TEMPORARY EXCAVATION SUPPORT SYSTEM FOR A NEW RAILWAY BRIDGE AND HIGHWAY UNDERPASS IN PITTSBURGH

Size: px
Start display at page:

Download "TEMPORARY EXCAVATION SUPPORT SYSTEM FOR A NEW RAILWAY BRIDGE AND HIGHWAY UNDERPASS IN PITTSBURGH"

Transcription

1 TEMPORARY EXCAVATION SUPPORT SYSTEM FOR A NEW RAILWAY BRIDGE AND HIGHWAY UNDERPASS IN PITTSBURGH Andrew G. Cusing 1, Member, ASCE and Cristoper J. Lewis 2, P.E., Member, ASCE ABSTRACT: Until recently, traffic exiting Pittsburg would use te West End Bridge to cross te Oio River only to become entangled in te West End Circle, wic consisted of two railway overpasses eac out-of-alignment wit te West End Bridge. A roadway improvement project involving te construction of a new railway bridge and igway underpass was undertaken to eliminate tis traffic circle and provide a direct connection between te West End Bridge and State Route 19. Brayman Construction Corporation as since completed tis project. Tis paper provides a summary of te design and construction sequencing of a temporary seet pile excavation support system tat was constructed to facilitate te completion of tis project. Te excavation support system consisted of opposing seet pile walls (soring and ancor walls) cross-tied wit prestressed tendons beneat te railroad corridor. Te general arrangement of tis system is sown in Figure 1. Te prestressed tendons limited te orizontal wall displacement to permissible levels specified by te railway owner, and te reuse of te pase one soring wall as te soring wall for te second pase of bridge construction eliminated te need to extract and re-drive seeting, resulting in reduced displacements and construction time. INTRODUCTION For te construction of te West End improvement project described above, railway traffic on te existing embankment could not be interrupted, except for a brief period to sift tracks for eac pase of construction. Since te excavation support system was offset approximately 3 m (10 ft) from te centerline of te nearest track, te railway owner specified tat te cumulative orizontal displacement at te top of te wall be limited to 19 mm (0.75 in) to control vertical settlement of te railbed. (1) Assistant Project Engineer, agcusing@dappolonia.com; (2) Principal Engineer, cjlewis@dappolonia.com; D Appolonia, 275 Center Road, Monroeville, PA 15146; pone:

2 To satisfy tese stringent constraints, a continuous AZ-36 seet pile soring wall of 12.5 m (41 ft) maximum eigt was cross-tied beneat te railway corridor to an ancor wall consisting of discrete pairs of AZ-18 seet piling. Te use of prestressed tendon ties limited te orizontal movement of te top of te wall to 13 mm (0.5 in). Potos of te soring wall during construction are provided in Figures 2 and 3, and te key factors governing design and construction are described below. GEOTECHNICAL PROPERTIES AND RAILWAY LOADING Embankment materials at te site consist of random mixtures of soils, slag, cinders and rock fragments, wit a silty to clayey soil component predominating. Excluding outlier values, SPT N values between 10 and 35 blows per 305 mm penetration were typical. Te properties for tese embankment soils were adopted in accordance wit AREMA (2001) as follows: φ = 30 and γ = 17.3 kn/m 3 (110 pcf). Te railway loading applicable to te structural design of all wall components was governed by te Cooper E-80 configuration (AREMA, 2001), wit te maximum 356 kn (80 kip) axle load distributed over te minimum 1.52 m (5 ft) axle spacing and 2.59 m (8.5 ft) tie widt, resulting in a 90 kpa (1.88 ksf) vertical surface surcarge. Te orizontal component of tis vertical stress acting on te soring wall was conservatively calculated using a Boussinesq distribution for a frictionless, rigid wall, as prescribed by te railway owner for structural design. In analyzing te final condition, eac of te two tracks was loaded to te 90 kpa (1.88 ksf) vertical surcarge. However, for te construction conditions, te railway owner permitted te design load for te far track to be reduced to a vertical surcarge of 45 kpa (0.94 ksf). WALL CONFIGURATION AND GENERAL EXCAVATION AND CONSTRUCTION SEQUENCE Notably, te support system described erein constituted a more constructable and better performing alternate to te original concept, wic required continuous seet pile ancor walls and numerous tie rods, inerently imposed strict installation tolerances, and presumed sustained track outages wic were deemed unacceptable by te railway owner. Te alternate ancor wall was configured wit discrete pairs of seet piling and discrete wales to afford te contractor generous tolerances for tie installation. Also, strand ties were selected in lieu of tie rods to greatly reduce te number of ties and drilling requirements and provide better control of wall deflections. Additionally, te ancor wall alignment was sifted furter from te railroad tracks to enable te contractor to install te wall witout being restricted by railroad operations. Driving of Ancor and Soring Walls Te ancor wall seet piling (AZ-18, Grade 50) was first installed to te dept limits sown in Figure 1. After te railway tracks were relocated for te Pase 1 2

3 3 m Top of Wall EL m Level 1 Ties & Walers EL m 14.5 m 7-Strand Tie 5 Level 2 Ties & Walers EL m 4-Strand Tie 3 Final Excavation EL m Railway Embankment Fill Bottom Tip EL m Bottom Tip EL m SHORING WALL (AZ-36) ANCHOR WALL (AZ-18) NOTE: Horizontal Tie Spacing = 2.5 m (TYP.) FIG. 1. Cross Section of Temporary Cross-Tied Seet Pile Soring and Ancor Walls, Pase 1 Construction, at a Maximum Soring Wall Heigt of 12.5 Meters detour, te soring wall seet piling (AZ-36, Grade 50) was driven to te dept limits sown in Figure 1, wit te top of te soring wall at El m (782 ft). Initial Excavation for Temporary and Permanent Free-Cantilever An initial 1.52 m (5 ft) ig excavation to El m (777 ft) was advanced in front of te soring wall to establis a construction platform and work area. Te railway owner would not permit a temporary (construction) cantilever condition greater tan 3.66 m (12 ft) ig or a permanent cantilever condition greater tan 3.05 m (10 ft) ig and restricted te exposed lengt of te temporary 3.66 m (12 ft) ig cantilever to 30.5 m (100 ft) prior to Level 1 tie installation. Recognizing tese restrictions, a limited excavation was conducted in front of te soring wall to El m (770 ft; a temporary 3.66 m (12 ft) ig cantilever) for installation of an initial section of Level 1 ties at El m (772 ft). Level 1 Strand Tie Installation and Prestressing An excavation in front of te ancor wall to El m (766 ft) was required to install te Level 1, 7-strand ties, wic were spaced every 2.5 m. 3

