1 Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E.
2 Project Overview The Ironton Russell Bridge Project entails the construction of a cast in place concrete cable stayed bridge over the Ohio River with structural steel approaches connecting the towns of Ironton, Ohio and Russell, Kentucky. The bridge will provide two 12-ft driving lanes and two 4 ft shoulders; a driving lane and shoulder in each direction. Span lengths for the approaches vary widely as they cross numerous (6) rail lines, the Ohio River levee and city streets. On the Kentucky side the spans are 140-ft and 235-ft; in Ohio the spans are 110-ft, 144-ft, 186-ft and 144-ft. The approach bridges are founded on small diameter drilled shafts (Kentucky) or steel pile (Ohio). The main span unit consists of three spans; two flanking spans at 370-ft and the center span of 900-ft. The main span unit is supported by two CIP, 316-ft tall, diamond shaped towers, founded on large diameter drilled shafts with rock sockets. When completed, the 900-ft main span will be the longest span the Ohio DOT has built. The contract value for construction of the new structure and removal of the existing is $81,266,742.05, with Brayman Construction Corporation the low bidder. Recent Construction Highlights - Main Span Tower 3 (KY) and Kentucky Back Span: Looking across to Ohio from the Kentucky dock, the staggered form work on Tower 3 can be viewed. In the photo above, formwork is set on Segment 12 right and on Segment 14 left. Page 1 of 8
3 Ironton Russell Bridge Project Project Summary: January 1, 2015 Tower 3 (KY) Anchor Box: The last of the 4 anchor box sections was set on the left leg (downstream side) of Tower 3. Bolted connections secure each box to the one below it. After BCC survey confirms the location of the anchor box, crews tighten the bolts to their required torque (below). Page 2 of 8
4 Tower 4 (OH): Above crews have partially installed rebar and formwork for Tower Segment 6B right (upstream). Tower 6B right was cast on December 22, 2014, currently crews are working to form 6b left in the same manner. Page 3 of 8
5 Scheduled Actual Select Milestone Events (Schedule Update 27) Date Date Notice to Proceed 3Feb12 Open Bridge to Traffic 02Sept16 End Project 06Jun17 Ohio Approach Set Structural Steel Ohio Approach 18Apr14 18Mar14 Complete Deck Concrete Ohio Approach 15Oct14 22Oct14** Main Span Cast KY Tower Footing 10May13 10May13 Cast OH Tower Footing 21Jan14 21Feb14 Cast First KY Tower Section 27June13 14June13 Cast Last KY Tower Section 09Feb15 Cast First OH Tower Section 05Mar14 27Mar14** Cast Last OH Tower Section 26Aug15 Complete KY Back span 06Aug14 15Aug14 Complete OH Back span 22Apr15 Set form traveler KY Tower 13Apr15 Set form traveler OH Tower 17Nov15 Main span Closure Pour 31May16 Kentucky Approach Set Structural Steel Kentucky Approach 13Sept13 6Sept13 Complete Deck Concrete KY Approach 10Dec13 20Nov13 % Complete ($) Paid $51.1M/Total $82.8M 61.7% % Complete (Time) Day 1032 of % **Non critical path activity. Bridge and Roadway Summary At Tower 3 (KY), Segment 14 left (downstream) was cast on December 18, Forming of Segment 15 left is ongoing. Work to form Segment 12 right (upstream) was cast on December 23, 2014 At Tower 4 (OH), Tower Segment 6B right (upstream) was cast on December 22, Crews are now preparing forms for Segment 6B left (downstream). The Ohio back span false work continued to progress during the month of December. Erection of the precast anchor blocks and floor beams began on December 31, Page 4 of 8
6 Tower 3 (KY) Progress thru 1/1/15 Page 5 of 8
7 Tower 4 (OH) Progress thru 1/1/15 Page 6 of 8
