PRO-TEC SENTRY BUILDING PONY WALL 90' WIDTH FOUNDATION MANUAL
|
|
- Antony Thompson
- 6 years ago
- Views:
Transcription
1 MANUAL NO KAG REV A PRO-TEC SENTRY BUILDING PONY WALL 90' WIDTH FOUNDATION MANUAL IMPORTANT - TO THE DEALER OR ERECTOR: RETURN THIS MANUAL TO THE OWNER FOR THEIR FUTURE REFERENCE SIOUX STEEL COMPANY, P.O. BOX 1265, SIOUX FALLS, SOUTH DAKOTA
2 Dear Sentry Building Owner, We would like to take this opportunity to thank you for purchasing a SIOUX STEEL PRO-TEC BUILDING. We believe that it will serve you well for many years. The framework uses quality certified structural grade steel tubing. All welded rafter assemblies are powder coated to provide maximum corrosion protection. We believe in providing QUALITY, RELIABILITY, DURABILITY, VERSATILITY, and COMMITMENT to meet the needs of our customer. Should you have any questions or comments during or following the installation, please feel free to call your SIOUX STEEL PRO-TEC BUILDING dealer or manufacturer. We will be glad to assist you in any way we can. IMPORTANT Improper Site Preparation, Assembly and Maintenance may invalidate warranty and cause unnecessary and costly mistakes. READ MANUAL FIRST If you have any questions, contact your local dealer or Call: Sioux Steel Co. at
3 TABLE OF CONTENTS SAFETY PAGE 3 GENERAL INFORMATION (30 PSF, 40 PSF, & 50 PSF) PAGE 4-6 COMPONENTS PAGE 7 TOOLS & EQUIPMENT PAGE 8 FOUNDATION LAYOUT PAGE 9-11 ANCHOR BOLT INSTALLATION PAGE RATCHET MOUNT INSTALLATION PAGE 14 ANCHOR BOLT INSTALLATION ON INSIDE PAGE 15 FACE OF FOUNDATION END WALL FOUNDATION (IF REQUIRED) PAGE
4 SAFETY Watch for this symbol. It points out important safety precautions. It means Attention Be Alert! DEFINITIONS: CAUTION: Indicates a hazardous situation, which, if not avoided, could result in minor or moderate injury. WARNING: Indicates a hazardous situation, which, if not avoided, could result in death or serious injury. DANGER: Indicates a hazardous situation, which, if not avoided, will result in death or serious injury. When constructing foundation: Use appropriate safety practices during construction of foundation. Hard hats are recommended to prevent injury to head. Gloves and other heavy clothing are recommended to prevent cuts and abrasions to hands and other body parts. Appropriate equipment and proper training in the operation of this equipment, are important factors for the safe construction of foundation. Reading, understanding, and following the instructions in this book are also very important for the safe construction of foundation. Sioux Steel Company includes all reasonable means for accident prevention, except a safe and careful operator. After foundation is complete: Ensure foundation area remains safe prior to erection of building. 3
5 GENERAL INFORMATION (30 PSF SNOW LOAD) 16 FT RAFTER SPACING Foundation for Sentry Building: In all cases, the soil and foundation must be sufficiently stable and deemed suitable to support the forces produced by the structure (listed below). It is recommended that the customer consult a qualified engineer to certify the soil conditions and foundation for their location. Soil and foundation must be able to withstand forces which meet or exceed the structural forces below. MAXIMUM BUILDING REACTIONS AT SERVICE LOADS In. (+X) lbs. Up (+Y) lbs. Down. (-Y) lbs. Induced Moment (ft-lbs) Service Load Out. (-X) lbs. (Z) lbs Dead Load n/a 210 Snow Load Wind Load Building reactions are based on occupancy category I outlined in ASCE 7-05, Table Building reactions are based on a building which is classified as partially enclosed as specified in ASCE 7-05, Section A total of 500 pounds may be suspended from each frame, as long as no single point force exceeds 250 pounds. -Customer should contact their dealer with any requests for other loading scenarios. Site Conditions for Sentry Building: The installation site must be sufficiently level to permit uniform wall assembly on a support foundation. In all cases, the area surrounding the Sentry Building must provide sufficient drainage to prevent soil erosion around the foundation. The structure has been designed to meet 90 mph exposure C wind load and 30 psf ground snow load, for open terrain with obstructions having heights generally less than 30 feet. This terrain must extend upwind for a distance greater than 2600 feet. The building must be positioned at least 20 feet away from existing structures with a higher eave to prevent excessive load from drifting snow. Contact your insurance agent prior to assembly to insure you are covered in case of inadvertent accidents that may occur during erection. NOTE: Sioux Steel Company is not responsible or liable for: - Any damage or failure that may occur due to incorrect erection of building. - Any soil analysis or foundation design, - Substitution of components not specified in the construction manual that lead to damage or failure. - Unstable soil conditions or foundation that lead to structure damage or failure. - Damage caused by leaning sidewalls. - Any modification of design or structure. - Any bodily injury that occurs during the assembly of the building or as a result of modification to the design or improper construction. Z Y X 4
