Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues

Size: px
Start display at page:

Download "Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues"

Transcription

1 February 24, 2017 CAPITAL PROJECT AND PLANNING UPDATE OLD NORTH Phase III and West Campus Entry: Three major components: Bid Set I and II (Interiors) Start Date: Aug Completion: Feb Size: 41,803 sq ft Total Project Budget: $8,450,000 CMSWillowbrook/Miles Associates Punch list items still in process all floors Work will continue the week of March 13. Temporary Door installation will remain on 3 rd and 4 th floors with 2-3 week delivery of real doors and may be delayed until Spring Break (pending delivery) Temporary clear glass in both permanent and temporary doors until delivery of frosted glass with 1-3 week delivery and installation and will be delayed until Spring Break (pending delivery) Bid Set III (Exterior West Campus Entry) Start Date: May 2016 Completion: Dec Size: NA Total Project Budget: $1,600,000 Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues Bid Set IV (Exterior and Interior Completion Elements) Start Date: July 2016 Completion: Feb Size: NA Total Project Budget: $350,000 Donor recognition signage: o Donor Wall final parts and pieces to be installed Feb o Room Signs complete o Individual Donor signs complete o RUSO plaques (3 each) complete o Exterior site furniture delivery scheduled week of Feb. 27 Campus Entry Signage Alpha Building Corp/Miles Associates o Construction fencing, etc. will go up Monday, Feb. 27 o Long lead time materials on order by contractor 1

2 MURDAUGH HALL: Start Date: May 2016 Completion: May 2017 Size: 79,432 sq ft Total Project Budget: $9,000,000 Anderson House Construction/FSB Architects Another CO is in progress with AH, includes multiple deducts to be used to offset discovered new work Contractor is still behind schedule and will need to work harder to maintain the completion schedule of May 8, 2017 South Ramp plaza excavation work will be suspended until documents are revised to correct drainage and access issues SOFTBALL COMPLEX: Start Date: June 2016 Completion: March 2017 Size: 2,709 sq ft Total Project Budget: $2,490,000 Timberlake Construction/Sparks Reed Architects TCI has identified that facility will be open for March 15 home game with minor work still in progress on interiors TCI states that the current completion date remains March 13, 2017 Our understanding is that an opening will be scheduled for March 24 th (Athletics to confirm) Roofing has started on both buildings for completion March 10 Exterior brickwork started on Press box Mechanical and electrical work continues in the Team Building. Wall paint is complete in several areas of the building Ceramic Tile work in bathrooms is complete Concrete site paving (walkways) are complete pending installation of Backstop poles Installation of Backstop poles is week of Feb 27 and concrete site paving will be completed week of March 6 Athletics has requested a list of additional project support items for consideration of funding Meeting today with Athletics, AES, and OIT to finalize IT and A/V components TURF: Start Date: July 2016 Completion: February 2017 Size: NA Total Project Budget is $550,000 FieldTurf International/Athletics/AES The FieldTurf is in place and is basically complete pending final grooming end of Feb. or early March (To be scheduled with PP and Athletics). FieldTurf will return end of Feb. to do UCO punch list items, final grooming and training 2

3 DINING FACILITY: Start Date: Dec Completion: Jun Size: TBD Total Project Budget: $19,000,000 Lingo Construction (CMR)/ADG Architects Kick off planning meeting was held January 25 with Client/ADG/Lingo/AES AES met with Lingo on Feb. 14 to finalize contract discussions MOU to be issued for Pre-Construction services ADG/AES met Feb 21 to begin coordination meetings in preparation of next client meeting Client meeting with ADG/Lingo/AES TBS for March 6 or 7 PERFORMING ARTS CENTER: Start Date: TBD Completion: TBD Size: TBD Total Project Budget: TBD City of Edmond is set to issue an initial planning RFQ to help establish City requirements and needs Programming interviews with (4) selected firms are being scheduled for March 7 th. o Beck o Hornbeek Blatt o HSE o Huitt-Zollars (Elliott) CAMPUS MASTER PLAN: Start Date: Dec Completion: Aug Size: NA Total Project Budget: $250,000 Rees Associates Next planning meetings will begin March 2017 Interim report to be prepared for review by Admin late March/early April TRANSPORTATION AND PARKING: Start Date: Jan. 17 Completion: Late July 2017 and Late July 2018 Size: NA Total Project Budget TBE Dewberry Design/Wallace Engineering/AES AES will coordinate work for the following: Consultants have been hired to begin the planning and design process for modifications to the lots to include: LOT 10 Reconfiguration, LOT 14, 15 (Visitor and Event Parking) (Dewberry Design) LOT 13 (Acadia Inn site) with work to begin as soon as possible (Wallace Engineering) Fielding Building Site with work to begin upon completion of Mitchell in May 2017 (Wallace Engineering) 3

