Dilley ISD 2013 Bond Program Project Update Report March 11, 2015
|
|
- Claud Williamson
- 6 years ago
- Views:
Transcription
1 Dilley ISD 2013 Bond Program Project Update Report March 11, 2015 Professional Services Contracts o Program Management - TASB/SE: Executed 5/5/13 Work on-going o Architect BWA: Executed 2/20/13 Work on-going see other sections of this report o Survey Aerial - Geodetics: Approved by Board 8/29/13 Work complete and submitted to ISD 10/18/13 o Survey Topographic and Boundary Rothe Survey: Approved by Board 11/18/1 Boundary Surveying 100% complete Supplemental Topographic Survey -100% Complete o Geotechnical Terracon: Approved by Board 12/16/13 Final Reports submitted to Design Team High School 3/27/14 and Elementary 3/19/14 Material Testing contract approved by Board. Terracon has provided contract for execution by ISD. Fee is at budget of $80,000.) o Asbestos Sampling TASB/CAM Environmental: Sampling test results complete Asbestos Consultant CAM Environmental - provided contract and specs for consulting services Phase with Bid Open 10/31 Future phases will be bid separately (minor work at High School; future demo of any abandoned buildings at Elem). o Asbestos Consultant / Contractor Phase 1 Jupe Environmental: Award of Phase 1 scope to Jupe Environmental at 11/5/14 meeting Future phases will be bid separately. 1
2 o Construction Manager-At-Risk (CMR) Gallagher Construction: Contract approved by Board GMP approved by Board in February! Amendment to contract submitted for GMP (Guaranteed Maximum Price). TASB/SE provided several comments to Gallagher. Gallagher has revised and will submit to Dr. McLain for execution. o Off-Site Water Line Engineering Design KSA Engineers, Inc. selected: Provided updated cost estimate TASB/SE negotiated savings for project fees (survey and TxDOT permit) Contract to be presented to Board at March meeting. Schematic Phase - Approved by Board 3/3/14 o High School, Middle School, Elementary School Design Development / Construction Documents o High School - Field House o High School New Building o Middle School o Elementary School Construction Documents Re-Bid Package - submitted 12/5/14 Scope Includes: i. Elementary campus will remain as-is. (except certain Demo will be bid now direct by District for Phase 1 Asbestos Abatement Areas) ii. High School will not include remodel of existing high school spaces for Middle School iii. High School does not include culinary arts finish out iv. High School will not include parking, drives, Field House, and other areas north of the new educational building v. High School bid to include HVAC control system, 3rd science room, and batting cages o Fire Flow Test completed on 5/9/14; Follow Up Meeting with City held on June 4, 2014; Completed evaluation of Off-Site Water line vs Storage Tanks; the city water system works to install fire pumps off of city lines city has approved. New 12 water line from City Elevated Storage will be more economical than onsite storage. Line does benefit City but the City has NOT agreed to any costsharing. City will not include as Change Order with current utility project as our project will exceed the 25% Change Order cap permitted by state law. Separate project is needed for ISD to design and construct and then turn over to City to own and maintain after acceptance. 2
3 o Permit Fees charged by City - City offered to provide 25% off their new permit fee rates; Permit fees approximately $90,000. City has requested fee be submitted; ISD requested that City provide invoice so it can be processed. Project Budget o Current invoicing tracking spreadsheet maintained by TASB/SE updated for current February invoices received to date. o Budget update presented at February meeting based on GMP for new projects. 3
4 Project Schedule o 3/9/15 Pre-construction conference completed. o 3/16/15 - Mobilization and Construction o 3/23/15 - Elementary Ground Breaking o 4/20/15 High School Ground Breaking o Substantial Completion Dates - Move-In Summer-2016 Construction: o Portable Building Lease Mobile Modular: Delivered 7/8/14. Monthly payment on-going o Elementary Campus Asbestos Abatement Complete o Elementary Campus Phase 1 Demo and Asbestos Abatement Complete Final invoice being reviewed and processed o Elementary and High School Project: Gallagher contract amendment being processed to ISD Gallagher working on executing contracts with Subcontractors Notes from 3/9/15 Pre-Construction Meeting Attendees: DISD - Clint McLain and Javier Torres Gallagher - Bobby Phillips and Johnny Jones ( cell) TASB/SE - Albert Garza and Stephen Dorman AEP - Mike - majasso@aep.com, cell Terracon - AEP - discussed placement of poles and transformers for High School. discussed elementary. Need locations tied down. 3 Phase runs the long sweep 90 Bend have to be steel (4" with 48" Radius bend). They need easement for 15'x15' at transformer and 10' for line. (Need Survey exhibit with metes and