1 Exhibit A Scope of Services and Deliverables Attachment to MnDOT Contract No. for Project Name Project # 16-TZ dated Scope of Services includes: Programming / Schematic Design Phase Design Development Phase Bidding Phase Services Construction Administration Services MnDOT Contract No. TABLE OF CONTENTS 1. CONSULTANT S RESPONSIBILITIES GENERAL A. DEFINITIONS B. STANDARD OF CARE C. THE CONSULTANT S BASIC SERVICES D. SCHEDULE FOR PERFORMANCE OF THE CONSULTANT S SERVICES E. APPROVAL OF GOVERNMENTAL AUTHORITIES F. ESTIMATES OF THE COST OF THE WORK G. MINNESOTA SUSTAINABLE BUILDING GUIDELINES H. MEETINGS I. DELIVERABLES REVIEW AND CONSULTANT RESPONSES J. SPECIAL SERVICES 2. MnDOT s OWNER RESPONSIBILITIES GENERAL A. DEFINITIONS B. PROJECT INFORMATION C. REVIEWS AND RESPONSES D. NOTICE OF DEFECTS E. COMMUNICATION 3. PROGRAMMING / SCHEMATIC DESIGN PHASE A. FINAL PROGRAM REQUIREMENTS B. MNDOT S SCHEMATIC DESIGN RESPONSIBILITIES C. MECHANICAL, CIVIL, WATER SERVICES AND ELECTRICAL ENGINEERS MEETING D. CONSULTANT S PROGRAMMING / SCHEMATIC DESIGN RESPONSIBILITIES E. PROGRAMMING / SCHEMATIC DESIGN DELIVERABLES 4. DESIGN DEVELOPMENT PHASE A. THE DESIGN DEVELOPMENT PHASE B. MNDOT S DESIGN DEVELOPMENT RESPONSIBILITIES C. CONSULTANT S DESIGN DEVELOPMENT RESPONSIBILITIES D. BUILDING CODE REVIEW AND SUBMITTALS E. DESIGN DEVELOPMENT PHASE DELIVERABLES 5. CONSTRUCTION DOCUMENT PHASE A. THE CONSTRUCTION DOCUMENT PHASE B. MNDOT S CONSTRUCTION DOCUMENT RESPONSIBILITIES C. CONSULTANT S CONSTRUCTION DOCUMENTS PHASE RESPONSIBILITIES D. THE PROJECT MANUAL E. CONSTRUCTION DRAWINGS F. FINAL ESTIMATE OF THE COST OF THE WORK G. BUILDING CODE REVIEW AND SUBMITTALS H. REVIEW BY MNDOT AND BUILDING USERS I. CONSTRUCTION DOCUMENT PHASE DELIVERABLES 6. BIDDING PHASE SERVICES A. MN/DOT S BIDDING PHASE RESPONSIBILITIES B. CONSULTANT S RESPONSIBILITIES FOR BIDDING ASSISTANCE C. BID OPENING AND AWARD OF CONTRACT D. BIDDING PHASE DELIVERABLES 7. CONSTRUCTION ADMINISTRATION SERVICES A. MnDOT S CONSTRUCTION ADMINISTRATION RESPONSIBILITIES B. CONSULTANT S CONSTRUCTION CONTRACT ADMINISTRATION PHASE RESPONSIBILITIES C. CONSTRUCTION CONTRACT ADMINISTRATION PHASE DELIVERABLES D. CONSULTANT S SCHEDULE FOR JOBSITE OBSERVATIONS Page 1 of 24

2 1. CONSULTANT S RESPONSIBILITIES GENERAL A. DEFINITIONS 1.1 Consultant used herein shall be comparable to the term Contractor used in the State of Minnesota Professional and Technical Services Contract. a. The term Consultant shall be construed to include the Prime Consultant and its Subconsultants. 1.2 SubConsultant used herein shall be comparable to term SubContractor used in the Professional Technical Services Agreement. B. STANDARD OF CARE The Consultant shall provide the professional services set forth in this Agreement consistent with the professional skill and care ordinarily provided by Design Professionals practicing in the same or similar locality under the same or similar circumstances. The Consultant shall perform its services as expeditiously as is consistent with such professional skill and care and the orderly progress of the Project. C. THE CONSULTANT S BASIC SERVICES shall consist of those described below and include usual and customary Architectural, Landscape Architecture, Cost Estimating and Energy Modeling services and Civil, Structural, Mechanical, Electrical and Water Services Engineering. 1.1 The Consultant shall provide Services as required by the Project Manual Document A201 State of Minnesota Addition for the Project, which is hereby incorporated into this Contract where it delineates the Services, Roles, Actions and Authority of the Architect in: Article 1 General Provisions Article 7 Changes in the Work Article 2 Owner Article 9 Payments and Completion Article 3 Contractor Article 12 Uncovering and Correction of Work Article 4 Architect Article 13 Miscellaneous Provisions Article 5 Subcontractors Article 14 Termination or Suspension of the Contract Article 6 Construction by Owner or by Separate Contractors Article 15 Claims and Dispute Resolution Page 2 of 24

3 1.2 SubConsultants: a. For additional requirements, refer to State of Minnesota Professional and Technical Services Contract Article 14. b. Consultant is responsible for coordinating and managing the work of its SubConsultants. The use of SubConsultants does not relieve the Consultant from its obligation to perform the services specified in this contract. 1.3 Final Estimates: Consultant s Basic Services include detailed cost estimating services, provided either in-house or by a Sub-consultant. 1.4 The Consultant s Basic Services include Services to revise the Project and to rebid the Project if required to meet MnDOT s budget. 1.5 The Consultant shall arrange for the reproduction of all documents required for Deliverables, MnDOT s internal reviews, and for the Consultant s use for the Project. The cost of reproduction will be reimbursed as scheduled in the Consultant s contract. D. SCHEDULE FOR PERFORMANCE OF THE CONSULTANT S SERVICES 1.1 For additional requirements, refer to State of Minnesota Professional and Technical Services Contract Articles 5, 9, 15, 20 and The Consultant shall submit for MnDOT s approval a Project Design Schedule for the performance of the Consultant s services. The time limit established for the Project Design shall not, except for reasonable cause, be exceeded by the Consultant. Any unreasonable delay may be justification for termination of the Consultant s contract. 1.3 The Project Design Schedule shall outline anticipated completion dates for Phases of the Design work and incorporate review time for MnDOT and governmental approvals as required to meet the time limit for the Project Design. 1.4 With MnDOT s approval, the Consultant shall adjust the interim schedule, if necessary, to meet the time limit, as the Project proceeds. E. APPROVAL OF GOVERNMENTAL AUTHORITIES 1.1 The Consultant shall, at appropriate times, contact the governmental authorities required to approve the Construction Documents and the entities providing utility services to the Project. In designing the Project, the Consultant shall respond to applicable design requirements imposed by such governmental authorities and by such entities providing utility services. 1.2 The Consultant shall [assist in filing] [file] documents with the Department of Labor and Industry and other governmental authorities having jurisdiction over the Project. [including but not limited to:] a. Environmental Protection Agency (EPA) / Minnesota Pollution Control Agency (MPCA). b. XXXX Watershed District 1.3 The Consultant shall prepare documents in formats required by Department of Labor and Industry for electronic submission. F. ESTIMATES OF THE COST OF THE WORK 1.1 Definitions: a. The Cost of the Work i. The total cost of the General Contract to construct all elements of the Project designed or specified by the Consultant, and including MnDOT s Outbuildings and appurtenances, if any; and shall include contractors general conditions costs, overhead and profit. b. MnDOT s Budget i. The Budget for the Cost of the Work shall be provided to the Consultant. ii. Contract Documents Deliverables resulting in bids within MnDOT s Budget is a requirement of this Contract. Page 3 of 23

4 1.2 Preparation a. Estimates shall be prepared to provide costs of construction anticipated at time of Bid and shall include contingencies for design, bidding and price escalation. b. Preliminary Estimates may be based on current area, volume or similar conceptual estimating techniques and shall be periodically refined to reflect the development of the Design. c. Interim Estimates shall be based on generally-accepted conceptual estimating techniques using industry standard estimating software. d. Draft Final and Final Estimates: Consultant s Basic Services include detailed cost estimating services, provided either in-house or by a SubConsultant using industry standard estimating software. 1.3 MnDOT maintains the right to rely upon the Consultant s Estimates: i. to determine which materials, equipment, component systems and types of construction are included in the Project. ii. to make reasonable adjustments in the program and scope of the Project; iii. to develop Alternates as may be necessary to adjust the estimated Cost of the Work to meet MnDOT s Budget. 1.4 If at any time the Consultant s Preliminary, Interim, Draft Final or Final Estimates of the Cost of the Work exceed MnDOT s budget for the Cost of the Work, the Consultant shall make appropriate and timely recommendations to MnDOT to adjust the Project s size, scope, quality or Budget. a. The Consultant s Basic Services include Services to make such adjustments to the Design Documents. 1.5 It is recognized that the Consultant cannot and does not warrant or represent that bids will not vary from MnDOT s budget for the Cost of the Work or from any estimate of the Cost of the Work or evaluation prepared or agreed to by the Consultant, however, if MnDOT s Budget for the Cost of the Work is exceeded by the lowest bona fide bid, MnDOT may elect to proceed with any of the following: a. Give written approval of an increase in the Budget, b. Terminate this Agreement, c. Authorize rebidding of the Project within a reasonable time, i. The Consultant s Basic Services include Services to rebid the Project to meet MnDOT s budget. d. In consultation with the Consultant, revise the Project program, scope, or quality as required to reduce the Cost of the Work. i. The Consultant, without additional compensation, shall modify the Construction Documents as necessary to comply with MnDOT s budget for the Cost of the Work. ii. The Consultant s modification of the Construction Documents shall be the limit of the Consultant s responsibility under this Article. G. MINNESOTA SUSTAINABLE BUILDING GUIDELINES 1.1 The Consultant shall make recommendations to MnDOT based upon the Minnesota Sustainable Building Guidelines (MSBG) to improve the ongoing performance of the Project towards the lowest lifetime costs and to promote design and operational decisions based on improving environmental, human and economic conditions. H. MEETINGS 1.1 The Consultant shall arrange and attend all Design Meetings, Construction Progress and Preinstallation Meetings and other meetings required by the jurisdiction or MnDOT. a. The Consultant shall timely prepare agendas for these meetings and distribute them to all attendees and to MnDOT prior to the meetings. 1.2 The Consultant shall attend all Pre-bid and Pre-construction Meetings. Page 4 of 23

