Metro-North s Response to Hurricane Irene. Chris Bennett, Vice President AECOM Toby Ritz, Chief Engineer MNR Capital Programs New York

Size: px
Start display at page:

Download "Metro-North s Response to Hurricane Irene. Chris Bennett, Vice President AECOM Toby Ritz, Chief Engineer MNR Capital Programs New York"

Transcription

1 Metro-North s Response to Hurricane Irene Chris Bennett, Vice President AECOM Toby Ritz, Chief Engineer MNR Capital Programs New York

2 The Port Jervis Line Line is operated under a service agreement with NJ TRANSIT; infrastructure repair is MNR responsibility New York State portion is 58.7 miles Predominantly a single track railroad with sections of double track and passing sidings Access to the right-of-way from the road is extremely limited Area of Damage: MP 31 MP 45

3 Key Issues On August 27-28, 2011: Tropical Storm Irene passed over the lower Hudson Valley of NY Large portion of Metro-North s Port Jervis Line was severely impacted Train service was suspended due to the significant damage in the 14-mile section of the railroad just north of Suffern, NY at MP31 to the Harriman Station at MP45 Disrupted 3,000 commuters It was essential to rebuild Metro-North s railroad as soon as possible!

4 Coordination Governor Declared State of Emergency Coordinated closely with impacted communities and private property owners Enabled the railroad and contractor to overcome the limited access to the railroad of right-of-way in the area Get the needed personnel and heavy machinery to the impacted areas so that rebuilding could move ahead quickly

5 Project Goal: Rebuild the Line and restore train service as quickly as possible MTA Chairman acted quickly with policy decisions to expedite rebuilding Invoked emergency powers for the MNR President to contract and procure goods and services for the effort expeditiously Put the full resources of the MTA behind rebuilding the line Began all-agency effort to recover costs incurred from responding to the hurricane through insurance and FEMA Directed MTA CFO to identify funds to pay for the service restoration efforts MNR used these policy decisions to move forward swiftly Dispatched railroad Maintenance of Way forces to make repairs to the line between Harriman and Port Jervis Contracted with AECOM for an emergency condition assessment of the line

6 Metro-North Response Metro-North hired AECOM: 1.To work closely with the railroad s forces 2.Perform an assessment of the massive damage to the railroad infrastructure 3.Resolve field condition challenges 4.Design enhancements to keep the project moving on an expedited basis

7 Use of Technology GPS CAMERA TECHNOLOGY 1849.jpg RESPONSIVE: Site Investigation performed less than one week after hurricane LIDAR AND 3D MODELING THOROUGH: Utilizing GPS Technology to deliver accurate, comprehensive data CONDITION ASSESSMENT REPORT: delivered ahead of original schedule MULTIDISCIPLINE PARTNER: Civil, Structural, Rail, and GIS collaboration INDUSTRY LEADING TECHNOLOGY: Used to model infrastructure 3D MODEL: delivered to Metro-North to assist with repairs

8 AECOM Challenges The Team worked continuously in their efforts to complete: Damage assessment to all elements of the 14 miles of devastated railroad Work together to prepare construction documents, allowing for Metro-North to get a competitive bid to procure an emergency construction contract on an expedited and cost-effective basis

9 Assessing the Damage Within hours after the storm, MNR began assessing the condition of the railroad from the air and the ground. Catastrophic damage was found in the 14 miles between Harriman and Suffern. Roadbed was washed away in numerous locations and for significant stretches Signal cable was exposed and under water Track was intact but twisted and misaligned Bridge structures were exposed with unknown damage There was significant erosion to the banks of the Ramapo River that abut the railroad right-of-way Limited damage was found in the 45 miles between Harriman and Port Jervis. Train service was inoperable.

10 The Ramapo River overflowed its banks with enough power to undermine the track MP 43.5 near Arden Station Road overpass one mile east of Harriman Station

11 MP 33.2 Sloatsburg

12 Flooding was so severe, certain inspections could not be performed for more than one week MP 33.2 Sloatsburg behind Davis Sports Shop

13 Some of the damage suggested that culverts should be built to divert future flooding

14 MP Sloatsburg Track bed was undermined or missing in many areas

15 Flyover Bridge 38.18

16 Flyover Bridge 38.03

17 Damage to exposed parts of railroad bridge structures demanded a complete inspection of all bridges above and below the water line

18 Track bed wash out

19 Track bed wash out and exposed cable

20 Embankment wash out: note C&S boxes

21 Condition Assessment Results & Recommendations The key findings of the AECOM Condition Assessment: Submitted on September 15, 2011 Half of the area from Suffern to Harriman sustained little or no damage. Bridge inspections performed both above and under water revealed that the bridges sustained some damage although the damage was not as extensive as was originally feared. The signal system fared slightly worse. The from east of Sloatsburg through Tuxedo sustained significant damage.

22 MNR worked to restore pre-storm train service by the end of 2011 MNR directed AECOM to create a phased rebuilding plan. Phase I included all work necessary to restore full train service on one track between Harriman and Suffern. Work included: Building access roads between the material staging areas and the right-of-way (work began week of September 19) Rebuilding the track bed sub grade Replacing ballast in the washout areas, compacting the track bed and surfacing the right-of-way Critical work on the under-grade bridges and the track slopes adjacent to the river In Phase I, the third-party contractor work was performed with extended hours. Phase I work was scheduled to be completed by the end of the year. At the end of Phase I, full train service was restored on November 28th Schedule changes for off-peak and weekend service due to single track For Phase II repairs, additional periodic off-peak and weekend train outages with bus substitutions may be required

23 MNR Forces Begin Repairs Placing sub ballast Placing ballast Stockpiling ballast

24 Accelerated Schedule Design documents were ready for bid by Oct. 9, MTA Real Estate negotiated with landowners for access points for workers, heavy-duty machines and material, so several locations could be rebuilt simultaneously. MNR contracted for additional equipment and equipment operators to assist MNR forces in track restoration work. MNR contracted with a third party contractor for access improvements and stockpile work. This work started on September 21, The amount of material required to rebuild was significant and purchasing began quickly. An estimated 150,000 tons of ballast and other fill material was needed to rebuild the sub-grade track structure and make repairs to the embankment. Contracts were executed with 4 companies to provide ballast and other fill.

