A COMPARATIVE STUDY ON THE PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY OF SOUTH AFRICA

Size: px
Start display at page:

Download "A COMPARATIVE STUDY ON THE PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY OF SOUTH AFRICA"

Transcription

1 A COMPARATIVE STUDY ON THE PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY OF SOUTH AFRICA Oluwaseun O. Oshungade 1 and Deon Kruger 2 1 Postgraduate School of Engineering Management, University of Johannesburg, South Africa oluwaseun.oshungade@gmail.com 2 Department of Civil Engineering Science, University of Johannesburg, South Africa dkruger@uj.ac.za ABSTRACT An indicator of an effective construction industry is the completion of a construction project on time, on budget, and on specification, which are all considered to be major project objectives. However, in the South African context, over and above these criteria, empowerment and employment creation are also considered to be crucial project/client objectives. All of these project objectives may be impacted on by the procurement methods used. Typical procurement methods include traditional, design/build (DB), and construction management (CM) procurement techniques. This study compares these procurement methods which are all used within the South African construction industry in order to analyse and determine which method would best improve the project objectives. This study was carried out using a desktop study and an interview. The findings of this study show that the traditional method of procurement is currently the most used route used for procurement in construction project in South Africa. Moreover, the findings also reveal that using the DB method will improve the project/client objectives. Based on this, the study concludes that the DB method will produce the best outcome in terms of the project/client objectives in the South African construction industry. The study thus suggest that public sector clients such as government and city councils, should be advised on the benefits of using the DB methods for procurement of their construction projects, as it will lead to the accomplishment of most of their project objectives. Keywords: Construction industry, Construction management, Design/build, South African Construction projects, Traditional procurement. INTRODUCTION According to Sunjka and Jacob (2013), the construction projects involve processes which are complex and dynamic. Construction projects involve a number of stakeholders and discrete business individuals such as professionals, investors, manufacturers, trade contractors, and others (Sunjka and Jacob, 2013). A large range of infrastructural facilities such as housing, water, power supply, transportation, waste disposal and manufacturing, are been produce by the construction industry (Ibrahim et al. 2014). This industry also has an exceptional ability to develop individuals by providing for human daily needs, creating employment, and generating investment and therefore, the socio-economic impact of this industry on the economic growth of any nation can never be underscored (Ibrahim et al. 2014). In addition, governments utilise this industry to assist in economic recoveries from recessions (Baloyi and Bekker, 2011). As stated by the South African Construction Industry Status Report (2004) as cited by Baloyi and Bekker (2011), the industry amounts for over 10% of the world s economy. In South Africa (SA), the construction industry contributed to about 35% of the Gross Domestic Fixed Investment in 1997 (Nkado, 1999). However, for the construction industry to be effective, projects must be completed on time, on budget and on agreed quality. These triads time, cost (budget), and quality are often referred to as the primary project objectives which must be achieved in order for a construction project to be successful. Also, from a project management perspective, the fulfilment of these primary project objectives is seen as the main criteria for a successful project (Chan and Kumaraswamy, 1997). Using effective and efficient procurement methods are prerequisites for optimizing project performance (Oladinrin et al. 2013; Muriro and Wood, 2010). Procurement methods are referred to as a structured process or procedural method used by owners to acquire construction products and services (Oladinrin et al. 2013). These procurement methods are mainly categorised into two types traditional and alternative procurement method (Figure 1) (Thwala and Mathonsi, 2012). Procurement methods have undergone developments and refinements over the years. This is due to the inadequacies of the traditional procurement method which was the most common (and often the only) construction procurement method until the early 20th century (Konchar and Sanvido, 1998). Owing to the inadequacies of the traditional procurement method, researchers came up with innovative procurement methods often referred to as alternative procurement methods (Shrestha et al. 2012). These alternative procurement methods include the Design/Build (DB), the Construction Management (CM), and the Management Contracting Procurement (MCP) method (Shrestha et al. 2012). The aim of this study is to compare the different procurement methods used in the construction industry of SA. For the purpose of this study, the procurement methods are limited to DB and CM procurement method as an alternative to the 4» 3 rd IPMA Research Conference» ISBN:

2 traditional procurement method. Thus, this paper presents a comparative study on the procurement methods used in the construction industry of SA. PROCUREMENT METHODS Various terms have been used by a number of researchers and practitioners for the term procurement method. Related terms to procurement methods include terms such as project delivery methods, procurement systems, procurement routes, project approach and contractual arrangement. Hence, for this study the term procurement method is used. Procurement method is that method that is used in securing a project (Adenuga, 2013). According to Shrestha et al. (2012), the procurement method is a process by which the component of design and construction, including the roles and responsibilities of parties involved, sequences of activities, cost of materials and labour are combined to deliver a project. It is a method for clients/owners to provide and fund constructed facilities (Shrestha et al. 2012). Procurement methods have turn out to be a crucial subject in the construction industry because construction involves a series of processes that are interrelated and sequential for the procurement of construction projects (Oladinrin et al. 2013). The success or failure of projects depends on the effectiveness and efficiency of these processes. From the mid 1960s to date, a number of procurement methods have emerged and are in use in the construction industry (Adenuga, 2013). Figure 1 show the two principal procurement methods. Procurement Methods Traditional Alternative TRADITIONAL PROCUREMENT METHODS The traditional procurement method is that procurement method which offers the clients three separate sequential tasks of design, bid, and build (Oladinrin et al. 2013). This method has been in existence ever since the end of the 18th century (Mbanjwa, 2003). For this method, the client is leading the project. Also, the client is in contract with two entities, namely the design consultant and the contractor. The client relies on the design consultant who may be an architect or consulting engineer to carry out the design work and also supervise the construction (Thwala and Mathonsi, 2012). The design consultant prepares the design and contract documents for the project after which, the main contractor is then procured by invitation of bids based on the detailed design documents prepared by the client and design consultant (Eriksson and Westerberg, 2011). The main contractor can be appointed through one of these three tendering methods open, selective and negotiated tendering (Thwala and Mathonsi, 2012). ALTERNATIVE PROCUREMENT METHODS Figure 1: Classes of procurement methods The word alternative procurement method denotes every other procurement methods other than the traditional procurement method used in construction and may also be referred to as non-conventional procurement methods (Thwala and Mathonsi, 2012; Oladinrin et al. 2013). These non-conventional procurement methods do not only consider the design and build aspects of a project, but also considers operating, financing and the managing of the project (Thwala and Mathonsi, 2012). There are three main variants of alternative procurement method integrated, management-oriented, and collaborative procurement methods (Thwala and Mathonsi, 2012). The integrated procurement method is often referred to as DB procurement method. For the purpose of this study, both the DB procurement and CM procurement methods as variants of the managementoriented procurement method will be further discussed in the next two subsequent sections. Design/Build (DB) procurement methods The DB procurement method is a procurement method where the two sequential phases of design and build are recognised as a single task. This method gives the client a single point of contact in which the client is in contract with only one entity, namely the main contractor (Grobler and Pretorius, 2002). In this method of procurement, the main contractor is responsible for both the design and construction of the project and all the phases of project from conception through design and construction are handled by the main contractor (Oladinrin et al. 2013). There are three variants of the DB procurement method direct, develop and construct, and competitive (Mbanjwa, 2003). An example of a project where the DB procurement method was use by the City of Johannesburg as client is in the construction of Nelson Mandela Bridge (Grobler and Pretorius, 2002). ISBN: » 3 rd IPMA Research Conference» 5