5 1.3 The Consultant shall prepare Record Minutes and distribute them to all attendees and to MnDOT, timely subsequent to the meetings. I. DELIVERABLES REVIEW AND CONSULTANT RESPONSES 1.1 For additional requirements, refer to State of Minnesota Professional and Technical Services Contract Articles 18 and The Consultant shall provide timely written responses to MnDOT s Review Comments in accordance with the Project Design Schedule. 1.3 The Consultant is responsible to address all MnDOT Review comments and redlines requiring action or response. Consultant Responses shall include: a. Specific, itemized records affirming incorporation of MnDOT comments. b. Consultant s responses regarding MnDOT comments which require further discussion. c. MnDOT comments may not be disregarded without action or response. 1.4 Quality Management Plan (QMP) and Quality Assurance and Quality Control Procedures. 9.1 and 22.1 For additional requirements, refer to State of Minnesota Professional and Technical Services Contract Articles 9 and 22. a. Consultant shall develop a project specific QMP specifying Quality Assurance and Quality Control (QA/QC) activities throughout the duration of the project. b. Consultant must submit the QMP to MnDOT s Project Manager for approval within five business days of Notice to Proceed. c. Consultant will distribute the QMP to all project team members, including SubConsultants. d. Deliverables shall include documentation of QA/QC activities performed for each Phase signed by a Consultant s Representative certifying completion. Insert descriptive verbiage below for additional services required and deliverables and reimbursables. J. SPECIAL SERVICES 1.1 Certified Survey: Consultant shall determine requirements for [and enter into a contract to procure as a reimbursable expense] [and provide as a Basic Service,] a Certified Survey of the property. a. The Consultant shall engage a Land Surveyor licensed by the state of Minnesota and arrange for the preparation of surveys to describe physical characteristics, legal limitations and utility locations for the Site of the Project. The cost of the Surveyor Services will be reimbursed as scheduled in the Consultant s contract. Survey deliverables shall include: b. Written legal property description and boundary survey of the Site. c. Certified Survey indicating: i. existing utilities surrounding the Site ii. existing utilities and structures on the Site iii. topography of the Site 1.2 Geotechnical Report: Consultant shall determine requirements for and [enter into a contract to procure as a reimbursable expense] a Geotechnical Report. 1.3 Wetland Delineation: Consultant shall determine requirements for [and enter into a contract to procure as a reimbursable expense] [and provide as a Basic Service,] a Wetland Delineation of the property. Page 5 of 23

6 2. MnDOT s OWNER RESPONSIBILITIES GENERAL A. DEFINITIONS 1.1 MnDOT as used herein shall be the Minnesota Department of Transportation. a. The Office of Maintenance Building Services Section and its Project Manager shall act as MnDOT s authorized representative where referenced herein. B. PROJECT INFORMATION 1.1 For additional requirements, refer to State of Minnesota Professional and Technical Services Contract Article Requirements and Limitations MnDOT shall provide information in a timely manner regarding requirements and limitations on the Project, not limited to: a. Budget for the Project. b. The time limit established for the Project Design. c. Legal, accounting, contract, Labor Compliance and insurance information required for the Project. d. MnDOT s requirements for mechanical, electrical, civil, voice, data communications, building automation systems, plantings, paving, water services and security systems. e. MnDOT s preferred materials, products, equipment, details and installation requirements, including MnDOT s required Specifications language. f. MnDOT s requirements for energy use and other State agency s requirements for building performance for the Project. g. Contact information for MnDOT personnel and their assignments for this Project. 1.3 Existing Conditions Information: a. Original construction drawings and specifications b. Facilities Condition Assessment Information c. Energy use and system performance records d. Hazardous materials information 1.4 Written Program: MnDOT shall provide MnDOT s objectives, schedule, constraints and criteria, including function, space requirements and relationships, flexibility, expandability, special equipment, systems and Site requirements. a. A statement of priorities and requirements. b. List of spaces including function, size, quantity, relationships, adjacencies and external requirements. c. Vehicle types, Equipment and Personnel Worksheet for each space. d. MnDOT s proposed Outbuildings 1.5 Site Information: MnDOT shall furnish surveys to describe physical characteristics, legal limitations and utility locations for the Site of the Project to include: a. Written legal property description and boundary survey of the Site. b. Certified Survey indicating: i. existing utilities surrounding the Site ii. existing utilities and structures on the Site iii. topography of the Site c. The survey and legal information shall include, as applicable, i. grades and lines of streets, alleys, pavements and adjoining property and structures; Page 6 of 23

7 ii. designated wetlands; adjacent drainage; rights-of-way, restrictions, easements, boundaries and contours of the site; iii. locations, dimensions and necessary data with respect to existing buildings, other improvements and trees; and information concerning available utility services and lines, both public and private, above and below grade, including inverts and depths. d. MnDOT shall make arrangements for and furnish the services of geotechnical engineers, soils conductivity testing, hazardous materials, regulated waste and contaminated soils / groundwater assessments and other investigative services which are reasonably required by the scope of the Project. 1.6 Tests, Inspections and Reports: MnDOT shall furnish tests, inspections and reports on file required by law or the Contract Documents, such as Special Inspections required for structural, mechanical, and chemical tests; and tests for air and water pollution and for hazardous materials. 1.7 Products, Manufacturers and Materials: a. MnDOT will provide Specification language and/or a list of requirements, products, manufacturers and materials to be incorporated into Consultant s Specification Sections 2 thru 48. b. Where Specification language and/or a list of products, manufacturers and materials are provided by MnDOT, no additional products, manufacturers or materials may be included in the Project Manual or approved as Substitutions without approval of MnDOT. 1.8 MnDOT s Vehicles, Equipment and Systems: a. MnDOT shall provide schedules, placement, power and connection requirements of MnDOT s [existing] [new] Equipment [which will be installed] in Project. b. MnDOT shall provide a schedule of Vehicles and turning schematics for vehicles which will be required to access the Site and Building. C. REVIEWS AND RESPONSES 1.1 For additional requirements, refer to State of Minnesota Professional and Technical Services Contract Articles 18 and MnDOT shall provide timely written reviews and responses to Consultant s inquiries and Deliverables in accordance with the Project Design Schedule. 1.3 MnDOT shall provide a written acknowledgement of receipt and review of Deliverables of each Phase which shall include: a. Enumerated general approval of Deliverables as warranted. b. Itemized comments and exceptions to the Deliverables. 1.4 MnDOT shall provide timely written Notice to Proceed with the subsequent Phase. D. NOTICE OF DEFECTS 1.1 For additional requirements, refer to State of Minnesota Professional and Technical Services Contract Articles 18 and MnDOT shall provide prompt written notice to the Consultant if MnDOT becomes aware of any fault or defect in the Deliverables, including errors, omissions or inconsistencies in the Deliverables. E. COMMUNICATION 1.1 MnDOT shall designate a Project Manager to facilitate communications of the Consultant with the Agency, MnDOT Building Services Engineers and the Building Users. 1.2 MnDOT shall endeavor to communicate with the Construction Contractor only through the Consultant about matters arising out of or relating to the Contract Documents and Construction of the Project. Page 7 of 23

8 3. PROGRAMMING / SCHEMATIC DESIGN PHASE A. FINAL PROGRAM REQUIREMENTS The Schematic Design Phase of the Project will establish the final requirements for area and space allocation, and set the quality standards for architectural, civil, water services, structural, mechanical and electrical components and establish the construction cost to meet MnDOT s budget. B. MNDOT S SCHEMATIC DESIGN RESPONSIBILITIES 1.1 Coordinate attendance of MnDOT representatives to all review meetings. 1.2 Solicit and facilitate comments from Building Users. 1.3 Provide input and review. 1.4 Initiate and secure legislative review of Design Deliverables including budget and program, if required. 1.5 Review proposed adjustments to the Project Scope, if required. C. MECHANICAL AND ELECTRICAL ENGINEERS MEETING / CIVIL / WATER SERVICES Before the Mechanical, Civil, Water Services and Electrical Consulting Engineers begin working on the Project they shall meet with MnDOT s Building Services Engineers to review MnDOT s requirements for the design of the mechanical and electrical systems. 1.1 Building Services Engineers shall provide direction regarding air-handling, automated control systems, lamping, security systems and system commissioning requirements. 1.2 Building Services Engineers shall suggest parameters for envelope energy performance, daylighting concepts and applicability of alternative energy sources. D. CONSULTANT S PROGRAMMING / SCHEMATIC DESIGN RESPONSIBILITIES 1.1 The Consultant shall develop a Program for the Project including function, space requirements and relationships, flexibility, expandability, special equipment, systems and Site requirements. OR 1.1 The Consultant shall review MnDOT s program, schedule, budget for the Cost of the Work, Project Site, and alternative approaches to design and construction of the Project, including the feasibility of incorporating environmentally responsible design approaches. a. The Consutant shall prepare a preliminary evaluation of the Owner s program, schedule, budget for the Cost of the Work, Project site, and the proposed project delivery method and other Initial Information, each in terms of the other. 1.2 The Consultant shall consider the relative value of alternative materials, building systems and equipment, together with other considerations based on the program and aesthetics in developing a design for the Project that is consistent with MnDOT s schedule and budget for the Cost of the Work. 1.3 Minnesota Water Conservation Guidelines (Executive Order 11-13): The consultant shall make recommendations to MnDOT to implement water-efficiency best practices based on the EPA's WaterSense at Work. 1.4 Initial Building Code Analysis: The Consultant shall review laws, codes, and regulations applicable to the Project and develop an Initial Building Code Analysis and a report on watershed, planning and zoning issues and other regulatory constraints. 1.5 The Consultant shall prepare: a. Site Design Concepts including MnDOT s proposed outbuildings, vehicle turning schematics, general grading, drainage and retention; water services systems, landscaping, utilities and recommend preferred concepts. b. Building Design Concepts including preliminary materials selections; and recommendations of Page 8 of 23

