1 Follow This Easy Process: Step 1: Verify your Eligibility a Applicant must verify that the facility is or will be a business customer receiving electricity service from PECO under a non-residential tariff (commercial, industrial, governmental, institutional, non-profit). a All installed equipment must meet or exceed the specifications given in the program application. Step 2: Submit Pre-Approval Application to Reserve Funds a A pre-approval application must be submitted before you purchase equipment or technology to be installed at the facility for which the incentive is being requested. a Incentive funds will be reserved when your pre-approval application is approved. a Complete the Applicant Information form and the Incentive Worksheet for each of the measures that you plan to install. You may submit the application via mail, fax or . a PECO Smart Construction Incentive funds are reserved based on the project completion date, and satisfying program terms and conditions. a Design Assistance incentives are available for projects achieving at least a 10% efficiency improvement over the ASHRAE standard through the Whole Building Performance Approach. Energy modeling is required, and incentive payments are made after construction and after measurement and verification work is completed. Design Assistance incentives are not available for prescriptive or custom projects. Step 3: Install Equipment or Perform Project Work a The equipment installed and/or work performed must meet or exceed the specifications and requirements found on the specifications page and be completed within the program period. Step 4: Submit Final Application a Submit a final application as soon as possible after the project is completed. With the exception of the new buildings a a PECO Smart Ideas for Your Business PECO Smart Construction Incentives Program Application Program is offered from June 1, 2013 to May 31, 2016, or until funds are exhausted Incentive Values and Measures Contained in this Application are valid June 1, 2015 May 31, 2016 Incentive values and measures may be modified or terminated at any time without prior notice THIS APPLICATION DOES NOT APPLY TO ANY SPACE WHERE THE END USE WILL BE RESIDENTIALLY METERED. CONTACT PROGRAM STAFF TO DISCUSS INCENTIVE OPTIONS FOR THESE AREAS. and major renovation whole building projects, this should happen no later than 90 days after project completion (commercial operability) but no later than May 15, The final application uses the same form as the pre-approval application. Include the following documentation with your final application: customer/contractor information, a signed final application agreement and all required plans, specifications, submittals and invoices. The PECO Smart Ideas program team will review your final application. For some projects, a final inspection will be part of the final review. The program team will send incentive checks four to six weeks after final project approval. If you are viewing this document in Microsoft Excel, please note that each section of the application is accessible through the tabs at the bottom of the Excel window. pecosmartideas@kema.com Mail PECO Smart Construction Incentives 4377 County Line Road Chalfont, PA Fax If you need assistance, please contact our program hotline PECO-SAVE ( ) Please visit our website Page 1

2 PECO SMART CONSTRUCTION INCENTIVES APPLICATION OPTIONS PECO Smart Construction Incentives offers three tracks for achieving electric savings for new construction: a Whole Building Performance track to capture interactive equipment savings, a Custom track for non-standard equipment such as compressors, specialty lighting applications, chillers, VSDs/VFDs, HVAC controls, etc., and a Prescriptive track for new lighting, HVAC, and refrigeration and food service equipment. In each case, the baseline energy code is ASHRAE Energy savings are calculated as the difference between a baseline energy code and the installed proposed design. Lighting projects must perform at least 5% more efficiently than code requirements to qualify for incentives. Whole Building Performance Track Whole building electric savings energy modeling required (Design Assistance is available for this track only) OR Custom Track KWh savings for non-standard equipment, controls, chillers, and VSDs/VFDs AND/OR Prescriptive Track Upgrades to efficient lighting, HVAC, refrigeration/food service equipment PECO Smart Construction Incentives 4377 County Line Road Chalfont, PA Phone: PECO-SAVE ( ) Fax: pecosmartideas@kema.com Page 2

3 INCENTIVES APPLICATION CHECKLIST DIRECTIONS: There are three separate tracks for receiving PECO Smart Construction Incentives. Please check the appropriate boxes below either for the pre-notification application or for the final application. For pre-notification, please indicate the incentive path your project intends to follow. Owners may wish to solicit the assistance of their design team in filling out this checklist. If you are submitting an application under the Whole Building Performance track, please do not fill out information for the Custom or Prescriptive Tracks. PRE-NOTIFICATION APPLICATION Required Attachments Customer Information Form AND Whole Building Performance Track Whole Building Performance OR Custom Track Custom Project AND/OR Prescriptive Track (Check all that apply) Interior Lighting (Prescriptive) HVAC (Prescriptive) Refrigeration/Food Service (Prescriptive) FINAL APPLICATION Required Attachments Customer Information Form Agreements & Signature Page Copy of Current PECO Bill Whole Building Performance Track Project Narrative Electrical (Lighting) Plans & ComCheck Mechanical Plans Architectural Plans (if applicable) LEED EAc1* Template (if applicable) Energy Model (Exceutable Files & Summary) Certification of kwh Savings OR Custom Track Custom Form Supporting Equipment Performance Data Supporting Energy Savings Calculations AND/OR Prescriptive Track (Check all that apply) Interior Lighting (Prescriptive) HVAC (Prescriptive) Refrigeration/Food Service (Prescriptive) Applicable Plan Sheets Application Date: Expected Start Date: Expected Completion Date: Application Date: Actual Start Date: Final Completion Date: Phone: PECO-SAVE ( ) Fax: * LEED Energy and Atmosphere Credit 1 PECO Smart Construction Incentives 4377 County Line Road Chalfont, PA Page 3

4 TERMS AND CONDITIONS PECO Energy Company (PECO) offers incentives for new construction projects under the PECO Smart Construction Incentives Program to encourage and help support cost-effective energy efficiency measures for commercial, industrial, governmental, institutional, and non-profit customers for non-residential facilities. Any and all energy savings or environmental credits generated by the project described in this application will be retained by PECO. Funds are limited and subject to availability. The program may be modified or terminated without prior notice. Program Effective Dates The program is available until May 31, The current cycle year runs from June 1, 2015, through May 31, 2016 ( Program Year Seven ). PECO Smart Construction Incentives are offered until approved funds are exhausted or until May 15, 2016, whichever comes first. All PECO Smart Construction Incentives projects must be completed and the final applications received no later than May 15, 2016 to be eligible for incentives. Program and Project Eligibility PECO Smart Construction Incentives are available for the common energy efficiency measures listed in the application worksheets. Incentives are available under the PECO Smart Construction Incentives program to non-residential customers within PECO's service territory who pay the Energy Efficiency Charge and receive electricity through PECO s distribution network, regardless of the retail electric supplier. Multi-family projects are also eligible for incentives under the PECO Smart Construction Incentives program and must provide their master meter account information and use the Multi-Family application form. Projects that reduce building energy use as compared to current building code requirements are eligible. Prescriptive measures are energy efficiency measures with pre-determined savings and incentive levels, and are paid on a unit basis. These measures are listed in the Lighting, HVAC, and Refrigeration and Food Service sections. Custom measures include energy efficiency measures not listed on the prescriptive application forms. Custom and Whole Building incentives must be approved by PECO in advance, are determined on a case-by-case basis, and are paid per unit of energy (kwh) saved. Incentives are also offered for new construction and major renovation projects that employ an integrated Whole Building design approach to achieve savings. Whole Building Design savings must be documented through comprehensive energy modeling. All projects are subject to measurement and verification by PECO, its evaluator or the PAPUC statewide program evaluator. The project must provide 100% of the energy benefits as stated in the application for a period of five years. PECO has the right to recover a pro-rated amount of any incentive paid if the customer ceases to be a distribution customer of PECO, or removes the equipment or systems at any time during the five-year period. Incentive Payment Limits Prescriptive and custom incentives cannot exceed 100% of the customer s total costs. Actual contractor labor costs incurred can be considered in the total project cost, while customer internal labor costs cannot. Page 4

