2017 Resurfacing Project Central Business District Informational Meeting June 13, 2017
|
|
- Debra Flowers
- 6 years ago
- Views:
Transcription
1 2017 Resurfacing Project Central Business District Informational Meeting June 13, 2017
2 2017 CBD Improvements Agenda Meeting Agenda Introduction Scope of Improvements Time frames for improvements May vary based on weather NICOR improvements are substantially complete and will not conflict with Village project Traffic Management Schedule Questions & Answers 2
3 2017 CBD Improvements Scope of Improvements 3
4 2017 CBD Improvements Scope of Work/Traffic Management Construction Stage 1: Pavement Milling and Temporary Striping Scheduled for July 5 through July 11 All streets are within the project limits Pavement milling (1-3/4 inches of asphalt surface removed) Night construction anticipated (7pm-6am) Temporary striping (center & parking stripes) Construction Stage 2: Pavement Patching and Brick Paver Cross Walk Construction Scheduled for July 7 through July 26 Streets impacted in Stage 2 Hinsdale Avenue and First Street between Garfield Street and Grant Street One half of East-West streets will be closed during each stage (2A & 2B) Pavement patching areas of structural failure Adjust manholes as necessary Construct the Brick Paver Crosswalks (1/2 half of street) Total of 14 cross walks to be constructed in construction stage (2A & 2B) Stage timeline: estimated 10 working days/stage Total crosswalk timeline (East-West Streets): estimated 20 working days 4
5 2017 CBD Improvements Traffic Management (an example of staging) 5
6 2017 CBD Improvements Scope of Work/Traffic Management Construction Stage 3: Pavement Patching & Brick Paver Cross Walk Construction Scheduled for July 27 through August 15 Streets impacted in Stage 3: Garfield Street, Washington Street, Lincoln Street, and Village Place One half of North-South streets will be closed in each stage (3A & 3B) Pavement patching areas of structural failure Adjust manholes as necessary Construct the brick paver crosswalks (1/2 half of street) Total of 9 cross walks to be constructed in Construction Stage (3A & 3B) Stage timeline: estimated 9 working days/stage Total crosswalk timeline (North-South Streets): estimated 18 working days Construction Stage 3: Village Place Construction Decorative concrete (Brick Paver Pattern) removed and replaced Minor areas of concrete patching and utility rim adjustments Project will be completed in 2 separate stages over a 2-3 week period Pedestrian access will be maintained throughout this portion project Sidewalks at crosswalks will be upgraded to meet the current ADA standards Sidewalks will remain open as much as possible but in any event pedestrian access to/from stores will be maintained 6
7 2017 CBD Improvements Scope of Work/Traffic Management Construction Stage 4: Asphalt Surface and Striping Once all streets have been patched and all crosswalks constructed, all streets will be paved with 2-inches of hot-mix asphalt surface course Stage timeline final paving: estimated 4 working days There may be full street closures during the final paving operation portion Stage timeline for striping (Night Operation 7pm-6am): estimated 2 nights Pedestrian access will be available during the Paving & Striping Stages 7
8 2017 CBD Improvements Traffic Management (Village Place Concept) 8
9 2017 CBD Improvements Schedule Key Project Dates: July 4, 2017 Annual parade July 5, 2017 Earliest start date for CBD resurfacing project August 19, 2017 Estimated completion of CBD resurfacing project August 22, 2017 First day of school for children at Hinsdale Middle School 9
10 Conclusion Questions & Answers Project Information Updates Weekly construction activity notices will be provided to all businesses and residents impacted during the construction project. Updates will also be posted on Village Website: If residents/businesses have questions or comments concerning the 2017 Central Business District Improvements, please submit questions or comments to: Daniel Deeter, PE - Village Engineer Village Contacts George Peluso, Director of Public Services Phone: Phone: hinsdaleoutreach@villageofhinsdale.org hinsdaleoutreach@villageofhinsdale.org Mail Village of Hinsdale 19 E. Chicago Avenue Hinsdale, IL Questions? 10
11 Accelerated MIP and Roadway and Infrastructure Improvements Accelerated Roadway and Infrastructure Plan Accelerated MIP Resurfacing Accelerated MIP Reconstruction Accelerated Roadway and Infrastructure Improvements 11
12 Accelerated MIP and Roadway and Infrastructure Improvements Main Roads To Be Improved Garfield Street York Road to Chicago Avenue (2017) Asphalt resurfacing Chicago Avenue County Line Road to Garfield Street (2018) Proposed heavy duty concrete Hinsdale Avenue Grant Street to Jackson Street (2018/2019) Proposed heavy duty concrete patching Garfield Street Chicago Avenue to 55 th Street (2019) Proposed heavy duty concrete Chicago Avenue Garfield Street to Route 83 (2020) Asphalt resurfacing 12