3 Construction Management (CM) procurement methods This method unites the three-party construction players consisting of the client, the designer and the contractor in a nonadversary relationship (Oladinrin et al. 2013). It also provides the client with an opportunity to partake fully in the construction process. This method is a fee-based arrangement in which the construction manager is fully responsible to the client and acts in the client s interest during every phase of the project (Oladinrin et al. 2013). Under this arrangement, all construction contracts are implemented directly between the client and contractors. This method allows the construction work to be broken down into a number of trade contracts and various specialists eliminating the need for one or more main contractors (Mbanjwa, 2003; Oladinrin et al. 2013). An example of a project which the CM procurement method was utilised by the City of Johannesburg as client was during the construction of new taxi rank at the Park Station (Mbanjwa, 2003). Comparison of procurement methods The selection of the right procurement method is crucial for all project stakeholders and is an important element which adds to project success and the overall client s fulfilment (Muriro and wood, 2010). These procurement methods Traditional, DB and CM procurement methods all have both advantages and disadvantages. Therefore, in selecting the most appropriate procurement method for a particular project, the pros and cons need to be considered carefully. Table 1 presents some differences and similarities amongst the procurement methods. Konchar and Sanvido (1998) conducted research on the comparison of U.S. project delivery systems and they found that the DB procurement method achieves significantly improved cost and schedule advantages over the CM and traditional procurement methods. In addition, it will also produce equal and sometimes more desirable quality performance than CM and the traditional procurement methods. Recent research conducted on the effects of selected procurement systems on building project performance in Nigeria revealed that the DB method is more cost effective than the other methods (Oladinrin et al, 2013). In the same research, it was also found that the CM method is the most appropriate method for achieving best quality. Table 1: Comparison of the various procurement methods Traditional DB CM 1 Client design and construct sequentially Client design and construct simultaneously Client design and construct separately 2 Client selects a contractor to perform construction work Client selects a contractor to perform both design and construction work Client selects a contractor to perform construction management services and construction work 3 Two separate contracts One single contract Two separate contracts 4 Design company only provide the complete design document and contractor perform the construction Contractor/design company perform both the design and construction Contractor has significant input in the design process and also perform the construction PROCUREMENT PERSPECTIVES IN SOUTH AFRICA South Africa (SA) with its industrialised economy is faced with many socio-economic challenges. These challenges have an effect on the South African construction industry. As a result of these socio-economic challenges, project objectives are no longer being determined only in terms of the primary objectives of the project (Mbanjwa, 2003). As stated, the following are considered as secondary objectives of any public project: transfer of skills, community empowerment and employment creation for the upliftment of the socio-economic status of Historically Disadvantaged Individuals (HDIs) (Mbanjwa, 2003). Hence, in selecting the right type of procurement method for a particular project in SA, the primary and secondary objectives of a project must both be considered. Also, selecting the right type of procurement method depends on the type of client and project public or private sector client or project. In SA, the public sector project s objectives differ from those of the private sector. Public sector project objectives include both primary and secondary objectives while private sector project objectives mainly focus on the primary objectives of the project (Mbanjwa, 2003). Thus, procurement methods in use in SA will be compared to determine which one will best satisfy the different projects/clients objectives. PROCUREMENT METHODS IN SOUTH AFRICA Grobler and Pretorius (2002), highlighted the three types of procurement methods used in SA while Mbanjwa (2003), added Management Contracting Procurement (MCP), and Design and Manage (D&M) to this list. The involvement of the various project participants clients (public and private), designers and contractors in the different procurement methods and sectors are important when considering the best procurement method to use. The evaluation of the best procurement method is also based on the different project objectives/selection criteria in respect to the responses of the various project participants. 6» 3 rd IPMA Research Conference» ISBN:

4 Involvement of the project participants in the different procurement methods and project sectors The project participants include public and private sector clients, designers, and contractors. Table 2 present the analysis of a survey conducted by Grobler and Pretorius (2002) on the involvement of project participants in the building and civil engineering project sector in SA. The average percentage by weight of the different project sectors is indicated in the table. These percentage numbers indicate that the majority of the project participants fell into the category of civil engineering construction. This means that 51.3% of the project participants were engaged with civil engineering project while 48.7% of the project participants dealt with building projects. This implies that the majority of the project participants were involved with civil engineering projects. Table 3 present the breakdown of the survey conducted by Grobler and Pretorius (2002) on the involvement of the project participants on the use of the different procurement methods in SA. Comparing the usage of traditional, the DB, and the CM procurement methods with each project participants, it can be deducted that public sector clients, designers, and contractors use the traditional procurement method more than the other methods for execution of public construction projects in SA. On the other hand, the private sector clients utilize the DB method more than the other methods for private construction projects in SA. Table 2: Involvement of project participants in the building and civil engineering sector (Adapted from Grobler and Pretorius, 2002) Sectors Project Participants Building Civil Engineering Public sector clients 2% 98% Private sector clients 92.5% 7.5% Designers 35% 65% Contractors 66% 34% Average by weight 48.7% 51.3% Table 3: Involvement of project participants in the different procurement methods (Adapted from Grobler and Pretorius, 2002) Procurement methods Project Participants Traditional DB CM Other Public sector clients 54% 11% 0% 35% Private sector clients 30% 44% 5% 21% Designers 77% 19% 2% 2% Contractors 59% 29% 6% 6% Table 4 indicates the percentage by weight of the procurement methods used in construction projects in SA. From the table, it can be seen that the traditional procurement method has the highest percentage usage by weight. This can further be buttressed by the survey Mbanjwa (2003) carried out on the use of procurement methods for delivering construction projects in SA. His survey revealed that the Traditional procurement method was the most widely known method implying that the project participants have an excellent knowledge of this method. Table 4: Percentage by weight of the procurement methods (Adapted from Grobler and Pretorius, 2002) Procurement methods Project Participants Traditional DB CM Other Average by weight of project participants (%) ISBN: » 3 rd IPMA Research Conference» 7

5 Comparison of the procurement methods in terms of project objectives/selection criteria This section gives a comparison of the procurement methods in terms of time, cost and quality while the secondary project objective is also considered. The comparison of the procurement methods in terms of project objectives/selection criteria is shown in Table 5 (Adapted from Grobler and Pretorius, 2002). The table points out the average percentage number by weight of project participants whom are in support of each procurement method to have satisfied each project objectives/selection criteria listed in the table. From the table, it can be seen that the DB methods outweighs the traditional and CM methods. It must be noted that in Mbanjwa s survey (2003), he determined that the CM method will best satisfy the empowerment and employment creation as the secondary project objective criteria in the South African context. Table 5: Comparison of the various procurement methods in terms of project selection/objectives criteria (Adapted from Grobler and Pretorius, 2002) Project objectives/selection criteria Procurement methods Average by weight of stakeholders 1. Procurement method which can best DB 66.6% establish project cost before start of the Traditional 20.8% detailed design. CM and Other 12.6% 2. Procurement method which can best establish schedule. 3. Procurement method which leads to shorter project duration. 4. Procurement method which will give better value for money. 5. Procurement method which is best suited for large and complex projects. 6. Procurement method which is best suited for small projects. 7. Procurement method which is more flexible regarding changes to the scope of work. 8. Procurement method which leads to better communication between stakeholders. 9. Procurement method which have fewer disputes and claims. DB 66.5% Traditional 20.8% CM and Other 12.7% DB 77% Traditional 8.6% CM and Other 14.4% DB 60.5% Traditional 25.1% CM and Other 14.4% DB 41.7% Traditional 45.8% CM and Other 12.5% DB 66.9% Traditional 16.5% CM and Other 16.6% DB 60.5% Traditional 26.7% CM and Other 12.8% DB 70.9% Traditional 14.6% CM and Other 14.5% DB 79.3% Traditional 8.3% CM and Other 12.4% METHODOLOGY The aim of the study was to investigate the best procurement method which leads to the optimization of project/ client objectives within the SA construction industry. This study was carried out using a desktop study and an interview. A desktop study involved a critical review and analysis of related published literature relevant to the study. This relevant published literature, ranges from published articles, journal and magazine articles, and relevant books. Through these sources of information, much relevant data was obtained. This data can be quantitative data or qualitative data. Quantitative data deals with numbers while qualitative data deals with descriptions. In this study, quantitative data was obtained and used for the analysis of this study. In Section 3, the detail of the quantitative data obtained and used for the analysis of this study is presented. 8» 3 rd IPMA Research Conference» ISBN:

6 An interview is a purposeful interaction between two or more people (Saunders et al. 2012: 372). Interviews can be structured, semi-structured and in-depth (Saunders et al. 2012: 374). Structured interviews are used in descriptive study; semi-structured interviews are used in an explanatory study and in-depth interviews in exploratory study (Saunders et al. 2012: 377). In this study, a structured interview was used. The interview was conducted with a relevant stakeholder in the City of Johannesburg, which is the economic hub of South Africa. Table 6: Demographic information of the interviewed stakeholder Demographic information Sector Civil engineering Years of experience 14 years Employment category Client Qualification M.Sc. Role of employment Director Tables 6 and 7, presents the demographic information of the interviewed relevant stakeholder and a list of questions asked during the interview. Table 7: List of questions asked during the interview Procurement methods Description of questions Traditional DB CM Others Procurement method with the highest number of usage Procurement method which will best satisfy time Procurement method which will best satisfy cost Procurement method which will best satisfy quality Procurement method which will best lead to empowerment and employment creation Most preferred procurement method FINDINGS AND DISCUSSION The findings of this study are based on a literature review as well as interviews with a senior construction staff at the department of infrastructure and services in the City of Johannesburg. The details of the interview are discussed in the last paragraph of this section. The findings in terms of involvement of project participants in the different project sectors and procurement methods is as shown in Figures 2, 3 and 4 respectively. These figures are derived from Tables 2, 3, and 4 in Section 3. Figure 2 indicates the involvement of project participants in the different project sector and it can be deduced that the majority of the public sector clients deal with civil engineering project while a large component of the private sector clients are engaged with building project. Likewise, the designers and contractors also follow a split trend implying that a significant proportion of designers fall into the civil engineering project sector whereas a high number of the contractors fall into the building project sector. However, going by the average weight of the project participants, the split is almost 50/50 with the project participants dealing with either civil engineering or building projects. As shown in the figure, the public sector clients are the highest project participants dealing with civil engineering projects while their private counterparts are the lowest. This indicates that the South African government (public sector clients) invest largely in infrastructural projects rather than building projects. ISBN: » 3 rd IPMA Research Conference» 9

7 Procurement Methods Sectors Oshungade & Kruger 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Public sector clients Private sector clients Designers Contractors Average by weight of project participants Civil Engineering 98 7, ,3 Building 2 92, ,7 Figure 2: Involvement of project participants in the different construction sectors in SA Figure 3 presents the involvement of project participants in the different procurement methods and indicates that designers are the highest user of traditional procurement methods. Other project participants contractors, public sector clients and private sector clients are rated 2nd, 3rd and 4th respectively in terms of traditional procurement methods usage. Similarly, from the figure it can be seen that the private sector clients are the highest user of DB procurement method. Following closely to the private sector clients, is the contractors, while the designers are third in line while the public sector clients indicate the lowest usage. Likewise, the figure shows that the contractors are the highest user of CM, follow by private sector clients and designers. However, from the figure it shows that the public sector clients don t use the CM procurement method. In summary, the highest user of traditional, DB and CM procurement methods are designers, private sector clients and contractors respectively Traditional DB CM Other 10 0 Public sector client Private sector client Designers Contractors Project Participants Figure 3: Involvement of project participants in the different procurement methods in SA Figure 4 shows the percentage by weight of the procurement methods used for construction projects in SA. From the figure, the traditional procurement method has the highest percentage at 62%, followed by DB with 29%, with CM as the lowest at about 1%. From this, it is obvious that amongst the three procurement methods used for construction projects in SA, the traditional method despite its shortcomings, is still the most popular and frequently use method. This is probably due to its long and entrenched existence, less awareness by role players of the other procurement methods, the advantage of empowerment and employment creation offered, and reluctance to change by the South African construction industry project participants due to the South African government legislation on procurement. 10» 3 rd IPMA Research Conference» ISBN:

8 Procurement Methods Oshungade & Kruger Percentage by weight of the procurement methods CM Other 1% 8% DB 29% Traditional 62% Figure 4: Percentage by weight of the procurement methods used in SA From Table 5, it was seen by comparing the project objectives/selection criteria that the DB procurement method was most highly rated by all stakeholders. Figure 5 presents a comparison of the procurement methods in terms of the major project objectives of time, cost and quality and it can be seen that the DB method received the highest percentage score, followed by the traditional method and lastly the CM. This implies that the DB method will best fulfil/improve the major project objective of time, cost, and quality. Thus, the DB procurement method will produce the best result as compared with traditional and CM procurement methods in terms of the major project objectives of time, cost, and quality DB Traditional CM 10 0 Time Cost Quality Project Objectives Figure 5: Comparison of the procurement methods in terms of major project objective in SA Lastly, during interviews with a senior construction staff employed by the Department of Infrastructure and Services of the City of Johannesburg, it was revealed that the usage of the traditional procurement method for construction projects in SA is very high in comparison with the DB and CM methods (Manqoba, 2014). Comparing this finding with the presentation in Figure 4, it can be seen that both findings prove that the traditional procurement method is still the most popular method used in the South African construction industry. The reason for the high usage of the traditional procurement method for construction projects in SA is that it will best satisfy the secondary project objectives of empowerment and employment creation (Manqoba, 2014). This is due to the fact that the traditional method is fair, equitable, transparent and competitive (Manqoba, 2014). However, Mbanjwa s survey (2003) revealed that the CM method will best satisfy the secondary project objectives of empowerment and employment creation. Analysing this disagreement during the said interview, it was pointed out that this disagreement was because of the understanding that the process for the CM procurement method might not be fair, equitable, transparent and competitive (Manqoba, 2014). It was also pointed out during the interview that the DB procurement method is believed to be able to assist with achieving this secondary project objective (Manqoba, 2014). Furthermore, the DB method was preferred over the traditional and CM procurement method because the staff interviewed at the Department of Infrastructure and Services of the City of Johannesburg have experience with the DB method and have noted its benefits compared to the other methods (Manqoba, 2014). ISBN: » 3 rd IPMA Research Conference» 11