6 GENERAL INFORMATION (40 PSF SNOW LOAD) 12 FT RAFTER SPACING Foundation for Sentry Building: In all cases, the soil and foundation must be sufficiently stable and deemed suitable to support the forces produced by the structure (listed below). It is recommended that the customer consult a qualified engineer to certify the soil conditions and foundation for their location. Soil and foundation must be able to withstand forces which meet or exceed the structural forces below. MAXIMUM BUILDING REACTIONS AT SERVICE LOADS In. (+X) lbs. Up (+Y) lbs. Down. (-Y) lbs. Induced Moment (ft-lbs) Service Load Out. (-X) lbs. (Z) lbs Dead Load n/a 185 Snow Load Wind Load Building reactions are based on occupancy category I outlined in ASCE 7-05, Table Building reactions are based on a building which is classified as partially enclosed as specified in ASCE 7-05, Section A total of 500 pounds may be suspended from each frame, as long as no single point force exceeds 250 pounds. -Customer should contact their dealer with any requests for other loading scenarios. Site Conditions for Sentry Building: The installation site must be sufficiently level to permit uniform wall assembly on a support foundation. In all cases, the area surrounding the Sentry Building must provide sufficient drainage to prevent soil erosion around the foundation. The structure has been designed to meet 90 mph exposure C wind load and 40 psf ground snow load, for open terrain with obstructions having heights generally less than 30 feet. This terrain must extend upwind for a distance greater than 2600 feet. The building must be positioned at least 20 feet away from existing structures with a higher eave to prevent excessive load from drifting snow. Contact your insurance agent prior to assembly to insure you are covered in case of inadvertent accidents that may occur during erection. NOTE: Sioux Steel Company is not responsible or liable for: - Any damage or failure that may occur due to incorrect erection of building. - Any soil analysis or foundation design, - Substitution of components not specified in the construction manual that lead to damage or failure. - Unstable soil conditions or foundation that lead to structure damage or failure. - Damage caused by leaning sidewalls. - Any modification of design or structure. - Any bodily injury that occurs during the assembly of the building or as a result of modification to the design or improper construction. Z Y X 5
7 GENERAL INFORMATION (50 PSF SNOW LOAD) 10 FT RAFTER SPACING Foundation for Sentry Building: In all cases, the soil and foundation must be sufficiently stable and deemed suitable to support the forces produced by the structure (listed below). It is recommended that the customer consult a qualified engineer to certify the soil conditions and foundation for their location. Soil and foundation must be able to withstand forces which meet or exceed the structural forces below. MAXIMUM BUILDING REACTIONS AT SERVICE LOADS In. (+X) lbs. Up (+Y) lbs. Down. (-Y) lbs. Induced Moment (ft-lbs) Service Load Out. (-X) lbs. (Z) lbs Dead Load n/a 210 Snow Load Wind Load Building reactions are based on occupancy category I outlined in ASCE 7-05, Table Building reactions are based on a building which is classified as partially enclosed as specified in ASCE 7-05, Section A total of 500 pounds may be suspended from each frame, as long as no single point force exceeds 250 pounds. -Customer should contact their dealer with any requests for other loading scenarios. Site Conditions for Sentry Building: The installation site must be sufficiently level to permit uniform wall assembly on a support foundation. In all cases, the area surrounding the Sentry Building must provide sufficient drainage to prevent soil erosion around the foundation. The structure has been designed to meet 90 mph exposure C wind load and 50 psf ground snow load, for open terrain with obstructions having heights generally less than 30 feet. This terrain must extend upwind for a distance greater than 2600 feet. The building must be positioned at least 20 feet away from existing structures with a higher eave to prevent excessive load from drifting snow. Contact your insurance agent prior to assembly to insure you are covered in case of inadvertent accidents that may occur during erection. NOTE: Sioux Steel Company is not responsible or liable for: - Any damage or failure that may occur due to incorrect erection of building. - Any soil analysis or foundation design, - Substitution of components not specified in the construction manual that lead to damage or failure. - Unstable soil conditions or foundation that lead to structure damage or failure. - Damage caused by leaning sidewalls. - Any modification of design or structure. - Any bodily injury that occurs during the assembly of the building or as a result of modification to the design or improper construction. Z Y X 6
8 COMPONENTS 1" CENTER OF RAFTER ARROW INDICATES TEM 21/32 4" 7" 8" 2 1/4" 7 3/4" CENTER TEM ARROW INDICATES TEM INSIDE OF WALL CENTER OF RAFTER 2" 21/32 5" 6" 2" 5 5/8" 10 7/16" CORNER TEM 1'-3 1/4" 1'-6 7/8" 1'-8 7/8" CENTER HOLE 1 1/2" 3/4" RATCHET MOUNT TEM 3/4" 17/32 2 1/2" 4 1/4" 5" NOTE: If templates were not ordered, construct out of plywood or other material based off of drawings above. 7
9 TOOLS AND EQUIPMENT (Customer Supplied) Measuring Tools: Transit-recommended String level String line (Long enough for your specific building) 300 Tape measure 4' level Plumb bob Excavating Tools: Spade Type Shovel Equipment to dig foundation. Material: Anchor bolts, 5/8 thread, 70 ksi min. tensile strength, four (4) for each center base plate and five (5) for corner base plate Inside face of foundation anchor bolts, 5/8" thread, 70 ksi min. tensile strength, six (6) for each center base plate (will be used during erection of structure) Anchor bolts, 1/2" thread, 70 ksi min. tensile strength two (2) for each ratchet mount location End Wall if required Anchor bolts, 5/8" thread, 70 ksi min. tensile strength, quantity will vary depending on end wall option 8
10 FOUNDATION LAYOUT (STEP 1) IMPORTANT: These foundation details are suggestions only. Soil conditions vary and should be checked with a qualified engineer. SIOUX STEEL IS NOT RESPONSIBLE FOR THE FOUNDATION DESIGN. IMPORTANT: Other foundation options are available, but must meet the loading requirements as stated on the GENERAL INFORMATION page of this manual. See pages 4-6. Step 1.1 Select a site to place your new Pro-Tec Sentry building and prepare by leveling and grading. See general information on pages 4-6 on site selection. Step 1.2 Stake out two corner posts A & B as shown in diagram below. A B DISTANCE IS EQUAL TO STATED LENGTH OF BUILDING + 4" 9
