Line of balance programming

Size: px
Start display at page:

Download "Line of balance programming"

Transcription

1 Line of balance programming 1. INTRODUCTION Most contractors are familiar with programming a single project where a critical path analysis or, more likely, a bar chart is drawn up indicating what activities must occur, when they must occur, and for how long they must occur. With multiple, repetitive projects i.e. the construction of 100 similar houses it is impractical to draw up 100 different bar charts and very cumbersome to show the construction of the 100 houses on a single bar chart. The method of doing the project is also different as the contractor building 100 houses will split his labour force into gangs each of which will specialise on one facet of the house construction, i.e. the superstructure brickwork. What this means is that the contractor will have one or any number of gangs of bricklayers that just build the superstructure for the houses. When they start any particular unit the sub-structure brickwork and floor is already complete and they leave the unit when the superstructure is complete and move onto the next unit. It is this forming of gangs focusing on only one aspect of the job that requires the specialised techniques of balancing the number and productivity of the gangs. This is to ensure a constant flow of work on the construction site. The best way to explain the technique is to work through an example. Lets take a housing project for 100 identical units each as indicated overleaf.

2

3 Line of balance programming 2. THE LINE OF BALANCE METHOD The first step is to identify the activities that you determine will be performed by separate gangs. Let us use the following as an example: ACTIVITY EXCAVATE AND CONCRETE TO FOOTINGS SUB-STRUCTURE BRICKWORK FILLING, DPC AND CONCRETE TO FLOOR SUPERSTRUCTURE BRICKWORK ROOF PLASTERING CEILINGS SCREED FINAL FINISHES Each of these activities thus becomes one item on our programme but, more importantly, also represents the work that will be performed by one gang of workers. Thus each housing unit will be built by nine separate crews each handling one of the activities shown above. To keep up with the necessary rate of construction for the overall project, there may well be more than one gang. However only one gang will work on a single unit. Thus there could be three or four units having the superstructure brickwork built at the same time. Step 2 is to determine the number of man hours needed to complete each activity for one house. Example : Superstructure brickwork : Number of man hours = Number of stock bricks divided by the production of one bricklayer per hour. Total number of stock bricks = (rough quantities taken from drawing) Production of bricklayer per hour = 800 per day / 8 hours = 100 per hour. Number of man hours = / 100 = 210 man hours. Use the following as an example : ACTIVITY MAN HOURS PER ACTIVITY EXCAVATE AND CONCRETE TO FOOTINGS 50

4 SUB-STRUCTURE BRICKWORK 70 FILLING, DPC AND CONCRETE TO FLOOR 95 SUPERSTRUCTURE BRICKWORK 210 ROOF 150 PLASTERING 80 CEILING 80 SCREED 90 FINAL FINISHES 150 Step 3 is to decide what the optimum gang size will be per activity per house. Example : Superstructure brickwork : Due to the size of the house you decide that the optimum gang size for the house is 6 bricklayers. The decision as to the gang size is based on experience and the size of the individual unit. The number of men in the gang is the productive workers and does not include assistants or general workers. Use the following as an example: ACTIVITY OPTIMUM GANG SIZEMAN HOURS PER ACTIVITY EXCAVATE AND CONCRETE TO FOOTINGS8 MEN 50 SUB-STRUCTURE BRICKWORK 4 MEN 70 FILLING,DPC AND CONCRETE TO FLOOR 8 MEN 95 SUPERSTRUCTURE BRICKWORK 6 MEN 210 ROOF 3 MEN 150 PLASTERING 3 MEN 80 CEILINGS 4 MEN 80 SCREED 4 MEN 90 FINAL FINISHES 6 MEN 150 Step 4 is to decide what handover rate of completed houses you require per week. This is influenced by the number of houses you are contracted to build and the contract time period stipulated. Let us presume that the contract documents stipulate you must construct 100 houses in a 6 month period i.e. 26 weeks. The first 50% of the contract will be taken up with building the first unit and thereafter the units will be completed at a rate of 100/13 = 7.69 say 8 per week. If once the line of balance calculations are completed you discover that the completion date is not met then the handover rate must be adjusted upwards i.e. to 10 per week. The calculations must then be redone to determine if the new completion date is correct. Step 5 is to determine the total number of men requiredto be working on a specific activity in order to complete exactly the handover rate i.e. 8. This is to adjust the optimum gang size or to determine the number of gangs used on the project.