5 TERMS AND CONDITIONS Application Review Process Pre-approval applications are required for all projects. A pre-approval application must be submitted before you purchase equipment or technology to be installed at the facility for which the incentive is being requested. Pre-approval is not a guarantee of program acceptance. Completed applications will be reviewed in the order received. The location or business name on the invoice must be the same as the application information. The incentive is reserved for the project when PECO receives a complete pre-approval application and determines that the project meets the program eligibility requirements. Applicants who submit incomplete applications will be notified of deficiencies upon review of the application, and could lose their place in line in the review process until all requested information is received. Applicants are encouraged to call the program hotline if they have any questions about documentation requirements. PECO will review final applications for eligibility and completeness. With the exception of the new building and major renovation whole building approach, the final application and all required supporting documentation must be received within 90 days of project completion but no later than May 15, 2016 to be eligible for incentives. Project documentation, including product specifications and drawings and equipment performance data is required. The Final Application and all required supporting documentation must be received by May 15, 2016 to be eligible for the current program year s incentives. PECO reserves the right to request additional supporting documentation necessary to ensure measure eligibility and verify that the expected energy savings will occur. Requested information may include, but is not limited to: Proof that the equipment is operational, manufacturer specifications, warranty information, etc. PECO will make a reasonable effort to maintain the confidentiality of customer information except that such information must be provided to the PA PUC and its contractor, as well as PECO s contractor for measurement and evaluation. The installed measures are not eligible for incentives from other PA Act 129 Phase 2 Energy Efficiency Programs. Lighting purchased from a retailer under PECO Smart Lighting Discounts is ineligible for an additional incentive under the PECO Smart Equipment Incentive program. Inspections and/or PUC s Statewide Program Evaluation PECO, its agents, measurement and verification contractor, and/or the PUC statewide program evaluator have the right to audit or inspect all projects to verify compliance with the program rules and verify the accuracy of project documentation. This may include pre-installation and/or post-installation inspections, detailed lighting layout descriptions, metering, data collection, interviews, and utility bill data analyses. The customer must allow access to project documents and the facility where the measures were installed for a period of five years after receipt of incentive payment by PECO. Requirements for Custom Project Electricity Savings Calculation The annual electricity savings must be calculated for custom projects using industry accepted engineering algorithms or simulation models. The applicant must estimate the annual electricity usage of both the base case and proposed equipment based on the projected operation of the facility. The applicant must utilize equipment that would meet the applicable federal and local energy codes as the baseline when calculating the annual energy savings. The applicant must be able to clearly describe the method used to calculate the savings. The applicant must provide all assumptions used in the calculations and document the source for these assumptions. Further information on custom measures can be found in the Policies and Procedures Manual, which can be downloaded from The method and assumptions used by the applicant to calculate the annual savings will be reviewed by PECO. PECO has sole and final determination of the annual energy savings to be used in calculating the incentive amount. PECO also reserves the right to require specific measurement and verification activities including monitoring and to base the incentive payment on the results of these activities. Tax Liability Incentives may be taxable for most taxpayers. If the incentive is more than $600, it will be reported to the IRS and the customer will be provided with an IRS form 1099, unless the customer is exempt. PECO is not responsible for any tax liability that may be imposed on any customer as a result of the payment of program incentives. All customers must supply their Federal Tax Identification number to PECO in order to receive a Program Incentive. Please consult with your tax professional for information on the tax treatment of the incentives. Page 5

6 TERMS AND CONDITIONS No Endorsement PECO does not endorse, support or recommend any particular manufacturer, product or system design in promoting this program, and PECO does not guarantee any specific level of energy savings with respect to any product, system design or energy efficiency measure. Warranties PECO DOES NOT WARRANT THE PERFORMANCE OF INSTALLED EQUIPMENT, AND/OR SERVICES RENDERED AS PART OF THIS PROGRAM, EITHER EXPRESSLY OR IMPLICITLY. NO WARRANTIES OR REPRESENTATIONS OF ANY KIND, WHETHER STATUTORY, EXPRESSED,OR IMPLIED, INCLUDING, WITHOUT LIMITATIONS, WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE REGARDING EQUIPMENT OR SERVICES PROVIDED BY A MANUFACTURER OR VENDOR. CONTACT YOUR VENDOR/SERVICES PROVIDER FOR DETAILS REGARDING PERFORMANCE AND WARRANTIES. Limitation of Liability By virtue of participating in this program, customers agree to waive any and all claims or damages against PECO, except the receipt of the program incentive, if eligible. Participating Customers agree that PECO s liability, in connection with this program, is limited to paying the program incentive specified. Under no circumstances shall PECO, its representatives, agents or subcontractors, be liable for any lost profits, special, punitive, consequential or incidental damages or for any other damages or claims connected with or resulting from participation in this program. Assignment Customers may assign a portion or all of their program incentive payment to a specified vendor. Customer s Certification Customer certifies that s/he purchased and installed the equipment listed in the application.. Customer agrees that all information is true and that s/he has conformed to all of the program and equipment requirements listed in the application. Termination PECO reserves the right to extend, modify (this includes modification of program incentive levels) or terminate this program without prior or further notice. Acknowledgement I have read, understood and am in compliance with all rules and regulations concerning this incentive program. I certify that all information provided is correct to the best of my knowledge, and I give PECO permission to share my records with the Pennsylvania PUC, and agents, representatives and contractors it selects to manage, coordinate or evaluate the program. Additionally, I hereby authorize PECO to have reasonable access to my property to inspect the installation and performance of the equipment eligible for incentives under the guidelines of the program. Page 6

7 INCENTIVE APPLICATION Important: Please read the terms and conditions before signing and submitting this application. You must complete all information and provide required additional documentation to avoid processing delays. CUSTOMER INFORMATION APPLICANT PHONE NUMBER NAME AS IT (WILL) APPEAR ON PECO BILL PECO ACCT # (if available) APPLICANT FEDERAL TAXPAYER ID # MAILING ADDRESS CITY STATE ZIP CONTACT PERSON (AUTHORIZED REPRESENTATIVE) ADDRESS PHONE NUMBER PROJECT ADDRESS (OR LOCATION IF ADDRESS IS NOT ASSIGNED) CITY STATE ZIP As an eligible customer/future customer, I verify the information is correct and request consideration for participation under this program. APPLICANT SIGNATURE PLEASE PRINT NAME PROJECT INFORMATION Primary Building Type (select one) OFFICE BUILDING INDUSTRIAL/MANUFACTURING RELIGIOUS WORSHIP/CHURCH RETAIL Number of Shifts MULTI-FAMILY (COMMON AREAS) GROCERY WAREHOUSE DAYCARE RESTAURANT STORAGE NURSING HOME LODGING - GUEST ROOMS AUTO RELATED HOSPITAL LODGING - COMMON AREAS DUSK-TO-DAWN/EXTERIOR HEALTH/MEDICAL CLINIC EDUCATION (K-12) PARKING GARAGES OTHER PUBLIC ORDER AND SAFETY EDUCATION (COLLEGE/UNIVERSITY) 24/7 FACILITIES OTHER SQUARE FOOTAGE OF BUILDING(S) AFFECTED BY THIS PROJECT x x x Business Type (select one) Tax Status (as entered on W9) Building Certification/Rating COMMERCIAL/INDUSTRIAL CORPORATION (Inc., PC, Etc.) Version GOVERNMENT/MUNICIPAL TAX EXEMPT LEED SCHOOL INDIVIDUAL ENERGY STAR NON-PROFIT PARTNERSHIP Other (describe) OTHER OTHER (may receive 1099) Describe Other % OF BLDG UNDER RENOVATION: BUILDING AGE: BLDG SYSTEMS UNDER RENOVATION: Renovation Projects Only (Must Include both lighting and HVAC to Qualify as New Construction Project) ADDITIONAL COMMENTS: Page 7

8 INCENTIVES APPLICATION PROJECT CONTACTS DESIGN TEAM LEAD CONTACT NAME OF CONTACT PERSON TITLE, FIRM APPLICANT FEDERAL TAXPAYER ID # CONTACT PHONE # EXTENSION CONTACT FAX # CONTACT ADDRESS MAILING ADDRESS CITY STATE ZIP ARCHITECTURAL CONTACT NAME OF CONTACT PERSON TITLE, FIRM CONTACT PHONE # EXTENSION CONTACT FAX # CONTACT ADDRESS MECHANICAL CONTACT NAME OF CONTACT PERSON TITLE, FIRM CONTACT PHONE # EXTENSION CONTACT FAX # CONTACT ADDRESS ELECTRICAL CONTACT NAME OF CONTACT PERSON TITLE, FIRM CONTACT PHONE # EXTENSION CONTACT FAX # CONTACT ADDRESS NAME OF CONTRACTING COMPANY (IF AVAILABLE) CONTRACTOR INFORMATION NAME OF CONTACT PERSON TITLE, FIRM CONTACT PHONE # EXTENSION CONTACT FAX # CONTACT ADDRESS Page 8

9 FINAL APPLICATION AGREEMENT FINANCIAL INCENTIVES MAY HAVE TAX IMPACTS; PAYMENTS MAY BE RECORDED ON FORM PAYMENT OF THE DESIGN INCENTIVE TO THE DESIGN TEAM IS AT THE DISCRETION OF THE PECO ACCOUNT HOLDER. COMPLETION NOTICE AND FINAL INCENTIVE REQUEST - OWNER BY SIGNING AND SUBMITTING THIS FINAL APPLICATION, I VERIFY THAT ALL CONSTRUCTION HAS BEEN COMPLETED AND A CERTIFICATE OF OCCUPANCY HAS BEEN ISSUED. SIGNED APPLICATIONS RECEIVED BY FAX OR WILL BE TREATED THE SAME AS ORIGINAL APPLICATIONS RECEIVED BY MAIL. NAME OF APPLICANT'S BUSINESS APPLICATION NUMBER (FROM RESERVATION LETTER) TOTAL INCENTIVES REQUESTED CHECK MAILING ADDRESS CITY STATE ZIP PRINT NAME/TITLE DATE ACTUAL COMPLETION DATE FEDERAL TAXPAYER ID # CUSTOMER SIGNATURE (PECO CUSTOMER) TOTAL PROJECT COST COMPLETION NOTICE AND FINAL INCENTIVE REQUEST - DESIGN INCENTIVE DESIGN INCENTIVE RECIPIENT SIGNATURE PRINT NAME/TITLE DATE FEDERAL TAXPAYER ID # TOTAL INCENTIVES REQUESTED CHECK MAILING ADDRESS CITY STATE ZIP PAYMENT RELEASE AUTHORIZATION TO THIRD PARTY Complete this section ONLY if incentive payment is to be paid to an entity other than the PECO account holder listed on the Applicant Information page. I am authorizing the payment of the incentive to the third party named below and I understand that I will not be receiving the incentive payment from PECO. I also understand that my release of the payment to a third party does not exempt me from the program requirements outlined in the measure specifications and Terms & Conditions. Authorized by: APPLICANT SIGNATURE (PECO CUSTOMER) PRINT NAME/TITLE DATE Check should be made payable to: PAYEE: COMPANY/INDIVIDUAL NAME MAILING ADDRESS CITY STATE ZIP CONTACT PHONE NUMBER FEDERAL TAXPAYER ID # TAX STATUS Corporation (Inc., PC, Etc.), Tax Exempt, Individual, Other (May receive 1099) Page 9