11 FOUNDATION LAYOUT (STEP 1) (CONT.) Step 1.3 Stake out other two corner posts C & D as shown in diagram below. Step 1.4 Verify diagonal measurements are equal to check squareness. Note: Cover will not fit properly if foundation is not square. Step 1.5 Recheck width measurement shown in diagram below. A B DIAGONAL DISTANCE ARE EQUAL 90' 9/16 TEMS DIAGONAL DISTANCE ARE EQUAL C DISTANCE IS EQUAL TO STATED LENGTH OF BUILDING + 4 D 10
12 FOUNDATION LAYOUT (STEP 1) (CONT.) Step 1.6 String a level line from A to B and C to D corner posts for the length of the building extending past each corner and as close to the ground as possible (6" maximum). Step 1.7 String a level line from A to C and B to D corner posts for the width of the building extending past each corner and as close to the ground as possible (6" maximum). Step 1.8 String a level line 8" in from A to B and C to D corner posts for inside location of foundation. This measurement is critical for installation of center rafters. A STRING LINE TEMS B STRING LINE INSIDE OF FOUNDATION STRING LINE TEMS /16 INSIDE OF FOUNDATION STRING LINE TEMS STRING LINE INSIDE OF FOUNDATION MIN C STRING LINE TEMS D 11
13 Step 2.1 Construct foundation. ANCHOR BOLT INSTALLATION (STEP 2) Step 2.2 Utilizing Corner Templates (192093), install (5) 5/8" anchor bolts (customer supplied) at each corner template location. Verify using diagram below for proper orientation and placement of templates. Leave 2" exposed above the concrete surface. Protect the exposed threads from concrete or damage. NOTE: If templates were not ordered, construct out of plywood or other material based off of drawings on page 7. VERIFY CORRECT ORIENTATION OF ARROWS ON TEMS TEMS INSIDE OF FOUNDATION 90-9/16 OUTSIDE TO TEMS TEMS (4X) CORNER TEM (192093) INSIDE OF FOUNDATION TEMS OUTSIDE TO TEMS DISTANCE IS EQUAL TO STATED LENGTH OF BUILDING
14 ANCHOR BOLT INSTALLATION (STEP 2) (CONT.) Step 2.3 Utilizing Center Templates (192093), install (4) 5/8" anchor bolts (customer supplied) at each arch interval location. Verify using diagram below for proper orientation and placement of templates. Leave 2" exposed above the concrete surface. Protect the exposed threads from concrete or damage. NOTE: If templates were not ordered, construct out of plywood or other material based off of drawings on page 7 NOTE: Arch intervals are based off of desired snow load. See chart below for correct snow load to arch interval. Step 2.4 Recheck all foundation measurements to assure they are maintained. INSIDE OF FOUNDATION 90-9/16 TEMS SNOW LOAD TO ARCH INTERVAL 30 PSF- 16' ARCH INTERVAL 40 PSF- 12' ARCH INTERVAL 50 PSF- 10' ARCH INTERVAL /16 INSIDE OF FOUNDATION MEASURE FROM CENTER OF NOTCH CENTER TEM (192092) VERFIY CORRECT ORIENTATION OF ARROW ON TEM INSIDE OF FOUNDATION 13
15 RATCHET MOUNT INSTALLATION (STEP 3) Step 3.1 Utilizing Ratchet Mount Template (190644), install (2) 1/2" anchor bolts (customer supplied) at each ratchet mount location. See drawing below for proper placement. Leave 2" exposed above the concrete surface. Protect the exposed threads from concrete or damage. NOTE: If templates were not ordered, construct out of plywood or other material based off of drawings on page 7 NOTE: Ratchet mount interval are based off of desired snow load. See chart below for correct snow load to ratchet mount interval. CORNER OF FOUNDATION MEASURE FROM CENTER RATCHET MOUNT TEM (190644) 5" FIRST RATCHET MOUNT LOCATION 8', 6', OR 5' ADDITIONAL RATCHET MOUNT LOCATION INSTALL EVERY 16', 12' OR 10 SNOW LOAD TO RATCHET MOUNT INTERVAL FIRST RATCHET MOUNT 30 PSF- 8' RATCHET MOUNT INTERVAL 40 PSF- 6' RATCHET MOUNT INTERVAL 50 PSF- 5 RATCHET MOUNT INTERVAL ADDITIONAL RATCHET MOUNT 30 PSF- 16' RATCHET MOUNT INTERVAL 40 PSF- 12' RATCHET MOUNT INTERVAL 50 PSF- 10' RATCHET MOUNT INTERVAL 14
16 ANCHOR BOLT INSTALLATION ON INSIDE FACE OF FOUNDATION (STEP 4) Anchor bolts on inside face of foundation will be installed when building is erected. See structural manual instructions. 15
17 END WALL FOUNDATION (IF REQUIRED) BASE TEMS ARROW REPRESENTS WALL 2" 2" 8" 5" 11/16" CENTER OF TOWER 8" 5" CENTER OF TOWER 11/16" 1 1/4" TPL BASE 4 1/2" 7 3/4" 9" 1 1/4" TPL HALF BASE 4 1/2" 6 1/4" ARROW REPRESENTS WALL 2 1/4" 10 1/2" 5 1/4" 8 1/4" CENTER OF TOWER 11/16" 1 1/4" TPL BASE 4 1/2" 7 3/4" 9" 16
18 END WALL FOUNDATION (IF REQUIRED) INSTRUCTIONS Step 1 Select End Wall Foundation layout drawing from following pages. Step 2 Construct necessary Base Plate Templates from previous page out of wood or other material. Step 3 Layout and construct desired foundation. Step 4 Utilizing Base Plate Templates install 5/8" anchor bolts (customer supplied) at each tower location. See correct End Wall Foundation layout on following pages for proper placement. Leave 2" exposed above the concrete surface. Protect the exposed threads from concrete or damage. 17
19 END WALL FOUNDATION (IF REQUIRED) SOLID END WALL FOUNDATION 9" 17'-2 1/4" TPL BASE 10 1/2" OUTSIDE OF WALL 35'-5 3/4" 9" TPL BASE ARROW INDICATES OUTSIDE OF WALL 53'-9 3/4" 72'-1 1/4" 90'-9/16" OUTSIDE TO TEMS 9" TPL BASE OUTSIDE OF WALL 9" TPL BASE 10 1/2" OUTSIDE OF WALL 18
20 END WALL FOUNDATION (IF REQUIRED) 18' DOOR END WALL FOUNDATION 9" 17'-1 3/4" TPL BASE 10 1/2" OUTSIDE OF WALL 35'-5 3/4" 6 1/4" TPL HALF BASE ARROW INDICATES WALL 54'- 1/2" 72'-1 3/4" 90' 9/16" OUTSIDE TO TEMS 6 1/4" TPL HALF BASE OUTSIDE OF WALL 9" OUTSIDE OF WALL TPL BASE 10 1/2" 19
21 END WALL FOUNDATION (IF REQUIRED) 2-18' DOORS END WALL FOUNDATION 6 1/4" 17'-1 3/4" TPL HALF BASE OUTSIDE OF WALL 35'-8 1/2" 6 1/4" 53'-9 3/4" TPL HALF BASE 72'-4 1/2" ARROW INDICATES WALL 90'-9/16" OUTSIDE TO TEMS 6 1/4" TPL HALF BASE OUTSIDE OF WALL 6 1/4" TPL HALF BASE OUTSIDE OF WALL 20
This guide can be used to prepare a specification for incorporating wall bracket jib cranes into a competitively bid construction project.