5 A simple formula exists, as follows : Example : Superstructure Brickwork : This implies that you have 7 gangs of 6 men working on 7 houses at any one time. The optimum gang size was decided as 6 men so there will be seven groups of such men. The following sheet has calculated the total number of men up to roof. As an exercise it would be good to calculate the total number of men requiredfor the other activities. Step 6 is to adjust this total number of men into multiples of the optimum gang size. The total number of men is not always a multiple of what you decided to use as the optimum gang size. For example the optimum gang size for Sub-Structure brickwork is 4. The total number of men requiredis 14 which is not a multiple of 4. You must therefore choose how many gangs you would

6 prefer to use. You can either use 3 gangs of 4 men giving 3 x 4 = 12 men in total or 4 gangs of 4 men giving 4 x 4 = 16 men in total. Or you might re-examine the choice you made of optimum gang size. Your choice of number of gangs has a big influence on the contract completion date as we shall soon discover. Step 7 is to review the rate of production per activity. To meet the contract period we calculated 8 units per week to be our handover rate. That was based on using exactly the right number of men to achieve that rate e.g. for sub-structure brickwork the number of men was 14. In step 6 we had to choose a multiple of 4 which resulted in the total number of men changing to 16. This results in the handover rate for that activity increasing in relation to the number of extra men used. The revised rate of production is thus calculated as being: In the case of sub-structure: Let us call this revised rate of production RN. Thus we see that the increased number of men has resulted in the handover rate for the activity sub-structure brickwork increasing from 8 to NOTE: If less men had been used than the original exact gang size then the revised handover rate would be less than 8. The following sheet has calculated the revised rate of production up to roof. It would be good to complete the rest of the table for yourself.

7 Step 8 is to calculate the time period between the start time of an activity on the first house and the start time for the same activity on the last house. In other words if the activity "Excavate and concrete to foundation" of house number 1, starts on day 1, then when does the, "Excavate and concrete to foundations" activity start on house No 100. The formula for this calculation is to take the total number of units (100) and deduct 1 (i.e. 99). Multiply this figure by 5 (the number of working days in a week). This figure then has to be divided by the rate of production, as revised. So if activity "Excavate and concrete to foundations" for house no 1 starts on day 1 then "Excavate and concrete to foundations" for house no 100 will start on day 78. The following sheet has calculated the total time lapse up to roof level and the actual time calculated rounded off to complete days.

8 Step 9 is the final step before drawing the programme. Thus now we must calculate how long it takes to complete each activity of the house. For example how long does it take to complete the roof on one of the units. This is easily calculated by taking the man hours per activity and dividing it by the gang size that is working on the activity and multiply it by the number of hours in the working day. Let s do the calculation for roof: In other words it takes the roof gang 7 days to erect the roof on each house. We are now ready to draw the Line of Balance Chart, based on the Figures in the following table:

9 Step 10 is to draw the line of balance chart. Take a piece of graph paper and indicate the number of days on the horizontal scale and the number of units on the vertical scale: See Diagram A. DIAGRAM A The diagram above shows the units along the vertical axis. Each division represents one unit with the total being 100. As these are the units to be built the bottom line is not zero, as often happens with graphs, but one - that is the first Unit. The basis for drawing up the Line of Balance diagram is contained in the figures in the table. The figures that were calculated in the early part of this module. The contract will start with the first activity on the first unit. That is "Excavation & Concrete" on Unit No 1. DIAGRAM B

