1 TL-2 Plastic Water Filled Barrier Product Manual ANOTHER AMORFLEX DEVELOPMENT

2 Table of contents Introduction 3 System overview 3 Before installation 3 Limitations and warnings 4 Safety statements 4 System design and design considerations 5 Parts identification 7 Bill of materials 7 Installation preparation 8 Installation instructions 9 Installation examples 12 Installation checklist 13 Maintenance and repair 14 Frequently asked questions 15 Crash test results summary 17 APPENDIX Technical Drawings Plan and elevation 18 Isometric end #1 19 Isometric end #2 20 Twin pin connector 21 Approval letter 22 Ph or visit January 2011 Page 2

3 Introduction TL-2 Plastic Water Filled Barrier made up of plastic units that when joined together using a steel connector and filled with water provide positive work zone barrier protection to temporary construction sites and other miscellaneous roadside activities. TL-2 Plastic Water Filled Barrier has been designed and tested to meet the evaluation criteria of NCHRP 350 Test Level 2 (TL-2) for a longitudinal barrier. When correctly installed it is capable of stopping, containing or redirecting an errant vehicle in a safe manner under NCHRP 350 impact conditions. TL-2 Plastic Water Filled Barrier is the world s first 100% polyethylene water filled barrier (no steel reinforcement) to have been judged to have satisfied the evaluation criteria of NCHRP 350 Test Level 2 (TL-2). The unique TL-2 Plastic Water Filled Barrier polyethylene composition, profile design and twin pin connector allow the barrier to be installed straight or down to a minimum radius of 28m if required. System overview TL-2 Plastic Water Filled Barrier is designed and constructed to provide acceptable structural adequacy, minimal occupant risk and safe trajectory as set forth in NCHRP 350 for longitudinal barriers. When impacted with an 820kg or 2000kg vehicle at speeds of up to 70kph and angles up to 25 degrees, the impacting vehicle is stopped, redirected or contained in a safe manner. Before installation Placement of TL-2 Plastic Water Filled Barrier shall be in accordance with the design as provided for the temporary work zone. Installation shall be in accordance with the installation instructions supplied for this product. Depending on the circumstances at the site, installation including the filling of a unit (using a truck mounted water tanker) should take no more than 1 minute for each 2.0m unit. TL-2 Plastic Water Filled Barrier is a highly engineered safety device made up of a relatively small number of parts. Before starting installation ensure that one is familiar with the make up of the system. Ph or visit January 2011 Page 3

4 Limitations and warnings Product Manual: TL-2 Plastic Water Filled Barrier TL-2 Plastic Water Filled Barrier has been rigorously tested and evaluated per the evaluation criteria in the NCHRP 350 guidelines for a longitudinal barrier. The impact conditions recommended in NCHRP 350 are intended to address typical in-service collisions. When properly installed and maintained TL-2 Plastic Water Filled Barrier allow an impacting vehicle to be stopped, contained or redirected in a safe and predictable manner under the NCHRP 350 impact conditions. Vehicle impacts that vary from the NCHRP 350 impact conditions described for longitudinal barriers may result in significantly different results than those experienced in testing. Vehicle impact characteristics different than, or in excess of, those encountered in NCHRP 350 testing (weight, speed and angle) may result in system performance that may not meet the NCHRP 350 evaluation criteria. TL-2 Plastic Water Filled Barrier can be installed with the ArmorZone End Treatment. If this treatment is not used then the end of the barrier must be shielded or flared as per NZTA requirements. Please contact CSP Pacific if you require further assistance. Safety statements General safety All required traffic safety precautions should be complied with. All workers should wear required safety clothing (high visibility vests, steel capped footwear, gloves etc.) Only authorised trained personnel should operate any machinery. Where overhead machinery is used, care must be taken to avoid any overhead hazards. Gloves should be worn at all times. Safety statements All installers must be well clear of the water tanker when the units are being filled. TL-2 Plastic Water Filled Barrier is a stand alone barrier and does not require at any stage during installation that the surrounding soil is dug or drilled in anyway. The empty units weigh 50kg each and should be unloaded by two personnel. Do not attempt to lift a unit which contains water. Final positioning of the empty units and placement of the steel connectors should be done by 1 personnel so as to remove the risk of hands and fingers being caught between the components. Ph or visit January 2011 Page 4

5 System design and design considerations Slopes A maximum slope of 1:10 is preferable. On slopes greater than this, follow the local road authorities guidelines. Kerbs As with all road side safety hardware, TL-2 Plastic Water Filled Barrier has been designed and tested so that the centre of gravity of the impacting vehicle is at a constant height in relation to the barrier. For this reason, it is preferred that kerbs or channels are not in front or behind the barrier as they will result in altering the height of the vehicle at impact. If there is no option but to install in front or behind of a kerb advice should be followed from the local authorities guidelines. Undulating ground conditions Site specific grading may be necessary to ensure that there are no humps or hollows that may significantly alter the impacting vehicles stability or substantially alter the barrier height in relation to the ground. Median and roadside applications TL-2 Plastic Water Filled Barrier can be used in both roadside and median applications. Length of need The length of need (LoN) of TL-2 Plastic Water Filled Barrier is 14m. Ensure that when installing the barrier that it is of sufficient length. For further details consult the local authority guidelines. Ph or visit January 2011 Page 5

6 Terminal end treatments TL-2 Plastic Water Filled Barrier is a free standing plastic barrier that if terminated inside the clear zone will require either an ArmorZone End Treatment fitted or the end of the barrier shielded or flared as per NZTA requirements. Soil conditions TL-2 Plastic Water Filled Barrier is installed above ground so soil conditions on site are not applicable. However it is recommended TL-2 Plastic Water Filled Barrier is installed on a compacted surface. Deflection Test kg pickup truck, 25 degree angle at 70kph Dynamic deflection Permanent deflection Working width 2.10m 2.10m 2.10m Test kg car, 20 degree angle at 70kph 1.05m 1.05m 1.05m Note: Results are from actual crash testing and the test article length was 50m. Results from Test 2-11 are the published TL-2 Deflection. Ph or visit January 2011 Page 6

7 Parts indentification Product Manual: TL-2 Plastic Water Filled Barrier 2.0m TL-2 Plastic Filled Barrier unit Twin Pin connector (100% polyethylene) (hot dipped galvanised) Bill of materials For every 2.0m (linear) of temporary barrier the following components are required: 2.0m TL-2 Plastic Water Filled Barrier unit 1 required Twin Pin steel connector 1 required Water 560 litres required Ph or visit January 2011 Page 7