SECTION 14654 WALL BRACKET JIB CRANE ***** Gorbel, Inc. manufacturers a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station and industrial
More informationWALL MOUNTED ARTICULATING JIB CRANE
SECTION 14656 WALL MOUNTED ARTICULATING JIB CRANE ***** Gorbel, Inc. manufacturers a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station and
More informationOwner s Manual & Safety Instructions
Owner s Manual & Safety Instructions Save This Manual Keep this manual for the safety warnings and precautions, assembly, operating, inspection, maintenance and cleaning procedures. Write the product s
More informationSKATEWHEEL FLOW RACK
SKATEWHEEL FLOW RACK 2 ASSEMBLY INSTRUCTIONS: Steel King Industries recommends that this product be assembled only by qualified personnel, experienced in assembly of storage racks, and knowledgeable of
More informationSK2000 Boltless Pallet Rack Installation and Assembly Manual
SK2000 Boltless Pallet Rack Installation and Assembly Manual Steel King Industries, Inc. 2700 Chamber St Stevens Pont, WI 54481 (800) 826 0203 www.steelking.com info@steelking.com ASSEMBLY INSTRUCTIONS:
More informationASSEMBLY MANUAL FOR LADDERS, SAFETY CAGES, & PLATFORMS FOR THE FOLLOWING TANKS
ASSEMBLY MANUAL FOR LADDERS, SAFETY CAGES, & PLATFORMS FOR THE FOLLOWING TANKS 2.66" INSIDE STIFFENED FLAT BOTTOM TANKS 2.66" OUTSIDE STIFFENED FLAT BOTTOM TANKS 4.00" INSIDE STIFFENED FLAT BOTTOM TANKS
More informationSTANDARD PRACTICE INSTRUCTION
STANDARD PRACTICE INSTRUCTION DATE: March 1, 2001 SUBJECT: Scaffolding Safety Program. REGULATORY STANDARDS: 29 CFR 1910.28 Safety Requirements For Scaffolding. 29 CFR 1910.29 Manually Propelled Mobile
More informationThis guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.
SECTION 14651 FREE STANDING JIB CRANE ***** Gorbel, Inc. manufacturers a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station and industrial
More informationPanel Jack Pro System BRACING, ALIGNMENT AND SCAFFOLDING EQUIPMENT
IMPORTANT SAFETY INFORMATION FOR USERS OF THE REECHCRAFT, BRACING SYSTEM PLEASE READ BEFORE USE Panel Jack Pro System BRACING, ALIGNMENT AND SCAFFOLDING EQUIPMENT UK Edition 1.3 26/11/2012 1 TABLE OF CONTENTS
More informationCEILING MOUNTED ARTICULATING JIB CRANE
SECTION 14657 CEILING MOUNTED ARTICULATING JIB CRANE ***** Gorbel, Inc. manufacturers a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station
More informationHORSE SHELTERS 6, 12, 15, 18, & 24 SHELTERS ASSEMBLY MANUAL
HORSE SHELTERS 6, 12, 15, 18, & 24 SHELTERS ASSEMBLY MANUAL Read this manual before using product. Failure to follow instructions and safety precautions can result in serious injury, death, or property
More informationPROFESSIONAL SOUND SYSTEMS WPB OPERATING MANUAL AND USER GUIDE. WPB User Manual.indd :21:39
PROFESSIONAL SOUND SYSTEMS WPB OPERATING MANUAL AND USER GUIDE www.wharfedalepro.com WPB User Manual.indd 1 2010-2-1 15:21:39 WPB Series TABLE OF CONTENTS 1..INTRODUCTION 2..INSTALLATION AND WHARFEDALE
More informationPOST FRAME BUILDING STANDARDS
CASS COUNTY, MISSOURI BUILDING CODES, ENVIRONMENTAL HEALTH AND ZONING DEPARTMENT 30508 S. West Outer Road, Harrisonville, MO 64701 P- (816) 380-8134 F- (816) 380-8130 POST FRAME BUILDING STANDARDS 201.3
More informationINSTALLATION MANUAL. Guardian Series. QSUS 18 x 40. Manual
Manual # Guardian Series INSTALLATION MANUAL QSUS 18 x 40 LE MANUEL D'INSTALLATION INSTALLATION HANDBUCH HANDBOEK VAN DE INSTALLATIE MANUAL DE LA INSTALACIÓN 03/07 Copyright 2005. All Rights Reserved.
More informationSECTION LATCHWAYS CONSTANT FORCE POSTS
PART 1 GENERAL 1.1 SYSTEM DESCRIPTION SECTION 112429 LATCHWAYS CONSTANT FORCE POSTS A. Type of system required: Constant Force Posts (CFP(s)) Use with Latchways Lifeline or single point anchors B. System
More informationStreamline Solar Photovoltaic Structural Criteria for Residential Rooftop Solar Energy Installations (Streamline Solar Form 5)
TOOKIT DOCUMENT #5 Streamline Solar Photovoltaic Structural Criteria for Residential Rooftop Solar Energy Installations (Streamline Solar Form 5) Use of this document This toolkit document includes a one
More informationSK3000 Structural Pallet Rack Installation and Assembly Manual
SK3000 Structural Pallet Rack Installation and Assembly Manual Steel King Industries, Inc. 2700 Chamber St Stevens Pont, WI 54481 (800) 826 0203 www.steelking.com info@steelking.com ASSEMBLY INSTRUCTIONS:
More informationScaffold Safety
Scaffold Safety 6800-2.0 Associated OHS Process: General Industry and Construction Safety The master copy of this document resides in electronic format. Printed copies of this document are for convenience
More informationThis guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.