25 Full restoration of the line was completed by the Spring of 2012 Phase II included the work required to finish full restoration of the line with additional flood mitigation to protect this significant investment: The rebuilding of the second track and track bed between Sloatsburg and Hillburn (completed by the end of December 2011). The repair of the signal system from Harriman to Hillburn and returned it to service (completed by the end of November 2011). Bridge repairs (completed by the end of November 2011). Continue to stabilize the river bank along the right-of-way by placing riprap, building slope protections (including a small a retaining wall), and other flood mitigations. Final completion of all in Spring of On January 15, 2012, train service will return to pre-storm timetable. All work (Phase I and Phase II) was closely monitored both in the field and by senior staff.

26 Placing rip-rap

27 Restoring Embankment

28 Debris Removal

29 Installing New Culvert

30 Installation of 3-36 pipes

31 Protecting and Restoring Signal Cables

32 Culvert Completed

33 Bridge Backwall Replacement Backwall demolition and another weather challenge

34 New Backwall

35 Poured Backwall

36 38.03 Almost done

37 Scour Survey at Bridge 38.18

38 Before and After

39 Before and After

40 Before and After

41 Overview Analysis of Project Goals POST-STORM (SEPT 2011) RECONSTRUCTION (NOV 2011) The reconstruction required the placement of over 100,000 tons of ballast, stone and rip-rap material Installation of numerous culverts Installation and testing of the railroad s signal system Repairs to several railroad bridges, and embankment restoration along over 5,000 feet of the Ramapo River The project team worked around the clock to reconstruct the railroad infrastructure to restore service to the Port Jervis Line in late November one month ahead of the planned accelerated schedule and over $10 million below the initial estimates for the storm damage repairs.

42 Running again! Test Run

43 Test Run

44 Service Restored on November 28

45 First Freight

46 Track work and rip-rap installation continued for Track 2

47 Summary Timeline Damage Inspection Complete September 9, 2011 Less than 2 weeks Bid Package Delivered to MNR September 28, 2011 Construction Begins October 12, 2011 Initial Track Service Restored November 28, 2011 Original Planned Track Service January, 2012 Condition Assessment Report Issued to MNR September 15, 2011 Original Plan for Assessment Report to MNR September 28, 2011 Bid Received. Contract Awarded. October 11, 2011

48 Summary of costs, cost recovery efforts and recognition Overall, MNR spent approximately $30 to $40 Million on providing interim service and rebuilding the Port Jervis Line. AECOM staff continued to support MTA and Metro-North to prepare supporting documentation for FEMA Insurance Claims Metro-North and AECOM received ACEC Diamond Award ACEC National Engineering Excellence Recognition Award

49 Thank You

Port Jervis Line Planning for the Future

Port Jervis Line Planning for the Future Port Jervis Line Planning for the Future Port Jervis Line Planning for the Future July 18, 2013 Metro-North Railroad 1 1 What Is The Port Jervis Line? 60 mile extension in New York State of NJT s Main/

More information

Appendix C: Port Jervis Line Capacity Improvements Analysis. Technical Memorandum 2: Passing Siding Alternative

Appendix C: Port Jervis Line Capacity Improvements Analysis. Technical Memorandum 2: Passing Siding Alternative Appendix C: Port Jervis Line Capacity Improvements Analysis Technical Memorandum 2: Passing Siding Alternative January 2018 TABLE OF CONTENTS 1. Introduction... 1 2. Passing Sidings: Locations and Components...

More information

Port Jervis Line Service Strategy Report. Appendix C: Port Jervis Line Capacity Improvements Analysis

Port Jervis Line Service Strategy Report. Appendix C: Port Jervis Line Capacity Improvements Analysis Port Jervis Line Service Strategy Report Appendix C: Port Jervis Line Capacity Improvements Analysis January 2018 TABLE OF CONTENTS Introduction... 1 1. Future PJL Service... 1 2. Project Alternatives...

More information

W. Tobey Ritz MTA Metro-North Railroad, Chief Engineer Capital Engineering New York/New York

W. Tobey Ritz MTA Metro-North Railroad, Chief Engineer Capital Engineering New York/New York What have we learned about future emergency preparedness from Irene and Sandy W. Tobey Ritz MTA Metro-North Railroad, Chief Engineer Capital Engineering New York/New York Metro North Railroad Storm Surge

More information

Bethel Bank Stabilization

Bethel Bank Stabilization Bethel Bank Stabilization Condition of Improvements 30 December 2014 Bethel Bank Stabilization, Alaska (CWIS No. 012314, 075440) Authorization Public Law 99-662, under Section 202, 17 November 1986, as

More information

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc.

