FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT

Size: px
Start display at page:

Download "FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT"

Transcription

1 FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT Department of Public Works Robert B. Boxer, Director

2 PROJECT MODEL PROFESSIONAL SERVICES STUDIES FEASIBILITY CLAIMS 1- PROJECT DEFINITION 2- CONCEPT 3- DESIGN & SPECIFICATIONS 4- ACQUISITION & UTILITIES 5- CONTRACT PACKAGE 6- ADVERTISE & AWARD 7- CONSTRUCTION ADMIN. 8- CLOSEOUT CONSTRUCTION CONTRACTORS 2 FY Capital Improvement Program Mid-Year Status Report

3 PROJECT MODEL CONCEPT DESIGN - CONSTRUCTION 1- PROJECT DEFINITION 2- CONCEPT 3- DESIGN & SPECIFICATIONS 4- ACQUISITION & UTILITIES 5- CONTRACT PACKAGE 6- ADVERTISE & AWARD 7- CONSTRUCTION ADMIN. 8- CLOSEOUT CONCEPT Planning Tasks Feasibility Constructability Budget Estimates Zoning Issues Schedule Public Information RFP Development DESIGN Design Efforts A/E Design Support Q/A-Q/C Analysis Cost Estimates Design Research User Requirements Life Cycle Analysis Maintenance Review Operating Cost Review Bid Package Prep Land Acquisition Public Information CONSTRUCTION Construction Management Contract Admin Change Orders RFIs Payment Applications Schedule Inspections External Agency Issues Safety Issues Quality Control Public Information 3 FY Capital Improvement Program Mid-Year Status Report

4 CAPITAL IMPROVEMENT PROGRAM FY PROJECTED STATUS AS OF Project Accomplishments January 2014 December 2014 CIP Projects W&OD Trail Lighting Sterling Road and Herndon Parkway Intersection Improvements Depot Siding Replacement, Restoration, and Painting Gateway Signs Underway Station Street Improvements Utility Undergrounding Sugarland Heights Storm Drainage Golf Course Stormwater Pond Retrofit Spring Street Utilities Park and Monroe Utility Relocations HMC Garage Emergency Lighting Hillwood Court Streetlights Design Park Avenue Streetlights 4 FY Capital Improvement Program Mid-Year Status Report

5 CAPITAL IMPROVEMENT PROGRAM FY PROJECTED STATUS AS OF Project Accomplishments January 2014 December 2014 (Continued ) CIP Projects Station Street Streetscape Underway Haley Smith Park Concession Building Sanitary Lateral Council Chambers VAV Upgrade Underway Paving Herndon Parkway (Elden Street (south) to Van Buren Street, inner and outer loop and turn lanes) Sterling Road (Herndon Parkway to Rock Hill Rd.) 5 FY Capital Improvement Program Mid-Year Status Report

6 CAPITAL IMPROVEMENT PROGRAM FY PROJECTED STATUS AS OF Project Accomplishments January 2014 December 2014 (Continued ) Non - CIP Projects HMC Minor Office Renovations HPD Access Control Renovations Paving Locust Street (Elden Street to Center Street) Ferndale Avenue (Park Ave. to Lopez Ln.) Third Street (Dranesville Rd. to Monroe St.) 6 FY Capital Improvement Program Mid-Year Status Report

7 CAPITAL IMPROVEMENT PROGRAM PROJECTED PERFORMANCE 7 FY Capital Improvement Program Mid-Year Status Report

8 FY CAPITAL IMPROVEMENT PROGRAM PROJECTED STATUS CIP# PROJECT DESCRIPTION CURRENT EFFORT FUNDING EST ENCUMBR CIP OBJECTIVE EXPECTED ACCOMPLISHMENT 1 Sports Field and Park Improvements Design and Construction $975,000 $50,000 Secure funding and complete design and construction of synthetic turf field Design of synthetic turf field to occur closer to construction funding, which is currently being pursued with Fairfax County. 3 Haley M. Smith Park Design and Construction $230,000 $230,000 Design and construct service facility for park Site plan design is complete and utility work is underway. Bldg. has been ordered with installation expected in spring. 7 Herndon Community Center Phase 5 Feasibility and Concept Phase $95,000 $95,000 Establish Phase 5 expansion feasibility and concept plan, to include cost estimate. 9 Trails to Herndon Metrorail Design $100,000 $100,000 Design of trail to Metro pavilion. Begin studies and establish budget for future expansion project. Design contract award for start of trail design from Worldgate Drive to Metro pavilion to be considered by TC in February. 10 Gateway Signs and Historic Markers Design and Construction 11 East Elden St. - Van Buren to Fairfax County Parkway 12 Vehicular and Pedestrian Access to Herndon Metrorail Station (Bus Bays) 13 Van Buren Street Improvements (Old Spring Street to South town line). $160,000 $160,000 Design and construction of town entrance signs Design $6,300,000 $1,200,000 (VDOT Administered) Design Seven gateway signs to be installed in January. Design consultant has begun work on project design. Survey complete. Project may be developed in phases. VDOT administered project. Public meeting expected this spring. Design $2,100,000 $500,000 Design Bus Bays Design bus bays and drop-off area on Herndon Parkway for future Metro station. RFP process complete and design contract to be considered by TC in February, after VDOT reviw and approval. Survey and Concept $150,000 $150,000 Survey and Concepts Survey work began this month with concept development to follow this summer. 8 FY Capital Improvement Program Mid-Year Status Report