8 Substructure Progress Chart thru 1/1/15 Kentucky Approach Ohio Approach Rear (KY) Abutment % complete Pier 6 % complete Drilled shafts 12 of Pile Installed 24 of Footing 7 of Footing 100 Backwall 2 of Stem 100 Wing walls 6 of Cap 100 Pier 1 Pier 7 Drilled shafts 3 of Pile Installed 24 of Footing 100 Footing 100 Stem 100 Stem 100 Cap 100 Cap 100 Main Span Pier 2 Pier 8 Drilled shafts 6 of Pile Installed 27 of Footing 100 Footing 100 Pier Segment 3 of Stem 100 Diaphragm Segment 4 of Cap 100 Pier 3 (Ky Tower) Forward (OH) Abutment Drilled shafts 6 of Pile Installed 22 of Footing 100 Footing 100 Tower Segments 13 of Backwall 2 of Wingwalls 2 of Pier 4 (OH Tower) Drilled shafts 6 of Footing 100 Tower Segments 5.5 of Pier 5 Drilled shafts 4 of Footing 100 Pier Segments 2 of Diaphragm Segment 3 of Page 7 of 8
9 Superstructure Progress Chart thru 1/1/15 Precast Floor beams # cast % cast 52 pieces total 52 of Precast Anchor blocks # cast % cast 108 pieces total 90 of Main Span Unit % complete Kentucky Back span Segments 12 of Ohio Back span Segments 0 of 12 0 Kentucky Cantilever Segments 0 of 15 0 Ohio Cantilever Segments 0 of 15 0 Kentucky Approach % complete Girders Fabricated 24 of Girders Erected 24 of Deck Castings 3 of Ohio Approach % complete Girders Fabricated 35 of Girders Erected 35 of Deck Castings 4 of Page 8 of 8
Ironton Russell Bridge Project
Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015
More informationIronton Russell Bridge Project
Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationIronton Russell Bridge Project
Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationIronton Russell Bridge Project
Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September
More informationIronton Russell Bridge Project
Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationThe Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects
The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309
More informationTilikum Crossing Transit Bridge. Portland, OR
Tilikum Crossing Transit Bridge Portland, OR Technical Information Size of Project: The Tilikum Crossing Transit Bridge is 1,720 ft. long and required 24,000 cy total concrete Strength Requirements: The
More informationBonner Bridge Replacement Update:
Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner
More informationSTRUCTURES INSPECTION CERTIFICATION TRAINING COURSE
STRUCTURES INSPECTION CERTIFICATION TRAINING COURSE Code Pre/Route AFE Function Part 0 1000 7116 1174 N Hadley Eisenbeisz Bridge Construction Engineer Rick Brandner Mitchell Area Darrell utter Assistant
More informationLRFD Bridge Design Manual Changes
LRFD Bridge Design Manual Changes Dave Dahlberg Bridge Design Manual & Policy Engineer May 17, 2017 Bridge Office mndot.gov/bridge Overview 1) Concrete mix designations 2) Reinforcing bar development and
More informationDan Carrier Parsons Brinckerhoff Project Manager Cooper River Bridge Charleston, South Carolina
OTEC 2004 Dan Carrier Parsons Brinckerhoff Project Manager Charleston, South Carolina Dan Carrier Background! Hazelet & Erdal 1966-1984 (Cincinnati, Ohio Office) Bridge Designer! Parsons Brinckerhoff 1984-2004
More information2016 ACEC/PA ANNUAL MEETING
2016 ACEC/PA ANNUAL MEETING z I-49 North, Segment K (I-220 to Martin Luther King Drive) Interchange Project Durk Krone, P.E., TRC Engineers Inc., Baton Rouge, La 1 I-49 North Segment K Project 2 AGENDA
More informationRt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening
Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening March 5, 2009 Nicholas J. Roper NOVA District Bridge Engineer Robert F. Price Resident Administrator of Loudoun/ Prince William Construction
More informationRed Wing Bridge Alternates
Alternate 1 Tied Arch Alternate 2 Simple Span Truss Alternate 1 Design Drawing Alternate 2 Design Drawing Similar Bridge Design to Alternate 1 Similar Bridge Design to Alternate 2 Evaluation Matrix for