bounds - as-built conditions but cannot set pad mount until easement is in place - TASB/SE to coordinate with surveyor). Contacts: DISD - Clint McLain and Javier Maintenance Director, Gallagher - Bobby PM and Johnny Superintendent for High School and Roger Superintendent for Elementary, TASB - Albert PM, SE - Stephen PM, BWA - Steve Johnson, Jay, Steve Shipp Gallagher control of subcontractors and workers - student no access, no smoking, identification - stickers on hard hats with Gallagher and numbered (background checks to be submitted for record - TASB/SE to follow up). Subcontractors - contract status and need list updated as we go Safety - they have weekly meeting with all subcontractors and discuss safety and then all trades meet as well. Fencing and Access Elementary - control access to keep students out. 4
5 Elementary will be issue with getting students to cafeteria (5th grade use the restrooms there). Discussed plan to fence off elementary. Gallagher to add temp walk (concrete) for 3rd grade building to allow access to cafeteria on south side of gym. Pre-K - 2nd to use route to south since almost same distance as routing through front and street. For older kid drop-off, need to go through middle of Pre-K - 2nd building and then out to south. (Need to send plan to teachers for new routes after spring break) Fencing and Access High School - Ag and Field House access is issue with initial underground work. Need to leave awning/sidewalk to access; will need to cut one section out and replace with temporary gravel. Cut off east access to student parking lot - entrance and exit to 117. Job Trailers - Gallagher plans 1 office trailer at elementary in front of cafeteria where bollards in parking lot are currently located. Gallagher plans 1 office trailer at High School (southwest corner possible but water is issue) Site security - no video; ISD has night security person. ISD has no plan for video during construction. Schedule - Elementary available now; Gym and Band Hall - access to this building after 03/13/15. Portable Building at High School still has ISD storage that needs to be relocated. SWPPP - 1 SWPPP with 2 site plans. Subcontractor will do monitoring. Summer School - High School was planning front side of building. Now planning to send to Middle School. Elementary summer school in 3rd grade building. Utilities - discussed utilities at both sites. Need to coordinate on gas at High School in particular. Harriman Street Water Line replacement by City - need to know schedule - replacement until after school is problematic (TASB/SE to contact TRC) Terracon for Construction Material Testing (CMT). Art Barrera is PM; Testing Contact TBD. Test Reports to all. Asbestos at high School - Need to test backside of high school where new will tie to new - 100'+/- of existing building; Will have new consultant. (TASB to coordinate for additional sampling - if needed - Sheet 2D2e) Construction set plans (when changes occur, will issue new plan sheet; addendum to not be changed on plans). ADA - Steve did receive ADA review (one restroom to be flipped; one landing to be enlarged) City Permit - City has asked for $90,000 fee. Need to advise City of construction when pull permits. Gallagher would like to setup Pre-Con with City. Asphalt subcontractor looking at credit if use geogrid. Shop Drawings - submit to BWA and TASB/SE at same time ASI - submittal log by BWA RFI - submittal log by Gallagher RFP - submittal log by BWA/Gallagher Agenda / Meetings - Gallagher to provide agenda for each meeting. Pay Requests - Gallagher to submit to BWA and copy TASB/SE. BWA will review and submit for payment. Does not need to go to board to approve but will need to provide for updates. 5
6 Groundbreaking(s) - March 23rd at 5:15pm for Elementary. April 20th at 5:15pm for High School. (TASB to provide invite) 6
Dilley ISD 2013 Bond Program Project Update Report June 14, 2016
Dilley ISD 2013 Bond Program Project Update Report June 14, 2016 Professional Services Contracts o Program Management - TASB/SE: Executed 5/5/13 Work on-going construction phase o Architect BWA: Executed
More informationDilley ISD 2013 Bond Program Project Update Report September 16, 2015
Dilley ISD 2013 Bond Program Project Update Report September 16, 2015 Professional Services Contracts o Program Management - TASB/SE: Executed 5/5/13 Work on-going construction phase o Architect BWA: Executed
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationRELATED DOCUMENTS & REQUIREMENTS
2 Existing Conditions NOTE: This is a new section, with content imported from other sections of the previous version of the KU Design Standards. Key revisions or additions to the earlier standards are
More information2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:
MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, 2007 North Medford High School: Project Summary: Renovate and add new addition based on facility evaluation and design.
More informationGREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015
GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations
More informationHOUSING AUTHORITY OF THE COUNTY OF SAN JOAQUIN
HOUSING AUTHORITY OF THE COUNTY OF SAN JOAQUIN INVITATION FOR BID (IFB) NO. 1415-003: GENERAL BUILDING CONTRACTOR, CLASS B MOUNTAIN VIEW REVITALIZATION PILOT PROGRAM, CONWAY HOMES AND SIERRA VISTA HOMES
More informationCARVER ELEMENTARY SCHOOL PROJECT January 2017 Monthly Status Report
CARVER ELEMENTARY SCHOOL PROJECT January 2017 Monthly Status Report Project: Current Phase: Construction Construction Type: New Construction Construction Start Date: 03Oct2016 Building Size (New): 112,350
More informationSALT LAKE CITY PUBLIC SAFETY BUILDING. (BID PACKAGE #3 Excavation, Shoring, Dewatering) PRE BID MEETING MINUTES. April 11, 2011
SALT LAKE CITY PUBLIC SAFETY BUILDING (BID PACKAGE #3 Excavation, Shoring, Dewatering) PRE BID MEETING MINUTES April 11, 2011 Team Introduction Troy Thompson Review Project Documents GSBS (Jeff Newman)
More informationJANUARY 25, 2016 ADDENDUM NO. 3 FOR. ORD Baggage Service Road Retaining Wall Repair
JANUARY 25, 2016 ADDENDUM NO. 3 FOR ORD Baggage Service Road Retaining Wall Repair Specifications and Contract Documents Number: 132110 CDA Project Number: H6163.15-02 For which bids are scheduled to be
More informationPre-Construction Meeting Minutes
Project Name Project # Project Address Tel: Fax: Gilbane Building Company Pre-Construction Meeting Date Start End Next Meeting Next Time Prepared By Company Purpose Location Next Location General Notes
More informationDAT MEETING NOTES # 3
DAT MEETING NOTES # 3 MOA ARCHITECTURE Design Advisory Team 821 17 th Street, Suite 400 Denver, Colorado 80202 303.308.1190 Phone 303.308.1197 Fax Project: Superior Elementary School Date: 16 December
More informationJanuary 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT
January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationOhlone Community College District
Bond Measure G March 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Closeout Progress
More informationRequest for Proposal for GC/CM Consultant Services Ferndale School District. Secondary High School GC/CM Program. October 19, 2018
Request for Proposal for GC/CM Consultant Services Ferndale School District Secondary High School GC/CM Program October 19, 2018 The Ferndale School District is requesting proposals for project management,
More informationREQUEST FOR PROPOSAL. Construction Management Services Not at Risk
REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk
More informationJune 12, 2017 Addendum #6 RFP # Modular Relocation & Site Development
June 12, 2017 Addendum #6 RFP #2017-003 Modular Relocation & Site Development Questions & Answers 1) To better facilitate a functional and qualified design build budget, please provide details, drawings,
More informationScope of Work Bid Package C-8 - West Overhead Doors
Scope of Work Bid Package C-8 - West Overhead Doors CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,
More informationCupertino Union School District
Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK
More informationMerritt Island High School
Project Project Update Update September April July 02, 8, 2010 2008 8, 2006 Project Project Manager Manager Anibal Gary Caussade Geiser Field Field Coordinator Bud Paul Mike Ball Friel Henry Mike Henry
More informationSANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016
FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 1 ACTIVE PROJECTS Santa Ana College Central Plant, Infrastructure and Mechanical Upgrades 2 COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements
More informationADDENDUM #1 Dated: August 14, Lubna Drive Water Booster Station Effective Water Storage Improvements Project Town of Christiansburg
Town of Christiansburg Lubna Drive Booster Station 8/14/2015 ADDENDUM #1 Dated: August 14, 2015 Lubna Drive Water Booster Station Effective Water Storage Improvements Project Town of Christiansburg 1.