10 FINAL APPLICATION AGREEMENT As an eligible PECO non-residential customer, I certify that work was completed on this project on or after June 1, The energy efficiency measures are for use in my non-residential facility and not for resale. Project documentation, including product specification sheets, drawings, and copies of dated invoices for the purchase and installation of the measures, is attached. I have attached any other documentation requirements as detailed in the Policy and Procedures Manual found at or requested of me by the program team. I understand that the location or business name on the invoice must be consistent with the application information. I agree to verification by the utility or its representatives of both sales transactions and equipment installation. I certify that the information on this application is true and correct, and that the Taxpayer ID Number and tax status are accurate. I understand that incentives over $600 may be reported to the IRS unless appropriate exemption documentation is provided to PECO. I agree that if: (1) I do not install the related product(s) identified in my application, or (2) I remove the related product(s) identified in my application before a period of five years or the end of the product life, whichever is less, then I shall refund a prorated amount of incentive funds to PECO based on the actual period of time in which the related product(s) were installed and operating (or the full amount if the product was never installed). Any measure that I have installed in my facility must provide 100% of the energy benefits as stated in this application for a period of five years, or for the life of the product, whichever is less. I understand that this is necessary to assure that the project s related energy benefits will be achieved. I understand that the program may be modified or terminated without prior notice. I understand that final applications and all required documentation must be received by the PECO Smart Construction Incentives program within 90 days of project completion but no later than May 15, 2016 and that all equipment must be purchased and installed prior to submitting the final application. I understand that this project must involve a facility improvement that results in improved energy efficiency and/or a permanent reduction in energy usage. I also understand that all materials removed, including lamps and PCB ballasts, must be permanently taken out of service and disposed of in accordance with all laws, including local codes and ordinances. I understand it is my responsibility to be aware of any applicable codes or ordinances, and that information about hazardous waste disposal can be found at: I understand that PECO and its representatives have the right to ask for additional information at any time, and that the PECO Smart Construction Incentives program will make the final determination of incentive levels for this project. I understand that PECO does not guarantee the energy savings and does not make any warranties associated with the measures eligible for incentives under this program, and further, that PECO has no obligations regarding and does not endorse or guarantee any claims, promises, work, or equipment made, performed, or furnished by any contractors or equipment vendors that sell or install any energy efficiency measures. I understand that in the event the application was pre-approved and funds were reserved based upon the application, such preapproval or reservation, including the specific dollar amount of reservation, did not represent a guarantee that such funds would be paid. Payment of incen-tives is based upon the final application. I understand the program terms and conditions, as well as the availability of funds. I have read and accept the PECO Smart Construction Incentives Terms and Conditions as they appear in this application. Page 10

11 INTERIOR LIGHTING WORKSHEET DIRECTIONS: Incentives are offered only for controls that are not required by ASHRAE Fill out the total interior lighting wattage controlled by qualifying occupancy sensors, central lighting controls, or daylight sensors. The incentives are based on the number of watts controlled by each type of control equipment. Incentives are available for interior lighting where the lighting power density is lower than the code-minimum power by at least 5%. To receive incentives for lighting, please complete the PA Act 129 TRM Appendix E form for interior lighting and provide the report and lighting plans with this application. The "Space-by-Space" or "Building Area" method can used to calculate the LPD for the purposes of the incentive. A U.S. Department of Energy COMcheck worksheet must be submitted as back-up documentation. In the spaces below, please enter the occupied square footage of the building, the total allowed watts, and the total proposed watts. The incentive is based on the difference between the ASHRAE allowed wattage and the installed wattage. Lighting plans (showing layout, quantities, and fixture types), lighting equipment schedule, architectural floor plans, PA Act 129 TRM Appendix E form, and a COMcheck report for interior lighting MUST be attached. Click here for a link to COMcheck software. Click here for a link to PA TRM Appendix E Interior Controls Equipment Type Incentive per W Total Watts Controlled (Watts) Incentive Calculated Occupancy Controls Total Lighting Controls Incentives: $0.20 Interior Lighting - Lighting Power Density Space-by-Space Approach Building Type Occupied Area (Sq Ft) Total Allowed Watts (Watts) Example: Sally's Retail Sales 100, ,000 Total Proposed Watts (Watts) Incentive per kw Total Incentive 113,533 $ $10, $ $ $ $ $ $ $ $ Total Interior Lighting Power Density Incentive: $0.00 LIGHTING PLANS, SCHEDULES, PA TRM APPENDIX C, AND COMCHECK REPORT OR EQUIVALENT MUST BE ATTACHED Page 11

12 LIGHTING SPECIFICATION Lighting Power Density Approach Under the Lighting Power Density Approach, the lighting power installed is compared with the lighting power allowed by code. Incentives are available for systems where the installed lighting power is lower than the code-allowed power by at least 5%. Savings are based on the Lighting Power Density (LPD) calculated on a watts per square foot basis. Incentives will be paid only on the area of the building where the lighting installation is complete and is ready for occupancy. If a portion of a building is not built-out such that the lighting in an area is not complete and ready for occupancy, then that portion is not eligible for an incentive. Baseline lighting power density is based on ASHRAE Either the "Space-by-Space" or "Building Area" method may be used to calculate the LPD for the purposes of the incentive. The incentive for the lighting performance based approach is $300 per kw reduction in connected load below the ASHRAE standard. The minimum lighting power density used to calculate the incentive shall be no lower than 50% of the ASHRAE value. Required Documentation: PECO Smart Construction Incentives Interior Lighting Form PA Act 129 TRM Appendix E Lighting Form COMcheck Interior Lighting Report or equivalent analysis demonstrating space-by-space or building area calculations. Reflected ceiling plans and electrical plan sheets showing lighting fixture layout Lighting fixture schedule sheet including fixture counts Fixture submittal or specification sheets showing model number and rated fixture wattage Architectural floor plans displaying floor area affected by proposed lighting installation Lighting Controls That Exceed Code Requirements Interior Occupancy Sensors Incentives are offered for occupancy-based controls in areas where they are not required by code. Passive infrared, ultrasonic detectors and fixture-integrated sensors or sensors with a combination sensor are eligible. All sensors must be hard-wired and control interior lighting fixtures. The incentive is per Watt controlled. An inventory of the controlled fixtures and their wattage must be provided for each sensor with the Final Application. Daylight Dimming System Incentives are offered for daylight sensor controls in spaces with suitable available ambient light for at least part of the day. Light may be through skylights, clerestories, windows or light tubes. The controls can be on/off, stepped or continuous dimming. The on/off controller should turn off artificial lighting when the interior illuminance meets the desired indoor lighting level. The stepped controller generally dims the artificial lighting 50% when the interior illuminance levels reach 50% of the desired lighting levels. Continuous or dimming controllers dim artificial lighting proportionally to the available ambient light. All types of daylight sensor controls are required to be commissioned in order to ensure proper sensor calibration and energy savings. Incentives are per Watt controlled. Lighting control options cannot be "double counted". Required Documentation: Cut sheets or submittals of lighting control systems Reflected ceiling plans or schedule showing which fixtures are controlled by lighting controls. Page 12

13 LIGHTING SPECIFICATION Lighting Power Density Code Requirements - Space by Space Method Common Space Type 223 Office-Enclosed Office-Open Plan Conference/Meeting/Multipurpose Classroom/Lecture/Training For Penitentiary Lobby For Hotel For Performing Arts Theater For Motion Picture Theater Audience/Seating Area For Gymnasium For Exercise Center For Convention Center For Penitentiary For Religious Buildings For Sports Arena For Performing Arts Theater For Motion Picture Theater For Transportation Atrium First Three Floors Atrium Each Additional Floor LPD (W/ft2) Common Space Type 223 LPD (W/ft2) 1.1 Lounge/Recreation For Hospital Dining Area For Penitentiary For Hotel For Motel For Bar Lounge/Leisure Dining For Family Dining Food Preparation Laboratory Restrooms Dressing/Locker/Fitting Room Corridor/Transition For Hospital For Manufacturing Facility Stairs Active Active Storage For Hospital Inactive Storage For Museum Electrical/Mechanical Workshop Sales Area In cases where both a common space type and a building specific type are listed the building specific space type shall apply. Page 13

14 LIGHTING SPECIFICATION Lighting Power Density Code Requirements - Space by Space Method Building Specific Space Types Gymnasium/Exercise Center Playing Area Exercise Area Courthouse/Police Station/Penitentiary Courtroom Confinement Cells Judges Chambers Fire Stations Fire Station Engine Room Sleeping Quarters Post Office-Sorting Area Convention Center-Exhibit Space Library Card File and Cataloging Stacks Reading Area Hospital Emergency Recovery Nurse Station Exam/Treatment Pharmacy Patient Room Operating Room Nursery Medical Supply Physical Therapy Radiology Laundry Washing LPD (W/ft2) Building Specific Space Types LPD (W/ft2) Automotive Service/Repair Manufacturing 0.9 Low (<25 ft Floor to Ceiling Height) High (>25 ft Floor to Ceiling Height) Detailed Manufacturing Equipment Room Control Room Hotel/Motel Guest Rooms Dormitory Living Quarters Museum General Exhibition Restoration Bank/Office Banking Activity Area Religious Buildings Worship Pulpit, Choir Fellowship Hall 0.9 Retail 2.7 Sales Area [For accent lighting, see (c)] Mall Concourse Sports Arena Ring Sports Area Court Sports Area Indoor Playing Field Area Warehouse Fine Material Storage Medium/Bulky Material Storage Parking Garage Garage Area Transportation Airport Concourse 0.6 Air/Train/Bus Baggage Area 1.0 Terminal Ticket Counter 1.5 Page 14

