Planning for Biomed Facility Puts Energy Efficiency Under Microscope

Size: px
Start display at page:

Download "Planning for Biomed Facility Puts Energy Efficiency Under Microscope"

Transcription

1 Planning for Biomed Facility Puts Energy Efficiency Under Microscope Chilled beams, runaround-loop ERV system included May 19, 2014 By DAN VASTYAN, Common Ground, Manheim, Pa. HPAC Engineering Constructing Washington State University s biomed building was a challenge, given rigid temperature and humidity set points, 24/7 operation, and high ventilation rates. The first part of a planned research complex, the new Pharmaceutical & Biomedical Sciences Building on Washington State University (WSU) Spokane s Riverpoint Campus features research and teaching laboratories, classrooms, and administrative and faculty offices. Constructing the four-story, 125,000-gross-square-foot facility was challenging, given the rigid temperature and humidity set points, 24/7 operation, and high ventilation rates that were required in a modern and architecturally pleasing building, Ken Billington, construction administrator with Affiliated Engineers Inc. (AEI), who oversaw construction and worked with the contracting team to coordinate and complete installation of the mechanical, electrical, and plumbing systems, said. 1 of 7

2 The Pharmaceutical & Biomedical Sciences Building s north side features a floorto-ceiling glass curtain wall, which presented design challenges related to perimeter conditioning. Spokane s weather conditions, when combined with the sleek building facades, required a good amount of creativity to achieve sustainable operating costs, Billington, who works out of AEI s Seattle office, continued. We feel that the end product resulted in a high-performance, state-of-the-art facility. Rapid Construction 2 of 7

3 Gary Solberg, project supervisor and manager for McClintock and Turk Inc., assembles piping connected to a below-grade sump pump. Work started at the biomed facility in the summer of 2012 and finished in November of 2013, Gary Solberg, project supervisor and manager for Spokane-based mechanical-contracting and design-build specialist McClintock and Turk Inc., said. It was a fast-track project, for sure. To keep pace, Solberg ran two shifts. For the majority of the project, McClintock and Turk kept 15 to 20 employees, including plumbers, pipefitters, welders, and apprentices, on the job. One of our toughest challenges was packing all the mechanical components into limited ceiling space, Solberg said. The labs have high ceilings, further limiting the available space. Yet we needed to install two separate domestic-hot-water systems one for the labs and one for restrooms and complete systems for fire suppression, plumbing, hydronic heating and cooling, acid-waste piping for the labs, and sheet-metal ductwork. Design Challenges 3 of 7

4 Among the design challenges the building presented, two stand out in Billington s mind: Conditioned-air delivery. The floor-to-ceiling glass curtain wall on the building s north side and resulting lack of space to run ductwork made conditioning the perimeter difficult. Radiant panels both floor- and wall-mounted and a radiant heated/chilled slab help to condition perimeter spaces. Air balancing. With the potential for hazardous chemicals and materials in the air, pressure in laboratories needs to remain negative to prevent infiltration. Offset air tracking was incorporated into the building s design, Billington said. This ensures proper pressurization independent of supply/exhaust-air quantities at any given time due to biosafety-cabinet and fume-hood operation in the laboratories. Pressurization remains constant during all operating phases of safety-cabinet and fume-hood operation. This was especially important at the building s lowest level. An anatomy lab and other specialized lab spaces on this level were subject to even more stringent pressurization and air-change rates, Billington said. Equipment Selection During the construction phase, McClintock and Turk worked with manufacturer representative Suntoya Corp., which supplied HydroTherm boilers, Taco pumps, expansion tanks, and accessories, and other key components. There are two mechanical rooms in the building: one in the penthouse dedicated to heating and one in the basement dedicated to cooling. In the penthouse, six 3-million-Btuh condensing boilers are piped in series, assembled in a lead-lagand-rotate configuration. A fin-tube baseboard system provides supplemental heat to office spaces and meeting rooms. In stairwells, wall-mounted radiators are used. Spread across all floors of the building, 305 variable-air-volume boxes supply primary heat to some areas and supplemental heat to others. 4 of 7

5 Radiant ceiling panels and in-floor radiant tubing heat large zones, while the latter also provides cooling. A modulating three-way valve responds to outdoor and indoor conditions for ideal supply-water temperature and draws water from the boilers or chillers, depending on the need. From the basement, three 275-ton Carrier Evergreen centrifugal chillers, with cooling towers on the roof, cool the building via the radiant system, with more than 300 chilled beams and coils serving the primary air-handling systems. The chilled beams, which are a mix of active and passive systems, are located throughout the office and laboratory areas. Radiant ceiling panels are utilized in public areas, including the cascading stairs on the building s north face. At full load, the building requires 18,000 MBH in heating mode and approximately 825 tons of cooling capacity. Chilled-water pumps in the basement mechanical room. 5 of 7

