF CURRENT PROGRAM CAPACITY 1,425 ENROLLMENT 2008 565 WARD 6 PROPOSED PROGRAM CAPACITY 1,100 Site Plan EASTERN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

January 1, 2009 March 31, 2009

January 1, 2009 March 31, 2009 January 1, 2009 March 31, 2009 1 G.O. Bond Project Status As of March 31, 2009 Completed OCC Soccer Fields GWC Library/Classroom Improvements OCC South Campus Utilities Upgrade GWC Student Center Remodel

More information

KEY ELEMENTARY SCHOOL

KEY ELEMENTARY SCHOOL INITIAL YEAR BUILT 1925 BUILDING AREA 52,000 SF CURRENT PROGRAM CAPACITY 320 ENROLLMENT 2008 328 WARD 3 PROPOSED PROGRAM CAPACITY 325 Site Plan KEY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Rebuilding our schools for health, safety, and cutting edge 21 st century learning

Rebuilding our schools for health, safety, and cutting edge 21 st century learning Rebuilding our schools for health, safety, and cutting edge 21 st century learning The problem The state of our schools: aging infrastructure The plan The Sustainable Built Environment Strategy: deep retrofits

More information

Town of Falmouth FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage COSTS FOR SUBSTANTIAL IMPROVEMENTS / REPAIR OF SUBSTANTIAL DAMAGE:

Town of Falmouth FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage COSTS FOR SUBSTANTIAL IMPROVEMENTS / REPAIR OF SUBSTANTIAL DAMAGE: S FOR SUBSTANTIAL IMPROVEMENTS / REPAIR OF SUBSTANTIAL DAMAGE: Included Costs: Items that must be included in the costs of improvement or costs to repair are those that are directly associated with the

More information

Cold Spring School District

Cold Spring School District Cold Spring School District Deferred Maintenance & Capital Facilities Program July 9, 2018 Deferred Maintenance District Fund 14 School Facilities Maintenance in General Three types of maintenance projects

More information

La Conner School District

La Conner School District hoarch.com La Conner School District Capital Bond Planning Meeting 4 - Master Plan Options / Budget Estimates July 18th, 2012 4010 Lake Washington Blvd, NE, Suite 320 Kirkland, Wa 425 828 8948 Agenda Meeting

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

DAVIS ELEMENTARY SCHOOL

DAVIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1943 BUILDING AREA 71,100 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 227 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan DAVIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-

More information

SECTION : OPERATION & MAINTENANCE MANUALS

SECTION : OPERATION & MAINTENANCE MANUALS SECTION 01 17 73: OPERATION & MAINTENANCE MANUALS 1. GENERAL: A. This section includes requirements for Contract Record - Operations and Maintenance manuals required prior to project closeout including,

More information

School Without Walls

School Without Walls INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment Summary of Findings The Matthew A. Henson ES Facility located at 1600 N. Payson Street in Baltimore, Maryland, was built in 1964. It comprises 75,228 gross square feet. The total current deficiencies for

More information

Project #1 (Prioritized): Proposed Project Title:

Project #1 (Prioritized): Proposed Project Title: Six-Year Appropriated Capital Improvements Projects Plan 2009 through 2015 Institution Name: North Carolina A&T State University Project #1 (Prioritized): Proposed Project Title: Engineering Research Center

More information

Health Life Safety Survey and Master Facilities Plan

Health Life Safety Survey and Master Facilities Plan Health Life Safety Survey and Master Facilities Plan Community Presentation Board Meeting June 22, 2015 June 22, 2014 Board Presentation Overview and Summary of the Health Life Safety Survey and Master

More information

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information

More information

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE Information and Required Forms for Structures in Flood Zones AE & VE

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE Information and Required Forms for Structures in Flood Zones AE & VE County of Monroe The Florida Keys Floodplain Coordinator Upper Keys: 305-453-8729 Middle & Lower Keys: 305-289-2866 SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE Information and Required Forms for Structures

More information

APPLICATION AND CERTIFICATE FOR PAYMENT

APPLICATION AND CERTIFICATE FOR PAYMENT AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 1 ACTIVE PROJECTS Santa Ana College Central Plant, Infrastructure and Mechanical Upgrades 2 COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements

More information

Facilities Feasibility Study Laurence G. Paquin Building Condition Assessment

Facilities Feasibility Study Laurence G. Paquin Building Condition Assessment Summary of Findings The Laurence G. Paquin Building Facility located at 2200 SINCLAIR LANE in Baltimore, Maryland, was built in 1975. It comprises 65,666 gross square feet. The total current deficiencies