9 FY CAPITAL IMPROVEMENT PROGRAM PROJECTED STATUS CIP# PROJECT DESCRIPTION CURRENT EFFORT FUNDING EST ENCUMBR CIP OBJECTIVE EXPECTED ACCOMPLISHMENT 14 Worldgate Drive Extension Survey and Concept 15 Downtown Streets Improvements ROW & Construction 16 Park-Monroe Intersection Improvements Utility Relocation and Construction $150,000 $150,000 Survey and Concept Develop concept for execution through private redevelopment. Project to be coordinated with the bus bays project. Design contract to be considered by TC in February. $1,145,000 $200,000 ROW and Construction of Phase II $1,600,000 $1,600,000 Utility relocation and construction ROW in progress for Phase II. Utility work in Spring Street completed in Phase II of streetscape construction bid anticipated in summer 2015, pending ROW completion. Utility relocations expected to be completed in February. Construction of intersection improvements is scheduled for bid in March. 17 Elden-Center Streets Intersection Improvements 18 GSA - Major Vehicle/Equip Replacement Design and ROW $1,180,000 $300,000 Design of improvements and ROW acquisition. Design of concepts is underway, with a public meeting expected in spring. Design to continue in 2015, to include initiation of ROW. Project construction to follow removal of temporary fire station, anticipated in Replacement $175,000 $175,000 Purchase two vehicles. Skid steer loader has been purchased. Small refuse packer is on order, expect February delivery. 19 Streetlights Design & Construct $150,000 $100,000 Complete three projects Hillwood Court (colonials) installation complete. Florida Ave project reprogrammed to later years. HPkwy near Cuttermill (cobras) in design, expect spring completion. 20 Storm Drainage Improvements Design $50,000 $50,000 Design one project. Design expected to begin later this fiscal year for Spring Street from Nash to Van Buren. 21 Buildings - Major Maintenance Design & Construct $960,000 $640,000 Design and construct Council chambers glass replacement and 397 HPkwy roof replacement. Council chambers glass replacement of only damaged or degraded panels complete. 397 HPkwy roof replacement contract awarded by TC on Jan. 13, construction expected to begin in March. 9 FY Capital Improvement Program Mid-Year Status Report

10 FY CAPITAL IMPROVEMENT PROGRAM PROJECTED STATUS CIP# PROJECT DESCRIPTION CURRENT EFFORT FUNDING EST ENCUMBR CIP OBJECTIVE EXPECTED ACCOMPLISHMENT 22 Sidewalk and Minor Trails Design & Construct $190,000 $190,000 Design and construct Locust St. sidewalk. Design complete. Land acquisition is underway. Construction to follow in Herndon Pkwy/Van Buren St Intersection Improvements 24 Herndon Pkwy/Sterling Rd Intersection Design & Construct Design & Construct 26 WO&D Trail Crossing Improvements Design & Construct 27 Downtown Utility Relocation Design & Construct $2,900,000 $450,000 Design improvements for Van Buren/HPkwy intersection. $500,000 $500,000 Design and Construct Improvements $245,000 $245,000 Design and Construct Improvements Concept developed and adopted by TC on Oct. 22, Design contract to be considered by TC in February. Design expected in 2015, ROW and utility relocation in 2016, and construction in Intersection improvements constructed in Aug Sidewalk in design for north side of Sterling Rd. Public meeting expected this spring. Construction could occur summer Construction award to be considered by TC on Jan 27 for spring construction. $400,000 $300,000 Construct duct bank Construction of duct bank on Spring Street has been completed. Project to construct duct bank on Station St. is next segment to be constructed. 28 Major Road Repaving Construct $345,000 $345,000 Repave arterial routes Herndon Parkway and Sterling Road paving complete. 29 Park Avenue Improvements Design $495,000 $55,000 Design Improvements Design is underway, with a public meeting expected this spring. ROW to follow, with construction anticipated in General Water Maintenance & Replacement Design & Construct $642,000 $425,000 Construct water mains and install new services. Center and Vine projects are out to bid for spring construction. Second Street reprogrammed to later years. 35 Metrorail Water System Study $158,000 $158,000 Evaluation Study to kickoff in late FY15. Improvements 36 Automated Meter Reading System Design & Construct $650,000 $650,000 Begin automation for commercial meters Anticipate procurement of AMR components through cooperative procurement in FY15 with installation in FY Metrorail - Sewer System Improvements Study $150,000 $150,000 Survey & Evaluation Study to kickoff in late FY FY Capital Improvement Program Mid-Year Status Report

11 FY CAPITAL IMPROVEMENT PROGRAM PROJECTED STATUS CIP# PROJECT DESCRIPTION CURRENT EFFORT FUNDING EST ENCUMBR CIP OBJECTIVE EXPECTED ACCOMPLISHMENT 39 Sewer Main Relining and Manhole Rehabilitation Program 40 Water Tanks and Booster Pump Stations Design & Construct Design & Construct $200,000 $200,000 Manhole rehabilitation and sewer relining for GC main Manhole rehabilitation underway. Main relining in golf course was partially completed and various relining locations. in the summer, and Dulles Place area completed this winter. Center Street and remainder of Golf Course to follow in the spring. $2,800,000 $1,000,000 Evaluate, Design and Construct Spring Knoll tank inspection complete. Bid package for repainting is underway; FY15 bid anticipated. Booster pump study is complete; options to be reviewed for FY16 design. 11 FY Capital Improvement Program Mid-Year Status Report

12 QUESTIONS? 12 FY Capital Improvement Program Mid-Year Status Report

13 Downtown Projects Department of Public Works Robert B. Boxer, Director

14 Downtown Projects Downtown Projects

15 2015 Downtown Projects Temp FS FS 15 Downtown Projects

16 2016 Downtown Projects Temporary Fire Station 16 Downtown Projects

17 2017 Downtown Projects 17 Downtown Projects

18 QUESTIONS? 18 January 21, 2014

19 Dry Utility Relocation Initiative Project Status Summary Town Council & Planning Work Session

20 Master Plan Analysis 20 Dry Utility Relocation Initiative

21 Master Plan Integration Power Infrastructure - Core Backbone (RED)

22 Master Plan Integration Preliminary Development Extensions (BLACK)

23 Additional External Factors VDOT Projects County Projects Utility Company System Enhancement Work Ongoing Private Development Plans 23 Dry Utility Relocation Initiative