6 Energy Recovery In all, the heating and cooling systems contain approximately 6,000 gal. of water, a large quantity considering the facility s size. Given copious amounts of insulation, that volume means valuable thermal mass, not standing heat loss. It also means a lot of pumping power. The heating and cooling systems use 23 large vertical inline pumps from Taco. Each pump is outfitted with suction diffusers to conserve space in the mechanical rooms. Taco s inline pumps feature a close-coupled design for improved alignment and increased seal life. Flow rates of up to 2,500 gpm and heads of up to 300 ft TDH are available for broad application. As is the case with most buildings of this type, and despite the number of pumps and the large water volume, the amount of energy required by utilizing pumped energy is substantially less than if fans and air-side equipment had been used exclusively to condition the building, Billington said. The building s energy-recovery loop circulates fluid between two air streams and captures heat from the building s exhaust, redirecting this energy to offset the heat required for building ventilation air. This results in a sensible effectiveness of up to 50 percent and equates to significant savings in overall heating cost. Because of the potential for hazardous materials in the laboratories and the physical location of the two air streams being affected, an enthalpy-wheel energy-recovery system was not considered. High air exchange created the need for energy recovery. A runaround-loop system was chosen because it has been proven effective in transferring energy between process loads (exhaust-air heat) and required ventilation air while eliminating the potential for cross-contamination. Dan Vastyan is an account manager for Common Ground [1], a trade-communications firm based in Manheim, Pa. For Design Solutions author guidelines, call Scott Arnold [2], executive editor, at , or write to him at scott.arnold@penton.com [3]. 6 of 7

7 of 7

SHIYUN CHEN ADVISOR: DR. BAHNFLETH. 1 Executive Summary Building Summary 3. 3 Existing Mechanical System. 4

SHIYUN CHEN ADVISOR: DR. BAHNFLETH. 1 Executive Summary Building Summary 3. 3 Existing Mechanical System. 4 Table of Contents 1 Executive Summary... 1 2 Building Summary 3 3 Existing Mechanical System. 4 4 Mechanical Design Objectives..... 4 5 Mechanical System Evaluation. 5 5.1 Air Distribution System Evaluation....

More information

Chilled Beams. The new system of choice?

Chilled Beams. The new system of choice? Chilled Beams The new system of choice? Presented By: Kevin M. Pope P.E. Jason Leffingwell Hammel Green And Abrahamson, Inc. and Ken Bauer, P.E., LEED AP Butters-Fetting Co., Inc. History of Chilled Beams

More information

Georgetown University New Science Center

Georgetown University New Science Center Georgetown University New Science Center Final Thesis Proposal PENN STATE UNIVERSITY Prepared For: Dr. William P. Bahnfleth Department of Architectural Engineering Prepared By: Kevin M Edstrom Mechanical

More information

Thesis Proposal. Clemson University Advanced Material Research Laboratory Anderson, SC. David Anderson Mechanical Option. Photo by Fred Martin

Thesis Proposal. Clemson University Advanced Material Research Laboratory Anderson, SC. David Anderson Mechanical Option. Photo by Fred Martin Thesis Proposal Photo by Fred Martin Clemson University Advanced Material Research Laboratory Anderson, SC David Anderson Mechanical Option Friday, December 15, 2006 Table of Contents 1. Executive Summary

More information

EMD SERONO RESEARCH CENTER EXISTING

EMD SERONO RESEARCH CENTER EXISTING EMD SERONO RESEARCH CENTER EXISTING BILLERICA, MA SHIYUN (SHARON) CHEN MECHANICAL AE SENIOR THESIS Building System Dedicated Outdoor Air System/ Systems Breadth Building Design Team Building: EMD Serono

More information

Grunenwald Science and Technology Building

Grunenwald Science and Technology Building Grunenwald Science and Technology Building Clarion University- Clarion, PA AE 482 Mechanical Project Proposal: Proposal for Alternative Designs Shane Helm The Pennsylvania State University Architectural

More information

Mechanical Systems Project Proposal

Mechanical Systems Project Proposal Mechanical Systems Project Proposal December 15, 2006 Table of Contents 1.0 Executive Summary... 2 2.0 Building Background... 3 3.0 Proposal Objectives... 5 4.0 Initial Considerations... 6 5.0 Proposed

More information

Interdisciplinary Science and Engineering Building

Interdisciplinary Science and Engineering Building 1 1 Senior Thesis Capstone Project Treado Thesis Proposal Interdisciplinary Science and Engineering Building University of Delaware Newark, DE 19716 2 2 Table of Contents Executive Summary 3-4 Building

More information

South Jefferson High School Huyett Road Charles Town, WV 25414

South Jefferson High School Huyett Road Charles Town, WV 25414 Thesis Proposal Mechanical System Redesign Report Charles Town, WV 25414 Prepared for Dr. Jelena Srebric The Pennsylvania State University By Jonathon Gridley Friday, December 15, 2006 1.0 Table of Contents

More information

Depth: Mechanical Redesign

Depth: Mechanical Redesign Depth: Mechanical Redesign Redesign Objectives The most important objective of the mechanical redesign is to provide Greenbriar East with ventilation that meets the requirements of ASHRAE Standard 62-2001.