15 LIGHTING SPECIFICATION Lighting Power Density Code Requirements - Building Area Method Building Area Type 221 Automotive facility Convention center Courthouse Dining: bar lounge/leisure Dining: cafeteria/fast food Dining: family Dormitory Exercise center Gymnasium Health-care clinic Hospital Hotel Library Manufacturing facility Motel Motion picture theater LPD (W/ft2) Building Area Type LPD (W/ft2) 0.9 Multifamily Museum Office Parking garage Penitentiary Performing arts theater Police/fire station 1 1 Post office Religious building Retail School/university Sports arena Town hall Transportation 1 1 Warehouse Workshop In cases where both a common space type and a building specific type are listed the building specific space type shall apply. Page 15

16 LED LIGHTING SPECIFICATIONS The integral lamp or fixture must appear on the Energy Star Qualified Products List or the Design Lights Consortium Qualified Products List.* Energy Star Qualified Fixture Product List: Energy Star Qualified Integral LED lamps: Design Lights Qualified Product List: All linear LED tubes that use an integrated driver operated directly through line voltage (bypassing an external electronic ballast or LED Driver), also referred to as "Type B" TLEDs, will not qualify for an incentive. This is due to the wide variety of installation characteristics of these types of lamps and the inherent potential safety concerns of being powered directly from the line voltage. Linear LED Eligibility Requirements: Must be listed on the Design LightsTM Consortium (DLC) Qualified Products List Lamps must have an integrated driver and be driven through electronic T8 fluorescent ballast OR Lamps must be driven via external LED driver Page 16

17 HVAC INCENTIVES WORKSHEET HVAC Incentive Equipment Type and Capacity Cooling Qualifying Efficiency Heating Qualifying Efficiency Measure Code (per cooling ton) Air-Source Air Conditioners H01 < 5.5 tons (< 65,000 Btu/h) 15 SEER N/A $60.00 H and < tons 12.5 IEER ( 65,000 Btu/h and < 135,000 Btu/h) N/A $30.00 H and < 20 tons 12.3 IEER ( 135,000 Btu/h and < 240,000 Btu/h) N/A $30.00 H04 20 and < tons 11.1 IEER / 10.6 IPLV (IPLV for units with ( 240,000 Btu/h and < 760,000 Btu/h) capacity-modulation only) N/A $30.00 H tons ( 760,000 Btu/h) 10.3 IEER / 10.3 IPLV (IPLV for units with capacity-modulation only) N/A $30.00 Air-Source Heat Pumps H06 < 5.41 tons 14.3 SEER 8.7 HSPF $45.00 H tons and < tons 12.3 IEER 3.3 COP $30.00 H tons and < tons 11.7 IEER 3.2 COP $30.00 H tons 10.5 IEER / 10.1 IPLV (IPLV for units with capacity-modulation only) 3.2 COP $30.00 Water-Source Heat Pumps H10 < 1.42 tons, Air-Source Heat Pump 12.3 EER Base Case 4.6 COP $30.00 H11 < 1.42 tons, All Other Base Cases 12.3 EER 4.6 COP $30.00 H tons and < 5.41 tons, Air-Source 13.2 EER Heat Pump Base Case 4.6 COP $30.00 H tons and < 5.41 tons, All Other 13.2 EER Base Cases 4.6 COP $30.00 Packaged Terminal Systems (New Construction) H14 PTAC (cooling) (0.213 x Cap / 1000) EER N/A $30.00 H15 PTHP (0.213 x Cap / 1000) EER (0.026 x Cap / 1000) COP $30.00 Ductless Mini-Split Heat Pump H16 <5.4 tons 17.0 SEER/13.0 EER 8.8 HSPF $30.00 HVAC Measure Code Make and Model Quantity (A) Cooling Capacity (Tons) (B) Cooling Efficiency Heating Capacity (Tons) Heating Efficiency Incentive (A x B x Incentive per cooling ton) Total HVAC Incentives: HVAC Measure Code Measure Quantity Incentive per Unit Hotel Guest Room Occupancy Sensor H17 Unit $30.00 (Electric Resistance Heat/AC) Total Other HVAC Incentives: Other HVAC Measures Incentive Unit Incentive Page 17

18 HVAC SPECIFICATIONS All equipment, units or parts that are discarded as a result of this program must be disposed of properly by the Applicant. HVAC Measure Code H01 - H09 H10 - H13 H14 - H15 H16 H17 Specification Air-Source Air Conditioners Air-Source Heat Pumps New unitary air conditioning units or air source heat pumps that meet or exceed the qualifying cooling efficiency shown in the HVAC Incentives Worksheet are eligible for an incentive. They can be either split systems or single package units. The efficiency of split systems is based on an ARI reference number. All packaged and split system cooling equipment must meet Air Conditioning and Refrigeration Institute (ARI) standards (210/240, 320 or 340/360), be UL listed, use a minimum ozone-depleting refrigerant (e.g., HCFC or HFC). All required efficiencies are based on the Consortium for Energy Efficiency (CEE) high-efficiency commercial air conditioning and heat pump specifications ( A manufacturer s specification sheet indicating the system efficiency must accompany the application. Disposal of the existing unit must comply with local codes and ordinances. Water-Source Heat Pumps The system consists of multiple units connected to a closed-loop hydronic system with continuous water circulation. The installed water source heat pump must be rated in accordance with the most recent version of ARI A manufacturer s specification sheet indicating the system capacity and efficiency for cooling and heating must accompany the application. Disposal of the existing unit must comply with local codes and ordinances. Package Terminal Systems (New Construction) Package terminal air conditioners and heat pumps are through-the-wall, self contained units that are 2 tons (24,000 Btu/h) or less. All EER values must be rated at 95 F outdoor dry-bulb temperature. Ductless Mini-Split Heat Pump <5.4 Tons Incentives are offered for Ductless Mini-Split Heat Pump <5.4 Tons with SEER rating greater than or equal to 17.0 and EER greater than or equal to 13.0 and HSPF greater than or equal to 8.8. Hotel Guest Room Occupancy Sensor (Electric Resistance Heat/AC) Incentives are offered for occupancy-based controls that control electric air conditioning, air source heat pumps, and / or electric heating units for individual hotel rooms. Systems with non-electric heat are not eligible. Sensors must be controlled by automatic occupancy detectors or a key-card system, and the default setting for controlled units differ by at least 5 degrees (or shut the unit fan and heating or cooling off completely) from the operating set point during unoccupied periods. The control system may also be tied into other electric loads, such as lighting and plug loads to shut them off when occupancy is not sensed. The incentive is per HVAC unit controlled, not per sensor, for multi-room suites. Replacement or upgrades of existing occupancy-based controls are not eligible as a prescriptive incentive. Page 18

19 REFRIGERATION/FOOD SERVICE INCENTIVES WORKSHEET Ref Measure Incentive/ Measure Incentive Unit Quantity Code Unit R01 Anti-Sweat Heater Controls Linear Foot $15.00 R14 ENERGY STAR Glass Door Freezer Unit $ R15 ENERGY STAR Solid Door Freezer Unit $ Total Refrigeration Incentives: Refrigeration Measures Incentive Food Service & Other Measures Food/Other Measure Code Measure Incentive Unit Quantity Incentive/ Unit F01 Beverage Machine Controls Unit $60.00 F02 Snack Machine Controls Unit $30.00 F03 ENERGY STAR Refrigerated Beverage Vending Machines Unit $50.00 Total Food Service & Other Incentives: Incentive Page 19

20 REFRIGERATION/MISCELLANEOUS SPECIFICATIONS Measure Code R01 R14 - R15 Specification Anti-Sweat Heater Controls Incentives are offered for devices that sense the relative humidity in the air outside of the display case and cycles or turns off the glass door (if applicable) and frame anti-sweat heaters when the ambient dewpoint is below a preset setpoint. Technologies that can turn off anti-sweat heaters based on sensing condensation (on the inner glass pane) also qualify. Incentive is based on the horizontal linear footage of the case. ENERGY STAR Solid Door Freezer ENERGY STAR Glass Door Freezer Incentives are offered for replacement of existing self-contained, open display freezers with freezers that are ENERGY STAR listed. Only units with built-in refrigeration systems are qualified. Units with remote refrigeration systems or units do not qualify. Customers must provide proof that the appliance meets the CEE or ENERGY STAR efficiency specifications using ASHRAE Standard (38 F ± 2 F). Incentive is per freezer. Table 6. Efficiency Standards for ENERGY STAR Qualified Commercial Glass Door Freezers (kwh per day) 1 Product Volume, cubic feet Freezer (kwh/day) 0 < V < V V < V V < V V 0.450V Table 7: ENERGY STAR Qualified Commercial Solid Door Freezers (kwh per day) 2 Product Volume, cubic feet Freezer (kwh/day) 0 < V < V V < V V < V V 0.158V Note: V = Internal volume in ft Note: V = Internal volume in ft 3 Measure Code F01 - F02 F03 Specification Beverage Machine Controls Snack Machine Controls Incentives are offered for refrigerated vending machines that contain non-perishable bottled and canned beverages. Controller for both types of systems must include a passive infrared occupancy sensor to turn off fluorescent lights and other energized machine systems when the surrounding area is unoccupied for 15 minutes or longer. For the refrigerated machines, the control logic may include periodic power up at 2-hour intervals or longer to maintain product temperature and provide compressor protection. ENERGY STAR Refrigerated Beverage Vending Machines Incentives are offered for ENERGY STAR beverage vending machines. Qualifying machines can be found at: Page 20

