Highway Construction Program

Size: px
Start display at page:

Download "Highway Construction Program"

Transcription

1 Highway Construction Program Monthly Delivery Progress Report Watch List April 2017 This report focuses on Capital Highway Program projects, which have, or may have significant changes in scope, schedule, or budget. These projects are reported monthly by CPDM to identify when and how these delivery issues are resolved. The Monthly Delivery Progress Report Watch List replaces the quarterly delivery progress report previously known as The Gray Notebook Watch List. A monthly report allows for timely reporting and improves transparency on delivery progress. This report sorts projects into three categories: new projects being reported on, changes from last month, and projects previously reported that have no changes and are not yet resolved. o New projects this month. These projects have been added to the watch list due to potential changes or issues in scope, schedule, or budget. This category also includes projects with changes that occurred and were resolved within the current month. o Changes from Prior Month. Changes discussed in this section were on the previous month s watch list and have other issues that have happened; or they may have been resolved. o No Changes from Prior Month. These projects were on the previous month s watch list and are being followed while an issue is in the process of being resolved. o Projects are Removed when delivery has been delayed out of the Six-Year Plan, when delivery has been attained, or when a significant issue has been mitigated and/or approved by WSDOT. For additional information on scope, schedule and budget for all projects, please visit WSDOT's project pages. This is the link that leads to the websites of individual projects: To search for a particular project, please enter the state route, county, project title or PIN. 1 April 2017

2 Summary Delivery Progress Report Summary Table as of April 30, 2017, with issues based on a monthly update. New in April 2017 Project I-90/N Fork Issaquah Creek - Fish Passage (King) B SR 524/Great Dane Creek - Fish Passage (Snohomish) D SR 529/NB Union Slough Bridge - Scour Repair (Snohomish) B US 2/West of Leavenworth - Slope Stabilization (Chelan) N US 2/Stevens Pass - Avalanche Deflection Berm (King) Y SR 20/Loup Loup Pass - Emergency Repair 2017 (Okanagan) J US 97/Swauk Creek Campground - Fish Passage Retrofit (Kittitas) M US 12/Unnamed Tributary to Wynoochee River Remove Fish Barrier (Grays Harbor) A US 101/Elwha River Bridge - Bridge Replacement (Clallam) F SR 112/Olsen Creek in Vicinity of Vista Dr Remove Fish Barrier (Clallam) A I-5/Woodland Vicinity at Horseshoe Lake - Upgrade Pump System (Clark, Cowlitz) W I-5/NB Interstate Bridge - South Tower Trunnion Replacement (Clark) T US 12/Indian Creek Vic to Wildcat Creek Bridge Vic Paving (Yakima) T Phase/Issue Construction: Cost increase Design: Schedule delay, Cost increase Design: Schedule delay Design: Schedule delay, Cost increase Design: Schedule delay Construction: Emergent project Design: Schedule delay Construction: Cost increase 2 April 2017

3 SR 167/SR 509 Puget Sound Gateway (King, Pierce) M00600R Design: Staging update Changes from Prior Month Project SR 548/Kickerville Rd - Intersection Improvements (Whatcom) B I-5/NB S Spokane St Vic - Concrete Pavement Replacement (King) G I-5/NB Spokane St to Lake WA Ship Canal Bridge - Special Bridge Repair I-5/Northbound Boeing Access Rd to NE Ravenna Bridge - Pavement Repair (King) I-5/NB I-90 Vic to James St Vic - Concrete Pavement Replacement (King) B SR 3/Belfair Area - Widening and Safety Improvements (Mason) D Phase/Issue Design: Schedule delay Construction: Cost increase No Changes from Prior Month Project I-5/SR 510 Interchange - Reconstruct Interchange (Thurston) C (CWA SR 14/West Camas Slough Bridge-Bridge Widening (Clark) A (CWA Revenue SR 99/S King St Vic to Roy St - Viaduct Replacement (King) E Phase/Issue Design: scope change, design element Design: scope change, design element Construction: cost estimate, schedule update Removed in March 2017 Project I-90/N Fork Issaquah Creek - Fish Passage (King) B Phase/Issue Construction: Cost increase 3 April 2017

4 SR 524/Great Dane Creek - Fish Passage (Snohomish) D SR 529/NB Union Slough Bridge - Scour Repair (Snohomish) B US 2/West of Leavenworth - Slope Stabilization (Chelan) N US 2/Stevens Pass - Avalanche Deflection Berm (King) Y SR 3/Belfair Area - Widening and Safety Improvements (Mason) D SR 548/Kickerville Rd - Intersection Improvements (Whatcom) B SR 20/Loup Loup Pass - Emergency Repair 2017 (Okanagan) J US 97/Swauk Creek Campground - Fish Passage Retrofit (Kittitas) M US 12/Unnamed Tributary to Wynoochee River Remove Fish Barrier (Grays Harbor) A US 101/Elwha River Bridge - Bridge Replacement (Clallam) F SR 112/Olsen Creek in Vicinity of Vista Dr Remove Fish Barrier (Clallam) A I-5/Woodland Vicinity at Horseshoe Lake - Upgrade Pump System (Clark, Cowlitz) W I-5/NB Interstate Bridge - South Tower Trunnion Replacement (Clark) T US 12/Indian Creek Vic to Wildcat Creek Bridge Vic Paving (Yakima) T SR 167/SR 509 Puget Sound Gateway (King, Pierce) M00600R Design: Schedule delay, Cost increase Design: Schedule delay Design: Schedule delay, Cost increase Design: Schedule delay Construction: Cost increase Design: Schedule delay Construction: Emergent project Design: Schedule delay Construction: Cost increase Design: Staging update Project Detail Below is the detail behind the above summary. 4 April 2017

5 New in April 2017 I-90/N Fork Issaquah Creek - Fish Passage (King) B Issue: The total cost estimate for the project has increased. This project is being reported and removed from this list. This project will realign North Fork Issaquah Creek near East Lake Sammamish Parkway. The creek crosses Front Street on and off ramps from I-90 twice but will be re-routed north to flow underneath East Lake Sammamish Parkway. A box culvert will be installed at the new creek location. A second culvert will be built underneath the highway to give the local migratory trout and salmon additional access to a nearby offshoot of North Fork Issaquah Creek. When complete, this project will open up almost a mile of additional fish habitat. The current total cost estimate increased by $2.4 million, from $5.2 million to $7.6 million. Initially, the project estimate was increased by $655,000 to install a new culvert for the tributary culverts that were identified within the project limits. WSDOT also received high bids, which further increased the project by $1,750,000. The construction contract was awarded on March 17, Construction is scheduled to begin summer 2017, and be completed fall SR 524/Great Dane Creek - Fish Passage (Snohomish) D Issue: The schedule has been delayed and the total cost estimate has increased. This project is being reported and removed from this list. This project will replace a small box culvert on Great Dane Creek with a larger culvert and rebuild the nearby streambed to provide a clearer passage for salmon and steelhead. The creek passes under State Route 524/Maltby Road just west of SR 9/Woodinville-Snohomish Road. When complete, this project will open up an additional 4.5 miles of fish habitat and help restore historical fish migration patterns. Originally, the construction phase was planned to be advertised in early 2017 and completed in fall Delays with attaining the Corps of Engineers permit delayed the right of way acquisition. Subsequently, advertisement was delayed eight months from early 2017 to fall 2017, and the operational completion was delayed by one year to fall The current cost estimate has increased by $308,000, from $1.1 million to $1.4 million. This project required more extensive coordination with the Muckleshoot Tribe and Corps than was originally anticipated. In addition, the culvert span length changed from 16 feet 5 April 2017