9 CONCLUSIONS AND RECOMMENDATIONS This study presents a comparative study on the traditional, DB and CM procurement methods used in the construction industry of SA. The findings of this study show that public sector clients are the main project participants dealing with civil engineering projects while their private counterparts are focuses more on building projects rather than civil engineering projects. This indicates that the South African government (public sector clients) invest largely into infrastructural projects rather than building project. Furthermore, the findings of this study revealed that the highest user of traditional, DB and CM procurement methods are designers, private sector clients and contractors respectively. Also, from the findings of this study it is discovered that amongst the traditional, DB, and CM procurement methods used for construction projects in SA, the traditional method is still and remains the most popular and frequently used method. Despite its shortcomings, it is still the commonly use method, probably because of its long existence, less awareness of other procurement methods by the various role players, the advantage it has for empowerment and employment creation, and the resistance to changes by the South African construction industry due to the South African legislation. Lastly, based on the findings of this study, it is concluded that the DB procurement method will produce the best result in terms of project objectives of time, cost, and quality as compared with traditional and CM procurement methods. Also, the DB method is believed to be able to achieve the secondary project objective of empowerment and employment creation in a way as revealed from the interviews with staff from the City of Johannesburg. However, from the discussions during the interview, it was highlighted that the traditional procurement method will best satisfy the project objective of empowerment and employment creation which is one of the major areas of concern of the SA government. This has a great impact on high and frequent usage of the traditional contract procurement method in SA. Based on the findings of this study, the study recommends that the public sector clients should be advised on the benefits of using the DB methods for procurement of their construction projects, as it will lead to the accomplishment of most of their project objectives. Also, it is recommended that a similar study be conducted with more detailed interviews and questionnaires because this study is based mainly on literature reviews and a limited interview due to time constraints. By doing this, it will help to validate the findings of this study. REFERENCES Adenuga, O.A. (2013). Comparison of the performance of traditional and direct labour methods of project procurement: A case study of some selected projects of the Nigerian Army. Ethiopian Journal of Environmental Studies and Management, 6(1): Baloyi, L. & Bekker, M. (2011). Causes of construction cost and time overruns: the 2010 FIFA world cup stadia in South Africa. Acta Structilia, 18(1): Chan, D.W.M. & Kumaraswamy, M.M. (1997). A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of Project Management, 15(1): Eriksson, P.E. & Westerberg, M. (2011). Effects of cooperative procurement procedures on construction project performance: A conceptual framework. Int. J. of Project Manage.,29(2): Grobler, K. & Pretorius, L. (2002). An evaluation of design-build as procurement method for building and civil engineering projects in South Africa. J. of the South African Institution of Civil Eng., 44(1): Ibrahim, I.I., Githae, W., & Stephen, D. (2014). Construction project procurement: project planning challenges of Nigerian Indigenous Contractors. Proceedings of the CIB W107 International Conference, Held January, 2014, (pp. 1-11). Lagos, Nigeria. Konchar, M. & Sanvido, V. (1998). Comparison of U.S. project delivery systems. Journal of Construction Engineering and Management, 124(6): Manqoba, S. (2014). Personal Communication, 31 st July, Department of Infrastructure and Services, City of Johannesburg, South Africa. Mbanjwa, S. (2003). The use and effectivness of construction management as a building system in the South African construction industry. M.S. thesis. Pretoria: Univ. Pretoria. Muriro, A. & Wood, G. (2010). A comparative analysis of procurement methods used on competitively tendered office projects in the UK. Proceedings of COBRA, Held 2-3 September, 2010, (pp. 1-16). Dauphine Université, Paris. Nkado, R.N. (1999). Competencies Required of Quantity Surveyors. Unpublished MBA research Report. Johannesburg: University of the Witwatersrand. Oladinrin, O.T., Olatunji, S.O., & Hamza, B.T. (2013). Effects of selected procurement systems on building project performance in Nigeria. International Journal of Sustainable Construction Engineering and Technology, 4(1): Saunders, M., Lewis, P., & Thornhill, A. (2012). Research Methods for Business students, 6 th ed. England: Pearson Education Limited. Shrestha, P.P., O Connor, J.T. & Gibson, G.E. (2012). Performance comparison of large Design-Build and Design-Bid-Build highway projects. Journal of Construction Engineering and Management, 138(1): South African Construction Industry Status Report. (2004). Synthesis Review of the South African Construction Industry and its Development, Discussion Document. Sunjka, B.P. & Jacob, U. (2013). Significant causes and effects of project delays in the Niger Delta region, Nigeria. Proceedings of SAIIE25, Held 9-11 July, 2013, (pp. 1 14). Stellenbosch, SA. Thwala, W.D. & Mathonsi, M.D. (2012). Selection of procurement systems in the South African construction industry: an exploratory study. Acta Commercii, 12: » 3 rd IPMA Research Conference» ISBN:

Appraising the State of Procurement Methods on Educational Building Projects in Abuja, Nigeria

Appraising the State of Procurement Methods on Educational Building Projects in Abuja, Nigeria Appraising the State of Procurement Methods on Educational Building Projects in Abuja, Nigeria Aje, Isaac O., Adedokun, Olufisayo A., & Igbalaye, Wasiu, O. Department of Quantity Surveying School of Environmental

More information

ASSESSMENT OF PROCUREMENT METHODS USED FOR EXECUTING MAINTENANCE WORKS IN LAGOS STATE. ADENUGA, O.A. 1 and DOSUMU, O.S. 2

ASSESSMENT OF PROCUREMENT METHODS USED FOR EXECUTING MAINTENANCE WORKS IN LAGOS STATE. ADENUGA, O.A. 1 and DOSUMU, O.S. 2 ASSESSMENT OF PROCUREMENT METHODS USED FOR EXECUTING MAINTENANCE WORKS IN LAGOS STATE ADENUGA, O.A. 1 and DOSUMU, O.S. 2 http://dx.doi.org/10.4314/ejesm.v5i4.s6 Received 16th August 2012; accepted 8th

More information

Design-Bid-Build Vs Design Build Projects: Performance Assessment of Commercial Projects In Sri Lanka

Design-Bid-Build Vs Design Build Projects: Performance Assessment of Commercial Projects In Sri Lanka Design-Bid-Build Vs Design Build Projects: Performance Assessment of Commercial Projects In Sri Lanka S. Ratnasabapathy and R. Rameezdeen Department of Building Economics, University of Moratuwa, Sri Lanka.

More information

PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY

PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY F.H.Mustapha, Department of Civil Eng. and Building, University of Glamorgan S.G.Naoum, Tarik Aygun, School of Construction

More information

Relationship between Design-Build Procurement Duration and Project Success

Relationship between Design-Build Procurement Duration and Project Success Relationship between Design-Build Procurement Duration and Project Success Migliaccio, G.C. Department of Civil Engineering, University of New Mexico (email: gcm@unm.edu) Bogus, S.M. Department of Civil

More information

Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa

Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa Abstract Mukuka MJ 1, Clinton Aigbavboa 2, and Wellington Thwala 3 The construction

More information

CAPITAL PROJECTS: PROCUREMENT & TENDERING STRATEGIES

CAPITAL PROJECTS: PROCUREMENT & TENDERING STRATEGIES Client Guide CAPITAL PROJECTS: PROCUREMENT & TENDERING STRATEGIES ABOUT THIS GUIDE: This quick reference guide is intended as an outline of the key procurement and strategies to be considered when undertaking

More information

CIDB PAPER 13 INVESTIGATION OF FACTORS THAT INFLUENCE THE SELECTION OF PROCUREMENT SYSTEMS OF THE SOUTH AFRICAN CONSTRUCTION INDUSTRY

CIDB PAPER 13 INVESTIGATION OF FACTORS THAT INFLUENCE THE SELECTION OF PROCUREMENT SYSTEMS OF THE SOUTH AFRICAN CONSTRUCTION INDUSTRY CIDB PAPER 13 INVESTIGATION OF FACTORS THAT INFLUENCE THE SELECTION OF PROCUREMENT SYSTEMS OF THE SOUTH AFRICAN CONSTRUCTION INDUSTRY Mathonsi, MD 1, Thwala WD 2 1. Department of Construction Management

More information

Unit 3: The Traditional Procurement Route

Unit 3: The Traditional Procurement Route Unit 3: The Traditional Procurement Route 3.1 Introduction This Unit briefly introduces the main features of the traditional procurement route as a widely used route that provides a good basis for examining

More information

ICES Core Cost Engineering Competencies

ICES Core Cost Engineering Competencies COST ENGINEERING CORE COMPETENCIES 2018 The quantity surveying competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off

More information

DR CLAIRE DEACON AND PROF JOHN SMALLWOOD NELSON MANDELA METROPOLITAN UNIVERSITY SOUTH AFRICA

DR CLAIRE DEACON AND PROF JOHN SMALLWOOD NELSON MANDELA METROPOLITAN UNIVERSITY SOUTH AFRICA INTERNATIONAL SEEDS CONFERENCE 2016 SUSTAINABILITY ECOLOGY ENGINEERING DESIGN FOR SOCIETY LEEDS, UNITED KINGDOM 14-15 SEPTEMBER 2016 THE INTEGRATION OF DESIGN, PROCUREMENT, AND CONSTRUCTION RELATIVE TO

More information

A quest for better quality in procurement delivery: A comparative analysis of design-build and traditional system

A quest for better quality in procurement delivery: A comparative analysis of design-build and traditional system ICEC2012 103 A quest for better quality in procurement delivery: A comparative analysis of design-build and traditional system Ramabodu, M.S. 1 and Verster, J.J.P. 2 1. Department of Quantity Surveying

More information

Analysis and Identification of Critical Factors of Delay in Construction Projects

Analysis and Identification of Critical Factors of Delay in Construction Projects Analysis and Identification of Critical Factors of Delay in Construction Projects 83 Analysis and Identification of Critical Factors of Delay in Construction Projects M.P.Venkatesh*, C.Umarani**, S. M.