24 Additional External Factors Broader Scope 24 Dry Utility Relocation Initiative

25 Additional External Factors VDOT East Elden Road Project

26 Additional External Factors Fairfax County Firehouse Renovation

27 Additional External Factors DVP Elden Street Overhead Circuit Overbuild

28 Additional External Factors Private Development Elden/Monroe Townhomes

29 QUESTIONS? 29 January 21, 2014

ENGINEERING DEPARTMENT

ENGINEERING DEPARTMENT ENGINEERING DEPARTMENT Additional information about the Engineering Department may be obtained by calling Tim Bailey, P.E., Director of Engineering, at (919) 469-4030, through email at tim.bailey@townofcary.org

More information

ENGINEERING DEPARTMENT

ENGINEERING DEPARTMENT ENGINEERING DEPARTMENT ADMINISTRATION Engineering Services/ Traffic and Transportation Engineering Services/ Stormwater Engineering Services/ Utilities Engineering Technical Services Engineering Field

More information

PUBLIC WORKS DEPARTMENT DESIGN & CONSTRUCTION DIVISION OCTOBER 2015 UPDATE

PUBLIC WORKS DEPARTMENT DESIGN & CONSTRUCTION DIVISION OCTOBER 2015 UPDATE PUBLIC WORKS DEPARTMENT DESIGN & CONSTRUCTION DIVISION OCTOBER 2015 UPDATE TJERNE PLACE CHAIN LAKE ROAD TO WOODS CREEK ROAD This project involves extending Tjerne Place from Chain Lake Road to Woods Creek

More information

CITY OF SAFETY HARBOR ENGINEERING

CITY OF SAFETY HARBOR ENGINEERING CITY OF SAFETY HARBOR ENGINEERING The Engineering Department provides the city with technical services including design of construction and maintenance projects, review of development plans, field surveys,

More information

Public Works Department Five Year Capital Improvement Plan FY PROPOSED

Public Works Department Five Year Capital Improvement Plan FY PROPOSED Public Works Department Five Year Capital Improvement Plan FY 2019-2023 PROPOSED Capital Improvement Plan Summary STREET DIVISION PROJECTS 141 Asphalt Sidewalk Replacement Program Funding Source Adopted

More information

Quarterly Transportation Report

Quarterly Transportation Report Prince William County Government Quarterly Transportation Report 2 nd Quarter 2011 Transportation Headlines Contracts Awarded University Blvd. PPTA (Design-Build) Awarded on February 1, 2011 Awarded to

More information

Long-Term Capital Improvement Funding Plan. March 18, 2014 City Council Study Session

Long-Term Capital Improvement Funding Plan. March 18, 2014 City Council Study Session Long-Term Capital Improvement Funding Plan March 18, 2014 City Council Study Session Overview Long-term 10 year view to know what s planned Project Overview Focus on FY 2014-15 and FY 2015-16 Funding Plan

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of April 21, 2007 DATE: April 20, 2007 SUBJECT: Approve the Award of a Contract to Sagres Construction Corp. for the construction of Phase I

More information

STAFF REPORT. Kevin Rohani, P.E. Public Works Director/City Engineer. FY 2017/18 First Quarter Report on the Capital Improvement Program

STAFF REPORT. Kevin Rohani, P.E. Public Works Director/City Engineer. FY 2017/18 First Quarter Report on the Capital Improvement Program STAFF REPORT DATE: November 14, 2017 TO: Bryan Montgomery, City Manager Approved and Forwarded to the City Council FROM: SUBJECT: Kevin Rohani, P.E. Public Works Director/City Engineer FY 2017/18 First

More information

Public Works designs, manages and builds more than $4 billion in construction projects across San Francisco. DOING BID ON OUR PROJECTS. JOIN THE CITY TEAM. BUSINESSwith BUILDINGS PLAYGROUNDS STREET RESURFACING

More information

Modified FY ,100, ,329,791

Modified FY ,100, ,329,791 Retail/North Andrews Gardens Neighborhood Improvement Program Expenses Through FY 4 Modified FY 5 Budget FY 26-21 North Andrews Gardens Neighborhood Improvement Project 21,524,34 22,75,757 --- 6,1, 6 ---

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President Phase 1 Phase 1 Cost Summary Expenditures (Nov 17 thru Apr 18) Total Expenditures (Thru Apr

More information

THANKS TO OUR SPONSORS! Hill International Consulting, Inc.

THANKS TO OUR SPONSORS! Hill International Consulting, Inc. THANKS TO OUR SPONSORS! Hill International Consulting, Inc. CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will

More information

Report to the Dulles Corridor Advisory Committee. Proposed Dulles Toll Road Toll Rate Adjustment. October 2018

Report to the Dulles Corridor Advisory Committee. Proposed Dulles Toll Road Toll Rate Adjustment. October 2018 Report to the Dulles Corridor Advisory Committee Proposed Dulles Toll Road Toll Rate Adjustment October 2018 Purpose The primary purpose of today s briefing is to: review the reasons for periodic adjustments

More information

Fuller /Fuller Heights Road Improvements

Fuller /Fuller Heights Road Improvements Transportation Fuller /Fuller Heights Road Improvements Total Cost - $4.4M Description This project will widen Fuller Road, which is the entrance road serving the Quantico Marine Corps Base, the Town of

More information

Bus Facilities System Infrastructure Rehabilitation

Bus Facilities System Infrastructure Rehabilitation Finance & Administration Committee Action Item III-A September 16, 2010 Bus Facilities System Infrastructure Rehabilitation Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

Public Utilities - Sewer

Public Utilities - Sewer County of Henrico, Virginia Capital Improvement Program FY 2017-18 through FY 2021-22 Fund 51 Enterprise Fund - W&S Request Request Request Request Request Project/Work Phase Priority FY 17-18 FY18-19

More information

ASPK G1801. The following is a status of ongoing road work in the City of Asbury Park. Items in bold indicate the most recent updates.