8 Installation preparation Getting started Product Manual: TL-2 Plastic Water Filled Barrier It is essential that TL-2 Plastic Water Filled Barrier is installed correctly. Please carefully read and understand the following instructions before installing. Note: These instructions relate only to the installation of TL-2 Plastic Water Filled Barrier and are for standard installations only. TL-2 Plastic Water Filled Barrier is designed so that it has exactly the same components and barrier setup whether in a roadside or median application. For all installations, start at one end and connect the units together until the correct barrier length and position is achieved. Preparation Before installing TL-2 Plastic Water Filled Barrier, ensure that all components required for the system are on site and have been identified. TL-2 Plastic Water Filled Barrier are a highly engineered safety device made up of relatively small number of parts. Before starting installation ensure that one is familiar with the make up of the system. Refer to the Parts identification and Bill of materials section in this manual for more information. Ensure that the area where TL-2 Plastic Water Filled Barrier is to be installed is flat enough and compacted so that the ground conditions will not significantly alter the height of the vehicle in relation to the height of the barrier. Minor site grading may be required. Tools required There are no tools required to install the components of TL-2 Plastic Water Filled Barrier. The plastic units can be manually lifted and positioned by 2 personnel and the twin pin used to connect the units is simply dropped into position. Each unit requires approx 560L of water and it is recommended that a large truck mounted tanker is sourced for fast barrier construction. A hose of up to 100mm in diameter can be used to fill the units. Ph or visit January 2011 Page 8

9 Installation instructions Standard installation Step 1 Site preparation Product Manual: TL-2 Plastic Water Filled Barrier It is preferred that TL-2 Plastic Water Filled Barrier is installed on compacted flat, level ground. Ensure that sufficient width and traffic control is available before installing TL-2 Plastic Water Filled Barrier. Due to the bulky nature of the units, deployment will be from a flat deck truck or similar. Each unit requires 560L of water and it is recommended that a large truck mounted tanker is used. TL-2 Plastic Water Filled Barrier should be installed in a tangent position to the direction of travel. TL-2 Plastic Water Filled Barrier units are dispatched in stacks of 15 with a unique triple strapped configuration to ensure safe unloading of each different tier. (Shown in figure 1) Using a fork hoist or similar the rows of 5 units can be lowered to ground level and from there manually moved into position. (Shown in figure 2). Figure 1 Figure 2 Ph or visit January 2011 Page 9

10 Step 2 Placement of the barrier units Unload the units and set out in a row along the intended barrier position. Make sure the configuration of the ends will fit together where they join. (shown in Figure 3) Lifting the units is a 2 person job; they weigh 50kg each when empty. Slide the units into position. (Shown in figure 4). The units must fit flush together so that the vertical holes on each unit line up. (Shown in figure 5 & 6). Note: None of the units are fixed to the ground in any way. Figure 5 Figure 6 Ph or visit January 2011 Page 10

11 Step 3 Connecting the barrier units Once the units are flush fit aligned, the twin pin connector can be positioned down the 2 vertical alignment holes. (Shown in figure 7 & 8). The connector sits in the vertical holes under its own weight only and is not connected to the barrier units in any other way. Note: If slight curvature of the barrier is required, position as required at this point. Figure 7 Figure 8 Step 4 Filling the barrier units Lifting the flap on the top of the unit will allow access to the 125mm diameter Water Fill Hole. (Shown in figure 9). Using a truck mounted tanker fill each unit to the top with water. (Shown in figure 10). Check that there are no leaks before filling the next unit. If there is a leak the unit must be replaced. It may be possible to fix at a later stage depending on the damage. Figure 9 Figure 10 Ph or visit January 2011 Page 11

12 Installation examples Product Manual: TL-2 Plastic Water Filled Barrier TL-2 Plastic Water Filled Barrier Standard installation (straight) TL-2 Plastic Water Filled Barrier Standard Installation (curved) Note: A minimum 28m radius curvature can be achieved when the flush fit connection is made between TL-2 Plastic Water Filled Barrier units. This positioning should be done before the units are filled with water. Ph or visit January 2011 Page 12

13 TL-2 Plastic Water Filled Barrier Installation Y/N Y/N The units are positioned on level ground. The set-out of the barrier is as per the design instructions. The lugs of each unit have a flush fit with each other and the twin pin steel connector is positioned through both vertical holes in the lugs of each unit. The lid and bung are attached to each unit correctly so as to ensure the units will remain full of water as intended. Each unit is filled to the top with water. (approx 560L) Check for leaks. The barrier is not fixed to the ground or any other device in any way. The end of the barrier is installed with an AmorZone End Treatment or shielded/flared as per NZTA requirements. Location: Installed by: Inspected by: Date: Date: For more information contact CSP Pacific on Ph or visit Installation Checklist January

14 Maintenance and repair Maintenance Product Manual: TL-2 Plastic Water Filled Barrier TL-2 Plastic Water Filled Barrier is maintenance free. Although it is recommended that inspections are carried out on barriers that are installed for long periods of time. Each unit has a lid and filter assembly to ensure that the barrier is only filled with water. However, in extreme conditions it may be possible for evaporation to take place and it is important that the units remain full. Repair After a typical impact Recommended tools: Flat deck truck A truck mounted water tanker A crow bar or similar Replacement parts required for a severe impact: TL-2 Plastic Water Filled Barrier units Steel Twin Pin connectors 560l of water for each unit Key steps: Separate the damaged components by removing the steel connector. Drain any units that are partially damaged. Assess which components are damaged and replace with new parts accordingly. Connect replacement units to the undamaged section of the barrier and align as required. Fit the replacement steel connectors between each unit. Fill all the units with water. For further information consult TL-2 Plastic Water Filled Barrier - Installation Instructions section in this Product Manual. After fire damage TL-2 Plastic Water Filled Barrier is made of polyethylene and joined together using steel connectors. It is possible that under extreme conditions, like Australian bushfires, that the components of the system can be damaged. If this is the case replace the components as described above and as outlined in TL-2 Plastic Water Filled Barrier Installation Instructions. Ph or visit January 2011 Page 14

15 Frequently asked questions Product Manual: TL-2 Plastic Water Filled Barrier 1) What type of equipment is required to install TL-2 Plastic Water Filled Barrier? The units are 50kg each when empty so can be unloaded and positioned by hand by 2 personnel. To connect the units together a steel connector is used and again fitted manually. Each unit requires approx 560L of water so it is recommended that a truck mounted water tanker is available. 2) Does your company provide spare parts? What is the lead-time for supply? It is important to fix a damaged barrier as soon as possible because it most probably won t perform as required when damaged. Replacement components are available from CSP Pacific and can be available between 1 and 3 working days. 3) On average, how long does it take to install a TL-2 Plastic Water Filled Barrier? Depending on the application and circumstances at the site, installation and assembly of the system should take a 2 person crew approx. 1 hour to install a 120m section. 4) What about vandalism, can TL-2 Plastic Water Filled Barrier be easily damaged? The units are constructed using a very strong polyethylene and would not easily be damaged. The construction is similar to other water filled barriers and this is not considered an issue. 5) How easily can TL-2 Plastic Water Filled Barrier be restored after impact? The system is made up of very few components and is a modular so easily repaired. A flat deck truck, crow bar and water tanker will be required to reinstate. 6) What maintenance does TL-2 Plastic Water Filled Barrier require? TL-2 Plastic Water Filled Barrier barrier is maintenance free barrier. For barriers installed for long periods of time and in extreme conditions, cyclic checks may be required to check that the units remain full of water. 7) What is the deflection of TL-2 Plastic Water Filled Barrier? The maximum deflection recorded during actual crash testing at TL-2 was 2.1m. 8) What is TL-2 Plastic Water Filled Barrier connected to? TL-2 Plastic Water Filled Barrier is a free standing system and neither anchored or connected to other systems. 9) Is the performance of TL-2 Plastic Water Filled Barrier jeopardised when the water is frozen? Testing on the TL-2 Plastic Water Filled Barrier has been carried out only with water in a liquid state and CSP Pacific believe the performance of the barrier may not be as intended if the water freezes. If conditions are below zero degrees the following additives will reduce the temperature at which the barrier will freeze. For percentages required, cost, environmental impact and reduced temperature consultation will be required with a third party. Sodium Chloride, Calcium Chloride, Ethylene/Propylene Glycol, Liquid CMA and Liquid Potassium Acetate. Ph or visit January 2011 Page 15