21 VFD SPECIFICATIONS (Apply as Custom Measure) Measure Code Specification Variable Speed Drives - 'Custom' Applications: V10 VFDs which are required by code are not eligible for incentives. VFDs or equivalent power reduction equipment are required in most HVAC applications by IECC 2009 (ASHRAE ). Please confirm that proposed VFDs are not required by code. A brief explanation regarding each VFD and its code application should be provided. All VFD s used in conjunction with a process or HVAC application will be paid using the custom analysis. Redundant or back-up units do not qualify. The VFD must control motor speed automatically in response to pressure, flow, temperature, or other variable signal. VFDs installed as soft start without automatic, manual, closed loop speed control do not qualify. Page 21

22 CUSTOM INCENTIVES WORKSHEET Please attach supporting documentation as described in the Policies and Procedures Manual. Prior to submitting application, please contact the SmartIdeas program staff. Incentives ($)/kwh $0.08 $0.10 Custom Lighting Custom HVAC, Refrigeration, Motors and Drives, Other Energy Conservation Measure (ECM) 1 System Description ECM Category*: Baseline Design kwh Savings ECM Cost** $/kwh Estimated Incentive Annual Oper. Hrs Energy Conservation Measure (ECM) 2 System Description ECM Category*: Baseline Design kwh Savings ECM Cost** $/kwh Estimated Incentive Annual Oper. Hrs Energy Conservation Measure (ECM) 3 System Description ECM Category*: Baseline Design kwh Savings ECM Cost** $/kwh Estimated Incentive Annual Oper. Hrs Energy Conservation Measure (ECM) 4 ECM Category*: Baseline System Description Design kwh Savings ECM Cost** $/kwh Estimated Incentive Annual Oper. Hrs Total Custom ECM Incentives***: * Energy Conservation Measure (ECM) Category is either Lighting, HVAC, Refrigeration, Motors and Drives, or Other ** ECM Cost is the cost to achieve the energy saving benefits. This does not include other costs associated with the project, if any. *** Total Custom Incentives may not exceed 100% of the ECM Cost. Page 22

23 CUSTOM PROJECTS SPECIFICATIONS Instructions for Energy Savings Calculations for Custom Projects Custom projects must involve measures that result in a reduction in electric energy use (kwh) or a permanent load reduction (kw). Electricity savings may result from either efficiency improvements or fuel switching. Custom Incentives are based on the first year Energy (kwh) savings. Projects involving measures covered by the prescriptive incentive portion of the program are not eligible for a custom incentive. Custom applications must be accompanied by detailed engineering calculations that document the annual total and on-peak energy savings. The following serve as guidelines for the minimum required documentation. Equipment Information Submittals A list of the present and proposed equipment and components to be installed, including manufacturer s catalog/model number Manufacturer s specification sheets showing capacities and performance for all major components Energy Savings Calculations Provide calculations documenting the predicted energy consumption of the existing (or baseline) and proposed system using appropriate analytical tools and clearly stated assumptions. Calculations may be performed by hand, but spreadsheet analysis or more rigorous modeling is preferred. All analysis should be provided in electronic format. All assumptions such as operating hours, existing and proposed equipment operational details must be presented. Engineering algorithms and procedures from recognized technical organizations such as ASHRAE, SMACNA, ANSI, etc. must be used. Use rated performance factors tested under accepted procedures specified by recognized rating agencies such as AHRI, ANSI, ASTM, etc. Provide an explanation when equipment performance rating conditions vary from standard conditions. In support of the calculations, extensive documentation must be provided that provides the basis for the savings estimates. The documentation must provide information on the equipment operating schedule, daily and seasonal load profile, and baseline AND energy efficient equipment performance at the operating loads. Typical documentation for custom projects often includes: Engineering or architectural drawings and equipment schedule sheets Component specification sheets that include part load efficiency or performance factors Spreadsheet calculations or input/output files and results from system modeling or other engineering analysis using accepted engineering algorithms and practices Log sheets, trend logs from a building management system, or other operating documentation that are often necessary to document operating hours and equipment loading, and used as a basis for the calculations (in some cases, short term monitoring may be required to document the load profile) Control sequence of operations that are necessary where controls play a part in the savings equation Additional documentation, other than that described in the application, may be required for program participation. Larger projects may also require pre- and post-project sub metering, or monitoring of loads and/or power input as part of another measurement and verification activity to demonstrate the actual energy savings that are realized. Baseline for Custom Analysis Where equipment is replaced prior to the end of its rated service life in order to achieve energy savings, the existing equipment performance may be used as the baseline in the energy savings calculations. Where equipment is replaced due to failure or for other reasons (such as obsolescence or a need for more capacity), the baseline performance used in the savings calculation should be either the minimum performance that would be required by code for that equipment type and application (where a code applies) or the performance of the equipment that would have been selected as the customer's "standard practice" when a code does not apply. Baseline or Existing System Summary Include make, model number, name plate information (such as operating voltage and rated full load amps), rated capacity, quantities, equipment condition and age, facility operating hours, equipment operating schedule, and load curves. If needed, attach separate sheets. All decisions regarding incentives for custom projects are in the sole discretion of PECO. Page 23

APPLICATION FOR COMBINED HEAT AND POWER INCENTIVES

APPLICATION FOR COMBINED HEAT AND POWER INCENTIVES APPLICATION FOR COMBINED HEAT AND POWER INCENTIVES PECO is offering cash incentives for qualified Combined Heat and Power (CHP) technology projects 1 to encourage the development of projects that improve

More information

Commercial & Industrial Custom Incentive Program

Commercial & Industrial Custom Incentive Program About This Application UGI Electric offers incentives for cost-effective custom energy efficiency improvements to help businesses reduce energy use by improving the efficiency of their equipment and facility.

More information

Lighting Rebates 2019 Rebate Application

Lighting Rebates 2019 Rebate Application 2019 Rebate Application P.O. Box 507 Brainerd, MN 56401 Business Member Information Business Name Installation Address City, State, Zip Contact Name Email Phone Number Account Number Rebate Recipient To

More information

PECO Smart Ideas for Your Business

PECO Smart Ideas for Your Business Follow This Easy Process: Step 1: Verify your Eligibility Applicant must verify that they are a business customer of PECO (commercial, industrial, governmental, institutional, and non-profit). Multifamily

More information

Lighting Rebates 2018 Rebate Application

Lighting Rebates 2018 Rebate Application 2018 Rebate Application Business Member Information Business Name Installation Address City, State, Zip Contact Name Email Phone Number Account Number P.O. Box 507 Brainerd, MN 56401 Wohlert@CWPower.com

More information

Ontario s Building Code

Ontario s Building Code Ministry of Municipal Affairs and Housing ONTARIO ONLY Ontario s Building Code PROPOSED CHANGE TO THE 2006 BUILDING CODE CHANGE NUMBER E-SB-10-03-01 CODE REFERENCE Supplementary Standard SB-10 Chapter

More information

Lighting Rebates Rebate Application

Lighting Rebates Rebate Application Rebate Application Coop Logo Here Business Member Information Business Name Installation Address City, State, Zip Contact Name Email Phone Number Account Number Rebate Recipient To release the rebate incentive

More information

Customer Benefits. Why Energy Efficiency? Consumers Energy Business Solutions. What Business Solutions Incentives Are Available?

Customer Benefits. Why Energy Efficiency? Consumers Energy Business Solutions. What Business Solutions Incentives Are Available? Why an Energy Efficiency Program? Business Solutions Energy Efficiency Incentive Program MPSC 21st Century Electric Energy Plan More electricity is needed as soon as practicable. One way of achieving this

More information

New Construction Lighting Application. Application Process. Details & Instructions

New Construction Lighting Application. Application Process. Details & Instructions New Construction Lighting Application Details & Instructions PSO provides technical assistance and rebates to assist businesses in making energy saving upgrades. Review details and requirements* at PowerForwardWithPSO.com.