More information

Progressive Design Build

Progressive Design Build Progressive Design Build July 19, 2018 Ash Dhingra P.E.,S.E TRADITIONAL PROCUREMENT Design-Bid-Build (DBB) Design to 100%, procurement (bid), and construction proceed sequentially Construction contract

More information

Member level the optimum standard is given against each activity statement

Member level the optimum standard is given against each activity statement QUANTITY SURVEYING CORE COMPETENCIES 2018 The quantity surveying competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off

More information

Estimating specialism core competencies

Estimating specialism core competencies CORE ESTIMATING COMPETENCIES 2015 The estimating competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off to a specific

More information

Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America)

Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America) Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America) 108 Appendix B: Questionnaire 109 CONSTRUCTION MANAGEMENT

More information

ASIAN JOURNAL OF MANAGEMENT RESEARCH Online Open Access publishing platform for Management Research

ASIAN JOURNAL OF MANAGEMENT RESEARCH Online Open Access publishing platform for Management Research Online Open Access publishing platform for Management Research Copyright by the authors - Licensee IPA- Under Creative Commons license 3.0 Research Article ISSN 2229 3795 Stakeholders perspective on cost

More information

1 Chapter one: Introduction

1 Chapter one: Introduction 1 Chapter one: Introduction 1.1 Background The nature of construction project delivery has changed greatly in the recent past with a lot more project owners requesting shorter delivery time and an early

More information

A COMMON PROCESS FOR SELECTING A CONSTRUCTION-PROJECT DELIVERY SYSTEM

A COMMON PROCESS FOR SELECTING A CONSTRUCTION-PROJECT DELIVERY SYSTEM A COMMON PROCESS FOR SELECTING A CONSTRUCTION-PROJECT DELIVERY SYSTEM Anat Chantemduang School of Civil Engineering, Faculty of Engineering, King Mongkut s Institute of Technology Ladkrabang, Bangkok,

More information

GAUTRAIN: SUCCESSFUL IMPLEMENTATION OF SOCIO ECONOMIC DEVELOPMENT OBJECTIVES ABSTRACT

GAUTRAIN: SUCCESSFUL IMPLEMENTATION OF SOCIO ECONOMIC DEVELOPMENT OBJECTIVES ABSTRACT GAUTRAIN: SUCCESSFUL IMPLEMENTATION OF SOCIO ECONOMIC DEVELOPMENT OBJECTIVES 1 CAREL VAN DER MERWE, 2 ELZER (JACK) VAN DER MERWE, 3 OLAUS AW VAN ZYL, 4 GEORGE NEGOTA 1 Executive Director, BKS (Pty) Ltd

More information

Assessment Project Management (PM) Roles Responsible for Abandonment of Construction Projects

Assessment Project Management (PM) Roles Responsible for Abandonment of Construction Projects Assessment Project Management (PM) Roles Responsible for Abandonment of Construction Projects Oluwaseun S. DOSUMU Sustainable Human Settlement and Construction Research Centre Faculty of Engineering and

More information

Procurement Options for NZ Construction Contracts

Procurement Options for NZ Construction Contracts 1 P a g e Tool Box Resource Procurement Options for NZ Construction Contracts A wide variety of contract arrangements have evolved in NZ for use on construction contracts. The following describes the most

More information

Evaluating the factors affecting Quality of Residential projects in Construction Industry

Evaluating the factors affecting Quality of Residential projects in Construction Industry Evaluating the factors affecting Quality of Residential projects in Construction Industry Ashish Mutha Sardar Patel college of Engineering, Mumbai Dr. Anil Ghadge Sardar Patel college of Engineering, Mumbai

More information

INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E.

INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E. INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E. Mohamed Salama 1, Moustafa Abd El Hamid and Bill Keogh School of Management and Languages, Heriot-Watt University, Riccarton,

More information

Commercial Planning Core Competencies PLANNING CORE COMPETENCIES 2018

Commercial Planning Core Competencies PLANNING CORE COMPETENCIES 2018 PLANNING CORE COMPETENCIES 2018 The competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off to a specific standard,

More information

Promoting social and economic objectives through procurement

Promoting social and economic objectives through procurement Promoting social and economic objectives through procurement The Standard for Infrastructure Procurement and Delivery Management (SIPDM) establishes developmental or secondary procurement policy relating

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

ECI: Two-Stage Contracts

ECI: Two-Stage Contracts ECI: Two-Stage Contracts Client and Contractor Considerations Michael Creedon Special Counsel ECI in Infrastructure and Major Projects Summit 2010 Sydney, 17 June 2010 Sessions Outline Introduction /

More information

Financial Provision for Construction Health and Safety (H&S)

Financial Provision for Construction Health and Safety (H&S) 1881 Financial Provision for Construction Health and Safety (H&S) John SMALLWOOD 1 and Fidelis EMUZE 2 1 Department of Construction Management, Nelson Mandela Metropolitan University, P.O. Box 77000, Port

More information

THE SELECTION OF SUBCONTRACTORS: IS PRICE THE MAJOR FACTOR?

THE SELECTION OF SUBCONTRACTORS: IS PRICE THE MAJOR FACTOR? THE SELECTION OF SUBCONTRACTORS: IS PRICE THE MAJOR FACTOR? Derek Lavelle 1, Jason Hendry and Glenn Steel School of the Built Environment, Northumbria University, Ellison Building, Ellison Place, Newcastle

More information

Procuring Infrastructure Public-Private Partnerships. Executive Summary

Procuring Infrastructure Public-Private Partnerships. Executive Summary Procuring Infrastructure Public-Private Partnerships Executive Summary 2018 2018 International Bank for Reconstruction and Development / The World Bank 1818 H Street NW Washington, DC 20433 Telephone:

More information

Condition of the South African Construction Industry as evaluated by Contractors, Employers and Agents

Condition of the South African Construction Industry as evaluated by Contractors, Employers and Agents ASOCSA2010-34 Condition of the South African Construction Industry as evaluated by Contractors, Employers and Agents Hendrik Jacobus Marx marxhj@ufs.ac.za of Quantity Surveying and Construction Management,

More information

PROF JOHN SMALLWOOD DEPT. OF CONSTRUCTION MANAGEMENT NELSON MANDELA METROPOLITAN UNIVERSITY SOUTH AFRICA

PROF JOHN SMALLWOOD DEPT. OF CONSTRUCTION MANAGEMENT NELSON MANDELA METROPOLITAN UNIVERSITY SOUTH AFRICA architecture OTHERWARE XXV INTERNATIONAL UNION OF ARCHITECTS CONGRESS DURBAN, SOUTH AFRICA, 4-9 AUGUST 2014 THE NEED FOR THE INCLUSION OF CONSTRUCTION HEALTH AND SAFETY (H&S) IN ARCHITECTURAL EDUCATION

More information

Economic Empowerment of Local Skilled Labour Through Force Account in Building Renovation

Economic Empowerment of Local Skilled Labour Through Force Account in Building Renovation Journal of Civil, Construction and Environmental Engineering 2017; 2(6): 159-164 http://www.sciencepublishinggroup.com/j/jccee doi: 10.11648/j.jccee.20170206.13 Case Report Economic Empowerment of Local

More information

The Influence of Project Documents on the Outcome of Construction Projects Procured by Traditional Contracts in Nigeria. Godwin Iroroakpo Idoro 1

The Influence of Project Documents on the Outcome of Construction Projects Procured by Traditional Contracts in Nigeria. Godwin Iroroakpo Idoro 1 Journal of Construction in Developing Countries, 17(1) 2012, 1 19, 2012 The Influence of Project Documents on the Outcome of Construction Projects Procured by Traditional Contracts in Nigeria Godwin Iroroakpo

More information

Exploring the Opportunities of Design and Build Contracts for the Construction Projects in Pakistan.