More informationI2-0 LIST OF ACTIVE SSDs
I2-0 0002.0001 Structural Standard Drawings - Layering Structure Aug 1, 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details Jun 1, 2002 Jul 17, 2002 0007.0002 Grout Vent Detail Mar 1, 2006
More informationEconomical Design / Case Studies
Economical Design / Case Studies Alabama Technology Transfer Center Workshop Michael Barker, PE University of Wyoming & SSSBA Bridge Technology Center Outline of Today s Presentation Competitiveness of
More informationIntroduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring
Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot
More informationMILTON-MADISON BRIDGE REPLACEMENT
MILTON-MADISON BRIDGE REPLACEMENT Andy Barber P.E. Kevin Hetrick P.E. 1 Presentation Overview KYTC lead Environmental Study TIGER Grant INDOT lead Design Build solution Bridge Sliding Project Status Questions
More informationSt. Anthony Falls I-35W Bridge Replacement. ASHE National Conference June 13, Dustin Thomas, P.E. I-35W Bridge Construction Engineer
St. Anthony Falls I-35W Bridge Replacement ASHE National Conference June 13, 2014 Dustin Thomas, P.E. I-35W Bridge Construction Engineer The Former Bridge - 9340 Opened to traffic in 1967 Steel truss bridge
More information7 Bridges in 74 Days. NC 12 Detour
7 Bridges in 74 Days (Or Less) NC 12 Detour Ocracoke NC 12 Bridges Ocracoke NC 12 Bridges Existing 7 bridges built in 1950's Timber structures w/ ACP Clear width 22.5 ft. 36 to 152 ft. long Limited redirective
More informationFinal Estimates Level 2
Florida Department of TRANSPORTATION Final Estimates Level 2 Module 6: Structures 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 6 1 6-1 Module Content Concrete Structures Bridges Substructure
More informationLIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs)
LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs) 0002.0001 Structural Standard Drawings - Layering Structure n/a Aug 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details n/a Jun 2002 Jul
More informationSR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA
ASHE NATIONAL PROJECT OF THE YEAR SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA For the PENNSYLVANIA DEPARTMENT OF TRANSPORTATION Engineering District 12-0 Submitted By: January 29, 2018 AMERICAN
More informationPROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012
PROJECT UPDATE Rendering View from the City of Chesapeake Elizabeth River Boat Landing and Park looking across the Elizabeth River at Portsmouth CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA The new 5,375
More informationI-94/I-69 Interchange Bridge Construction
I-94/I-69 Interchange Bridge Construction General Project Information Let in August 2013 Cost of $76 million Prime Contractor Walter Toebe Construction Company Reconstruction of I-94 from Griswold to Lapeer
More informationABC, FHWA SHRP2 R04: Project update, lessons learned. Finn Hubbard, Fish & Associates Inc. SHRP2 ABC/PBES Implementation Technical Lead
ABC, FHWA SHRP2 R04: Project update, lessons learned Finn Hubbard, Fish & Associates Inc. SHRP2 ABC/PBES Implementation Technical Lead January 11, 2015 Goals for ABC Enhanced Mobility Safety Reduced Costs***
More informationAMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE HISTORIC BRIDGE REHABILITATION AND MAINTENANCE CASE STUDY
More informationABRAHAM LINCOLN BRIDGE
ABRAHAM LINCOLN BRIDGE PROJECT LOCATION: CONNECTING LOUISVILLE, KY WITH JEFFERSON, IN ACROSS THE OHIO RIVER. CATEGORY B: TRANSPORTATION PROJECT OWNER: KENTUCKY TRANSPORTATION CABINET COWI North America
More informationDesign and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.
Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on
More informationDesign & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By:
Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By: ABSTRACT Shafi M. Sharifan, Ph.D., P.E. Wei Koo & Associates Orange, California Kosal Krishnan,
More informationABC Technology and Steel Bridges
ABC Technology and Steel Bridges Accelerated Bridge Construction (ABC) Technologies C. C. Fu, Ph.D., P.E. Director/Research Professor Bridge Engineering Software & Technology (BEST) Center Department of
More informationResults you can rely on
z 1 I-49 North Segment K Project 2 AGENDA PROJECT OVERVIEW BRIDGE DESIGN ARCHITECTURAL ENHANCEMENTS SPECIAL PROVISIONS COST ESTIMATE AND FINAL BIDS CONSTRUCTION 3 SITE LOCATION PROJECT SITE ARKANSAS 185
More informationDESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE
Design of the Main Spans of the Chongqing Caiyuanba Bridge ARCH 04 M.C. Tang and J. Sun @CIMNE, Barcelona, 2004 DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE Man-Chung Tang* and John Sun+
More informationI-345 Feasibility Study Public Meeting
I-345 Feasibility Public Meeting December 11, 2012 December 11, 2012 1 Feasibility Team TxDOT Dallas District & Bridge Division Parsons Brinckerhoff Huitt-Zollars APM Halff Associates Civil Associates
More informationSHRP 2 - R04 Innovative Bridge Designs for Rapid Renewal
SHRP 2 - R04 Innovative Bridge Designs for Rapid Renewal FEHRL Long Life Bridges SQUARE (Brussels) Thursday June 10, 2010 Objective RAPID RENEWAL Bridge Systems WHAT IS THE BIG IDEA? Manufactured Bridges
More informationA NEW STEEL ARCH BRIDGE FOR THE US 52 MISSISSIPPI RIVER CROSSING
A NEW STEEL ARCH BRIDGE FOR THE US 52 MISSISSIPPI RIVER CROSSING GREG HASBROUCK, PE MARTIN FURRER, PE, SE FAITH DUNCAN, PE BIOGRAPHY Greg Hasbrouck is a Project Manager with Parsons in Chicago and was
More information1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY
Detailing of ABC Bridges for Simplicity and Durability Michael P. Culmo, P.E. CME Associates, Inc. East Hartford, CT DETAILS This presentation contains many preferred details My favorite details will be
More informationNew Jersey Turnpike Authority
New Jersey Turnpike Authority DOCUMENT UPDATE REQUEST Forward to Assistant Chief Engineer, Design Initiator Russell Saputo, PE Submittal Date 6/21/16 Firm Stantec Consulting Services Inc. Telephone 201-587-9040
More informationStrengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions
13 th BIENNIAL SYMPOSIUM OCTOBER 25-28, 2010 Strengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions Jian Huang, Ph.D., P.E. and R. Wayne McLennon, P.E. TranSystems Corporation 2400 E. Commercial
More informationShort Span Steel Bridges
Short Span Steel Bridges MINK 2015 Michael Barker, PE University of Wyoming & SSSBA Bridge Technology Center Outline of Today s Presentation SSSBA & espan140 Design Competitiveness of Steel Bridges Economics
More informationAlberta Bridge Inventory STANDARD BRIDGE & CULVERT COMPONENTS. Standard Bridges. Typical Bridge Components. In Alberta there are about 13,300 bridges.
STANDARD BRIDGE & CULVERT COMPONENTS Alberta Bridge Inventory In Alberta there are about 13,300 bridges. Types of bridges in Alberta: Standard bridges 3521 (26%) Bridge size culverts 8348 (63%) Major bridges
More informationAccelerated Bridge Construction in USA
Accelerated Bridge Construction in USA Abstract Rush hour traffic is a common daily occurrence in the USA. Highway and bridge construction further aggravates the situation. The Federal Highway Administration
More informationLesner Bridge Replacement
Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on
More informationPHASING CONSIDERATIONS FOR BRIDGES
PHASING CONSIDERATIONS FOR BRIDGES Christopher Miller, P.E. 6/11/18 Table of contents 1 What Not to Do 3 2 Span Arrangement 4-9 3 4 5 6 Superstructure Geometric Considerations Superstructure Structural
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS
MICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS SECTION 1 - MISCELLANEOUS STANDARDS 1.00.01 -.05 Table of Contents 1.11.01 Decimal Parts of a Foot and Inch 1.21.01 Factors
More informationAGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.