More informationOwner's Representative Scope Matrix - D/B Rev 10/28/2013
Ecluded Owner's Representative Scope Matri - D/B Rev 10/28/2013 The following matri is a worksheet to identify required and optional scope for Owner's Representative services. Please identify the scope
More informationNEW NORWOOD HIGH SCHOOL
TOWN OF NORWOOD NEW NORWOOD HIGH SCHOOL MONTHLY PROGRESS REPORT MARCH 2010 Prepared by: 266 Main Street Suite 31A Medfield, MA 02052 www.compasspminc.com Table of Contents: I. Executive Summary II. III.
More informationScope of Work Bid Package C-4 - West Polished Concrete
Scope of Work Bid Package C-4 - West Polished Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,
More informationCapital Projects Progress Report. September Presented by
Capital Projects Progress Report September 2018 Presented by October 5, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York
More informationQ&A: The Block/Parsons Alley Construction RFP
Q&A: The Block/Parsons Alley Construction RFP 1. Is there a Geotechnical Report available? 2. Would it be possible to extend the bid date to a day other than a Monday? 3. Is it possible to extend the date
More informationCHARLES COUNTY GOVERNMENT ITB NO GOVERNMENT BUILDING ATRIUM RENOVATION
CHARLES COUNTY GOVERNMENT Department of Fiscal and Administrative Services Purchasing Division Telephone: 301-645-0656 July 26, 2017 ITB NO. 18-03 GOVERNMENT BUILDING ATRIUM RENOVATION ADDENDUM NUMBER
More informationRequest for Proposal: Due October 29, 2018, 2:00 pm
To Retrofit the Existing Restroom Building or Demolish the Current Building and Install a Pre- Fab Building at Valle Lindo Park Request for Proposal: Due October 29, 2018, 2:00 pm Bob Cerasuolo Park Services
More informationUniversity of Massachusetts Procurement Department 140 Hicks Way 407 Goodell Building Amherst, MA 01003
University of Massachusetts Procurement Department 140 Hicks Way 407 Goodell Building Amherst, MA 01003 May 16, 2016 Addendum #1 Contract Number: UMA16-25 Project Number: 1000730 Speedtype: 157194 Title:
More informationPort KC RFP NORTHLAND PARK BUILDING V
Port KC RFP NORTHLAND PARK BUILDING V 1. The RFP refers to landscaping plans. However, it does not appear that the landscaping plans were issued with the rest of the RFP. Will these be issued with an addendum?
More informationRFQ /ME - ADDENDUM 3
RFQ 150855/ME - ADDENDUM 3 RFQ Closing: November 3, 2015 at 2:00 PM (Local Time) Page 1 of 5_ RFQ Number: 150855/ME Date: October 26, 2015 RETURN SUBMITTALS AS SHOWN BELOW Copies of submittal required:
More informationCabrillo Unified School District Response Document 1 for Pilarcitos/ Hatch RFP for Lease-Lease Back Services
Cabrillo Unified School District Response Document 1 for Pilarcitos/ Hatch RFP for Lease-Lease Back Services 1. With a target construction start of 6/2015 we would like to know the current status or phase
More informationUNL East Campus Union OAC Meeting Minutes
November 5, 2018 UNL East Campus Union OAC Meeting Minutes TOPICS OF DISCUSSION: 1. Introductions/Attendance a. RDg Nick Schulz, Architect b. UNL Nate Perry, Project Manager c. UNL Sneha Bhoir, Project
More informationTime Item Notes: Presenter. 7:15-7:45 Washington Elementary Design Updates JJ Henri
WOODBURN SCHOOL DISTRICT 103 Bond Advisory & Accountability Committee Agenda Woodburn School District Office 1390 Meridian Drive May 17, 2017 6:30-8:30 pm Time Item Notes: Presenter 6:30-6:35 6:35-6:40
More informationEvanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201
Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October
More information(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet
(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet Project Name: UM Project # Design Professional: Meeting Place: Meeting Time:
More informationWEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES
1. Introduction WEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES The Town of West Yellowstone (Town) is seeking a qualified
More informationSMMUSD LINCOLN MIDDLE SCHOOL ATHLETIC FIELD PROJECT