13 Accelerated Construction MIP Map 13
14 Accelerated MIP and Roadway and Infrastructure Improvements Highlights for miles of asphalt resurfacing, asphalt patching and concrete patching Work is scheduled to begin on June 15, 2017 Contractor is mobilizing on the south side of the Village and will work north Work is scheduled to be completed by late Fall 14
15 2017 Accelerated Construction MIP Plan 15
16 Accelerated MIP and Roadway and Infrastructure Improvements Highlights for miles of roadway reconstruction and resurfacing Other infrastructure improvements 2.6 miles of water main improvements Adjacent drainage and sump pump improvements Planned sewer separation per original MIP Eight Place - Madison Street to East End Elm Street Fourth Street to Sixth Street Hickory Street Bruner Street to Adams Street The Lane Walker Road to Elm Street Eight Street Bruner Street to Bodin Street 16
17 Accelerated MIP and Roadway and Infrastructure Improvements Highlights for miles of roadway reconstruction and resurfacing Other infrastructure improvements 1.37 miles of water main improvements Adjacent drainage and sump discharge improvements Planned sewer separation per original MIP Bruner Street Sixth Street to Eighth Street Bodin Street Seventh Street to Eighth Street Grant Street Eight Street to Ninth Street Fifth Street Garfield Street to Park Street Sixth Street Garfield Street to Oak Street Park Avenue Sixth Street to Seventh Street 17
18 Accelerated MIP and Roadway and Infrastructure Improvements Highlights for 2020 Resurface and water main improvements on Chicago Avenue from Garfield Street to Route 83 Project to be funded through federal Surface Transportation Program funds 18
19 Presentation Maps 19
20 Accelerated MIP and Roadway and Infrastructure Improvements Summary of Improvements by 2020 Approximately 30 miles of roadway improvements Approximately 5 miles of water main improvements Improved street drainage and elimination of sump pump discharges Completion of all sewer separation per NPDES permit with Illinois Environmental Protection Agency 20
21 Accelerated MIP and Roadway and Infrastructure Improvements Communication Construction Activity Notices Direct mail to resident Village website E-news 21
22 Accelerated MIP and Roadway and Infrastructure Improvements Questions? 22
23 Accelerated MIP and Roadway and Infrastructure Improvements Hinsdale Middle School Parking Update 23
24 Southeast Lot Current Conditions North Lot West North Lot East West Lot
25 Southeast Lot Weeks 1 and 2 1. Mobile classroom moved From West lot to North lot West 2. Shuttle Service in Use 3. North lot East and Southeast Lot Used for shuttle parking North Lot West West Lot North Lot East Spaces Available Washington Second to Third 39 West Lot 21 North Lot East 42 Southeast Lot 27 Total 129
26 Southeast Lot Weeks 3 to 9 1. Construction Trailer on Washington From West lot to North lot West 2. North Lot East and Southwest Lot becomes 2 hour parking 3. West Lot Pay box use up to 6 hours North Lot West West Lot North Lot East Spaces Available Washington Second to Third 33 West Lot 66 North Lot East 36 Southeast Lot 0 Total 135
27 Southeast Lot North Lot West North Lot East West Lot Weeks 9 to Construction Completion 1. Long Term Temporary Lot Complete Pay box use up to 6 hours. 2. Washington Street Closed 2 nd to 3 rd St. 3. Construction Trailer Spaces Available Washington Second to Third 0 West Lot 0 North Lot East 0 Southeast Lot 0 Long-Term Temp Lot 129 Total 129
28 Traffic Pattern and Plan Effective 6-19 Mobile Classrooms Shopper Parking Open (one sign) Pay box Shopper Only Parking 6 hours maximum Or Orange Permit 9am to 5pm Except Sundays (2 signs) Two Hour Parking Or Orange Permit Required 9am to 5pm Except Sundays (4 signs)
Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.
1 Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 2 During this public meeting, we will explain the 75 th Street Corridor Improvement
More informationDepartment of Street Services
Department of Street Services FY 07-08 Proposed Budget Briefing to the City Council September 5, 2007 Purpose An overview of the Department of Street Services Scope of operation and maintenance activities
More informationVILLAGE OF MORTON GROVE DEPARTMENT OF PUBLIC WORKS RIGHT-OF-WAY (ROW) PERMIT APPLICATION REQUIREMENTS
VILLAGE OF MORTON GROVE DEPARTMENT OF PUBLIC WORKS RIGHT-OF-WAY (ROW) PERMIT APPLICATION REQUIREMENTS For general information concerning submittal requirements, please refer to Village Code 7-9-4 (c.).