6 to 19 feet in an effort to address stakeholder's concerns with the dimensions of the new culvert. SR 529/NB Union Slough Bridge - Scour Repair (Snohomish) B Issue: The schedule has been delayed. This project is being reported and removed from this list. This project will repair the water's scour action that has removed soils from under the pile cap at Pier 9. Large boulders will be placed at Piers 5, 6, 8, 9, 10 and 11 on the northbound State Route 529 Steamboat Slough Bridge between Everett and Marysville. Originally, the construction phase was planned to be advertised in winter 2018 and completed in fall WSDOT will now combine this work with SR 529/SB Union Slough Bridge - Rehabilitation (152906E) and SR 529/NB Union Slough Bridge - Substructure Repair (152906F) to reduce traveler impacts and gain construction efficiencies. Combining the work will delay the advertisement by eight months to fall 2018, which will extend the construction duration from one season to two. This will delay the project completion by two years, to fall US 2/West of Leavenworth - Slope Stabilization (Chelan) N Issue: The project footprint has changed, which has delayed the schedule one year and may increase the total project cost estimate. This project is being reported and removed from this list. This project will stabilize the rock slopes by placing cable net, rock bolts, and rock doweling, and removing loose rock from the slope. The project is located on the eastside of US 2, near Fall Creek, five miles west of Leavenworth. Originally, the construction phase was planned to be advertised in fall 2016 and completed in fall The construction was delayed by two years, which has delayed the advertisement to fall 2018 and completion to fall WSDOT's use of drones during the geotechnical investigation identified additional potentially unstable rocks just outside the project limits and above where the cable nets and rock bolts are to be installed. The agency determined removing these potentially unstable rocks should be included in this project before the cable nets are installed. The project has been delayed because more time is needed to perform additional analysis to better understand project impacts and determine the appropriate course of action. WSDOT will provide more information as it becomes available. US 2/Stevens Pass - Avalanche Deflection Berm (King) Y 6 April 2017

7 Issue: The project has been delayed. This project is being reported and removed from this list. This project will construct a berm to redirect avalanches and debris from reaching the highway. The project is located just east of Tunnel Creek on the eastside of the Stevens Pass Highway (U.S. Highway 2). When complete, this project will mitigate delays to the traveling public and protect the highway. Originally, the construction phase was planned to be advertised in winter of 2018 and completed in the fall The advertisement was delayed 10 months to fall 2018 and will be constructed during The project was delayed to align with the availability of Western Federal Lands grant funding. SR 20/Loup Loup Pass - Emergency Repair 2017 (Okanagan) J Issue: Due to excessive rain, a mudslide covered the State Route 20 roadway. This project is being reported and removed from this list. A substantial rain event occurred on Friday, April 7, over an area that remains unstable after it was badly burned in the Carlton Complex Fire of Mud, water, and debris blocked the roadway at a location approximately four miles east of Twisp. The rain caused flash flooding that washed out and plugged culverts and drainage structures, undermined the highway shoulder, removed a large section of driving lane, and caused a rockslide that covered both lanes of State Route 20. The project will repair the damaged roadway and drainage features to restore safe operation of the highway. The estimated cost for the repair work is $675,000. US 97/Swauk Creek Campground - Fish Passage Retrofit (Kittitas) M Issue: The construction duration has changed, which has delayed the project completion. This project is being reported and removed from this list. This project will build new structures that are fish passable to replace the two existing culverts on Swauk Creek that cross under the highway. This project is located on U.S. 97, approximately 3 miles north of the Mineral Springs Resort. Originally, the construction was planned to be advertised in fall 2017 and completed in fall 2018, within one construction season. The construction duration has increased from one to two seasons, which has delayed the project completion to fall The delay will provide additional time to perform hydraulic design and obtain concurrence from the U.S. Forest Service and environmental permitting agencies. The 7 April 2017

8 delay also aligns with funding provided by Mid-Columbia for stream restoration on the portion of Swauk Creek between the new structures. US 12/Unnamed Tributary to Wynoochee River Remove Fish Barrier (Grays Harbor) Issue: The total cost estimate on this project has increased. This project is being reported and removed from this list. The existing drainage structure at this location has been identified as a fish passage barrier. By replacing the existing structure with a fish passable structure, the restriction to fish passage will be eliminated. The total project cost has increased by $2.3 million, from $3.6 million to $5.9 million. With design underway, a more refined estimate indicates a need for additional funds for design, right of way, and construction. The current design cost estimate is consistent with WSDOT s other recently designed fish passage projects. The right of way increase is due to a need that was not identified during the scoping phase. The construction cost increase is due to increasing the size of the culvert from 125 feet long to 218 feet long. US 101/Elwha River Bridge - Bridge Replacement (Clallam) F Issue: The total cost estimate on this project has increased. This project is being reported and removed from this list. The existing bridge built in 1926 is structurally deficient. This project replaces the existing bridge with a new structure designed to meet current standards. The new structure will reduce the potential for catastrophic failure and preserve the functional integrity of the roadway. Since the Elwha Dam was removed, the Elwha River has been reestablishing its natural grade and position in the valley. The river has eroded 14 feet of depth from the river bottom exposing and partially undermining pier foundations. The bridge sufficiency rating has dropped and the rating is structurally deficient. A Preliminary Engineering (PE) phase of $500,000 has initially been set up to begin alternatives analysis, environmental process, and to support community engagement. The PE phase is being increased by $2.3 million for the design of the replacement bridge. The Right of Way and Construction phases will also be established after further design. SR 112/Olsen Creek in Vicinity of Vista Dr Remove Fish Barrier (Clallam) A Issue: The total cost estimate on this project has increased. This project is being reported and removed from this list. 8 April 2017

9 The existing drainage structure at this location has been identified as a fish passage barrier. By replacing the existing structure with a fish passable structure, the restriction to fish passage will be eliminated. The project total has increased by $1.3 million, to $4.1 million. With design underway, a more refined estimate indicates a need for additional funds for design, right of way, and construction. The current design cost estimate is consistent with WSDOT s other recently designed fish passage projects. The right of way increase is due to needs that were not identified during the scoping phase. The construction cost increase is due to a change in the bridge type. I-5/Woodland Vicinity at Horseshoe Lake - Upgrade Pump System (Clark, Cowlitz) W Issue: The total cost estimate on this project has increased. This project is being reported and removed from this list. This project will enable a consistent flow from the Lewis River into Horseshoe Lake to continue. WSDOT currently maintains and operates a pump from the Lewis River near Woodland under I-5 to Horseshoe Lake to prevent the lake from becoming stagnant. The pump intake screens do not meet current standards. The Washington Department of Fish & Wildlife requested that WSDOT bring the screens up to current standards before issuing a new Hydraulic Project Approval permit, which expired in summer WSDOT will work with a consultant to design and install the system upgrade. The consultant team completed their analysis and presented a final alternatives analysis report to WSDOT in January. After evaluating a wide spectrum of possible pump options and configurations, WSDOT endorsed moving forward with an inclined pump, the most cost effective option. The inclined pump will be constructed adjacent to the existing pump and will extend from the edge of the riverbank into the river. It has an attached fish screen suspended above the riverbed. The cost of the preferred alternative is $2.7 million, which is $2.2 million more than originally budgeted. I-5/NB Interstate Bridge - South Tower Trunnion Replacement (Clark) T Issue: The total cost estimate on this project has increased. This project is being reported and removed from this list. This project will extend the Interstate Bridge service life by replacing the lift span trunnion shaft on the south tower. The Oregon Department of Transportation is the lead on this project and shares costs equally with WSDOT. 9 April 2017