4 Ayers Closure initial planning will begin January 2017 (Dewberry Design will assist with planning efforts) Initial Planning for Parking Structure East of LOT 14 (Dewberry Design) Parking lot planning for Duplex site north of Lot 54, (University and Edwards)(Wallace Engineering) AES/Aux Enterprises/T&P/Dewberry met Dec. 9 to review design options, schedules and work scope for use in preparation of a fee proposal Dewberry PO issued AES/T&P/Aux Enterprises met with Dewberry/Wallace/ADG Feb 23 MITCHELL HALL BACKSTAGE: Start Date: Dec Completion: April 2017 Size: 20,000 sq ft Total Project Budget: $5,750,000 Majority of the furniture has been ordered. (scheduled for installation April 24-28) Shiloh s updated construction schedule (received ) reflects substantial completion at April 17th. Project schedule is dependent upon near term completion of buried heating/cooling lines west of building. Grand Opening is set for May 3 rd, 2017 A/V installation scheduled for after grand opening. SOUTH CENTRAL PLANT: Start Date: Jul Completion: Fall 2017 Size: 6,500 sq ft Total Project Budget: $18,500,000 Three major components: (Work for all three is currently underway) $3M building to house the plant equipment - start date: 11/15/16 completion: 09/01/17 Construction of the building has commenced. Concrete work underway. Pre-cast concrete structure scheduled to go up mid-march. $12M chiller plant equipment and controls - start date: 2/24/17 completion: 11/30/17 $3.5M underground piping - start date: 07/01/16 completion: 07/30/17 Underground piping work, on the STEM building site, is complete. Main piping project at 30% completion Remaining installation on hold until May 4

5 STEM TEACHING & RESEARCH CENTER: Start Date: Jan Completion: Fall 2018 Size: 55,000 sq ft Total Project Budget: $24,000,000 Site work is underway. Construction meetings are on-going. Project website with construction camera is available online at Facilities or College of Math & Science home pages. A&E Services requested that Elliott + put together a finishes presentation to share with the college. (March 2017) SPORTS PERFORMANCE CENTER: Phase 1 Start Date: Apr Completion: Jun Size: 42,000 sq ft Total Project Budget: $14,000,000 Construction is scheduled to begin mid -April This is contingent upon the delivery and bidding of an early site work bid package. (Drawings due Feb ) Project needs to be available for Athletic Dept. use July 30, Project meetings occur twice a month and include: construction manager (JE Dunn), architect (Studio), Athletic Dept., and A&E Services. Updated estimate provided by JE Dunn NORTH HAMILTON ANNEX: Start Date: Summer 2018 Completion: Fall 2019 Size: 26,000 sqft Total Project Budget: $9,000,000 Design work will begin March Meeting to discuss project Construction scheduled to begin May (involves demolition of northern portion of Hamilton Field House) Bonding request contingent upon Legislature approval. Project account is set-up. LIBERAL ARTS ADDITION: Start Date: Fall 2017 Completion: Summer 2019 Size: 52,000 sqft Total Project Budget: $17,500,000 Design work continues. Beck Design and A&E Services met with the college (monthly meetings with the college will be on-going) Bonding request contingent upon Legislature approval. CAMPUS PROJECTS: (ADM) GUEST HOUSE: Start Date: 12/05/16 End Date: 03/31/17 Total Cost: $42, Submitted proposed interior paint color to Nancy for approval on 02/20/17. Moving of furniture from yellow house scheduled for end of March. 5