16 Note: There is no internal steel in TL-2 Plastic Water Filled Barrier so if used corrosion is not an issue. 10) Can TL-2 Plastic Water Filled Barrier units be moved when full? It is possible and extreme care must be taken, a full unit weighs 610kg. Each unit is equipped with fork hoist holes through the barrier and must be used with the appropriate machinery and safety equipment. Ph or visit January 2011 Page 16

17 Crash test results summary Product Manual: TL-2 Plastic Water Filled Barrier A total of 2 official crash tests where completed on the TL-2 Plastic Water Filled Barrier to NCHRP 350 Test 2-10 Test Article TL-2 Plastic Water Filled Barrier (length 50mm) Post Spacing n/a Test Vehicle. Speed Impact Angle 820 kg Car (820C) 70 kph 20 deg Test 2-11 Test Article TL-2 Plastic Water Filled Barrier (length 50mm) Post Spacing n/a Test Vehicle. Speed Impact Angle 2000 kg Car (2000P) 70 kph 25 deg For both tests the vehicles where safely redirected by the TL-2 Plastic Water Filled Barrier. The vehicles did not penetrate, underride or override the test installations. The test article was judged to have satisfied the requirements of NCHRP Report 350 criteria TL-2. Ph or visit January 2011 Page 17

18 Appendix Technical drawings Plan and elevation Ph or visit January 2011 Page 18

19 Isomeric end #1 Ph or visit January 2011 Page 19

20 Isomeric end # 2 Ph or visit January 2011 Page 20

21 Twin Pin steel connector Ph or visit January 2011 Page 21

22 July 2010 Interim Acceptance for Safety Barrier Product Product: Armorflex P2 TL-2 Plastic Barrier Safety Barrier - Temporary Expiry Date: 30 June 2011 The Armorflex P2 TL-2 plastic barrier system has been tested in accordance with NCHRP Report 350 and is deemed to comply with the required evaluation criteria for Test Level 2 (TL-2). Pending further updates to the NZTA s M23 Specification for Roads Safety Barrier Systems, the Armorflex P2 system is granted interim acceptance by the New Zealand Transport Agency for use on the state highway network, with the following conditions: Product Identification Conditions of Use The Armorflex P2 temporary barrier system must be installed and maintained in accordance with the product installation/maintenance manual and relevant NZTA specifications. NZTA specifications and standards shall prevail where there is discrepancy between the product manual(s) and the NZTA specifications and standards. Installers must ensure that they are familiar with relevant conditions, requirements and limitations of the system, particularly with regard to the appropriate length of need, minimum installation length and test deflection. Vehicle impacts that vary from the NCHRP Report 350 impact conditions may result in significantly different results than those experienced in testing.

23 The Armorflex P2 temporary barrier system has been evaluated in accordance with the Test Level 2 criteria presented in NCHRP Report 350 under the following test conditions: 820kg small car impacting at an angle of 20º and a nominal speed of 70kph; 2,000kg pick-up truck impacting at an angle of 25º and a nominal speed of 70kph. Units MUST be connected with the appropriate steel connecting pin and filled with water when in use. Since there is currently no crashworthy terminal for the Armorflex P2, its ends should be flared away from approaching traffic or adequately shielded. A copy of this Interim Acceptance Letter must be appended to the Installation Manual. Expiry of Acceptance This acceptance expires on 30 June 2011 and replaces any previous acceptance. New installations of the Armorflex P2 must not be deployed on the state highway network after the expiry date of acceptance unless a further period of acceptance is granted or the product has been formally included in the M23 Specification for Roads Safety Barrier Systems, in which case the M23 specification would replace this interim acceptance. The New Zealand Transport Agency reserves the right to rescind or modify, at any time, acceptance of the Armorflex P2 temporary barrier system. Authorised by the National Traffic and Safety Manager 2

ArmorZone TL-2 Barrier

ArmorZone TL-2 Barrier ArmorZone TL-2 Barrier Product Manual ANOTHER AMORFLEX DEVELOPMENT Table of contents Introduction 3 System overview 3 Before installation 3 Limitations and warnings 4 Safety statements 4 System design

More information

ArmorZone TL-2 Barrier and End Treatment

ArmorZone TL-2 Barrier and End Treatment ArmorZone TL-2 Barrier and End Treatment Product and Installation Manual ANOTHER AMORFLEX DEVELOPMENT Table of contents Introduction 3 System Overview 3 Before Installation 3 Limitations and Warnings 4

More information

Product Manual Release 05/17

Product Manual Release 05/17 Temporary Safety Barrier (TL-2 MASH) Product Manual VHD (v3) www.valmonthighway.com Table of Contents 1.0 ArmorZone Introduction... 3 2.0 Before Installation... 3 3.0 Limitations & Warnings... 3 4.0 System

More information

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2)

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2) Installation Manual Orion TL-3 Steel Barrier VHD (v2) 300914 Table of Contents Orion Introduction.......... 3 Limitations & Warnings. 4 Before Installation..... 3 System Design & Design Considerations

More information

INSTALLATION MANUAL ORION BARRIER. NCHRP 350 TL-3 Portable Steel Longitudinal Barrier

INSTALLATION MANUAL ORION BARRIER. NCHRP 350 TL-3 Portable Steel Longitudinal Barrier INSTALLATION MANUAL ORION BARRIER NCHRP 350 TL-3 Portable Steel Longitudinal Barrier INSTALLATION AND MAINTENANCE MANUAL Table of Contents Orion Introduction.......... 3 System Overview..... 3 Before Installation....

More information

Universal Armorwire Terminal End

Universal Armorwire Terminal End Installation Manual Universal Armorwire Terminal End Anchoring for 3 & 4 Cable Barriers VHD (v2) 300914 Table of Contents Universal A.T.E Introduction.. 3 Limitations and Warnings.... 3 Before Installation..

More information

ArmorWire Cable Barrier

ArmorWire Cable Barrier Installation Manual ArmorWire Cable Barrier TL-3 & TL-4 Systems VHD (v2) 300914 Table of Contents ArmorWire Introduction......... 3 Limitations and Warnings... 3 Before Installation. 3 Design Considerations......

More information

Nu-Guard 31. Roadside and Median Guardrail System. MASH TL-3 & NCHRP TL-4 Product & Installation Manual

Nu-Guard 31. Roadside and Median Guardrail System. MASH TL-3 & NCHRP TL-4 Product & Installation Manual Nu-Guard 31 Roadside and Median Guardrail System MASH TL-3 & NCHRP TL-4 Product & Installation Manual Ph 0800 655 200 or visit www.csppacific.co.nz April 15 / Page 1 Table of Contents NU-GUARD 31 Introduction......

