1 Exposition Light Rail Transit Project Expo Project Briefing Phase 1 and 2 For IRWA October 26, 2010
2 Phase 1 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor 12 Stations, 2 Shared with Blue Line 1,500 Spaces at 3 Park and Ride Lots Estimated Daily Riders in 2020: 27,000 Estimated Travel Time: 30 minutes Estimated Cost: $899 million Construction Completion: 75% Partial Opening: 2011 Culver City Opening: 2012
3 Phase 1 Alignment Map
4 Typical At-Grade Station
5 Phase 1 Downtown Corridor Update Construction Activities Installation of street lighting and traffic signals along the alignment from Washington Blvd to Vermont Ave Blue Line Tie-In coordination Installation of track (rail) and power systems (OCS and TPSS) along the ROW Installation of Blue Line Tie-In at Flower Street/Washington Boulevard Street restoration and intersection reconstruction Installation of Bollard foundations at Trousdale Parkway
6 Phase 1 Mid-Corridor Update Construction Activities Utility improvements and sewer realignments from Vermont Ave to La Brea Ave Street reconstruction work from Vermont Ave to Arlington Avenue Finish work at the Western and Crenshaw stations, including placement of station furnishings Reconstructed Intersection at Raymond Avenue/Exposition Boulevard Installation of track (rail) and power systems (OCS and TPSS) along the ROW Installation of fencing along the ROW Installation of ROW fencing near Arlington Avenue
7 Phase 1 Construction Activities West End Update Construction of aerial stations at La Brea Ave and La Cienega Blvd Construction of La Cienega parking structure Construction of bridge over Ballona Creek Utility improvements between National Bridge and Venice/Robertson Installation of sound wall posts and panels Construction of falsework and pouring of concrete for Venice/Robertson aerial structure Test Pile Drilling at La Cienega Parking Structure Installation of falsework for the Venice/Robertson aerial structure
8 Phase 1 Crenshaw Station
9 Phase 2 Project Description Phase 2 from Culver City to Santa Monica: 6.6 mile Corridor Expo Board certified FEIR on Feb 4, new stations, some with Parking Estimated Travel Time from Downtown LA to Santa Monica: 46 minutes Estimated Daily Riders in 2030 from Downtown LA to Santa Monica: 64,000 Project Completion: 2015 Estimated cost: $1.5 billion
10 Phase 2 Phase 2 Alignment Map
11 Environmental Process NOI/NOP SCOPING SCREENING DEIR Notice of Intent/ Notice of Preparation Public input on alternatives to be considered Select alternatives that will most likely meet the Purpose and Need Draft Environmental Impact Report AGENCY APPROVAL FEIR Expo Board will certify the FEIR Final Environmental Impact Report
12 Expo/Overland Crossing
13 Phase 2 Bundy Station
14 Phase 2 Colorado Avenue
15 Phase 2 Phase 2 Update Preliminary Engineering On February 4, 2010, the Expo Board certified the FEIR under the California Environmental Quality Act (CEQA) and approved the Recommended Preferred Alternative Exposition Right-of-Way and Colorado Avenue In May 2010, Expo awarded contracts to two competing design-build firms for Preliminary Engineering (PE) work. Skanska Rados, Joint Venture URS Shimmick, Joint Venture During PE, Expo has continued to work with both cities, and various agencies and stakeholders to further refine project elements and discuss design options. In February 2011, Expo will select one of these PE firms as the design-build contractor to complete the final design work and construct the project, which is scheduled to be completed in 2015.