More information

The Milton S. Hershey Medical Center Academic Support Building. AE Senior Thesis Kari Anne Donovan Mechanical Option

The Milton S. Hershey Medical Center Academic Support Building. AE Senior Thesis Kari Anne Donovan Mechanical Option The Milton S. Hershey Medical Center Academic Support Building AE Senior Thesis Kari Anne Donovan Mechanical Option Presentation Outline Existing Conditions Distributed Chilled Water Feasibility Study

More information

Air-Water Systems. Chilled Ceilings and Beams TROX USA. Principle of Operation. Radiant Effect on Occupants. Early 1980 s. Chilled Ceiling Panels

Air-Water Systems. Chilled Ceilings and Beams TROX USA. Principle of Operation. Radiant Effect on Occupants. Early 1980 s. Chilled Ceiling Panels Air-Water Systems and Beams Early 1980 s 1980 1990 2005 Buildings well insulated for heating Advent of personal computers Need to remove heat from space Limited space available TROX USA 1 2 Principle of

More information

City High Middle School pre-design recommendations. March 29, 2017

City High Middle School pre-design recommendations. March 29, 2017 City High Middle School pre-design recommendations March 29, 2017 City High Middle School table of contents 2 3 4 5 6 7 8 9 10 11 12 13 table of contents project description and purpose existing systems

More information

David H. Koch Institute for Integrative Cancer Research Senior Capstone Mechanical Option. Proposal

David H. Koch Institute for Integrative Cancer Research Senior Capstone Mechanical Option. Proposal 0 David H. Koch Institute for Integrative Cancer Research Senior Capstone Mechanical Option Proposal David H. Koch Institute for Integrative Cancer Research Massachusetts Institute of Technology Cambridge,

More information

Project Proposal Proposal for Investigation of Alternative Systems

Project Proposal Proposal for Investigation of Alternative Systems Project Proposal Proposal for Investigation of Alternative Systems 01.15.2010 Defense Media Activity Building Fort George G. Meade Penn State University Architectural Engineering Faculty Advisor: Dr. Treado

More information

DEA Clandestine Laboratory Training Center

DEA Clandestine Laboratory Training Center DEA Clandestine Laboratory Training Center David M. Potchak Penn State University Architectural Engineering Mechanical Option Background Information Existing Mechanical Systems Redesign Objectives Alternate

More information

Design Standard Sustainability

Design Standard Sustainability Design Standard Sustainability Purpose Educational institutions have the ability to influence the ideals and principles of our future decision makers; as such, East Side Union High School District (ESUHSD)

More information

Technical Report Three Mechanical Systems Existing Conditions Evaluation

Technical Report Three Mechanical Systems Existing Conditions Evaluation 09 10 Technical Report Three Mechanical Systems Existing Conditions Evaluation WESTINGHOUSE ELECTRIC CO. NUCLEAR ENGINEERING HEADQUARTERS CAMPUS Pittsburgh, PA Daniel P. Aughenbaugh Mechanical Dr. Bahnfleth

More information

Mechanical Systems Proposal

Mechanical Systems Proposal Mechanical Systems Proposal Prepared for: Dr. William Bahnfleth, Professor The Pennsylvania State University, Department of Architectural Engineering Prepared by: Chris Nicolais Mechanical Option December

More information

Mechanical Systems Redesign Proposal. Thesis Proposal. Morton Hospital Expansion

Mechanical Systems Redesign Proposal. Thesis Proposal. Morton Hospital Expansion Mechanical Systems Redesign Proposal Thesis Proposal Morton Hospital Expansion Taunton, MA Courtney Millett Mechanical Option Advisor: Dr. Bahnfleth December 12, 2014 Revised: January 16, 2015 Revised:

More information

KEY ELEMENTARY SCHOOL

KEY ELEMENTARY SCHOOL INITIAL YEAR BUILT 1925 BUILDING AREA 52,000 SF CURRENT PROGRAM CAPACITY 320 ENROLLMENT 2008 328 WARD 3 PROPOSED PROGRAM CAPACITY 325 Site Plan KEY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma LEED Green Building Certification The purpose of the LEED Green Building Rating is to provide a national standard that aims to improve environmental, health and economic performance of buildings using

More information

MECHANICAL PROJECT PROPOSAL (Revised)

MECHANICAL PROJECT PROPOSAL (Revised) PSUAE MECHANICAL PROJECT PROPOSAL (Revised) REDESIGN PROJECT Nicholas B Scheib 2011 M e c h a n i c a l O p t i o n - IP Table of Contents The Sunshine Elementary School Executive Summary... 2 Project

More information

Proposal: Mechanical System Redesign

Proposal: Mechanical System Redesign Proposal: Mechanical System Redesign The 959 Eighth Avenue 10019 Faculty Advisor: Dr. James Freihaut December 12, 2005 Table of Contents 1.0 Executive Summary 2.0 3.0 Proposal Obectives 4.0 Preliminary

More information

Element Z General Design Requirements Existing Facilities Information

Element Z General Design Requirements Existing Facilities Information Anderson Central 100B, PART 1 - INTRODUCTION 1.01 OVERVIEW A. This Section provides general information for building systems and components. B. Refer to the Owner s Design Guideline Elements A though G

More information

EnergyPro Building Energy Analysis. Nine-story Office Building

EnergyPro Building Energy Analysis. Nine-story Office Building EnergyPro Building Energy Analysis Nine-story Office Building EnergyPro Building Energy Analysis for an office building Project Scope The purpose of the EnergyPro energy model was to evaluate the energy

More information

Mechanical Project Proposal

Mechanical Project Proposal Mechanical Project Proposal Miller Children s Hospital Prepared for: Dr. James Freihaut Department of Architectural Engineering The Pennsylvania State University Prepared by: Stephen Haines December 18

More information

Technical Assignment 2 Building and Plant Energy Analysis

Technical Assignment 2 Building and Plant Energy Analysis Technical Assignment 2 Building and Plant Energy Analysis Des Places Residence Hall Duquesne University Pittsburgh, PA Peter Edwards Advisor: James Freihaut October 4, 2010 Table of Contents Executive