More information

Sentryline II Cable Barrier

Sentryline II Cable Barrier Product Manual Sentryline II Cable Barrier TL-3-3 Cable & TL-4-4 Cable Systems Proudly distributed by BJM(v6) 120210 ANOTHER ARMORFLEX DEVELOPMENT Table of Contents Sentryline II Introduction 3 Deflection..

More information

SLED End Treatment System Manual

SLED End Treatment System Manual SLED End Treatment System Manual PN 45045 Revision A (Dated 03/14/11) Table of Contents IMPORTANT: Read and understand ALL installation instructions before attempting to install the SLED End Treatment

More information

Sentry Water-Cable Barrier Installation, Maintenance, and Repair Manual

Sentry Water-Cable Barrier Installation, Maintenance, and Repair Manual Sentry Water-Cable Barrier Installation, Maintenance, and Repair Manual TL-1, TL-2 and TL-3 Rated Longitudinal Barrier and Longitudinal Channelizing Device Designed without the need for an external attached

More information

Product Manual: ABSORB 350 Crash Cushion ABSORB 350. Crash Cushion. Product Manual. Ph or visit

Product Manual: ABSORB 350 Crash Cushion ABSORB 350. Crash Cushion. Product Manual. Ph or visit ABSORB 350 Crash Cushion Product Manual Ph 0800 655 200 or visit www.csppacific.co.nz June 10/ Page 1 Table of Contents Information brochure...p. 3 Benefits of...p. 4 Where to use...p. 5 System configuration...p.

More information

Universal TAU-II Redirective, Non-Gating, Crash Cushion

Universal TAU-II Redirective, Non-Gating, Crash Cushion TB 010925 Rev. 2 Page 1 of 10 Product Specification Universal TAU-II Redirective, Non-Gating, Crash Cushion I. General The Universal TAU-II system is a Redirective, Non-Gating Crash Cushion in accordance

More information

Sentryline Terminal End III Non-Release Terminal End. Anchoring for 4 cable barrier system. Training and Product Installation Manual

Sentryline Terminal End III Non-Release Terminal End. Anchoring for 4 cable barrier system. Training and Product Installation Manual Sentryline Terminal End III Non-Release Terminal End Anchoring for 4 cable barrier system Training and Product Installation Manual Please call Australian Construction Products on 02 8708 4400 or visit

More information

BarrierGuard 800 Gate

BarrierGuard 800 Gate BarrierGuard 800 Gate Product Manual Australia & New Zealand NCHRP 350 TL-3 Assembly, Installation & Operation Revision History Revision Date Prepared by Approved by Reason for change 1a 22 nd July 2015

More information

DESIGN GUIDE. Advancing Safety Through Innovation. TCC-DG01 07/18/02 Page 1

DESIGN GUIDE. Advancing Safety Through Innovation. TCC-DG01 07/18/02 Page 1 DESIGN GUIDE Advancing Safety Through Innovation Patents Pending Copyright 2002 BSI TCC-DG01 07/18/02 Page 1 TAU-II Crash Cushion DESIGN Table of Contents Preface 22 Introduction 2 Important Information..

More information

T-39 Thriebeam. Product Manual. NCHRP 350 Test Level 3 & 4 Compliant Barrier. Release 01/11

T-39 Thriebeam.  Product Manual. NCHRP 350 Test Level 3 & 4 Compliant Barrier. Release 01/11 T-39 Thriebeam NCHRP 350 Test Level 3 & 4 Compliant Barrier Product Manual T-39 is licensed to Ingal Civil Products by Trinity Industries Inc. of the U.S.A. www.ingalcivil.com.au T-39 Thriebeam NCHRP 350

More information

RAMSHIELD. New Zealand Edition. Product & Installation Manual. MASH TL3 Compliant W-Beam Barrier. Ref: PM 023/0

RAMSHIELD. New Zealand Edition. Product & Installation Manual. MASH TL3 Compliant W-Beam Barrier. Ref: PM 023/0 RAMSHIELD MASH TL3 Compliant W-Beam Barrier Product & Installation Manual New Zealand Edition Ref: PM 023/0 Table of Contents 1.0 Introduction... 5 2.0 Specifications... 5 3.0 How RAMSHIELD Works... 6

More information

NOTES ON THE SPECIFICATION FOR ROAD SAFETY BARRIER SYSTEMS

NOTES ON THE SPECIFICATION FOR ROAD SAFETY BARRIER SYSTEMS 1. INTRODUCTION A road safety barrier is considered to be a hazard and should only be used when the consequences of hitting it are less than the hazard/object which it is shielding. The use of a road safety

More information

BarrierGuard 800 Gate

BarrierGuard 800 Gate Product and Installation Manual BarrierGuard 800 Gate NCHRP 350 TL-3 Australia & New Zealand Rev. A 06/17 2018 Highway Care Limited. All Rights Reserved. Page 1 of 23 Revision History Revision Date Prepared

More information

Safeguard Gate. Safety Barrier. Product Manual. Safeguard Gate Safety Barrier: Product Manual

Safeguard Gate. Safety Barrier. Product Manual. Safeguard Gate Safety Barrier: Product Manual Safeguard Gate Safety Barrier Product Manual Ph 0800 655 200 or visit www.csppacific.co.nz 30-Oct-07 / Page 1 Table of Contents Safeguard Gate Safety Barrier: Product Manual Information Brochure... p.

More information

Specification for Road Safety Hardware Systems

Specification for Road Safety Hardware Systems Specification for Road Safety Hardware Systems APPENDIX C: TEMPORARY ROAD SAFETY BARRIER SYSTEMS February 2018 Prepared for NZTA by Parallaxx Ltd NZTA M23C 2017 INTRODUCTION AND REFERENCES This hardware

More information

TRACC. Crash Attenuation Cushion. Product Manual

TRACC.   Crash Attenuation Cushion. Product Manual TRACC Crash Attenuation Cushion Product Manual Release 07/15 TRACC is licensed to Ingal Civil Products by Trinity Industries Inc. of the U.S.A. www.ingalcivil.com.au TRACC Crash Attenuation Cushion 1.0

More information

TRACC. Crash Attenuation Cushion. Product Manual

TRACC.  Crash Attenuation Cushion. Product Manual TRACC Crash Attenuation Cushion Product Manual Release 08/16 TRACC is licensed to Ingal Civil Products by Trinity Industries Inc. of the U.S.A. www.ingalcivil.com.au TRACC Crash Attenuation Cushion 1.0

More information

TRACC. Product Manual. Crash attenuation cushion. Release 10/14

TRACC.  Product Manual. Crash attenuation cushion. Release 10/14 TRACC Crash attenuation cushion Product Manual Release 10/14 TRACC is licensed to Ingal Civil Products by Trinity Industries Inc. of the U.S.A. www.ingalcivil.com.au TRACC Crash attenuation cushion 1.0

More information

Product Specification ArmorGuard Barrier System

Product Specification ArmorGuard Barrier System TB 081030 Rev. 0 Page 1 of 6 Product Specification ArmorGuard Barrier System I. General The ArmorGuard Barrier System is a longitudinal barrier, as defined in the AASHTO Roadside Design Guide, which can

More information

BarrierGuard (02) GROUP. a new era in road safety

BarrierGuard (02) GROUP. a new era in road safety BarrierGuard a new era in road safety 800 GROUP (02) 9425 3000 The BarrierGuard 800 a new generation of state-of-the-art design The BarrierGuard 800 heralds a new era in road safety technology. This new

More information

ARMOR-BLOCK. Installation guide. Installation Manual: ARMOR-BLOCK Retaining Wall System. Cap Block. Exposed void for planting.