9 preferred concepts. c. Building Systems Design Concepts for HVAC, Plumbing, Water Services and Electrical Systems. i. Develop initial analysis of envelope energy performance, daylighting concepts and applicability of alternative energy sources including geothermal and solar. ii. Develop initial schematic control systems, lamping, and system commissioning requirements. iii. Investigate applicability of utility company energy rebate programs and water-efficiency best practices. d. Design Concept Narrative description of proposed building systems, including building envelope materials and brief descriptions of structural, mechanical, electrical, and grading/drainage system concepts. e. Preliminary Estimate of Cost of Construction based on Building and Site area. B. PROGRAMMING / SCHEMATIC DESIGN DELIVERABLES The Consultant shall provide electronic (pdf) files of all Deliverables. Provide paper copy drawings and reports in sizes and quantities indicated by the MnDOT. 1.1 Programming Documents a. List of spaces including function, size, quantity, relationships, adjacencies and external requirements. b. Equipment and Personnel Worksheet for each space. OR 1.2 Preliminary evaluation of the Owner s program, schedule, budget. 1.3 Initial Building Code Analysis and report on planning and zoning issues and regulatory constraints. 1.4 Building Systems Design Concepts for HVAC, Plumbing, Water Services and Electrical Systems. a. Analysis of envelope energy performance, daylighting concepts and applicability of alternative energy sources including geothermal and solar. b. Initial schematic control systems, lamping, and system commissioning requirements. c. Report on utility company energy rebate programs and water-efficiency best practices. 1.5 Design Concept Drawings Appropriately scaled as follows: a. Site Design Concepts i. Utilities, Water Services Systems, Grading and Drainage ii. Site Access and Vehicle maneuvering schematics iii. Plantings b. Building Design Concepts i. Floor plan(s) ii. Principal exterior elevations iii. Two building sections iv. Typical exterior wall sections 1.6 Design Concept Narrative 1.7 Preliminary Estimate Cost of Construction 1.8 Meeting Minutes. 1.9 Updated Project Design Schedule for Design Reviews and Consultant Services Quality Management Plan (QMP) documentation of QA/QC activities performed. Page 9 of 23

10 2. DESIGN DEVELOPMENT PHASE A. THE DESIGN DEVELOPMENT PHASE of the Project will commence upon MnDOT s written approval of the Schematic Design Deliverables. 1.1 The Work of this Phase shall incorporate MnDOT s itemized Review comments and shall respond to adjustments required to accommodate budget constraints. 1.2 Deliverables shall illustrate and describe the development of the approved Schematic Design to fix and describe the size and character of the Project as to architectural, structural, water services, mechanical and electrical systems, and such other elements as may be appropriate. 1.3 Deliverables shall include outline specifications to identify major materials and systems and to establish general quality levels. B. MNDOT S DESIGN DEVELOPMENT RESPONSIBILITIES 1.1 Coordinate attendance of MnDOT representatives and Building Users to review meetings. 1.2 Solicit and facilitate comments from Building Users. 1.3 Provide input and review. 1.4 Respond to requests for information from the Consultant. 1.5 Provide information and guide specifications on MnDOT s preferred materials and equipment. C. CONSULTANT S DESIGN DEVELOPMENT RESPONSIBILITIES 1.1 The Consultant shall prepare Design Development Documents for MnDOT s approval consisting of Drawings and other documents appropriate for the Project. 1.2 The Consultant shall document progress with the Project Design Schedule and inform MnDOT of the status of progress. 1.3 Architectural Design Development a. Develop roof and floor plans, elevations, building sections, room finishes and door information. b. Coordinate locations and layout of Building Systems into design. c. Prepare Outline Specifications for all materials and equipment including Product Data or cutsheets indicating quality of products and materials. Incorporate MnDOT s preferred materials and equipment. d. Coordinate locations of MnDOT Equipment and Vehicles. 1.4 Structural Design Development a. Develop roof framing, wall framing and foundation systems with conceptual calculations for loads. b. Prepare Outline Specifications for all materials. 1.5 Mechanical Design Development Develop schematics which indicate all Heating Ventilation and Air Conditioning (HVAC) equipment, major duct layouts, temperature control system concept, all fire and life safety equipment and all plumbing system layouts, control system schematics, lamping and system commissioning requirements. a. Perform analysis of envelope energy performance and applicability of alternative energy sources. b. Determine the applicability of utility company energy rebate programs. Page 10 of 23

11 c. Implement water-efficiency best practices based on the EPA's WaterSense at Work. d. Develop 1/4" scale drawings of equipment rooms with all equipment laid out to scale. e. Coordinate all hook-ups required for MnDOT s equipment. f. Procure catalog cuts of all proposed equipment and fixtures. g. Develop Outline Specifications for all materials and equipment. h. Prepare Outline Commissioning Plan for Building Automation System. 1.6 Electrical Design Development Develop schematics which indicate primary and secondary service, fire alarm systems, light fixtures and lamping, outlet locations for power, phone and data and cable distribution. a. Prepare analysis of daylighting concepts. b. Determine the applicability of utility company energy rebate programs. c. Develop 1/4" scale drawings of equipment rooms with all equipment laid out to scale. d. Coordinate all hook-ups required for MnDOT s equipment. e. Procure catalog cuts of all proposed equipment and fixtures. f. Prepare Outline Specifications for all materials and equipment. 1.7 Civil and Sitework Design Development Develop site designs for: a. Conceptual Storm Water Pollution Prevention Plan. (SWPPP) b. Grading, drainage and retention. c. Public utility access and Site distribution. d. Water Services Systems. e. Paving Plan and Vehicle Turning Schematic. f. MnDOT s proposed outbuildings. g. Landscaping concepts. h. Site Lighting. 1.8 Interim Estimate of the Cost of the Work The Consultant shall prepare and submit to MnDOT an Interim Estimate of the Cost of the Work, based upon proposed materials, equipment, component systems and types of construction. D. BUILDING CODE REVIEW AND SUBMITTALS 1.1 Initial Application for Plan Review: The Consultant shall submit the "Initial Application for Plan Review" form to the Department of Labor and Industry, Construction Codes and Licensing, Building Codes and Standards (DLI Building Codes). a. If a local Jurisdiction is designated or if DLI will perform the Plan Review, the Consultant shall provide documents and coordinate preliminary reviews and meetings with the designated Jurisdiction. E. DESIGN DEVELOPMENT PHASE DELIVERABLES The Consultant shall provide electronic (pdf) files of all Deliverables. Provide paper copy drawings and reports in sizes and quantities indicated by the MnDOT. 1.1 Updated Project Design Schedule for Design Reviews and Consultant Services. 1.2 Quality Management Plan (QMP) documentation of QA/QC activities performed. Page 11 of 23

12 1.3 Building Code Analysis and report on watershed, planning and zoning issues and regulatory constraints. 1.4 Outline Specifications for all proposed materials and equipment. 1.5 Interim Estimated Cost of the Work. 1.6 Meeting Minutes. 1.7 Design Development Building Drawings: Appropriately scaled drawings to indicate: a. Roof, floor and ceiling plans, elevations, wall sections. b. Locations and layout of Building Systems. c. Roof framing, wall framing and foundation systems. d. Layout of equipment rooms. e. Locations of MnDOT s vehicles and equipment. 1.8 Design Development Site Drawings: a. Conceptual Storm Water Pollution Prevention Plan. (SWPPP) b. Grading, drainage and retention. c. Public utility access and Site distribution. d. Water Services Systems. e. Paving Plan and Vehicle Turning Schematic. f. MnDOT s proposed outbuildings. g. Landscaping concepts. h. Site Lighting. 1.9 Design Development Informational Submittals: a. Catalog cuts of all proposed equipment. b. Materials, finish and color schedules for proposed interior and exterior products. c. Analysis of daylighting concepts. d. Analysis of envelope energy performance and applicability of alternative energy sources. e. Applicability of Water-efficiency best practices. 3. CONSTRUCTION DOCUMENT PHASE A. THE CONSTRUCTION DOCUMENT PHASE of the Project will commence upon MnDOT s written approval of the Design Development Deliverables. 1.1 The Work of this Phase shall incorporate MnDOT s itemized Review comments and shall respond to adjustments required to accommodate budget constraints. 1.2 The Construction Documents Deliverables shall illustrate and describe the further development of the approved Design Development and shall consist of Drawings and Specifications setting forth in detail the quality levels of materials and systems and other requirements for the construction of the Work. B. MNDOT S CONSTRUCTION DOCUMENT RESPONSIBILITIES 1.1 Coordinate attendance of MnDOT representatives to all review meetings. 1.2 Solicit comments from Building Users regarding requests by the Consultant. 1.3 Provide input and review. Page 12 of 23