6 DPS ANNEX: Start Date: 11/01/16 End Date: mid to late March Total Cost: $14, Project at 85% completion Received quote from Patco to upgrade existing electrical service on 02/16/17. Met with Patco to review existing conditions and scope of work on 02/14/17. Requested quote from Patco per purchasing department requirements on 02/13/17. BUILDING SURGE PROTECTION: Objective protect hvac and other sensitive equipment from damage as the result of EE power failures. PO in place to install protection on (14) buildings Work to be performed during summer 17 ELECTRICAL PANEL UPGRADES: Objective replace aging electrical panels in (8) buildings These panels are either overloaded or replacement parts are no longer available Process will take a minimum of 3 years depending on access to classroom buildings Building will be without electrical service for 2 to 3 days during retrofit Meeting to be scheduled with Provost and Deans to coordinate priorities and scheduling JCI LIGHTING RETROFIT: Project at 50% completion JCI will begin work in Housing over spring and summer breaks 6

October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL:

October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL: October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL: Final pay applications and change orders in progress, still in discussion with AH Received final Change Order and Close out documents

More information

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018 Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018 TABLE OF CONTENTS Description Page Construction Summary 1 1 - Residence Life Operations

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

State College Area School District Memorial Field Phase 2 Update

State College Area School District Memorial Field Phase 2 Update State College Area School District Memorial Field Phase 2 Update The State College Area School District Is continuing renovations to its primary outdoor sporting venue, known as Memorial Field. The Design

More information

Facilities Planning & Management

Facilities Planning & Management Facilities Planning & Management 1100 North Grand Avenue Walnut, CA 91789 909-274-4850 www.mtsac.edu CONSTRUCTION QUARTERLY UPDATE 9/1/2016 PROJECT MANAGER: Gary Gidcumb / Fernan Siocon September 1, 2016

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project

More information

Boynton High School & Blackford Site

Boynton High School & Blackford Site Boynton High School & Blackford Site Balance (E- D) 980075 Blackford Campus Repairs (Asphalt, Plaster, Complete 100% 07/16/18 10/05/18 $725,367.67 $735,233.50 $352,463.56 -$9,865.83 $382,769.94 4 980066

More information

Facilities Modernization Program Funded by Measure B Project Report

Facilities Modernization Program Funded by Measure B Project Report Facilities Modernization Program Funded by Measure B Project Report April 2015 Learning Resource Center- B100 Learning Resource Center Architect: Construction Manager: Contractor: Steinberg Architects

More information

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS MOORESTOWN HIGH SCHOOL 06/22/15 08/28/15 Security vestibule at main entrance and transportation office; replacement of selected exterior doors; access controls at exterior doors 06/22/15 12/31/15 Upgrade

More information

MONTHLY PROGRESS REPORT

MONTHLY PROGRESS REPORT MONTHLY PROGRESS REPORT Through May 2018 Strong Schools Bond Capital Improvement Projects Prepared by fs3 Hodges 1 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report

More information

GREENE COUNTY PUBLIC SCHOOLS ADDITIONS + RENOVATIONS

GREENE COUNTY PUBLIC SCHOOLS ADDITIONS + RENOVATIONS GREENE COUNTY PUBLIC SCHOOLS ADDITIONS + RENOVATIONS SCHOOL BOARD UPDATE l Cost Estimates 14 June 2017 PROCESS FEB 09 Owner Kick-off FEB 23 Principals Review FEB 27 Traffic, Circulation + Safety Transportation

More information

Merritt Island High School

Merritt Island High School Project Project Update Update September April July 02, 8, 2010 2008 8, 2006 Project Project Manager Manager Anibal Gary Caussade Geiser Field Field Coordinator Bud Paul Mike Ball Friel Henry Mike Henry

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 1 ACTIVE PROJECTS Santa Ana College Central Plant, Infrastructure and Mechanical Upgrades 2 COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements

More information

DISTRICT ADVISORY COMMITTEE MEETING MAY 2, 2018 HALF CENT SALES TAX PROGRESS REPORT

DISTRICT ADVISORY COMMITTEE MEETING MAY 2, 2018 HALF CENT SALES TAX PROGRESS REPORT DISTRICT ADVISORY COMMITTEE MEETING MAY 2, 2018 HALF CENT SALES TAX PROGRESS REPORT PIERSON REPLACEMENT SCHOOL Architect: BRPH Construction Management: WELBRO Building Corporation School Opening: Aug.