ARMOR-BLOCK. Installation guide. Installation Manual: ARMOR-BLOCK Retaining Wall System. Cap Block. Exposed void for planting. ARMOR-BLOCK Installation guide Cap Block Exposed void for planting In situ soil Engineered backfill Compacted and prepared base Setback Lip Ph 0800 655 00 or visit www.csppacific.co.nz 19 February 08 /

More information

Technical Memorandum: Road Safety Hardware Series. technical memorandum

Technical Memorandum: Road Safety Hardware Series. technical memorandum technical memorandum road safety hardware series Frequently Asked Questions - Barriers & Terminals TM-2000 October 2012 Purpose To provide a list of frequently asked questions with answers in regard to

More information

February 9, In Reply Refer To: HSST/CC-114

February 9, In Reply Refer To: HSST/CC-114 Mr. Geoff Maus Chief Design Engineer TrafFix Devices, Inc. 160 Avenida La Pata San Clemente, California 92673 Dear Mr. Maus: February 9, 2011 1200 New Jersey Ave., SE Washington, D.C. 20590 In Reply Refer

More information

In-Ground Removable Bollard PRODUCT MANUAL. Installation Operation Maintenance

In-Ground Removable Bollard PRODUCT MANUAL. Installation Operation Maintenance PRODUCT MANUAL In-Ground Removable Bollard Installation Operation Maintenance Access Technologies (WA) Pty Ltd PO Box 1060 GWELUP DC WA 6018 Email: ask-us@accesstechnologies.com.au Phone: +61-(0)8-6305

More information

Installation and Repair Manual

Installation and Repair Manual Trinity Attenuating Crash Cushion Installation and Repair Manual An NCHRP Report 350 Crash Cushion CSP Pacific Business Unit of Fletcher Concrete & Infrastructure Limited 306 Neilson Street Onehunga, Auckland

More information

High Performance. Cost Effective. Easy Installation.

High Performance. Cost Effective. Easy Installation. High Performance Cost Effective Easy Installation 1 www.highwaycareint.com Testing & Approval BarrierGuard 800 has been tested to meet the highest performance standards in the world, passing both the American

More information

ADA-COMPLIANT SAFETY DEVICES PRODUCT GUIDE. SafetyRail TM Barricade SafetyWall TM Barricade BoardWalk Temporary RAMP

ADA-COMPLIANT SAFETY DEVICES PRODUCT GUIDE. SafetyRail TM Barricade SafetyWall TM Barricade BoardWalk Temporary RAMP ADA-COMPLIANT SAFETY DEVICES PRODUCT GUIDE SafetyRail TM Barricade SafetyWall TM Barricade BoardWalk Temporary RAMP SafetyWall TM ADA-COMPLIANT PEDESTRIAN BARRICADE Ideal for creating accessible work zones.

More information

AS THE EFFECT ON BRIDGE BARRIERS

AS THE EFFECT ON BRIDGE BARRIERS ABSTRACT AS5100.2 2017 THE EFFECT ON BRIDGE BARRIERS David Coe, Senior Principal, Pitt & Sherry The revision to AS5100 in 2017 resulted in significant changes to the design loading and impact heights for

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: ROADWAY SAFETY FEATURES SPECIFIC SUBJECT: NCHRP 350 TEST REQUIREMENTS LOCATION

More information

Subject: ACTION: National Cooperative Highway Research Program (NCHRP) Report 350 Hardware Compliance Dates

Subject: ACTION: National Cooperative Highway Research Program (NCHRP) Report 350 Hardware Compliance Dates Memorandum - FHWA Safety Program Page 1 of 2 Memorandum US Department of Transportation Federal Highway Administration Subject: ACTION: National Cooperative Highway Research Program (NCHRP) Report 350

More information

Work Zone Positive Protection Toolbox

Work Zone Positive Protection Toolbox Work Zone Positive Protection Toolbox This booklet serves as a toolbox to describe various types of positive protection devices currently in use and provides guidance on where and how each is typically

More information

ROADSIDE SAFETY BARRIER ELEMENTS Module 3

ROADSIDE SAFETY BARRIER ELEMENTS Module 3 2 ROADSIDE SAFETY BARRIER ELEMENTS Module 3 3 Roadside Design Options 4 Expected Crash Reduction of Relocation of Fixed Objects Source: NCHRP Report 500, Vol 6, Exhibit V-26 Purpose of Safety Barriers

More information

ADA-COMPLIANT SAFETY DEVICES PRODUCT GUIDE. SafetyRail TM Barricade SafetyWall TM Barricade BoardWalk Temporary RAMP

ADA-COMPLIANT SAFETY DEVICES PRODUCT GUIDE. SafetyRail TM Barricade SafetyWall TM Barricade BoardWalk Temporary RAMP ADA-COMPLIANT SAFETY DEVICES PRODUCT GUIDE SafetyRail TM Barricade SafetyWall TM Barricade BoardWalk Temporary RAMP SafetyWall TM ADA-COMPLIANT PEDESTRIAN BARRICADE Ideal for creating accessible work zones.

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR MOVABLE CONCRETE TRAFFIC BARRIER

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR MOVABLE CONCRETE TRAFFIC BARRIER MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR MOVABLE CONCRETE TRAFFIC BARRIER C&T:JKG 1 of 5 C&T:APPR:JAR:EMB:02-10-04 a. Description. Furnish, install, operate, and maintain the Moveable

More information

BarrierGuard 800. Temporary Steel Safety Barrier NCHRP 350 TL-3 & TL-4. Product and Installation manual

BarrierGuard 800. Temporary Steel Safety Barrier NCHRP 350 TL-3 & TL-4. Product and Installation manual BarrierGuard 800 Temporary Steel Safety Barrier NCHRP 350 TL-3 & TL-4 Product and Installation manual Ph 0800 655 200 or visit www.csppacific.co.nz May 2012 / Page 1 Table of Contents Application Guide.........