ASPK G1801. The following is a status of ongoing road work in the City of Asbury Park. Items in bold indicate the most recent updates. MEMORANDUM TO: CC: Michael N. Capabianco, Asbury Park City Manager Mayor John Moor and City Council Members Cindy Dye, City Clerk William McClave, Superintendent of Public Works Frederick Reffetto, Esq.,

More information

Request for Proposals No ; Various On-call Professional Design and Engineering Services Addendum No. 1 Page 2

Request for Proposals No ; Various On-call Professional Design and Engineering Services Addendum No. 1 Page 2 Addendum Number 1 Request for Proposals No. 17-001 Various On-call Professional Design and Engineering Services To all prospective firms under specifications for Request for Proposals (RFP) No. 17-001,

More information

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON APRIL 24, 2017

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON APRIL 24, 2017 TO: CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON APRIL 24, 2017 FROM: SUBJECT: KELLY SCHERR, P. ENG, MBA, FEC MANAGING DIRECTOR, ENVIRONMENTAL & ENGINEERING SERVICES AND CITY ENGINEER CONTRACT AWARD:

More information

Capital Investment Program CAPITAL BUDGET

Capital Investment Program CAPITAL BUDGET Capital Investment Program 2012-2014 CAPITAL BUDGET Table of Contents Page CAPITAL BUDGET FUNDING ALLOCATION 3 S Asset Management Projects Roadway Maintenance 4 Downtown ADA Ramp Upgrades 5 Storm Drain

More information

ENGINEERING 1. Downtown Campus Connection Sidewalk construction and the sidewalk art have been completed. The project has been closed out.

ENGINEERING 1. Downtown Campus Connection Sidewalk construction and the sidewalk art have been completed. The project has been closed out. To: Kathie Grinzinger, City Manager June 30, 2011 From: Randy Chesney, Interim Director DPW/City Engineer Subject: Quarterly Capital Improvement Projects Status Report Second Qr. ENGINEERING 1. Downtown

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May

More information

FLORIDA STATE UNIVERSITY MASTER PLAN 9 General Infrastructure

FLORIDA STATE UNIVERSITY MASTER PLAN 9 General Infrastructure GENERAL INFRASTRUCTURE ELEMENT NOTE: Unless otherwise noted, the goals, objectives and policies contained in this element shall guide development of the Main Campus and Southwest Campus in Tallahassee

More information

Projects Under Construction Relocation of Fire Station #2: moving to near NW corner of 15 th & Kelly, decrease response time by being west of RR,

Projects Under Construction Relocation of Fire Station #2: moving to near NW corner of 15 th & Kelly, decrease response time by being west of RR, Projects Under Construction Relocation of Fire Station #2: moving to near NW corner of 15 th & Kelly, decrease response time by being west of RR, March 14, 2018 groundbreaking, 14-16 months for construction.

More information

Storm Water and Sanitary Sewer

Storm Water and Sanitary Sewer Public Works Department Summary Report on Planned Capital Improvements Storm Water and Sanitary Sewer Introduction Public Works has assembled this summary report to highlight major capital improvements

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,

More information

ENGINEERING DEPARTMENT UPDATE

ENGINEERING DEPARTMENT UPDATE To: Date: Public Works Committee Safety & Public Properties Committee Month ending July 31, 2018 RESIDENTIAL & COMMERCIAL REVIEWS AND PERMITTING A. Summary of Permits Type July Submitted 2018 YTD Submitted

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2016 FEBRUARY 2017 Phase 2 Cost Summary December Expenditures $ 79.6 Million Total Expenditures $ 1.068 Billion

More information

CRYSTAL CITY, POTOMAC YARD, AND PENTAGON CITY TAX INCREMENT FINANCING AREA

CRYSTAL CITY, POTOMAC YARD, AND PENTAGON CITY TAX INCREMENT FINANCING AREA CRYSTAL CITY, POTOMAC YARD, AND PENTAGON CITY TAX INCREMENT FINANCING AREA Our Mission: To provide a supplemental financial mechanism for the revitalization of Crystal City, Potomac Yard, and Pentagon

More information

CITY & COUNTY MANAGER S REPORT APRIL 28, Brainard Drive Relocation

CITY & COUNTY MANAGER S REPORT APRIL 28, Brainard Drive Relocation CIP Status Report.. This is the update for the month of April for Capital Improvement Program (CIP) projects. A financial table is presented for each project under construction shown in the report. The

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF APRIL 30, 2016 JUNE 2016 Phase 2 Cost Summary April Expenditures $ 17.5 Million Total Expenditures $ 739.6 Million Total

More information

Revenues and expenditures increase based on the tax district increase due to increases in real estate assessments in CY 2016 compared to CY 2015.