More information

Facilities Maintenance & Operations Update. Presidents Executive Cabinet March 6, 2017

Facilities Maintenance & Operations Update. Presidents Executive Cabinet March 6, 2017 Facilities Maintenance & Operations Update Presidents Executive Cabinet March 6, 2017 1 Update Proposition 39 Year 4: March 6 March 31 Will complete all exterior lighting upgrades to LED Aquatic Center

More information

Oconomowoc Area School District Facility Construction Update June 29, 2018

Oconomowoc Area School District Facility Construction Update June 29, 2018 Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major

More information

Heritage High School

Heritage High School Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery

More information

Semi-Annual Report. January 1, 2012 June 30, 2012

Semi-Annual Report. January 1, 2012 June 30, 2012 Semi-Annual Report January 1, 2012 June 30, 2012 G.O. Bond Project Status As of June 30, 2012 Completed OCC Soccer Fields GWC Library/Classroom Improvements OCC South Campus Utilities Upgrade GWC Student

More information

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan Community Information Meeting October 2017 AGENDA Meeting Objectives Draft Plan Overview School Improvements for specific site Feedback/Listening

More information

PROJECT UPDATES: 1.01 Cox Building Annex - Tony Salcido (3 min)

PROJECT UPDATES: 1.01 Cox Building Annex - Tony Salcido (3 min) PROJECT UPDATES: 1.01 Cox Building Annex - Tony Salcido (3 min) 1. Commissioning is ongoing and will be completed by September 30, 2014. 2. Graphics for the EMS is complete. CPT to coordinate training

More information

Biddeford School Department

Biddeford School Department Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6

More information

Portsmouth Middle School Additional Funding Request

Portsmouth Middle School Additional Funding Request City Council Work Session Portsmouth Middle School Additional Funding Request Monday March 18, 2013 Project Background School Board selected Parrott Avenue site after lengthy, comprehensive and public

More information

PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016

PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016 PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016 1 ACTIVE PROJECTS Santa Ana College Chavez Hall Renovation Temporary Village Phase 2 Santiago Canyon College Orange Education Center

More information

Completed projects. Projects in progress. Program developments

Completed projects. Projects in progress. Program developments 1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site

More information

DEL MAR COLLEGE Capital Improvement Program for Proposed Southside Campus. Prepared by;

DEL MAR COLLEGE Capital Improvement Program for Proposed Southside Campus. Prepared by; DEL COLLEGE 2016 Capital Improvement Program for Proposed Southside Campus Prepared by; DEL COLLEGE 2016 Capital Improvement Program for Proposed Southside Campus GENSLER, UST 2, 2016 EXECUTIVE SUMY After

More information

Facilities and Planning Department Measure E Update March 2017

Facilities and Planning Department Measure E Update March 2017 State Seismic Mitigation Program (SSMP) The District s application for SSMP funds for Horace Mann Building A will be reviewed for approval by the State Allocation Board at its next scheduled meeting on

More information

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005

More information

Project Information. Nominations of Artists. University of Houston

Project Information. Nominations of Artists. University of Houston UNIVERSITY OF HOUSTON SYSTEM SYSTEM WIDE ART ACQUISTION COMMITTEE AGENDA ITEM ITEM: UH University Center Transformation Project Artwork-Artists Nominations DATE PREVIOUSLY SUBMITTED: NA SUMMARY: Nominations

More information

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects. SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial

More information

MONTHLY EXECUTIVE UPDATE MARCH 21, Thursday, March 21, 13

MONTHLY EXECUTIVE UPDATE MARCH 21, Thursday, March 21, 13 PROPOSITION R PROGRAM UPDATE MONTHLY EXECUTIVE UPDATE MARCH 21, 2013 1 CENTRAL PLANT BOILERS--- COMPRESSORS--- CONDENSERS--- PIPING--- COMMISSIONING PREPARATIONS 2 Central Plant Accomplished in March:

More information

Cultural Facilities: Capital Needs Inventory and Priorities. Arts, Culture and Libraries Committee October 17, 2016

Cultural Facilities: Capital Needs Inventory and Priorities. Arts, Culture and Libraries Committee October 17, 2016 Cultural Facilities: Capital Needs Inventory and Priorities Arts, Culture and Libraries Committee October 17, 2016 Purpose To provide an overview of the buildings managed through the Office of Cultural

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

Frost Technical Center

Frost Technical Center Frost Technical Center 1955 Greenhouses Addition Various other additions and renovations Provide site security improvements Provide improved Admin area field of view to site entrance Provide security camera