ADDENDUM 01 SMMUSD LINCOLN MIDDLE SCHOOL ATHLETIC FIELD PROJECT 06/08/2017 DSA NO. A03-117787/File No.19-96 Prepared By DLR Group Project No. 75-07256-24 SECTION 00 91 00 GENERAL ADDENDUM 01 1.01 The following
More informationWILLIE L. BROWN JR. MIDDLE SCHOOL May 24, Willie L. Brown. Jr. Middle School. Design/Build Pre-Qualification Conference. Insert project image
WILLIE L. BROWN JR. MIDDLE SCHOOL May 24, 2012 Insert project image Agenda Call to Order Introduction of Project Team Members: SFUSD Consultants CM: Swinerton Management & Consulting John Baker Bridging
More informationBUREAU Joe Iuviene, AIA January 20, 2017
architectural BUREAU Joe Iuviene, AIA January 20, 2017 Alterations & Additions NEW TOWN HALL for TOWN OF AUSTERLITZ 816 State Route 203, Spencertown, New York 12165 ADDENDUM NO. 1 This addendum amends
More informationNovember 16, 2017 Addenda #1
University of North Carolina at Charlotte Science Building Project Early Package I Existing Building Heating Conversions SCO # 16-14355-02B November 16, 2017 Addenda #1 This Addendum has been issued to
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September
More informationJuly 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY
July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationOhlone Community College District
Bond Measure G February 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Schedule
More informationCAPITAL PROJECTS UPDATE
JULY 15, 2004 CAPITAL PROJECTS UPDATE ISSAQUAH SCHOOL DISTRICT CAPITAL PROJECTS DEPARTMENT Director Steve Crawford Project Coordinators Mike Archer Tom Mullins Royce Nourigat Office Staff Debbie Massaro
More informationREQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services
REQUEST FOR PROPOSALS Construction Manager CM Services Pre-Construction and Construction Services Big Sky Fire Department Station 1 Project Big Sky Fire District OWNER Big Sky, Montana November 2016 Request
More informationADDENDUM # 3 DATE: February 16, 2018
ADDENDUM # 3 DATE: February 16, 2018 REFERENCE: Invitation for Bid No.: S-LB-18607 IFB Issue Date: January 25, 2018 Title: Stonewall Middle School Addition and Renovations Architect/Engineer: Architecture
More informationFair Oaks Water District
Fair Oaks Water District Request for Proposal To develop a set of construction drawings, construction specifications and bid documents for a Skyway Well in Fair Oaks. (FOWD Job #C19WTSTSTHD) Prepared by:
More informationLa Porte Independent School District 2014 Bond Program Status Report August 11, 2015
La Porte Independent School District 2014 Bond Program Status Report August 11, 2015 La Porte ISD 2014 Bond Program ADMINISTRATION: Superintendent: Lloyd Graham Deputy Superintendent: Dr. Linda Wadleigh
More informationWORK AND PROJECT REQUIREMENTS
WORK AND PROJECT REQUIREMENTS BID PACKAGE 3A SITE CONCRETE & CONCRETE TURNKEY CRABAPPLE MIDDLE SCHOOL REPLACEMENT April 26, 2018 EXHIBIT B CONSTRUCTION DOCUMENTS AND SPECIFICATIONS shall be acknowledged
More informationUrban Development Unpacked: Crosstown Concourse
Urban Development Unpacked: Crosstown Concourse Thank You to our Annual Sponsors! GOLD SILVER BRONZE COMMUNITY CAPITAL GRINDER, TABER & GRINDER HIGHWOODS PROPERTIES INTEGRA REALTY SERVICES MALASRI ENGINEERING
More informationPhilip A. Ginsburg, General Manager Toks Ajike, Director, Planning and Capital Projects
Date January 17, 2017 To: Through: From: Subject: Recreation and Park Commission Capital Committee Philip A. Ginsburg, General Manager Toks Ajike, Director, Planning and Capital Projects Nicole Avril,
More informationRequest for Proposal Design Build Services Kiel High School Athletic Field Improvements
Request for Proposal Design Build Services Kiel High School Athletic Field Improvements I. General The Kiel Area School District is accepting written proposals from qualified firms to provide Design build
More informationMCER Study for Little Powder K-8
MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives
More informationREQUEST FOR PROPOSAL (RFP) for the Construction of Base Building Requirements for the new Alaska Gallery exhibit.