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc. ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975 Source: Hey and Associates, Inc. DEFINITION A bridge or culvert crossing installed across a stream or watercourse for short-term

More information

NCDOT Overview. Nick Tennyson, Chief Deputy Secretary March 4, 2015

NCDOT Overview. Nick Tennyson, Chief Deputy Secretary March 4, 2015 NCDOT Overview Nick Tennyson, Chief Deputy Secretary March 4, 2015 Overview Major Functions of DOT Board of Transportation Highway System Overview Construction- Road Building Process Operations and Maintenance

More information

Port Jervis Line Service Strategy Report

Port Jervis Line Service Strategy Report Port Jervis Line Service Strategy Report January 2018 TABLE OF CONTENTS Executive Summary... 1 Introduction... 4 Chapter 1: Background... 5 1.1 Physical Characteristics of the PJL... 5 1.2 Rail Service

More information

2017 MNR RIDERSHIP REPORT APPENDIX

2017 MNR RIDERSHIP REPORT APPENDIX 2017 MNR RIDERSHIP REPORT APPENDIX List of Ridership Tables in Appendix Table 1: Table 2: Table 3: Table 4: Table 5: Table 6: Table 7: Table 8: Table 9: Table 10: Table 11: 2017 Annual Ridership Summary

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Dat e: August 2018 March Update Lemm restoration contract awarded to ICI Construction on March 2nd Contractor began mobilization on March 5th

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Date: August 2018 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main

More information

Section 5 Specification 5.22 Supply and Install Smooth Wall Steel Pipes TABLE OF CONTENTS

Section 5 Specification 5.22 Supply and Install Smooth Wall Steel Pipes TABLE OF CONTENTS TABLE OF CONTENTS 5.22 SUPPLY AND INSTALL SMOOTH WALL STEEL PIPES... 1 5.22.1 GENERAL... 1 5.22.2 MATERIALS... 1 5.22.2.1 Culvert Material... 1 5.22.2.2 Material for Bedding, Backfill and Sealing... 1

More information

SUWANNEE RIVER WATER MANAGEMENT DISTRICT INVITATION TO BID NO. 17/ AE POT SPRINGS RESTORATION PROJECT. Addendum #1 October 11, 2018

SUWANNEE RIVER WATER MANAGEMENT DISTRICT INVITATION TO BID NO. 17/ AE POT SPRINGS RESTORATION PROJECT. Addendum #1 October 11, 2018 SUWANNEE RIVER WATER MANAGEMENT DISTRICT INVITATION TO BID NO. 17/18-037 AE POT SPRINGS RESTORATION PROJECT Addendum #1 October 11, 2018 Due to impacts of Hurricane Michael and the closure of District

More information

North Umpqua Hydroelectric Project (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form

North Umpqua Hydroelectric Project (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # CW2-3 Priority Ranking Med Locator Information/GPS Lat: Long: Impact Rating 3 Start Project Development: Clearwater 2 Risk Rating

More information

Description. Installation and Implementation Requirements

Description. Installation and Implementation Requirements Earth Dike SC-6 Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description Structure that prevents erosion by intercepting, diverting, and conveying surface run-on (storm water

More information

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013 United States Department of Agriculture Natural Resources Conservation Service Denver Federal Center Building 56, Room 2604 P.O. Box 25426 Denver, CO 80225 720-544-2818-OFFICE alton.albin@co.usda.gov Flood

More information

VENTURA RIVER 1 LEVEE SYSTEM VENTURA COUNTY, CALIFORNIA NLD ID #

VENTURA RIVER 1 LEVEE SYSTEM VENTURA COUNTY, CALIFORNIA NLD ID # VENTURA RIVER 1 LEVEE SYSTEM VENTURA COUNTY, CALIFORNIA NLD ID # 380510086 PERIODIC INSPECTION REPORT NO 1 GENERALIZED EXECUTIVE SUMMARY 8 JUNE 2012 FINAL RATING: MINIMALLY ACCEPTABLE FINAL RATING DATE:

More information

Climate Change: What It Means for Transportation Infrastructure

Climate Change: What It Means for Transportation Infrastructure Climate Change: What It Means for Transportation Infrastructure Tropical Storm Irene Great Flood of 2010 Michael P. Lewis RIDOT Director AASHTO President Hurricane Sandy The Issues for Rhode Island Sea

More information

Town of Aurora Stream Management Master Plan PUBLIC INFORMATION CENTRE May 1 st, 2018

Town of Aurora Stream Management Master Plan PUBLIC INFORMATION CENTRE May 1 st, 2018 Town of Aurora Stream Management Master Plan PUBLIC INFORMATION CENTRE May 1 st, 2018 Your comments are encouraged and appreciated, as this will provide us an opportunity to address project issues and

More information

Parks and Open Space 5201 St. Vrain Road Longmont, Colorado Fax:

Parks and Open Space 5201 St. Vrain Road Longmont, Colorado Fax: Parks and Open Space 5201 St. Vrain Road Longmont, Colorado 80503 303.678.6200 Fax: 303.678.6177 www.bouldercounty.org HALL RANCH 2 ACCESS ROAD REPAIRS Project Summary for Limited Impact Special Use Review

More information

FHWA Emergency Relief Program. Emergency Relief Program

FHWA Emergency Relief Program. Emergency Relief Program FHWA Jeff Horton, Area Engineer FHWA Washington Division Hurricane Katrina - 2005 1 Loma Prieta, CA Earthquake -1989 SR 530 Oso Landslide - 2014 Skagit River Bridge Collapse - 2013 2 Statute 23 U.S. Code

More information

Commercial Portfolio

Commercial Portfolio Commercial Portfolio Entire School District - $21,475,490 FLOODING The flood of 2016 strikes Baton Rouge and floods 26 campuses in a local parish. INSPECTION Guarantee inspects buildings and sites affected,