10 The table shows that it takes one day to complete the excavation and concrete to each unit. So the start of our first "bar" will be at Day One and Unit One. This puts it in the bottom left corner of the diagram. From that point we now need to plot the "Time Lapse" - that is the time that will pass before Activity One is done on Unit 100. Thus the excavation on Unit 100 will be done on Day , this being the Time Lapse shown in the table for this activity. We can thus plot an inclined line, or bar form Day 1 to Day 78. The duration of the activity, in this case one day, is shown by the width of the bar. We will add these bars to our diagram as we go along until all nine activities have been added. DIAGRAM C The following activity is "Sub-structure Brickwork". Here the duration of the activity is 3 days and the Time Lapse between Unit 1 and Unit 100 is 54 days. Since this lapse of time is shorter than that of Activity One this will mean that it will be bar at a steeper angle than the first one. This is because the progress from first Unit to last Unit is only 54 days, as opposed to 77 days for Activity One. This will mean that we need to start drawing our bar from the top down. Obviously the gang doing this activity will be working as a faster pace than the previous gang. They cannot do their work until the previous activity is complete. So we need to programme them to follow on at Unit 100 immediately after the gang doing Activity One. Thus they can start work on the sub-structure brickwork on Unit 100 on day 79, the previous gang finished their work on Day 78. Working back from there we find that this activity can start on Unit 1 on Day 25, immediately after Day 24 on the horizontal scale. The duration of the activity is 3 days so the width of the bar will indicate this. This bar then will run from Day 25 to Day 27 for Unit 1 and from Day 79 to Day 81 for Unit 100. We see here one of the strengths of this form of programming. The inclination might be to start this gang on Unit 1 immediately after the first gang had finished their work. However because they move at a faster pace than the previous activity, they would soon run out of work and be waiting

11 for the previous gang to complete. Now we know that we can bring them in more than three weeks afterwards and still keep our project on programme for final completion. DIAGRAM D The next activity "Fill & Concrete" is the casting of the floor slab, which is programmed to be done before the superstructure brickwork is started. The duration is two days and the elapsed time is 74 days. This is considerably longer than the previous activity so it can start immediately after the substructure brickwork on Unit 1 is done. As this gang is slower they will progressively fall further and further behind the gang working on Activity Two. So on Day 28 the gang can start backfilling on Unit 1. The concrete will be cast the following day, Day 29 and then they will proceed to Unit 2. With the time lapse being 74 days work will start on Unit 100 on Day 102. The bar itself is narrower since the duration is only two days. DIAGRAM E

12 . Now comes a major activity, that of the "Superstructure Brickwork". This activity take five days to complete on each unit. It has a time lapse period of 62 days, so will catch up on the previous gang. So once again we will start calculating from Unit 100 and work backwards. The previous activity ends on Unit 100 on Day 104. Working back from there that gives us Day 42 (104-62) as the first day of Activity Four on Unit 1. The activity takes five days so work will end on Unit 1 on Day 46. Again we have a case here of a gang that need not be brought onto site until the previous activity is well advanced. In fact some twenty units will have had the concrete floor cast before they need to start work. Then they will be right behind on Unit 100, if all goes according to the programme. DIAGRAM F

13 Looking at the figures for Activity Five we see that although the duration is longer, 7 days, the time lapse works out to the same 62 days. Thus the bar will run exactly parallel to the previous one, though it will be a thicker bar. Theoretically work could start immediately on the following day, Day 47. However it is often advisable to leave a day or so between such activities for any delays that may occur on the previous activity. This is known as a "buffer" and makes some allowance for things that may go wrong. This is particularly important on activities that run parallel, such as these two. Any delay with the bricklaying gang will immediately affect the roofing team. The buffer does make some allowance for such things. So the bar for Activity Five runs next to the previous one with just a one day allowance between them. DIAGRAM G

14 This brings us to "Plaster", Activity Six. The duration is four days and the elapsed time is 66 days. This makes it a slower activity than the previous one. Thus we can start immediately after Activity Five is completed on Unit 1 and expect to see the gap between the two bars widening as the job progresses. Work will start on Day 55 and Unit 1 will be completed by this team on Day 58. With a time lapse of 66 days, work will begin on Unit 100 on Day 121 with completion on Day 124. DIAGRAM H