Exploring the Opportunities of Design and Build Contracts for the Construction Projects in Pakistan. Sixth International Conference on Construction in the 21 st Century (CITC-VI) Construction Challenges in the New Decade July 5-7 2011, Kuala Lumpur, Malaysia Exploring the Opportunities of Design and Build

More information

Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria

Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria Agu. N. N1 and Ibe, B. O. Department of Quantity Survey, Nnamdi, Azikiwe University, Awka, Anambra State, Nigeria

More information

The potential of knowledge management processes for facilitating PFI projects

The potential of knowledge management processes for facilitating PFI projects Loughborough University Institutional Repository The potential of knowledge management processes for facilitating PFI projects This item was submitted to Loughborough University's Institutional Repository

More information

2011 Proceedings of PICMET '11: Technology Management In The Energy-Smart World (PICMET)

2011 Proceedings of PICMET '11: Technology Management In The Energy-Smart World (PICMET) Towards a Framework for Human Resource Management Processes in the Mature Project Orientated Organisation: The Case for an ICT Organisation in South Africa Jacob Duif, Marie-Louise Barry Department of

More information

EVALUATION OF THE LEVEL OF COMPLIANCE WITH CONSTRUCTION DESIGN MANAGEMENT (CDM 2007) REGULATIONS BY CLIENTS IN NIGERIA

EVALUATION OF THE LEVEL OF COMPLIANCE WITH CONSTRUCTION DESIGN MANAGEMENT (CDM 2007) REGULATIONS BY CLIENTS IN NIGERIA EVALUATION OF THE LEVEL OF COMPLIANCE WITH CONSTRUCTION DESIGN MANAGEMENT (CDM 2007) REGULATIONS BY CLIENTS IN NIGERIA By A. O. Ogunde 1, D. J. Owolabi 1, P. O. Kukoyi 2 & O.C. Oloke 3 1 Department of

More information

Session THREE. Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: Self-directed (6 hours)

Session THREE. Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: Self-directed (6 hours) Session THREE Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: What type of tendering methods are there? What does qualification mean? Do you (the MC) bid for every job? Do you (the MC) price

More information

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES T.M.S. Elhag and A.H. Boussabaine School of Architecture and Building Engineering, The University of Liverpool, Liverpool L69 3BX, UK Understanding the

More information

PUBLIC-PRIVATE PARTNERSHIP

PUBLIC-PRIVATE PARTNERSHIP PUBLIC-PRIVATE PARTNERSHIP Law firm Sajic GP Banja Luka Bulevar vojvode Zivojina Misica 49B, Banja Luka Bosnia and Herzegovina Tel: +387 51 227 620 Fax: +387 51 227 623 e-mail: info@afsajic.com www.advokatskafirmasajic.com

More information

South Africa. Fluxmans Inc. 11 Biermann Avenue Rosebank 2196 Johannesburg Republic of South Africa

South Africa. Fluxmans Inc. 11 Biermann Avenue Rosebank 2196 Johannesburg Republic of South Africa South Africa Fluxmans Inc 11 Biermann Avenue Rosebank 2196 Johannesburg Republic of South Africa Tel: (27) (11) 328 1700 E-mail: gbrett@fluxmans.com Website: www.fluxmans.com 1.Does your legal system provide

More information

International Journal of Advanced Research in Engineering Vol 2(3) Jul-Sep 2016

International Journal of Advanced Research in Engineering Vol 2(3) Jul-Sep 2016 An Overview of Procurement Methods and Techniques for Effective Delivery of Construction Projects Abstract-Procurement processes in the construction industry are many and the choice of a suitable one depends

More information

1 July Guideline for Municipal Competency Levels: Head of Supply Chain and Supply Chain Senior Managers

1 July Guideline for Municipal Competency Levels: Head of Supply Chain and Supply Chain Senior Managers 1 July 2007 Guideline for Municipal Competency Levels: Head of Supply Chain and Supply Chain Senior Managers Municipal Regulations on Minimum Competency Levels issued in terms of the Local Government:

More information

A Business Model for Programme Managing the Supply Chain Portfolio

A Business Model for Programme Managing the Supply Chain Portfolio Introduction By Prof Pieter Steyn Effective and efficient management of is widely regarded as the key to optimal organisational performance. How to achieve this has remained a complex challenge to executives

More information

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA PROGRESSIVE DESIGN-BUILD Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA ADVANTAGES/DISADVANTAGES DESIGN BID BUILD (HARD BID) The traditional project delivery method, which customarily

More information

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan

More information

The Changing Face of Quantity Surveying Practices in Construction Industry

The Changing Face of Quantity Surveying Practices in Construction Industry The Changing Face of Quantity Surveying Practices in Construction Industry YESHWANTH BABU REDDY School of Architecture and Building Deakin University Table of Contents: 1.1 Background... 2 1.2 Introduction...

More information

Management Development Programme

Management Development Programme Development Programme PROJECT MANAGEMENT Introduction Name and Surname Your organisation and Department Occupation Any PM experience and / or training?? Family Something that most people don t know about

More information

of conduct for all parties engaged in construction procurement October 2003 development through partnership

of conduct for all parties engaged in construction procurement October 2003 development through partnership code of conduct for all parties engaged in construction procurement October 2003 development through partnership Code of Conduct for all Parties engaged in Construction Procurement - in terms of the Construction

More information

Compliance with Public Procurement Act and its Correlation with Procurement Performance of Senior High Schools in Ghana

Compliance with Public Procurement Act and its Correlation with Procurement Performance of Senior High Schools in Ghana Compliance with Public Procurement Act and its with Procurement Performance of Senior High Schools in Ghana Benjamin Adu-Fosu MBA Logistic and Supply Chain Management, Information Systems and Decision

More information

A Failure to Communicate

A Failure to Communicate A Failure to Communicate Professional liability insurers agree: the most effective step design firms can take to lessen the chances of a claim is to improve client communications. In fact, a study of more

More information

IDENTIFYING THE CRITICAL CAUSES OF CONFLICT IN CONSTRUCTION PROJECTS IN NIGERIA

IDENTIFYING THE CRITICAL CAUSES OF CONFLICT IN CONSTRUCTION PROJECTS IN NIGERIA Nigerian Journal of Technology (NIJOTECH) Vol. 35, No. 2, April 2016, pp. 290 296 Copyright Faculty of Engineering, University of Nigeria, Nsukka, Print ISSN: 0331-8443, Electronic ISSN: 2467-8821 www.nijotech.com

More information

SUBCONTRACTING IN THE SOUTH AFRICAN CONSTRUCTION INDUSTRY; OPPORTUNITIES FOR DEVELOPMENT

SUBCONTRACTING IN THE SOUTH AFRICAN CONSTRUCTION INDUSTRY; OPPORTUNITIES FOR DEVELOPMENT SUBCONTRACTING IN THE SOUTH AFRICAN CONSTRUCTION INDUSTRY; OPPORTUNITIES FOR DEVELOPMENT Copyright 2013 ISBN 978-0-620-56039-9 SUBCONTRACTING IN THE SOUTH AFRICAN CONSTRUCTION INDUSTRY; OPPORTUNITIES FOR