More information

1 Project Information. 2 Building Type. 3 Trade Ally/Contractor Information. HVAC Rebate Worksheet. Retrofit New Construction

1 Project Information. 2 Building Type. 3 Trade Ally/Contractor Information. HVAC Rebate Worksheet. Retrofit New Construction HVAC Rebate Worksheet Before you start Instructions: Complete all relevant information for your project. Include with complete application package. The HVAC Worksheet should be completed for new construction

More information

Application Center Equipment Guide. Product Type Category Name Product. Heating & Cooling Equipment Unitary Packaged Heating & Cooling Air Conditioner

Application Center Equipment Guide. Product Type Category Name Product. Heating & Cooling Equipment Unitary Packaged Heating & Cooling Air Conditioner HVAC TECHNICAL SHEET GENERAL INFORMATION SMECO s Business Solutions program is designed to help commercial and industrial customers maximize energy efficiency and manage energy costs. With cost-saving

More information

What products are eligible for the rebate? < 149 tons > 150 tons

What products are eligible for the rebate? < 149 tons > 150 tons If you have questions while completing this form, please contact Energy Management Solutions, Inc. weekdays during business hours for assistance. Phone: 952-767-7450 Fax: 952-556-9171 Send your completed

More information

COMPLIANCE OVERVIEW. Module 2: Compliance Overview 4/6/2017 COMPLIANCE AND ENFORCEMENT

COMPLIANCE OVERVIEW. Module 2: Compliance Overview 4/6/2017 COMPLIANCE AND ENFORCEMENT COMPLIANCE OVERVIEW 1. Compliance and enforcement 2. Permitting and certification 3. Compliance approaches 4. Required forms 5. New additions and major changes COMPLIANCE AND ENFORCEMENT Primary responsibility

More information

2018 Smart Energy New Homes Program Manual

2018 Smart Energy New Homes Program Manual 2018 Smart Energy New Homes Program Manual Reduce the Use: Residential Table of Contents Section 1 Introduction... 1-1 1.1 Program Overview... 1-1 1.2 Program Administrator... 1-1 1.3 Program Contact Information...

More information

What products are eligible for the rebate? Fixtures & Lamps: LED Commercial Fixtures LED Lamps

What products are eligible for the rebate? Fixtures & Lamps: LED Commercial Fixtures LED Lamps If you have questions while completing this form, please contact Energy Management Solutions, Inc. weekdays during business hours for assistance. Phone: 952-767-7450 Fax: 952-556-9171 Send your completed

More information

Rooftop Units, Air Source Heat Pumps and Economizers

Rooftop Units, Air Source Heat Pumps and Economizers Commercial and Industrial Rooftop Units, Air Source Heat Pumps and Economizers 2018 Rebate Application Connexus Energy 14601 Ramsey Blvd NW Ramsey, MN 55303 ConnexusEnergy.com 763.323.2600 Business Member

More information

General Lighting Recommendations

General Lighting Recommendations General Lighting Recommendations DESIGN GUIDELINES FOR ENERGY EFFICIENT LIGHTING SYSTEMS According to the US Department of Energy, 51 percent of the energy used in commercial buildings is consumed by lighting

More information

Prescriptive Program. Terms And Conditions General Eligibility. Commercial and Industrial Customers. Rebate Checklist

Prescriptive Program. Terms And Conditions General Eligibility. Commercial and Industrial Customers. Rebate Checklist Prescriptive Program Industrial Customers Rebate Checklist Get your rebate check faster by checking off these easy steps before mailing your application form. Incomplete applications may be delayed. q

More information

2019 Lighting Retrofit Rebate Instructions. City of Winthrop

2019 Lighting Retrofit Rebate Instructions. City of Winthrop Rebate Instructions By participating in the We Save program, you can save energy and earn a rebate when you replace existing lighting with qualifying, energy-efficient lighting. What Rebate Can I Earn?

More information

Custom Incentive Application for Business Customers

Custom Incentive Application for Business Customers 2018 Custom Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the Terms and Conditions

More information

2018 Commercial Rebate Program

2018 Commercial Rebate Program Black Hills Energy offers Colorado Commercial and Industrial electric customer rebates for some of the most commonly installed efficiency projects. Follow the checklist below to determine if you are eligible

More information

Heating and Cooling Incentive Application for Business Customers

Heating and Cooling Incentive Application for Business Customers 2019 Heating and Cooling Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: IMPORTANT INSTRUCTIONS: Step 1: Determine Eligibility: Pre-approval is

More information

Heating and Cooling Incentive Application for Business Customers

Heating and Cooling Incentive Application for Business Customers 2019 Heating and Cooling Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: IMPORTANT INSTRUCTIONS: Step 1: Determine Eligibility: Pre-approval is

More information

Heating and Cooling Incentive Application for Business Customers

Heating and Cooling Incentive Application for Business Customers 2019 Heating and Cooling Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: IMPORTANT INSTRUCTIONS: Step 1: Determine Eligibility: Pre-approval is

More information

2019 Lighting Retrofit Rebate Instructions. City of Le Sueur

2019 Lighting Retrofit Rebate Instructions. City of Le Sueur Rebate Instructions By participating in the We Save program, you can save energy and earn a rebate when you replace existing lighting with qualifying, energy-efficient lighting. What Rebate Can I Earn?

More information

2019 Lighting Retrofit Rebate Instructions. City of Brownton

2019 Lighting Retrofit Rebate Instructions. City of Brownton Rebate Instructions By participating in the We Save program, you can save energy and earn a rebate when you replace existing lighting with qualifying, energy-efficient lighting. What Rebate Can I Earn?

More information

TABLE Lighting Power Densities Using the Building Area Method

TABLE Lighting Power Densities Using the Building Area Method TABLE 9.5.1 Densities Using the Building Area Method Building Area a LPD (W/ft 2 ) Automotive facility 0.82 Convention center 1.08 Courthouse 1.05 Dining: bar lounge/leisure 0.99 Dining: cafeteria/fast

More information

2019 Lighting New Construction Rebate Instructions. City of Winthrop

2019 Lighting New Construction Rebate Instructions. City of Winthrop Rebate Instructions By participating in the We Save program, you can save energy and earn a rebate when you purchase and install qualifying lighting in a new building or an addition to, or major renovation

More information

2019 Lighting New Construction Rebate Instructions. City of Olivia

2019 Lighting New Construction Rebate Instructions. City of Olivia Rebate Instructions By participating in the We Save program, you can save energy and earn a rebate when you purchase and install qualifying lighting in a new building or an addition to, or major renovation

More information

Heating and Cooling Incentive Application for Business Customers

Heating and Cooling Incentive Application for Business Customers 2019 Heating and Cooling Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: IMPORTANT INSTRUCTIONS: Step 1: Determine Eligibility: Pre-approval is

More information

2019 Lighting New Construction Rebate Instructions. City of Buffalo

2019 Lighting New Construction Rebate Instructions. City of Buffalo Rebate Instructions By participating in the We Save program, you can save energy and earn a rebate when you purchase and install qualifying lighting in a new building or an addition to, or major renovation

More information

Georgia Clean Energy Property Tax Credit Overview:

Georgia Clean Energy Property Tax Credit Overview: Georgia Clean Energy Property Tax Credit Overview: Successfully Proposing an GCEPTC Compliant Lighting Solution and Supporting Documents to Obtain a Tax Deduction SURVEY, AUDIT & DESIGN TEAM Walter P.

More information

2016 Commercial Rebate Program

2016 Commercial Rebate Program 2016 Commercial Rebate Program Colorado Electric Commercial and Industrial Customers Black Hills Energy offers Colorado Commercial and Industrial electric customers rebates for some of the most commonly

More information

2019 Lighting New Construction Rebate Instructions. City of Le Sueur

2019 Lighting New Construction Rebate Instructions. City of Le Sueur Rebate Instructions By participating in the We Save program, you can save energy and earn a rebate when you purchase and install qualifying lighting in a new building or an addition to, or major renovation

More information

Food Service Equipment Application - July 1, 2016 through June 30, 2017

Food Service Equipment Application - July 1, 2016 through June 30, 2017 Food Service Equipment Application - July 1, 2016 through June 30, 2017 Customer Information Company Name (as listed on utility bill) Doing usiness as (if applicable) Installation Start Date: Installation

More information

2019 Lighting New Construction Rebate Instructions. City of Brownton

2019 Lighting New Construction Rebate Instructions. City of Brownton City of Brownton Rebate Instructions By participating in the We Save program, you can save energy and earn a rebate when you purchase and install qualifying lighting in a new building or an addition to,

More information

Type of Business: Office Restaurant Retail Government Grocery Other Health Lodging School Church Industrial Multifamily Facility Size (ft 2 )

Type of Business: Office Restaurant Retail Government Grocery Other Health Lodging School Church Industrial Multifamily Facility Size (ft 2 ) 2016 Business Lighting Application LIMITED FUNDING: Before purchasing your equipment, contact your local utility for rebate availability. CUSTOMER INFORMATION Location Name Company Name Tax ID Website

More information

Business Energy Rebates Application

Business Energy Rebates Application Business Energy Rebates Application Business Energy Rebates make it easy and affordable for you to select energy efficient products for your business. In-store and mail-in rebates are available for energy

More information

Heating and Cooling Incentive Application for Residential Customers

Heating and Cooling Incentive Application for Residential Customers 2019 Heating and Cooling Incentive Application for Residential Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the

More information

Heating and Cooling Incentive Application for Residential Customers

Heating and Cooling Incentive Application for Residential Customers 2019 Heating and Cooling Incentive Application for Residential Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the

More information

Heating and Cooling Incentive Application for Residential Customers

Heating and Cooling Incentive Application for Residential Customers 2019 Heating and Cooling Incentive Application for Residential Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the

More information

Heating and Cooling Incentive Application for Residential Customers

Heating and Cooling Incentive Application for Residential Customers 2018 Heating and Cooling Incentive Application for Residential Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the

More information

Heating and Cooling Incentive Application for Residential Customers

Heating and Cooling Incentive Application for Residential Customers 2019 Heating and Cooling Incentive Application for Residential Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the