More information

Arkansas Transportation Report

Arkansas Transportation Report Arkansas Transportation Report October 2017 Arkansas River traffic continues to make up ground Through the first eight months of 2017, barge activity on the Arkansas River continues to make up ground after

More information

Climate Change Resilience and the Vermont Agency of Transportation

Climate Change Resilience and the Vermont Agency of Transportation Climate Change Resilience and the Vermont Agency of Transportation Gina Campoli, Environmental Policy Manager Vermont Agency of Transportation Flooding, Vulnerability and Risk Oh My! AASHTO s 21 st Century

More information

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan)

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan) A. B. Brown History of Construction 40 CFR 257.73 (c) (i.) (ii.) (iii.) Owner Name: Southern Indiana Gas and Electric Company dba Vectren Power Supply Owner Address: One Vectren Square, PO Box 209, Evansville,

More information

(1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options)

(1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options) Sub-sector Guideline: (1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options) Basic Concept A. General Concept Climate change will increase

More information

Mayor and Council Tony Seibert, Drainage Engineer Waechter Creek Culvert Emergency Repair at Simpson Road Extension

Mayor and Council Tony Seibert, Drainage Engineer Waechter Creek Culvert Emergency Repair at Simpson Road Extension SS 1~A ABBOTSFORD Report No. ENG 23-2014 COUNCIL REPORT Regular Committee March 14,2014 File No: 5330-30 To: From: Subject: Mayor and Council Tony Seibert, Drainage Engineer Waechter Creek Culvert Emergency

More information

Retaining Wall Replacement along Theodore Fremd Avenue at Blind Brook

Retaining Wall Replacement along Theodore Fremd Avenue at Blind Brook Retaining Wall Replacement along Theodore Fremd Avenue at Blind Brook City of Rye Westchester County City Council Public Meeting Presentation September 16, 2009 Presentation Outline Project Overview Existing

More information

Jeffrey D. Knueppel, P.E. General Manager. Robert L. Lund, Jr., P.E. Assistant General Manager EM&C

Jeffrey D. Knueppel, P.E. General Manager. Robert L. Lund, Jr., P.E. Assistant General Manager EM&C Accelerated Design-Build Replacement of SEPTA s Crum Creek Viaduct Jeffrey D. Knueppel, P.E. General Manager Robert L. Lund, Jr., P.E. Assistant General Manager EM&C Key Presentation Take-Aways NEED TO

More information

Appendix D - Evaluation of Interim Solutions

Appendix D - Evaluation of Interim Solutions Appendix D - Evaluation of Interim Solutions D.1 Introduction The implementation of long-term improvements is projected to take 5 to 8 years. To reduce the number of years of flooding impacts, the partner

More information

Temporary Stream Crossing

Temporary Stream Crossing Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

Temporary Stream Crossing

Temporary Stream Crossing Temporary Stream Crossing NS-4 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution

More information

REGIONAL CONSTRUCTION STANDARDS

REGIONAL CONSTRUCTION STANDARDS REGIONAL CONSTRUCTION STANDARDS SIXTH EDITION Publication Update 6.5 (Full Committee Approved Proposed Revision 6.5 Storm Sewer Joint Wrap - Section 302 As Publication Update 6.5) March 27, 2018 Copyright

More information

CWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending April 20, 2013

CWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending April 20, 2013 CWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending April 20, 2013 RIVER DIVERSION SEGMENT This week on the River Diversion, Ducworks completed the steel pipe installation below the waterline elevation.

More information

Work Group Discussion Guidance

Work Group Discussion Guidance Infrastructure Work Group Discussion Guidance Lead Work Group Member: Agency or Department: Additional Departments/Organizations Identified Please list any contact information for the departments or organizations

More information

APPENDIX B PROJECT DESCRIPTION AND ALTERNATIVE ANALYSIS

APPENDIX B PROJECT DESCRIPTION AND ALTERNATIVE ANALYSIS APPENDIX B PROJECT DESCRIPTION AND ALTERNATIVE ANALYSIS INTRODUCTION The Chesapeake Energy Center (Station), owned and operated by Virginia Electric and Power Company dba Dominion Virginia Power (Dominion),

More information

B.C. MINIST RY OF TRANSPORTATION. Maintenance Specification Chapter FLOOD CONTROL AND WASHOUT RESPONSE

B.C. MINIST RY OF TRANSPORTATION. Maintenance Specification Chapter FLOOD CONTROL AND WASHOUT RESPONSE B.C. MINIST RY OF TRANSPORTATION Maintenance Specification Chapter 7-760 FLOOD CONTROL AND WASHOUT RESPONSE 1. OBJECTIVE To safeguard Highway Users and adjacent properties; to prevent damage to Highways

More information

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND RAIL-HWY PROJECT DEVELOPMENT GUIDE AND New procedures for Railroad Right-of-Entry Agreements & Bid Documents (SP Item 007) Bridge Division Webinar - July 18, 2013 GUIDE TO RAILROAD PROJECT DEVELOPMENT

More information

Kalkaska County Road Commission 1049 Island Lake Road Kalkaska, MI Telephone: Facsimile:

Kalkaska County Road Commission 1049 Island Lake Road Kalkaska, MI Telephone: Facsimile: Kalkaska County Road Commission 1049 Island Lake Road Kalkaska, MI 49646 Telephone: 231.258.2242 Facsimile: 231.258.8205 The Kalkaska County Road Commission is an Equal Opportunity Provider and Employer

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

St. Anthony Falls I-35W Bridge Replacement. ASHE National Conference June 13, Dustin Thomas, P.E. I-35W Bridge Construction Engineer

St. Anthony Falls I-35W Bridge Replacement. ASHE National Conference June 13, Dustin Thomas, P.E. I-35W Bridge Construction Engineer St. Anthony Falls I-35W Bridge Replacement ASHE National Conference June 13, 2014 Dustin Thomas, P.E. I-35W Bridge Construction Engineer The Former Bridge - 9340 Opened to traffic in 1967 Steel truss bridge

More information

Construction Report. Owner: City of Kissimmee. Project Manager: John Tulak. Prepared By: Infrastructure Engineers, Inc.