More informationPublic Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California Tel
Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California 93030 Tel 805.385.8280 October 24, 2018 ADDENDUM NO. 2 Vineyard Avenue Street Resurfacing Project PW 16-12 SCHEDULED
More informationCity of Berkley, Michigan Harvard Road Reconstruction & Water Main Replacement Project FREQUENTLY ASKED QUESTIONS (FAQ)
FREQUENTLY ASKED S (FAQ) The purpose of this document is to provide detailed information about the Harvard Road Reconstruction & Water Main Replacement Project. This project will directly affect residents
More informationCapital Improvement Plan (CIP) Adopted Oct. 17, 2016
2017-2021 Capital Improvement Plan (CIP) Adopted Oct. 17, 2016 Fiscal Year 2017 Adopted Capital Improvement Plan Table of Contents Page Description CIP Project Category Start Timeline N/A 1 Introduction
More informationCity of Reno Public Works
City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV 89505 (775) 334-3304 (775) 334-1226 FAX SPECIAL CONDITIONS OF APPROVAL FOR Permit # EAE11-00XXX Applicant: Job Description:
More informationTraffic Management Guide to Concrete Overlay Solutions. Dale S. Harrington P.E. Representing CP Tech Center
Traffic Management Guide to Concrete Overlay Solutions December 5, 2014 ACPA Annual Meeting Dale S. Harrington P.E. Representing CP Tech Center Traffic Management- Concrete Overlays Traffic Management
More informationFROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS DATE: JULY 9, 2007 CMR:251 A:07
TO: HONORABLE CITY COUNCIL FROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS DATE: JULY 9, 2007 CMR:251 A:07 SUBJECT: APPROVAL OF A CONTRACT WITH BOND BLACKTOP, INC., IN THE AMOUNT OF $556,812 FOR PHASE 1 AND
More informationPUBLIC WORKS OPERATIONS GENERAL FUND
PUBLIC WORKS OPERATIONS GENERAL FUND The Operations General Fund budget consists of Operational Maintenance of Village owned Rights-of-Way (ROW) and include such items as maintenance of our streets and
More informationVT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017
VT 14 East Montpelier Bridge Project Informational Meeting February 22, 2017 Welcome & Introductions VTrans Mark Sargent, Project Manager Wayne Symonds, Structures Program Manager Chris Barker, Resident
More informationEvanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201
Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October
More informationNaperville Public Library. Parking Lot Work Naper Blvd. Library & 95 th St. Library
Naperville Public Library Request for Pricing Parking Lot Work Naper Blvd. Library & 95 th St. Library Submission Date/Time: May 31, 2018, at 10:00 a.m. CST Place: Nichols Library-Board Room 200 West Jefferson
More informationReconstruction Project Update
I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial
More informationstudy for 2018 include:
MEMORANDUM TO: Mayor and City Council gk FROM: Shawn Sanders irector of Public Works DATE: March 15, 2018 RE: Feasibility Study for the 2018 Street Improvement Project Project No. 2018-02 INTRODUCTION
More informationCITY OF NEW ORLEANS. Repaving the Gateway to the French Quarter: Implementing the Downtown Infrastructure Improvement Project
CITY OF NEW ORLEANS Repaving the Gateway to the French Quarter: Implementing the Downtown Infrastructure Improvement Project Agenda Background Project Scope 2 Superdome Central Business District French
More informationSection 403. DRAINAGE STRUCTURES
403.01 Section 403. DRAINAGE STRUCTURES 403.01. Description. This work consists of adjusting, constructing, or temporarily lowering drainage structures and cleaning existing drainage structures and leads
More informationHighway 15 Project Hutchinson, MN
Highway 15 Project Hutchinson, MN Adjacent Properties and Businesses Meeting Hutchinson Area Chamber of Commerce 1 Agenda Topic 1) Introduce the project scope 2) Project goals and benefits 3) Project timeline
More information811 Emerson St. - Demolition & Site Prep
811 Emerson St. - Demolition & Site Prep 811 Emerson St. Evanston, IL 60201 CA Focus Evanston Property Owner, LLC General Contractor Owner Architect Construction Management Plan Phase I January 24t h,
More informationASPK G1801. The following is a status of ongoing road work in the City of Asbury Park. Items in bold indicate the most recent updates.
MEMORANDUM TO: CC: Michael N. Capabianco, Asbury Park City Manager Mayor John Moor and City Council Members Cindy Dye, City Clerk William McClave, Superintendent of Public Works Frederick Reffetto, Esq.,
More informationLife Cycle Cost Analysis
Life Cycle Cost Analysis Washington Street Widening 144 th Avenue to 148 th Avenue City of Thornton Deborah Turner, PE Overview Project Location What is Life Cycle Cost Analysis? Project Background 7 Steps
More informationOverview. Preventive Maintenance Concepts. What are thin and ultra thin mixes. Experience in Michigan with ultra thin
Overview Preventive Maintenance Concepts What are thin and ultra thin mixes Experience in Michigan with ultra thin Case Study- Washington County Thin mix overlays Preventive Maintenance The planned strategy
More informationNOTE: 1) PRIOR TO BEGINNING WORK TRANSFER RIM ELEV. FROM MH K1 TO A TEMPORARY BENCH MARK FOR USE AS CONTROL DURING CONSTRUCTION. 2) CONTRACTOR TO INST
NOTE: 1) PRIOR TO BEGINNING WORK TRANSFER RIM ELEV. FROM MH K1 TO A TEMPORARY BENCH MARK FOR USE AS CONTROL DURING CONSTRUCTION. 2) CONTRACTOR TO INSTALL MANHOLE LIDS FLUSH WITH EXISTING GROUND SURFACE.