16 Phase 2 Phase 2 Update Refinement of Project Elements Identification of potential utility conflicts and proposed mitigations Verification of right-of-way acquisitions Soil investigations for aerial structure foundations Limits of work for street reconstruction Identification of risk factors and ways to mitigate Typical truck-mounted drill rig for soil sampling
17 Phase 2 Projected Schedule Expo Phase 2 Projected Schedule Start of Environmental Process January 2007 Public Scoping Meetings February - March 2007 Definition of AA/DEIS/DEIR Alternatives October 2007 Public Comment Period and Hearings on DEIR January - March 2009 Expo Board Discussion of Alternatives April 2009 Approval of Final EIR February 2010 Conduct Preliminary Engineering March - December 2010 Begin Final Design & Construction February 2011 Begin Revenue Service Early 2015
18 Reaching Stakeholders Where They Are
19 Contact Information For more information regarding this project, please contact: Monica Born, PE Project Director for Phase or mborn@exporail.net
Exposition Light Rail Transit Project
Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update May 1, 2008 PHASE 1 Phase 1 Project Status Design Design approximately 86% complete Construction Construction
More informationExpo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012
Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Meeting Agenda Phase 2 Design Update Meeting Meeting Purpose and Format Final Design Update Expo Bikeway Update
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations,
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report February through April 2012 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report April 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report July 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationWestside Subway Extension
Los Angeles County Metropolitan Transportation Authority Westside Subway Extension Community Update Meeting August 2009 Purpose of Tonight s Meeting Summary of Comments from Public Scoping Update on Alternatives
More informationRegional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report
Los Angeles County Metropolitan Transportation Authority Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Public Scoping Meeting 1 Agenda!
More informationOPTIONAL STATIONAVIATION/MANCHESTER
CRENSHAW/LAX TRANSIT CORRIDOR PROJECT FEIS/FEIR OPTIONAL STATIONAVIATION/MANCHESTER Aviation and Manchester, Looking East Aviation/Manchester Station (Optional) The Optional Aviation/Manchester Station
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report December 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationMetro Blue Line Improvements & Project Update
Metro Blue Line Improvements & Project Update February 9, 2018 MBL Operational Improvements - External Metro & LADOT coordination to identify traffic signal and intersection treatments aimed at increasing
More informationEastside Transit Corridor Phase 2
Eastside Transit Corridor Phase 2 Community Meeting, June 22, 2016 Page 1 Purpose of Tonight s Meeting Page 2 Update on Metro Board directed Technical Study (Nov. 2014) SR-60 Alternative Washington Blvd
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationProject Budget and Schedule Status
Item Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee February 20, 2014 & Schedule Performance Summary Chart Slide # Project
More informationPREPARED TESTIMONY OF LEE LISECKI. Q. Please state your name, professional position, and business address.
Application 06-12-005 et al. Exhibit Date: August, 2008 PREPARED TESTIMONY OF LEE LISECKI Q. Please state your name, professional position, and business address. A. My name is Lee Lisecki. I am a principal
More informationProject Budget and Schedule Status Report
Item 52 Transit Program Project Budget and Schedule Status Report Construction Committee June 19, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments 3 Crenshaw/LAX
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report April / May 2016 (Final) TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction
More informationProject Budget and Schedule Status
Item 47 Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee January 16, 2014 & Schedule Performance Summary Chart Project Performance
More informationProject Budget and Schedule Status Report