More information

CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA

CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA MJ Mukuka 1, CO Aigbavboa 2, and WD Thwala 3 Department of Construction Management & Quantity Surveying,

More information

Effects of construction projects schedule overruns: A case of the Gauteng Province, South Africa

Effects of construction projects schedule overruns: A case of the Gauteng Province, South Africa Available online at www.sciencedirect.com ScienceDirect Procedia Manufacturing 00 (2015) 000 000 www.elsevier.com/locate/procedia 6th International Conference on Applied Human Factors and Ergonomics (AHFE

More information

Project Procurement Considerations in This Market. October 14, 2016

Project Procurement Considerations in This Market. October 14, 2016 Project Procurement Considerations in This Market October 14, 2016 Overview Thank you for being here! Introduction About QBS Colorado Project Delivery Methods Market Information Federal & State Information

More information

Legal Alert? August 2011? Oil and Gas Local Content Act

Legal Alert? August 2011? Oil and Gas Local Content Act Legal Alert? August 2011? Oil and Gas Local Content Act In this Issue:- 1. Legal News? New Tenancy Law in Lagos. 2. Executive Summary on the Nigerian Oil and Gas Industry Content Development Act. 3. Full

More information

Inform Practice Note #7

Inform Practice Note #7 Inform Practice Note #7 May 2007 (Version 1 - May 2007) Subcontracting Arrangements cidb s Inform Practice notes provide guidance and clarity in achieving client objectives in construction procurement

More information

ANALYSIS OF DELAY IN EXECUTION OF CONSTRUCTION PROJECTS

ANALYSIS OF DELAY IN EXECUTION OF CONSTRUCTION PROJECTS ANALYSIS OF DELAY IN EXECUTION OF CONSTRUCTION PROJECTS P. Muralidhar 1, Rahul Kumar Jain 1, B. Srivasta 1, V. Poorna Chandra Rao 1 1 National Institute of Construction Management and Research (NICMAR),

More information

ICES Core Cost Engineering Competencies

ICES Core Cost Engineering Competencies CM CORE 1 Cost Engineering Commercial Management Core Competency Cost Engineering Specialism COMPETENCIES AND ASSESSMENT Financial and commercial processes in civil engineering January 2015 Technical Member

More information

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 Background A Task Force established by CIC Comprising Government, Clients, Consultants,

More information

SANRAL DELIVERING TOWARDS ECONOMIC GROWTH IN SOUTH AFRICA. Presenter : Zandile Nene Project Manager : Design & Construction SANRAL : Eastern Region

SANRAL DELIVERING TOWARDS ECONOMIC GROWTH IN SOUTH AFRICA. Presenter : Zandile Nene Project Manager : Design & Construction SANRAL : Eastern Region SANRAL DELIVERING TOWARDS ECONOMIC GROWTH IN SOUTH AFRICA Presenter : Zandile Nene Project Manager : Design & Construction SANRAL : Eastern Region CONTENTS 1. SANRAL background 2. SANRAL current network

More information

Available online at ScienceDirect. Procedia Manufacturing 3 (2015 )

Available online at  ScienceDirect. Procedia Manufacturing 3 (2015 ) Available online at www.sciencedirect.com ScienceDirect Procedia Manufacturing 3 (2015 ) 1690 1695 6th International Conference on Applied Human Factors and Ergonomics (AHFE 2015) and the Affiliated Conferences,

More information

Why the Construction Quality of Design-build Projects Is Not Satisfactory? A Queensland Study

Why the Construction Quality of Design-build Projects Is Not Satisfactory? A Queensland Study Why the Construction Quality of Design-build Projects Is Not Satisfactory? A Queensland Study Abstract David Balson 1, Jason Gray 2 and Bo Xia 3 Design-build (DB) system is well-known to be a popular and

More information

Pioneering Alternative Project Delivery in Ohio

Pioneering Alternative Project Delivery in Ohio Pioneering Alternative Project Delivery in Ohio Ali Bahar, PE Principal Engineer Metropolitan Sewer District of Greater Cincinnati Tim Koch, PE, Vice President, Brown and Caldwell 1 Agenda Construction

More information

Evaluation on the Application of Quality Management System in Tanzania Building Construction Projects

Evaluation on the Application of Quality Management System in Tanzania Building Construction Projects American Journal of Management Science and Engineering 2017; 2(6): 170-175 http://www.sciencepublishinggroup.com/j/ajmse doi: 10.11648/j.ajmse.20170206.12 ISSN: 2575-193X (Print); ISSN: 2575-1379 (Online)

More information

International Journal of Engineering Research and General Science Volume 4, Issue 4, July-August, 2016 ISSN

International Journal of Engineering Research and General Science Volume 4, Issue 4, July-August, 2016 ISSN Causes of Variation Orders on Public Building Projects in Addis Ababa Andualem Endris Yadeta 1 1 School of Civil and Environmental Engineering, Addis Ababa Institute of Technology, Addis Ababa University,

More information

Giorgiana Teccuci Aisha Nadar

Giorgiana Teccuci Aisha Nadar Giorgiana Teccuci Aisha Nadar Role of the Consulting Engineer in the Context of the New Yellow Book & its Dispute Board Provisions Agenda The FIDIC Contracts The Consulting Engineer and their role What

More information

UNIT 5. Bid Evaluation Committee - Goods

UNIT 5. Bid Evaluation Committee - Goods UNIT 5 Bid Evaluation Committee - Goods 1 1 Unit Outcomes Enabling Outcome 1: Explain the Composition and Functions of an Evaluation Committee for a Range of Commodities Enabling Outcome 2: Check standard

More information

Sample Social Clauses to Encourage Community Benefits from Waste

Sample Social Clauses to Encourage Community Benefits from Waste Sample Social Clauses to Encourage Community Benefits from Waste What are social clauses and community benefits? 1 The UK Sustainable Development Strategy has set the challenge of making the UK an EU leader

More information

SMS RETROFIT & PARTNERSHIP DELIVERY FRAMEWORK. An Introduction for SHAP Members

SMS RETROFIT & PARTNERSHIP DELIVERY FRAMEWORK. An Introduction for SHAP Members SMS RETROFIT & PARTNERSHIP DELIVERY FRAMEWORK An Introduction for SHAP Members SUREFIRE RETROFIT PARTNERSHIP & DELIVERY FRAMEWORK The SMS Retrofit Partnership & Delivery Framework was competitively tendered

More information

Comparing Suitability of NEC and FIDIC Contracts in Managing Construction Project in Egypt

Comparing Suitability of NEC and FIDIC Contracts in Managing Construction Project in Egypt Comparing Suitability of NEC and FIDIC Contracts in Managing Construction Project in Egypt Noha D. Rasslan B.Sc. in Construction Engineering and Management German University in Cairo Cairo, Egypt Ayman

More information

Assessing the impact of main contractor's site co-ordination on sub-contractors' performance in Hong Kong

Assessing the impact of main contractor's site co-ordination on sub-contractors' performance in Hong Kong Loughborough University Institutional Repository Assessing the impact of main contractor's site co-ordination on sub-contractors' performance in Hong Kong This item was submitted to Loughborough University's

More information

New England Environmental EXPO April 29, 30, May 1, 1997 World Trade Center, Boston, MA

New England Environmental EXPO April 29, 30, May 1, 1997 World Trade Center, Boston, MA New England Environmental EXPO April 29, 30, May 1, 1997 World Trade Center, Boston, MA PROCUREMENT FOR PUBLIC-PRIVATE PARTNERSHIPS FOR WATER AND WASTEWATER FACILITIES: HOW TO ELICIT TOP-QUALITY PROPOSALS