GORBEL PRODUCT SPECIFICATIONS 2010 Gorbel, Inc., P.O., Box 593, Fisher, New York 14453-0593 PHONE: 800-821-0086, FAX: 585-924-6273; WEBSITE: www.gorbel.com November SECTION 41 22 31PRIVATE FREE STANDING
More informationSECTION STEEL JOIST FRAMING
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 05 21 00 1. Use this section only for NCA projects. 2. Delete between //---// if not applicable to project. Also delete any other item or paragraph not applicable
More informationWALL CANTILEVER WORK STATION JIB CRANE
SECTION 14662 WALL CANTILEVER WORK STATION JIB CRANE ***** Gorbel, Inc. manufactures a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station
More informationOVERALL STRUCTURAL SYSTEM
EXECUTIVE SUMMARY The at the Pittsburgh International Airport, PA, is a 275,000 square foot multi-use building located directly adjacent to the airport s landside terminal. The building consists of an
More information55-Gallon Tilting Drum Ring
55-Gallon Tilting Drum Ring Owner s Manual WARNING: Read carefully and understand all ASSEMBLY AND OPERATION INSTRUCTIONS before operating. Failure to follow the safety rules and other basic safety precautions
More informationDynoRaxx EVOLUTION PR Guide to Code Compliant Installation
DynoRaxx EVOLUTION PR Guide to Code Compliant Installation Publication Number 100611 866.620.2410 dynoraxx.com Table of Contents I. Installer Responsibilities... 3 II. Simplified Procedure for Calculating
More informationSafeDeck Supported Scaffold System
SafeDeck Supported Scaffold System Table of Contents Origination 1 Range of Motion 1 Installation Efficiency 2 Third-Party Testimonial 2 SafeDeck Specifications 3 Competent Person 4 Tools Required 4 Components
More informationSECTION FABRICATED ENGINEERED STRUCTURES. A. Pre-engineered, shop-fabricated structural steel building with formed purlin framing.
PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 13 34 00 FABRICATED ENGINEERED STRUCTURES A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1
More informationAluminum Headache Rack
Instruction Manual Aluminum Headache Rack ITEM NO.: AHAR Read and understand this entire manual before assembling, installing, operating, or servicing this product. SAVE THIS MANUAL IMPORTANT SAFETY INFORMATION
More informationLoseke Technologies, Inc. p r e s e n t s
p r e s e n t s A Tour of PrecisionPlus Building Software for the Future Introduction would like to take this opportunity to thank you for your interest in PrecisionPlus, the leading metal building design,
More informationUSER'S GUIDE FOR INSPECTION OF DAMAGED STORAGE RACK SYSTEMS DON T WAIT UNTIL IT S TOO LATE!
USER'S GUIDE FOR INSPECTION OF DAMAGED STORAGE RACK SYSTEMS DON T WAIT UNTIL IT S TOO LATE! TABLE OF CONTENTS Common Safety Problems...4 Industry Standards...5 Severe Column Damage...6 Horizontal and Diagonal
More informationStandard Duty Cantilever Rack Installation and Assembly Guide
Standard Duty Cantilever Rack Installation and Assembly Guide Steel King Industries, Inc. 2700 Chamber St Stevens Pont, WI 54481 (800) 826 0203 www.steelking.com info@steelking.com ASSEMBLY INSTRUCTIONS:
More informationSECTION PLATE CONNECTED WOOD TRUSSES
SECTION 06173 PLATE CONNECTED WOOD TRUSSES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Shop fabricated wood trusses for roof and floor framing. 2. Bridging, bracing, and anchorage. B. Related Sections:
More informationSafety Documents > Safety Manual > Scaffolds
Safety Documents > Safety Manual > Scaffolds D. Scaffolds 1. General Requirements for All Scaffolds a. Scaffolds shall be furnished and erected in accordance with this standard for persons engaged in work
More informationStructural Criteria for Residential Rooftop Solar Energy Installations
Structural Criteria for Residential Rooftop Solar Energy Installations STEP 3 Expedited Structural Criteria Use of this document This toolkit document includes a list of structural criteria for over-the-counter
More informationStructural Criteria for Residential Rooftop Solar Energy Installations
PV TOOLKIT PV TOOLKIT DOCUMENT #5 Structural Criteria for Residential Rooftop Solar Energy Installations Use of this document This toolkit document includes a one-page list of structural criteria for over-the-counter
More informationStructural Criteria for Residential Rooftop Solar Energy Installations
SWH TOOLKIT DOCUMENT #4 Structural Criteria for Residential Rooftop Solar Energy Installations Use of this document This toolkit document includes a one-page list of structural criteria for over-the-counter
More informationModel m x 1.98 m NPRM with Roof Pads For 1.2 m Antenna Systems
Installation Instructions 800026-0 Model 60057-03.98 m x.98 m NPRM with Roof Pads For.2 m Antenna Systems ASC Signal Corporation 35 Industrial Park Drive Smithfield, NC 27577 USA Telephone: +-99-934-97
More informationPreference Slimline 5537 Utility Console I NSTALLATION GUIDE
Preference Slimline 5537 Utility Console I NSTALLATION GUIDE WARNING Failure to install the 5537 as described in this installation guide may cause the unit to collapse, resulting in serious injury to personnel.