Item 58 Transit Program Project Budget and Schedule Status Report Construction Committee October 16, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments
More information11. PHASED IMPLEMENTATION STRATEGY
11. PHASED IMPLEMENTATION STRATEGY 11.1. ALTERNATIVES ANALYSIS SUMMARY The Harbor Subdivision AA Study analyzed both existing and forecast transportation conditions within the Study Area and identified
More informationLand Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences
Figure 5-16. Santa Monica/San Vicente 1/4-Mile Station Area August 16, 2010 Page 5-35 Figure 5-17. Beverly Center 1/4-Mile Station Area August 16, 2010 Page 5-36 5.8 Alternative 5 Santa Monica Extension
More informationWest Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Interagency Meeting June 19, 2017
West Santa Ana Branch Transit Corridor Draft EIS/EIR Scoping Interagency Meeting June 19, 2017 Agenda > Welcome and Introductions > Purpose of Interagency Scoping > Timeline and Process > Agency Coordination
More informationCrenshaw/LAX Transit Project Construction Update Meeting July 28, 2015
Crenshaw/LAX Transit Project Construction Update Meeting July, 2015 1 Project Overview Design-Build Contract - Walsh Shea Corridor Constructors (WSCC) 8.5 mile Light Rail Line Eight (8) new stations Three
More informationSUMMARY OF IMPACTS NEW IMPACTS AND PROPOSED MITIGATION
4.21 SUMMARY OF IMPACTS 4.21.1 NEW IMPACTS AND PROPOSED MITIGATION Table 4.21-1 uses the following abbreviations to classify impacts by level of significance: The changes to the Project made during the
More informationPublic Works Department
Public Works Department Monthly Report Public Works Department Monthly February Report 2017 George Chavez Assistant City Manager/Director of Public Works Key Message The Public Works Department reached
More information4.0 AFFECTED ENVIRONMENT AND ENVIRONMENTAL CONSEQUENCES
4.0 Affected Environment & Environmental Consequences 4.0 AFFECTED ENVIRONMENT AND ENVIRONMENTAL CONSEQUENCES INTRODUCTION This section examines the environmental consequences associated with the proposed
More informationProject Budget and Schedule Status
Item Program Management Project Budget and Schedule Status Transit Project Delivery Construction Committee November 21, 2013 & Schedule Performance Summary Chart 2 1 Crenshaw/LAX Transit 1,749 2,058 2,058
More informationWest Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Meeting June 2017
West Santa Ana Branch Transit Corridor Draft EIS/EIR Scoping Meeting June 2017 Agenda > Welcome and Introductions > Purpose of Scoping > Timeline and Process > Environmental Approach and Methodology >
More informationFACT SHEETS LOS ANGELES COUNTY
FACT SHEETS LOS ANGELES COUNTY WHAT IS THE REGIONAL TRANSPORTATION PLAN/ SUSTAINABLE COMMUNITIES STRATEGY (RTP/SCS) Every four years the Southern California Association of Governments (SCAG) prepares a
More informationFuture Build Alternative Traffic Forecasts and Level of Service Analysis
4.2.10 Future Build Alternative Traffic Forecasts and Level of Service Analysis For the five Build Alternatives, study intersections within one mile of potential station locations were analyzed, as it
More informationAGENDA REGULAR BOARD MEETING
Exposition Metro Line Construction Authority 707 Wilshire Blvd #34 Los Angeles, CA 90017 213-243-5500 BuildExpo.org AGENDA REGULAR BOARD MEETING Kenneth Hahn Hall of Administration 500 West Temple Street
More informationTHIS PAGE INTENTIONALLY LEFT BLANK.
THIS PAGE INTENTIONALLY LEFT BLANK. DRAFT ENVIRONMENTAL IMPACT STATEMENT/ENVIRONMENTAL IMPACT REPORT LEAD AGENCIES: Federal Transit Administration, U.S. Department of Transportation and Los Angeles County
More information1.4 Analysis of Alignment Alternatives
Parkway is 20.94 miles, with 8.16 miles in Orange County, 7.37 miles in Lake County and 5.41 miles in Seminole County. SR 46 Reconstruction and Realignment, which would begin at the SR 46/US 441 interchange
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update January 14, 2008 PHASE 1 Phase 1 Project Status Design Design approximately 78% complete Construction Packages
More informationPurple Line Extension Section 1 Construction Community Meeting September 26, 2017
Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 1 Agenda Sections 1 & 2 Section 1 Construction Updates TBM Art and Naming Contest Project Construction Updates: Wilshire/Western
More informationEngineering & Construction -- Transit Status Report. Significant Issues