More information

2016 Commercial Efficiency Program

2016 Commercial Efficiency Program Existing Building Rebate Application, Version 2.0 The Commercial Efficiency Program offers rebates to commercial, industrial, institutional, educational, municipal or multi-family building customers who

More information

2016 Residential HVAC Rebate Application

2016 Residential HVAC Rebate Application Instructions for Use STEP1 Determine Eligibility Verify the utility company listed on the rebate application is your electric utility. Applications for other participating utility service providers can

More information

Heating and Cooling Incentive Application for Residential Customers

Heating and Cooling Incentive Application for Residential Customers 2019 Heating and Cooling Incentive Application for Residential Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the

More information

Heating and Cooling Incentive Application for Business Customers

Heating and Cooling Incentive Application for Business Customers 2015 Heating and Cooling Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the

More information

Business Energy Rebates Application

Business Energy Rebates Application Business Energy Rebates Application Business Energy Rebates make it easy and affordable for you to select energy efficient products for your business. and mail-in rebates are available for energy efficient

More information

Combined Heat and Power Application

Combined Heat and Power Application Combined Heat and Power Application Baltimore Gas and Electric Company (BGE) offers incentives for qualified Combined Heat and Power (CHP) projects through the BGE Smart Energy Savers Program to help commercial,

More information

SUMMARY OF SERVICES & INCENTIVES

SUMMARY OF SERVICES & INCENTIVES SMALL BUSINESS PROGRAM 2017 SUMMARY OF SERVICES & INCENTIVES Effective through December 31, 2017 Last updated February 1, 2017 EFFICIENCY INCENTIVES SUMMARY The Focus on Energy Small Business Program offers

More information

LIGHTING TECHNICAL SHEET

LIGHTING TECHNICAL SHEET GENERAL INFORMATION LIGHTING TECHNICAL SHEET SMECO's Business Solutions program is designed to help commercial and industrial customers maximize energy efficiency and manage energy costs. With cost-saving

More information

Heating and Cooling Incentive Application for Business Customers

Heating and Cooling Incentive Application for Business Customers 2019 Heating and Cooling Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: IMPORTANT INSTRUCTIONS: Step 1: Determine Eligibility: Pre-approval is

More information

2019 Residential EnergyWise Incentives

2019 Residential EnergyWise Incentives Norris Public Power District 606 Irving Street P.O. Box 399 - Beatrice, NE 68310 (402) 223-4038 www.norrisppd.com 2019 Residential EnergyWise Incentives Programs Included: Attic Insulation Incentive Cooling

More information

2017 Lighting Program Colorado: Commercial and Industrial Electric Customers

2017 Lighting Program Colorado: Commercial and Industrial Electric Customers Black Hills Energy offers Colorado Commercial and Industrial electric customers rebates for some of the most commonly installed lighting projects. We offer commercial customers two options to receive rebates.

More information

Danville Utilities Home$ave Program Manual

Danville Utilities Home$ave Program Manual 2017-2019 Danville Utilities Home$ave Program Manual Version 063017 This Program Manual is intended to serve as a reference manual for the residential customers of Danville Utilities that are interested

More information

BOARD OF PUBLIC WORKS 1600 O Street Auburn, NE Rebate Program

BOARD OF PUBLIC WORKS 1600 O Street Auburn, NE Rebate Program BOARD OF PUBLIC WORKS 1600 O Street Auburn, NE 68305 2018 Rebate Program Effective for new equipment installed after January 1, 2018. This program is subject to change at the sole discretion of the Auburn

More information

LIGHTING DISTRIBUTOR INSTANT REBATE PROGRAM

LIGHTING DISTRIBUTOR INSTANT REBATE PROGRAM Lighting Distributor Instant Rebate Program Program Year 2016 (July 1, 2016 June 30, 2017) The Hawaii Public Utilities Commission has contracted with Leidos Engineering, LLC to administer the Hawaii Energy

More information

Heating and Cooling Efficiency Program

Heating and Cooling Efficiency Program Terms & Conditions for Incentive Application Customer Information and Agreement Incentive Availability Incentive qualifications and amounts are subject to change or termination at any time. Incentives

More information

Clean Energy Ally Program Orientation

Clean Energy Ally Program Orientation Clean Energy Ally Program Orientation PRESENTED BY Lisa Harmon B USINESS A L L IANCES M ANAGER 2 WHAT WE DO Help you make smart energy choices. Because smart energy choices reduce energy use save money

More information

Heating, Ventilation & Air Conditioning Systems ( Member Information Page )

Heating, Ventilation & Air Conditioning Systems ( Member Information Page ) 2017 Commercial Program Heating, Ventilation & Air Conditioning Systems ( Member Information Page ) WrightHennepin Cooperative Electric Assn., P.O. Box 330, Rockford, MN 55373 Ph: 7634773000 Business Member

More information

ANNUAL STAKEHOLDER MEETING

ANNUAL STAKEHOLDER MEETING ANNUAL STAKEHOLDER MEETING 2015 Technical Reference Manual High Impact C&I Measure Updates July 11, 2014 Presented by the Statewide Evaluation Team: MEETING AGENDA MEETING AGENDA Weather Mapping Lighting

More information

Gas Optimization Study Program Application

Gas Optimization Study Program Application Instructions for Use All Gas Optimization Studies must receive pre-approval from the program BEFORE the study begins. For detailed instructions, please refer to the steps below. If you have any questions,

More information

Commercial & Industrial Energy Optimization Programs

Commercial & Industrial Energy Optimization Programs SP Energy and Water Work Group Breakfast Meeting Commercial & Industrial Energy Optimization Programs May 2, 2011 Agenda Introduction DTE Energy Your Energy Savings Program Overview 2011 Program Changes

More information

Policies & Procedures Manual

Policies & Procedures Manual Policies & Procedures Manual Ver. 4.0 Rev. 9-01-13 1/2/2014 9:53 AM Table of Contents 1. Program Overview... 4 1.1 Incentive Types... 4 2. Program Effective Dates... 5 3. Customer Eligibility... 5 4. Project

More information

Heating and Cooling Incentive Application for Business Customers

Heating and Cooling Incentive Application for Business Customers 2014 Heating and Cooling Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the

More information

MEASUREMENT AND VERIFICATION GUIDELINES FOR RETROFIT AND NEW CONSTRUCTION PROJECTS

MEASUREMENT AND VERIFICATION GUIDELINES FOR RETROFIT AND NEW CONSTRUCTION PROJECTS EL PASO ELECTRIC COMPANY S LARGE COMMERCIAL AND INDUSTRIAL STANDARD OFFER PROGRAM MEASUREMENT AND VERIFICATION GUIDELINES FOR RETROFIT AND NEW CONSTRUCTION PROJECTS This document includes detailed information

More information

DTE Energy Commercial & Industrial Energy Optimization Program. Trade Ally Meeting. Guardian Plumbing & Heating January 20, 2011

DTE Energy Commercial & Industrial Energy Optimization Program. Trade Ally Meeting. Guardian Plumbing & Heating January 20, 2011 DTE Energy Commercial & Industrial Energy Optimization Program Trade Ally Meeting Guardian Plumbing & Heating January 20, 2011 Agenda Introduction DTE Energy Your Energy Savings Program Overview 2011 Program

More information

New Construction Program Applications Specifications. Projects permitted utilizing ASHRAE

New Construction Program Applications Specifications. Projects permitted utilizing ASHRAE New Construction Program Applications Specifications Projects permitted utilizing ASHRAE 90.1-2010 September 2017 TABLE OF CONTENTS PROCESS OVERVIEW 3 INCENTIVE PAYMENTS AND TIERING 4 WHOLE BUILDING PERFORMANCE

More information

Residential electric heating and cooling rebates

Residential electric heating and cooling rebates Rhode Island Residential electric heating and cooling rebates Save energy and money, improve comfort, and make your home better with these energy savings offers for residential electric customers. Systems

More information

Title 24: Where We're Headed with the 2013 Standards. Featuring: Martyn C. Dodd EnergySoft, LLC

Title 24: Where We're Headed with the 2013 Standards. Featuring: Martyn C. Dodd EnergySoft, LLC Title 24: Where We're Headed with the 2013 Standards Featuring: Martyn C. Dodd EnergySoft, LLC www.energysoft.com Overall Changes in Scope and Application Welcome Overall Changes in Scope and Application

More information

Custom Application 2018 Retrofit Program

Custom Application 2018 Retrofit Program The Retrofit Program is designed for Commercial and Industrial (C&I) customers to help replace aging and inefficient equipment and systems with more energy efficient technologies. Tailored to a customer's

More information

COMMERCIAL FOOD SERVICE EQUIPMENT REBATE APPLICATION

COMMERCIAL FOOD SERVICE EQUIPMENT REBATE APPLICATION COMMERCIAL FOOD SERVICE EQUIPMENT REBATE APPLICATION 1. CUSTOMER INFORMATION (please print) Account Name Doing Business As (if different from Account Name) Installation Address City State Zip Code Mailing

More information

PECO Smart Ideas for Your Business

PECO Smart Ideas for Your Business PECO Smart Ideas for Your Business April 2015 Agenda PECO Smart Ideas incentive programs Program measures and process Tools and Trade Allies 2 1 PECO Smart Ideas PA Act 129 Program incentives designed

More information

Grays Harbor PUD Energy Services. Commercial, Industrial, Agricultural Incentive Program Catalog IT S YOUR PUD!