15 The "Ceilings" are the next activity in the programme. This again moves at a faster rate than the plaster with an elapsed time of 57 days. Working from Unit 100, work can start on that unit straight after the plaster is completed. That means work will start on Day 125. Taking away the elapsed time of 57 days we get to Day 68 as the time the gang will start work on site. They will begin Unit 1 on that day, completing it after four days of work, on Day 71. DIAGRAM I The floor screeds will now be done. This is Activity Eight and it has a duration of three days. The elapsed time is 69 days so that progress will be slower than the previous activity. Thus we be able to set the gang to work on Unit 1 as soon as it is available. They will begin work on Day 72, finishing on Day 74. The gang will complete work on Unit 100 over the period of Day 141 to Day 143. DIAGRAM J

16 Then we come to the final activity, that of "Final Finishes". It has a duration of four days and an elapsed time of 62 days. This will require us to work backwards from Unit 100. Thus the finishings to Unit 100 can take place over the time period of Days 144 to 147. Going backwards we then find out this team will be able to start on Unit 1 on Day 82. They will complete on Day 85. If one looks at the final programme most of the activities are fairly well balanced, i.e. without too much idle time between the finish of one activity and the start of the next activity. Remember the idle time is caused by the time lapses for activities being different. There is idle time caused by the fact that the "sub-structure brickwork" activity has a time lapse of 54 days comparedto excavations before it with a 77 day time lapse and "fill and concrete" after it with a 74 day time lapse. If we could get sub-structure brickworks time lapse to be closer to days then the situation could be improved. This can be achieved in a number of ways: 1. When revising our total number of men to be used in sub-structure brickwork we could round the total down to the lesser multiple of the gang size per house. This would slow down the revised rate of build and therefore increase the time lapse. 2. We could take another look at our optimum size and change the number of men per activity. As we based our original calculations on what we consideredto be the optimum gang size this form of balancing should be the last to be undertaken. 3. If the handover rate is too slow an extra gang could be introduced for the whole duration of the activity or only a portion of the activity. For example in order to increase the handover rate of screed for a portion of the contract one could increase the number of gangs from 5 to 6 from midway through the activity. This would mean that for the first 50 units the handover rate would be 7.2 and the time lapse 69. For the second 50 units the handover rate would be units and the time lapse 46. This again would have the effect of reducing the idle time between activities.

17 Line of balance programming 3. MONITORING PROGRESS The target progress on site is easily read from the graph by drawing a vertical line from the date on the horizontal axis that coincides with the date on which the progress report is being done on. This is shown on Diagram K. Where the vertical line drawn intersects each activity a horizontal line is drawn to the vertical axis. From this the number of units which should have been completed can be determined. The actual progress must be arrived at by walking around the site and noting what activities for what houses are actually complete. DIAGRAM K: From this diagram we can see the following: it is Day 60 when the progress is being checked Activity 1 - the excavation and concrete to the footings of Unit No 82 should be underway Activity 2 - the substructure brickwork to Unit 75 should be complete Activity 3 - fill and concrete to Unit 43 should have been done Activity 4 - superstructure brickwork should be completed as far as Unit 24 Activity 5 - Unit 11 should have its roof completed Activity 6 - the plastering team will have just started on site and should have completed the first three Units

18 If a check on site reveals progress on site to be different to that indicated above then an investigation must take place. A gang working at a slower pace will sooner or later interfere with the progress of the following teams. A gang working at a faster pace will catch up the one in front of them and run out of work.

19 Line of balance programming 4. CONCLUSION The Line of Balance System of programming was developed for housing schemes with multiple units. It is ideal where the units are identical or very similar in size as the amount of work in each unit will be substantially the same. The system has also been used for programming the tower sections of high-rise buildings with multiple floors that are basically similar. Once the principles are understood it is a simple system, though the calculations involved can be onerous. Obviously the secret for a smooth flow of work is to balance the work teams so that they produce completed units at approximately the same rate. For activities with a large work content it may require having more than one gang. Thus several units may be under construction at the same time but the overall rate of production will be approximately the same as the other activities. Thus this activity is kept in balance with the others. For activities where the work content is low, for example glazing on a small housing unit, there may be no alternative but that the gang is called in when required. Thus the glazier will start work and, because he progresses at above the normal rate, he will catch up to the team in front. He will then leave the site and return once there were enough units ready for him to make it worthwhile. Line of Balance is a powerful programming tool for multi-unit contracts. It is easy to understand and provides vital information on the progress requiredon every unit to be able to meet the contract period.