More informationPlease ensure receipt of this Addendum is acknowledged on page 1 of the Form of Tender.
No. 1 Project: 47th Ave Road Reconstruction Owner: District of Chetwynd Date: March 5, 2019 Ref. No.: 1320.0095.01 This Addendum is issued prior to Tender Closing Date, in accordance with the Tender Documents
More informationCapital District Transportation Committee November 6, Unit Costs for Non-State Highway Reconstructions with Federal Funds
Capital District Transportation Committee November 6, 2018 Unit Costs for Non-State Highway Reconstructions with Federal Funds CDTC s unit costs for non-state reconstruction projects were last updated
More informationProject Type: Drainage and Storm Systems
580 Dakin Avenue Box Culvert & Utility Improvements Project $944,952 Improvements to approx. 3,000 lf of existing 4'x5' concrete box culvert; clean interior, patch surface, fill joints/cracks; install
More informationSUPPLEMENTAL ECMS ADVANCED INFORMATION JULY 14, 2016 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
Updated June 27, 2016 BEAVER COUNTY SR 7446(LBB) #92912 PROPOSAL:$54.72 PLANS:$42.46 12X18:$52.11 24X36:$752.70 EXSTRUCT:$48.62 12X18:$59.67 24X36:$861.90 The description and location of the project is
More informationTOWNSHIP OF HOWELL TOWNSHIP OF HOWELL ENGINEERING PROJECTS STATUS REPORT OCTOBER 29, Resurfacing of Aldrich Road West Contract # 11-06
TOWNSHIP OF HOWELL DEPARTMENT OF COMMUNITY DEVELOPMENT & LAND USE 4567 Route 9 North, 2 nd Floor Phone: (732) 938-4500 x2300 Post Office Box 580 Fax: (732) 414-3243 Howell, NJ 07731-0580 Web: www.twp.howell.nj.us
More informationPublic Works Projects in 2016
Public Works Projects in 2016 1. River Road: Replace deteriorated/failed culvert with Army Corp of Engineers (ACOE) stream smart sized culvert per permit. 2. Union Street: Replace old sidewalk from Lincoln
More informationCITY OF ALBANY Public Works Department ADDENDUM #1 ST , MAIN STREET REHABILITATION
CITY OF ALBANY Public Works Department ADDENDUM #1 ST-13-04-2014, MAIN STREET REHABILITATION In order to clarify the intent of the Specifications and Drawings, the following provisions are provided and
More informationTHE ANTICIPATED SEQUENCE OF EVENTS ARE AS FOLLOWS, BUT THE CONTRACTOR IS RESPONSIBLE FOR ALL MEANS AND METHODS
GENERAL PLAN NOTES PERMANENT SIGNS PROJECT SCOPE THIS PROJECT INCLUDES REMOVAL OF PORTIONS OF CONCRETE CURB & GUTTER AND HMA SURFACE; INSTALLATION OF SANITARY AND STORM SEWER AND UNDERDRAIN; EXCAVATION
More informationDriveways and Other Concrete Slabs
Driveways and Other Concrete Slabs V I L L A G E O F H A N O V E R P A R K F I R E D E PA R T M E N T I certify that I have received a copy of these regulations and will comply with the regulations contained
More informationRequest for Proposal Design Engineering Services City of Glendale 2019 Road Projects August 2018
Request for Proposal Design Engineering Services City of Glendale 2019 Road Projects August 2018 The City of Glendale, Wisconsin is requesting engineering proposals from qualified consultants for the design
More informationSPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc.