4 FIG 2. Soring Wall Under Railway Loading FIG 3. Soring Wall After Installation of Level 2 Ties 4

5 Te strand ties were prestressed to 0.45 GUTS, usually from te soring wall side. As te strand ties along a given section of wall were stressed and locked off, te excavation limits were extended by an equivalent lengt to advance te installation of te remaining Level 1 ties. Excavation for Level 2 Strand Tie Installation and Pre-stressing After incrementally installing te Level 1 ties, te Stage 2 excavation to El m (753 ft) and El m (751 ft) in front of te soring and ancor walls, respectively, commenced to enable te installation of te Level 2, 4-strand ties spaced every 2.5 m at El m (755 ft). Once te Level 2 ties were installed and prestressed, backfill was placed in front of te ancor wall to approximate te original grade of te embankment. Final Dept of Excavation, Soring Wall Side Te critical portions of te soring wall employed two tie levels, as previously described, and required a final excavation to El m (741 ft), as sown in Figure 1, resulting in a 12.5 m (41 ft) ig wall. Only one tie level (8-strand ties) was required for te remaining portions of te wall were te final excavation line ranged from El m (753 ft) to El m (748.5 ft). Te final excavation for te abutment construction was pased to closely coincide wit te initiation of foundation construction. HORIZONTAL DISPLACEMENT PREDICTIONS AND MEASUREMENTS As noted previously, te design of te excavation support system was mainly driven by te railway owner s requirements to limit disruption of train traffic and control orizontal wall displacements and settlement of te railbed. In te following subsections, orizontal wall displacements for te cantilever (bot temporary and permanent) and single tie level conditions are evaluated. In addition, te observed displacements are discussed. Predicted Displacement Temporary and Permanent Cantilever Conditions Te soring wall orizontal displacement predictions presented in tis section apply to te temporary and permanent cantilever conditions (i.e., Stage 1 excavation for tie installation and permanent free cantilever wall sections). Te metod used to predict tese cantilever wall displacements involved a two-step process. First, te maximum orizontal displacement at te top of te wall associated wit te development of te active eart pressure was determined, witout consideration of te effect of te railroad surcarge. Te relationsips reported by Cloug and Duncan (1991) were employed. As a consequence of te pre-loading effect of te railway traffic on te existing embankment soils, te relationsip for medium-dense sand was adopted. On tis basis, te orizontal displacement required to mobilize te active eart pressure is approximately times te exposed cantilever wall eigt c. 5

6 Te additional effect of te railroad surcarge on te orizontal displacement was determined by introducing te factor f q, wic is computed as follows: f v q = 1+ = 1+ (1) σ σv were: = cange in orizontal stress at dept c (cantilever eigt) due to te orizontal component of te railroad surcarge; σ = orizontal effective stress at dept c due to te overburden (embankment) soil; v = cange in vertical stress at dept c due to te vertical component of railroad surcarge; and = vertical effective stress at dept c due to te overburden (embankment) soil. σ v Te values σ, σv, σ, and σ v are related to te coefficient of active eart pressure, K a as follows: σ 1 sin φ = = K a = (2) σ 1+ sin φ v v Te combined effect of active eart load and railway surcarge on te orizontal displacement (δ ) at te top of a cantliever wall of eigt c can ten be expressed as: δ = f (3) c q A friction angle ( φ) of 30 and unit weigt (γ) of 17.3 kn/m 3 (110 pcf) were used to calculate K a and σ v, consistent wit te prescribed properties. Te results of tis two-step procedure are summarized in Table 1. TABLE 1. Summary of Predicted Horizontal Displacements at Top of Wall for te Temporary and Permanent Cantilever Conditions Exposed Cantilever Maximum Horizontal Displacement at Top of Wall, δ mm (in) Heigt c, m (ft) Temporary Cantilever Condition Permanent Cantilever Condition 3.66 (12) (0.503) N/A 3.05 (10) N/A (0.564) Concerning values of c = 3.66 and 3.05 m (12 and 10 ft), te predicted maximum orizontal displacements at te top of te soring wall for bot te 6

7 temporary and permanent cantilever conditions are less tan te specified limit of 19 mm (0.75 in), wit values for te temporary condition approximating 13 mm (0.5 in). Tie Prestress and Predicted Wall Displacement - Single Tie Level In determining te required prestress for te upper tie level, te following incremental displacements for tree stages of construction were considered: Stage 1: Temporary 3.66 m (12 ft) cantilever wit ground surface at El m (782 ft) and cut to El m (770 ft) Displacement for tis stage is addressed in Table 1. Stage 2: Installation and Prestressing of Level 1 Strand Ties at El m (772 ft) Displacement reduction due to wall movement into te existing embankment. Stage 3: Excavation to El m (748.5 ft) Displacement at tis stage as two potential components: 3a.) Strand tie elongation (if te prestress level is less tan te actual induced reaction [presumed to be 0.6 GUTS]) 3b.) Structural cantilever movement (wit c = 3.05 m = 10 ft) above te tie level, wic occurs in response to te increase in railroad surcarge between te temporary and permanent conditions. Te average increase in orizontal surcarge pressure witin te top 3.05 m of te soring wall is approximately 4.8 kpa (0.1 ksf). Te calculations demonstrated tat a prestress level of 0.42 GUTS would control te maximum orizontal displacement of te top of te soring wall to less tan 19 mm (0.75 in). Terefore, a target prestress level of 0.45 GUTS was subsequently specified. Incremental and cumulative orizontal displacements for Stages 1 troug 3 are summarized in Table 2 for a prestress level of 0.42 GUTS. For sections of walls wit two rows of ties, and a final excavation to El m (741 ft), te effects of prestressing te bottom row of ties to 0.45 GUTS and te subsequent additional excavation were approximately equal and opposite, resulting in no appreciable influence on te resulting cumulative lateral displacement for te single tie condition provided in Table 2. Altoug prestressing te cross-tie tendons to te full design load of 0.6 GUTS would ave resulted in lower calculated orizontal wall displacements, tis option was not selected due to concern for potential strand overstress, especially considering tat a significant proportion of te design load was transient. Observed Displacements Te maximum orizontal displacement at te top of te soring wall during construction was no more tat 13 mm (0.5 inc), wic was somewat less tan te predicted value of 18.7 mm. Te conservative nature of te displacement estimate was most likely attributable to te fact tat te prescribed Cooper E-80 loading was 7