13 1.4 Respond to requests for information from the Consultant. 1.5 Provide Project Manual Documents: MnDOT Contract No. a. Division 00 Procurement and Contracting Requirements: including Bidding Requirements, Insurance Requirements, Labor and Wage Rate Requirements, Conditions of the Contract and forms of agreement between the State / MnDOT and the Construction Contractor. b. Division 01: General Requirements: including Price and Payment Procedures, Administrative Requirements; Quality, Performance and Product Requirements; Temporary Facilities and Controls; Execution and closeout Requirements. c. Specification Contract language required verbiage. C. CONSULTANT S CONSTRUCTION DOCUMENTS PHASE RESPONSIBILITIES 1.1 Construction Contract Documents a. The Consultant shall prepare Construction Contract Documents for MnDOT s approval consisting of Drawings and Project Manual setting forth the requirements for the construction of the Work. b. Coordinate placement and connection requirements of MnDOT s equipment which will be installed in Project. c. Manage and coordinate the drawings and specifications of the Sub-Consultants. d. Coordinate with MnDOT s responsibilities for providing Bidding Requirements, Conditions of the Contract and forms of agreement between MnDOT and the Construction Contractor. e. Assist in the development and documentation of Unit Prices, Alternates and Allowances. 1.1 Project Design Schedule The Consultant shall maintain, update and document progress with the Project Design Schedule and inform MnDOT of the status of progress. 1.2 The Consultant shall incorporate into the Construction Documents the design requirements of governmental authorities having jurisdiction over the Project. a. Prepare final building code analysis. b. Assist MnDOT in preparing and filing documents necessary for government approvals. c. Structural Special Inspections forms shall be prepared and included in the Project Manual. 1.3 The Consultant shall compile Final Estimate of Cost of the Work. 1.4 The Consultant shall obtain acceptance of the Construction Documents from appropriate Agency authorities, as required. 1.5 The Consultant shall prepare applications for utility company energy rebate programs. D. THE PROJECT MANUAL shall contain the Bidding Requirements, General Conditions of the Contract for Construction (Division 00), and General Requirements (Division 01) and other provisions and requirements as furnished by MnDOT. 1.1 MnDOT will provide Division 00 and Division 01 of the Project Manual in CSI Three-part Format. 1.2 The Consultant may use their standard master specifications formatted to conform with CSI Master Format 2004 for Divisions 2 through 48. a. Use of ArCom MasterSpec program is preferred for coordination with MnDOT Division 00 and Page 13 of 23

14 Division 01. b. Consultant shall make revisions as required to comply with the language and provisions of MnDOT s Division 00 and Division 01 and to incorporate MnDOT s preferred materials and equipment. 1.3 Project Information: a. Title Page shall bear the Project name, the State Project ID #, the MnDOT Building Number and the address of MnDOT Building Services Section. b. Subsequent sheets shall bear the Project name, the State Project ID # and the MnDOT Building Number. 1.4 Specification Sections Requirements: a. Sections shall bear MnDOT s Conditions of the Contract paragraphs. i. Sections containing the Work of Alternates, Allowances, Unit Prices and/or Informational Line items shall bear MnDOT s contract paragraphs regarding Contract Requirements for these. ii. Sections containing work affected by the SWPPP requirements shall bear MnDOT s contract paragraphs regarding Contract Requirements for these. b. Manufacturers and products shall be specified to comply with [Buy America] [American-made Steel] and MnDOT s contract language requirements. i. A minimum of three manufacturers must be specified for each product or material where manufacturers or products are listed. E. CONSTRUCTION DRAWINGS shall be created on AutoCadd Computer Aided Design Drafting (CADD) system. 1.1 Drafting Standards: a. MnDOT will provide layering and set-up standard requirements which must be incorporated into the CADD files. b. eplan Filing: The Consultant shall prepare documents in formats required by Department of Labor and Industry for electronic submission. 1.2 Project Information: a. Title Page shall bear the State Project ID #, the MnDOT Building Number and the address of MnDOT Building Services Section and other information as directed by the MnDOT Project Manager. b. Subsequent sheets shall bear the Project name, the State Project ID # and the MnDOT Building Number. 1.3 Sheet Organization a. The Consultant shall submit a Sheet Schedule draft for approval. b. Sheet number identification shall not exceed 4 characters. Sheet numbers shall be numerically consecutive. c. Sheets shall not contain more that 25% unused area. d. Details shall be numbered from top to bottom and from right to left. 1.4 Sheet Sizes: Drawings shall be prepared on MnDOT s approved sizes sheets (11x17 or 22x34), or other as approved by MnDOT. 1.5 Drafting and Lettering on Drawings shall be of such a size and quality to permit legible reproduction at one half size. a. Lettering shall be no smaller than 14 point (approximately 3/32") when 22x34 sheets are reduced to one half size. (11x17) b. Graphic Scales and North Arrows, where appropriate, shall be provided on all Drawings. Page 14 of 23

15 c. Abbreviations and Symbols shall be recognized industry-standard. d. Notes: i. ConDoc style keynote system (Specification Section based) shall not be used unless accompanied by full notations on each drawing / detail. ii. Use of numbered notes is not permitted unless approved and accompanied by a legend of full notations on each sheet. e. Exterior Wall Sections shall be provided for each wall type condition, cut through openings where possible, at such scale as to communicate of the relationships of the elements of the full wall. The extensive use of building section drawings is discouraged. 1.6 Building Code Information shall appear on the Title Page or Sheet 1 of the Drawings: Building Occupancy Classification(s) Occupant Loads Construction Type(s) Snow Load Allowable Floor Areas vs Actual Frost Depth Plan of Required Separations MnSBC Edition applicable Plumbing Fixture Requirements Fire Protection Requirements Exiting Load Plan Fire Extinguisher Location Plan F. FINAL ESTIMATE OF THE COST OF THE WORK 1.1 The Consultant shall prepare and submit to MnDOT a Draft Final and a Final Estimate of the Cost of the Work based specified materials, equipment, component systems and types of construction. G. BUILDING CODE REVIEW AND SUBMITTALS 1.1 Submittals at the completion of the Construction Documents: a. The Consultant shall submit documents in formats required by Department of Labor and Industry for electronic submission. b. The Consultant shall submit the "Application for Plan Review" form and send [it along with two] complete sets of construction documents to DLI Building Codes, if they are performing the plan review, or the Consultant shall submit as required by the local Jurisdiction designated by DLI to perform the Plan Review. c. The Mechanical Sub-Consultant shall submit [two copies of the] Plumbing Drawings and Specifications to the Department of Labor and Industry, Construction Codes and Licensing, Plumbing Plan Review and Inspections (DLI Plumbing) for review. d. The Civil Sub-Consultant shall provide the documents and submissions for the Storm Water Pollution Prevention Plan and Watershed requirements. e. MnDOT will pay for Plan Review Fees as a reimbursable to the Consultant. H. REVIEW BY MNDOT AND BUILDING USERS 1.1 Review at 75% Document Completion: When the Construction Documents are deemed 75% complete, the Consultant shall submit electronic (pdf) files of all Deliverables. Provide paper copy drawings and reports in sizes and quantities indicated by the MnDOT. a. The Consultant shall submit to MnDOT a Draft Final Estimate of the Cost of the Work based specified materials, equipment, component systems and types of construction. b. Within two weeks after MnDOT receives the Drawings a meeting will be scheduled with all Consultants working on the Project to review the documents with MnDOT. 1.2 Review at 95% Document Completion: When the Construction Documents are deemed 95% complete, the Consultant shall submit electronic (pdf) files of all Deliverables. Provide paper copy drawings and reports in sizes and Page 15 of 23

16 quantities indicated by the MnDOT. a. Consultant shall submit the Final Cost Estimate based specified materials, equipment, component systems and types of construction. b. Within two weeks after MnDOT receives the Drawings a meeting will be scheduled with all Consultants working on the Project to review the documents with MnDOT. I. CONSTRUCTION DOCUMENT PHASE DELIVERABLES Provide electronic (pdf) files of all Deliverables. Provide Project Manuals and drawings at full size and half size paper copies and as indicated for Reviews and Bidding. 1.1 Updated Project Design Schedule for Design Reviews and Consultant Services. 1.2 Quality Management Plan (QMP) documentation of QA/QC activities performed. 1.3 Project Manual and Drawings for construction of the Project. 1.4 Storm Water Pollution Prevention Plan. 1.5 Responses to and incorporation of Plan Review comments from code authorities. 1.6 Final Estimate of Construction Costs. 1.7 Final Building Code Analysis and report on watershed, planning and zoning issues and regulatory constraints. 1.8 Applications for utility company energy rebate programs. 6. BIDDING PHASE SERVICES A. MN/DOT S BIDDING PHASE RESPONSIBILITIES 1.1 MnDOT will arrange for the Solicitation for Bids to be placed for Web-Based Distribution through the Minnesota Department of Administration, Materials Management Division. 1.2 Review of Consultant s recommendations on Requests for Prior-approval to Bid. 1.3 Provide input on questions from prospective bidders and provide clarifications and interpretations of the provisions of Division 00 and Authorize and pay for the printing of bidding documents as a reimbursable expense to this Contract. 1.5 Provide Addendum insert documents for revisions to Division 00 and 01, if required. 1.6 Pre-bid Conference: MnDOT will arrange and conduct the Pre-bid meeting. 1.7 Coordinate with the Minnesota Department of Administration, Materials Management Division a. Receive and evaluate the Bids and Alternates b. Review and verify Bidder Qualifications c. Forward recommendation of the award of the contract. d. Issue the Notice to Proceed. B. CONSULTANTS RESPONSIBILITIES FOR BIDDING ASSISTANCE The Consultant shall assist MnDOT in bidding the Project. 1.1 Printed Document Distribution a. Provide paper copy drawings and reports in sizes and quantities indicated by the MnDOT. 1.2 Digital Web-Based Distribution All publication of Documents will be through the Web-Based Distribution System. The Consultant shall not distribute the Project Manual, Drawings or Addenda to parties other than MnDOT s Project Page 16 of 23