ITEM XX Engineering & Construction -- Transit Status Report Significant Issues Presented By Bryan Pennington Executive Director Engineering and Construction 1 1 I-405 SEPULVEDA PASS IMPROVEMENTS PROJECT
More informationLos Angeles Westside Purple Line Extension Project Challenges and Lessons Learned
Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Ashok Kothari, P.E. WSP USA, Sr. Vice President Los Angeles, California Michael McKenna, P.E. LACMTA Executive Officer,
More information1.0 INTRODUCTION 1.1 CEQA REQUIREMENTS 1.2 PUBLIC REVIEW PROCESS
1.1 CEQA REQUIREMENTS 1.0 INTRODUCTION Before approving a project that may cause a significant environmental impact, the California Environmental Quality Act (CEQA) requires the Lead Agency to prepare
More informationMid-Coast Corridor Transit Project Project Working Group June 16, 2014
Mid-Coast Corridor Transit Project Project Working Group June 16, 2014 Project Overview $1.7 billion TransNet and federal funding 11 mile extension of San Diego Trolley Blue Line Old Town Transit Center
More informationRailyard Alternatives & i-280 Boulevard (rab) Feasibility Study Phase I: Preliminary Options Analysis
Railyard Alternatives & I-280 Boulevard Feasibility Study 1 Railyard Alternatives & i-280 Boulevard (rab) Feasibility Study Phase I: Preliminary Options Analysis San Francisco Planning Department TJPA
More informationExecutive Summary Introduction and Background
ES.1 Introduction and Background The Los Angeles County Metropolitan Transportation Authority (LACMTA) completed the Final Environmental Impact Report/Environmental Assessment (Final EIR/EA) for the Wilshire
More informationCity of Los Angeles. Integrated Resources Plan (IRP) Certification of Final Environmental Impact Report (EIR) and Adoption of IRP Recommendations
City of Los Angeles Integrated Resources Plan (IRP) Certification of Final Environmental Impact Report (EIR) and Adoption of IRP Recommendations City Council Meeting November 14, 2006 The Challenges New
More informationCentral San Pedro Neighborhood Council Port Committee Meeting February 19, 2014 Augie Bezmalinovich Port of Los Angeles
Central San Pedro Neighborhood Council Port Committee Meeting February 19, 2014 Augie Bezmalinovich Port of Los Angeles 1. Call to Order 2. Introduction of Guests 3. Consideration of Agenda 4. Port of
More informationWELCOME HDR, all rights reserved.
WELCOME Public Meeting on Environmental Assessment East Side Corridor (SD100) I-90 to South of Madison Street Northern Segment of Hwy 100 Date: October 21, 2014 2014 HDR, all rights reserved. Introductions-
More informationCrenshaw/LAX Transit Project
Crenshaw/LAX Transit Project Construction Update Community Meeting January 25 th, 2017 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance
More informationPeninsula Corridor Electrification Project. Draft Environmental Impact Report
Peninsula Corridor Electrification Project Draft Environmental Impact Report Public Meeting Purpose of Tonight s Meeting Provide an overview of Draft Environmental Impact Report (Draft EIR) Receive comments,
More informationTransportation Update
Transportation Update Projects Underway Norview Avenue About the Project: The Norview Avenue Interchange Improvement Project will eliminate the existing weave movement associated with the on- and off-ramps
More informationChapter 1. Introduction
Chapter 1. Introduction 1.1 Purpose of the Supplemental Environmental Impact Report (EIR) The California Environmental Quality Act (CEQA) requires preparation of an Environmental Impact Report (EIR) when
More informationWELCOME EAST LINK OVERLAKE MASTER PLANNED DEVELOPMENT
WELCOME The purpose of tonight s meeting is to: Educate the Overlake community about why Sound Transit is applying for a Master Planned Development Permit to build East Link within the City of Redmond
More informationMetro Board Action: Motion 22.1
Los Angeles County Metropolitan Transportation Authority Metro Board Action: Motion 22.1 Implementation Update presented to the Corridor Advisory Committee March 17, 2016 Background Motion 22.1 October
More informationMetro Purple Line Extension
metro.net/works Metro Purple Line Extension Construction Fact Sheet summer 2013 building the stations Construction at each station is estimated to take five to seven years. The station is a large box,
More informationPurple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018
Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Section 2 Pre-Construction
More informationMETRO BLUE LINE TRACK IMPROVEMENT PROJECT. July2016 TRANSMITTAL NO. 3
ADDENDUM NO. 2 TO MITIGATED NEGATIVE DECLARATION METRO BLUE LINE TRACK IMPROVEMENT PROJECT LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY (JUNE 2015) SCH # 2015051044 METRO BLUE LINE TRACK IMPROVEMENT
More informationHILLS CITY OF BEVERLY HILLS BEVERLY PUBLIC WORKS DEPARTMENT MEMORANDUM. Public Works Commission TO: FROM: Rob Welch, Acting City Engineer
April 18, 2018 MEMORANDUM PUBLIC WORKS DEPARTMENT HILLS BEVERLY CITY OF BEVERLY HILLS Public Works Commission Rob Welch, Acting City Engineer Capital Projects Update Capital Improvement Projects Update
More informationVTA s BART Silicon Valley Phase II Extension
VTA s BART Silicon Valley Phase II Extension Santa Clara Community Working Group December 3, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction Methods
More informationI-225 Rail Line Board Update. Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013
I-225 Rail Line Board Update Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013 I-225 Rail Line 10.5 mile light rail line Starts at Nine Mile Station Eight stations Serves Aurora City Center Serves
More informationWestside Purple Line Extension Section 1 Project Overview
Westside Purple Line Extension Section 1 Project Overview Westside Purple Line Extension (WPLE) Section 1 Project Purple Line Project Alignment The WPLE corridor traverses portions of three jurisdictions,
More informationPROJECT: WESTSIDE SUBWAY EXTENSION TRANSIT CORRIDOR PROJECT
34 One Gateway Plaza Los Angeles, CA 90012-2952 CONSTRUCTION COMMITTEE SEPTEMBER 20, 2012 PROJECT: WESTSIDE SUBWAY EXTENSION TRANSIT CORRIDOR PROJECT ACTION: APPROVE USE OF DESIGN-BUILD CONTRACTING DELIVERY
More informationCity of Los Angeles 2010 Bicycle Plan First Year of the First Five-Year Implementation Strategy & Figueroa Streetscape Project Draft EIR
5.0 ALTERNATIVES California Environmental Quality Act (CEQA) requires that an EIR describe a range of reasonable alternatives to the project or to the location of the project that could feasibly avoid
More informationCEQA Initial Study Checklist ENVIRONMENTAL CHECKLIST FORM. Potential Industries Solid Waste Facility Permit for a Recycling Transfer Station
CEQA Initial Study Checklist ENVIRONMENTAL CHECKLIST FORM 1. Project Title and Summary: Potential Industries Solid Waste Facility Permit for a Recycling Transfer Station Site: 8.4 acres Expansion: Addition
More informationPurple Line Extension. Beverly Hills Community Meeting August 22, 2016
Purple Line Extension Beverly Hills Community Meeting August 22, 2016 1 3 Purple Line Extension Project Alignment 2 Section 2 and 3 Status Under Construction Forecasted Schedule Section 1 Section 2 Section
More information. '- oate : _-=o_s-4-.b...;.t_t>-~f-..2..:: /} () 0 ' CAJA Environmental Services. ~: LllM M -tt~ ~ tt loa.( C./ May 10, 2016
CAJA Environmental Services 11990 San Vicente Boulevard, Suite 250 Phone 310-469-6700 Fax 310-806-9801 May 10, 2016 Ms. Luci Ibarra, Sr. City Planner Major Projects 200 North Spring Street City Hall Room
More informationt 1 Budgeted Expenditure to Date Total Project Cost: $ 1,228,440 $ 1,000,222
Water Projects Maple Wells Project (CIP No. 0916) Scope of Work: Construction of two municipal supply wells at the Maple Yard (342 Foothill Road) and a pipeline to convey well water to the water treatment
More informationLAWA Update Ground Transportation Planning and Metro Coordination
LAWA Update Ground Transportation Planning and Metro Coordination SPAS Approved LAX Ground Transportation Projects The Specific Plan Amendment Study (SPAS) includes LAX Ground Transportation Projects:
More informationEglinton Crosstown LRT Construction Liaison Committee
Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated
More informationPurple Line Extension. Construction Community Meeting March 16, 2017
Purple Line Extension Construction Community Meeting March 16, 2017 1 Agenda Project Construction Updates: Western, La Brea, Fairfax and La Cienega La Brea Station Street Configuration Update Fairfax Decking:
More informationCOASTAL CONSERVANCY. Staff Recommendation December 8, 2005 BALLONA WETLANDS ENHANCEMENT PLANNING. File No Project Manager: Mary Small
COASTAL CONSERVANCY Staff Recommendation December 8, 2005 BALLONA WETLANDS ENHANCEMENT PLANNING File No. 04-088 Project Manager: Mary Small RECOMMENDED ACTION: Authorization to disburse up to $200,000