8 developed for steam locomotives, wic are generally eavier tan modern day diesel engines. TABLE 2. Summary of Predicted Incremental and Cumulative Horizontal Displacements at Top of Wall for Single-Tie Wall Section, wit 0.42 GUTS Tie Prestress Stage Baseline Horiz. Excavation Vertical RR El. m (ft) Surcarge T.O.W., mm (in) 1 Temp. Cantliever Near: 90 kpa δ 1 = 12.8 (0.503) 2 Level 1 Tie Prestressing (770.0) Far: 45 kpa δ 2 = (-0.916) 3 (a) Tie Elongation Near: 90 kpa δ 3a = 28.9 (1.139) 3 (b) Added RR Surcarge (748.5) Far: 90 kpa δ 3b = 0.3 (0.012) Predicted Cumulative Displacement Single Tie Wall Section δ = 18.7 (0.738) SUMMARY Tis paper as summarized te design and construction sequencing of a temporary excavation support system consisting of opposing seet pile walls (soring and ancor walls) cross-tied wit prestressed tendons beneat a railroad corridor to facilitate te construction of a new railway bridge and igway underpass in Pittsburg s West End. Te orizontal offset of te proposed ancor wall from te soring wall, as sown in Figure 1, was greater tat set for fort in te original design, wic permitted continuous operation of railway traffic during all pases of construction, wit te exception of brief periods for track relocation for eac pase of bridge construction. Also, te use of prestressed tendon ties limited te orizontal wall displacement to permissible levels specified by te railway owner. In addition, te reuse of te soring wall from Pase 1 bridge construction as te soring wall for te second pase eliminated te need to extract and re-drive seeting, wic resulted in reduced displacements and construction time. REFERENCES AREMA (2001). Manual for Railway Engineering, American Railway Engineering and Maintenance-of-Way Association. Cloug, G.W. and Duncan, J.M. (1991). Eart Pressures, Foundation Engineering Handbook (Capter 6), Second Edition, Y.H. Fang, Ed., Van Nostrand Reinold, New York. 8

CE 115 Intro to Civil Eng: Geotechnical Engineering Soil Pressure Acting on Wall

CE 115 Intro to Civil Eng: Geotechnical Engineering Soil Pressure Acting on Wall CE 115 Intro to Civil Eng: Geotecnical Engineering Soil Pressure Acting on Ground Surface Soil Pressure Were: σ = soil pressure acting on wall φ k a = tan 2 45, active eart pressure coefficient 2 γ = unit

More information

Steel Pipe Bridges in Sweden Detailed Design Procedures

Steel Pipe Bridges in Sweden Detailed Design Procedures Steel Pipe Bridges in Sweden Lars Pettersson, Skanska Sweden AB, Major Projects 2007-06 1 In Sweden Steel Pipe Bridges are structurally designed according to a andbook developed by te oyal Institute of

More information

Estimation of Critical Stress in Jointed Concrete Pavement

Estimation of Critical Stress in Jointed Concrete Pavement Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Beavioral Scien ce s 04 ( 03 ) 08 7 nd Conference of Transportation Researc Group of India (nd CTRG) Estimation of Critical

More information

Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River

Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River DEEP FOUNDATIONS 207 Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River W. Robert Thompson, III, 1 M.ASCE, P.E., Jeffrey R. Hill, 2 M.ASCE, P.E., and J. Erik Loehr,

More information

TECHNICAL NOTE. On Cold-Formed Steel Construction DESIGN CONSIDERATIONS FOR FLEXURAL AND LATERAL-TORSIONAL BRACING

TECHNICAL NOTE. On Cold-Formed Steel Construction DESIGN CONSIDERATIONS FOR FLEXURAL AND LATERAL-TORSIONAL BRACING TECHNICAL NOTE On Cold-Formed Steel Construction Ligt Gauge Steel Engineers Association Wasington, D.C. Toll-Free: 1 (866) 465-4732 www.lgsea.com $5.00 DESIGN CONSIDERATIONS FOR FLEXURAL AND LATERAL-TORSIONAL

More information

2.36 Bridge Inspections. Introduction. Scope and Objective. Conclusions

2.36 Bridge Inspections. Introduction. Scope and Objective. Conclusions Introduction Te Department of Works, Services and Transportation is responsible for construction, inspection and maintenance of bridges in te provincial road system. Te Transportation Services Division

More information

Northport Berth 3 design and construction monitoring

Northport Berth 3 design and construction monitoring Proc. 18 th NZGS Geotechnical Symposium on Soil-Structure Interaction. Ed. CY Chin, Auckland Lucy Coe, Nicola Ridgley, Do Van Toan Beca Infrastructure Limited, Auckland, NZ Keywords: retaining wall, deflections,

More information

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5 .364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. Due: Friday December 2. This question concerns the stability of an open slope cutting that will be used to provide construction access for a 3.2m deep

More information

Design of Earth Dams. Earth Dam Components

Design of Earth Dams. Earth Dam Components Design of Eart Dams Eart Dam Components 1 Design Requirements Types of Eart Dams Oter Types of Dams Concrete Roller Compacted concrete Debris flows Coice of Type Depends on Availability of materials Trucking

More information

CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS

CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 539 NOVEMBER 2014 CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS TABLE OF CONTENTS 539.01 SCOPE 539.02 REFERENCES 539.03 DEFINITIONS

More information

( h) ( ) Effect of Boiler Pressure (Using Molliar Diagram i.e., h-s diagram) We have, but W P << W T. = = h h h h

( h) ( ) Effect of Boiler Pressure (Using Molliar Diagram i.e., h-s diagram) We have, but W P << W T. = = h h h h Effect of Boiler Pressure (Using Molliar Diagram i.e., -s diagram) We ave, ( 3 ) ( 4 ) η t but W P P > P for te fixed

More information

Upon speaking with the representatives with Technical Foundations as well as Walder Foundations, it was determined that:

Upon speaking with the representatives with Technical Foundations as well as Walder Foundations, it was determined that: As part of our analyses, we have considered the design and construction of the cantilever retaining wall that will be located along the north side of Lucks Lane, between Falling Creek and Gladstone Glen