Homeowners Guide To. Understanding the Construction. Process

Homeowners Guide To. Understanding the Construction. Process A Homeowners Guide To Understanding the Construction Process Produced By H.M.P. Builders, Inc. 1036 SW 13 th Court Pompano Beach, FL 33069 Phone # 954-785-7555 Fax # 954-785-9828 License # CGC 009174 &

More information

PART A: JOB PROCDRE FOR PLASTERING

PART A: JOB PROCDRE FOR PLASTERING PART A: JOB PROCDRE FOR PLASTERING 1. SCOPE: The scope of this procedure shall apply to all cement plaster finishes to column, ceilings, walls and similar surfaces on backgrounds met with such as brick,

More information

Project Planning & Control Prof. Koshy Varghese Department of Civil Engineering Indian Institute of Technology, Madras

Project Planning & Control Prof. Koshy Varghese Department of Civil Engineering Indian Institute of Technology, Madras Project Planning & Control Prof. Koshy Varghese Department of Civil Engineering Indian Institute of Technology, Madras Lecture 10 Lesson 04 Gantt / Bar Chart History, Representation Progress Monitoring,

More information

CONSTRUCTING THE BUILT ENVIRONMENT

CONSTRUCTING THE BUILT ENVIRONMENT VOCATIONAL WJEC LEVEL 1 / 2 AWARD in CONSTRUCTING THE BUILT ENVIRONMENT SAMPLE ASSESSMENT MATERIALS - External Teaching from 2018 WJEC LEVEL 1/2 VOCATIONAL AWARD IN CONSTRUCTING THE BUILT ENVIRONMENT esam

More information

Small House Extension Project

Small House Extension Project Small House Extension Project The activities of a small project are shown in the following network. Normal working hours are 8 hours/day. An overtime hour has %90 productivity of a regular hour. For the

More information

Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise Building Construction

Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise Building Construction P P Periodica Polytechnica Architecture 48(2), pp. 87-92, 2017 https://doi.org/10.3311/ppar.10833 Creative Commons Attribution b Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise

More information

CHAPTER 8. Concrete Work

CHAPTER 8. Concrete Work Concrete Work Clay Bricklaying Made Easy CONCRETE WORK Foundations for walls and piers All loadbearing walls and piers are required to stand on a concrete foundation, which must be able to receive and

More information

Measuring Walls in Accordance with ARM4 - An Introductory Demonstration

Measuring Walls in Accordance with ARM4 - An Introductory Demonstration Dublin Institute of Technology ARROW@DIT Other Resources School of Surveying and Construction Management 2017-11-20 Measuring Walls in Accordance with ARM4 - An Introductory Demonstration Tony Cunningham

More information

Construction Technology Revision Guide

Construction Technology Revision Guide Construction Technology Revision Guide Sub structures and Super structures Super structure (Wall, floors roof) Sub structure (Foundations) 2 Thermal Insulation Thermal insulation helps to prevent heat

More information

A Guide to the Last Planner for Construction Foremen and Supervisors Gregory A. Howell, P.E.

A Guide to the Last Planner for Construction Foremen and Supervisors Gregory A. Howell, P.E. A Guide to the Last Planner for Construction Foremen and Supervisors Gregory A. Howell, P.E. Last Planners prepare assignments for people who do work. Last Planners can be found throughout construction

More information

chapter Principles of building OVERVIEW

chapter Principles of building OVERVIEW Principles of building chapter 4 OVERVIEW Whatever type of building is being constructed there are certain principles/elements that must be included, for example a block of 75 Carpentry and Joinery NVQ

More information

BUILDING SKILLS. Building Skills : Basic Painting. Building Skills : Plaster & Tiler. Course Content : Course Content : Duration : 10 Days