10 Previous budget estimates were based on the 1997 north tower trunnion replacement. A recently updated estimate paid special attention to change orders and claims on the previous project, as well as increased labor rates and changes in traffic conditions. As a result, the WSDOT portion of the project cost has increased by $3.4 million, to $8.2 million. US 12/Indian Creek Vic to Wildcat Creek Bridge Vic Paving (Yakima) T Issue: The total cost estimate on this project has increased. This project is being reported and removed from the list. This project will rehabilitate the existing deteriorating pavement on U.S. 12 east of White Pass along Rimrock Lake. The estimated cost has increased by $686,000, from $2.3 million to $3 million. The increase is mainly due to higher than expected bids. In addition, the Wildcat Bridge deck has experienced significant deterioration due to the recent winter conditions. WSDOT will remove the bumps and repair the pavement as an interim fix to extend the bridge deck life until the bridge is replaced; construction will start in SR 167/SR 509 Puget Sound Gateway (King, Pierce) M00600R Issue: Switching the order of staging on the project. This project is being reported and removed from this list. The overall Gateway Project constructs a new four-lane alignment on SR 167 between I-5 in Tacoma and SR 161 in Puyallup and will connect SR 509 south from SeaTac to I- 5. Through WSDOT s practical design process and in meetings with stakeholders, the strategic implementation plan identified staging the project in the following order along SR 167: I-5 to SR 509 before I-5 to SR 161. This accelerates the SR 167/I-5 to SR 509 portion of the project by four years, and delays the 167/I-5 to SR 161 portion of the project by five years. Additionally, WSDOT is adjusting the funding totals to better match the needs of the stages. A transfer of $140 million from the SR 167/I-5 to Stage 1 will be made to the SR 167/I-5 to Stage 2. There is no cost change to the overall SR 167/SR 509 Puget Sound Gateway project. Changes from Prior Month SR 3/Belfair Area - Widening and Safety Improvements (Mason) D 10 April 2017

11 Changes from Prior Report: The total cost estimate on this project has increased. This project is being reported and removed from this list. Roadway improvements on this project will address traffic congestion, safety and the need for pedestrian facilities from SR 106 to NE Belfair Street. Improvements include the continuation of the existing two-way left turn lane from the vicinity of the intersection of SR 3 and Romance Hill Road to the intersection of SR 3 and SR 106. Other improvements are pedestrian and bicycle facilities, storm sewer improvements, and mitigation requirements. When complete, this project will relieve congestion and enhance motorist safety. Previously reported: Heavy rainfall and a higher than expected water table caused three detention ponds to flood. The ponds were redesigned, resulting in project delays and cost increases of $1 million. Update to the September 2016 report: Previously, there was insufficient information for the construction costs associated with the drainage redesign. Change orders and additional construction costs will now increase the project cost estimate an additional $2.3 million. I-5/NB S Spokane St Vic - Concrete Pavement Replacement (King) G Changes from Prior Report: The cost estimate has increased and the schedule has been delayed. Previously reported: This project, estimated at $8.6 million, is in the design phase. This concrete pavement replacement project has been combined with the I-5/NB Martin Luther King Jr Way to NE Ravenna Br - Pavement Repair & More project into a single design-build contract, to potentially reduce the overall cost of the project and associated traffic impacts. The construction delivery for this project has been delayed by one year from 2017 to 2018 to align with the delivery schedule of the second project. This project is now scheduled to be advertised in fall 2016 and operationally complete in fall Update to the August 2015 report: The current cost estimate has increased by $2.4 million, from $8.6 million to $11 million. All Proposers exceeded the project budget amount and indicated that the project risk was the most significant reason for the increase. Some of the project risks identified are: Lack of access to and from the work site would delay construction trucks from reaching the work site on time. Weekend closure restrictions and no available weekends to work during the summer. Too many projects in the area competing for the same labor pool. 11 April 2017

12 Construction at night or on weekends, requiring overtime and premium pay for trucks and labor. A safety risk for weekend construction, which will take place next to live traffic. As a result, WSDOT is currently in negotiation with the Proposers to reach a best and final offer. I-5/NB Spokane St to Lake WA Ship Canal Bridge - Special Bridge Repair (King)100522C Changes from Prior Report: The cost estimate has further increased and there is a potential schedule risk. Previously reported: WSDOT updated the project cost estimate to reflect additional reinforced concrete panel replacement work and bridge approach slabs, a contract incentive to reduce the number of weekend closures, and updated unit bid prices on several bid items, based on recent projects costs. In addition, 37 expansion joints on 10 bridges on I-5 were identified and added to the I-5/NB Spokane St to Lake WA Ship Canal Bridge - Special Bridge Repair (100522C) project. The additions increased the construction duration of the design-build contract from one season to two. The increased work will delay operational completion by one year, from fall 2018 to fall Update to the February 2017 report: The current cost estimate has further increased by $1.3 million, from $5 million to $6.3 million. All Proposers exceeded the project budget amount and indicated that the project risk was the most significant reason for the increase. Some of the project risks identified are: Lack of access to and from the work site, which would delay construction trucks from reaching the work site on time. Weekend closure restrictions and no available weekends to work during the summer. Too many projects in the area competing for the same labor pool. Construction at night or on weekends, requiring overtime and premium pay for trucks and labor. A safety risk for weekend construction, which will take place next to live traffic. In addition, a potential schedule risk was identified: the construction duration could be delayed to a third season, further delaying the operationally complete date by one year, from fall 2019 to fall As a result, WSDOT is currently in negotiation with the Proposers to reach a best and final offer that is agreeable. I-5/Northbound Boeing Access Rd to NE Ravenna Bridge - Pavement Repair (King) 12 April 2017