2004 Specifications CSJ 0299-04-049, Etc. SPECIAL PROVISION 000---979 Detours, Barricades, Warning Signs, Sequence of Work, etc. 1. Description of Project. A. General. This project provides for the construction
More information2018 Utility & Street Reconstruction
2018 Utility & Street Reconstruction Public Hearing On Proposed Special Assessments/Hookup Fees for Installation and Construction of Public Improvements Introduction of the Village technical staff Laura
More informationCity of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House. March 27, 2018
City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House March 27, 2018 Agenda 1. Construction Team 2. Anticipated Construction Staging 3. Anticipated Construction Schedule
More informationCITY OF LA QUINTA GENERAL NOTES GENERAL NOTES
CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES 1. ALL WORK SHALL BE DONE IN ACCORDANCE WITH THE LATEST EDITION OF THE STANDARD PLANS OF THE CITY OF LA QUINTA, THE LATEST EDITION OF THE STANDARD SPECIFICATIONS
More informationMISCELLANEOUS PAVING PROJECTS & SIGNAL INSTALLATION
TAMPA-HILLSBOROUGH COUNTY EXPRESSWAY AUTHORITY LETTER OF CLARIFICATION NO. 1 REQUESTS FOR PROPOSALS FOR MISCELLANEOUS PAVING PROJECTS & SIGNAL INSTALLATION RFQ No. O-01616 THEA Page 1 of 6 LETTER OF CLARIFICATON
More informationASSOCIATED PENNSYLVANIA CONSTRUCTORS SUPPLEMENTAL ECMS ADVANCED INFORMATION LETTING MAY 24, 2018 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
ASSOCIATED PENNSYLVANIA CONSTRUCTORS Updated May 4, 2018 FULTON COUNTY SR 0000(FMC) #109343 PROPOSAL:$21.36 PLANS:$9.02 12X18:$11.07 24X36:$159.90 X-SEC:$7.48 12X18:$9.18 24X36:$132.60 This project involves
More informationEngineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida
Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida November 7, 2014 SUBMITTED BY: Dewberry Bowyer-Singleton 520 South
More informationTOWNSHIP OF HOWELL TOWNSHIP OF HOWELL ENGINEERING PROJECTS STATUS REPORT AUGUST Resurfacing of Aldrich Road West Contract # 11-06
TOWNSHIP OF HOWELL DEPARTMENT OF COMMUNITY DEVELOPMENT & LAND USE DIVISION OF ENGINEERING 251 Preventorium Road Phone: (732) 938-4500 x2300 Post Office Box 580 Fax: (732) 919-1080 Howell, NJ 07731-0580
More informationFY 2019 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects
Baltic Avenue, Maine to Mississippi Avenues Project ID Numbers: S1702 / 173620 This project will mill and repave the roadway, upgrade ADA ramps, and improve drainage, thermoplastic stripping, manholes,
More informationDOCUMENTATION WORKBOOK FY 2014
DOCUMENTATION WORKBOOK SPECIFIC TASK TRAINING PROGRAM Conducted by the ILLINOIS CENTER FOR TRANSPORTATION (ICT) AND IDOT BUREAU OF CONSTRUCTION FY 2014 WORKBOOK TABLE OF CONTENTS Workbook Page 1... Maximum
More informationSECTION B1 BITUMINOUS CONCRETE PAVING GENERAL
SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL This section covers the restoration of roadways and sidewalks, in whole or in part, with bituminous concrete paving. WITHIN 4 DAYS OF BACKFILLING IN AREAS
More informationCurb and Gutter Replacement Project Phase I
Phase I Prepared for: Prepared by: Cheyenne Downtown Development Authority / Main Street 1601 Capitol Avenue Cheyenne, WY 82001 307 433 9730 BenchMark Engineers, PC 1920 Thomes Avenue, Suite 620 Cheyenne,
More informationTangerine Road Dove Mountain Boulevard to La Cañada Drive
Tangerine Road Dove Mountain Boulevard to La Cañada Drive PUBLIC MEETING The Highlands at Dove Mountain November 19, 2015 PRESENTATION OUTLINE 1. Tangerine Road Corridor in Review Project Need Project
More informationPUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE
PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE GENERAL Final restoration of areas within the public right-of-way associated with Street Excavation Permits shall be completed as determined
More informationADDENDUM. DATE: 10/12/15 BROADWAY CROSSWALKS IMPROVEMENT PROJECT CONTRACT No: BID DATE: 10/27/15 ADDENDUM No: 1
CITY OF PLACERVILLE, CALIFORNIA DEVELOPMENT SERVICES DEPARTMENT- ENGINEERING DIVISION ADDENDUM DATE: 10/12/15 PROJECT: BROADWAY CROSSWALKS IMPROVEMENT PROJECT CONTRACT No: 41506 BID DATE: 10/27/15 ADDENDUM
More informationSection 7 Roadway GENERAL REQUIREMENTS I. TYPICAL SECTION...7-1
Section 7 Roadway GENERAL REQUIREMENTS...7-1 I. TYPICAL SECTION...7-1 7.1 LANE WIDTHS...7-1 7.2 SHOULDER WIDTHS...7-1 7.3 CROSS SLOPE...7-2 7.4 CURB AND UNDERDRAINS...7-2 7.5 SIDEWALKS AND DRIVEWAYS...7-2
More informationSECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS
SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01
More informationPreventive Maintenance Project & Treatment Selection
Preventive Maintenance Project & Treatment Selection 19 th Annual TERRA Pavement Conference February 12, 2015, St. Paul, MN Mark Watson, MnDOT Maintenance Outline Introduction Network Level Project Level
More informationPerimeter Site Improvements
Perimeter Site Improvements Phase 1-5 Architect: W+W Architects and Planners Anticipated Milestone Activities: Phase 1, 2 & 3 Construction Manager: Bernards 08.08.13 Directional Signage Contractor: Woodcliff
More informationARLINGTON COUNTY, VIRGINIA
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of April 25, 2009 DATE: April 13, 2009 SUBJECT: SP #401 Site Plan amendment to revise Conditions #6, 19, 21, 36, and 45 and other modifications
More informationRehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016
Rehabilitation of West Main Street Culvert and Shirley Street Bridge Town of Ayer November 22, 2016 Agenda Outline Introductions Project Goals and Objectives Existing Conditions Review Design Considerations
More informationDrainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.