BUILDING SKILLS. Building Skills : Basic Painting. Building Skills : Plaster & Tiler. Course Content : Course Content : Duration : 10 Days Building Skills : Basic Painting Use and maintain hand tools Prepare new wall surfaces Prepare old wall surfaces Coat new wall surface with P. V. A Prepare wooden & metal surface (Door & Frame) for enamel

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

Water distribution within the canal network

Water distribution within the canal network Structures for water control and distribution 15 Chapter 4 Water flowing in a secondary irrigation canal can be divided over the tertiary canal network in several ways. One way is to divide the flow proportionally

More information

Make sure you understand the drawing & instructions. Materials and components you will need

Make sure you understand the drawing & instructions. Materials and components you will need Make sure you understand the drawing & instructions We have kept this project as simple as possible - you should be able to complete it in a weekend. Every stage has been illustrated with drawings. All

More information

Office Building. Analysis #2: Utilizing a Matrix Schedule

Office Building. Analysis #2: Utilizing a Matrix Schedule Analysis #2: Utilizing a Matrix Schedule Problem Statement In the past, the team has accelerated the schedule by re-sequencing or re-designing a specific system and/or piece of the schedule to gain back

More information

Contents. Before you begin. Introduction: Carrying out concreting to simple forms 1. Element 1: Planning and preparing 3

Contents. Before you begin. Introduction: Carrying out concreting to simple forms 1. Element 1: Planning and preparing 3 Contents Contents Before you begin v Introduction: Carrying out concreting to simple forms 1 Element 1: Planning and preparing 3 Section 1.1: Obtaining, confirming and applying work instructions and 4

More information

TECH REPORT 3 SANTA ROSA JUNIOR COLLEGE STUDENT CENTER. Alternative Methods Analysis. Dan Vallimont 2009 SENIOR THESIS

TECH REPORT 3 SANTA ROSA JUNIOR COLLEGE STUDENT CENTER. Alternative Methods Analysis. Dan Vallimont 2009 SENIOR THESIS SANTA ROSA JUNIOR COLLEGE STUDENT CENTER Alternative Methods Analysis Dan Vallimont 2009 EXECUTIVE SUMMARY The construction challenges, schedule acceleration scenarios, and value engineering topics of

More information

STATISTICAL TECHNIQUES. Data Analysis and Modelling

STATISTICAL TECHNIQUES. Data Analysis and Modelling STATISTICAL TECHNIQUES Data Analysis and Modelling DATA ANALYSIS & MODELLING Data collection and presentation Many of us probably some of the methods involved in collecting raw data. Once the data has

More information

Construction Scheduling and Estimating

Construction Scheduling and Estimating P.E. Civil Exam Review: Construction Scheduling and Estimating J.P. Mohsen Email: jpm@louisville.edu 2 Project Management What is a Project? Project unique, one-time operational activity or effort Examples

More information

Best Practices. Dennis Clausen Director of Training GOMACO Corporation

Best Practices. Dennis Clausen Director of Training GOMACO Corporation Best Practices Dennis Clausen Director of Training GOMACO Corporation Considerations for Profile Paving Stringline Installation & Maintenance Subgrade Stability and Accuracy Concrete Control & Placement

More information

COUNTY BLOCK. Construction Guidelines on County Block Steps. Special Considerations When Building Steps. Natural Beauty Absolute Strength

COUNTY BLOCK. Construction Guidelines on County Block Steps. Special Considerations When Building Steps. Natural Beauty Absolute Strength Construction Guidelines on County Block Limits of Liability This County Block Installation Guide provides general information about the product, including installation procedures, technical and engineering

More information

Measuring Building Substructures: Solutions to First Year Introductory Level Examination Questions

Measuring Building Substructures: Solutions to First Year Introductory Level Examination Questions Dublin Institute of Technology ARROW@DIT Other Resources School of Surveying and Construction Management 2016-08-04 Measuring Building Substructures: Solutions to First Year Introductory Level Examination