13 Changes from Prior Report: The cost estimate has further increased and there is a potential schedule risk. Previously reported: WSDOT updated the project cost estimate to reflect additional reinforced concrete panel replacement work and bridge approach slabs, a contract incentive to reduce the number of weekend closures, and updated unit bid prices on several bid items, based on recent projects costs. In addition, 37 expansion joints on 10 bridges on I-5 were identified and added to the I-5/NB Spokane St to Lake WA Ship Canal Bridge - Special Bridge Repair (100522C) project. The additions increased the construction duration of the design-build contract from one season to two, delaying the operationally complete date by one year, from fall 2018 to fall Update to the February 2017 report: The current cost estimate has further increased by $4 million, from $16.9 million to $20.9 million. All Proposers exceeded the project budget amount and indicated that the project risk was the most significant reason for the increase. Some of the project risks identified are: Lack of access to and from the work site, which would delay construction trucks from reaching the work site on time. Weekend closure restrictions and no available weekends to work during the summer. Too many projects in the area competing for the same labor pool. Construction at night or on weekends, requiring overtime and premium pay for trucks and labor. A safety risk for weekend construction, which will take place next to live traffic. In addition, a potential schedule risk was identified: the construction duration could be delayed to a third season, further delaying the operationally complete date by one year, from fall 2019 to fall As a result, WSDOT is currently in negotiation with the Proposers to reach a best and final offer that is agreeable. I-5/NB I-90 Vic to James St Vic - Concrete Pavement Replacement (King) B Changes from Prior Report: The cost estimate has further increased and there is a potential schedule risk. Previously reported: WSDOT updated the project cost estimate to reflect additional reinforced concrete panel replacement work and bridge approach slabs, a contract incentive to reduce the number of weekend closures, and updated unit bid prices on several bid items, based on recent projects costs. In addition, 37 expansion joints on April 2017

14 bridges on I-5 were identified and added to the I-5/NB Spokane St to Lake WA Ship Canal Bridge - Special Bridge Repair (100522C) project. The additions increased the construction duration of the design build contract from one season to two, delaying the operationally complete date by one year from fall 2018 to fall Update to the February 2017 report: The current cost estimate has increased by $2.9 million, from $8.6 million to $11.5 million. All Proposers exceeded the project budget amount and indicated that the project risk was the most significant reason for the increase. Here are some of the project risks identified: Lack of access to and from the work site, which would delay construction trucks from reaching the work site on time. Weekend closure restrictions and no available weekends to work during the summer. Too many projects in the area competing for the same labor pool. Construction at night or on weekends, requiring overtime and premium pay for trucks and labor. A safety risk for weekend construction, which will take place next to live traffic. In addition, a potential schedule risk was identified: the construction duration could be delayed to a third season, further delaying the operationally complete date by one-year from fall 2019 to fall As a result, WSDOT is currently in negotiation with the Proposers to reach a best and final offer that is agreeable. SR 548/Kickerville Rd - Intersection Improvements (Whatcom) B Changes from Prior Report: Continuing delays with right of way acquisition have further delayed the project. This project is being reported and removed from this list. Previously reported: WSDOT increased the diameter of the roundabout from 75 feet to 110 feet. This intersection is the primary access route for the Cherry Point Refinery, which has a high percentage of left-turning truck traffic. The larger diameter (110-foot) is required for the truck movements. This change increased the project footprint and triggered a need for additional right of way, which delayed the construction from 2016 to 2017 and increased the total project cost to $1.4 million. Update to the August 2015 report: Delays in acquiring the right of way needed for the project has further delayed the project. The advertisement has been delayed by seven 14 April 2017

15 months, from spring 2017 to fall 2017, which will further delay the construction season from 2017 to The completion date will be delayed by one year, to summer No Changes from Prior Month I-5/SR 510 Interchange - Reconstruct Interchange (Thurston) C Status: No Change Previously reported: WSDOT is requesting a scope change to remove the specific interchange type 'Single Point Urban Interchange' (SPUI) from the project description. The available funding for the project is not sufficient to construct an SPUI. Additionally, traffic modeling indicates that a Diverging Diamond Interchange (DDI) performs better and at a significantly reduced project cost. The lead project proponent, the City of Lacey, was part of the Value Engineering workshop that recommended the proposed change. The City Council is in full support of constructing a Diverging Diamond Interchange. SR 14/West Camas Slough Bridge-Bridge Widening (Clark) A Status: No Change Previously reported: WSDOT is requesting a scope change on this project that will defer the improvements and shift funding. Originally, this project was to widen and retrofit the bridge to increase capacity and reduce travel time to accommodate expected residential, commercial, and industrial growth on SR 14. The agency request is to defer the SR 14 West Camas Slough Bridge and shift the funding to another project on the SR 14 Corridor. Funding will go towards addressing congestion on SR 14 from the SR 14/I-205 Interchange to SE 164th Avenue. Initial concepts for the project include constructing auxiliary lanes in both directions between the interchanges and modifying the ramp configuration from I-205 to eastbound SR 14. Community engagement and practical solution implementation will further refine the scope and operational elements of the project. The cities of Vancouver, Camas, and Washougal as well as the Port of Camas/Washougal support this proposed change and are committed to working with WSDOT to identify the best application of these funds to reduce traffic delays along SR 14. SR 99/S King St Vic to Roy St - Viaduct Replacement (King) E Status: No Change. 15 April 2017

16 Previously reported: The original tunnel contract opening date was November The Seattle Tunnel Partners (STP), the design build contractor, first delayed the opening to spring of According to their new schedule, the estimated completion date for the tunnel is November After STP hands over the tunnel to the state, work must be done to connect the new tunnel to SR 99 in the south and Aurora Avenue North in the north. Based on STP s schedule, WSDOT estimates the tunnel would be open to traffic in early The state cannot verify STP s schedule. Based on a preliminary review of the budget, the program anticipates a cash-flow need of up to $60 million in the biennium, to ensure continued progress. Looking toward completion of the viaduct replacement program, the program estimates a total provisional budget need of $223 million. Funds from litigation, insurance claims, and savings from unpaid early completion incentives may offset some of the costs. Due to litigation, funding sources may not be resolved until after the tunnel is open to traffic. Update to the November 2016 report: The Program completed a Cost Risk Evaluation that included statistical modeling to update the total program budget. The program total budget need was reduced to $167 million (from $223 million). Of this amount, $18 million will be covered by local funding. For more updates on the Alaskan Way Viaduct Replacement project, please see the Alaskan Way Viaduct website at 16 April 2017

Highway Construction Program

Highway Construction Program Highway Construction Program Monthly Delivery Progress Report Watch List February 2017 This report focuses on Capital Highway Program projects, which have, or may have significant changes in scope, schedule,

More information

Highway Construction Program

Highway Construction Program Highway Construction Program Monthly Delivery Progress Report Watch List October 2018 This report focuses on Capital Highway Program projects, which have, or may have significant changes in scope, schedule,

More information

Highway Construction Program

Highway Construction Program Highway Construction Program Monthly Delivery Progress Report Watch List November 2018 This report focuses on Capital Highway Program projects, which have, or may have significant changes in scope, schedule,

More information

Implementing Asset Management: WSDOT s Experience

Implementing Asset Management: WSDOT s Experience Implementing Asset Management: WSDOT s Experience 6 th National Conference on Transportation Asset Management Aaron Butters, P.E. Systems Analysis and Program Development Manager November 2, 2005 1 Highway

More information

Mega Projects at WSDOT

Mega Projects at WSDOT Mega Projects at WSDOT Managing multiple projects in major urban corridors LINEA LAIRD, WSDOT ASSISTANT SECRETARY ENGINEERING & OPERATIONS Presentation to Oregon State Legislature Congestion Work Group

More information

King County Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds

King County Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds News Release Contact: Al Sanders 206-477-1016 August 31, 2015 Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds The Flood Control District