Route 15/29 SBL Bridge Superstructure Replacement & Widening Existing Structure Scope Accelerated Procedure Staging (Superstructure) Preparatory Work (Substructure) NOVA District Questions EXISTING STRUCTURE
More informationModjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction
Introduction This memo presents a summary of a three dimensional (3D) analysis of the Organic concept for the proposed St. Croix River bridge project. The Organic concept has several attributes that are
More informationPLANNING AND DESIGN PARAMETERS BRIDGE STRUCTURES. Engr. Ericson Mammag Feasibility Study Preparation CHARM2 Project
PLANNING AND DESIGN PARAMETERS BRIDGE STRUCTURES Engr. Ericson Mammag Feasibility Study Preparation CHARM2 Project KEY ELEMENTS IN RURAL INFRA Planning & Design Bridges Potable Communal Small Water Roads
More informationJohn A. Roebling Bridge Rehabilitation History
John A. Roebling Bridge Rehabilitation History Presented By: Rob Hans, P.E. Chief District Engineer Kentucky Transportation Cabinet 1 Introduction Original Construction Completed 1867 First Major Reconstruction
More informationPueblo's New 4th street
PROJECT Pueblo's New 4th street BRIDGE Bridge aesthetics selected by the Pueblo community complement the bridge theme, which blends contemporary sculpture, natural environment, and Pueblo heritage. Rendering:
More informationUNDERWATER BRIDGE INSPECTION REPORT DISTRICT 6 - RICE COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 66532 227 th STREET (TWP 45) OVER THE STRAIGHT RIVER DISTRICT 6 - RICE COUNTY SEPTEMBER 12, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION
More informationJohn James Audubon Bridge. Introduction
John James Audubon Bridge Introduction The Project Why build the bridge? The bridge--proposed to be the longest cable-stayed bridge in America--will replace an existing ferry between the communities of
More informationSTATUS OF MAJOR PROJECT INVESTMENTS BRIEFING TO INLAND WATERWAYS USERS BOARD
STATUS OF MAJOR PROJECT INVESTMENTS BRIEFING TO INLAND WATERWAYS USERS BOARD February 20, 2009 Sandy Gore Project Programs Team 1 $ Million 450 400 350 300 250 200 150 100 50 0-50 -100-150 IWTF HISTORY
More informationAccelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents
Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents Washington State s Skagit River Bridge Emergency Slide Bijan Khaleghi
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2015 FEBRUARY 2016 Phase 2 Cost Summary December Expenditures $ 62.9 Million Total Expenditures $ 655.6 Million
More informationEXODERMIC DEXKS AND STEEL BRIDGES
EXODERMIC DEXKS AND STEEL BRIDGES Recent revisions to the Exodermic design promise to further reduce costs and simplify erection By Robert A. Bettigole Pictured at top is part of the Boston Central Artery/Tunnel
More informationPennDOT e-notification No. 13
PennDOT e-notification No. 13 Bureau of Project Delivery Bridge Design and Technology Division April 3, 2006 (Revised April 2016) Interim Revision to Bridge Standard Drawing(s) Drawing 86-353 PE (Change
More informationESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA
ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE 412.1 OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA BURLINGTON NORTHERN AND SANTA FE RAILWAY By: John W. Hronek
More informationConstruction of Bridges
Construction of Bridges Materials suitable for the Construction of Long-span Bridges 1. Stone in arch masonry 2. Steel in girder or box-section constructed in steel plates and standard sections 3. Steel
More informationJane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions
Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions Scott Eshleman, P.E., S.E, CVS, Stanley Consultants Keith Sargent, P.E., Thomas Engineering Group, LLC February
More informationASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa
2014 HDR Architecture, 2014 HDR, Inc., all rights reserved. ASCE STRUCTURAL ENGINEERING CONFERENCE Ames Iowa WHAT DO YOU DO IF YOU HAVE MORE PROJECT THAN BUDGET? DESIGN BUILDER SELECTION METHOD Fixed Price
More informationPresented by: Taya Retterer BRG Webinar July 30, 2012
Presented by: Taya Retterer BRG Webinar July 30, 2012 PHASED CONSTRUCTION RECOMMENDATIONS FOR BRIDGES Will be posted to the TxDOT Website http://www.dot.state.tx.us/business/contractors_consultants/bridge/default.htm
More informationAPPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES
APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES Massachusetts Department of Transportation Highway Division I-95 / Whittier Bridge Replacement Type Study Report 6. Evaluation of
More informationGrade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.
Grade Separation Systems Single-Span Rail Bridge Construction Procedure An innovation from art engineering inc. GSS Single-Span Example Shown: An existing railroad grade crossing. Existing railroad Existing
More informationIMUA ANNUAL PRESENTATION 2013
IMUA ANNUAL PRESENTATION 2013 1 Who We Are: Founded in 1947 in Colorado Have expanded to a company of approximately 2,000 With Operations Constructing Transportation, Water and Energy Infrastructure throughout
More informationJohn A. Roebling Bridge Rehabilitation History
John A. Roebling Bridge Rehabilitation History Presented By: Rob Hans, P.E. Senior Project Manager CT Consultants, Inc. Former Chief District Engineer Kentucky Transportation Cabinet 1 Bridge History Original
More informationWidening the Harrods Creek Arch Bridge
Approaches to Historic Bridge Rehabilitation Case Study #1 Widening the Harrods Creek Arch Bridge Richard Sutherland, P.E. Daryl Carter, P.E. Presenter s Logo 1 Case Study #1 Harrods Creek Arch Bridge
More informationRt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016
Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb
More informationSTRUCTURES INSPECTION SELF STUDY TRAINING COURSE PART ONE
STRUCTURES INSPECTION SELF STUDY TRAINING COURSE PART ONE 2012 STRUCTURES INSPECTION SELF STUDY TRAINING COURSE PART ONE 2012 STATE CONSTRUCTION OFFICE This 2012 update was produced by Dan Hurtado, P.