More information

Section 02 SUBSTRUCTURE

Section 02 SUBSTRUCTURE 02 Section 02 SUBSTRUCTURE 1. Trenches to be level, square and free from loose material and standing water. Steps and sides of foundations must be plumb. 2. All tree roots must be removed. Trench depths

More information

4. Construction Analysis Façade Sequencing

4. Construction Analysis Façade Sequencing 4. Construction Analysis Façade Sequencing Problem Statement As a developer catering to Class-A tenants, the owners of are placing a strong emphasis on the occupancy schedule for the office spaces. The

More information

Sunnyvale Plaza. Mid-Atlantic Region, United States. Nathan Braskey Construction Management. November 15, Technical Assignment #3

Sunnyvale Plaza. Mid-Atlantic Region, United States. Nathan Braskey Construction Management. November 15, Technical Assignment #3 November 15, 2013 Sunnyvale Plaza Mid-Atlantic Region, United States Nathan Braskey Construction Management FACULTY CONSULTANT: CRAIG DUBLER EXECUTIVE SUMMARY The following technical report explores several

More information

Module 55 Firm Costs. What you will learn in this Module:

Module 55 Firm Costs. What you will learn in this Module: What you will learn in this Module: The various types of cost a firm faces, including fixed cost, variable cost, and total cost How a firm s costs generate marginal cost curves and average cost curves

More information

2. Action plan tasks. These tasks are more complicated and cannot be easily completed without good thought and planning. These are some examples:

2. Action plan tasks. These tasks are more complicated and cannot be easily completed without good thought and planning. These are some examples: Tool 4 For Effective Action Plans, GAS IT At the most basic level, a manager s job is to get stuff done. The management part comes into play because a manager must get stuff done by directing the actions

More information

PART R3-L ZONE, LOW DENSITY MULTIPLE DWELLING DISTRICT

PART R3-L ZONE, LOW DENSITY MULTIPLE DWELLING DISTRICT PART 3.2 - R3-L ZONE, LOW DENSITY MULTIPLE DWELLING DISTRICT Uses 1 The following uses are permitted: (a) single family dwellings; (b) two family dwellings; (c) multiple dwellings; (d) churches; (e) public

More information

CHAPTER 4, SECTION 1

CHAPTER 4, SECTION 1 DAILY LECTURE CHAPTER 4, SECTION 1 Understanding Demand What Is Demand? Demand is the willingness and ability of buyers to purchase different quantities of a good, at different prices, during a specific

More information

BISON PRECAST FLOORING SPECIFICATION

BISON PRECAST FLOORING SPECIFICATION BISON PRECAST FLOORING SPECIFICATION 1.0 SCOPE OF THE SPECIFICATION 1.01 Relates to: This specification covers the design, manufacture and associated site work of the following types of floors:- Hollowcore

More information

PREPLANNING: A REWARDING EXPERIENCE

PREPLANNING: A REWARDING EXPERIENCE Preplanning: a rewarding experience 115 PREPLANNING: A REWARDING EXPERIENCE Virgilio A. Ghio CVG Construction Engineers, Lima, Peru Ernesto Valle Vainsa Engineering and Construction, Santiago, Chile Leonardo

More information

E3937. Leader s Guide

E3937. Leader s Guide E3937 Supported Scaffolding Safety in Construction Environments Leader s Guide 2009 Marcom Group Ltd. WORKING SAFELY WITH SUPPORTED SCAFFOLDING This easy-to-use Leader s Guide is provided to assist in

More information

TECHNICAL INFORMATION SHEET NUMBER 1a

TECHNICAL INFORMATION SHEET NUMBER 1a BASIC BUILDING REQUIREMENTS FOR THE CONSTRUCTION OF TRADITIONAL SQUASH COURTS Building Requirements The dimensions of a singles or doubles court is shown on the attached diagram. Width and length of the

More information

ECHO PRESTRESS DURBAN (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE

ECHO PRESTRESS DURBAN (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE ECHO PRESTRESS DURBAN (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE INTRODUCTION TO ECHO PRESTRESS In today s world of innovation and fast tracking, the Echo Prestress hollow-core