More information

CHAPTER 5 GENERAL BUILDING LIMITATIONS

CHAPTER 5 GENERAL BUILDING LIMITATIONS CHAPTER GENERAL BUILDING LIMITATIONS SECTION 0 GENERAL 0. Scope. Provisions of tis capter sall govern te eigt and area of buildings. For definitions, see Capter. SECTION 0 DEFINITIONS SECTION 03 HEIGHT

More information

ONTARIO PROVINCIAL STANDARD SPECIFICATION

ONTARIO PROVINCIAL STANDARD SPECIFICATION ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 539 NOVEMBER 2003 CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS TABLE OF CONTENTS 539.01 SCOPE 539.02 REFERENCES 539.03 DEFINITIONS 539.04

More information

A Study on Pendulum Seismic Isolators for High-Rise Buildings

A Study on Pendulum Seismic Isolators for High-Rise Buildings ctbu.org/papers Title: Autors: Subjects: Keywords: A Study on Pendulum Seismic Isolators for Hig-Rise Buildings Ikuo Tatemici, Maeda Corp. Mamoru Kawaguci, Kawaguci & Engineers Masaru Abe, Hosei University

More information

Implementation of this Special Provision requires a complete understanding of the following documents:

Implementation of this Special Provision requires a complete understanding of the following documents: VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR Quality Assurance/Quality Control (QA/QC) for the Construction of Deep Foundation Systems for Design-Build and PPTA Contracts November 10, 2009

More information

Comparison of Empirical Fragmentation Models at the Gol-Gohar Iron Ore Mine

Comparison of Empirical Fragmentation Models at the Gol-Gohar Iron Ore Mine In te Name of God Comparison of Empirical Fragmentation Models at te Gol-Goar Iron Ore Mine Dr. Moammad Taji 24-26 August 2015 Sydney, Australia Contents 2 Introduction Fragmentation surely is one of te

More information

KEYSTONE COUNTRY MANOR SYSTEM DESIGN CHARTS

KEYSTONE COUNTRY MANOR SYSTEM DESIGN CHARTS KEYSTONE COUNTRY MANOR SYSTEM DESIGN CARTS Design Details Design Assumptions Friction angle (PI) for earth pressure calculations of geogrid reinforced walls is evaluated at 26, 0 and 4 only. For other

More information

Chapter 2. Functions and Graphs. 03 Feb 2009 MATH 1314 College Algebra Ch.2 1

Chapter 2. Functions and Graphs. 03 Feb 2009 MATH 1314 College Algebra Ch.2 1 Capter Functions and Graps 03 Feb 009 MATH 1314 College Algebra C. 1 .1 Basics of Functions & Teir Graps 03 Feb 009 MATH 1314 College Algebra C. Objectives Find te domain & range of a relation. Evaluate

More information

20 th STATEWIDE CONFERENCE ON LOCAL BRIDGES. Excavation Protection System Planning & Design

20 th STATEWIDE CONFERENCE ON LOCAL BRIDGES. Excavation Protection System Planning & Design 20 th STATEWIDE CONFERENCE ON LOCAL BRIDGES Excavation Protection System Planning & Design Syracuse, New York 5 November 2014 Training Manual Excavation Protection System Planning & Design Syracuse, New

More information

UPRR GUIDELINES FOR TEMPORARY SHORING Scope. General Criteria. FROM:

UPRR GUIDELINES FOR TEMPORARY SHORING Scope. General Criteria. FROM: UPRR GUIDELINES FOR TEMPORARY SHORING 4-10-2013 FROM: http://www.uprr.com/aboutup/operations/specs/shoring/index.shtml Scope The scope of these guidelines is to inform public agencies, design engineers,

More information

ANALYSIS OF TENSION MEMBERS

ANALYSIS OF TENSION MEMBERS CHATER Structural Steel Design LRFD Metod Tird Edition ANALYSIS OF TENSION MEMBERS A. J. Clark Scool of Engineering Department of Civil and Environmental Engineering art II Structural Steel Design and

More information

SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2

SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2 ABSTRACT SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR Robert Small 1, Rob Jameson 2 Seismic Upgrade of the University Mound Reservoir North Basin included 542 micropiles with 1335 KN (300 kip) design capacity

More information

UNDERPINNING A CRANE FOUNDATION

UNDERPINNING A CRANE FOUNDATION UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New

More information

Introduction of Prediction Method of Welding Deformation by Using Laminated Beam Modeling Theory and Its Application to Railway Rolling Stock

Introduction of Prediction Method of Welding Deformation by Using Laminated Beam Modeling Theory and Its Application to Railway Rolling Stock IJR International Journal of Railway Vol., No. 4 / December 009, pp. 175-179 Introduction of Prediction Metod of Welding Deformation by Using Laminated Beam Modeling Teory and Its Application to Railway

More information

Table of Contents 18.1 GENERAL Overview Responsibilities References

Table of Contents 18.1 GENERAL Overview Responsibilities References Table of Contents Section Page 18.1 GENERAL... 18.1-1 18.1.1 Overview... 18.1-1 18.1.2 Responsibilities... 18.1-1 18.1.3 References... 18.1-2 18.2 MISCELLANEOUS FOUNDATION DESIGNS... 18.2-1 18.2.1 Buildings...

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

Dead man sheet pile wall (SI units)

Dead man sheet pile wall (SI units) Dead man sheet pile wall (SI units) Deep Excavation LLC Software program: DeepEX 2015 Document version: 1.0 January 16, 2015 www.deepexcavation.com Deep Excavation LLC 1 A. Project description In this

More information

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

NPTEL Course GROUND IMPROVEMENT USING MICROPILES Lecture 22 NPTEL Course GROUND IMPROVEMENT USING MICROPILES Prof. G L Sivakumar Babu Department of Civil Engineering Indian Institute of Science Bangalore 560012 Email: gls@civil.iisc.ernet.in Contents

More information

Cantilever Sheet Pile Wall (English units)

Cantilever Sheet Pile Wall (English units) Cantilever Sheet Pile Wall (English units) Deep Excavation LLC Software program: DeepEX 2018 Document version: 1.0 August 14, 2018 www.deepexcavation.com www.deepex.com DEEP EXCAVATION 1 A. Project description

More information

Chapter 21 GEOTECHNICAL REPORTS

Chapter 21 GEOTECHNICAL REPORTS Chapter 21 GEOTECHNICAL REPORTS Final SCDOT GEOTECHNICAL DESIGN MANUAL June 2010 Table of Contents Section Page 21.1 Introduction... 21-1 21.2 Geotechnical Base Line Report... 21-1 21.3 Bridge Geotechnical

More information

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM T. C. NEEL and K.BOZKURT ABSTRACT This work shall consist of the design, manufacture

More information

Replacing Existing Lock 4: Innovative Designs for Charleroi Lock

Replacing Existing Lock 4: Innovative Designs for Charleroi Lock INFRASTRUCTURE SYSTEMS CONFERENCE CONFERENCE -- Replacing Existing Lock 4: Innovative Designs for Charleroi Lock LISA R. PIERCE, P.E. DAVE A. STENSBY, P.E. Project Managers INCA Engineers, Inc. STEVE R.