Grays Harbor PUD Energy Services. Commercial, Industrial, Agricultural Incentive Program Catalog IT S YOUR PUD! Grays Harbor PUD Energy Services Commercial, Industrial, Agricultural Incentive Program Catalog IT S YOUR PUD! This catalog outlines the available incentives for making energy efficient improvements at

More information

Dayton Chapter February 9, Bob Thomson, P.E., LEED-AP, CDT

Dayton Chapter February 9, Bob Thomson, P.E., LEED-AP, CDT Dayton Chapter February 9, 2009 Bob Thomson, P.E., LEED-AP, CDT World Population is estimated to be 6,000,000,000 people U.S. Population is estimated to be 3,000,000 people U.S. makes up 5% of the world

More information

COMMERCIAL FOOD SERVICE EQUIPMENT REBATE APPLICATION

COMMERCIAL FOOD SERVICE EQUIPMENT REBATE APPLICATION COMMERCIAL FOOD SERVICE EQUIPMENT REBATE APPLICATION SECTION A. CUSTOMER INFORMATION (please print) Account Name Doing Business As (if different from Account Name) Installation Address City State Zip Code

More information

Next Connecticut Energy Code

Next Connecticut Energy Code Connecticut Chapter Association of Energy Engineers Next Connecticut Energy Code 1 Next Connecticut State Building Code n 2012 International Building Code n 2012 International Existing Building Code n

More information

Installation address City State ZIP. Complete all fields for each piece of equipment purchased and installed. Natural Gas Furnace Information

Installation address City State ZIP. Complete all fields for each piece of equipment purchased and installed. Natural Gas Furnace Information HEATING AND COOLING 2018 ILLINOIS FOR YOUR HOME REBATE APPLICATION Instructions: Fill out application completely and sign. Attach supporting documentation: itemized invoice(s), SAVE test results/contractor

More information

HEATING, COOLING AND AIR-CONDITIONING MEASURES

HEATING, COOLING AND AIR-CONDITIONING MEASURES HEATING, COOLING AND AIR-CONDITIONING MEASURES FOR BUSINESS CUSTOMERS The following information is provided as part of the PowerSavers conservation program to encourage non-residential customers to select

More information

CUSTOMER FACILITY INFORMATION

CUSTOMER FACILITY INFORMATION This Project Information Form provides a template to collect project systems and equipment information and specifications. In addition, this form serves as a general overview of eligibility criteria for

More information

FirstEnergy s Pennsylvania Utilities. Energy Efficiency Programs for Business

FirstEnergy s Pennsylvania Utilities. Energy Efficiency Programs for Business FirstEnergy s Pennsylvania Utilities Energy Efficiency Programs for Business 2018 TODAY S AGENDA Introduction to Sodexo Summary of Pennsylvania Act 129 Overview of program website Overview of Application

More information

Pepco C&I Energy Savings Program. AOBA Briefing April 27, 2011

Pepco C&I Energy Savings Program. AOBA Briefing April 27, 2011 Pepco C&I Energy Savings Program AOBA Briefing April 27, 2011 Program Eligibility Pepco s Maryland commercial and industrial customers are eligible for CASH incentives for projects that reduce electric

More information

Compressed Air Incentive Application for Business Customers

Compressed Air Incentive Application for Business Customers 2018 Compressed Air Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the Terms

More information

CREDIT COMPLIANCE (Please complete the color coded criteria(s) based on the option path selected)

CREDIT COMPLIANCE (Please complete the color coded criteria(s) based on the option path selected) (Responsible Individual) (Company Name) I,, from verify that the information provided below is accurate, to the best of my knowledge. CREDIT COMPLIANCE (Please complete the color coded criteria(s) based

More information

LIGHTING TECHNICAL SHEET

LIGHTING TECHNICAL SHEET GENERAL INFORMATION LIGHTING TECHNICAL SHEET SMECO's Business Solutions program is designed to help commercial and industrial customers maximize energy efficiency and manage energy costs. With cost-saving

More information

Retrofit Lighting. Program Details & Instructions

Retrofit Lighting. Program Details & Instructions Retrofit Lighting Program Details & Instructions AEP-PSO s High Performance Business Program (HPB) is designed to help non-residential customers replace aging, inefficient equipment and systems with energy-efficient

More information

Commercial and industrial rebate application instructions

Commercial and industrial rebate application instructions rebate application instructions Page 1 Applying for your rebate is easy! Review the check list below, complete, print, sign the application, and submit. Checklist for completing your application o Read

More information

HEATING AND COOLING EQUIPMENT

HEATING AND COOLING EQUIPMENT HEATING AND COOLING EQUIPMENT 2017 SOUTH DAKOTA NONRESIDENTIAL PROGRAM AND APPLICATION MidAmerican Energy Company s EnergyAdvantage Heating and Cooling program offers financial incentives to all nonresidential

More information

FOR ADDITIONS and REMODELS Before filling out this application, read Green Building & Green Points Guideline Booklet for more in-depth information.

FOR ADDITIONS and REMODELS Before filling out this application, read Green Building & Green Points Guideline Booklet for more in-depth information. City of Boulder Residential Building Guide Green Building & Green Application Resource Conservation Ordinance 7565 www.bouldergeenpoints.com FOR ADDITIONS and REMODELS Before filling out this application,

More information

Incentives. After work is complete:

Incentives. After work is complete: SAVE your WAY Create your own Energy Demand Savings with OUC s Commercial & Industrial Custom Incentive Program Overview OUC is committed to helping your business become more energy efficient. We understand

More information

Food Service Catalog. Pacific Gas and Electric Company COMMERCIAL COMBINATION OVEN (ELECTRIC) COMMERCIAL COMBINATION OVEN (GAS)

Food Service Catalog. Pacific Gas and Electric Company COMMERCIAL COMBINATION OVEN (ELECTRIC) COMMERCIAL COMBINATION OVEN (GAS) Food Service Catalog Energy Efficiency Rebates for Your Business Carefully read the specifications below to determine that you are installing a qualifying product(s). Customers applying for a gas measure

More information

IECC 2015 with Hawaii Amendments COMMERCIAL DESIGN CHECKLIST

IECC 2015 with Hawaii Amendments COMMERCIAL DESIGN CHECKLIST IECC 2015 with Hawaii Amendments COMMERCIAL DESIGN CHECKLIST ENVELOPE REQUIREMENTS Project: Date: Instructions RECOMMENDED: List performance values, note exceptions that were applied, or provide other

More information

3% Energy Savings 4.5% Peak Demand Reduction

3% Energy Savings 4.5% Peak Demand Reduction 2 3% Energy Savings 4.5% Peak Demand Reduction May 31, 2013 3 Incentive Equipment Cost 4 Non-Standard Lighting Program Street Lighting Program, OAL, Traffic Lights Motors & Drives Program HVAC Program

More information

Commercial & Industrial Energy Audit Rebate Application

Commercial & Industrial Energy Audit Rebate Application Laclede Gas (Laclede) and Missouri Gas Energy (MGE) offer commercial and industrial customers standard and custom rebates on a wide range of natural gas products and improvements. Whether making basic

More information

Efficiency Works Business Programs Guide 2019

Efficiency Works Business Programs Guide 2019 Efficiency Works Business Programs Guide 2019 Revised: January 11, 2019 TABLE OF CONTENTS EFFICIENCY WORKS BUSINESS OVERVIEW... 3 CONTACT INFORMATION... 3 UTILITY SERVICE TERRITORY... 4 GENERAL PARTICIPATION

More information

BETA OPTION 1: PERFORMANCE RATING METHOD. Section General Information

BETA OPTION 1: PERFORMANCE RATING METHOD. Section General Information LEED-CS 2. Certification Submittal Template OPTION 1: PERFORMANCE RATING METHOD I confirm that the energy simulation software used for this project has all capabilities described in EITHER section `G2

More information

COOLING EQUIPMENT 2018 ILLINOIS FOR YOUR BUSINESS REBATE APPLICATION

COOLING EQUIPMENT 2018 ILLINOIS FOR YOUR BUSINESS REBATE APPLICATION COING EQUIPMENT 2018 ILLINOIS FOR YOUR BUSINESS REBATE APPLICATION Instructions: Fill out form completely and sign. Attach itemized invoices and supporting documentation, if applicable. Failure to complete

More information

Retrofit Lighting Rebate Application. Application Process. Details & Instructions. Equipment Eligibility

Retrofit Lighting Rebate Application. Application Process. Details & Instructions. Equipment Eligibility Retrofit Lighting Rebate Application Details & Instructions PSO provides technical assistance and rebates to assist businesses in making energy saving upgrades. Review details and requirements* at PowerForwardWithPSO.com.

More information

Ductless Heat Pump Program Guidelines

Ductless Heat Pump Program Guidelines Ductless Heat Pump Program Guidelines In order for Lane Electric and its members to insure quality heat pump installation, we are requiring that all systems meet the necessary qualifications for the Bonneville

More information

Changes to the Minnesota Commercial Energy Code. Presented by: Andy Thielen, PE

Changes to the Minnesota Commercial Energy Code. Presented by: Andy Thielen, PE Changes to the Minnesota Commercial Energy Code Presented by: Andy Thielen, PE Warning! The following is an outline of proposed code changes. There is no guarantee that the final code adopted by the State

More information