More informationConstruction Division Update Upcoming Work. Greg Henion, P.E. Deputy State Construction Engineer
Construction Division Update Upcoming Work Greg Henion, P.E. Deputy State Construction Engineer Pre-Qualification 2 Why prequalification? Contractor s ability to perform the work: Quality Safety Experience
More informationPatrick Prescott, Community Development Director By: David L. Kriske, Assistant Community Development Director
DATE: April 26, 2016 TO: FROM: Ron Davis, Interim City Manager Patrick Prescott, Community Development Director By: David L. Kriske, Assistant Community Development Director SUBJECT: Modification of two
More informationMichael Gillam Deputy Program Director - Southern California
International Right of Way Association Los Angeles Chapter: C A L I F O R N I A H I G H - S P E E D R A I L Michael Gillam Deputy Program Director - Southern California January 25, 2011 A Statewide System
More informationSR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014
SR 710 North Study Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014 1 1 1 Agenda Public Outreach Activities Project Report
More information4.13 Economic and Fiscal Impacts
4.13 Economic and Fiscal Impacts This section describes the potential for economic and fiscal impacts that could arise from the construction and long-term operation of the proposed transit improvements
More informationATTACHMENT 1 DRAFT STAGE A BASELINE SCOPE OF WORK 1. GENERAL DESCRIPTION OF PHASE 2 OF THE EXPOSITION LIGHT RAIL TRANSIT PROJECT
ATTACHMENT 1 DRAFT STAGE A BASELINE SCOPE OF WORK 1. GENERAL DESCRIPTION OF PHASE 2 OF THE EXPOSITION LIGHT RAIL TRANSIT PROJECT Phase 2 of the Exposition Light Rail Transit Project (Project), from Culver
More informationLA WATERFRONT PROGRAM WILMINGTON & SAN PEDRO
LA WATERFRONT PROGRAM WILMINGTON & SAN PEDRO American Council of Engineering Companies November 12, 2008 OVERVIEW Santa Monica Bay Downtown Los Angeles Palos Verdes Peninsula San Pedro Wilmington Port
More informationAirport Metro Connector. 96th Street Transit Station July 13, 2016 Public Hearing
Airport Metro Connector 96th Street Transit Station July 13, 2016 Public Hearing Project Objectives > Provide a reliable, fast, and convenient connection for passengers traveling between LAX and the regional
More informationVTA s BART Silicon Valley Phase II Extension
VTA s BART Silicon Valley Phase II Extension Downtown-Diridon Community Working Group December 1, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction
More informationRestoration of Historic Streetcar Service in Downtown Los Angeles. Executive Summary -- Alternatives Analysis (AA) FINAL
Restoration of Historic Streetcar Service in Downtown Los Angeles Executive Summary -- Alternatives Analysis (AA) FINAL January 13, 2012 This page intentionally left blank Table of Contents S1.0 PURPOSE
More informationJim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project
Memorandum Date: January 15, 2014 To: CC: From: Subject: Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Paul Danielson, P.E. Project Manager, Southwest Light Rail
More informationI-70 East PACT DRAFT EVALUATION DATA
I-70 East PACT DRAFT EVALUATION DATA Future Current Alignment NEIGHORHOOD QUALITY: Maintain quality of life and protect community values. Improve or maintain neighborhood connectivity Assess neighborhood
More informationProject Budget And Schedule Status Report
Item 47 Project Budget And Schedule Status Report Presented by Brian Boudreau Executive Director, Program Management Construction Committee June 18, 2015 & Schedule Performance Summary Chart Slide # Project
More informationMetro Gold Line Eastside Extension Review Advisory Committee May 11, 2006
Review Advisory Committee May 11, 2006 1 Ramona Opportunity High School/ Indiana Station Status 2 Ramona Opportunity High School/ Indiana Station Status 1. On April 19, 2006, Metro held an Indiana Station
More informationFACT SHEETS SAN BERNARDINO COUNTY
FACT SHEETS SAN BERNARDINO COUNTY WHAT IS THE REGIONAL TRANSPORTATION PLAN/ SUSTAINABLE COMMUNITIES STRATEGY (RTP/SCS) Every four years the Southern California Association of Governments (SCAG) prepares
More informationTable 2: Recommended Improvement Projects - Northeast Area Transit Evaluation. Plan