More information

CEX6230 GEOTECHNICS Dear Student:

CEX6230 GEOTECHNICS Dear Student: CEX6230 GEOTECHNICS 31.05.2010 Dear Student: Geotechnics (CEX6230) discusses design and construction aspects of Geotechnical Engineering. Even though this course requires a pass in CEX4230, I find that

More information

geopier Lateral resistance

geopier Lateral resistance technical bulletin No. 4 geopier Lateral resistance This Technical Bulletin discusses the behavior of Geopier supported shallow foundation systems when subjected to lateral loads. Lateral loads are applied

More information

Melt Pool Size Control in Thin-Walled and Bulky Parts via Process Maps

Melt Pool Size Control in Thin-Walled and Bulky Parts via Process Maps Melt Pool Size Control in Tin-Walled and Bulky Parts via Process Maps Aditad Vasinonta, Jack L. Beut and Raymond Ong Department of Mecanical Engineering Carnegie Mellon University Pittsburg, PA 15213 Abstract

More information

Special Provision No. 599S22 March 2001

Special Provision No. 599S22 March 2001 RETAINED SOIL SYSTEM, TRUE ABUTMENT - Item No. RETAINED SOIL SYSTEM, FALSE ABUTMENT - Item No. RETAINED SOIL SYSTEM, WALL/SLOPE, HIGH RETAINED SOIL SYSTEM, WALL/SLOPE, MEDIUM RETAINED SOIL SYSTEM, WALL/SLOPE,

More information

CHAPTER 11: WALLS.

CHAPTER 11: WALLS. CHAPTER 11: WALLS MODULAR BLOCK WALL (DRY CAST) Rather than being pre-approved as systems, the components of Modular block walls (dry cast) are pre-approved separately. The approved MBW components are

More information

Stability of a Mechanically Stabilized Earth Wall

Stability of a Mechanically Stabilized Earth Wall Stability of a Mechanically Stabilized Earth Wall GEO-SLOPE International Ltd. www.geo-slope.com 1400, 633-6th Ave SW, Calgary, AB, Canada T2P 2Y5 Main: +1 403 269 2002 Fax: +1 403 266 4851 Introduction

More information

In te current study, wind-induced torsional loads on low and medium eigt buildings were examined in te boundary layer wind tunnel. uilding model (scal

In te current study, wind-induced torsional loads on low and medium eigt buildings were examined in te boundary layer wind tunnel. uilding model (scal Te Sevent International Colloquium on luff ody Aerodynamics and Applications (AA7) Sangai, Cina; September 2-6, 2012 Wind-induced torsional aerodynamic loads on low and medium eigt buildings M. Elsarawy,

More information

Outline of Presentation. Behavior of Laterally Loaded Piles in A Mechanically Stabilized Earth (MSE) Wall

Outline of Presentation. Behavior of Laterally Loaded Piles in A Mechanically Stabilized Earth (MSE) Wall Behavior of Laterally Loaded Piles in A Mechanically Stabilized Earth (MSE) Wall Jie Han, Ph.D., PE, F.ASCE Glenn L. Parker Professor of Geotechnical Engineering The University of Kansas, USA Outline of

More information

GEOTECHNICAL INVESTIGATION. Adelaide Street at Canadian Pacific Rail Underpass Mile Galt Subdivision London, Ontario

GEOTECHNICAL INVESTIGATION. Adelaide Street at Canadian Pacific Rail Underpass Mile Galt Subdivision London, Ontario GEOTECHNICAL INVESTIGATION Adelaide Street at Canadian Pacific Rail Underpass Mile 113.73 Galt Subdivision London, Ontario Submitted to: Mr. Ardian Spahiu, P.Eng., Transportation Design Engineer Corporation

More information

Rte. 66/29 Interchange Reconstruction Project: ,C505 Grade Separation of Two Crossings Norfolk Southern Railway Right of Way and Track

Rte. 66/29 Interchange Reconstruction Project: ,C505 Grade Separation of Two Crossings Norfolk Southern Railway Right of Way and Track Rte. 66/29 Interchange Reconstruction Project: 0066-076-113,C505 Grade Separation of Two Crossings Norfolk Southern Railway Right of Way and Track Mileposts B-8.1 thru B-8.8 DOT 714-363S, 714-364Y Gainesville,

More information

UNIT V RETAINING WALLS RETAINING WALL 2.5. Retaining walls are structures used to retain earth or water or other materials such as coal, ore, etc; where conditions do not permit the mass to assume its

More information

June i TABLE OF CONTENTS

June i TABLE OF CONTENTS June 2005 - i - 05-526 TABLE OF CONTENTS SECTION PAGE 1.0 INTRODUCTION... 1 1.1 Purpose of the Investigation... 1 1.2 Description of the Project and Scope of Work... 1 1.3 Site Geology... 1 1.4 Site Description

More information

GEO-SLOPE International Ltd, Calgary, Alberta, Canada Tie-back Wall

GEO-SLOPE International Ltd, Calgary, Alberta, Canada   Tie-back Wall 1 Introduction Tie-back Wall This example simulates the sequential construction of a sheet-pile shoring wall tied back with pre-stressed anchors. The purpose is to demonstrate the steps involved in modeling

More information

Effect of Seismic Reinforcement of Sheet Pile Quay Wall Using Ground Anchor

Effect of Seismic Reinforcement of Sheet Pile Quay Wall Using Ground Anchor Effect of Seismic Reinforcement of Sheet Pile Quay Wall Using Ground Anchor M. Yoshida & M. Mitou Penta-Ocean Construction Co., Ltd., Japan O. Kiyomiya Waseda University, Japan S. Tashiro TOA Corporation,

More information

Diaphragm wall with tieback supports (English units)