Construction Report. Owner: City of Kissimmee. Project Manager: John Tulak. Prepared By: Infrastructure Engineers, Inc. 2014 Construction Report Fall Report Owner: City of Kissimmee Project Manager: John Tulak Prepared By: Infrastructure Engineers, Inc. Prime Contractor: Gibbs and Register, Inc. Engineer: VHB, Inc. 1 of

More information

Mike Sarmento Senior Construction Manager Floodplain Management Program Urban Drainage and Flood Control District

Mike Sarmento Senior Construction Manager Floodplain Management Program Urban Drainage and Flood Control District Mike Sarmento Senior Construction Manager Floodplain Management Program Urban Drainage and Flood Control District Today s Objectives Understanding of the Maintenance Eligibility Program (MEP) Get us all

More information

ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT

ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT August 28, 2017 Please find the following addendum to the below mentioned BID. Addendum No.: 1 Bid#: 416-15-17-53-2 Project Name: Lower W-15 Area

More information

New York State DOT Adaptation to Climate Change and Extreme Weather. Elisabeth Lennon New York State Department of Transportation

New York State DOT Adaptation to Climate Change and Extreme Weather. Elisabeth Lennon New York State Department of Transportation New York State DOT Adaptation to Climate Change and Extreme Weather Elisabeth Lennon New York State Department of Transportation Union College, January 2014 New York State Transportation is A vast and

More information

Upgrading Rail Lines for Higher Speeds

Upgrading Rail Lines for Higher Speeds Upgrading Rail Lines for Higher Speeds Railroad Infrastructure Diagnosis and Prognosis David E. Staplin, PE University of Nevada Las Vegas, October 16, 2018 Upgrading Rail Lines for Higher Speeds A Perspective

More information

Frequently Asked Questions. Rebuilding After the 2017 Redwood Complex Fire

Frequently Asked Questions. Rebuilding After the 2017 Redwood Complex Fire COUNTY OF MENDOCINO DEPARTMENT OF PLANNING AND BUILDING SERVICES 860 N. Bush Street- Ukiah, California 95482 Telephone 707-234-6650 Fax 707-463-5709 Rebuilding After the 2017 Redwood Complex Fire 1. When

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: CULVERT DESIGN SPECIFIC SUBJECT: COUNTERSINKING AND LOW FLOW CONSIDERATIONS

More information

CSX BRIDGE OVER TENNESSEE RIVER SLOUGH NEAR BRIDGEPORT, ALABAMA BRIDGE REPLACEMENT AND TRACK IMPROVEMENTS. Introduction

CSX BRIDGE OVER TENNESSEE RIVER SLOUGH NEAR BRIDGEPORT, ALABAMA BRIDGE REPLACEMENT AND TRACK IMPROVEMENTS. Introduction CSX BRIDGE 122.6 OVER TENNESSEE RIVER SLOUGH NEAR BRIDGEPORT, ALABAMA BRIDGE REPLACEMENT AND TRACK IMPROVEMENTS AREMA PRESENTATION September 13, 1999 Presented by: Rick Garro, P.E. Assistant Chief Engineer

More information

Rocky Hill. Challenges

Rocky Hill. Challenges Rocky Hill Rocky Hill is located in the southern portion of the Capitol Region. Its land area covers 13.9 square miles with an estimated 2010 Census population of 19,703. Elevation in Rocky Hill ranges

More information

W. W. HAY SEMINAR SERIES. Tower 55 Multimodal Improvements NATIONAL UNIVERSITY RAIL CENTER UNIVERSITY OF ILLINOIS AT URBANA-CHAMPAIGN

W. W. HAY SEMINAR SERIES. Tower 55 Multimodal Improvements NATIONAL UNIVERSITY RAIL CENTER UNIVERSITY OF ILLINOIS AT URBANA-CHAMPAIGN W. W. HAY SEMINAR SERIES NATIONAL UNIVERSITY RAIL CENTER UNIVERSITY OF ILLINOIS AT URBANA-CHAMPAIGN Tower 55 Multimodal Improvements 2015 HDR, Inc., all rights reserved. W. W. HAY SEMINAR SERIES TOWER

More information

LONG ISLAND RAIL ROAD PROCUREMENTS FOR BOARD ACTION. May 26, 2010

LONG ISLAND RAIL ROAD PROCUREMENTS FOR BOARD ACTION. May 26, 2010 LONG ISLAND RAIL ROAD PROCUREMENTS FOR BOARD ACTION May 26, 2010 Page 136 D Long Island Rail Road Subject Department Date Request for Authorization to Award Various Procurements May 26, 2010 Vendor Name

More information

Bridge Replacement Project. Preliminary Hydraulic Study. Lincoln, California BRLS-5089 (021) BRIDGE 19C Mcbean Park Drive at Auburn Ravine