More information

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION AUGUST 2015 Table of Contents 1 Decision... 1 1.1 Project Description... 2 1.2 Basis for the FHWA Decision... 7 1.2.1

More information

SOUTH MEDFORD INTERCHANGE BRIDGES

SOUTH MEDFORD INTERCHANGE BRIDGES Eleven bridges were required for the project THe I-5 south medford Interchange by Keith Kaufman, Knife River Corporation Northwest and Daniel J. McIntier, formerly with H.W. Lochner Inc. Interstate 5 is

More information

Oklahoma Department of Transportation Environmental Programs Division Office Fax

Oklahoma Department of Transportation Environmental Programs Division Office Fax Oklahoma Department of Transportation Environmental Programs Division Office 521-3050 Fax 522-5193 Documented Categorical Exclusion (DCE) for I-40: Pavement Reconstruction and Added Lanes from the Douglas

More information

Projects Recommended for Funding

Projects Recommended for Funding 2017-2019 Projects Recommended for Funding The Floodplains by Design coalition requests continued funding at the $60 million level in the FY 2017-19 capital budget. This request will fund new projects

More information

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges I. ABSTRACT Keith A. Riniker, PE, PTOE This paper presents the Folded Interchange design and compares

More information

BMI Precast PRECAST & PRESTRESSED CONCRETE PRODUCTS

BMI Precast PRECAST & PRESTRESSED CONCRETE PRODUCTS PRECAST & PRESTRESSED CONCRETE PRODUCTS has over 80 years experience in the building and concrete industry. We manufacture a wide range of precast, prestressed products from boat ramp planks to pilings,

More information

Reconstruction Project Update

Reconstruction Project Update I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

CLA /10.54, PID Project Description:

CLA /10.54, PID Project Description: Project Description: The proposed project will consist of widening IR 70 to three lanes from Enon Road (SLM 06.75) to the US 68 interchange ramps (SLM 10.55). IR 70 is a component of the Strategic Highway

More information

IMPROVING I 81 IN MARYLAND

IMPROVING I 81 IN MARYLAND IMPROVING I 81 IN MARYLAND April 25, 2017 Stephen A. Bucy, P.E. Improving I 81 in Maryland Overview: Facts SHA s Comprehensive I 81 Strategy Current Phase 1 Widening Project Update Closing Improving I

More information

Assessment of Current Status, Plans, and Preliminary Alternatives for High Capacity Transportation in the I-5 Corridor

Assessment of Current Status, Plans, and Preliminary Alternatives for High Capacity Transportation in the I-5 Corridor CONNECTING THURSTON COUNTY AND THE CENTRAL PUGET SOUND Alternatives to Meet Transportation Needs in the I-5 Corridor Working Paper #1 June 2011 Assessment of Current Status, Plans, and Preliminary Alternatives

More information

Information for File # RJH

Information for File # RJH Information for File #2011-01629-RJH Applicant: Matthew Ternes Corps Contact: Ryan Huber, U. S. Army Corps of Engineers, 211 North Broadway, Suite 221, Green Bay, Wisconsin 54303; ryan.j.huber@usace.army.mil;

More information

APPENDIX N East King County Subarea High Capacity Transit (HCT) Analysis: Approach to Assessing System-Level Alternatives

APPENDIX N East King County Subarea High Capacity Transit (HCT) Analysis: Approach to Assessing System-Level Alternatives Sound Transit Regional Transit Long-Range Plan Draft Supplemental Environmental Impact Statement APPENDIX N East King County Subarea High Capacity Transit (HCT) Analysis: Approach to Assessing System-Level

More information

I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions

I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions General Overview What is the I-65/I-70 North Split Reconstruction Project? The I-65/I-70 North Split Reconstruction Project

More information

Organization. Project Management Institute, Olympia Chapter Date Nov. 20, 2012

Organization. Project Management Institute, Olympia Chapter Date Nov. 20, 2012 Organization Project Management Institute, Olympia Chapter Date Nov. 20, 2012 Program Overview The Alaskan Way Viaduct Replacement Program includes projects led by the Washington State Department of Transportation,

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions) FY 2018-2027 WIDE TRANSPORTATION IMPROVEMENT PROGRAM NY Susquehanna and Western Rail Line Bicycle/Pedestrian Path DBNUM: NS9803 / UPC: 058018 The 4.8 mile New York, Susquehanna, and Western Railway (NYS&W)

More information

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS SECTION PAGE NO. SECTION TITLE NO. EXECUTIVE SUMMARY -------------------------------------------------------------------- ES-1 1.0 INTRODUCTION

More information

Accelerated and Innovative Bridge Construction In Washington State

Accelerated and Innovative Bridge Construction In Washington State Accelerated and Innovative Bridge Construction In Washington State Bijan Khaleghi Bijan.Khaleghi@WSDOT.WA.Gov Washington State Department of Transportation Bridge and Structures Office Olympia Washington

More information

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) ,

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) , PLACEMENT OF PRECAST PRESTRESSED CONCRETE GIRDER BRIDGE SPANS WITH SELF PROPELLED MODULAR TRANSPORTERS PIONEER CROSSING DESIGN/BUILD PROJECT, AMERICAN FORK, UT Steve Haines, P.E., Parsons, (303) 831-8100,

More information

Case Study 15. Moonlight Crossing Concrete Box Vented Ford

Case Study 15. Moonlight Crossing Concrete Box Vented Ford Appendix A Case Study 15 Case Study 15. Moonlight Crossing Concrete Box Vented Ford Location Northeastern California. Plumas National Forest. On Lights Creek, 8 miles north of Taylorsville, CA., Forest

More information

Welcome! Route 1 Viaduct Rehabilitation Project Chelsea Project File No

Welcome! Route 1 Viaduct Rehabilitation Project Chelsea Project File No Welcome! Route 1 Viaduct Rehabilitation Project Chelsea Project File No. 605287 25% Design Public Hearing Chelsea City Hall January 24, 2018 6:30 p.m. Introduction Welcome & Introductions by MassDOT PM

More information

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 1 Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 2 During this public meeting, we will explain the 75 th Street Corridor Improvement

More information

PUBLIC WORKS DEPARTMENT DESIGN & CONSTRUCTION DIVISION OCTOBER 2015 UPDATE

PUBLIC WORKS DEPARTMENT DESIGN & CONSTRUCTION DIVISION OCTOBER 2015 UPDATE PUBLIC WORKS DEPARTMENT DESIGN & CONSTRUCTION DIVISION OCTOBER 2015 UPDATE TJERNE PLACE CHAIN LAKE ROAD TO WOODS CREEK ROAD This project involves extending Tjerne Place from Chain Lake Road to Woods Creek

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions) FY 2018-2027 WIDE TRANSPORTATION IMPROVEMENT PROGRAM ADA Central, Contract 3 DBNUM: 15419 / UPC: 154190 This contract will bring projects into compliance with current ADA design requirements that could

More information

Advanced Construction Techniques

Advanced Construction Techniques Alaskan Way Viaduct Replacement Program Organization University of Washington Date October 20, 2011 Presentation Overview SR 99 south end viaduct replacement. Design-build contracting. SR 99 tunnel project.