More information

Bronx Community College. Five-Year Capital Plan FY through FY

Bronx Community College. Five-Year Capital Plan FY through FY Five-Year Capital Plan FY 2019-20 through FY 2023-24 Projects in priority order / costs in $ thousands Project Name FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24 (B) Campus-Wide Fire Alarm Replacement DC

More information

Corsicana High School

Corsicana High School Contents Corsicana High School...2 General comments, campus capacity, and student demographics...2 1.0 School Site...4 2.0 Building Systems and Components...6 3.0 Building Safety and Security...19 4.0

More information

Coos Bay Best Bond Cost Breakdowns

Coos Bay Best Bond Cost Breakdowns Coos Bay Best Bond Cost Breakdowns Overview [For itemized breakdown by school, see following pages.] Harding: New 7 th /8 th grade school on Harding site, including second gym: $18,440,000 Demotion of

More information

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage Property Address: Company Name: Contractor Name: Contractor Address: City: State: Zip: License Number: Phone Number

More information

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005

More information

PATTERSON ELEMENTARY SCHOOL

PATTERSON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1945 BUILDING AREA 78,300 SF CURRENT PROGRAM CAPACITY 368 ENROLLMENT 2008 463 WARD 8 PROPOSED PROGRAM CAPACITY 500 Site Plan PATTERSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

October 1, 2008 December 31, 2008

October 1, 2008 December 31, 2008 October 1, 2008 December 31, 2008 1 G.O. Bond Project Status As of December 31, 2008 Completed OCC Soccer Fields GWC Library/Classroom Improvements OCC South Campus Utilities Upgrade GWC Student Center

More information

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor

More information

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage Property Address: Company Name: Contractor Name: Contractor Address: City: State: Zip: License Number: Phone Number

More information

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding

More information

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality Executive Summary: Thesis Proposal Final Draft The following pages contain a final draft of the thesis proposal for the South Baltimore District Court House. The basic layout consists of focusing on Knowledge

More information

Building Condition Report. Building Condition

Building Condition Report. Building Condition Price Memorial Building #0001 Present Building Use: The Administration building currently houses offices for the President, and Senior Administration. Building History: Built in 1879 Overall Size: 24,922

More information

REQUEST FOR PROPOSAL # SQ # ARCHITECTURAL / ENGINEERING CONSULTING SERVICES CAMPUS FACILITIES AUDIT

REQUEST FOR PROPOSAL # SQ # ARCHITECTURAL / ENGINEERING CONSULTING SERVICES CAMPUS FACILITIES AUDIT REQUEST FOR PROPOSAL # SQ # 10274 ARCHITECTURAL / ENGINEERING CONSULTING SERVICES CAMPUS FACILITIES AUDIT MIDDLESEX COUNTY COLLEGE 2600 WOODBRIDGE AVENUE EDISON, NEW JERSEY 08818 Prepared By: Randolph

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

TEXAS A&M ENGINEERING

TEXAS A&M ENGINEERING TEXAS A&M ENGINEERING 312 Jack K. Williams Administration Building I 3126 TAMU I College Station, Texas 77843-3126 M. Katherine Banks, Ph.D., P.E. Vice Chancellor and Dean of Engineering Director, Texas

More information

QUARTERLY REPORT. January 1, 2014 March 31, 2014

QUARTERLY REPORT. January 1, 2014 March 31, 2014 QUARTERLY REPORT Coast Community College District Program Summary Closed CCC NBLC Lease Revenue Bond Retirement Completed DIST Help Desk Software OCC Gym Acoustic Retrofit OCC Large Lecture Hall Seating

More information

Commercial Remodel Permit

Commercial Remodel Permit Commercial Remodel Permit Zoning requirements Staff recommends always verifying the zoning requirements for your project before deciding to build. Warrensburg has eleven separate zoning districts, each

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will

More information

COMMERCIAL PROJECT INFORMATION

COMMERCIAL PROJECT INFORMATION Community Development Building and Inspection Services 2100 Ridge Avenue Evanston, Illinois 60201-2798 T 847.448.4311 FAX 847.448.8020 www.cityofevanston.org COMMERCIAL PROJECT INFORMATION The Community

More information

East Los Angeles College Project Priority List Occupancy Date

East Los Angeles College Project Priority List Occupancy Date East Los Angeles College Project Priority List Priority Project Name Occupancy Date Notes 1 Fine Arts/Performing Arts Center 2010 11 Need NOC, DSA Cert and DSA 6 Forms for closeout in FUSION. 2 Multi Media

More information

Project #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50

Project #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50 Project #1139 Budget #82 $ Budgeted $ Billed to Date $ Paid to Date $ Due 210,087.68 120,979.20 120,979.20 77,158.50 Deposit Paid Deposit Due Phase I: Project Programming and Research $ Budgeted $ Billed