More information

North Pocono High School

North Pocono High School Building System Integration Energy and Cost Analysis Architectural Engineering Senior Thesis Presentation Pennsylvania State University Presentation Outline Project Outline Existing System Design Conditions

More information

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding

More information

FUNDAMENTALS OF CHILLED BEAMS ANSI/ASHRAE STANDARD , METHODS OF TESTING CHILLED BEAMS

FUNDAMENTALS OF CHILLED BEAMS ANSI/ASHRAE STANDARD , METHODS OF TESTING CHILLED BEAMS FUNDAMENTALS OF CHILLED BEAMS ANSI/ASHRAE STANDARD 200-2015, METHODS OF TESTING CHILLED BEAMS NEMIC 2017 Hello! I am Davor Novosel I am here because I love to share what I know about chilled beams with

More information

Ceiling Radiant Cooling Panels

Ceiling Radiant Cooling Panels Copyright 2006, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc This posting is by permission from ASHE Journal This article may not be copied nor distributed in either paper

More information

LOW CARBON HEATING FOR COMMERCIAL BUILDINGS USING GRID SUPPLIED ELECTRCITY DURING-OFF PEAK PERIODS

LOW CARBON HEATING FOR COMMERCIAL BUILDINGS USING GRID SUPPLIED ELECTRCITY DURING-OFF PEAK PERIODS LOW CARBON HEATING FOR COMMERCIAL BUILDINGS USING GRID SUPPLIED ELECTRCITY DURING-OFF PEAK PERIODS R. Hutcheson, P.Eng. LEED AP, CxA, S. Jorens B.Eng., D. Knapp, PhD., P.Phys., LEED AP Arborus Consulting

More information

AE 481W Thesis Proposal

AE 481W Thesis Proposal AE 481W Thesis Proposal I I Advisor: Dr. Treado UNIVERSITY OF CALIFORNIA SAN DIEGO RADY SCHOOL OF MANAGEMENT LA JOLLA, CA TABLE OF CONTENTS Executive Summary.3 Mechanical System Overview..4 Design Objectives,

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/06/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/06/2013 BUILDING SURVEY DATE 0067 1110 WEST GREEN STREET URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.810 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 18,640,900 OFFICE BUILDING GROSS SQUARE FEET 175,513

More information

Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal

Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal The following documentation provides an example submittal for the LEED-NC v2.1 Energy & Atmosphere Credit 1 (EAc1). This sample EAc1 submittal

More information

Interdisciplinary Science and Engineering Building

Interdisciplinary Science and Engineering Building 1 1 Senior Thesis Capstone Project Treado Thesis Proposal Interdisciplinary Science and Engineering Building University of Delaware Newark, DE 19716 2 2 Table of Contents Executive Summary 3-4 Building

More information

Acknowledgements 4. Executive Summary 5

Acknowledgements 4. Executive Summary 5 Table of Contents Acknowledgements 4 Executive Summary 5 Building Overview.. 6 Building Summary.. 6 Site. 6 Evaluation of Existing Mechanical System. 7 Mechanical System Overview 7 Design Objective 7 Outdoor

More information

percent hours of the year heat rejected to loop percent hour building load on loop, Btuh percent hour building load on loop, Btuh

percent hours of the year heat rejected to loop percent hour building load on loop, Btuh percent hour building load on loop, Btuh HOBOKEN RESIDENTIAL C- Ground Loop Pump Calculations Central Geothermal System building load on loop, Btuh Bin - 5 5 25 35 45 55 hours of the year Count 3 35 48 64 79 89 96 96 3 32 3 6 5 7 274 292 86 46

More information

Mechanical Depth. Redesign and Analysis

Mechanical Depth. Redesign and Analysis Depth Redesign and Analysis 14 Analysis Scope The scope of my mechanical redesign will include the 2 nd and 3 rd floors of the SW hospital wing which includes Semi-Private, Private and Isolations rooms.

More information

EnergyPro Building Energy Analysis. Single-story School Building

EnergyPro Building Energy Analysis. Single-story School Building EnergyPro Building Energy Analysis Single-story School Building EnergyPro Building Energy Analysis for a single-story school bulding Project Scope The purpose of the EnergyPro energy model was to evaluate

More information

Level 1 Modules tdp-101 hvac industry overview tdp-103 concepts of air conditioning tdp-102 abcs of comfort

Level 1 Modules tdp-101 hvac industry overview tdp-103 concepts of air conditioning tdp-102 abcs of comfort TDP-101 HVAC Industry Overview This TDP provides a general overview of the commercial HVAC industry and provides an awareness of the design process and construction. The documents involved in construction,

More information

The Impact of VISIONWALL High Performance Windows on the Northern Telecom Building in Ottawa, Ontario

The Impact of VISIONWALL High Performance Windows on the Northern Telecom Building in Ottawa, Ontario The Impact of VISIONWALL High Performance Windows on the Northern Telecom Building in Ottawa, Ontario Visionwall Technologies Inc. 14904-123 Avenue Edmonton, Alberta, Canada T5V 1B4 Tel: 403 451 4000 Fax:

More information

Ceiling Radiant Cooling Panels

Ceiling Radiant Cooling Panels 2006, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc (wwwashraeorg) Published in ASHE Journal Vol 48, Oct 2006 For personal use only Additional reproduction, distribution,

More information

The Elithis Tower is an experimental and demonstration. Elithis Tower in Dijon, France. nzeb case studies