More informationDesigned To Meet Your Operational Needs
Designed To Meet Your Operational Needs Contact Us Thank you for considering Pro Tec Engineered Buildings. We look forward to discussing your next building project. Pro Tec Engineered Buildings A Division
More informationBuilding and Safety Division 245 E Bonita Avenue Ph:
Building and Safety Division 245 E Bonita Avenue Ph: 909-394-6260 E-Mail: solar@ci.san-dimas.ca.us Use of this document Applicants for Expedited Permitting must complete and submit this document in its
More informationConergy SolarFamulus II
Conergy SolarFamulus II Installation manual www.conergy.com Table of Contents Table of Contents SolarFamulus II for universal use on flat roofs 1 Introduction 1 1.1 Short description 1 1.2 Intended use
More informationOpen-Web Truss Long Span Installation Guidelines
TECHNICAL BULLETIN #301 Open-Web Truss Long Span Installation Guidelines RedBuilt has maintained a policy of manufacturing and marketing products of the highest quality to our customers. We guarantee the
More information.1 American Institute of Steel Construction (AISC) Specifications for Steel Buildings AISC
05 12 00 STRUCTURAL STEEL FRAMING Page 1 of 3 1 General 1.1 SECTION INCLUDES.1 Structural steel framing and support members 1.2 RELATED SECTIONS.1 Section 05 50 00 Metal Fabrications 1.3 REFERENCES.1 American
More informationSECURE. UNIVERSAL. MOUNTING. Tilt Kit Installation Manual
SECURE. UNIVERSAL. MOUNTING Tilt Kit Installation Manual 1.0 INTRODUCTION... 3 2.0 KITS / PRODUCT RANGE... 4 2.1 Leg Kits... 4 2.2 Rail Kits... 4 3.0 PREPARATION FOR INSTALLATION... 5 3.1 Applications...
More informationStructural Criteria for Residential Rooftop Solar Energy Installations
TOOLKIT DOCUMENT #5 Structural Criteria for Residential Rooftop Solar Energy Installations Use of this document This toolkit document includes a one-page list of structural criteria for espedited approval,
More informationPage 10-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LIGHTING AND SIGNS
Page 10-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 FOUNDATION SYSTEM SECTION 10 CONTENTS INTRODUCTION... 10-3 PRODUCT BENEFITS... 10-3 RECOMMENDED FACTORS of SAFETY for DESIGN...
More informationSectional Scaffold. Scaffold Access Unit Installation Instructions
Sectional Scaffold Scaffold Access Unit Installation Instructions 2 Scaffold Access Unit Installation Instructions SAU6 Painted: 18.3 lb Galvanized: 20.2 lb Label 7112A0003 NOTICE Please read and follow
More informationStructural Criteria for Residential Rooftop Solar Energy Installations
Structural Criteria for Residential Rooftop Solar Energy Installations This document applies to flush mounted solar arrays installed on the roofs of wood framed one and two family dwellings. Flush mounted
More informationSECTION STRUCTURAL RETROFIT ROOF SUB-FRAMING SYSTEM
SECTION 13 34 21 - STRUCTURAL RETROFIT ROOF SUB-FRAMING SYSTEM PART 1 - GENERAL 1.1 DESCRIPTION A. The structural retrofit roof sub-framing system will provide support for a new metal roofing system constructed
More informationF500 Steeplechase Waterjump with Valve Option
Gill Athletics www.gillathletics.com Phone: (800) 367-3090 Fax: (217) 367-8440 Excavation F500 Steeplechase Waterjump with Valve Option Installation Guide Read all instructions before installing!!! Establish
More informationSECTION DECORATIVE METAL RAILINGS
SECTION 05 73 00 DECORATIVE METAL RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES A. Vertical Stainless Steel Cable Railing System. B. Horizontal Stainless Steel Cable Railing System. 1.2 RELATED SECTIONS
More informationCITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS
CITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS PART 1 - GENERAL 1.01 SUMMARY A. Section Includes furnishing and installing chain-link fabric fence, gate, and appurtenances. 1.02
More informationAmerican Residential Deck Railing Design Guide
American Residential Deck Railing Design Guide Intended for use by Designers & Architects Engineers & Professional Installers 8 th Edition ProbuiltRailings.com TABLE OF CONTENTS ProBuilt Design Manual
More informationPallet Gate Installation Instructions and Operators Manual
Pallet Gate Installation Instructions and Operators Manual Models PLG-6084 PLG-7284 PLG-6084-SST PLG-7284-SST Table of Contents Product Information...2 Installation Instructions...4 Parts and Reordering...7
More informationPE45 AMAZON MONKEY BARS OWNER'S MANUAL
PE45 AMAZON MONKEY BARS OWNER'S MANUAL WARNING! The disassembled product may contain small parts which pose a choking hazard to children under 3. IMPORTANT: This product may contain sharp points and small
More informationSeries 8009A 9-Meter Earth Station Antenna. Site Preparation Manual
Series 8009A 9-Meter Earth Station Antenna Site Preparation Manual Manual Part No. 42S314B April 2003 Notice All Rights Reserved The information contained in this document is proprietary to ViaSat, Inc.
More informationDEALER PRICE BOOK CO, KS, MD, NM, OH, PA. 210 Airport Rd. Mount Airy, NC Toll Free: Fax:
2018 DEALER PRICE BOOK CO, KS, MD, NM, OH, PA 210 Airport Rd. Mount Airy, NC 27030 Toll Free: 800.579.8589 Fax: 336.719.2091 ABOUT US Eagle Carports, Inc. has been producing high-quality metal structures
More informationStructural Criteria for Residential Rooftop Solar Energy Installations
PV TOOLKIT DOCUMENT #5 Structural Criteria for Residential Rooftop Solar Energy Installations Use of this document This toolkit document includes a one-page list of structural criteria for over-the-counter
More informationALUMINUM CURB RAMP. Model 98037
ALUMINUM CURB RAMP Model 98037 Set up And Operating Instructions Diagrams within this manual may not be drawn proportionally. Due to continuing improvements, actual product may differ slightly from the
More informationCANTILEVER RACK SPECIFICATIONS PART 1 GENERAL 1.1 SCOPE 1.2 APPROVED MANUFACTURER 1.3 REGULATORY ORGANIZATIONS AND GROUPS 1.4 QUALITY ASSURANCE
CANTILEVER RACK SPECIFICATIONS PART 1 GENERAL 1.1 SCOPE This specification is intended to describe the general requirements applicable to a proper structural cantilever rack design. In addition, it is
More informationStructural Criteria for Residential Rooftop Solar Energy Installations
SWH TOOLKIT DOCUMENT #4 Structural Criteria for Residential Rooftop Solar Energy Installations Use of this document This toolkit document includes a one-page list of structural criteria for over-the-counter
More informationOwner s Manual & Safety Instructions
Owner s Manual & Safety Instructions Save This Manual Keep this manual for the safety warnings and precautions, assembly, operating, inspection, maintenance and cleaning procedures. Write the product s
More informationASSEMBLY INSTRUCTIONS RESIDENTIAL SOLUTION CROSSRAIL GROUND MOUNT SYSTEM USA
ASSEMBLY INSTRUCTIONS RESIDENTIAL SOLUTION CROSSRAIL GROUND MOUNT SYSTEM USA TABLE OF CONTENTS TABLE OF CONTENTS SAFETY REGULATIONS MATERIALS REQUIRED ASSEMBLY ENGINEERING DRAWINGS TERMS AND CONDITIONS
More informationModular Simplicity Dero
B I K E H AV E N Modular Simplicity The Bike Haven bridges the gap between short and long term bike parking. The simple, modular canopy design makes it easy to create the bike shelter that fits your needs.