More information

Transportation Update

Transportation Update Transportation Update Projects Underway Norview Avenue About the Project: The Norview Avenue Interchange Improvement Project will eliminate the existing weave movement associated with the on- and off-ramps

More information

Tokul Creek Intake Diversion Dam and Fishway Replacement

Tokul Creek Intake Diversion Dam and Fishway Replacement University of Massachusetts Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

Project Information. Pursuant to Section 404 of the Clean Water Act (33 U.S. Code 1344), notice is hereby given that

Project Information. Pursuant to Section 404 of the Clean Water Act (33 U.S. Code 1344), notice is hereby given that US ARMY Corps Of Engineers Little Rock District JOINT PUBLIC NOTICE CORPS OF ENGINEERS STATE OF ARKANSAS Application Number: 2014-00083-1 Date: December 22, 2014 Comments Due: January 16, 2015 TO WHOM

More information

Culvert deep under Everson-Goshen Road may be partially blocked, raising upstream water levels. Fall work. Winter flood damage to Graveline Road.

Culvert deep under Everson-Goshen Road may be partially blocked, raising upstream water levels. Fall work. Winter flood damage to Graveline Road. WHATCOM COUNTY PU BLIC W O RKS D EPARTM EN T Jon Hutchings DIRECTO R ADMINISTRATION CIVIC CENTER 322 N. Commercial Street, Suite 210 Bellingham, WA 98225-4042 Telephone: (360) 778-6230 FAX: (360) 778-6231

More information

NW La Center Road/I-5 Interchange Improvement Project (MP 16.80)

NW La Center Road/I-5 Interchange Improvement Project (MP 16.80) FINAL DRAFT - NW La Center Road/I-5 Interchange Improvement Project (MP 16.80) La Center, Washington February 2015 FINAL DRAFT - NW La Center Road/I-5 Interchange Improvement Project (MP 16.80) La Center,

More information

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the

More information

SR 542 Anderson Creek Culvert

SR 542 Anderson Creek Culvert American Public Works Association Project of the Year Award Submission $5M, but less than $25M Category Environmental Project completed on schedule without extensions. Bridge opened 14 days early. Project

More information

Sound Transit is updating its Regional Transit Long-Range Plan, which

Sound Transit is updating its Regional Transit Long-Range Plan, which Final Supplemental Environmental Impact Statement EXECUTIVE SUMMARY INTRODUCTION Sound Transit is updating its Regional Transit Long-Range Plan, which outlines the agency s vision for a high-capacity transit

More information

Federal Way Transit Center to Tacoma Dome Light Rail

Federal Way Transit Center to Tacoma Dome Light Rail Subarea South King/Pierce Primary Mode Light Rail Facility Type Corridor Length 9.7 miles Date Last Modified July 1, 2016 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION This project

More information

I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017

I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017 I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017 State Project # 0064-965-264, P101, R201, C501, B616, B617, B618, B619, B620, B621, D601, D602 Federal # NHS-064-3(479),

More information

Warren Wagon Road Improvement Project McCall Ranger District, Payette National Forest Project Description

Warren Wagon Road Improvement Project McCall Ranger District, Payette National Forest Project Description Warren Wagon Road Improvement Project McCall Ranger District, Payette National Forest Project Description Introduction The analysis of the Warren Wagon Road Improvement Project is tiered to the 2003 Environmental

More information

ADOT Yuma District. Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012

ADOT Yuma District. Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012 ADOT Yuma District Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012 Active Construction Projects SR 95@ Bill Williams River NWR Rd CAP Intersection US 95, Castle

More information

Zoo Interchange Reconstruction

Zoo Interchange Reconstruction May 14, 2013 Roberto Gutierrez, PE WisDOT Chris Hager, PE - WisDOT Zoo Interchange Reconstruction Overview of Presentation overview WisDOT Southeast Region I-94 North-South I794/I-94 restriping Hoan bridge

More information

Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida

Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida November 7, 2014 SUBMITTED BY: Dewberry Bowyer-Singleton 520 South

More information

I-15 South, MP 0 to MP 16 Environmental Assessment. Public Hearing. August 7, :00 PM to 7:00 PM

I-15 South, MP 0 to MP 16 Environmental Assessment. Public Hearing. August 7, :00 PM to 7:00 PM I-15 South, MP 0 to MP 16 Environmental Assessment Public Hearing August 7, 2012 5:00 PM to 7:00 PM 1 PROJECT OVERVIEW The Federal Highway Administration (FHWA) and the Utah Department of Transportation

More information

Final Recommendations Identification of Improvements, Strategies, and Solutions

Final Recommendations Identification of Improvements, Strategies, and Solutions Identification of Improvements, Strategies, and Solutions Prepared by: December 2015 TABLE OF CONTENTS 1. Introduction... 1 1 2. Freight Policy Recommendations... 2 1 3. Freight Infrastructure Recommendations...

More information

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 WELCOME IL 47 Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 MEETING PURPOSE MEETING AGENDA 1. Welcome/Introduction 2. Review Previous Public Involvement 3. Process/Schedule

More information

Chapter 6 Freight Plan

Chapter 6 Freight Plan Chapter 6 Freight Plan Overview This chapter presents a review and assessment of needs, deficiencies, policies and improvement options affecting the freight transportation system within the Medford Urban

More information

Clinton Keith Road Extension Project

Clinton Keith Road Extension Project Clinton Keith Road Extension Project Addendum to Supplemental Environmental Impact Report (SCH#1995062022) Clinton Keith Road Extension Project Riverside County, California Prepared for County of Riverside

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Lynnwood Link Extension 2013 Draft EIS Comments and Responses Page 157 C-001-001 Sound Transit acknowledges your opposition to Alternative C1 due to its residential impacts and impacts to Scriber Creek Park and wetlands. Page 158 C-002-001 Following the Draft EIS,

More information

FINAL DRAFT - WSDOT Projects Proposed for Federal Stimulus Funding Consideration - Short List

FINAL DRAFT - WSDOT Projects Proposed for Federal Stimulus Funding Consideration - Short List FINAL DRAFT - WSDOT Projects Proposed for Federal Funding Consideration - Short List Federal /Federal Federal Highway Administration (FHWA) Surface Transportation Washington State Ferries Capital Unfunded

More information

State Route 8 Bridge Replacement Project

State Route 8 Bridge Replacement Project OPEN HOUSE PUBLIC INVOLVEMENT MEETING Celebration Church 688 Dan Street, Akron, Ohio Tuesday, July 14, 2015 5:00 PM to 7:00 PM State Route 8 Bridge Replacement Project Existing Bridge Future Bridges: Steel

More information

Appendix Q Draft Location Hydraulic Study Report For the State Route 32 Widening Between Fir Street and Yosemite Drive at Dead Horse Slough and South

Appendix Q Draft Location Hydraulic Study Report For the State Route 32 Widening Between Fir Street and Yosemite Drive at Dead Horse Slough and South Appendix Q Draft Location Hydraulic Study Report For the State Route 32 Widening Between Fir Street and Yosemite Drive at Dead Horse Slough and South Fork Dead Horse Slough in the, California Draft Location

More information

Project Planning area. King County Department of Transportation Road Services Division

Project Planning area. King County Department of Transportation Road Services Division NE Novelty Hill Road Transportation Improvement Citizen Advisory Group Presentation Project Planning area King County Department of Transportation Road Services Division i i February 25, 2009 Why are we

More information

SECTION 55A1 ROBINSON TOWNSHIP, WASHINGTON COUNTY

SECTION 55A1 ROBINSON TOWNSHIP, WASHINGTON COUNTY WEEK ENDING SEPTEMBER 14, 2018 SECTION 55A1 ROBINSON TOWNSHIP, WASHINGTON COUNTY Contractor: Independence Excavating, Inc 1. Work Shift Day shift (M-F) with Saturday as a makeup day. 2. Traffic Candor

More information

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. Welcome Public Meeting August 2, 2017 5:00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. www.glenwoodsouthbridge.net Welcome to the South Bridge Environmental Assessment Public Meeting Why Are We Here Tonight?