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: ROADWAY SAFETY FEATURES SPECIFIC SUBJECT: NCHRP 350 TEST REQUIREMENTS LOCATION

More information

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August Double Slide Rail August 2015 1 DOUBLE SLIDE RAIL INSTALLATION METHOD Introduction Slide rail shoring systems can be used for trenches up to 12m wide and 6m deep. Module length is determined by panels

More information

Chapter 4 Bridge Program Drawings

Chapter 4 Bridge Program Drawings Chapter 4 Bridge Program Drawings Section 4.10-Bridge Railing Introduction Steel bridge railing and concrete bridge barrier rail are installed along the edge of the bridge roadway to keep errant vehicles

More information

NOTES FOR THE PERFORMANCE BASED SPECIFICATION FOR TRAFFIC SIGNS

NOTES FOR THE PERFORMANCE BASED SPECIFICATION FOR TRAFFIC SIGNS CONTENTS NOTES FOR THE PERFORMANCE BASED SPECIFICATION FOR TRAFFIC SIGNS 1. SCOPE... 2 2. RELATED DOCUMENTS... 2 3. DEFINITIONS... 2 4. COMPLIANCE... 2 5. SIGN FACE DESIGN... 3 6. VISIBILITY... 3 6.1 Performance

More information

BarrierGuard 800. Temporary Steel Safety Barrier NCHRP 350 TL-3 & TL-4. Product and Installation Manual

BarrierGuard 800. Temporary Steel Safety Barrier NCHRP 350 TL-3 & TL-4. Product and Installation Manual Product & Installation Manual : BarrierGuard 800 BarrierGuard 800 Temporary Steel Safety Barrier NCHRP 350 TL-3 & TL-4 Product and Installation Manual Ph 0800 655 200 or visit www.csppacific.co.nz July

More information

TRACC-Family System Manual

TRACC-Family System Manual Trinity Attenuating Crash Cushion TRACC-Family System Manual A Family of NCHRP Report 350 Crash Cushions Trinity Industries, Inc. 2525 Stemmons Freeway Dallas, Texas 75207 U.S. Calls: (800)-644-7976 International

More information

MDS TL4 Minimum Deflection Systems

MDS TL4 Minimum Deflection Systems MDS Approvals FHWA NCHRP 350 MASH-08 EN1317 H2 Bridge & Road STEEL BARRIER SYSTEMS Page 1 V11 Run-off-road crashes are one of the most common types of crashes in urban and highway environments. Installing

More information

SMART CUSHION INNOVATIONS SCI100GM General Specifications

SMART CUSHION INNOVATIONS SCI100GM General Specifications SMART CUSHION INNOVATIONS SCI100GM General Specifications DESCRIPTION: The SCI100GM is a redirective, non-gating crash attenuator that consists of a base, supporting frames, a sled, side panels, a wire

More information

INSTALLATION AND MAINTENANCE MANUAL ABSORB 350 BARRIER. NCHRP 350 TL-3 Non-Redirective Crash Cushion

INSTALLATION AND MAINTENANCE MANUAL ABSORB 350 BARRIER. NCHRP 350 TL-3 Non-Redirective Crash Cushion INSTALLATION AND MAINTENANCE MANUAL ABSORB 350 BARRIER NCHRP 350 TL-3 Non-Redirective Crash Cushion Installation and Maintenance MANUAL PATENTS PENDING Table of Contents INSTALLATION MANUAL Preface 2 Introduction

More information

PN Revision D January SoftStop. System. End Terminal. Product Manual

PN Revision D January SoftStop. System. End Terminal. Product Manual PN 10007556 Revision D SoftStop End Terminal Product Manual System SoftStop System Tangent End Terminal The SoftStop System Tangent End Terminal ( SoftStop System ) has been tested to American Association

More information

Instructions. Slim temporary safety barriers SB 50 Installation and Maintenance Manual. Documentation for license partners

Instructions. Slim temporary safety barriers SB 50 Installation and Maintenance Manual. Documentation for license partners Slim temporary safety barriers SB 50 Installation and Maintenance Manual Documentation for license partners General information 2 Planning 3 Installation 4 Special elements 7 Procedures after an impact

More information

CONSTRUCTION SPECIFICATION FOR ENERGY ATTENUATORS

CONSTRUCTION SPECIFICATION FOR ENERGY ATTENUATORS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 723 NOVEMBER 2011 CONSTRUCTION SPECIFICATION FOR ENERGY ATTENUATORS TABLE OF CONTENTS 723.01 SCOPE 723.02 REFERENCES 723.03 DEFINITIONS 723.04 DESIGN

More information

MDS TL5 Minimum Deflection Systems

MDS TL5 Minimum Deflection Systems MDS Minimum Deflection Systems Approvals FHWA NCHRP 350 MASH EN1317 H4 MDS BARRIERS Bridge & Road STEEL BARRIER SYSTEMS Page Page 1 1 V11 MDS BARRIERS Run-off-road crashes are one of the most common types

More information

INGAL CIVIL PRODUCTS. Product Manual. Release 01/18.

INGAL CIVIL PRODUCTS. Product Manual. Release 01/18. Product Manual www.ingalcivil.co.nz 1.0 Introduction 2.0 Specifications Introducing Ezy-Guard HC, a member of the Ezy-Guard family, the next generation steel guardrail barrier providing superior motorist

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

Instructions for the use of the Link 4 Pallet Rack Lifter (PRL) model 5000

Instructions for the use of the Link 4 Pallet Rack Lifter (PRL) model 5000 Instructions for the use of the Link 4 Pallet Rack Lifter (PRL) model 5000 (How to move your pallet racking using the Link 4 Pallet Rack Lifter) This process is for a typical rack move and reset. Each

More information

Design and Testing of an Easy to Use Pinned-down Temporary Concrete Barrier with Limited Deflections

Design and Testing of an Easy to Use Pinned-down Temporary Concrete Barrier with Limited Deflections 12 th International LS-DYNA Users Conference Automotive(1) Design and Testing of an Easy to Use Pinned-down Temporary Concrete Barrier with Limited Deflections Nauman M. Sheikh and Roger P. Bligh Texas

More information

Speedlock Pallet Racking

Speedlock Pallet Racking Assembly specification These instructions are to assemble Dexion Speedlock Pallet Racking which conforms with the specifications below. Frame heights not more than 4800mm Frame depths 840mm Not less than

More information

Corporate Safety Procedure Grid Mesh, Handrail and Flooring Removal. Table of Contents

Corporate Safety Procedure Grid Mesh, Handrail and Flooring Removal. Table of Contents Table of Contents 1. Purpose... 2 2. Scope... 2 3. Roles and Responsibilities... 2 3.1 Manager/Supervisor... 2 3.2 Workers... 2 3.3 Technical Specialist/Engineer... 2 4. Definitions... 2 5. Procedure...