Bridge Replacement Project. Preliminary Hydraulic Study. Lincoln, California BRLS-5089 (021) BRIDGE 19C Mcbean Park Drive at Auburn Ravine Bridge Replacement Project Preliminary Hydraulic Study Lincoln, California BRLS-5089 (021) BRIDGE 19C 0059 Mcbean Park Drive at Auburn Ravine Prepared By: Prepared By: Date 11/25/2014 Thomas S. Plummer

More information

Washington State DOT s Vulnerability Assessment: Asking the Climate Question

Washington State DOT s Vulnerability Assessment: Asking the Climate Question Washington State DOT s Vulnerability Assessment: Asking the Climate Question Paula Hammond, P.E. Secretary of Transportation Dave Dye Deputy Secretary Steve Reinmuth Chief of Staff Infrastructure Adaptation

More information

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section

More information

CEQ s Draft Guidance on the Impacts of Climate Change in NEPA Reviews

CEQ s Draft Guidance on the Impacts of Climate Change in NEPA Reviews CEQ s Draft Guidance on the Impacts of Climate Change in NEPA Reviews Mike Savonis, Alan Summerville, Elizabeth Diller, Chris Evans, Dana Spindler, and Angela Wong October 28, 2015 New CEQ Requirement

More information

Jacksonville Port Authority Blount Island Marine Terminal Rail Improvements Jacksonville, Florida

Jacksonville Port Authority Blount Island Marine Terminal Rail Improvements Jacksonville, Florida Jacksonville Port Authority Blount Island Marine Terminal Rail Improvements Jacksonville, Florida By: Bryan K. Haye, Senior Project Manager; Michael J. Shostak, P.E., Vice President; and Clinton C. Lalla,

More information

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows:

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows: UNION PACIFIC RAILROAD SCOPE OF HYDROLOGIC/HYDRAULIC DESIGN ENGINEERING AND PERMITTING SERVICES FOR SIZING WATERWAY OPENINGS AT NEW AND REPLACEMENT STRICTURES These flood passage criteria were developed

More information

Climate Change Resiliency Program

Climate Change Resiliency Program Climate Change Resiliency Program Presentation to FMCB March 20, 2017 Winter of 2015 -- Winter Resiliency Winter 2015 revealed very disruptive vulnerabilities in MBTA operations Response to Winter 2015

More information

Sustainable Disaster Recovery Within a Dynamic Watershed: A Colorado Flooding Case Study

Sustainable Disaster Recovery Within a Dynamic Watershed: A Colorado Flooding Case Study Sustainable Disaster Recovery Within a Dynamic Watershed: A Colorado Flooding Case Study Jeff Brislawn, AMEC Environment and Infrastructure ASFPM Annual Conference 2014 Presentation Outline The event of

More information

CONTROL OF WORK 1.02 AUTHORITY AND DUTIES OF THE ENGINEER S AUTHORIZED REPRESENTATIVE

CONTROL OF WORK 1.02 AUTHORITY AND DUTIES OF THE ENGINEER S AUTHORIZED REPRESENTATIVE 1.01 AUTHORITY OF THE ENGINEER CONTROL OF WORK A. The work included in the contract is to be done to the complete satisfaction of the Engineer, and the decision of the Engineer as to the true construction

More information

4/12/2016. Partnering to Rebuild after the Oso Landslide. By Janice Fahning, Megan Slater, Jason Smith, and Becki Kniveton

4/12/2016. Partnering to Rebuild after the Oso Landslide. By Janice Fahning, Megan Slater, Jason Smith, and Becki Kniveton Partnering to Rebuild after the Oso Landslide By Janice Fahning, Megan Slater, Jason Smith, and Becki Kniveton 1 SR 530 Slide Emergency Response Phase 2: Reconstruction/Restoration April 29, 2014 to Present

More information

MetroLink Operations 700 South Ewing Street Saint Louis, Missouri

MetroLink Operations 700 South Ewing Street Saint Louis, Missouri Operating Procedure SOP # Date: Page 1 of 10 Classifications: OCC Rail Dispatchers Maintenance of Way - Contractors Other Departments: Real Estate Operation Safety - Risk Management - Engineering & New

More information

SECTION EXCAVATION AND FILL

SECTION EXCAVATION AND FILL SECTION 02315 EXCAVATION AND FILL PART 1 GENERAL 1.01 SUMMARY A. Furnish labor, materials, equipment, and incidentals necessary to perform excavation, backfill, grading, and slope protection required to

More information

Preface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF)

Preface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF) Preface In 2008, the inter-agency Drainage Act & Section 28 Regulations Team (DART) was established by the Ministry of Natural Resources (MNR) and the Ministry of Agriculture, Food and Rural Affairs (OMAFRA)

More information

Missouri River Flood Response Activity

Missouri River Flood Response Activity For the purpose of compliance with the National Environmental Policy Act (NEPA), the categorical exclusions identified in this table are potentially applicable to flood recovery efforts. The following

More information

LOS ANGELES RIVER 7 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID #

LOS ANGELES RIVER 7 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # 3805010078 PERIODIC INSPECTION REPORT NO 1 GENERALIZED EXECUTIVE SUMMARY FINAL SYSTEM RATING: UNACCEPTABLE FINAL RATING DATE: AUGUST 26, 2015 PERIODIC INSPECTION

More information

Appendix A: Project Planning and Development A-1 White Paper on Transit and the Tappan Zee Hudson River Crossing Project

Appendix A: Project Planning and Development A-1 White Paper on Transit and the Tappan Zee Hudson River Crossing Project Appendix A: Project Planning and Development A-1 White Paper on Transit and the Tappan Zee Hudson River Crossing Project Purpose of White Paper White Paper on Transit and the Tappan Zee Hudson River Crossing