More information3.0 TEMPORARY DETOUR BRIDGES
3.0 TEMPORARY DETOUR BRIDGES Table of Contents 3.1 General...1 3.2 STORAGE SITES:...2 3.3 BID ITEMS:...2 3.4 INDEX OF PLAN SHEETS with H-Pile:...3 3.5 INVENTORY SHEET FOR DETOUR BRIDGES WITH H-PILE:...4
More informationHistoric Bridge Foundation Facebook Archives
Historic Bridge Foundation Facebook Archives Focus Bridge: Adamsville Bridge April 2016 The Adamsville Bridge is one of the most unique historic bridges in America. It is a reinforced concrete cantilever
More informationI-74 over the Mississippi River
I-74 over the Mississippi River Design and Construction of Arch Foundations 104 th Transportation and Highway Engineering Conference Presented by: Andrew J. Keaschall, PE, SE, Alfred Benesch & Company
More informationLesner Bridge Replacement
Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on
More informationRESILIENT INFRASTRUCTURE June 1 4, 2016
RESILIENT INFRASTRUCTURE June 1 4, 2016 WESTMINSTER DRIVE UNDERPASS ACCELERATED BRIDGE CONSTRUCTION USING GIGO (GET IN-GET OUT) BRIDGE CONCEPT Mark D Andrea, M.Sc., P.Eng. Stantec Consulting Ltd., Canada
More informationRESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO
RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT July 1, 2017 to September 30, 2017 Period Year 2 Project Shake Table Studies of a Bridge System with ABC Connections Submitted by M. Saiidi,
More informationFairfax Bridge Rehabilitation Program - Bridge Preventive Maintenance Program. January 29, 2014
Fairfax Bridge Rehabilitation Program - Bridge Preventive Maintenance Program - Creek Road Bridge Presented by the Team of January 29, 2014 Bridge Design Process Project team explores both repair and replace
More informationRESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO
RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT October 1, 2017 to December 31, 2017 Period Year 2 Project Shake Table Studies of a Bridge System with ABC Connections Submitted by M. Saiidi,
More informationFort (M-85) Street Bascule Bridge
Fort (M-) Street Bascule Bridge DESIGN Overview History Geotech/Substructures Superstructure Aesthetics CONSTRUCTION Steel and Machinery Fabrication Existing Bridge Removal Road Reconstruction Bridge Replacement
More informationOHIO S CONCRETE BRIDGES
Ohio Fulton Road BRIDGE REPLACEMENT by Gregory Kronstain, Ohio Department of Transportation, John Dietrick, Michael Baker Jr. Inc., and Brendan Finn, Cuyahoga County Engineer s Office OHIO S CONCRETE BRIDGES
More informationDesign studies of the Castle Bridge over Wislok River in Rzeszow with application of CAD System
Design studies of the Castle Bridge over Wislok River in Rzeszow with application of CAD System Author: Dariusz Alterman Superviser: Dr. Tomasz Siwowski, Civ. Eng. Chairman of the examination committee:
More informationReplacing the Aging US 52 Mississippi River Bridge
2019 TRANSPORTATION & HIGHWAY ENGINEERING CONFERENCE F. Duncan, PE, G. Hasbrouck, PE and A. Dour, PE Replacing the Aging US 52 Mississippi River Bridge February 26, 2019 Project Overview US 52 / IL 64
More informationIN THE EYE OF THE STORM: UTILIZING PRECAST SOLUTIONS TO ACCELERATE BRIDGE CONSTRUCTION
IN THE EYE OF THE STORM: UTILIZING PRECAST SOLUTIONS TO ACCELERATE BRIDGE CONSTRUCTION Darin Splittgerber, PE, HDR Engineering Inc., Kansas City, MO Dusten Olds, PE, HDR Engineering Inc., Omaha, NE ABSTRACT
More informationSpecification Changes and Their Effect on Plans. Bridge Construction Issues. BRG VTC April, 2010
Specification Changes and Their Effect on Plans Bridge Construction Issues BRG VTC April, 2010 Brian D. Merrill, P.E. BRG Construction & Maintenance Branch Also: Common Plan Review Items Revised Specifications
More informationARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company