17 Manager. 1.3 Pre-bid Conference: The Consultant shall attend the Pre-bid Conference and shall prepare Pre-bid Conference Notes to include in the Addenda. 1.4 Addenda The Consultant shall prepare all necessary Addenda using the electronic document format provided by MnDOT. a. The Addenda will be posted by MnDOT through the [Minnesota Department of Administration, Materials Management Division] [MnDOT Business Services Section] on the Web-Based Distribution System. b. Responses and Clarifications: The Consultant shall receive inquiries from prospective bidders and shall prepare responses, clarifications and interpretations of the Contract Documents in the form of Addenda. c. Requests for Product Approval to Bid: The Consultant shall consider requests for Product Approval to Bid and prepare Addenda identifying additional Manufacturers approved to Bid. C. BID OPENING AND AWARD OF CONTRACT 1.1 The bids will be received and opened in public at the location, date and time indicated in the Solicitation for Bids. The Consultant is not required to attend the bid opening. a. The Consultant may be requested to direct a letter to MnDOT recommending the Award of the Contract or recommending of rejecting the bids and citing reasons for such recommendation. D. BIDDING PHASE DELIVERABLES Provide electronic (pdf) files of all Deliverables. 1.1 Addenda to include: a. Responses, Clarifications and Interpretations b. Product Approvals to Bid c. Pre-bid Conference Minutes 1.2 Recommendation on Award of the Contract, if requested. 3. CONSTRUCTION ADMINISTRATION SERVICES A. MnDOT S CONSTRUCTION ADMINISTRATION RESPONSIBILITIES 1.1 General: a. Attend Construction Progress meetings. b. Outbuildings designed by MnDOT: i. MnDOT Project Manager shall visit the Site to become generally familiar with the progress and quality of the Work, and to determine, in general, if the Work observed will be in accordance with the Contract Documents when fully completed. ii. MnDOT Project Manager shall prepare and distribute Jobsite Observation Reports about the progress and quality of the portion of the Work in progress or completed. iii. MnDOT will review and return submittals on the Outbuildings. c. Provide timely response to all items requiring MnDOT s actions, directions or information. d. Contract for required Special Inspections testing during construction. e. Manage all work by MnDOT s separate contractors and consultants. 1.2 Pre-Construction Meeting a. MnDOT Project Manager shall schedule the Pre-Construction Meeting for attendance by the Consultant and the Construction Contractor. i. MnDOT will manage the Pre-Construction Meeting. Page 17 of 23

18 ii. MnDOT Project Manager shall record minutes and distribute them to all attendees. 1.3 Contractor s Applications for Payment: a. Review with Prime Contractor all Applications for Payment for Labor Compliance and Materials Documentation. b. Execute the Certificate for Payment. c. Process payments and manage project budget. 1.4 Changes in the Work a. Review all Requests for Substitutions and authorize acceptance if appropriate. b. Review Consultant s recommendations on Responses to Requests for Proposals. c. Review and execute Construction Change Directives. d. Prepare and execute Supplemental Agreements. 1.5 Substantial Completion a. Attend the Pre-substantial and Substantial Completion Inspections. b. Approve Certificate of Substantial Completion. 1.6 Contract Close-Out a. Receive and review all warranties and related documents. b. Attend the 10-Month Inspection. c. Receive and review Contractor s Close Out submittals. B. CONSULTANT S CONSTRUCTION CONTRACT ADMINISTRATION PHASE RESPONSIBILITIES 1.1 General: The Consultant shall provide Services as required by A201 Reference: Article a. The Consultant shall advise and consult with the Owner during the Construction Phase Services. The Consultant shall have authority to act on behalf of the Owner only to the extent provided in this Agreement. The Consultant shall not have control over, charge of, or responsibility for the construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, nor shall the Consultant be responsible for the Contractor s failure to perform the Work in accordance with the requirements of the Contract Documents. The Consultant shall be responsible for the Consultant s negligent acts or omissions, but shall not have control over or charge of, and shall not be responsible for, acts or omissions of the Contractor or of any other persons or entities performing portions of the Work. b. The Consultant shall administer the Contract for Construction according to the Conditions of the Contract AIA A201 (State of Minnesota edition as bound in the Project Manual); interpret the requirements of the Contract Documents; and advise MnDOT concerning performance of the Prime Construction Contractor. c. The Consultant shall review and respond to written requests for information about the Contract Documents in writing with reasonable promptness. If appropriate, the Consultant shall prepare and issue supplemental Drawings and Specifications in response to Requests for Information (RFI s). 1.2 Construction Documents a. Upon award of the Contract, the Consultant shall provide to the Prime Construction Contractor a complete digital Project Manual and Drawings set which incorporates all Addenda and Accepted Alternates into a Conformed Set in a PDF digital file format. b. During the course of construction, the Consultant shall provide documentation of changes and Page 18 of 23

19 modifications in a PDF digital file format to the Prime Construction Contractor for its use. 1.3 Pre-Construction Meeting a. Consultant shall attend the Pre-Construction Meeting. 1.4 Pre-Installation Meetings a. Consultant shall schedule the Pre-Installation Meetings with the Contractor. i. The Consultant will manage the Pre-Installation Meetings. ii. Consultant shall record and distribute minutes. 1.5 Construction Progress Meetings and Observations of the Work The Consultant shall provide Services as required by A201 Reference: Article , Article 12, Article 13.5, a. The Consultant, and Sub-Consultants as needed, shall attend Construction Progress Meetings as scheduled below. b. The Consultant and Sub-Consultants shall visit the Site at intervals appropriate to the stage of construction, and as scheduled below, to become generally familiar with the progress and quality of the Work, and to determine, in general, if the Work observed will be in accordance with the Contract Documents when fully completed. The Consultant shall have the authority to reject Work that does not conform to the Contract Documents, whether or not such Work is fabricated, installed or completed. c. The Consultant and Sub-Consultants shall prepare and distribute Jobsite Observation Reports documenting progress and quality of the portion of the Work in progress or completed. Consultant shall report to MnDOT: i. Known deviations from the Contract Documents. ii. Defects and deficiencies observed in the Work. iii. Deviations from Construction Schedule d. Storm Water Pollution Prevention Plan The Consultant shall observe implementation of the Storm Water Pollution Prevention Plan (SWPPP) for compliance with Contract requirements. e. The Commissioning Plan The Consultant shall manage implementation of the Building Automation Commissioning Plan for compliance with Contract requirements. 1.6 Interpretations of the Contract Documents: The Consultant shall provide Services as required by A201 Reference: Article , Article , a. The Consultant shall prepare Architect s Supplemental Information (ASI s) and prepare responses to the Contractor s Requests for Information (RFI s). b. The Consultant shall interpret and make recommendations to MnDOT regarding matters concerning performance under, and requirements of, the Contract Documents on written request of either MnDOT or Contractor. c. Interpretations and recommendations of the Consultant shall be consistent with the intent of and reasonably inferable from the Contract Documents and shall be in writing or in the form of drawings. d. The Consultant shall render initial decisions on Claims between the Owner and Contractor as provided in the Contract Documents. When making such interpretations and recommendations, the Consultant shall endeavor to secure faithful performance by both MnDOT and the Contractor, and shall not show partiality to either. Page 19 of 23

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

Professional Practice 544

Professional Practice 544 February 22, 2016 February 29, 2016 Professional Practice 544 AIA-B101 Owner - Architect Agreement Michael J. Hanahan Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com

More information

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction - State of Ohio Professional Services Agreements for Public Facility Construction TABLE OF CONTENTS ARTICLE 1 - BASIC SERVICES... 1 ARTICLE 2 - PROGRAM VERIFICATION STAGE... 2 ARTICLE 3 - SCHEMATIC DESIGN

More information

ARTICLE 1 - ARCHITECT/ENGINEER S BASIC SERVICES

ARTICLE 1 - ARCHITECT/ENGINEER S BASIC SERVICES - Architect/Engineer s Scope of Services (Multiple-Prime Project) State of Ohio Professional Services Agreements for Public Facility Construction 1.1 General ARTICLE 1 - ARCHITECT/ENGINEER S BASIC SERVICES

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Architect s client identified

More information

Attachment 1 Architectural Services

Attachment 1 Architectural Services A. Phase 1, Programming and Schematic Design: 1. Ascertain the requirements for each project through a meeting with the COUNTY, and a review of an existing schematic layout of each project, if such layout

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year Two Thousand and BETWEEN the Architect s client identified as the Owner: Capitol

More information

AGREEMENT FOR ARCHITECTURAL SERVICES

AGREEMENT FOR ARCHITECTURAL SERVICES AGREEMENT FOR ARCHITECTURAL SERVICES This Agreement for ( Agreement ) is dated XX XX, 20XX for reference purposes only and is made by and between SANTA MONICA-MALIBU UNIFIED SCHOOL DISTRICT, a California

More information

CHAPTER 3: DESIGN. TN Higher Education Designers Manual October 2018 Page 1 of 12

CHAPTER 3: DESIGN. TN Higher Education Designers Manual October 2018 Page 1 of 12 3.01 GENERAL A. Design the project to meet the authorized scope, budget, and schedule. B. Upon initiation of the project, arrange to review with the Owner the service and administrative requirements as

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services... A-2. B. Architectural Programming... A-5

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services... A-2. B. Architectural Programming... A-5 EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER A. Basic Services... A-2 B. Architectural Programming... A-5 1. Project Initiation... A-5 C. Design Services... A-6 1. Schematic Design Phase...