More informationHouston Community College 3200 Main Parking Garage November 15, 2010 Houston Community College
SECTION 323113 - CHAIN LINK FENCES AND GATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationSECTION COLD-FORMED METAL TRUSSES
SECTION 054400 COLD-FORMED METAL TRUSSES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationComparison letter for MegaMet s MegaStorm Door against door construction details in FEMA 361 section 7.4.1
October 20, 2014 MegaMet Industries, Inc. P.O Box 635 Birmingham, AL 35201 ATTN: Re: Edward Wall ewalljr777@gmail.com Comparison letter for MegaMet s MegaStorm Door against door construction details in
More informationOPERATOR S SAFETY MANUAL
June 2011 OPERATOR S SAFETY MANUAL Sumner Pipe Jacks www.sumner.com 7514 Alabonson Road Houston, TX 77088 U.S.A ph: 281.999.6900 fax: 281.999.6966 470 Collier MacMillan Drive Unit 2 & 3 Cambridge, ON N1R
More informationCity of Santa Monica. Building and Safety Division. Structural Criteria for Residential Rooftop Solar Energy Installations
City of Santa Monica Building and Safety Division Structural Criteria for Residential Rooftop Solar Energy Installations Effective: 9-30-2015 Revised: 9-30-2015 Use of this document This toolkit document
More informationTypical Deck. CONSTRUCTION TIP SHEET 5 Basic Decks w/ 60 lb Live Loading
CONSTRUCTION TIP SHEET 5 w/ 60 lb Live Loading April 1, 2017 This Tip Sheet reflects code requirements of the 2015 International Residential Code (IRC) with Washington State Amendments which update the
More informationUSER'S GUIDE FOR INSPECTION OF DAMAGED STORAGE RACK SYSTEMS DON T WAIT UNTIL IT S TOO LATE!
USER'S GUIDE FOR INSPECTION OF DAMAGED STORAGE RACK SYSTEMS DON T WAIT UNTIL IT S TOO LATE! TABLE OF CONTENTS Introduction...3 Major Safety Issues For Pallet Racking...4 Industry Standards...5 Severe Column
More information1. Base plates, setting plates and anchor rods for columns. 8. Lintels if connected to structural steel columns.
PAGE 051200-1 SECTION 051200 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,
More informationReliant Holdings Ltd Safety Management System
Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 7 Purpose The purpose of this program is to prevent injuries due to falls from elevated work areas and ensure employees
More informationTechnical Assignment 3 December 3, 2007
Technical Assignment 3 December 3, 2007 101 Eola Drive, Orlando, FL Justin Raducha Pennsylvania State University Faculty Advisor: M. Kevin Parfitt Table of Contents Table of Contents... 2 Executive Summary...
More informationDraft. Not yet Approved
2016 Part 3.2.5 Recommended Design Criteria and Functional/Operating Guidelines for Overhead Bridge and Cantilever Structures and Placement of Grade Crossing Warning Devices Revised 2017 (8 Pages) A. Purpose
More informationC Series Mechanical Pit Levelers. P.O. Box 338 Spring Hill, Tennessee fax:
C Series Mechanical Pit Levelers SM P.O. Box 338 Spring Hill, Tennessee 37174 1-800-251-3382 fax: 931-486-0316 www.pioneerleveler.com DO NOT install, operate or service product unless you have read and
More informationPS 3000 Installation Manual Step-By-Step Procedures C.9. DOOR AND WINDOW OPENINGS C.9.1 PREPARE IN ADVANCE. C.9.2 VBUCK CONSTRUCTION.
C.9. DOOR AND WINDOW OPENINGS Openings for doors and windows are formed with bucks, or frames, which are constructed to the rough opening dimensions required for the doors and windows to be installed.