More information

Study of Delay Factors in Construction Projects

Study of Delay Factors in Construction Projects Study of Delay Factors in Construction Projects Shabbab Al Hammadi 1, M. Sadique Nawab 2 Assistant Professor, Civil Engineering Department, Shaqra University, Al Dawadmi, KSA 1 Lecturer, Civil Engineering

More information

Applying the procurement prescripts of the CIDB in the Public Sector

Applying the procurement prescripts of the CIDB in the Public Sector CONSTRUCTION PROCUREMENT BEST PRACTICE GUIDELINE #A2 Construction Industry Development Board Pretoria Tel: 012 343 7136 or 012 481 9030 Fax: 012 343 7153 E-mail: cidb@cidb.org.za 1. Introduction Applying

More information

Chapter 4 State Requirements for Educational Facilities Section 4.1

Chapter 4 State Requirements for Educational Facilities Section 4.1 providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,

More information

Prescription of qualifications. ARB Criteria at Parts 1, 2 and 3

Prescription of qualifications. ARB Criteria at Parts 1, 2 and 3 Prescription of qualifications ARB Criteria at Parts 1, 2 and 3 Approved: January 2010 Effective From: 2011/2012 Introduction Under the Architects Act 1997, the Architects Registration Board (ARB) has

More information

Kirk W Buffington, CPFIM, CPPO, C.P.M.,

Kirk W Buffington, CPFIM, CPPO, C.P.M., Kirk W Buffington, CPFIM, CPPO, C.P.M., An Overview We will be talking about: The elements of the RFP process Factors determining the selection of the procurement method The elements of risk and how they

More information

ADDENDUM NO. 1. Date: January 11, for. RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College. BID No.

ADDENDUM NO. 1. Date: January 11, for. RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College. BID No. ADDENDUM NO. 1 Date: January 11, 2017 for RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College BID No. 332 South Orange County Community College District General-All

More information

STUDY ON THE MANAGEMENT OF EPC PROJECTS

STUDY ON THE MANAGEMENT OF EPC PROJECTS International Journal of Civil, Structural, Environmental and Infrastructure Engineering Research and Development (IJCSEIERD) ISSN(P): 2249-6866; ISSN(E): 2249-7978 Vol. 5, Issue 3, Jun 2015, 11-22 TJPRC

More information

MANAGING OPERATIONAL SAFETY IN ALL PHASES OF THE LIFE CYCLE OF RAILWAY OPERATIONS

MANAGING OPERATIONAL SAFETY IN ALL PHASES OF THE LIFE CYCLE OF RAILWAY OPERATIONS MANAGING OPERATIONAL SAFETY IN ALL PHASES OF THE LIFE CYCLE OF RAILWAY OPERATIONS V M Panzera Pr. Eng. (Safety Advisor to the Railway Safety Regulator) ABSTRACT The National Railway Safety Regulator Act,

More information

GOVERNMENT OF GRENADA GEOTHERMAL RESOURCE DEVELOPMENT PROJECT

GOVERNMENT OF GRENADA GEOTHERMAL RESOURCE DEVELOPMENT PROJECT GOVERNMENT OF GRENADA GEOTHERMAL RESOURCE DEVELOPMENT PROJECT TERMS OF REFERENCE GEOTHERMAL ENERGY PROJECT COORDINATOR 1 P a g e 1. BACKGROUND The Government of Grenada wishes to progress the development

More information

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods PROCUREMENT 5/21/13 Agenda Common Tendering Systems Procurement Methods 1 Agenda Common Tendering Systems Procurement Methods Common Tendering Systems Competitive / Open-bid: (Qualified) contractors are

More information

Analysis and evaluation of criteria for pre-selecting contractors in the Saudi Arabian construction sector

Analysis and evaluation of criteria for pre-selecting contractors in the Saudi Arabian construction sector Loughborough University Institutional Repository Analysis and evaluation of criteria for pre-selecting contractors in the Saudi Arabian construction sector This item was submitted to Loughborough University's

More information

Evaluation and comparison of tenders and the use of procurement to promote industrial, social and environmental policies

Evaluation and comparison of tenders and the use of procurement to promote industrial, social and environmental policies 21 January 2009 Original: English United Nations Commission on International Trade Law Working Group I (Procurement) Fifteenth session New York, 2-6 February 2009 Evaluation and comparison of tenders and

More information

November, 2013 Vol 2 Issue 11 ISSN: (Online)

November, 2013 Vol 2 Issue 11 ISSN: (Online) ISSN: 2278 0211 (Online) An Analysis Of Procurement Procedures On The Implementation Of Government Construction Projects In Kenyan Public Universities: Case Study Of Masinde Muliro University Zuleha R.

More information

Investigation of Major Success Factors on Building Construction: the Case of Bole Sub City, Addis Ababa

Investigation of Major Success Factors on Building Construction: the Case of Bole Sub City, Addis Ababa Investigation of Major Success Factors on Building Construction: the Case of Bole Sub City, Addis Ababa Mamaru Dessalegn Belay Civil Engineering Jimma University; Institute of Technology Jimma, Ethiopia

More information

Comparisons of Procurement Characteristics of Traditional and. Labour-Only Procurements in Housing Projects in Nigeria

Comparisons of Procurement Characteristics of Traditional and. Labour-Only Procurements in Housing Projects in Nigeria Comparisons of Characteristics of Traditional and Labour-Only s in Housing Projects in Nigeria Olabode Ogunsanmi Department of Building, University of Lagos, Lagos * E-mail of corresponding author: bode_ogunsanmi2004@yahoo.co.uk

More information

Assessment of Cost Escalation and Overrun in Construction Projects

Assessment of Cost Escalation and Overrun in Construction Projects Assessment of Cost Escalation and Overrun in Construction Projects Mrs.Jeya Priya.R Assistant Professor Department of Civil Engineering, MNM Jain Engineering College, Anna University, Chennai-97. Abstract

More information

Conception Design Construction Operation.

Conception Design Construction Operation. 4 Development Process and Procurement 4.1 The development process by which the project moves from the earliest ideas to the final completion of the facilities and their use can be considered as having

More information

Capital City Partnership Chief Executive Officer Job Specification

Capital City Partnership Chief Executive Officer Job Specification Capital City Partnership Chief Executive Officer Job Specification TITLE: Chief Officer GRADE: 10 ( 48,490-57,926) RESPONSIBLE TO: Board of Directors Organisation Details The Capital City Partnership (CCP)

More information

GSR Management System - A Guide for effective implementation

GSR Management System - A Guide for effective implementation GSR Management System - A Guide for effective implementation 1 Introduction Governments are facing challenges in meeting societal expectations and have an interest in Governmental Social Responsibility

More information

i. SPECIALISED AREAS OF WORK

i. SPECIALISED AREAS OF WORK A OVERVIEW B2B (Pty) Ltd was established in 2012 as a consulting firm. The company comprises a team of professionals from various disciplines which include qualified, professionally registered engineers

More information

MATCHING A PROCUREMENT SYSTEM TO CLIENT AND PROJECT NEEDS: A PROCUREMENT SYSTEM EVALUATOR

MATCHING A PROCUREMENT SYSTEM TO CLIENT AND PROJECT NEEDS: A PROCUREMENT SYSTEM EVALUATOR MATCHING A PROCUREMENT SYSTEM TO CLIENT AND PROJECT NEEDS: A PROCUREMENT SYSTEM EVALUATOR M.D. AMBROSE and S.N. TUCKER CSIRO Building, Construction and Engineering, Melbourne, Australia Abstract The selection

More information

PPC2000: Association Of Consultant Architects Standard Form Of Project Partnering Contract

PPC2000: Association Of Consultant Architects Standard Form Of Project Partnering Contract PPC2000: Association Of Consultant Architects Standard Form Of Project Partnering Katie Saunders and David Mosey 1 Introduction PPC2000 (Mosey 2005) is a published form of multi-party contract for procurement

More information