403.01 Section 403. DRAINAGE STRUCTURES 403.01 Description. Adjust, construct, or temporarily lower drainage structures. Clean existing drainage structures and leads as directed by the Engineer. Drainage
More informationFebruary 27th, 2018 City of Mayville
February 27th, 2018 City of Mayville Project Location and Schedule Construction work Detour Route Business Access During Construction Temporary Business Signs What WisDOT Can Do During Construction What
More informationImplementing a Pavement Management System PASER Based City of Omaha, NE
Implementing a Pavement Management System PASER Based City of Omaha, NE Introductions JESS HASTINGS, PE Project Manager 10 Years of Experience TIM O BRYAN, PE Senior Project Manager 30 Years of Experience
More informationTo: Plan Holder Project: O Neill Ranch Well and Treatment Plant Project
5180 SOQUEL DR. SOQUEL, CA 95073 PO Box 1550 CAPITOLA, CA 95010 TEL 831-475-8500 FAX 831-475-4291 BOARD OF DIRECTORS To: Plan Holder Project: O Neill Ranch Well and Treatment Plant Project Dr. THOMAS LAHUE
More informationResidential Street Rebuild Program (RSRP) Test Project Updates Rogerson Drive & Ralston Avenue. Council Presentation January 23, 2018
Residential Street Rebuild Program (RSRP) Test Project Updates Rogerson Drive & Ralston Avenue Council Presentation January 23, 2018 1 RSRP Test Projects PURPOSE Obtain up-to-date pricing Better define
More informationSECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS
SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS Section Page 26-1 GENERAL... 26.1 26-2 PAVEMENT KEYCUTTING... 26.1 26-3 PAVEMENT PLANING... 26.2 26-4 PLANED PAVEMENT CONFORMS... 26.3
More informationTH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP &
TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP 4910-29 & 0504-14 Contract No. 1002252 Project Overview is in need of professional and technical assistance to provide detail design for State
More informationRE: Jackson Row - truck route
Will Rasbach From: Sent: To: Cc: Subject: Mayor Pat Patterson Tuesday, January 13, 2015 3:46 PM Will Rasbach; Bart Robinson; Randy Barber (rbarber@oxfordms.net); jowens@oxfordpolice.net
More informationDistrict 2 System Preservation Projects for FY 17 and FY 18
District 2 System Preservation Projects for FY 17 and FY 18 Gregory B. Holsey - District Engineer Thomas S. Revelle - Assistant District Engineer Project Development Bret Hadzimichalis Assistant District
More informationA City Project Review of Eagles Edge subdivision water system and drainage improvements.
DATE: November 24, 2014 TO: FROM: Planning Commission Jonathan Lange, Planner Community Development Department FILE NO.: CSP2014 0021 PROPOSAL: A City Project Review of Eagles Edge subdivision water system
More informationWESTERN ENGINEERING CONSULTANTS, Inc LLC
WESTERN ENGINEERING CONSULTANTS, Inc LLC 127 S. Denver Avenue, Ft. Lupton CO 80621 2501 Mill St. Brush, CO 80723 Ph. 303-913-7341, Fax 720-294-1330 Email: firstname.lastname@westerneci.com August 24, 2017
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)
ADA South, Contract 1 w/o ROW DBNUM: 15420 / UPC: 154200 This contract will bring projects into compliance with current ADA design requirements that could not be completed within original design or construction
More informationTransportation Management Plan
Transportation Management Plan I 80 PE County, MP 51.38 to MP 62.49 One Inch Mill and Two Inch Fill With Open Grade July 2016 Prepared by Lisa Ouellette Nevada Department of Transportation Executive Summary
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)
FY 2018-2027 WIDE TRANSPORTATION IMPROVEMENT PROGRAM ADA Central, Contract 3 DBNUM: 15419 / UPC: 154190 This contract will bring projects into compliance with current ADA design requirements that could
More informationCHAPTER 20 PUBLIC IMPROVEMENTS OPINION OF COSTS TABLE OF CONTENTS
CHAPTER 20 PUBLIC IMPROVEMENTS OPINION OF COSTS TABLE OF CONTENTS Section Title Page 20.1 General... 20-1 20.2 Units and Costs... 20-1 20.2.1 Erosion Control...20-1 20.2.2 Street Improvements...20-1 20.2.3
More informationPinellas County. Staff Report. Subject: Unincorporated Area (Municipal Services Taxing Unit) Paving Program Report.