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

WATKINS ELEMENTARY SCHOOL

WATKINS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 69,300 SF CURRENT PROGRAM CAPACITY 578 ENROLLMENT 2008 550 WARD 6 PROPOSED PROGRAM CAPACITY 550 Site Plan WATKINS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

SHEPHERD ELEMENTARY SCHOOL

SHEPHERD ELEMENTARY SCHOOL INITIAL YEAR BUILT 1932 BUILDING AREA 79,700 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 355 WARD 4 PROPOSED PROGRAM CAPACITY 400 Site Plan SHEPHERD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Collins Middle School

Collins Middle School Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0

More information

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB CONSTRUCTION COST BREAKDOWN Property Owner s Name or Borrowers Name Brief Description of Project John Homeowner Build single family residence Property Address Property City Property Zip Code 4625 Jillbarr

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

Scenario Pricing Estimates Existing Structure Rehabilitation Multifamily Apartments 750 N Edinburgh Avenue Los Angeles, CA Project No.

Scenario Pricing Estimates Existing Structure Rehabilitation Multifamily Apartments 750 N Edinburgh Avenue Los Angeles, CA Project No. February 16, 2016 Ms. Elisa Paster, Esq. Glaser Weil LLP 10250 Constellation Boulevard, Floor 19 Los Angeles, CA 90067 (310) 553-3000 RE: Scenario Pricing Estimates Existing Structure Rehabilitation Multifamily

More information

Program Update. Chino Health Science Parking Lot

Program Update. Chino Health Science Parking Lot Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction

More information

Kasson Elementary/Middle School Grades PK 8

Kasson Elementary/Middle School Grades PK 8 Barbour County Schools Comprehensive Educational Facilities Plan 2010-2020 Kasson Elementary/Middle School Grades PK 8 Blackwood Associates, Inc. / MSES consultants, Inc. / Roy Blizzard and Associates

More information

The Total Cost of Ownership (TCO) is the total of all costs generated over the useful lifespan of the facility (30-50 years).

The Total Cost of Ownership (TCO) is the total of all costs generated over the useful lifespan of the facility (30-50 years). The Total Cost of Ownership (TCO) is the total of all costs generated over the useful lifespan of the facility (30-50 years). The goal of TCO is to determine a value that will reflect the true cost of

More information

Sub-Section A Lompoc County Offices Executive Summary

Sub-Section A Lompoc County Offices Executive Summary Facility Condition Assessment 2014 Sub-Section A Lompoc County Offices Executive Summary The Lompoc County Offices was assessed for deficiencies, and each building system and site was assigned a condition

More information

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018 Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018 TABLE OF CONTENTS Description Page Construction Summary 1 1 - Residence Life Operations

More information

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS (August 28, 2018) PIERCE HALL IMPROVEMENTS PROJECT NO. 950511-950532 UNIVERSITY OF CALIFORNIA, RIVERSIDE PREQUALIFICATION PROCESS ALL

More information

Introduction to Construction, June 2013, page 1 of 6

Introduction to Construction, June 2013, page 1 of 6 Indiana Department of Education Academic Content Framework INTRODUCTION TO CONSTRUCTION Introduction to Construction is a course that will offer hands-on activities and real world experiences related to

More information

C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) Fax: (630)

C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) Fax: (630) C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) 353-8115 Fax: (630) 852-4709 BUILDING PERMIT INFORMATION PACKET Revised: October 2018 Building Codes: International Residential

More information

DESIGN & CONSTRUCTION GUIDELINES

DESIGN & CONSTRUCTION GUIDELINES DESIGN & CONSTRUCTION GUIDELINES EDITION: USF FACILITIES MANAGEMENT - DC 5 DCG FACILITIES MANAGEMENT DESIGN & CONSTRUCTION PHONE: (813) 974-2845 4202 E. FOWLER AVENUE, OPM 1000 TAMPA, FLORIDA 33620-7550

More information

Section I Lompoc Animal Services Executive Summary

Section I Lompoc Animal Services Executive Summary Section I Lompoc Animal Services Executive Summary In 2013-2014, the Consultant conducted initial facility condition assessment data collection at the County of Santa Barbara, with specific attention to

More information

KENTUCKY STATE UNIVERSITY

KENTUCKY STATE UNIVERSITY KENTUCKY STATE UNIVERSITY Proposed Projects Involving the State General Fund (cash or bonds)* Priority Project Title / Description Total Budget 2004-2006 1 Hathaway Hall Renovation Phase II $11,200,000

More information