More information

Cupertino Union School District

Cupertino Union School District Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK

More information

Bronx Community College. Five-Year Capital Plan FY through FY

Bronx Community College. Five-Year Capital Plan FY through FY Five-Year Capital Plan FY 2019-20 through FY 2023-24 Projects in priority order / costs in $ thousands Project Name FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24 (B) Campus-Wide Fire Alarm Replacement DC

More information

PROJECT UPDATES: 1.01 Cox Building Annex - Tony Salcido (3 min)

PROJECT UPDATES: 1.01 Cox Building Annex - Tony Salcido (3 min) PROJECT UPDATES: 1.01 Cox Building Annex - Tony Salcido (3 min) 1. Fax lines at Cox Annex were connected on May 8, 2014. Faxes are now operational. CPM is waiting on confirmation on additional line extension

More information

DEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION

DEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION DEL MAR UNION SCHOOL DISTRICT TECHNOLOGY & 21 ST -CENTURY LEARNING INITIATIVE BOND PROJECT DESCRIPTION The Board of Trustees of Del Mar Union School District ("District") has evaluated the need to acquire,

More information

James Lick High School

James Lick High School James Lick High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan James Lick High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew P.

More information

Ohlone Community College District

Ohlone Community College District Bond Measure G March 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Closeout Progress

More information

July 1 September 30, 2008

July 1 September 30, 2008 July 1 September 30, 2008 1 G.O. Bond Project Status As of September 30, 2008 Completed OCC Soccer Fields GWC Library/Classroom Improvements OCC South Campus Utilities Upgrade GWC Student Center Remodel

More information

Program Update. Chino Health Science Parking Lot

Program Update. Chino Health Science Parking Lot Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction

More information

School of Business Project # Overall Project Cost: $26,700, Architect: Urbahn. Scheduled Completion Date: 10/2014.

School of Business Project # Overall Project Cost: $26,700, Architect: Urbahn. Scheduled Completion Date: 10/2014. School of Business Project #26290 Overall Project Cost: $26,700,000.00 Architect: Urbahn Scheduled Completion Date: 10/2014 Contractor: N/A Description: This project will construct a new academic building

More information

HIDDEN VALLEY ELEMENTARY SCHOOL

HIDDEN VALLEY ELEMENTARY SCHOOL SCHOOL DATA Address: 3435 Bonita Vista Santa Rosa, CA 95404 Established: 975 Permanent Classrooms: 29 Portable Classrooms: 8 Building Area: Site Area: Satellite Building Area: Satellite Site Area: 48,802

More information

MIRACOSTA COMMUNITY COLLEGE DISTRICT

MIRACOSTA COMMUNITY COLLEGE DISTRICT MIRACOSTA COMMUNITY COLLEGE DISTRICT FACILITIES MASTER PLAN UPDATE MARCH 16, 2016 PHASE TWO: Board of Trustees Presentation 1 Facilities Master Plan Update: Cost Community Learning Center San Elijo Campus

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING APRIL 17, 2018

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING APRIL 17, 2018 FACILITIES COMMITTEE MEETING APRIL 17, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure Johnson Student Center Johnson Demolition Science Center & Building J Demolition

More information

Governing Board Capital Construction Program Annual Workshop September 10, 2013 Agenda

Governing Board Capital Construction Program Annual Workshop September 10, 2013 Agenda Governing Board Capital Construction Program Annual Workshop September 10, 2013 Agenda Prop R Status Projects Completed Status of Facilities Master Plans Prop R 5-Year Construction Plan Summary; IPP s

More information

January 1, 2009 March 31, 2009

January 1, 2009 March 31, 2009 January 1, 2009 March 31, 2009 1 G.O. Bond Project Status As of March 31, 2009 Completed OCC Soccer Fields GWC Library/Classroom Improvements OCC South Campus Utilities Upgrade GWC Student Center Remodel

More information

PRESENTATION JANUARY 24, 2017

PRESENTATION JANUARY 24, 2017 4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction

More information

ATHLETIC FACILITIES. High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan. Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan

ATHLETIC FACILITIES. High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan. Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan ATHLETIC FACILITIES High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan SWARTZ CREEK HIGH SCHOOL STADIUM 1 Dragon Drive, Swartz