Pinellas County 315 Court Street, 5th Floor Assembly Room Clearwater, Florida 33756 Staff Report File #: 15-804, Version: 1 Agenda Date: 11/24/2015 Subject: Unincorporated Area (Municipal Services Taxing
More informationConstruction Coordination & Management Planning MassDOT-Highway/MBTA. 495/MetroWest Partnership Briefing July 11, 2018
Construction Coordination & Management Planning MassDOT-Highway/MBTA 495/MetroWest Partnership Briefing July 11, 2018 Overview The Construction Coordination and Management Planning exercise was a 100-day
More informationSandstone Curb Replacement Standards
Sandstone Curb Replacement Standards Division of Infrastructure Management SCOPE OF CURB REPLACEMENT (Funding Dependent) Sandstone Curb Section I - Purpose: Sandstone curb may be replaced only if existing
More informationJobs & Transportation Ramping it Up Roadway and Traffic Dan Groh, P.E.
Jobs & Transportation Ramping it Up Roadway and Traffic Dan Groh, P.E. Ohio DOT Work Zone Process Review Ohio DOT Work Zone Process Review This review was conducted by the Ohio Department of Transportation
More informationCITY OF SAFETY HARBOR ENGINEERING
CITY OF SAFETY HARBOR ENGINEERING The Engineering Department provides the city with technical services including design of construction and maintenance projects, review of development plans, field surveys,
More informationIt is the CONTRACTORS RESPONSIBILITY to use OSHA approved shoring
PERMIT# EXCAVATION/RIGHT OF WAY PERMIT ATE: NOTE: No permit shall be issued \vithout CURRENT Montana Contractors License, Insurance and Bonding on file with the Public Works epartment. It is the CONTRACTORS
More informationConstruction Notice: Infrastructure Renewal on York and Talbot Streets
Construction Notice: Infrastructure Renewal on York and Talbot Streets Date: March 22, 2019 To: Business owner, resident and/or property owner Project Details: The City of London in partnership with J-AAR
More informationPublic Works Department Five Year Capital Improvement Plan FY PROPOSED
Public Works Department Five Year Capital Improvement Plan FY 2019-2023 PROPOSED Capital Improvement Plan Summary STREET DIVISION PROJECTS 141 Asphalt Sidewalk Replacement Program Funding Source Adopted
More informationSPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013
SPECIAL PROVISIONS - SP2014 BOOK Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2014-119 (PLANT MIXED ASPHALT PAVEMENT) or SP2014-121 (PLANT MIXED ASPHALT PAVEMENT FOR
More informationCurrent Construction Projects in Progress. Thru January 31, 2016
Current Construction Projects in Progress Thru January 31, 2016 Orange Ave Pump Station Improvements Before After Project consist of the removal of the existing pumps, housing and piping. Remove and replace
More informationINFRASTRUCTURE FINANCING PLAN FOR THE WOODGLEN SPECIFIC PLAN
FINAL REPORT INFRASTRUCTURE FINANCING PLAN FOR THE WOODGLEN SPECIFIC PLAN Prepared for: City of Modesto Prepared by: Willdan Financial Services Approved by Modesto City Council on July 9, 2013 Resolution
More informationEXIST PIPE 12 FT LANDSCAPING PROPOSED PLAN LEFT EXIST. R/W REPLACE INLET TOP EXIST PIPE
EDGE OF PAVEMENT EXIST SIDEWALK PROPOSED SIDEWALK PROPOSED SIDEWALK EXIST PIPE DBI SD 12 FT 12 FT LANDSCAPING LANDSCAPING EXIST DITCH TO BE REMOVED EXISTING PLAN (RIGHT SIDE SHOWN, LEFT SIDE SIMILAR) PROPOSED
More informationAGENDA ITEM NO. June 6, 2017
DocuSign Envelope ID: 7CA39164-0C90-42A5-B40D-ED361AA88939 AGENDA ITEM NO. June 6, 2017 May 23, 2017 Honorable Board of Supervisors County of Alameda 1221 Oak Street, Suite 536 Oakland, CA 94612-4305 Dear
More informationSUPPLEMENTAL ECMS ADVANCED INFORMATION AUGUST 10, 2017 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
Updated July 21, 2017 ALLEGHENY COUNTY SR 0000 #109397 PROPOSAL:$28.56 The description and location of the project is as follows: This work is the 3-year term maintenance if intelligent transportation
More informationOctober 17, Albany MS Logistics Plan. Overview:
October 17, 2017 Albany MS Logistics Plan Overview: The project consists of the development of a former school site which still contains fences, aggregate base, and asphalt surfaces into the new Albany
More informationCOMMUNITY PLAZA WAY ASPHALT PAVEMENT OVERLAY ADDENDUM NO.1 UPPER SKAGIT INDIAN TRIBE PAGE 1
UPPER SKAGIT INDIAN TRIBE COMMUNITY PLAZA WAY ASPHALT PAVEMENT OVERLAY ADDENDUM NO. 1 (7 pages total) Issue Date: May 11, 2016 General: Recitations of each and every section of the bid documents impacted
More informationThe following is a status of ongoing road work in the City of Asbury Park. Items in bold indicate the most recent updates.