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS A. SCOPE OF PROJECT... 1 B. BASIC SERVICES... 1 C. PRE-DESIGN AND START-UP SERVICES... 4 D. SCHEMATIC DESIGN PHASE... 7 E. DESIGN

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS A. SCOPE OF PROJECT... 1 B. BASIC SERVICES... 1 C. PRE-DESIGN AND START-UP SERVICES... 4 D. SCHEMATIC DESIGN PHASE... 7 E. DESIGN

More information

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order [Introductory Note to User: The following text as published describes

More information

Document B105. Standard Form of Agreement Between Owner and Architect for a Residential or Small Commercial Project

Document B105. Standard Form of Agreement Between Owner and Architect for a Residential or Small Commercial Project TM Document B105 2007 Standard Form of Agreement Between Owner and Architect for a Residential or Small Commercial Project AGREEMENT made as of the in the year (In words, indicate day, month and year.)

More information

Appendix D University of Maine System. Supplementary Requirements to AIA Document B Standard Form of Architect s Services

Appendix D University of Maine System. Supplementary Requirements to AIA Document B Standard Form of Architect s Services Appendix D University of Maine System Supplementary Requirements to AIA Document B201-2007 Standard Form of Architect s Services This document provides the Architect s scope of services only and must be

More information

AGREEMENT BETWEEN DESIGNING ARCHITECT AND THE DISTRICT BOARD OF TRUSTEES OF PALM BEACH STATE COLLEGE

AGREEMENT BETWEEN DESIGNING ARCHITECT AND THE DISTRICT BOARD OF TRUSTEES OF PALM BEACH STATE COLLEGE AGREEMENT BETWEEN DESIGNING ARCHITECT AND THE DISTRICT BOARD OF TRUSTEES OF PALM BEACH STATE COLLEGE THIS AGREEMENT, is made and entered into this day of, between the DISTRICT BOARD OF TRUSTEES OF PALM

More information

INSTRUCTIONS FOR USING THE MICHIGAN SCHOOL BUSINESS OFFICIALS ( MSBO ) PROTOTYPE FORM OWNER/ARCHITECT AGREEMENT WITH CONSTRUCTION MANAGER COORDINATION

INSTRUCTIONS FOR USING THE MICHIGAN SCHOOL BUSINESS OFFICIALS ( MSBO ) PROTOTYPE FORM OWNER/ARCHITECT AGREEMENT WITH CONSTRUCTION MANAGER COORDINATION INSTRUCTIONS FOR USING THE MICHIGAN SCHOOL USINESS OFFICIALS ( MSO ) PROTOTYPE FORM OWNER/ARCHITECT AGREEMENT WITH CONSTRUCTION MANAGER COORDINATION Please be advised that the purpose of this Instruction

More information

600 - Phase C Intermediate Review Checklist for the Architect- Engineer

600 - Phase C Intermediate Review Checklist for the Architect- Engineer 600 Phase C Intermediate Review Checklist for the Architect Engineer This checklist is to be used by the ArchitectEngineer during Phase C of the Project and shall be included in the Intermediate Review

More information

CONSTRUCTION DOCUMENTS Part 1

CONSTRUCTION DOCUMENTS Part 1 Audio Presentation Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org

More information

University Architect & VP for Facilities Policy & Procedure #14

University Architect & VP for Facilities Policy & Procedure #14 University Architect & VP for Facilities Policy & Procedure #14 TITLE: OBJECTIVE AND PURPOSE: RESPONSIBILITY: ADMINISTRATION OF AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER (MAJOR PROJECTS) To establish

More information

[JURISDICTION] S AMENDMENTS TO AIA DOCUMENT B , STANDARD FORM OF ARCHITECT S SERVICES: DESIGN AND CONTRACT ADMINISTRATION

[JURISDICTION] S AMENDMENTS TO AIA DOCUMENT B , STANDARD FORM OF ARCHITECT S SERVICES: DESIGN AND CONTRACT ADMINISTRATION [JURISDICTION] S AMENDMENTS TO AIA DOCUMENT B141-1997, STANDARD FORM OF ARCHITECT S SERVICES: DESIGN AND CONTRACT ADMINISTRATION ARTICLE 2.1. PROJECT ADMINISTRATION SERVICES. Paragraph 2.1.2. Paragraph

More information

Educational Use Only S A M P L E S A M P L E

Educational Use Only S A M P L E S A M P L E CONSENSUSDOCS 240 STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER This document was developed through a collaborative effort of entities representing a wide cross-section of the construction

More information

Chapter 4 State Requirements for Educational Facilities Section 4.1

Chapter 4 State Requirements for Educational Facilities Section 4.1 providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services...A-1. B. Pre-Design and Start-Up Services...

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services...A-1. B. Pre-Design and Start-Up Services... EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER A. Basic Services...A-1 B. Pre-Design and Start-Up Services...A-3 1. Project Initiation...A-3 2. Development of Architectural Program...A-4

More information

Chapter 6, Construction

Chapter 6, Construction Chapter 6, Construction CHAPTER CONTENTS 6.1 OWNER-CONTRACTOR AGREEMENT A. Preparation B. Owner Signature C. Award 6.2 PRE-CONSTRUCTION CONFERENCE A. Administration B. Attendees C. Pre-Construction Conference

More information

REQUEST FOR PROPOSALS FOR. Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA

REQUEST FOR PROPOSALS FOR. Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA REQUEST FOR PROPOSALS FOR Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA City of Coralville Iowa Coralville, IA Page 1 of 6 Please review and provide response to this letter

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE DIVISION 1 GENERAL REQUIREMENTS SECTION 01 32 16 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. All drawings and technical specifications, Notice to Bidders, Instructions and Information to Bidders, Bid Proposal

More information

ARCHITECTURAL / ENGINEERING SERVICES RFQ. North Sound Behavioral Health Organization

ARCHITECTURAL / ENGINEERING SERVICES RFQ. North Sound Behavioral Health Organization ARCHITECTURAL / ENGINEERING SERVICES RFQ North Sound Behavioral Health Organization ARCHITECTURAL/ENGINEERING RFQ TABLE OF CONTENTS SECTION 1.0 PROJECT DESCRIPTION... 3 Background Owner & Team Members

More information

PLANNING AND EVALUATION PRELIMINARY DESIGN

PLANNING AND EVALUATION PRELIMINARY DESIGN PLANNING AND EVALUATION Project Initiation Discuss and refine client requirements Project brief, Schedule, Budget Confirm client's space needs and program Establish scope of work Obtain client-supplied

More information

EXHIBIT A TO CONTINUING SERVICES AGREEMENT

EXHIBIT A TO CONTINUING SERVICES AGREEMENT ARCHITECTURE SERVICES EXHIBIT A TO CONTINUING SERVICES AGREEMENT ARTICLE 1 - OWNER S OBLIGATIONS 1.1 In addition to the provisions of SECTION 4 of the Agreement, Owner shall provide an initial budget for

More information

BIDDING INFORMATION FOR HOLLY HILL ADMINISTRATION COMPLEX RENOVATION AND ADDITION. for the COUNTY OF ORANGEBURG. Project Number: FY

BIDDING INFORMATION FOR HOLLY HILL ADMINISTRATION COMPLEX RENOVATION AND ADDITION. for the COUNTY OF ORANGEBURG. Project Number: FY BIDDING INFORMATION FOR HOLLY HILL ADMINISTRATION COMPLEX RENOVATION AND ADDITION for the COUNTY OF ORANGEBURG Project Number: FY13-1206 October 18, 2012 1180 Columbia Avenue Suite 201 29063 (803) 781-1451

More information

INDIANA UNIVERSITY AGREEMENT BETWEEN OWNER AND ARCHITECT FOR PROJECTS OVER $500,000. AGREEMENT made as of the day of, in the year of between the:

INDIANA UNIVERSITY AGREEMENT BETWEEN OWNER AND ARCHITECT FOR PROJECTS OVER $500,000. AGREEMENT made as of the day of, in the year of between the: INDIANA UNIVERSITY AGREEMENT BETWEEN OWNER AND ARCHITECT FOR PROJECTS OVER $500,000 AGREEMENT made as of the day of, in the year of between the: OWNER: The Trustees of Indiana University 1800 N. Range

More information

Document Synopses by Series

Document Synopses by Series Document Synopses by Series AIA Contract Documents are divided into six alphanumeric series by document use or purpose: A Series: Owner/Contractor Agreements B Series: Owner/Architect Agreements (p. 13)

More information

1.0 ABOUT THE NU GUIDELINES

1.0 ABOUT THE NU GUIDELINES Construction Policies & Procedures Northeastern University Guidelines for Capital Project Design & Implementation.0 ABOUT THE NU GUIDELINES This document is intended to describe in a comprehensive manner

More information

The Home Depot U.S.A., Inc. Instructions to Bidders

The Home Depot U.S.A., Inc. Instructions to Bidders The Home Depot U.S.A., Inc. Instructions to Bidders Home Depot Page 1 of 5 Article 1 Definitions 1.1 Bidding Documents include the Bidding Requirements and the proposed Contract Documents. The Bidding

More information

Owner's Representative Scope Matrix - D/B Rev 10/28/2013

Owner's Representative Scope Matrix - D/B Rev 10/28/2013 Ecluded Owner's Representative Scope Matri - D/B Rev 10/28/2013 The following matri is a worksheet to identify required and optional scope for Owner's Representative services. Please identify the scope