More information

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY 31 25 00 EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY A. Erosion and sedimentation control shall be provided by the Contractor for all areas of the site denuded or otherwise disturbed

More information

MTA Metro North Railroad. P&MM Inventory Report Page 115

MTA Metro North Railroad. P&MM Inventory Report Page 115 MTA Metro North Railroad P&MM Inventory Report 2001-2011 Page 115 Mission The Material Management and Storeroom Operations subgroup of the Procurement and Material Management Department, is tasked with

More information

Pipeline Rehabilitation amidst Environmentally Sensitive Location

Pipeline Rehabilitation amidst Environmentally Sensitive Location 523 Pipeline Rehabilitation amidst Environmentally Sensitive Location Steve Bian, P.E. 1, Anna Pridmore, Ph.D. 2, Rudy Loera, M.S., P.E. 3, John Marshall, P.E. 4 1 DC Water, Supervisor, Civil & Structural

More information

Lake Elmo, MN Code of Ordinances STORM WATER AND EROSION AND SEDIMENT CONTROL

Lake Elmo, MN Code of Ordinances STORM WATER AND EROSION AND SEDIMENT CONTROL Lake Elmo, MN Code of Ordinances STORM WATER AND EROSION AND SEDIMENT CONTROL 150.270 STATUTORY AUTHORIZATION. This subchapter is adopted pursuant to the authorization and policies contained in M.S. Chs.

More information

Customer Service and Operations Committee. Board Information Item III-B. October 9, 2014

Customer Service and Operations Committee. Board Information Item III-B. October 9, 2014 Customer Service and Operations Committee Board Information Item III-B October 9, 2014 Major Red Line Construction Page 12 of 58 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Earth Dikes and Drainage Swales

Earth Dikes and Drainage Swales Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

APRIL 2017 MAMARONECK & SHELDRAKE RIVERS NEW YORK FLOOD RISK MANAGEMENT GENERAL REEVALUATION REPORT FOR THE VILLAGE OF MAMARONECK

APRIL 2017 MAMARONECK & SHELDRAKE RIVERS NEW YORK FLOOD RISK MANAGEMENT GENERAL REEVALUATION REPORT FOR THE VILLAGE OF MAMARONECK MAMARONECK & SHELDRAKE RIVERS NEW YORK FLOOD RISK MANAGEMENT GENERAL REEVALUATION REPORT FOR THE VILLAGE OF MAMARONECK APRIL 2017 APPENDIX C4: STRUCTURAL Table of Contents 1.0 STRUCTURAL INTRODUCTION...

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

INTRODUCTION: DESIGN AND CRAFTSMANSHIP:

INTRODUCTION: DESIGN AND CRAFTSMANSHIP: INTRODUCTION: Bridge 9 on Smith Bridge Road was an innovative and historic project. Becoming only the third covered bridge still active in Delaware, its design was meant to replicate the original bridge

More information

Peer Exchange Report Out Emergency Response. Northeast Bridge Preservation Conference Newport, RI 2012

Peer Exchange Report Out Emergency Response. Northeast Bridge Preservation Conference Newport, RI 2012 Peer Exchange Report Out Emergency Response Northeast Bridge Preservation Conference Newport, RI 2012 Group number: 1 Discussion topic: Emergency Response 4 DOTs, 5 Industry First responders are generally

More information

REQUEST FOR CONSTRUCTION BIDS May 23, 2017

REQUEST FOR CONSTRUCTION BIDS May 23, 2017 REQUEST FOR CONSTRUCTION BIDS May 23, 2017 Cambridge Greenway Trail / Railroad Bridge Replacement Flood Mitigation Project 1.0 Project Background A former railroad bridge that currently carries the Cambridge

More information

207 TEMPORARY SEDIMENT AND EROSION CONTROLS

207 TEMPORARY SEDIMENT AND EROSION CONTROLS 2013 Construction and Material Specifications Hydraulics and Environmental Summary Ron Trivisonno, Office of Construction Administration 207 TEMPORARY SEDIMENT AND EROSION CONTROLS This item has been removed

More information

Construction Coordination & Management Planning MassDOT-Highway/MBTA. 495/MetroWest Partnership Briefing July 11, 2018

Construction Coordination & Management Planning MassDOT-Highway/MBTA. 495/MetroWest Partnership Briefing July 11, 2018 Construction Coordination & Management Planning MassDOT-Highway/MBTA 495/MetroWest Partnership Briefing July 11, 2018 Overview The Construction Coordination and Management Planning exercise was a 100-day

More information

Tips with Creation of your Erosion and Sediment Control Plan

Tips with Creation of your Erosion and Sediment Control Plan Tips with Creation of your Erosion and Sediment Control Plan By Chris Droste, CESCO Senior Erosion Control Specialist Westmoreland Conservation District Forming Your Narrative Use the DEP checklist. Page

More information

Presentation Outline

Presentation Outline St. John s Tunnel Rehabilitation A Demonstration of Successful Fast- Track Design and Construction Christopher P. Russell, P.E. Shannon & Wilson Inc., Staff Engineer Gregory R. Fischer, Ph.D., P.E. Shannon

More information

Nomination for Virginia Railway Express 2013 Rail Disaster Drill. Category: Emergency Preparedness- Rail Security Awarding

Nomination for Virginia Railway Express 2013 Rail Disaster Drill. Category: Emergency Preparedness- Rail Security Awarding Nomination for Virginia Railway Express 2013 Rail Disaster Drill Category: Emergency Preparedness- Rail Security Awarding Attachments: 1 Letter from Fairfax Fire and Rescue Introduction Virginia Railway