Table 2: Recommended Improvement Projects - Northeast Area Transit Evaluation Project Location/Type Description Document Source US 85 US 85 interchange/baseline (WCR 2) Single-point diamond interchange
More informationPlacerville, a Unique Historical Past Forging into a Golden Future
Placerville, a Unique Historical Past Forging into a Golden Future City Manager s Report June 24, 2014 City Council Meeting Prepared by: Nathan Stong, City Engineer Item #: Subject: Adopt a Resolution:
More informationSilicon Valley Rapid Transit Corridor Final Supplemental EIR
3-5 3-6 3-7 3-8 3-9 RESPONSE TO COMMENT LETTER S-1 California Regional Water Quality Control Board S-1.1 The clear span bridge for the existing UPRR freight and future BART tracks was a design developed
More informationClick to edit Master title style I N D U S T R Y D AY O C T O B E R 1,
Click to edit Master title style I N D U S T R Y D AY O C T O B E R 1, 2 0 1 4 Welcome Nevada Governor Brian Sandoval Nevada DOT Director Rudy Malfabon, PE Goals Goals Obtain the best value for the costs
More informationWestside Subway Extension Combined Presentation: Alignments from Beverly Hills-Century City-Westwood/UCLA Presented in Westwood: May 18, 2010
Westside Subway Extension Combined Presentation: Alignments from Beverly Hills-Century City-Westwood/UCLA Presented in Westwood: May 18, 2010 Presented in Beverly Hills: June 7, 2010 Where We are in the
More informationENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM
ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM Each applicant needs to thoroughly review the conditions of development issued by the Planning Division in the format of a Resolution approving your project
More informationLONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17
LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17 1 PROJECT TEAM & COLLABORATORS 2 OPEN HOUSE SERIES Tuesday, May 16, 2017 6-8:00 pm La Verne City Council Chambers 3660 D Street La
More informationSouth Bay Metro Green Line Extension
Meeting Agenda Project overview and update Recap of the Scoping Meetings Progress on the project alternative and proposed station locations Meeting Schedule 6:00 Open House 6:30 Presentation 7:15 Public
More informationCHAPTER 4 ENVIRONMENTAL ANALYSIS, CONSEQUENCES, AND MITIGATION
CHAPTER 4 ENVIRONMENTAL ANALYSIS, CONSEQUENCES, AND MITIGATION This chapter of the Final Environmental Impact Statement/Environmental Impact Report (EIS/EIR) discusses the environmental analysis, consequences,
More informationPurple Line Extension Section 2 Community Meeting September 28, 2017
Purple Line Extension Section 2 Community Meeting September 28, 2017 Agenda Century City/Constellation Station Advance Utility Relocation (AUR) Launch Box Geotech/potholing Rodeo Drive Station Advance
More informationEnvironmental Impact Statement for the California High-Speed Rail System Burbank to Los Angeles Section, CA
This document is scheduled to be published in the Federal Register on 07/24/2014 and available online at http://federalregister.gov/a/2014-17384, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION
More informationRegional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting
Regional Connector Transit Project Construction Update June 9, 2016 Project Wide Community Meeting 1 Agenda > Introductions & Project Overview > Tunnel Boring Machine Update > Construction Updates > Community
More information2.0 PROJ ECT D ESCRI PTION
2.0 PROJ ECT D ESCRI PTION 2.1 PROJECT LOCATION The proposed project is in the City of Los Angeles (Figure 2.1-1, Regional Project Location Map) in the communities of Venice and Playa Del Rey (see Figure
More informationBonnie Doon Grade Separation
6. 2 Bonnie Doon Grade Separation Recommendation: That the April 18, 2017, Integrated Infrastructure Services report CR_4461, be received for information. Report Summary This report provides information
More information3. ADOPT the SPAS Mitigation, Monitoring and Reporting Program (MMRP).
, Meeting Date: February 5, 2013 Completed Pending N/A Rev lewev for Capital Budget Operating Budget CEQA 01130/13 01/31/13 01/31/13 01/30/13 APoroval Status EIY D N DNA EIYONDNA Y N MYDNOCand By DS RW
More informationVenice Pumping Plant Dual Force Main Project Draft EIR
City of Los Angeles Venice Pumping Plant Dual Force Main Project Draft EIR 4.0 ALTERATIVES UDER COSIDERATIO Alternatives under consideration for this Project are defined by the alignment and construction
More information