More information

Dick s Sporting Goods Demolition Package

Dick s Sporting Goods Demolition Package REQUEST FOR PROPOSAL FOR COMPETITIVE SEALED PROPOSALS TO PROVIDE: Dick s Sporting Goods Demolition Package at Salt Lake City, UT 2425 E. Camelback Rd. Suite 750 Phoenix AZ 85016 Notice of Extended Payment

More information

CONSTRUCTION MANAGEMENT REQUEST FOR PROPOSAL EAST RUTHERFORD PUBLIC SCHOOLS

CONSTRUCTION MANAGEMENT REQUEST FOR PROPOSAL EAST RUTHERFORD PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT REQUEST FOR PROPOSAL EAST RUTHERFORD PUBLIC SCHOOLS I. INTRODUCTION The East Rutherford School District is planning to hold a referendum on December 12, 2017 that incorporates facility

More information

AGREEMENT FOR DESIGN CONSULTANT SERVICES BETWEEN NEW HANOVER COUNTY BOARD OF EDUCATION. hereinafter referred to as the Owner AND

AGREEMENT FOR DESIGN CONSULTANT SERVICES BETWEEN NEW HANOVER COUNTY BOARD OF EDUCATION. hereinafter referred to as the Owner AND AGREEMENT FOR DESIGN CONSULTANT SERVICES BETWEEN NEW HANOVER COUNTY BOARD OF EDUCATION hereinafter referred to as the Owner AND hereinafter referred to as the Design Consultant PROJECT: OWNER'S PROJECT

More information

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement Township of Severn REQUEST FOR PROPOSAL Architectural & Professional Services Fire Station Replacement Deadline for proposal submission is June 15, 2017 at 2:00 p.m. Contact Person: Tim Cranney Director

More information

CONTRACT FOR CONSULTANT SERVICES Agreement entered into as of MPS Board of Education approval date (if required, NA if not required):

CONTRACT FOR CONSULTANT SERVICES Agreement entered into as of MPS Board of Education approval date (if required, NA if not required): CONTRACT FOR CONSULTANT SERVICES - 2016 Agreement entered into as of MPS Board of Education approval date (if required, NA if not required): For the project: MPS Project Name: By and Between: The Owner:

More information

RFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No.

RFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No. SPECIAL CONDITIONS Article I, Section A delete this paragraph in its entirety and replace it with the following language: Owner s representative to act on its behalf with respect to this Agreement shall

More information

DOCUMENT BRIDGING DOCUMENTS. A. Bridging Documents define Owner s Program for the Project including, without limitation:

DOCUMENT BRIDGING DOCUMENTS. A. Bridging Documents define Owner s Program for the Project including, without limitation: DOCUMENT 00 5201 BRIDGING DOCUMENTS ARTICLE 1 GENERAL 1.01 Bridging Documents A. Bridging Documents define Owner s Program for the Project including, without limitation: 1. Size, type, shape, height, configuration,

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility RFP Components CLIENT: TradePort International Corporation, Operators of John C. Munro

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

CITY OF CHICAGO DEPARTMENT OF BUILDINGS

CITY OF CHICAGO DEPARTMENT OF BUILDINGS CITY OF CHICAGO DEPARTMENT OF BUILDINGS GUIDELINES FOR THE PREPARATION OF REQUESTS FOR QUALIFICATIONS FOR THE SELECTION OF CONSULTING FIRMS TO PERFORM LIFE SAFETY EVALUATIONS The Chicago Department of

More information

ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS

ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS CONSULTANT FEE SCHEDULE FOR LANDSCAPE ARCHITECTURAL CONSULTING SERVICES A GUIDELINE NOV 2008 TABLE OF CONTENTS Table Of Contents... 2 INTRODUCTION...

More information

ALBUQUERQUE PUBLIC SCHOOLS. General Conditions of the Agreement between APS and the Design Professional

ALBUQUERQUE PUBLIC SCHOOLS. General Conditions of the Agreement between APS and the Design Professional ALBUQUERQUE PUBLIC SCHOOLS General Conditions of the Agreement between APS and the Design Professional (Part B of the Agreement) TABLE OF CONTENTS Article 1 Article 2 Definitions Design Professional s

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

EXHIBIT 6 Preconstruction Work

EXHIBIT 6 Preconstruction Work EXHIBIT 6 Preconstruction Work The following tasks shall be accomplished by the CM/GC as part of its obligations during the preconstruction phase. The work is to be coordinated with the services requirements

More information

A D D E N D U M. REPLACE: Project Summary with attached revised Project Summary. 1 Specification Section Project Summary

A D D E N D U M. REPLACE: Project Summary with attached revised Project Summary. 1 Specification Section Project Summary A D D E N D U M 1 TO All Plan Holders ISSUE DATE 20 January 2017 PROJECT # 15-028 REGARDING Switchgear Replacement NARRATIVE PAGES 1 15-02812 KVa Switchgear Replacement Project SPECIFICATION PAGES 10 DRAWING

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

Main Building Auditorium

Main Building Auditorium Main Building Auditorium Theatre and Lighting Upgrade Moberly Area Community College 101 College Avenue Moberly, Missouri This document contains all necessary instructions and specifications to perform

More information

Florida Army National Guard Construction Facilities Management Office. Scope of Work:

Florida Army National Guard Construction Facilities Management Office. Scope of Work: Florida Army National Guard Construction Facilities Management Office Florida Armory Revitalization Program (FARP) Design Guidelines September 2011 Scope of Work: To provide complete design for the renovation/alterations

More information

OSNI PONCA OFFICE REMODEL

OSNI PONCA OFFICE REMODEL OSNI PONCA OFFICE REMODEL PROJECT MANUAL OCTOBER 2016 SCHEMMER PROJECT NO. 06571.002 OSNI PONCA OFFICE REMODEL TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000115 LIST OF DRAWING

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate

More information

CONTRACT FOR PROFESSIONAL SERVICES CHAPTER TWO PROFESSIONAL S REQUIRED SERVICES

CONTRACT FOR PROFESSIONAL SERVICES CHAPTER TWO PROFESSIONAL S REQUIRED SERVICES Contract For Professional Services Chapter Two Professional s Required Services Rev. 05/16/12 Client Contract Number TABLE OF CONTENTS ARTICLE 1 GENERAL PROJECT SERVICES... 4 1.1 Essential Services...

More information

DRAFT AGREEMENT BETWEEN OWNER AND PROJECT ARCHITECT

DRAFT AGREEMENT BETWEEN OWNER AND PROJECT ARCHITECT DRAFT AGREEMENT BETWEEN OWNER AND PROJECT ARCHITECT This Agreement is made as of, 20 (the Effective Date ) MD ANDERSON AGREEMENT No. By and between The Owner: The University of Texas M. D. Anderson Cancer

More information

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

AMERICAN INSTITUTE OF ARCHITECTS (AIA) DOCUMENT SUMMARY

AMERICAN INSTITUTE OF ARCHITECTS (AIA) DOCUMENT SUMMARY AMERICAN INSTITUTE OF ARCHITECTS (AIA) DOCUMENT SUMMARY Conventional Project Family A101 2007 (formerly A101 1997) Standard Form of Agreement Between Owner and Contractor where the basis of payment is

More information

Florida Army National Guard Construction Facilities Management Office. Scope of Work:

Florida Army National Guard Construction Facilities Management Office. Scope of Work: Florida Army National Guard Construction Facilities Management Office Florida Armory Revitalization Program (FARP) Design Guidelines October 2008 Scope of Work: To provide complete design for the renovation/alterations

More information

AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES

AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES This Agreement, approved on January 20 th, 2009 by and between the Monroe County Community School Corporation, 315 North Drive, Bloomington, Indiana (hereinafter

More information

CONSTRUCTION MANAGEMENT CORE COMPETENCIES

CONSTRUCTION MANAGEMENT CORE COMPETENCIES CONSTRUCTION MANAGEMENT CORE COMPETENCIES A Guide to the Construction Management Core Competencies and their Body of Knowledge CM PROFESSIONAL PRACTICE... 1 CM PROJECT MANAGEMENT... 4 COST MANAGEMENT...

More information

1.1 THE ARCHITECT S SPECIFICATIONS AND DRAWINGS 1.2 THE BIDDING CONTRACTORS

1.1 THE ARCHITECT S SPECIFICATIONS AND DRAWINGS 1.2 THE BIDDING CONTRACTORS GENERAL The commercial bidding process is a well-defined path of positioning oneself to be the successful bidder amongst a group purporting to offer the same quality materials and labor. There are certain

More information

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Appendix A RFP No. 894-2014 Page 1 of 1 Template Version: SrC120131129 - Consulting Services RFP APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Revision: 2014-09-22 DEFINITION OF

More information

NOTICE TO BIDDERS. Bids will be publicly opened and read aloud at approximately 2:15pm in the Saugatuck-Douglas District Library.

NOTICE TO BIDDERS. Bids will be publicly opened and read aloud at approximately 2:15pm in the Saugatuck-Douglas District Library. SECTION 00 02 00 - NOTICE TO BIDDERS NOTICE TO BIDDERS Notice is hereby given that sealed bids will be received: By: Saugatuck-Douglas District Library 137 Center Street Douglas, MI 49406 For: Saugatuck-Douglas

More information

RECITALS. 1. District and Consultant previously entered into the Contract.