More information

QuadGuard System. General Specifications. CEN General Specifications

QuadGuard System. General Specifications. CEN General Specifications QuadGuard System General Specifications CEN General Specifications QuadGuard System GENERAL SPECIFICATIONS I. GENERAL All QuadGuard Systems shall be designed and manufactured by Energy Absorption Systems,

More information

Product Manual REACT 350 (36") (3 foot [915 mm] wide Systems) Reusable Energy Absorbing Crash Terminal

Product Manual REACT 350 (36) (3 foot [915 mm] wide Systems) Reusable Energy Absorbing Crash Terminal (3 foot [915 mm] wide Systems) Reusable Energy Absorbing Crash Terminal Self-Restoring, Reusable Crash Cushions for Narrow Hazards ENERGY ABSORPTION SYSTEMS, INC. A Quixote Company Saving Lives By Design

More information

Barriers, Parapets, and Railings

Barriers, Parapets, and Railings Barriers, Parapets, and Railings Arielle Ehrlich State Bridge Design Engineer May 17, 2017 Bridge Office mndot.gov/bridge MnDOT Vocabulary Is it a barrier, a parapet or a railing? BARRIER. It is concrete

More information

CONSTRUCTION SPECIFICATION FOR GUIDE RAIL END TREATMENT - STEEL BEAM ENERGY ATTENUATING TERMINAL SYSTEMS

CONSTRUCTION SPECIFICATION FOR GUIDE RAIL END TREATMENT - STEEL BEAM ENERGY ATTENUATING TERMINAL SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 732 APRIL 2017 CONSTRUCTION SPECIFICATION FOR GUIDE RAIL END TREATMENT - STEEL BEAM ENERGY ATTENUATING TERMINAL SYSTEMS TABLE OF CONTENTS 732.01

More information

Road Safety. Zoneguard MASS. Column Mounted Floor Mounted Flexible Rigid

Road Safety. Zoneguard MASS. Column Mounted Floor Mounted Flexible Rigid Brifen Bridge Rail High Mast Zoneguard MASS Column Mounted Floor Mounted Flexible Rigid Engineering In House Design Service On Site Visit Training and Accreditation Technical Support About Us Our products

More information

Strengthened Soil Wall Construction Manual

Strengthened Soil Wall Construction Manual Strengthened Soil Wall Construction Manual This information has been prepared by Shaw Technologies, Inc. as an aid in constructing their Strengthened Soil Wall system. Final determination of the suitability

More information

Miller Collective Safety at Height Solutions EPIC ULTRA Barrier System EPIC Post-N-Barrier System EPIC Basic Barrier System

Miller Collective Safety at Height Solutions EPIC ULTRA Barrier System EPIC Post-N-Barrier System EPIC Basic Barrier System For over 65 years the Miller brand has been synonymous with personal fall protection products and services. As the global leader in safety at height solutions, Honeywell Safety Products introduces a new

More information

Delta Level 1000 Hinged Lip Pit Mounted & Suspended Frame Dock Leveller

Delta Level 1000 Hinged Lip Pit Mounted & Suspended Frame Dock Leveller Delta Level 1000 Hinged Lip Pit Mounted & Suspended Frame Dock Leveller Product Description The Delta Level 1000 is one of our ranges of hinged lip dock levellers. Dock levellers are indispensable for

More information

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.MUNI 616 APRIL 2018 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03 DEFINITIONS

More information

DESIGN BULLETIN #75/2012 (Rewritten October 2016)

DESIGN BULLETIN #75/2012 (Rewritten October 2016) DESIGN BULLETIN #75/2012 (Rewritten October 2016) Alberta Roadside Design Guide High Tension Cable Barrier System Median and Roadside Installation October 27, 2016 Rewrite of Design Bulletin #75/2012 April

More information

Brifen Wire Rope Safety Barrier TL-3 & TL-4

Brifen Wire Rope Safety Barrier TL-3 & TL-4 Brifen Wire Rope Safety Barrier TL-3 & TL-4 Product and Installation Manual Ph 0800 655 200 or visit www.csppacific.co.nz June 2012 / Page 1 Table of Contents Background 3 Design Considerations 4 Design

More information

2016 MUTCD CONCEPT TTC COMMENTS. Michael A. Chacon Traffic Operations Division

2016 MUTCD CONCEPT TTC COMMENTS. Michael A. Chacon Traffic Operations Division 2016 MUTCD CONCEPT TTC COMMENTS Michael A. Chacon Traffic Operations Division MUTCD 4 Ballot items were discussed at the June 2014 meeting in TTC, as well as additional topics. TTC No. 1 Pedestrian and

More information

TEMPORARY EDGE PROTECTION SYSTEM DESCRIPTION CTS. Combisafe International AB

TEMPORARY EDGE PROTECTION SYSTEM DESCRIPTION CTS. Combisafe International AB TEMPORARY EDGE PROTECTION SYSTEM DESCRIPTION CTS Combisafe International AB CTS Combisafe International AB Contents Safety instructions... 3 Important... 4 General... 4 Data... 5 Safety posts 4140/4145/4150...

More information

B STEEL BEAM GUIDE RAIL - OPSS.PROV 721

B STEEL BEAM GUIDE RAIL - OPSS.PROV 721 B721-2 - - OPSS.PROV 721 721-2.1 GENERAL Steel beam guide rail (SBGR) is a semi-rigid barrier system which restrains and redirects vehicles by a combination of beam bending (W-shaped steel section), tension,

More information

GUARDSAFE providing adaptable solutions for more than 30 years

GUARDSAFE providing adaptable solutions for more than 30 years GUARDSAFE providing adaptable solutions for more than 30 years There are a lot of barriers in the marketplace now, but ours started it all. Remcon Plastics has been creating high-quality, durable roto-molded

More information

Alberta Transportation Roadside Design Guide February 2012 APPENDIX E GUIDELINES FOR THE SELECTION AND DESIGN OF HIGH TENSION CABLE BARRIER SYSTEMS

Alberta Transportation Roadside Design Guide February 2012 APPENDIX E GUIDELINES FOR THE SELECTION AND DESIGN OF HIGH TENSION CABLE BARRIER SYSTEMS Roadside Design Guide February 2012 GUIDELINES FOR THE SELECTION AND DESIGN OF HIGH TENSION CABLE BARRIER SYSTEMS COVER PAGE February 2012 Roadside Design Guide THIS PAGE INTENTIONALLY LEFT BLANK COVER

More information

Precast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS

Precast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS Precast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS GENERAL INSTALLATION INSTRUCTIONS 1 Ensure that the trench where the channels are going to be installed has enough room for the appropriate

More information

Specification for Road Works Series Road Restraints Systems (Vehicle and Pedestrian)

Specification for Road Works Series Road Restraints Systems (Vehicle and Pedestrian) Specification for Road Works Series 400 - Road Restraints Systems (Vehicle and Pedestrian) CC-SPW-00400 March 2013 CC Construction & Commissioning Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS

More information

Multi-Fab sells to registered dealers only; however, we can assist in finding you a dealer.

Multi-Fab sells to registered dealers only; however, we can assist in finding you a dealer. ATTACHMENTS This term refers to implements that can be added to a fork truck for handling a load. Attachments such as clamps, slip sheet forks and carpet poles can have an effect on capacity and should

More information

SECTION 616 TEMPORARY TRAFFIC CONTROL

SECTION 616 TEMPORARY TRAFFIC CONTROL SECTION 616 TEMPORARY TRAFFIC CONTROL 616.1 Description. This work shall consist of furnishing, installing, operating, maintaining, cleaning, relocating and removing temporary traffic control devices and

More information

Reinforced Earth wall Construction Manual

Reinforced Earth wall Construction Manual COVER PAGE CT-PE-W02 Rev: 5 Reinforced Earth wall Construction Manual Concrete Facing Reinforced Earth Malaysia Sdn Bhd 80-1, Jalan 8/62A Bandar Menjalara 52200 Kuala Lumpur Tel : 03-62746162, Fax : 03-62747212

More information

R-126-I PLACEMENT OF TEMPORARY CONCRETE BARRIER AND TEMPORARY STEEL BARRIER DETA IL 2 MICHIGAN DEPARTMENT OF TRANSPORTATION ** LATERAL OFFSET