MEMORANDUM TO: CC: Michael N. Capabianco, Asbury Park City Manager Mayor John Moor and City Council Members Cindy Dye, City Clerk William McClave, Superintendent of Public Works Frederick Reffetto, Esq.,
More informationSpecial Provisions for Pavement Open Cuts
1. All patches are to be replaced in accordance with the following requirements and as shown in Figure 1. 2. All Excavations or Open Cuts shall comply with OSHA Technical Manual, Chapter 2, Title Excavation:
More informationBerkshire Region TIP Project Data Form
BASIC INFORMATION: 1. TIP ID #: 2. MUNICIPALITY: 3. ROUTE# AND/OR NAME: Berkshire Region TIP Project Data Form 4. PROJECT TYPE (CHECK BEST DEFINITION OF PROJECT): Intersection Improvement Road Resurfacing
More informationHosted by: M Squared Engineering on behalf of the Illinois Department of Transportation Thursday, February 9, 2012 Eiger Lab, Rockford, IL
Hosted by: M Squared Engineering on behalf of the Illinois Department of Transportation Thursday, February 9, 2012 Eiger Lab, Rockford, IL TECHNICAL SUPPORTIVE SERVICES IN IDOT DISTRICTS 2 & 3 FOR CERTIFIED
More informationASSOCIATED PENNSYLVANIA CONSTRUCTORS SUPPLEMENTAL ECMS ADVANCED INFORMATION LETTING MARCH 1, 2018 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
As of February14, 2018 SNYDER COUNTY SR 2007(012) #93607 PROPOSAL:$16.56 PLANS:$4.40 12X18:$5.40 24X36:$78.00 The description and location of the project are as follows: The work is the furnishing and
More informationCITY OF FORT WAYNE Public Works - Right of Way Department. Permit Application. Information and Guidelines
CITY OF FORT WAYNE Public Works - Right of Way Department Permit Application Information and Guidelines http://cityoffortwayne.org/ 1 A non-refundable fee application to cover administration costs for
More informationAsphalt Parking Lots Restoration and Maintenance Retail Shopping Centers (See: 2009 Parking Lot Maintenance and Repair)
Inland Commercial Property Management, Inc. 2901 Butterfield Road Oak Brook, IL 60523 Phone: 877.206.5656 Fax: 630.218.5270 Request for Proposal Date: March 12, 2009 Submit to: Dale Rammien E-mail: drammien@inlandrealestate.com
More informationAPPENDIX E: Capital Programs and Descriptions
APPENDIX E: Capital s and Descriptions Number Name Description 1007 Debt Service -General Administers the servicing of Pinellas County public debt. 1008 Reserves Oversees the management and allocation
More informationPRESENTATION TO MWRD ADVISORY TECHNICAL PANEL
VILLAGE OF SCHAUMBURG FOOTING DRAIN DISCONNECTION COST-SHARE PROGRAM PRESENTATION TO MWRD ADVISORY TECHNICAL PANEL MARCH 21, 2012 Village of Schaumburg, IL SCHAUMBURG, ILLINOIS Located 26 miles northwest
More information2311 Egg Harbor Road Susan Shin-Angulo Lindenwold, NJ Freeholder Liaison Phone Fax
Jackson Rd (CR 534) Reconstruction Project Between NJSH RT #73 (MP 12.67) To Atco Ave. (MP 14.92) Townships of Berlin & Waterford County of Camden, New Jersey Bi-Weekly Progress Report Monday 4/23/18 thru
More informationADDENDUM NO. 1. ISSUED: March 23, 2018 PROJECT: Aurora, Indiana. BID DATE: March 27, 2018
ADDENDUM NO. 1 ISSUED: March 23, 2018 PROJECT: 2 nd Street CCMG Project BID DATE: March 27, 2018 The following addenda items modify, change, delete from or add to the requirements of the Contract Documents
More informationTransportation and Utilities
4 Section 4 Transportation and Utilities 4.0 Introduction Transportation and utility systems are essential to accommodate and support development proposed in the Future Land Use Map. The following pages
More informationPalm Beach County Engineering Overview & Implementation Plan for the One Penny Sales Surtax
Palm Beach County Engineering Overview & Implementation Plan for the One Penny Sales Surtax Engineering Sales Tax Projects Bridges $ 43.4 m (27) Roads (Resurfacing) $ 77.6 m (121) Roads (Restriping) $
More informationWashington County Landfill Reconstruction Project: Progress Updates
Home Site Index Glossary What's New Ask MPCA Visitor Center MPCA Home > Clean Up > Perfluorochemicals > Perfluorochemical (PFC) Waste Sites > Washington County Site Progress Updates Washington County Landfill
More informationCity of Fontana Department of Engineering 8353 Sierra Ave Fontana, CA Phone (909) Fax (909)
City of Fontana Department of Engineering 8353 Sierra Ave Fontana, CA 92377 Engineering@Fontana.org Phone (909) 350-7610 Fax (909) 350-7676 PERMIT NO. Excavation and Traffic Control Application Company
More information