Revenues and expenditures increase based on the tax district increase due to increases in real estate assessments in CY 2016 compared to CY 2015. CRYSTAL CITY, POTOMAC YARD, AND PENTAGON CITY TAX INCREMENT FINANCING AREA Our Mission: To provide a supplemental financial mechanism for the revitalization of Crystal City, Potomac Yard, and Pentagon

More information

Chesapeake Bay TMDL Action Plan and MS4 Program Update. Presentation to the Herndon Town Council. May 5, 2015

Chesapeake Bay TMDL Action Plan and MS4 Program Update. Presentation to the Herndon Town Council. May 5, 2015 Chesapeake Bay TMDL Action Plan and MS4 Program Update Presentation to the Herndon Town Council May 5, 2015 Overview Quick Background Meeting the Chesapeake Bay Restoration Requirements Draft Chesapeake

More information

Ohlone Community College District

Ohlone Community College District Bond Measure G March 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Closeout Progress

More information

Pinellas County Capital Improvement Program, FY FY2016 Project Summary Report

Pinellas County Capital Improvement Program, FY FY2016 Project Summary Report Function : Transportation Activity : Road & Street Facilities Category : Arterial Roads Pinellas County Capital Improvement Program, FY2011 - FY2016 Project No: 1618 Title: 118th Avenue Expressway Cost

More information

Windshield Inventory of Substandard Buildings within Proposed CRA Village of Palm Springs CONGRESS AVENUE SUB-AREA

Windshield Inventory of Substandard Buildings within Proposed CRA Village of Palm Springs CONGRESS AVENUE SUB-AREA CONGRESS AVENUE SUB-AREA 1195 South Congress Avenue Former Regency Party Rental Warehouse 3.09 acres 2017 Taxable Value = $1,700,000 Second Floor and Rear Warehouse Not Occupiable Florida Building Code/Fire

More information

CM/GC Contracting Lessons Learned from Portland and San Francisco

CM/GC Contracting Lessons Learned from Portland and San Francisco CM/GC Contracting Lessons Learned from Portland and San Francisco Lance Erz, TriMet Robin M Reitzes, SF City Attorney s Office American Public Transportation Association Legal Affairs Seminar February

More information

STEERING COMMITTEE MEETING #6

STEERING COMMITTEE MEETING #6 STEERING COMMITTEE MEETING #6 August 7 th, 2017 Topic: Infrastructure (Sewer & Water, Transportation follow up) 6:00 p.m. Transportation follow up Follow up issues map Transportation plan strategies table

More information

DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS THROUGH

DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS THROUGH RIVERSIDE COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS 2018-19 THROUGH 2022-23 Project Number Stg No. Project

More information

Omaha CSO Program and the South Omaha Industrial Area Lift Station, Force Main and

Omaha CSO Program and the South Omaha Industrial Area Lift Station, Force Main and Omaha CSO Program and the South Omaha Industrial Area Lift Station, Force Main and Gravity Sewer Projects November 16, 2010 Welcome Agenda CSO Program Overview Community Enhancements Project Overview Detours

More information

Quarterly Transportation Report 1 st Quarter 2015 March 10, Thomas Blaser Director Department of Transportation

Quarterly Transportation Report 1 st Quarter 2015 March 10, Thomas Blaser Director Department of Transportation Quarterly Transportation Report 1 st Quarter 2015 March 10, 2015 Thomas Blaser Director Department of Transportation Burwell Rd./Fitzwater Dr. Improvements Brentsville Magisterial District Out of five

More information

Route 7 Corridor Improvements Project Reston Avenue to Jarrett Valley Drive Public Hearing

Route 7 Corridor Improvements Project Reston Avenue to Jarrett Valley Drive Public Hearing Project Reston Avenue to Jarrett Valley Drive Public Hearing Nicholas J. Roper, P.E. District Project Development Engineer Email: nicholas.roper@vdot.virginia.gov Phone: (703)259-1953 Agenda 7:00-7:15

More information

CAPITAL IMPROVEMENT PROGRAM

CAPITAL IMPROVEMENT PROGRAM CAPITAL IMPROVEMENT PROGRAM CITY OF NEW PORT RICHEY PASCO COUNTY, FLORIDA FY 2014/2015 - FY 2018/2019 Presented September 3, 2014 Rob Marlowe, Mayor Judy DeBella Thomas, Deputy Mayor Bill Phillips, Councilman

More information

t 1 Budgeted Expenditure to Date Total Project Cost: $ 1,228,440 $ 1,000,222

t 1 Budgeted Expenditure to Date Total Project Cost: $ 1,228,440 $ 1,000,222 Water Projects Maple Wells Project (CIP No. 0916) Scope of Work: Construction of two municipal supply wells at the Maple Yard (342 Foothill Road) and a pipeline to convey well water to the water treatment

More information

5 YEAR CAPITAL IMPROVEMENT PROGRAM

5 YEAR CAPITAL IMPROVEMENT PROGRAM 5 YEAR CAPITAL IMPROVEMENT PROGRAM 329 City of Hermosa Beach Department of Public Works Capital Improvement Program For Fiscal Years 2015-16 Thru 2019-20 PROJECT NAME FY15-16 1 FY16-17 FY 17-18 FY 18-19

More information

Departments Public Works Department

Departments Public Works Department Departments Public Works Department Public Works REQUEST FOR COUNCIL CONSIDERATION MEETING DATE: August 21, 2017 AGENDA ITEM: CITY GOAL: Discussion: the Installment of the Staff Work Plan Public Works

More information

Springfield High School Master Plan Presentation Town Hal Meeting 3 Phasing / Traffic and Parking

Springfield High School Master Plan Presentation Town Hal Meeting 3 Phasing / Traffic and Parking 1 3.1 Springfield High School Springfield School District Delaware County - Pennsylvania Master Plan Presentation Town Hall Meeting 3 Phasing / Traffic and Parking December 11th, 2014 2 3.2 Town Hall Meetings

More information

Transportation Update

Transportation Update Transportation Update Projects Underway Norview Avenue About the Project: The Norview Avenue Interchange Improvement Project will eliminate the existing weave movement associated with the on- and off-ramps

More information

Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018

Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018 Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018 2 Phase 2 Cost Summary September Expenditures $ 19.4 Million Total Expenditures $ 1.868

More information

Highway 15 Project Hutchinson, MN

Highway 15 Project Hutchinson, MN Highway 15 Project Hutchinson, MN Adjacent Properties and Businesses Meeting Hutchinson Area Chamber of Commerce 1 Agenda Topic 1) Introduce the project scope 2) Project goals and benefits 3) Project timeline