REQUEST FOR PROPOSAL (RFP) for the Construction of Base Building Requirements for the new Alaska Gallery exhibit. 1. INVITATION The Anchorage Museum is soliciting bids from qualified general contractors
More informationTOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR
February 5, 2018 SUMMARY OF CM/GC SELECTION PROCESS FOR DIMMIT II APARTMENT BUILDING The Town of Winter Park requests proposals from qualified Construction Manager / General Contractor (CM/GC) firms for
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report September 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationPre-Bid Request for Information Log
Page: 1 of 5 PB-001 PB #001 When will the bid be due? Bids are due April 29, 2016 at 3pm, hard copies as indicated in specification section 001100 page 1. CD WA HRCG PB-002 PB #002 Is it lump sum bid?
More informationQUESTIONS & ANSWERS ITB HELEN MCCALL PARK IMPROVEMENTS
QUESTIONS & ANSWERS ITB 017-030 HELEN MCCALL PARK IMPROVEMENTS QUESTION: Site Lighting. The prints show that the existing site lighting structures are to be relocated on site. Is this the only site lighting
More informationADDENDUM NO. 3. Project: GREENE COUNTY FSMF DOT BID PACKAGE #1
ADDENDUM NO. 3 Project: GREENE COUNTY FSMF DOT-170005 BID PACKAGE #1 Index of Contents Addendum No. 3... 3 Pages Pre-Bid Meeting Agenda... 4 Pages Pre-Bid Meeting EDGE Requirements... 2 Pages Pre-Bid Meeting
More informationUNC Charlotte Science Building Project Early Package 1. Pre-Bid Meeting: November 14, 2017
UNC Charlotte Science Building Project Early Package 1 Pre-Bid Meeting: November 14, 2017 Balfour Beatty Project Team Mike Bedell Project Executive Aaron Frederiksen Annie Hughes Project Manager Precon
More informationSECTION ADDENDUM NUMBER 1
University of South Carolina Rebid Sumwalt College Instructional Lab Renovation Columbia, South Carolina State Project #H27-Z254 GMKA Project #15053.01 PARTICULARS 1.01 DATE: NOVEMBER 18, 2016 SECTION
More informationUpdate on FCPS Construction/Renovation Projects. June 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationOwner s Meeting Minutes /27/11
Owner s Meeting Minutes 329 Attendees: M. Martinez A. Tomlinson A. Patterson C. Muldoon B. Englert L. Rosas L. McKinsey M. Wood T. Johns M. Schoeppner J. Baez N. Malone S. McMurray E. Colocho B. Young
More informationREYNOLDS MIDDLE SCHOOL BATHROOM ADA RENOVATIONS RFP Addendum #1 Prebid Meeting Notes 1:30pm, November 14, 2016
Attending: REYNOLDS MIDDLE SCHOOL BATHROOM ADA RENOVATIONS Jim Patton Patton Construction Group jimpatton@pattonconstructiongroup.com Ryan Jones J. Bartholomew, LLC info@div7.org Tom Stenzel Stenzel Development
More informationREQUEST FOR QUALIFICATIONS ARCHITECTURAL DESIGN SERVICES
Section I GENERAL NOTICE A. Owner: Metro Parks 1069 W. Main Street Westerville, Ohio 43081 REQUEST FOR QUALIFICATIONS ARCHITECTURAL DESIGN SERVICES B. Project: Highbanks Metro Park: Event Center at the
More informationEDS Upgrades and CBRA Improvements. Addendum No. 1 DATE OF ADDENDUM: 08/05/2016
EDS Upgrades and CBRA Improvements Addendum No. 1 DATE OF ADDENDUM: 08/05/2016 The following changes, additions, and/or deletions are considered as Addendum No. 1, and are hereby made a part of the contract
More informationSAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1
SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 PROJECT: Longfellow ES Exit Balcony Addition DATE: March 4, 2019 755 Morse Street, SF, CA 94112 SFUSD Project No.12059
More informationModular Unit Rental Route 309 Stockpile, PennDOT Montgomery County Maintenance Statement of Work
GOVERNING SPECIFICATIONS The purpose of this Invitation for Bid (IFB) is to procure a rented Modular Unit for the Pennsylvania Department of Transportation (hereinafter referred to as PennDOT) Montgomery
More informationADDENDUM # 01. Date: 5/4/2018. Pickens Area Bus Office Repaving Project. IFB Number:
ADDENDUM # 01 Date: 5/4/2018 Reference: IFB Number: 118-22-5-11 The following questions were submitted for clarification and/or to request additional information. All questions that were submitted are
More informationSECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN
SECTION 01 14 11 CONSTRUCTION OPERATIONS PART 1 - GENERAL 1.1 SUMMARY A. The Construction Operations Plan provides a coordinated construction environment to ensure an orderly, secure and safe operation
More informationUpdate on FCPS Construction/Renovation Projects. August 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationSAMPLE WORK PLAN. 2. Execute subcontractor agreements and gather forms and documentation required from each sub
SAMPLE WORK PLAN You have just been awarded a $500,000 construction contract as a prime bidder. You will perform 60% of the work in-house (including your suppliers) and 40% will be performed by 3 different
More informationINVITATION FOR BID FOR GENERAL CONTRACTORS
INVITATION FOR BID FOR GENERAL CONTRACTORS Arlington Public Schools Purchasing Department BID TITLE: BID #: ARLINGTON PUBLIC SCHOOLS REMOVAL AND REPLACEMENT OF THE STADIUM BLEACHERS AND PRESS BOX AT WAKEFIELD
More informationCompleted projects. Projects in progress. Program developments
1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationPROVIDENCE COLLEGE - RUANE FRIAR DEVELOPMENT CENTER
PROVIDENCE COLLEGE - RUANE FRIAR DEVELOPMENT CENTER NOTICE TO CONSTRUCTION MANAGERS: Dimeo Construction Company (DCC), Providence College s Owner Project Manager (OPM) is soliciting Guaranteed Maximum
More informationCOUNTY OF SAN JOAQUIN
June 4, 2012 COUNTY OF SAN JOAQUIN General Services Department 44 North San Joaquin Street, Suite 590 Stockton, California 95202-2778 (209) 468-3357, Fax (209) 468-2186 GABRIEL E. KARAM Director Capital
More informationMIRACOSTA COLLEGE. [X] MiraCosta College Bid Opportunities Website /FAX
MIRACOSTA COLLEGE BID ADDENDUM MiraCosta Community College District Distribution: One Barnard Drive [X] Owner [X] Architect Oceanside, California 92056 [X] MiraCosta College Bid Opportunities Website 760.795.6691/FAX
More informationManhattan Beach Unified School District
Manhattan Beach Unified School District Page 1 TABLE OF CONTENTS 1. Executive Summary... 2 1.1 Overview... 2 1.2 Summary of Progress... 3 2. Schedule... 4 2.1 Overview... 4 3. Financials... 4 3.1 Overview...
More informationMPA Project No. L1429-C1 Project Title: Terminal C Enhancements Location: Logan International Airport
MPA Project No. L1429-C1 Project Title: Terminal C Enhancements Location: Logan International Airport RESPONSES TO QUESTIONS and/or RFI s Date: 6/1/2018 The attention of Contractors submitting Filed Sub-Bids
More informationTRIAD ENGINEERING CONSULTANTS, INC.