The Elithis Tower is an experimental and demonstration. Elithis Tower in Dijon, France. nzeb case studies COM Elithis Tower in Dijon, France Elithis Tower, located in Dijon, France, provides strong evidence that net zero energy office buildings are achievable in near future. The building, which was designed

More information

AN INNOVATIVE DEDICATED OUTDOOR AIR APPLICATION FOR A GOVERNMENT OFFICE TOWER. MICHAEL HALLENBECK, PE, CEM Southland Industries

AN INNOVATIVE DEDICATED OUTDOOR AIR APPLICATION FOR A GOVERNMENT OFFICE TOWER. MICHAEL HALLENBECK, PE, CEM Southland Industries AN INNOVATIVE DEDICATED OUTDOOR AIR APPLICATION FOR A GOVERNMENT OFFICE TOWER MICHAEL HALLENBECK, PE, CEM Southland Industries BRAC 133 OVERVIEW PROJECT OVERVIEW FAN POWERED INDUCTION UNIT CENTRAL UTILITY

More information

Coach House: Hunziker Hall:

Coach House: Hunziker Hall: Number: Morristown, NJ From: Sergiu Pelau Sheet: 1 of 5 Date of Visit: 12/7/11 Coach House: 1. Central plant located in Hunziker Wing connecting piping is leaking a. Gas fired plant 10 year old b. Two

More information

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal : REVISION I

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal : REVISION I Broad Institute Expansion: Cambridge, Massachusetts Mechanical Thesis Proposal : REVISION I Table of Contents Executive Summary... 2 Building Overview... 3 Mechanical System Overview... 4 Mechanical System

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 I DATE: May 9-11, 2017 ****************************************************************************** SUBJECT: SDSU Harding Hall Renovation

More information

HVAC SYSTEM DESIGN PROCESS

HVAC SYSTEM DESIGN PROCESS HVAC SYSTEM DESIGN PROCESS Ball State Architecture ENVIRONMENTAL SYSTEMS 2 Summer 2011 Grondzik 1 HVAC System Design Process Establish design intents/criteria (including code/standard compliance) Establish

More information

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal Broad Institute Expansion: Cambridge, Massachusetts Mechanical Thesis Proposal Table of Contents Executive Summary... 2 Building Overview... 3 Mechanical System Overview... 4 Mechanical System Design Objectives...

More information

PARK PLACE CASE STUDY VANCOUVER. Heat reclaim system expected to reduce steam consumption 80%, GHG emissions 68%

PARK PLACE CASE STUDY VANCOUVER. Heat reclaim system expected to reduce steam consumption 80%, GHG emissions 68% Heat reclaim system expected to reduce steam consumption 80%, GHG emissions 68% Address 666 Burrard St, Vancouver Management QuadReal Property Group Type of Building Office Year of Construction 1984 Number

More information

SURNA Grow Facility: Systems Comparison - IEA

SURNA Grow Facility: Systems Comparison - IEA SURNA Grow Facility: Systems Comparison - IEA May 2016 SURNA Grow Facility This analysis provides the projected energy and associated cost comparison between the Surna proposed facility in comparison to

More information

The New Student Housing Building at The Mount St. Mary s s University Emmitsburg,, Maryland

The New Student Housing Building at The Mount St. Mary s s University Emmitsburg,, Maryland The New Student Housing Building at The Mount St. Mary s s University Emmitsburg,, Maryland Erik Shearer Mechanical Presentation Outline Project Background Current Mechanical Systems Mechanical Alternatives

More information

43% reduction in water use below code maximum 100% 100% 14% reduction in lighting power density. 56% of offices have thermal comfort controls 100%

43% reduction in water use below code maximum 100% 100% 14% reduction in lighting power density. 56% of offices have thermal comfort controls 100% Insert school or unit logo Nocera Lab LEED CI v3.0 12 Oxford Street, Cambridge, MA GOLD Project Profile Laboratories are typically regarded as an energy intensive building typology. Many of these buildings

More information

Table of Contents. Page 1

Table of Contents. Page 1 Table of Contents Acknowledgments...2 Executive Summary...4 Project Background...5 Existing Mechanical System...8 Proposed Mechanical Redesign...13 Impact of Proposed Mechanical System on Structure...36

More information

Italcementi Center for Research and Innovation

Italcementi Center for Research and Innovation Italcementi Center for Research and Innovation Bergamo, Italy LEED-NC v2.1 EAc1 A. Project Narrative (Viridian) analyzed the energy use of the proposed Italcementi Center for Research and Innovation located

More information

Demonstration of modeling of radiant cooling system in design builder. Prashant Bhanware & Bharath Reddy

Demonstration of modeling of radiant cooling system in design builder. Prashant Bhanware & Bharath Reddy Demonstration of modeling of radiant cooling system in design builder Prashant Bhanware & Bharath Reddy CONTENTS Introduction to Design Builder Building Energy Simulation Modeling procedure Making a model

More information

Final Thesis Report Mechanical System Alternatives Analysis

Final Thesis Report Mechanical System Alternatives Analysis [Type text] Nassau Community College Life Sciences Building Garden City, NY Final Thesis Report Mechanical System Alternatives Analysis Prepared By: Prepared For: James D. Freihaut, PhD Dustin Eplee Date:

More information

CREATIVE ENERGY NES Building Compatibility Design Guide October 15

CREATIVE ENERGY NES Building Compatibility Design Guide October 15 City Builders Energy Innovators Creative Thinkers CREATIVE ENERGY NES Building Compatibility Design Guide October 15 CREATIVE ENERGY VANCOUVER PLATFORMS INC. Suite 1 720 Beatty Street Vancouver, Canada

More information

University of Minnesota Duluth Civil Engineering Building

University of Minnesota Duluth Civil Engineering Building Energy Data Attachment University of Minnesota Duluth Civil Engineering Building LEED Energy Modeling The energy modeling for LEED NC 2.2 was performed against ASHRAE 9.1-24 Appendix using equest version

More information

2-Pipe fan coil terminal units were selected as the parallel system to handle the remaining sensible cooling load.