More information

Lake Samish Comprehensive Stormwater Plan Capital Improvement Recommendations

Lake Samish Comprehensive Stormwater Plan Capital Improvement Recommendations Lake Samish Comprehensive Stormwater Plan Capital Improvement Recommendations drainage. The easement could potentially be used to site a surface water quality treatment facility for the flow. The design

More information

FINAL. Sound Transit Long-Range Plan Update Issue Paper S.6: Potential Tacoma Link Extension - East. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update Issue Paper S.6: Potential Tacoma Link Extension - East. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.6: Potential Tacoma Link Extension - East Prepared for: Sound Transit Prepared by: Parsons Brinckerhoff Quade & Douglas, Inc. FINAL March 2005 Foreword

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

SR 432 RAIL REALIGNMENT AND HIGHWAY IMPROVEMENTS PROJECT ELECTED AND AGENCY OFFICIALS PROJECT BRIEFING May 14, 2014

SR 432 RAIL REALIGNMENT AND HIGHWAY IMPROVEMENTS PROJECT ELECTED AND AGENCY OFFICIALS PROJECT BRIEFING May 14, 2014 SR 432 RAIL REALIGNMENT AND HIGHWAY IMPROVEMENTS PROJECT ELECTED AND AGENCY OFFICIALS PROJECT BRIEFING May 14, 2014 History: Studies of the SR 432 rail and highway corridor began back in the late 1980s,

More information

Appendix C - Highway 400 Widening and Interchange Evaluation Summary Tables

Appendix C - Highway 400 Widening and Interchange Evaluation Summary Tables Highway 400 Improvements from 1 km South of Highway 89 to the Junction of Highway 11 Appendix C - Highway 400 Widening and Interchange Tables Prepared for: Ontario Ministry of Transportation Four General

More information

Safe, innovative, quality construction since Riding on the Strength

Safe, innovative, quality construction since Riding on the Strength Safe, innovative, quality construction since 1880 Riding on the Strength of EXPERIENCE The Expertise The Experience The People The Equipment The Work Ethic The quality To get your job done safely, on time

More information

1.1 Purpose of the Project

1.1 Purpose of the Project Chapter 1 Purpose and Need for East Link Project 1.1 Purpose of the Project The purpose of the East Link Project is to expand the Sound Transit Link light rail system from Seattle to Mercer Island, Bellevue

More information

Interchange Workshop Report (August 2004)

Interchange Workshop Report (August 2004) U.S. Highway 14 Corridor Study New Ulm to North Mankato Table of Contents Section Interchange Workshop Report (August 2004) Page 1. Introduction and Next Steps 1 2. Interchange Workshop Participants &

More information

Phase 1, SR 509 Completion Project NEPA Re evaluation

Phase 1, SR 509 Completion Project NEPA Re evaluation Economics COPY TO: PREPARED BY: Project File DATE: November, 2017 SUBJECT 1. Introduction Puget Sound Gateway Program Team Phase 1, SR 509 Completion Project NEPA Re evaluation This memorandum was prepared

More information

Review of Construction Costs and Time Schedules for Virginia Highway Projects

Review of Construction Costs and Time Schedules for Virginia Highway Projects Joint Legislative Audit and Review Commission of the Virginia General Assembly Review of Construction Costs and Time Schedules for Virginia Highway Projects JLARC Staff Briefing December 19, 2000 Introduction

More information

5/11/2016 SR 15 SECTION 088 CSVT SOUTHERN SECTION SR 15 SECTION 088 CSVT SOUTHERN SECTION AGENDA

5/11/2016 SR 15 SECTION 088 CSVT SOUTHERN SECTION SR 15 SECTION 088 CSVT SOUTHERN SECTION AGENDA PUBLIC OFFICIALS MEETING MAY 11, 2016 AGENDA I. INTRODUCTIONS V. CURRENT PROJECT STATUS VI. PROJECT SCHEDULE VII. UPCOMING ACTIVITIES VOPEN DISCUSSION & QUESTIONS IX. ACTION ITEMS 1 A. Bridge Lighting

More information

Northeast Bridge Preservation Partnership Meeting

Northeast Bridge Preservation Partnership Meeting Northeast Bridge Preservation Partnership Meeting Superstructure Preservation Strategies Aetna Viaduct Superstructure Repairs Route I-84 City of Hartford, CT State Project No. 63-648 David A. Cutler, P.E.

More information

4/26/2013. I-435 and Front Street Diverging Diamond Interchange Missouri Department of Transportation. KCITE 2012 Excellence in Transportation Award

4/26/2013. I-435 and Front Street Diverging Diamond Interchange Missouri Department of Transportation. KCITE 2012 Excellence in Transportation Award 4/26/2013 I-435 and Front Street Diverging Diamond Interchange Missouri Department of Transportation KCITE 2012 Excellence in Transportation Award I-435 and Front Street Diverging Diamond Interchange Missouri

More information

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions Scott Eshleman, P.E., S.E, CVS, Stanley Consultants Keith Sargent, P.E., Thomas Engineering Group, LLC February

More information

5.0 PRELIMINARY ENVIRONMENTAL REVIEW

5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.1 INTRODUCTION A preliminary environmental review was performed on the proposed freeway improvements that form Concept C, which encompasses the three freeway corridors

More information

4. FISH PASSAGE CONCEPTS

4. FISH PASSAGE CONCEPTS Feasibility Study for Restoration of Titlow Lagoon Fish Passage South Puget Sound Salmon Enhancement Group 4. FISH PASSAGE CONCEPTS Fish passage could be improved by rehabilitating the existing fish passage,

More information

Asset Management Performance Measures for Privatized Highway Concessions in British Columbia

Asset Management Performance Measures for Privatized Highway Concessions in British Columbia Asset Management Performance Measures for Privatized Highway Concessions in British Columbia Travis Gilbertson Geoplan Opus Consultants Inc. Victoria, British Columbia Canada 1 Outline 1. DBFO Projects

More information

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310 INTERCHANGE MODIFICATION REPORT FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310 PREPARED BY: VIRGINIA DEPARTMENT OF TRANSPORTATION STAUNTON DISTRICT DECEMBER 13, 2006

More information

extent feasible. Per the and low constructability,

extent feasible. Per the and low constructability, RELEVANT PUBLIC PROJECTS AND REFERENCES TranTech is proud of its accomplishments in structural engineering. Our staff members have provided design servicess to numerous public agencies on very successful