More information

Instructional Science Facility Phase I

Instructional Science Facility Phase I Instructional Science Facility Phase I University of Wisconsin La Crosse Campus October 27, 2015 UWL Science Lab Building Phase 1 1 Project Schedule Timeline July Aug Sept Oct Nov Dec Jan Feb Mar Apr May

More information

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 TABLE OF CONTENTS PROGRAM SUMMARY DESIGN EXPLORATION EXISTING SITE PLAN - ANALYSIS DEMOLITION SITE PLAN PROPOSED SITE PLAN PROPOSED FLOOR PLANS DEMOLITION

More information

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope

More information

La Porte Independent School District 2014 Bond Program Status Report August 11, 2015

La Porte Independent School District 2014 Bond Program Status Report August 11, 2015 La Porte Independent School District 2014 Bond Program Status Report August 11, 2015 La Porte ISD 2014 Bond Program ADMINISTRATION: Superintendent: Lloyd Graham Deputy Superintendent: Dr. Linda Wadleigh

More information

APSU PROJECT REPORT 8/2/2018

APSU PROJECT REPORT 8/2/2018 373/003X92018 Harvill Hall Fan Coil & Controls Upgrade Housing Joe Mills (millsj@apsu.edu) LOI Replacement of Building Fan Coils & Controls 01Approval\Planning Construction Cost 320,000.00 Contingency

More information

Chino Valley Unified School District Monthly Construction Update

Chino Valley Unified School District Monthly Construction Update h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

EL CAMINO COLLEGE. Facilities Master Plan Report November 2008 PROJECTS IN DESIGN

EL CAMINO COLLEGE. Facilities Master Plan Report November 2008 PROJECTS IN DESIGN EL CAMINO COLLEGE Facilities Master Plan Report November 2008 PROJECTS IN DESIGN I. Math, Business & Allied Health Building (MBA) The scope of this building is the construction of a new building at the

More information

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement Projects under Construction Data and Telecom Cabling-VPA, New Gym, & Physical Science Architect/Engineer: P2S Engineering Original Contract: $154,882 Construction Manager: Bernards Approved Change Orders:

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (01-22-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 29% COMPLETE SAMUEL

More information

MCKINLEY INSTITUTE OF TECHNOLOGY BRAILSFORD & DUNLAVEY RGM AND ASSOCIATES MEASURE T BOND

MCKINLEY INSTITUTE OF TECHNOLOGY BRAILSFORD & DUNLAVEY RGM AND ASSOCIATES MEASURE T BOND MCKINLEY INSTITUTE OF TECHNOLOGY N E I G H B O R H O O D M E E T I N G A P R I L 2 4, 2 0 1 7 1 1 LPA MASTER PLAN 2 PHASE 1 SCOPE Blue Line 3 PHASE 1 SCOPE Blue Line 4 BOND T REVISED PROGRAM SCOPE 1 Modernize

More information

Capital Improvement Program Monthly Status Report

Capital Improvement Program Monthly Status Report Projects Upgrades in Multipurpose Building 1300 In order to meet the needs of the building s three distinct uses administrative gatherings, recreational program space, and as a general venue and event

More information

Contract No. EX CS001 - Construction of an Annex to Baptist Lui Ming Choi Secondary School at Yuen Wo Road, Shatin, New Territories.

Contract No. EX CS001 - Construction of an Annex to Baptist Lui Ming Choi Secondary School at Yuen Wo Road, Shatin, New Territories. - Part A: Project Particulars Section Section 1 Construction of New Annex Section 2 Conversion works Contract Period Commencement Date Completion Date Revised Completion Date 730 days 28/12/2015 26/12/2017

More information

Berryessa Union School District Measure L Bond Construction Program

Berryessa Union School District Measure L Bond Construction Program Berryessa Union School District Measure L Bond Construction Program Board of Trustees Update December 8, 2015 Introduction The following presentation is intended to provide the Board of Trustees with an

More information

Board Report. Bond Program Update:

Board Report. Bond Program Update: March 2014 Bond website: www.pcc.edu/bond Bond Program Update: Winter term is quickly coming to an end and as spring term approaches we have more buildings and areas opening for use for students and staff.