2-Pipe fan coil terminal units were selected as the parallel system to handle the remaining sensible cooling load. Redesign Introduction This report is an in depth analysis of the mechanical systems of the Outreach Innovation Building located in University Park, PA and the impact these changes had on other systems

More information

MODULE 5 HVAC FUNDAMENTALS OF MODERN LABORATORY DESIGN

MODULE 5 HVAC FUNDAMENTALS OF MODERN LABORATORY DESIGN MODULE 5 HVAC FUNDAMENTALS OF MODERN LABORATORY DESIGN Module 5 PG1 MODULE 5 GOAL Provide a fundamental understanding of Laboratory Heating, Ventilating and Air Conditioning Concepts and Systems Module

More information

Retail Effects of ANSI/ASHRAE/IES Standard

Retail Effects of ANSI/ASHRAE/IES Standard Retail Effects of ANSI/ASHRAE/IES Standard 90.1-2016 Prepared by Dialectic Inc. INTRODUCTION Background ANSI/ASHRAE/IES 90.1-2016 Energy Standard for Buildings Except Low-Rise Residential Buildings replaces

More information

The Ed Roberts Campus

The Ed Roberts Campus The Ed Roberts Campus Proposal Anderson Clemenceau Mechanical Option Advisor: Donghyun Rim December 12, 2014 2 Contents Executive Summary... 3 Building Overview... 4 Existing Mechanical System... 5 Airside

More information

Oklahoma University Children s Medical Office Building

Oklahoma University Children s Medical Office Building Oklahoma University Children s Medical Office Building Oklahoma City, O.K., BAE Advisor: Laura Miller Presentation Outline VRF System Dedicated Outdoor Air System Evaluation VRF Indoor Units Design Criteria

More information

TDPs provide you with new technical training materials designed to help your contractors, engineers, and designers to effectively design, specify,

TDPs provide you with new technical training materials designed to help your contractors, engineers, and designers to effectively design, specify, TDP Catalog TDPs provide you with new technical training materials designed to help your contractors, engineers, and designers to effectively design, specify, sell, and apply HVAC equipment in commercial

More information

A Paradigm Shift in ERV Technology. Paul Ehrlich, PE President Building Intelligence Group PLLC

A Paradigm Shift in ERV Technology. Paul Ehrlich, PE President Building Intelligence Group PLLC A Paradigm Shift in ERV Technology Paul Ehrlich, PE President Building Intelligence Group PLLC August 9, 2013 Existing Buildings and Energy Existing buildings: Floor space: Floor space per building: Energy

More information

Integration of Mechanical System Redesign. The New Learning Center Lutheran Theological Seminary at Philadelphia

Integration of Mechanical System Redesign. The New Learning Center Lutheran Theological Seminary at Philadelphia Integration of Mechanical System Redesign Geothermal Heat Pump Redesign The New Learning Center Lutheran Theological Seminary at Philadelphia Wesley S. Lawson Architectural Engineering Mechanical Option

More information

Hunter s Point South Intermediate School & High School

Hunter s Point South Intermediate School & High School Hunter s Point South Intermediate School & High School Long Island City, NY M E C H A N I C A L O P T I O N Technical Report Two Building and Plant Energy Analysis Report By: Advisor: Dr. Stephen Treado

More information

WESTINGHOUSE ELECTRIC NUCLEAR

WESTINGHOUSE ELECTRIC NUCLEAR WESTINGHOUSE ELECTRIC NUCLEAR ENGINEERING HEADQUARTERS DANIEL AUGHENBAUGH - MECHANICAL OPTION Daniel Aughenbaugh Mechanical Option PRESENTATION OUTLINE INTRODUCTION EXISTING MECHANICAL SYSTEM MY DESIGN

More information

MOLD & MILDEW. VOLAR Barracks Rehabs Ft. Polk & Ft. Hood

MOLD & MILDEW. VOLAR Barracks Rehabs Ft. Polk & Ft. Hood MOLD & MILDEW CORRECTIVE ACTIONS VOLAR Barracks Rehabs Ft. Polk & Ft. Hood Jack Osborne, P.E. Fort Worth District Corps of Engineers Scope: OVERVIEW Ft. Polk (awarded Jan 09) Remodel 16 VOLAR Style Barracks

More information

Olivet Nazarene University Student Life and Recreation Center Project By Elara Engineering

Olivet Nazarene University Student Life and Recreation Center Project By Elara Engineering Olivet Nazarene University Student Life and Recreation Center Project By Elara Engineering 29 N. Wacker Renovation Project CHAPTER/REGIONAL TECHNOLOGY AWARD - SHORT FORM 1. Category (Check one and indicate

More information

ASHRAE Standard Ventilation Compliance Evaluation Mechanical Technical Report #1. Bronx School for Law, Government, & Justice Bronx, NY