Diaphragm wall with tieback supports (English units) Diaphragm wall with tieback supports (English units) Deep Excavation LLC Software program: DeepEX 2015 Document version: 1.0 December 16, 2014 www.deepexcavation.com Deep Excavation LLC 1 A. Project description

More information

FLORIDA DEPARTMENT OF TRANSPORTATION

FLORIDA DEPARTMENT OF TRANSPORTATION TEMPORARY WIREWALL MSE RETAINING WALLS SAMPLE DETAIL DRAWINGS INDEX DESCRIPTION 1 TITLE 2 GENERAL NOTES 3-4 TEMPORARY WIREWALL DETAILS 5-6 TRI-WEB TEMPORARY WALL DETAILS 7 TYPICAL TEMPORARY WIREWALL 8

More information

Downloaded from Downloaded from /1

Downloaded from  Downloaded from  /1 PURWANCHAL UNIVERSITY VI SEMESTER FINAL EXAMINATION-2003 LEVEL : B. E. (Civil) SUBJECT: BEG359CI, Foundation Engineering. Full Marks: 80 TIME: 03:00 hrs Pass marks: 32 Candidates are required to give their

More information

I-35W Retaining Wall Design Exhibit A - Draft Scope of Work

I-35W Retaining Wall Design Exhibit A - Draft Scope of Work Background MnDOT, Metro Transit, Hennepin County, and the City of Minneapolis are in the process of developing a project for Interstate 35W between 43 rd Street in Minneapolis and 15 th Street in Minneapolis.

More information

ENGINEERING DIRECTIVE

ENGINEERING DIRECTIVE Number: E-95-001 Date: 2/2/95 ENGINEERING DIRECTIVE Ross B. Dindio (Signature on Original) CHIEF ENGINEER The purpose of this engineering directive is to formally notify ALL Department engineering personnel

More information

Ching Guan Kee ABSTRACT

Ching Guan Kee ABSTRACT Japanese Geotechnical Society Special Publication The 15th Asian Regional Conference on Soil Mechanics and Geotechnical Engineering Effects of base grouting and deep cement mixing on deep foundation bored

More information

Scaling Effects in Laser-Based Additive Manufacturing Processes

Scaling Effects in Laser-Based Additive Manufacturing Processes Scaling Effects in Laser-Based Additive Manufacturing Processes Andrew J. Birnbaum and Jack L. Beut Department of Mecanical Engineering Carnegie Mellon University Pittsburg, Pa 15213 James W. Sears Advanced

More information

Table of Contents 5.1 GENERAL Overview Investigation and Engineering Information

Table of Contents 5.1 GENERAL Overview Investigation and Engineering Information Table of Contents Section Page 5.1 GENERAL... 5.1-1 5.1.1 Overview... 5.1-1 5.1.2 Investigation and Engineering Information... 5.1-2 5.2 PRELIMINARY GEOTECHNCIAL REPORTS... 5.2-1 5.2.1 Preliminary Geotechnical

More information

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway Jeff Sizemore, P.E. Geotechnical Design Support Engineer SCDOT Ed Tavera, P.E. Principal Geotechnical Engineer Geoengineers

More information

Optimized geothermal binary power cycles

Optimized geothermal binary power cycles Optimized geotermal binary power cycles Kontoleontos E., Mendrinos D., Karytsas C. Centre for Renewable Energy Sources, 9t km Maratonos ave., 9009 Pikermi Attikis, Greece ABSTRACT Tis study as been carried

More information

Shake Table Testing of GRS Bridge Abutments

Shake Table Testing of GRS Bridge Abutments Shake Table Testing of GRS Bridge Abutments Prof. John S. McCartney and Yewei Zheng University of California San Diego Department of Structural Engineering Presentation to: NHERI-UCSD Geotechnical Workshop

More information

Analysis of the stability of sheet pile walls using Discontinuity Layout Optimization

Analysis of the stability of sheet pile walls using Discontinuity Layout Optimization Analysis of the stability of sheet pile walls using Discontinuity Layout Optimization S. D. Clarke, C. C. Smith & M. Gilbert The University of Sheffield, UK ABSTRACT: In this paper it is demonstrated that

More information

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) ,

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) , PLACEMENT OF PRECAST PRESTRESSED CONCRETE GIRDER BRIDGE SPANS WITH SELF PROPELLED MODULAR TRANSPORTERS PIONEER CROSSING DESIGN/BUILD PROJECT, AMERICAN FORK, UT Steve Haines, P.E., Parsons, (303) 831-8100,

More information

Pump Station Excavation

Pump Station Excavation Pump Station Excavation SPONSORED BY THE KIEWIT CORPORATION A capstone project for the The Department of Civil & Environmental Engineering in The Ira A. Fulton College of Engineering and Technology Brigham

More information

Chapter 18 EARTH RETAINING STRUCTURES

Chapter 18 EARTH RETAINING STRUCTURES Chapter 18 EARTH RETAINING STRUCTURES Final SCDOT GEOTECHNICAL DESIGN MANUAL June 2010 SCDOT Geotechnical Design Manual Earth Retaining Structures Table of Contents Section Page 18.1 Introduction...18-1

More information

Part 28. Temporary Structures for Construction TABLE OF CONTENTS

Part 28. Temporary Structures for Construction TABLE OF CONTENTS Section/Article Part 28 Temporary Structures for Construction 2015 TABLE OF CONTENTS Description 28.1 General............................................................................... 8-28-2 28.1.1

More information

Southwest Housing, Arizona State University

Southwest Housing, Arizona State University Prepared by KSENIA TRETIAKOVA Structural Option 01.09.2012 Architectural Engineering Pennsylvania State University 2012 Southwest Housing, Arizona State University Technical Report #3 Lateral System 01.09.2012

More information

USE OF TEMPORARY ANCHORS IN REINFORCED SOIL WALL CONSTRUCTION FOR THE M4 MOTORWAY WIDENING

USE OF TEMPORARY ANCHORS IN REINFORCED SOIL WALL CONSTRUCTION FOR THE M4 MOTORWAY WIDENING WALL CONSTRUCTION FOR THE M4 MOTORWAY WIDENING Tristan McWilliam 1 and Dr Loges Paramaguru 2 1 Principal Geotechnical Engineer, Golder Associates, 2 Senior Geotechnical and Tunnelling Engineer, Jacobs