More informationWIND SPEED AND DESIGN CRITERIA FOR FLEXIBLE FACE SIGNS CONSTRUCTED OF ABC EXTRUSIONS
WIND SPEED AND DESIGN CRITERIA FOR FLEXIBLE FACE SIGNS CONSTRUCTED OF ABC EXTRUSIONS 2005 EDITION This edition is based upon ASCE 7-98 recommendations for wind speed and wind loads. These have changed
More informationSTATE UNIVERSITY CONSTRUCTION FUND. UNIVERSITY CON DIRECTIVE 5-1 Issue date: October 2014
STATE STRUCTION FUND DIRECTIVE 5-1 Issue date: October 2014 STRUCTURAL STEEL 1. General: It is the Fund's policy that the design of the structural steel is the prime responsibility of the project's Structural
More informationSystems Scaffold Tubular Scaffold Access Unit Installation Instructions
Systems Scaffold Tubular Scaffold Access Unit Installation Instructions 2 Tubular Scaffold Access Unit Installation Instructions LTUB7 Galvanized: 24.1 lb Label 7112A0003 NOTICE Please read and follow
More informationInstallation Instructions
EconoDrain Trench Forming System Installation Instructions MultiDrain We Drain Your Site, Not Your Budget MultiDrain Systems, Inc. P.O. Box 88, Barium Springs, NC 28010 (704) 508-1010 or Toll Free 800-433-1119
More informationOwner s Manual & Safety Instructions
Owner s Manual & Safety Instructions Save This Manual Keep this manual for the safety warnings and precautions, assembly, operating, inspection, maintenance and cleaning procedures. Write the product s
More informationVHSR-SERIES RACKS FOR SHEET MATERIAL
VESTIL MANUFACTURING CORP. 2999 North Wayne Street, P.O. Box 507, Angola, IN 46703 Telephone: (260) 665-7586 -or- Toll Free (800) 348-0868 Fax: (260) 665-1339 www.vestilmfg.com e-mail: sales@vestil.com
More informationTCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II
SECTION 052100 - STEEL JOISTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections
More informationAnchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi
STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel
More informationKE DURASOL GENNIUS PERGOLA SYSTEMS
KE DURASOL GENNIUS PERGOLA SYSTEMS SYSTEM NOTES: KE DURASOL GENNIUS PERGOLA SYSTEM WITH RETRACTABLE FABRIC SHALL BE INSTALLED PER MANUFACTURER'S SPECIFICATION. 1. PERGOLA FABRIC SHALL BE RETRACTED PRIOR
More informationGroundTrac. Installation Manual
APPLICATION: The GroundTrac system is designed with a minimum amount of installed footings at greatly reduced labor. The system integrates with ordinary 1-1/2 schedule #40 galvanized water pipe. This ground
More informationMulti-Purpose Scaffolding Instruction Manual
Limited Warranty World Factory, Inc. World Factory, Inc. (Seller) warrants to the original Buyer only, that each YellowStone Product will be free from defects in material and workmanship for a period of
More informationTABLE OF CONTENTS. 1.0 INTRODUCTION 1.1 Greenstone Structural Engineered Panels 1.2 Drawing and Element Numbers
version 2.5 updated as of 08.04.2017 2 TABLE OF CONTENTS 1.0 INTRODUCTION 1.1 Greenstone Structural Engineered Panels 1.2 Drawing and Element Numbers 2.0 ASSEMBLY 2.1 Sequence of Assembly 2.2 Preparation
More informationGUIDE SPECIFICATIONS CURA ADJUSTABLE REROOF FRAMING SYSTEMS SECTION REROOFING ADJUSTABLE FRAMING SYSTEM
- --- -- ----..-------~------------------------------------ GUIDE SPECIFICATIONS CURA ADJUSTABLE REROOF FRAMING SYSTEMS SECTION 07415 REROOFING ADJUSTABLE FRAMING SYSTEM PART 1 - GENERAL 1.01 SCOPE A.
More informationMade in U.S.A. Wave Style Bike Rack Submittal Sheet. Materials: 1.5 Schedule 40 Steel Pipe (1.
Submittal Sheet Materials: 1.5 Schedule 40 Steel Pipe (1.9 OD) Finishes: Powder Coat Our powder coat finish assures a high level of adhesion and durability by following these steps: 1. Sanded down 2. Washed
More informationSECTION PRE-ENGINEERED EXTRUDED ALUMINUM DECKING WALKWAY COVERS SPECIFICATION
Awning Works Inc Aluminum Decking Walkway Cover Specification CSI- Division 10 SECTION 10530 PRE-ENGINEERED EXTRUDED ALUMINUM DECKING WALKWAY COVERS SPECIFICATION PART 1 GENERAL 1.01 DESCRIPTION OF WORK
More informationSteps in Building a Shed
Steps in Building a Shed The design and location of your new shed will depend on how it will be used - a shed for storing tools will be much simpler than one you intend to use as a small shop. For example,
More informationStructural Criteria for Residential Rooftop Solar Energy Installations
TOOKIT DOCUMENT #5 Structural Criteria for Residential Rooftop Solar Energy Installations Use of this document This toolkit document includes a one-page list of structural criteria for over-the-counter
More informationSECTION STRUCTURAL METAL FRAMING
SECTION 05100 STRUCTURAL METAL FRAMING PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Structural steel framing including lintels, shelf angles, bearing plates, anchor bolts and other items as shown on
More informationBuilding Specifications for City of Pleasant Hill
1 Building Specifications for City of Pleasant Hill RECTANGULAR FABRIC TENSION MEMBRANE COVER REFERENCES Except where more stringent requirements are specified, comply with the applicable requirements
More informationSECTION ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Casino Modular Railing System
SECTION 05 5200 ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Casino Modular Railing System PART 1 GENERAL 1.01 WORK INCLUDED A. Furnish and/or install stainless steel railings and components. 1.02 REFERENCE
More informationMade in U.S.A. Sunrise Bike Rack Submittal Sheet. Materials: Finishes: Mount Options: Capacity: Setbacks:
Submittal Sheet Materials: 1.5 Schedule 40 Steel Pipe (1.9 OD) Finishes: Galvanized An after fabrication hot dipped galvanized finish is available Powder Coat Our powder coat finish assures a high level
More informationSJI Code of Standard Practice
Standard Practice CODE OF STANDARD PRACTICE FOR STEEL JOISTS AND JOIST GIRDERS SECTION 1 GENERAL 1.1 SCOPE Adopted by the Steel Joist Institute April 7, 1931 Revised to May 18, 2010 - Effective December
More informationSECTION ORNAMENTAL ALUMINUM RAILING
SECTION 05730 ORNAMENTAL ALUMINUM RAILING PART 1 GENERAL 1.1 SECTION INCLUDES A. Aluminum Pipe Railing 1.2 RELATED SECTIONS A. Section 03300 Cast-In-Place Concrete: Placement of sleeves cast in concrete.
More informationElevation "L" ASTOR II DESIGN CRITERIA: 2012 International Residential Code with Georgia Amendments
REVISION CHANGES: REV. NO. REV. DATE C COPYRIGHT 2014 TAYLOR MORRISON --- THESE DRAWINGS AND ITS REPRODUCTIONS ARE THE PROPERTY OF taylor morrison AND MAY NOT BE REPRODUCED, PUBLISHED OR USED IN ANY WAY
More information