ASHRAE Standard Ventilation Compliance Evaluation Mechanical Technical Report #1. Bronx School for Law, Government, & Justice Bronx, NY ASHRAE Standard 62.1 2004 Ventilation Compliance Evaluation Mechanical Technical Report #1 Bronx, NY Prepared By: Yulien Wong Faculty Advisor: Dr. Jelena Srebric October 4, 2005 TABLE OF CONTENTS 1.0 EXECUTIVE

More information

Part 1 Review Questions on material covered in Midterms I & II

Part 1 Review Questions on material covered in Midterms I & II 1 Arch 463 ECS Fall 2001 Name FINAL 40 Multiple Choice Questions Part 1 Review Questions on material covered in Midterms I & II 1. Passive systems for environmental control A. can enhance human comfort

More information

Appendix E-1f: Small Building Methodology for Pre-SB2030 Projects

Appendix E-1f: Small Building Methodology for Pre-SB2030 Projects Appendix E-1f: Small Building Methodology for Pre-SB2030 Projects Prescriptive Bundle Option Method for Office Buildings less than 30,000 GSF This section describes energy strategy requirements for three

More information

EADQUARTERS. Thesis Revised Proposal. Stephanie Kunkel Mechanical Option

EADQUARTERS. Thesis Revised Proposal. Stephanie Kunkel  Mechanical Option EADQUARTERS 707 N. Calvert St. Mechanical System Renovation Construction Management & Lighting/Electrical Breadths Stephanie Kunkel www.engr.psu.edu/ae/thesis/portfolios/2011/slk5061 Mechanical Option

More information

Achieving Near Net-Zero Energy Usage in Laboratory

Achieving Near Net-Zero Energy Usage in Laboratory Page 1 of 8 Published on www.tradelineinc.com (http://www.tradelineinc.com) Home > Achieving Near Net-Zero Energy Usage in Laboratory Facilities Achieving Near Net-Zero Energy Usage in Laboratory Facilities

More information

ashrae) VENTILATING PRINCIPLES AIR CONDITIONING OF HEATING AND 7th Edition A Textbook with Design Data Based on the 2013 ASHRAE Handbook Fundamentals

ashrae) VENTILATING PRINCIPLES AIR CONDITIONING OF HEATING AND 7th Edition A Textbook with Design Data Based on the 2013 ASHRAE Handbook Fundamentals PRINCIPLES OF HEATING VENTILATING AND AIR CONDITIONING 7th Edition A Textbook with Design Data Based on the 2013 ASHRAE Handbook Fundamentals William J. Coad Harry J. Sauer, Jr. ashrae) Contents Part I

More information

nycaspelegislative@gmail.com newsletter@asseny.org PS62R NYC s First Net Zero Energy School (and one of the first in the World) What is Net Zero? Our Definition : The building will produce (on site) as

More information

Draft Feasibility Study for the Expansion of Southeast Library

Draft Feasibility Study for the Expansion of Southeast Library DC public Library KH KEAST & HOOD METROPOLITAN E N G I N E E R I N G I N C S H A P I RO-O BRIEN Draft Feasibility Study for the Expansion of Southeast Library Draft Submission: November 4, 2016 1 OVERVIEW

More information

CREDIT COMPLIANCE (Please complete the color coded criteria(s) based on the option path selected)

CREDIT COMPLIANCE (Please complete the color coded criteria(s) based on the option path selected) (Responsible Individual) (Company Name) I,, from verify that the information provided below is accurate, to the best of my knowledge. CREDIT COMPLIANCE (Please complete the color coded criteria(s) based

More information

Colorado Mountain College: Sustainable Design Standards

Colorado Mountain College: Sustainable Design Standards Colorado Mountain College: Sustainable Design Standards Objective: Design and build to the highest energy and water standards in order to meet the College s Carbon Neutrality Objective in the most cost-effective

More information

3/6/2017 Past president & currently on the board of directors for the Wisconsin Geothermal Association

3/6/2017 Past president & currently on the board of directors for the Wisconsin Geothermal Association Saving energy and money with Geothermal technology Presented By Mark Flock President Flock s Heating & Air Conditioning WaterFurnace GeoPro Master Dealer Nate Certified Ground Source Loop Installer Member

More information

Applying Geothermal Technology for Large Scale Projects

Applying Geothermal Technology for Large Scale Projects Jeff Urlaub, PE MEP Associates, LLC jeffu@mepassociats.com 715.832.5680 Engineering Future Focused Solutions Applying Geothermal Technology for Large Scale Projects Breakout Session Category (e.g. Residential)

More information

Mechanical Thesis Proposal

Mechanical Thesis Proposal Mechanical Thesis Proposal New Braunfels Regional Rehabilitation Hospital Adam Bernardo Mechanical Option Faculty Advisor: Dr. William Bahnfleth Revised: 2/13/12 New Braunfels, TX ADAM BERNARDO MECHANICAL

More information

Energy Modeling of Dedicated Outdoor Air Systems for a Small Commercial Pilot Project

Energy Modeling of Dedicated Outdoor Air Systems for a Small Commercial Pilot Project Energy Modeling of Dedicated Outdoor Air Systems for a Small Commercial Pilot Project BUILDING ENERGY SIMULATION FORUM, AUGUST 17, 2016 AMY MONTGOMERY, MASc, P.Eng. Overview Pilot project: energy efficient