More information

ENGINEERING UPDATE MAY 16, 2016

ENGINEERING UPDATE MAY 16, 2016 ENGINEERING UPDATE MAY 16, 2016 CRAN BE RRY TO WNSHI P, PENNSYL V ANI A Jason Kratsas, P.E., Director of Engineering 724-776-4806 x 1148 PROJECT: GRANTS, PERMITS & REPORTS Timeline: June through September

More information

January 15, The meeting was called to order at 7:00 p.m. by Mayor Docimo. The meeting was advertised in the following manner:

January 15, The meeting was called to order at 7:00 p.m. by Mayor Docimo. The meeting was advertised in the following manner: The meeting was called to order at 7:00 p.m. by Mayor Docimo. The meeting was advertised in the following manner: A. Posting written notice on the Official Bulletin Board in the Township Municipal Building

More information

MONTGOMERY STREET. Construction Manager at Risk (CMAR) Services

MONTGOMERY STREET. Construction Manager at Risk (CMAR) Services 2 nd PRE-PROPOSAL CONFERENCE March 6, 2015 MONTGOMERY STREET (City Project #02432) Construction Manager at Risk (CMAR) Services PROCUREMENT MARCH 19, 2015 1 Michael Weiss, P.E. City of Fort Worth Project

More information

Town of Brunswick. Tax Increment Financing Districts and TIF Budget

Town of Brunswick. Tax Increment Financing Districts and TIF Budget Town of Brunswick Tax Increment Financing Districts and 2018-19 TIF Budget Downtown Development and Transit Oriented TIF District Molnlycke TIF District Brunswick Landing and Brunswick Executive Airport

More information

DC CLEAN RIVERS PROJECT Northeast Boundary Tunnel and WMATA Coordination. Florida Avenue Site

DC CLEAN RIVERS PROJECT Northeast Boundary Tunnel and WMATA Coordination. Florida Avenue Site District of Columbia Water and Sewer Authority George S. Hawkins, General Manager DC CLEAN RIVERS PROJECT Northeast Boundary Tunnel and WMATA Coordination Florida Avenue Site 1 Background Project Snapshot

More information

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Topics of Presentation 1. Team Introductions 2. Project Overview Location, Aerial View & Site Plan 3. Overall Schedule 4. Sequence

More information

CONSOLIDATED CITY - COUNTY Duval County City of Jacksonville, Florida. Adopted Capital Improvement Program FY

CONSOLIDATED CITY - COUNTY Duval County City of Jacksonville, Florida. Adopted Capital Improvement Program FY CONSOLIDATED CITY - COUNTY Duval County City of Jacksonville, Florida Adopted Capital Improvement Program FY 2012-2016 FY 13-17 ADOPTED CAPITAL IMPROVEMENT PROJECTS FUNDING SOURCE FY 12/13 FY 13/14 FY

More information

APPENDIX E: Capital Programs and Descriptions

APPENDIX E: Capital Programs and Descriptions APPENDIX E: Capital s and Descriptions Number Name Description 1007 Debt Service -General Administers the servicing of Pinellas County public debt. 1008 Reserves Oversees the management and allocation

More information

Strategic Plan Update Plan Update May 24, 2018

Strategic Plan Update Plan Update May 24, 2018 1 Strategic Plan Update 2018-2022 Plan Update May 24, 2018 Town of Brownsburg Strategic Plan In April 2014, the Town Council motioned to adopt the Town of Brownsburg s first ever strategic plan. 2 Purpose

More information

South Sounder Capital Improvements Program

South Sounder Capital Improvements Program Subarea South King/Pierce Primary Mode Commuter Rail Facility Type Infrastructure Improvement Length Date Last Modified July 1, 2016 PROJECT AREA AND REP RESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION

More information

2017 Transportation and Storm Drainage Projects

2017 Transportation and Storm Drainage Projects 2017 Transportation and Storm Drainage Projects Request for Qualifications Pre-Submittal Meeting: Welcome and Introductions Sign-in sheet Meeting Agenda Provide overview of solicitation and selection process

More information

TRANSPORTATION. Governmental Projects

TRANSPORTATION. Governmental Projects TRANSPORTATION Governmental Projects Function: Activity: Category: Transportation Road & Street Facilities Arterial Roads Project No: 1618 Title: 118th Avenue Expressway Cost Center: 841418 Department:

More information

Bid Award for State Street Pedestrian Improvements

Bid Award for State Street Pedestrian Improvements 11.3 TO: FROM: SUBJECT: Kent Studebaker, Chair Members of the Redevelopment Agency Sidaro Sin, Development Project Manager Bid Award for State Street Pedestrian Improvements DATE: April 27, 2015 ACTION

More information

SECTION 7. Public Infrastructure, Facilities and Services. 8Chapter 8 INFRASTRUCTURE ELEMENT

SECTION 7. Public Infrastructure, Facilities and Services. 8Chapter 8 INFRASTRUCTURE ELEMENT SECTION 7 Public Infrastructure, Facilities and Services 8Chapter 8 INFRASTRUCTURE ELEMENT INF-2 CHAPTER 8 Infrastructure Element INTRODUCTION Cupertino s public infrastructure works in tandem with the

More information

Capital Improvement Plan Summary

Capital Improvement Plan Summary City of Chesapeake, Virginia FY 2011-12 Operating Budget Capital Improvement Plan Summary Overview The City Council adopts a five-year Capital Improvement Plan (CIP) for which funds are appropriated for

More information

FY Capital Improvement Program Quarterly Project Status Report 2/5/2014

FY Capital Improvement Program Quarterly Project Status Report 2/5/2014 Capital Improvement Program Quarterly Status Report Q2 2/5/2014 TABLE OF CONTENTS OBJECTIVE SECTION I CIP FY14 PROJECT STATUS SUMMARIES: ACPS SYSTEM-WIDE PROJECTS O RENOVATIONS O CAPACITY O SECURITY O