More information

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report APPENDIX B Excerpts from the October 2002 Interstate 83 and PA Route 921 The objective for the SR 921 interchange site was to study alternatives for construction of a new interchange. There are no short-term

More information

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening March 5, 2009 Nicholas J. Roper NOVA District Bridge Engineer Robert F. Price Resident Administrator of Loudoun/ Prince William Construction

More information

Alaskan Way Viaduct Independent Technical Review

Alaskan Way Viaduct Independent Technical Review Final Report Alaskan Way Viaduct Independent Technical Review Prepared for Seattle Department of Transportation April 10, 2015 1100 112th Avenue NE Suite 500 Bellevue, WA 98004 Contents Section Page Acronyms

More information

SAN ANTONIO STREET BRIDGE AT COMAL RIVER. Open House

SAN ANTONIO STREET BRIDGE AT COMAL RIVER. Open House SAN ANTONIO STREET BRIDGE AT COMAL RIVER Open House May 1, 2018 SAN ANTONIO STREET BRIDGE AT COMAL RIVER, NEW BRAUNFELS COMAL COUNTY OPEN HOUSE MAY 1, 2018 5:00 P.M 7:00 P.M. New Braunfels Civic/Convention

More information

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV Noise Technical Report 2015 Addendum NOISE TECHNICAL REPORT 2015 Addendum PREPARED FOR: Federal Highway Administration and Georgia Department of Transportation PREPARED BY: Parsons Brinckerhoff Project

More information

Future Eligible Project Cost. Total Federal Funding (including NSFHP) Are matching funds restricted to a specific project component? If so, which one?

Future Eligible Project Cost. Total Federal Funding (including NSFHP) Are matching funds restricted to a specific project component? If so, which one? Project Name Previously Incurred Project Cost Future Eligible Project Cost Total Project Cost NSFHP Request Total Federal Funding (including NSFHP) Are matching funds restricted to a specific project component?

More information

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013 United States Department of Agriculture Natural Resources Conservation Service Denver Federal Center Building 56, Room 2604 P.O. Box 25426 Denver, CO 80225 720-544-2818-OFFICE alton.albin@co.usda.gov Flood

More information

RESOLUTION NO

RESOLUTION NO RESOLUTION NO. 2018-12 RESOLUTION OF THE SOUTHEASTERN WISCONSIN REGIONAL PLANNING COMMISSION AMENDING THE TRANSPORTATION IMPROVEMENT PROGRAM FOR SOUTHEASTERN WISCONSIN: 2017-2020 WHEREAS, the Southeastern

More information

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb

More information

NJTPA Transportation Improvement Program Fiscal Years

NJTPA Transportation Improvement Program Fiscal Years Routes Name: CR 571 Mileposts: 4.85 DBNUM: N1127 County Route 571/County Route 527, Reconstruction, Toms River Township This project is for intersection improvements at CR 571 and CR 527 in Tom s River

More information

4.11 TRAFFIC AND CIRCULATION

4.11 TRAFFIC AND CIRCULATION 4.11 4.11.1 ENVIRONMENTAL SETTING EXISTING TRAFFIC CONDITIONS Hyampom Road is the only all-weather access to the community of Hyampom, thereby making it the only school bus and mail route. It is also a

More information

Design-Build and Design-Bid-Build

Design-Build and Design-Bid-Build Design-Build and Design-Bid-Build Comparison of Overall Cost and Time Question: How does the total cost and time to deliver a $55,000,000 and 814 day design-build project compare to using design-bid-build

More information

Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement

Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina Presented By: Chip Smith, PE Woolpert Kate Labadorf,

More information

I-95 Corridor Study Phase II Highway Element

I-95 Corridor Study Phase II Highway Element I-95 Corridor Study Phase II Highway Element FAMPO Policy Committee July 16, 2018 1 I-95 Phase 2 Study Final Report A final report is being created to document the findings of the I-95 Phase 2 Study and

More information

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199))

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199)) 11060 White Rock Road, Suite 200 Rancho Cordova, CA 95670 Phone: (916) 363-4210 Fax: (916) 363-4230 M e m o r a n d u m To: Reena Gohil, Environmental Planner Date: May 30, 2017 California Department of

More information

3.6 Construction Methods

3.6 Construction Methods Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required

More information

CIP-01: Stream Channel Stabilization, Silver Creek

CIP-01: Stream Channel Stabilization, Silver Creek CIP-01 CIP-01: Stream Channel Stabilization, Silver Creek HIGHEST PRIORITY This project consists of stream channel stabilization to address channel incision and the replacement of two cross-culverts. Preferred

More information

PUBLIC INFORMATION MEETING June 24, 2015

PUBLIC INFORMATION MEETING June 24, 2015 Gallows Road (RTE. 650) over Arlington Boulevard (RTE. 50) Fairfax County Bridge Rehabilitation, Preventive Maintenance and Pier Repairs Phase 1 - Project No. 0650-029-235; UPC 106956, Pier Repair Phase

More information

Ohio Contractor Association Annual Work Forecast Program. John Picuri, District 4 Deputy Director Myron Pakush, District 12 Deputy Director

Ohio Contractor Association Annual Work Forecast Program. John Picuri, District 4 Deputy Director Myron Pakush, District 12 Deputy Director Ohio Contractor Association Annual Work Forecast Program John Picuri, District 4 Deputy Director Myron Pakush, District 12 Deputy Director John R. Kasich, Ohio Governor Jerry Wray, ODOT Director ODOT S

More information

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016 Rehabilitation of West Main Street Culvert and Shirley Street Bridge Town of Ayer November 22, 2016 Agenda Outline Introductions Project Goals and Objectives Existing Conditions Review Design Considerations

More information

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017 VT 14 East Montpelier Bridge Project Informational Meeting February 22, 2017 Welcome & Introductions VTrans Mark Sargent, Project Manager Wayne Symonds, Structures Program Manager Chris Barker, Resident

More information

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company James P. Hyland Page 1 ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING Kansas City Terminal Railway Company James P. Hyland, P.E. Senior Bridge Engineer TranSystems Corporation James P. Hyland Page 2

More information

WELCOME. Public Meeting for I-35 / I-44 Interchange. October 6, 2015

WELCOME. Public Meeting for I-35 / I-44 Interchange. October 6, 2015 WELCOME Public Meeting for I-35 / I-44 Interchange October 6, 2015 TEAM INTRODUCTIONS PURPOSE OF THIS MEETING is to present the alternative alignments for the I-35/I-44 and I-35/NE 63rd Street Interchanges

More information

Elizabeth River Crossings OpCo, LLC Elizabeth River Tunnels Project Monthly Report Owners and Holders Pursuant to Continuing Disclosure Agreement

Elizabeth River Crossings OpCo, LLC Elizabeth River Tunnels Project Monthly Report Owners and Holders Pursuant to Continuing Disclosure Agreement Elizabeth River Crossings OpCo, LLC Elizabeth River Tunnels Project Monthly Report Owners and Holders Pursuant to Continuing Disclosure Agreement November 2015 From: Greg Woodsmall, Chief Executive Officer,

More information