More information

Chapter 1 INTRODUCTION

Chapter 1 INTRODUCTION Chapter 1 Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 1.1 Introduction... 1 1.2 Preconstruction Division... 1 1.2.1 Regional Production Groups... 2 1.2.2 Preconstruction

More information

ASSESSMENT OF THE POWER CURVE FLATTENING METHOD: AN APPROACH TO SMART GRIDS

ASSESSMENT OF THE POWER CURVE FLATTENING METHOD: AN APPROACH TO SMART GRIDS ASSESSENT OF THE POWER CURVE FLATTENING ETHOD: AN APPROACH TO SART GRIDS S. CARILLO APARICIO F. J. LEIVA ROJO Giacomo PETRETTO Gianluca GIGLIUCCI SmartGrids Endesa Red I+D Endesa S.A. Enel Ingegneria e

More information

Forging. Types of Forging Dies. Open-Die Forging. Outline. Forging. Types of forging Forging analysis Examples

Forging. Types of Forging Dies. Open-Die Forging. Outline. Forging. Types of forging Forging analysis Examples Forging Outline Forging Types of forging Forging analysis Examples Oldest of te metal forming operations, dating from about 5000 B C Components: engine cranksafts, connecting rods, gears, aircraft structural

More information

2.0 Purpose. 3.0 Work Plan. Page 1 of 7

2.0 Purpose. 3.0 Work Plan. Page 1 of 7 2.0 Purpose The purpose of this document is to present the findings of the field investigation and concept design study, as well as recommend appropriate track relocation and bridge modifications to provide

More information

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04 UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04 1. Description This work shall consist of the design, manufacture and construction of a T-WALL structure

More information

Standard Test Method for Fracture Strength in Cleavage of Adhesives in Bonded Metal Joints 1

Standard Test Method for Fracture Strength in Cleavage of Adhesives in Bonded Metal Joints 1 Designation: D 3433 99 Standard Test Metod for Fracture Strengt in Cleavage of Adesives in Bonded Metal Joints 1 Tis standard is issued under te fixed designation D 3433; te number immediately following

More information

Lecture Retaining Wall Week 12

Lecture Retaining Wall Week 12 Lecture Retaining Wall Week 12 Retaining walls which provide lateral support to earth fill embankment or any other form of material which they retain them in vertical position. These walls are also usually

More information

Finite Element Analysis of Flexible Anchored Sheet Pile Walls: Effect of Mode of Construction and Dewatering Naveen Kumar 1, Arindam Dey 2*

Finite Element Analysis of Flexible Anchored Sheet Pile Walls: Effect of Mode of Construction and Dewatering Naveen Kumar 1, Arindam Dey 2* Golden Jubilee Conference of the IGS Bangalore Chapter, Geo-Innovations, 30-31 October 2014 Finite Element Analysis of Flexible Anchored Sheet Pile Walls: Effect of Mode of Construction and Dewatering

More information

Measurement and Reporting of Vapor Phase Mercury Emissions from Low-Emitting Stationary Sources (DRAFT 9/25/08)

Measurement and Reporting of Vapor Phase Mercury Emissions from Low-Emitting Stationary Sources (DRAFT 9/25/08) Measurement and Reporting of Vapor Pase Mercury Emissions from Low-Emitting Stationary Sources (DRAFT 9/25/08) 1. Scope and Application Te purpose of tis protocol is to establis procedures for te measurement

More information

Retaining Wall Design for the Railroad Infrastructure: What Makes Its Design and Construction Unique? A Selection Approach

Retaining Wall Design for the Railroad Infrastructure: What Makes Its Design and Construction Unique? A Selection Approach Retaining Wall Design for the Railroad Infrastructure: What Makes Its Design and Construction Unique? A Selection Approach Authors Names and Contact Information: Bryan Duevel Jacobs Associates 101 SW Main

More information

GEO-SLOPE International Ltd, Calgary, Alberta, Canada Tie-back Wall

GEO-SLOPE International Ltd, Calgary, Alberta, Canada   Tie-back Wall 1 Introduction Tie-back Wall This example simulates the sequential construction of a sheet-pile shoring wall tied back with pre-stressed anchors. The purpose is to demonstrate the steps involved in modeling

More information

Temporary Shoring. Specifications, Applications, & Best Practices. Stephen M. (Matt) Revell, P.E. Assistant Geotechnical Engineer

Temporary Shoring. Specifications, Applications, & Best Practices. Stephen M. (Matt) Revell, P.E. Assistant Geotechnical Engineer Temporary Shoring Specifications, Applications, & Best Practices Stephen M. (Matt) Revell, P.E. Assistant Geotechnical Engineer Temporary Shoring Specifications, Applications, & Best Practices Temporary

More information

SPECIAL SPECIFICATION 4385 Railroad Bridge Construction

SPECIAL SPECIFICATION 4385 Railroad Bridge Construction 2004 Specifications CSJ 0912-71-622 SPECIAL SPECIFICATION 4385 Railroad Bridge Construction 1. Description. Construct Railroad bridges following the recommendations in the applicable Chapters of the current

More information

Development of the Combi-Gyro Method, a New Steel Wall Construction Method Combining Steel Sheet Piles and Pipe Piles

Development of the Combi-Gyro Method, a New Steel Wall Construction Method Combining Steel Sheet Piles and Pipe Piles Technical Report NIPPON STEEL & SUMITOMO METAL TECHNICAL REPORT No. 113 DECEMBER 2016 UDC 624. 155 Development of the Combi-Gyro Method, a New Steel Wall Construction Method Combining Steel Sheet Piles

More information

Settlement Reduction Effect of Advanced Back-to-Back Reinforced Retaining Wall

Settlement Reduction Effect of Advanced Back-to-Back Reinforced Retaining Wall IJR International Journal of Railway Vol. 6, No. 3 / September 2013, pp. 107-111 The Korean Society for Railway Settlement Reduction Effect of Advanced Back-to-Back Reinforced Retaining Wall Koh, Taehoon,

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

MACOMB COUNTY DEPARTMENT OF ROADS REQUEST FOR PROPOSAL (RFP)

MACOMB COUNTY DEPARTMENT OF ROADS REQUEST FOR PROPOSAL (RFP) MACOMB COUNTY DEPARTMENT OF ROADS REQUEST FOR PROPOSAL (RFP) SCOPE OF SERVICES FOR GEOTECHNICAL ENGINEERING FOR VARIOUS AND AS-NEEDED BRIDGE STRUCTURES December 6, 2017 The Macomb County Department of