More information

Gloucester Parkway Extension RFQ Information Meeting

Gloucester Parkway Extension RFQ Information Meeting Gloucester Parkway Extension RFQ Information Meeting May 24, 2013 Tim Hartzell, PE District Project Manager Kevin Reichert, PE APD Project Manager and POC Topics Project Location & Overview RFQ Information

More information

2016/2017 Organizational Chart. Effective 7/1/2016 Budgeted 29 FTE Positions Budgeted 1 Part-Time Position Budgeted 4 Intern Positions

2016/2017 Organizational Chart. Effective 7/1/2016 Budgeted 29 FTE Positions Budgeted 1 Part-Time Position Budgeted 4 Intern Positions 2016/2017 Organizational Chart Effective 7/1/2016 ed 29 FTE Positions ed 1 Part-Time Position ed 4 Intern Positions Ricardo Sandoval Administrative Secretary (1) Transportation/Land Development Project

More information

Project # Project Title Page #

Project # Project Title Page # WATER UTILITY City of Virginia Beach, Virginia Fiscal Years 21-11 through 215-16 Capital Improvement Program Alphabetical Project Index Project # Project Title Page # Water Utility 5255 Automated Mobile

More information

COMMUNITY BOARD EIGHT

COMMUNITY BOARD EIGHT SECOND AVENUE SUBWAY PROJECT COMMUNITY BOARD EIGHT PROJECT UPDATE February 15, 2011 SECOND AVENUE SUBWAY - PHASE 1 Scope: Tunnels from 92 nd St to 63 rd St Stations at 96 th St, 86 th St, 72 nd St and

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASES 1 AND 2 AS OF SEPTEMBER 30, 2014 November 2014 0 Phase 1 Cost Summary September Expenditures $ 2.5 Million Total Expenditures

More information

Proposed Southside St. Petersburg Community Redevelopment Plan

Proposed Southside St. Petersburg Community Redevelopment Plan Proposed Southside St. Petersburg Community Redevelopment Plan Proposed Southside St. Petersburg Community Redevelopment Planning Area City Council Resolution 2012-416 (September 6, 2012) Request feedback

More information

ENGINEERING DEPARTMENT. Provide engineering and public improvements in the most economical manner.

ENGINEERING DEPARTMENT. Provide engineering and public improvements in the most economical manner. ENGINEERING DEPARTMENT MISSION STATEMENT: Provide engineering and public improvements in the most economical manner. The Engineering Department performs the following services to maintain and improve the

More information

FY Capital Improvement Program Quarterly Project Status Report 3/31/2014

FY Capital Improvement Program Quarterly Project Status Report 3/31/2014 FY 2014 Capital Improvement Program Quarterly Status Report Q3 3/31/2014 TABLE OF CONTENTS OBJECTIVE SECTION I CIP FY14 PROJECT STATUS SUMMARIES: ACPS SYSTEM-WIDE PROJECTS O RENOVATIONS O CAPACITY O SECURITY

More information

Introduction 1. CIP Development Process 2. How to Use This Document 2. Summary of Construction Activities 2

Introduction 1. CIP Development Process 2. How to Use This Document 2. Summary of Construction Activities 2 TABLE OF CONTENTS Introduction 1 CIP Development Process 2 How to Use This Document 2 Summary of Construction Activities 2 Summary of Projects by Fund General Fund (001) 3 Summary of Projects by Fund Stormwater

More information

ALBEMARLE COUNTY SERVICE AUTHORITY

ALBEMARLE COUNTY SERVICE AUTHORITY AGENDA TITLE: Rivanna Water & Sewer Authority (RWSA) Monthly Update STAFF CONTACT(S)/PREPARER: Gary O Connell, Executive Director AGENDA DATE: February 16, 2017 CONSENT AGENDA: Informational ATTACHMENTS:

More information

City Council Work Session Handouts. April 24, 2017

City Council Work Session Handouts. April 24, 2017 City Council Work Session Handouts April 24, 2017 I. Review and Discuss Zoning File 17-08 II. Review and Discuss Zoning File 17-09 III. IV. Review and Discuss the Public Safety Campus Update Review and

More information

Report to the Zone Commissioners Design and Construction Projects for Calendar Year 2009 GENERAL

Report to the Zone Commissioners Design and Construction Projects for Calendar Year 2009 GENERAL Zone 4 Report to the Zone Commissioners Design and Construction Projects for Calendar Year 2009 By Dusty Williams, General Manager-Chief Engineer January 2010 GENERAL: Throughout the District (all Zones)

More information

APPENDIX E: Capital Programs and Descriptions

APPENDIX E: Capital Programs and Descriptions APPENDIX E: Capital s and Descriptions Pinellas County Number Name Description 1007 Debt Service -General Administers the servicing of Pinellas County public debt. 1008 Reserves Oversees the management

More information

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017 Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.