TRIAD ENGINEERING CONSULTANTS, INC. 2638 Willard Dairy Rd Providing High Point, NC Suite 100 Plumbing, Mechanical and 27265 (336) 454-0225 Electrical Engineering Services Since 1984 admin@triadengmep.com
More informationVILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information
VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES Part I: Proposal Information A General Information The Village of Vernon Hills is soliciting proposals for construction
More informationEXPANSION & RENOVATION
ISSUE 04 NOVEMBER 2011 SAN JOSE CONVENTION CENTER EXPANSION & RENOVATION MONTHLY PROGRESS REPORT Project Summary CONTENTS Project Summary Expansion & Renovation Update Central Utility Plant Update Schedule
More informationLake County School District s. Construction Audit for. Eustis Heights Elementary School. Executive Summary & Detailed Audit Report
1 Lake County School District s Construction Audit for Eustis Heights Elementary School Executive Summary & Detailed Audit Report Fiscal Year 2014 2015 Completed By: Thomas A. Mock, CIA Date: August 27,
More informationAll subcontractor bidders are responsible for assuring that their subcontractors and vendors are properly apprised of the contents of this Addendum.
ADDENDUM NUMBER: 2 PROJECT: UNC Charlotte Residence Hall Phase XIV - Elevator Bid Package DATE: May 28, 2015 OWNER: UNC Charlotte ARCHITECT: FWA Group NOTICE TO BIDDERS: This addendum is issued prior to
More informationConstruction Administration Process
Construction Administration Process February 1, 2009 Division of Construction, MCPS START COMPLETED OPEN SCHOOL 25.6 1 ISSUE TICE TO PROCEED LETTER TO BOE ACCEPTS FROM 30 BOE MEMBER INSPECTS 29 TEACHERS
More informationWARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y
WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y 2 0 1 8 Agenda Overview of the Bond 2018 Work 2 Agenda Overview of the Bond 2018 Work 3 Overview of Bond Why Now? Interest rates remain at historic
More informationWINTERHAVEN PUBLIC SAFETY FACILITY PROJECT
WINTERHAVEN PUBLIC SAFETY FACILITY PROJECT Funded by: California Department of Housing and Community Development (HCD) through its Community Development Block Grant (CDBG) Program and the County of Imperial.
More informationCARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report
CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report Project: Current Phase: Construction Construction Type: New Construction Construction Start Date: 03Oct2016 Building Size (New): 112,350
More informationSouderton Area School District: Addition/Renovations to Shannock Valley Elementary School
Souderton Area School District: Addition/Renovations to Shannock Valley Elementary School ADDENDUM No. 1-E Issue Date: February 20, 2017 TO ALL BIDDERS: This addendum is issued to clarify, amend, or supersede
More informationAnswer: See Section clarification language provided in this addendum.
For work self-performed by the Contractor, the Contract shall primarily use the latest available calendar year issue of RS Means Facilities Construction Cost Data and the Cost Works electronic version,
More informationJune 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY
June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationCapital Projects Progress Report. January Presented by
Capital Projects Progress Report January 2019 Presented by February 8, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York 14428
More informationREQUEST FOR PROPOSAL Asphalt & Concrete Repair
REQUEST FOR PROPOSAL 2017 Asphalt & Concrete Repair English Landing Elementary School Union Chapel Elementary School Lakeview Middle School Park Hill High School Prairie Point Elementary School Congress
More informationProject Update. Facilities Committee Meeting
Lower Merion School District Project Update Close-Out Phase for Gladwyne Elementary School (Temp. CR s and Add ns/ Renov s) Penn Valley Elementary School (Add ns/ Renov s) Bala Cynwyd Middle Schools (Add
More informationC ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) Fax: (630)
C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) 353-8115 Fax: (630) 852-4709 BUILDING PERMIT INFORMATION PACKET Revised: October 2018 Building Codes: International Residential
More informationNEIDIG ELEMENTARY SCHOOL ADDITION & RENOVATION PHASING. Neidig Community Meeting July 2018
NEIDIG ELEMENTARY SCHOOL ADDITION & RENOVATION PHASING Neidig Community Meeting July 2018 PROPOSED NEIDIG ELEMENTARY SCHOOL Expanded parking Separate bus loop Gymnasium Addition 2 story classroom wing
More informationPRESENTATION JANUARY 24, 2017
4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction
More information