More information

Design and Performance of Lightweight Fill Embankment on Sensitive Soils at Willingdon Interchange

Design and Performance of Lightweight Fill Embankment on Sensitive Soils at Willingdon Interchange Design and Performance of Lightweight Fill Embankment on Sensitive Soils at Willingdon Interchange Kazunori Fujita, B.Sc. Project Manager, GeoPacific Consultants Ltd., Vancouver, BC. Matt Kokan, M.A.Sc.,

More information

Auto landing using fuzzy logic

Auto landing using fuzzy logic 6t International PD Worksop on Systems and Control, October 4-8, 25 Izola, Slovenia INTRODUCTION Auto landing using fuzzy logic Pavle Boskoski, Biljana Mileva 2, Stojce Deskoski 3 Faculty of Electrical

More information

EVALUATION OF SEISMIC FAILURE POTENTIAL OF EXISTING RETAINING WALLS USING POTABLE CONE

EVALUATION OF SEISMIC FAILURE POTENTIAL OF EXISTING RETAINING WALLS USING POTABLE CONE 4 th International Conference on Earthquake Geotechnical Engineering June 25-28, 2007 Paper No. 1138 EVALUATION OF SEISMIC FAILURE POTENTIAL OF EXISTING RETAINING WALLS USING POTABLE CONE Mitsu OKAMURA

More information

Use of DMT for subsurface characterization: strengths and weaknesses

Use of DMT for subsurface characterization: strengths and weaknesses Use of DMT for subsurface characterization: strengths and weaknesses Hai-Ming Lim Burgess Engineering and Testing, Inc., Moore, Oklahoma, USA Musharraf Zaman School of Civil Engineering and Environmental

More information

Natalia Maca. TITAN POLSKA Sp. z o.o Kraków, Miłkowskiego 3/801 Tel Fax

Natalia Maca. TITAN POLSKA Sp. z o.o Kraków, Miłkowskiego 3/801 Tel Fax Natalia Maca TITAN POLSKA Sp. z o.o. 30-349 Kraków, Miłkowskiego 3/801 Tel. 0 12 255 59 00 Fax. 0 12 255 59 07 www.titan.com.pl biuro@titan.com.pl Presentation plan General information Design problems

More information

EN Eurocode 7. Section 8 Anchorages Section 9 Retaining structures. Brian Simpson Arup Geotechnics

EN Eurocode 7. Section 8 Anchorages Section 9 Retaining structures. Brian Simpson Arup Geotechnics EUROCODES Background and Applications EN1997-1: Anchorages and Retaining structures Brussels, 18-20 February 2008 Dissemination of information workshop 1 EN 1997-1 Eurocode 7 Section 8 Anchorages Section

More information

MSE WALLS CASE STUDIES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

MSE WALLS CASE STUDIES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch MSE WALLS CASE STUDIES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch COMMON RETAINING WALL TYPES CONCRETE BLOCK MSE TEMPORARY EARTH SPREAD FOOTING Gabions Drilled Shaft Soil Nail Tiedback

More information

A. Section includes temporary excavation support and protection systems.

A. Section includes temporary excavation support and protection systems. SECTION 31 50 00 - EXCAVATION SUPPORT AND PROTECTION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

Distribution Restriction Statement

Distribution Restriction Statement DEPARTMENT OF THE ARMY CECW-ED U.S. Army Corps of Engineers CECW-EG Washington, DC 20314-1000 ETL 1110-2-352 Technical Letter No. 1110-2-352 31 March 1994 Engineering and Design STABILITY OF GRAVITY WALLS

More information

BROADENING OF HIGHWAYS AT CRITICAL SLOPE WATERWAY EMBANKMENTS USING VERTICAL PILES

BROADENING OF HIGHWAYS AT CRITICAL SLOPE WATERWAY EMBANKMENTS USING VERTICAL PILES BROADENING OF HIGHWAYS AT CRITICAL SLOPE WATERWAY EMBANKMENTS USING VERTICAL PILES Assoc. Prof. Hisham Arafat Mahdi 1 Head of Structural Engineering & construction Management-FUE-Egypt ABSTRACT The main

More information

Chapter 18 EARTH RETAINING STRUCTURES GEOTECHNICAL DESIGN MANUAL

Chapter 18 EARTH RETAINING STRUCTURES GEOTECHNICAL DESIGN MANUAL Chapter 18 EARTH RETAINING STRUCTURES GEOTECHNICAL DESIGN MANUAL January 2019 Table of Contents Section Page 18.1 Introduction... 18-1 18.2 Earth Retaining Structure Classification... 18-2 18.2.1 Load

More information

The requirements for the above tender items are contained in OPSS 942.

The requirements for the above tender items are contained in OPSS 942. B942 - - OPSS 942 942.1 GENERAL Ground anchors are systems used to transfer tensile loads to soil or rock. These systems comprise prestressing steel tendons, steel anchorages, spacers, centralizers and

More information

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the

More information

FDOT UTILITY MARKUPS AND UTILITY CONFLICTS!

FDOT UTILITY MARKUPS AND UTILITY CONFLICTS! FDOT UTILITY MARKUPS AND UTILITY CONFLICTS! INTRODUCTIONS Chris Stermer - Wantman Group Utility Coordination Manager, 18 years utility coordination and utility engineering & design experience. (Natural

More information

0.3 to 0.18 W/mK (depending on construction) by CSTB

0.3 to 0.18 W/mK (depending on construction) by CSTB CI/SfB Xt6 September 2017 Contents System components 2 Applications 3 resistances 4-6 considerations 7 Installation guidance 8 Isotec Termally Insulated Balcony Connectors Ancon Isotec Isotec is a ig performance

More information

Draft for Public Comment Australian/New Zealand Standard

Draft for Public Comment Australian/New Zealand Standard COMMITTEE EL-056 DR AS/NZS 3823.4.2:2014 Amd 1:2016 (Project ID: 103934 Draft for Public Comment Australian/New Zealand Standard LIABLE TO ALTERATION DO NOT USE AS A STANDARD BEGINNING DATE FOR COMMENT:

More information

A Low-Temperature Creep Experiment Using Common Solder

A Low-Temperature Creep Experiment Using Common Solder A Low-Temperature Creep Experiment Using Common Solder L. Roy Bunnell, Materials Science Teacer Soutridge Hig Scool Kennewick, WA 99338 roy.bunnell@ksd.org Abstract: Tis experiment uses common lead-tin

More information