More information

Through. February Current Strong Schools Bond Capital Improvement Projects. Prepared by

Through. February Current Strong Schools Bond Capital Improvement Projects. Prepared by MONTHLY PROGRESS REPORT Through February 2012 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive

More information

Auburn University Construction Project Update March 2010

Auburn University Construction Project Update March 2010 New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish

More information

Facilities Services Newsletter Summer 2012

Facilities Services Newsletter Summer 2012 Facilities Services Newsletter Summer 2012 Facilities Services Spring & Summer Project Update Commencement Completed! Reunion Completed! Language School Setups Completed! Hepburn Water Service - Completed!

More information

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, 2007 North Medford High School: Project Summary: Renovate and add new addition based on facility evaluation and design.

More information

Perimeter Site Improvements

Perimeter Site Improvements Perimeter Site Improvements Phase 1-5 Architect: W+W Architects and Planners Anticipated Milestone Activities: Phase 1, 2 & 3 Construction Manager: Bernards 08.08.13 Directional Signage Contractor: Woodcliff

More information

Independence Adult Center

Independence Adult Center Campus Master Plan March 15, 2004 Master Plan Contents Volume I: District Master Plan Andrew P. Hill High School Campus Master Plan Foothill High School Campus Master Plan Independence High School Campus

More information

FUTURE BOND PROGRAM PRELIMINARY PROJECT LIST

FUTURE BOND PROGRAM PRELIMINARY PROJECT LIST FUTURE BOND PROGRAM PRELIMINARY PROJECT LIST March 10, 2018 TABLE OF CONTENTS PROJECT SUMMARY LIST AND COST PROJECT DESCRIPTIONS MISSION COLLEGE PROJECT DESCRIPTIONS WEST VALLEY COLLEGE PROJECT DESCRIPTIONS

More information

Santa Teresa High School

Santa Teresa High School Santa Teresa High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan Santa Teresa High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew

More information

Through. November Current Strong Schools Bond Capital Improvement Projects. Prepared by

Through. November Current Strong Schools Bond Capital Improvement Projects. Prepared by MONTHLY PROGRESS REPORT Through November 2010 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive

More information

Auburn University Construction Project Update June 2010

Auburn University Construction Project Update June 2010 New Basketball Arena: Construction Cost: $68.5 million. The Arena achieved the Substantial Completion project milestone as of June 4 th, 2010. Punch list item work is ongoing. Work related to the project,

More information

Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018.

Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018. Capital Projects Status Report October 1, 2018 Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah 84119 P 801.974.8365 F 801.974.8375 Current Projects 1. Edison construction update: In Area

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 33% COMPLETE As

More information

Birmingham Public Schools

Birmingham Public Schools Birmingham Public Schools 2015 BOND ISSUE PROGRAM Project Status Update Tuesday June 5, 2018 Agenda Dashboard Update for Website Summer 2018 Construction Project Preview Summer 2018 Construction Progress

More information

CONSTRUCTION UPDATE. April AUM Projects. Client: Housing and Residence Life Construction Cost: $28 million Completion Date: July 2013

CONSTRUCTION UPDATE. April AUM Projects. Client: Housing and Residence Life Construction Cost: $28 million Completion Date: July 2013 April 2013 AUM Projects AU Montgomery New Residence Hall AU Projects AU Recreation and Wellness Center Biggio Drive Parking Facility Biodiversity Learning Center CONSTRUCTION UPDATE AU Montgomery New Residence

More information

LOVEJOY Independent School District

LOVEJOY Independent School District Long-Range Facilities Planning Projected Bond Sale Project Series 2014 Series 2018 Series 2023 Total (2013 Cost) (with 6% Yearly Inflation) 1. Hart Elementary $ 6,716,424 $ 6,168,802 $ 1,200,121 $ - $

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities

More information

Capital Project Recommendations Presented to the Board of Education 9/23/2014

Capital Project Recommendations Presented to the Board of Education 9/23/2014 Capital Project Recommendations Presented to the Board of Education 9/23/2014 The administration has been working to identify a division of the proposed $15M in capital projects between the athletic field

More information

4. Commissioning is ongoing and will be completed by October 30, CPT to coordinate training with LASC staff, TBD

4. Commissioning is ongoing and will be completed by October 30, CPT to coordinate training with LASC staff, TBD PROJECT UPDATES: 1.00 General Announcement 1. October 31, 2014 will be the last day on the Program for the current College Project Director, Gustavo Ripalda. 2. Mark Al-Soufi has been appointed by PMO