R-126-I PLACEMENT OF TEMPORARY CONCRETE BARRIER AND TEMPORARY STEEL BARRIER DETA IL 2 MICHIGAN DEPARTMENT OF TRANSPORTATION ** LATERAL OFFSET 50' ON TANGENT (TYPICAL FOR DETAILS, 2, 3, & 4) 50' 50' 25' 25' PLASTIC DRUM LINE (SEE STANDARD PLAN R-3-SERIES) ** LATERAL OFFSET TRANSITION FROM TANGENT TO :6 FLARE RATE IN 40' MINIMUM. SLOPED END SECTION

More information

4 ft. and 6 ft. Downstream Defender Handling and Installation Instructions

4 ft. and 6 ft. Downstream Defender Handling and Installation Instructions 4 ft. and 6 ft. Downstream Defender Handling and Installation Instructions Page 2 Materials Supplied By Hydro International Ledger Angle (x4) Top Slab Top Riser Benching Skirt 4ft./6ft. Downstream Defender

More information

" RISKS ASSOCIATED WITH THE INSTALLATION OF THE SYSTEM

 RISKS ASSOCIATED WITH THE INSTALLATION OF THE SYSTEM PALLET RACK 85-110 installation, use and maintenance instructions Shelving made entirely of first grade certified steel sheet and cold-profiled steel with galvanized steel according to SENDZIMIR process

More information

Alberta Transportation Roadside Design Guide November 2016 APPENDIX E GUIDELINES FOR THE SELECTION AND DESIGN OF HIGH TENSION CABLE BARRIER SYSTEMS

Alberta Transportation Roadside Design Guide November 2016 APPENDIX E GUIDELINES FOR THE SELECTION AND DESIGN OF HIGH TENSION CABLE BARRIER SYSTEMS Alberta Transportation Roadside Design Guide November 2016 APPENDIX E GUIDELINES FOR THE SELECTION AND DESIGN OF HIGH TENSION CABLE BARRIER SYSTEMS APPENDIX E COVER PAGE November 2016 Alberta Transportation

More information

SP Prop Steel prop. // Versatile, strong, safe

SP Prop Steel prop. // Versatile, strong, safe Steel prop // Versatile, strong, safe IMPORTANT: Any safety provisions as directed by the appropriate governing agencies must be observed when using our products. The pictures in this brochure are snapshots

More information

SECTION 20 LOADING AND SECURING OF LOADS

SECTION 20 LOADING AND SECURING OF LOADS SECTION 20 LOADING AND SECURING OF LOADS ROA MANUAL SCHEDULE OF AMENDMENTS SECTION 20 AMENDMENT NUMBER PAGES AMENDED AMENDMENT SUMMARY DATE ISSUED CONTENTS Section Description Page 20.1 Scope 20-1 20.2

More information

I-GUIDE SAFEPASS ROAD BARRIER SAFETY SOLUTIONS JONSEREDS 1/12 IG-SAFEPASS ROAD BARRIER-1710

I-GUIDE SAFEPASS ROAD BARRIER SAFETY SOLUTIONS JONSEREDS 1/12 IG-SAFEPASS ROAD BARRIER-1710 I-GUIDE SAFEPASS ROAD BARRIER IG-SAFEPASS ROAD BARRIER-1710 1/12 SAFEPASS GENERAL About SafePass Road Barrier SafePass Road Barrier is intended for use as work zone protection where a longitudinal road

More information

Lesson 4: Flood Response Methods

Lesson 4: Flood Response Methods Lesson 4: Flood Response Methods In this lesson, you will learn the advantages and disadvantages of expedient flood works. Selecting the proper flood response technique is essential to the success of the

More information

Corrugated Guardrail and Box Beam Barriers

Corrugated Guardrail and Box Beam Barriers HIGHWAY SAFETY CORPORATION PRODUCT SHOWCASE Highway Safety Corporation has been serving the highway construction industry for over 30 years. We are a major manufacturer and supplier of highway guardrail

More information

ATT-42/95 SAMPLING, Asphalt

ATT-42/95 SAMPLING, Asphalt 1.0 Scope ATT-42/95 SAMPLING, Asphalt 1.0 SCOPE This method describes the procedures for obtaining representatives samples of asphalt, crack sealer and crack sealing materials. 2.0 EQUIPMENT The following

More information

Pedestrian Restraint Systems Bridge Rail

Pedestrian Restraint Systems Bridge Rail Pedestrian Restraint Systems Bridge Rail CONTAINMENT MDS TL5 H4a /W4 Pedestrian Restraint Systems Page 1 Pedestrian Guardrails PG1A Clear Vision Pedestrian Guardrails Pedestrian Guardrails - are used to

More information

Bridge Barriers Implementing the AS5100 Bridge Design Code Provisions

Bridge Barriers Implementing the AS5100 Bridge Design Code Provisions Bridge Barriers Implementing the AS5100 Bridge Design Code Provisions By Vincenzo Colosimo, B.Eng, G.Dip.CE, G.Dip.ME, MICE. Bridge Loads Engineer VicRoads Design VicRoads SYNOPSIS Bridge Barriers have

More information

Part 12 General Safety Precautions

Part 12 General Safety Precautions Part 12 General Safety Precautions Housekeeping 185 An employer must ensure that a work site is kept clean and free from materials or equipment that could cause workers to slip or trip. Lighting 186(1)

More information

B723 ENERGY ATTENUATORS - OPSS 723

B723 ENERGY ATTENUATORS - OPSS 723 B723 - OPSS 723 723.1 GENERAL Various proprietary permanent and temporary energy attenuators are used to reduce the hazard associated with the ends of permanent and temporary concrete barriers. Tables

More information

Aluminum Headache Rack

Aluminum Headache Rack Instruction Manual Aluminum Headache Rack ITEM NO.: AHAR Read and understand this entire manual before assembling, installing, operating, or servicing this product. SAVE THIS MANUAL IMPORTANT SAFETY INFORMATION

More information

INSTALLATION MANUAL FOR MODULAR EXPANSION JOINT (LG SYSTEM)

INSTALLATION MANUAL FOR MODULAR EXPANSION JOINT (LG SYSTEM) INSTALLATION MANUAL FOR MODULAR EXPANSION JOINT (LG SYSTEM) TABLE OF CONTENTS 1. INTRODUCTION TO THE MODULAR EXPANSION JOINT 1.1 Purpose 1.2 How They Work 1.3 Movement Capacity 1.3.1 Longitudinal Direction

More information

Requirements for Manufacturing, Transporting, Siting, Commissioning and preparation of Park Home Bases

Requirements for Manufacturing, Transporting, Siting, Commissioning and preparation of Park Home Bases Gold Shield Code of Practice Requirements for Manufacturing, Transporting, Siting, Commissioning and preparation of Park Home Bases 1 Manufacturing Requirements 1.1 Manufacturers are responsible for providing

More information

Tasman Retaining Wall System

Tasman Retaining Wall System Tasman Retaining Wall System The Tasman Retaining Wall System incorporates purpose made corners and capping units to provide classical reconstructed stone retaining walls for any landscape situation. From

More information