More information

GARFIELD ELEMENTARY SCHOOL

GARFIELD ELEMENTARY SCHOOL INITIAL YEAR BUILT 1910 BUILDING AREA 58,908 SF CURRENT PROGRAM CAPACITY 446 ENROLLMENT 2008 278 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan GARFIELD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Existing Earth and Ocean Sciences (EOS) Building

Existing Earth and Ocean Sciences (EOS) Building 11 ENERGY SYSTEMS 11.0 ENERGY SYSTEMS The novel approach to capturing and sharing energy with a neighbouring building is an elegant solution to the problem of adding a building to a campus and of how to

More information

Thesis Proposal. Park. Findlay 12/10/2010. Connor Blood

Thesis Proposal. Park. Findlay 12/10/2010. Connor Blood 1 Park Place Corporate Center One Mechanical Senior Thesis Project Thesis Proposal Park Place Corporate Center One Findlay Township,, PA 12/10/2010 Proposal Connor Blood 2 Park Place Corporate Center One

More information

YORK PASSIVE CHILLED BEAMS ENGINEERING GUIDE

YORK PASSIVE CHILLED BEAMS ENGINEERING GUIDE YORK PASSIVE CHILLED BEAMS ENGINEERING GUIDE Contents YORK Passive Chilled Beams 3 CB-PBE-YK / CB-PBR-YK Performance Data 5 CB-PBE-YK Dimensions 7 CB-PBR-YK Dimensions 8 Specifications 9 2 YORK Passive

More information

Redland Tech Center Rockville, MD. Shawn Pepple Construction Management April 14, 2009

Redland Tech Center Rockville, MD. Shawn Pepple Construction Management April 14, 2009 Rockville, MD Redland Tech Center Project Overview Two office buildings with stand alone parking garage Building II: 9 levels; 210,240 SF Building III: 6 levels; 136,430 SF Parking Garage: 6 levels; 310,600

More information

Part 1 Review Questions on material covered in Midterms I & II

Part 1 Review Questions on material covered in Midterms I & II 1 Arch 463 ECS Fall 2016 Name FINAL 40 Multiple Choice Questions Part 1 Review Questions on material covered in Midterms I & II 1. The Climate Consultant is a powerful site analysis tool because A. it

More information

Comparing Economics of Various Methods of Improving Energy Efficiency of Commercial Buildings

Comparing Economics of Various Methods of Improving Energy Efficiency of Commercial Buildings Comparing Economics of Various Methods of Improving Energy Efficiency of Commercial Buildings Marek Czachorski¹, Tim Kingston¹ and Jaroslav Wurm, PhD² ¹Gas Technology Institute, Des Plaines, Illinois,

More information

Reed Berinato Mechanical Option. Building and Plant Energy Analysis Report October 27, Contents

Reed Berinato Mechanical Option. Building and Plant Energy Analysis Report October 27, Contents Contents Executive Summary... 3 LEED Green Building Rating Discussion... 4 ASHRAE Standard 90.1-1999... 5 Introduction to ASHRAE Standard 90.1-1999... 5 Envelope Compliance... 5 Lighting Compliance...

More information

1. How the research adds to the understanding of the area investigated

1. How the research adds to the understanding of the area investigated Final Scientific/Technical Report Project Title: CID #: Recipient: Eagan Civic Arena DE-EE0002807 Cherryl Mesko City of Eagan Minnesota 3830 Pilot Knob Road Eagan, MN 55122 cmesko@cityofeagan.com 651-675-5505

More information

Evaluating Alternative Fume Hood System Technologies Using Advanced Building Simulation

Evaluating Alternative Fume Hood System Technologies Using Advanced Building Simulation Evaluating Alternative Fume Hood System Technologies Using Advanced Building Simulation William J. Kosik, P.E., C.E.M. 1 Karl Aveard, AIA Associate 2 Heather R. Beaudoin, P.E., C.E.M. 3 Erik L. Olsen 3

More information

THESIS PROPOSAL UNIVERSITY RIDGE AT EAST STROUDSBURG UNIVERSITY EAST STROUDSBURG, PA PREPARED FOR: JAMES FREIHAUT, PH.D.

THESIS PROPOSAL UNIVERSITY RIDGE AT EAST STROUDSBURG UNIVERSITY EAST STROUDSBURG, PA PREPARED FOR: JAMES FREIHAUT, PH.D. THESIS PROPOSAL UNIVERSITY RIDGE AT EAST STROUDSBURG UNIVERSITY EAST STROUDSBURG, PA PREPARED FOR: JAMES FREIHAUT, PH.D. BY: MATTHEW CARR MECHANICAL OPTION JANUARY 22, 2007 Table of Contents Executive

More information

ERRATA SHEET FOR ANSI/ASHRAE/IES STANDARD (I-P edition) Energy Standard for Buildings Except Low-Rise Residential Buildings.

ERRATA SHEET FOR ANSI/ASHRAE/IES STANDARD (I-P edition) Energy Standard for Buildings Except Low-Rise Residential Buildings. ERRATA SHEET FOR ANSI/ASHRAE/IES STANDARD 90.1-2010 (I-P edition) Energy Standard for Buildings Except Low-Rise Residential Buildings April 17, 2013 The corrections listed in this errata sheet apply to

More information

Technical Development Program

Technical Development Program TDP Catalog TDPs provide you with new technical training materials designed to help your contractors, engineers, and designers to effectively design, specify, sell, and apply HVAC equipment in commercial

More information