RECITALS. 1. District and Consultant previously entered into the Contract. SEVENTH AMENDMENT TO MASTER CONTRACT FOR PROFESSIONAL SERVICES FOR ARCHITECTURAL SERVICES DURHAM O&M BUILDING REMODEL PHASE 2 PROJECT NUMBER 6687 CLEAN WATER SERVICES AND MWA ARCHITECTS, INC. This Amendment,

More information

DRAFT AGREEMENT BETWEEN OWNER AND PROJECT ENGINEER

DRAFT AGREEMENT BETWEEN OWNER AND PROJECT ENGINEER DRAFT AGREEMENT BETWEEN OWNER AND PROJECT ENGINEER This Agreement is made as of, 20 (the Effective Date ) MD ANDERSON AGREEMENT No. By and between The Owner: The University of Texas M. D. Anderson Cancer

More information

CHAPTER 4: PROJECT MANUAL GUIDE

CHAPTER 4: PROJECT MANUAL GUIDE 4.01 GENERAL A. The Designer s requirements for preparation of a Project Manual are defined by the Agreement. This chapter provides the Owner s guidance for procedures and use of standard documents in

More information

2. Clarification: The building address is 801 Henderson Street.

2. Clarification: The building address is 801 Henderson Street. East Energy Structural Steel Painting University of South Carolina Project Number H27-Z037 Addendum One October 19, 2015 NOTE: The following amendments, additions, and deletions shall be made to the Construction

More information

EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN

EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN Financial Project ID: 417069-1-32-04 Work Program Item No.: N/A Federal Aid Project ID: County/Section No.:

More information

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax ADDENDUM 707 Minnesota Ave., Suite 506 Kansas City, Kansas 66101 Tel. 913.287.1900 Fax. 816.300.4102 www.wskfarch.com A r c h i t e c t u r e I n t e r i o r D e s i g n I l l u s t r a t I o n P l a n

More information

VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information

VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES Part I: Proposal Information A General Information The Village of Vernon Hills is soliciting proposals for construction

More information

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina Project Manual for Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina DWG Consulting Engineers 1009 Anna Knapp Blvd. Suite 202 Mt Pleasant, South Carolina 29464

More information

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR PROJECT MANUAL FOR Ogden Regional Medical Center 5475 South 500 East Ogden, UT 84405 for MountainStar Healthcare Construction Documents NJRA Architects, Inc. 5272 South College Dr. Murray, Utah 84123 Telephone:

More information

REQUEST FOR PROPOSALS AUDIT

REQUEST FOR PROPOSALS AUDIT REQUEST FOR PROPOSALS 2017-18 AUDIT PROFESSIONAL AUDIT SERVICES ANNUAL FINANCIAL STATEMENT PROPOSAL DEADLINE DATE Tuesday, February 6, 2018 at 3:00pm SUBMIT PROPOSAL TO: Ahmad Sheikholeslami Chief Business

More information

Request for Proposal. February 6, 2017

Request for Proposal. February 6, 2017 Request for Proposal Holy Redeemer Medical Office Building 1648-1650 Huntingdon Pike Huntingdon Valley, PA 19046 MANDATORY CONTRACTOR WALK-THRU: Wednesday, February 8, 2017 at 8:30 AM BIDS DUE: Monday,

More information

PUBLIC CONTRACT CODE SECTION

PUBLIC CONTRACT CODE SECTION PUBLIC CONTRACT CODE SECTION 22160 22169 22160. (a) The Legislature finds and declares that the design build method of project delivery, using a best value procurement methodology, has been authorized

More information

AGREEMENT BETWEEN OWNER AND ENGINEER FOR PROFESSIONAL ENGINEERING SERVICES FOR WATERMAIN EXTENSION FROM CASPIAN AVENUE CITY OF VOLGA, SOUTH DAKOTA

AGREEMENT BETWEEN OWNER AND ENGINEER FOR PROFESSIONAL ENGINEERING SERVICES FOR WATERMAIN EXTENSION FROM CASPIAN AVENUE CITY OF VOLGA, SOUTH DAKOTA AGREEMENT BETWEEN OWNER AND ENGINEER FOR PROFESSIONAL ENGINEERING SERVICES FOR WATERMAIN EXTENSION FROM CASPIAN AVENUE CITY OF VOLGA, SOUTH DAKOTA This Agreement, made and entered into this day of, 2018,

More information

Chapter 2 Parties to the Contract

Chapter 2 Parties to the Contract Chapter 2 Parties to the Contract 2.1 Introduction Construction work may include building of a new structure, additions, alterations, expansion, replacement, dismantling, erection, commissioning, rehabilitation,

More information

DEAN + TYLER + BURNS ARCHITECTURE

DEAN + TYLER + BURNS ARCHITECTURE DEAN + TYLER + BURNS ARCHITECTURE May 17, 2017 Community Safe Room for the City Springville 580 Indian Crest Drive Indian Springs, AL 35124 tel.: 205.427.7890 email: m@rchitecture-e.com ADDENDUM NO. 3

More information

1.3 CODES: All federal, state, and local codes applicable to the Project.

1.3 CODES: All federal, state, and local codes applicable to the Project. MINIMUM QUALIFICATIONS 1. Licensed Architect in New Mexico 2. Minimum of 5 years experience in building and structural design and implementation 3. Minimum of 5 years experience of architectural services

More information

REQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL SERVICES CLEARWATER PUBLIC SCHOOLS EWING PUBLIC SCHOOLS NELIGH-OAKDALE PUBLIC SCHOOLS

REQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL SERVICES CLEARWATER PUBLIC SCHOOLS EWING PUBLIC SCHOOLS NELIGH-OAKDALE PUBLIC SCHOOLS REQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL SERVICES CLEARWATER PUBLIC SCHOOLS EWING PUBLIC SCHOOLS NELIGH-OAKDALE PUBLIC SCHOOLS 1. REQUEST FOR PROPOSALS. Clearwater Public Schools, Ewing Public Schools,

More information

Construction Documents Education Program

Construction Documents Education Program PLANNING AND PRE-DESIGN THE CONSTRUCTION SPECIFICATIONS INSTITUTE 110 South Union Street, Suite 100 Alexandria, VA 22314-3351 www.csinet.org CDEP 1.0.1: 03-1 Copyright Materials This presentation is protected

More information

AGREEMENT BETWEEN ARCHITECT AND OWNER

AGREEMENT BETWEEN ARCHITECT AND OWNER AGREEMENT BETWEEN ARCHITECT AND OWNER By this AGREEMENT, effective this day of, 201, by and between Vail Unified School District No. 20 ("Owner"), an Arizona unified school district organized and operating

More information

CLEAN WATER SERVICES AND CAROLLO ENGINEERS, INC. RECITALS. 1. District and Consultant previously entered into the Master Contract.

CLEAN WATER SERVICES AND CAROLLO ENGINEERS, INC. RECITALS. 1. District and Consultant previously entered into the Master Contract. THIRTY-FOURTH AMENDMENT TO MASTER CONTRACT FOR WASTEWATER TREATMENT PLANT ENGINEERING SERVICES ROCK CREEK AWWTF DIGESTER 1 AND 2 MODIFICATIONS PROJECT NO. 6787 CLEAN WATER SERVICES AND CAROLLO ENGINEERS,

More information

City of Palo Alto (ID # 4369) City Council Staff Report

City of Palo Alto (ID # 4369) City Council Staff Report City of Palo Alto (ID # 4369) City Council Staff Report Report Type: Consent Calendar Meeting Date: 1/13/2014 Summary Title: Seismic Upgrade Project Amendment #1 w/ URS Title: Approval of Amendment Number

More information

City of Eagle Point 2017 Paving Instruction to Bidders

City of Eagle Point 2017 Paving Instruction to Bidders City of Eagle Point 2017 Paving Instruction to Bidders Issued: August 2, 2017 Closing Date and Time: Wednesday August 16, 2016 at 2:00 pm Project Summary The City of Eagle Point is requesting bids for

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Amounts Fee: $ Reimbursement: Reimbursables: $

Amounts Fee: $ Reimbursement: Reimbursables: $ [INSTRUCTIONS FOR COMPLETING THIS FORM ARE IN RED-COLORED ITALICS AND BRACKETS. COMPLETE EVERY FIELD AND DELETE ALL RED-COLORED TET INSTRUCTIONS, INCLUDING THE SHADING & BRACKETS.] B101 PROJECT ATTACHMENT

More information

CONSTRUCTION MANAGEMENT AGREEMENT

CONSTRUCTION MANAGEMENT AGREEMENT CONSTRUCTION MANAGEMENT AGREEMENT This Construction Management Agreement ( Agreement ) is made and entered into effective November 1, 2012, by and between the Newark Unified School District ( District

More information

CHAPTER 4: PROJECT MANUAL GUIDE

CHAPTER 4: PROJECT MANUAL GUIDE 4.01 GENERAL A. The Designer s requirements for preparation of a Project Manual are defined by the Agreement. This chapter provides the Owner s guidance for procedures and use of standard documents in

More information

TECHNICAL REVIEW DESIGN DEVELOPMENT PHASE

TECHNICAL REVIEW DESIGN DEVELOPMENT PHASE TECHNICAL REVIEW DESIGN DEVELOPMENT PHASE Document Quality and Coordination Drawings, specifications and Design Report are generally neat, clear, and accurate. Design documents are generally coordinated

More information

1ARCHITECTURE TABLE OF CONTENTS

1ARCHITECTURE TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 0102 COVER 00 0107 SEALS PAGE 00 0111 TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS 01 1000 01 2000 01 2100 01 2300 01

More information

PRIVATE PLAN ROOM. Document Information Sheet

PRIVATE PLAN ROOM. Document Information Sheet PRIVATE PLAN ROOM Document Information Sheet Job Name: Partial Renovation for Lewes Streets Department Breakroom Bid Date: October 22, 2018 2:00 pm Placed on file by: George, Miles, and Buhr Contact: Lee

More information

Architectural Services

Architectural Services Architectural Services 2016 Capital Improvement Program Request for Proposal Number: 18-20 Title of the Projects: Renovations to Weaver Middle School Procurement Department Bibb County School District

More information