James P. Hyland Page 1 ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING Kansas City Terminal Railway Company James P. Hyland, P.E. Senior Bridge Engineer TranSystems Corporation James P. Hyland Page 2
More informationUNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 60019 MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS AUGUST 29, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF
More informationH3-2 LIST OF ACTIVE ONTARIO PROVINCIAL STANDARD DRAWINGS Division 900 Fencing and Guide Rails
0911.1300 Type A, Installation 0911.1310 Type C, Installation 0911.1320 Tall Wall, Installation 0911.1400 Guide Rail System Concrete Barrier, Precast I-Lock Connection, Installation - Temporary and Permanent
More informationDEVELOPMENT OF GUIDE FOR SELECTION OF SUBSTRUCTURE FOR ABC PROJECTS
DEVELOPMENT OF GUIDE FOR SELECTION OF SUBSTRUCTURE FOR ABC PROJECTS Quarterly Progress Report For the period ending August 31, 2018 Submitted by: PIs - Armin Mehrabi, Hesham Ali Graduate Students - Mohamadtaqi
More informationThe OMO River Bridge/2010
Sometimes the simplest bridge designs come in the most complex and innovative engineering and construction packages. Such is the case with the OMO River Bridge located in the Southern Nations and Nationalities
More informationSociety of Women Engineers Region H Conference
Society of Women Engineers Region H Conference Faith Duncan, PE & Greg Hasbrouck, PE Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Project Overview US 52 / IL 64 over the Mississippi
More informationAccelerated Bridge Construction Award
Accelerated Bridge Construction Award PBES SR 288 Main Street Bridge Project Wampum Borough, Pennsylvania This is a first for PADOT to incorporate an all precast project built in an accelerated manner
More informationVT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017
VT 14 East Montpelier Bridge Project Informational Meeting February 22, 2017 Welcome & Introductions VTrans Mark Sargent, Project Manager Wayne Symonds, Structures Program Manager Chris Barker, Resident
More informationUNDERWATER BRIDGE INSPECTION REPORT DISTRICT 4 - WILKIN COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 84505 CSAH NO. 14 OVER THE OTTER TAIL RIVER DISTRICT 4 - WILKIN COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC.
More informationSafe, innovative, quality construction since Riding on the Strength
Safe, innovative, quality construction since 1880 Riding on the Strength of EXPERIENCE The Expertise The Experience The People The Equipment The Work Ethic The quality To get your job done safely, on time
More informationProvincial Highways Management. Ministry of Transportation PRODUCTION RATES. Contract Management Office Estimating Section
Provincial Highways Management Ministry of Transportation PRODUCTION RATES Estimating Section 2011 2011 Production Rates Manual: Edited by: Paul Sosney Head, Contract Award Last Update: May 2011 Technical
More informationSOUTH MEDFORD INTERCHANGE BRIDGES
Eleven bridges were required for the project THe I-5 south medford Interchange by Keith Kaufman, Knife River Corporation Northwest and Daniel J. McIntier, formerly with H.W. Lochner Inc. Interstate 5 is
More informationREHABILITATION PACKAGE 4-a
4-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 4-a Rehab option 4-a is a rehabilitation package whereby all spans of the existing steel truss structure would be rehabilitated and strengthened.
More informationDESIGN AND LAUNCHING OF A REDUNDANT TRUSS OVER RAILROAD YARD
2018 Purdue Road School Transportation Conference Rendering by Touchstone Architecture Martin Furrer, PE, SE March 6, 2018 DESIGN AND LAUNCHING OF A REDUNDANT TRUSS OVER RAILROAD YARD Project Location
More informationG2-0 LIST OF ACTIVE MTODs
G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw
More information