More information

ENGINEERING DEPARTMENT

ENGINEERING DEPARTMENT ENGINEERING DEPARTMENT CITY OF PARKLAND CITYWIDE MOBILITY UPDATE OCTOBER 21, 2015 CITYWIDE MOBILITY UPDATE Introduction and Purpose Provide update on the recommended projects from the Citywide Mobility

More information

SPRINGBROOK 2017 Offsite Levies

SPRINGBROOK 2017 Offsite Levies SPRINGBROOK 2017 Offsite Levies DETAILED CALCULATIONS REPORT BYLAW No. 2017/25 SCHEDULE A December 2017 RDC 2398 Final Version Table of Contents Springbrook 2017 Offsite Levies 2017 Detailed Calculations

More information

Capital Improvement Plan

Capital Improvement Plan Capital Improvement Plan 2015 2019 Santa Fe Streetscape, Santa Fe looking East (Photo courtesy of Olsson Associates) Capital Improvement Plan Projects TABLE OF CONTENTS Page Active Lifestyles 9 Lone Elm

More information

Honorable Mayor and City Council, Project Management Team c/o Jeff Hulsether, PE City Engineer

Honorable Mayor and City Council, Project Management Team c/o Jeff Hulsether, PE City Engineer MEMORANDUM TO: FROM: Honorable Mayor and City Council, Project Management Team c/o Jeff Hulsether, PE City Engineer Scott D. Hedlund, PE, PMP DATE: RE: Monthly Project Status Update SEH No. BRDMN 131759

More information

Wastewater System Financial Plan. For the Corporation of the City of Thunder Bay

Wastewater System Financial Plan. For the Corporation of the City of Thunder Bay Wastewater System Financial Plan For the Corporation of the City of Thunder Bay Prepared January 2015 City of Thunder Bay 500 Donald Street East PO Box 800 Thunder Bay, Ontario, Canada P7C 5K4 Contents

More information

The Municipality of Leamington

The Municipality of Leamington The Five Energy Conservation and Demand Management Plan July, 214 Table of Contents Page # Section 1- Introduction 1.1 Background... 3 1.2 Purpose... 3 1.3 Approach... 4 Section 2- Our Organization 2.1

More information

The Municipality of Leamington

The Municipality of Leamington The Five Energy Conservation and Demand Management Plan July, 214 Table of Contents Page # Section 1- Introduction 1.1 Background... 3 1.2 Purpose... 3 1.3 Approach... 4 Section 2- Our Organization 2.1

More information

The Year Ahead: ARLINGTON COUNTY, VIRGINIA

The Year Ahead: ARLINGTON COUNTY, VIRGINIA The Year Ahead: ARLINGTON COUNTY, VIRGINIA Locality Information Upcoming A&E Contracts- Multimodal Annual Services On-Call Contract Renewal: Planning Complete Streets Engineering and Design Bicycle and

More information

WHEREAS, a new Global Headquarters has the potential to add to the City's

WHEREAS, a new Global Headquarters has the potential to add to the City's NOVEMBER 8, 2017 17-534 RESOLUTION CARRIED 6-1P LOST LAID OVER WITHDRAWN PURPOSE: APPROVE PROPOSED TERMS AND CONDITIONS FOR THE SALE OF A PORTION OF LAKESHORE MUNICIPAL GOLF COURSE AND DEVELOPMENT AGREEMENT

More information

Operational Analysis of Dulles Toll Road Ramps to Tysons. Board Transportation Committee Meeting September 17, 2013

Operational Analysis of Dulles Toll Road Ramps to Tysons. Board Transportation Committee Meeting September 17, 2013 Operational Analysis of Dulles Toll Road Ramps to Tysons Board Transportation Committee Meeting September 17, 2013 Seyed Nabavi Fairfax County Department of Transportation 1 Agenda Overview & Assumptions

More information

Wilmette - Background

Wilmette - Background Reducing Basement Backups through Intergovernmental Cooperation and Design-Build Presented By Michael N. Young, P.E. Brigitte Ann Berger, P.E. Wilmette - Background North Shore Suburb of Chicago 5 Square

More information

Presentation for Business Opportunities & Entrepreneurial Training Summit

Presentation for Business Opportunities & Entrepreneurial Training Summit Welcome to the Presentation for Business Opportunities & Entrepreneurial Training Summit October 9, 2018 Ned Carey, C.M. Chief - Division of Administration & Performance Management Safety Management System

More information

CODE CONSOLIDATION PHASE II SUMMARY OF CHANGES Effective February 1, 2011, Ordinance s

CODE CONSOLIDATION PHASE II SUMMARY OF CHANGES Effective February 1, 2011, Ordinance s CODE CONSOLIDATION PHASE II SUMMARY OF CHANGES Effective February 1, 2011, Ordinance 2010-70s Revisions to Title 2 Administration 2.45 Land Use Advisory Commissions. Twelve individual LUAC chapters were

More information

General Departmental Summary

General Departmental Summary Summer Gravel Road Maintenance General Departmental Summary This quarter has been fairly routine. We have had no water main breaks in the past three months, however we have performed routine maintenance

More information

WATER AND SEWER INFRASTRUCTURE PROGRAMS

WATER AND SEWER INFRASTRUCTURE PROGRAMS Arlington County, Virginia WATER AND SEWER INFRASTRUCTURE PROGRAMS Program Description This program provides and maintains water delivery, sanitary sewer collection, and wastewater treatment systems that

More information

APPENDIX E: Capital Programs and Descriptions

APPENDIX E: Capital Programs and Descriptions APPENDIX E: Capital s and Descriptions Pinellas County Number Name Description 1007 Debt Service -General Administers the servicing of Pinellas County public debt. 1008 Reserves Oversees the management

More information

Route 7 Widening Project Project No , P101, R201, C501 UPC No January 15, a.m. NOVA District Building

Route 7 Widening Project Project No , P101, R201, C501 UPC No January 15, a.m. NOVA District Building PROJECT SHOWING MINUTES Route 7 Widening Project January 15, 2013 10 a.m. NOVA District Building Overview / Welcome: Michael Gleasman, PE, Area Construction Engineer (VDOT) Overview: A question and answer

More information

Norwood High Service Pump Replacement

Norwood High Service Pump Replacement T E C H N I C A L M E M O R A N D U M 737-02 NORWOOD HIGH SERVICE PUMP REPLACEMENT 737-02 Norwood High Service Pump Replacement PREPARED FOR: JEA Planning PREPARED BY: Joshua M. Brown DATE: February 2017

More information