More information

Request for Proposal for GC/CM Consultant Services Ferndale School District. Secondary High School GC/CM Program. October 19, 2018

Request for Proposal for GC/CM Consultant Services Ferndale School District. Secondary High School GC/CM Program. October 19, 2018 Request for Proposal for GC/CM Consultant Services Ferndale School District Secondary High School GC/CM Program October 19, 2018 The Ferndale School District is requesting proposals for project management,

More information

Grossmont-Cuyamaca Community College District Facilities Construction Update

Grossmont-Cuyamaca Community College District Facilities Construction Update Grossmont-Cuyamaca Community College District Facilities Construction Update September 13, 2016 Presented by Penny McGrew Program Manager Gafcon, Inc. Bond Program Update Agenda Districtwide Energy Conservation

More information

Physical Plant. Detailed Assessment Report

Physical Plant. Detailed Assessment Report Physical Plant Detailed Assessment Report 2012-2013 Mission / Purpose The Physical Plant Department enhances the University of West Alabama s mission to provide opportunities for students to pursue a quality

More information

RATIONALE AND REASONING

RATIONALE AND REASONING RATIONALE AND REASONING Background The main tenant residing in BMH is the Anthropology Department. Most of the building systems constructed in the building are over forty years old and are at the end of

More information

Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013

Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013 Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013 Information Session Agenda Background. Scope of work and why these renovations are important. Project cost. How

More information

Bruce Powers, Park Analyst / Project Manager Parks & Recreation Department

Bruce Powers, Park Analyst / Project Manager Parks & Recreation Department 6.1 TO: FROM: SUBJECT: Kent Studebaker, Mayor Members of the City Council Bruce Powers, Park Analyst / Project Manager Parks & Recreation Department East Waluga Sports Fields Replacement Project DATE:

More information

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project BOYERTOWN AREA SCHOOL DISTRICT February 28, 2017 Junior High West Project Overview On June 16, 2015 the board of school directors authorized KCBA Architects to begin the design development stage of the

More information

Southwest Health System Construction Newsletter October 7, 2017

Southwest Health System Construction Newsletter October 7, 2017 Southwest Health System A Week in Review Patient Wing Interior sheetrock is 99% complete in the Patient Wing proper Taping and finishing is following behind sheetrock, and Nunn is preparing rooms for paint

More information

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS (August 28, 2018) PIERCE HALL IMPROVEMENTS PROJECT NO. 950511-950532 UNIVERSITY OF CALIFORNIA, RIVERSIDE PREQUALIFICATION PROCESS ALL

More information

CESAR CHAVEZ LANGUAGE ACADEMY

CESAR CHAVEZ LANGUAGE ACADEMY SCHOOL DAA Address: 2570 West Steele Lane Santa Rosa, CA 95403 Established: Campus - 1972, CCLA - 2013 Permanent Classrooms: 14 Portable Classrooms: 4 Building Area: Site Area: 17,000 sq. ft. 24.08 acres

More information

Assistant Superintendent for Business Services. Executive Director of Facility Services Assistant Director of Facility Services

Assistant Superintendent for Business Services. Executive Director of Facility Services Assistant Director of Facility Services 2016 BOND PROGRAM CONSTRUCTION STATUS REPORT June 2018 Administration Assistant Superintendent for Business Services Randy McDowell Facility Planning and Construction Executive Director of Facility Services

More information

Assistant Superintendent for Business Services. Executive Director of Facility Services Assistant Director of Facility Services

Assistant Superintendent for Business Services. Executive Director of Facility Services Assistant Director of Facility Services 2016 BOND PROGRAM CONSTRUCTION STATUS REPORT June 2018 Administration Assistant Superintendent for Business Services Randy McDowell Facility Planning and Construction Executive Director of Facility Services

More information

Projects Currently in Planning, Design and Construction. April 12, 2017

Projects Currently in Planning, Design and Construction. April 12, 2017 Projects Currently in Planning, Design and Construction April 12, 2017 in Planning Programming, Space Planning, Site Design Review and Construction Support for Various Capital Projects Administrative Space

More information

Addendum to Agenda Item: SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN

Addendum to Agenda Item: SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN GREENWICH PUBLIC SCHOOLS Greenwich, CT November 27, 2017 Addendum to Agenda Item: 2018-2019 SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN Please note edited pages should replace original sheets in

More information