More information

17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS

17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS 17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS 17.1 Description The work covered by this section of the specifications consists of furnishing all labor, the construction and installation of open storm drain

More information

Statement of Qualification for Port Authority Projects

Statement of Qualification for Port Authority Projects for Port Authority Projects Malick & Scherer, P.C. (M&S), is a multidisciplinary engineering firm providing engineering and surveying services for infrastructure projects throughout New Jersey, New York,

More information

Lessons Learned Meeting Notes

Lessons Learned Meeting Notes EXTERNAL MEMORANDUM Lessons Learned Meeting Notes Distribution Date: April 24, 2017 Date of Meeting: April 19, 2017 Project: Sacramento Wash Crossing at Oatman Highway TRACS No. T0021 01D Federal Project

More information

Suggested Stormwater Management Practices For Individual House Lots

Suggested Stormwater Management Practices For Individual House Lots Suggested Stormwater Management Practices For Individual House Lots These practices are necessary to satisfy the water quantity and water quality criteria of the Rappahannock Stormwater Ordinance. These

More information

SAN GABRIEL RIVER/SAN JOSE CREEK 1 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID #

SAN GABRIEL RIVER/SAN JOSE CREEK 1 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # SAN GABRIEL RIVER/SAN JOSE CREEK 1 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # 3805010052 PERIODIC INSPECTION REPORT NO 1 GENERALIZED EXECUTIVE SUMMARY FINAL SYSTEM RATING: MINIMALLY ACCEPTABLE

More information

Norfolk Southern s Online Rebuild of the Coosa River Bridge

Norfolk Southern s Online Rebuild of the Coosa River Bridge Norfolk Southern s Online Rebuild of the Coosa River Bridge Author: Harold Hal E. Lewis, PE, Vice President, HDR Engineering, Inc. 200 West Forsyth Street, Suite 800, Jacksonville, Florida 32202 Telephone:

More information

Danielle Spila Pennsylvania DOT August 6, 2010

Danielle Spila Pennsylvania DOT August 6, 2010 Danielle Spila Pennsylvania DOT August 6, 2010 2008 - Advisory Committee established October 2009 Action plan developed 42% CO2 reduction below 2000 levels by 2020 52 work plans recommended to Governor

More information

Greenbush Project FAQ's Last Updated: July 26, 2004

Greenbush Project FAQ's Last Updated: July 26, 2004 Greenbush Project FAQ's Last Updated: July 26, 2004 The Service Q: When will service start? A: Service is currently scheduled to start in mid-2006. The exact date has not yet been set. Q: What will the

More information

Bridge Asset Management City of Battle Creek Planning and Projects

Bridge Asset Management City of Battle Creek Planning and Projects Bridge Asset Management City of Battle Creek Planning and Projects Michigan Bridge Conference, March 20, 2013 Gregory B. Rickmar P.E., Public Works Department, City of Battle Creek Alan Halbeisen, P.E.

More information

Bridge Development Update

Bridge Development Update Bridge Development Update Rebecca Curtis, PE Michigan Department of Transportation Bridge Management Engineer 2014 Michigan Bridge Conference Bridge Development Update Load Rating Plan of Corrective Action

More information

Local Flood Hazard Mitigation Program. A framework for hazard mitigation in the NYC West of Hudson Water Supply Watersheds

Local Flood Hazard Mitigation Program. A framework for hazard mitigation in the NYC West of Hudson Water Supply Watersheds Local Flood Hazard Mitigation Program A framework for hazard mitigation in the NYC West of Hudson Water Supply Watersheds Flood Hazard Mitigation Defined 2 2 Presentation Overview Why and how is the NYC

More information

SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY

SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY Ryers Station Improvement Project Robert L. Lund, Jr., PE Assistant General Manager Engineering, Maintenance and Construction Division David J. Sands,

More information

U.S. Landfall Date October 29, miles. Extent of Tropical Storm Force Winds (from Center)

U.S. Landfall Date October 29, miles. Extent of Tropical Storm Force Winds (from Center) D Information Sandy U.S. Landfall Date October 29, 2012 U.S. Landfall Location Strength at U.S. Landfall Sustained Winds at U.S. Landfall Extent of Tropical Storm Force Winds (from Center) Affected Coastal

More information

An information series from the national authority on concrete masonry technology. Drainage swale. (optional) Cap unit. (optional)

An information series from the national authority on concrete masonry technology. Drainage swale. (optional) Cap unit. (optional) Provided by: Brown's Concrete Products Limited An information series from the national authority on concrete masonry technology ROLES AND RESPONSIBILITIES ON SEGMENTAL RETAINING WALL PROJECTS TEK 15-3A

More information

RECOMMENDED PROCEDURES FOR RAILWAY CULVERT INSPECTION

RECOMMENDED PROCEDURES FOR RAILWAY CULVERT INSPECTION RECOMMENDED PROCEDURES FOR RAILWAY CULVERT INSPECTION By: Robert J. Frascella, P.E.; Chairman, AREMA Committee 1, Sub-committee-4 Culverts; Senior Project Manager Railroads; Jacobs Civil Inc. and James

More information

COFFERDAM (no.) CODE 803

COFFERDAM (no.) CODE 803 ILLINOIS URBAN MANUAL PRACTICE STANDARD COFFERDAM (no.) CODE 803 Source: Kane-DuPage Soil and Water Conservation District DEFINITION A cofferdam is a temporary structure within a waterway or body of water

More information