More information

Long-Hole Stope Evaluation. Operating procedures. Introduction. 1. Approach of the model. 2. Notification. 3. Worksheets

Long-Hole Stope Evaluation. Operating procedures. Introduction. 1. Approach of the model. 2. Notification. 3. Worksheets Model: Level: Long-Hole Stope Evaluation Macro Operating procedures Introduction The goal of the model is to evaluate the total stope production by taking into account the required development work and

More information

How to Estimate the Cost of Painting an Exterior Masonry Wall. December 2010 TABLE OF CONTENTS SECTION 1: INTRODUCTION... 3

How to Estimate the Cost of Painting an Exterior Masonry Wall. December 2010 TABLE OF CONTENTS SECTION 1: INTRODUCTION... 3 How to Estimate the Cost of Painting an Exterior Masonry Wall December 2010 TABLE OF CONTENTS SECTION 1: INTRODUCTION... 3 Main CSI Division... 3 Specific Sub-division... 3 Brief Description... 3 SECTION

More information

York Road Blog July 2015 update

York Road Blog July 2015 update York Road Blog July 2015 update The superstructure is progressing very well and the lads and ladies have been busy helping the bricklayers and forming working relationships with them after the change of

More information

PLANNING THE INSTALLATION

PLANNING THE INSTALLATION C H A P T E R 12 PLANNING THE INSTALLATION THOMAS A. DOOLEY AND JERALD R. ROUNDS THE PROCESS OF PLANNING Planning is one of the most important parts of any project and is particularly critical in construction.

More information

MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar

MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar L7 Project Time Management - II www.notes638.wordpress.com Content 1. Slack Time 2. Network Replanning 3. Estimating Activity

More information

Building Elements. Roof Wall. Slab/beam. Superstructure. Column. Basement. Substructure. Foundation

Building Elements. Roof Wall. Slab/beam. Superstructure. Column. Basement. Substructure. Foundation Development Process Learning Objective Understand the development process describe the roles and function of the construction team explain the communication means and essential documents for the development

More information

SPECIFICATIONS FOR THE CONSTRUCTION OF NEW PASSENGER EQUIPMENT CARS PREFACE

SPECIFICATIONS FOR THE CONSTRUCTION OF NEW PASSENGER EQUIPMENT CARS PREFACE SPECIFICATIONS FOR THE CONSTRUCTION OF NEW PASSENGER EQUIPMENT CARS Standard ADOPTED 1939; ADVANCED TO STANDARD, 1945. PREFACE The specifications have been prepared on the basis that they will be used

More information

Village of Glencoe 675 Village Court, Glencoe, Illinois

Village of Glencoe 675 Village Court, Glencoe, Illinois Village of Glencoe 675 Village Court, Glencoe, Illinois 60022 847-835-4111 March 1, 2002 June, 2002 Clarifications Added Dear Homeowner, Architect, and Contractor: The attached materials will help you

More information

Vladimir Liberzon Shane Archibald Olga Makar-Limanov INTRODUCTION

Vladimir Liberzon Shane Archibald Olga Makar-Limanov INTRODUCTION t c e j o r P r e d i p S Vladimir Liberzon Shane Archibald Olga Makar-Limanov INTRODUCTION Spider Project Introduction Spider Project is powerful professional project management software, developed in

More information

5/9/ Florida Building Code, Existing Building. Chapters Approved Course Title 2010 Existing Building Code Chapters

5/9/ Florida Building Code, Existing Building. Chapters Approved Course Title 2010 Existing Building Code Chapters 2010 Florida Building Code, Existing Building A Code for Existing Buildings This slide is being narrated. If you do not hear a voice, check your speakers or return to the Main Menu and click on System

More information

AMENDMENTS TO OPSS 408 (OCT 89) CONSTRUCTION SPECIFICATION FOR ADJUSTING OR REBUILDING MANHOLES, CATCH BASINS, DITCH INLETS AND VALVE CHAMBERS

AMENDMENTS TO OPSS 408 (OCT 89) CONSTRUCTION SPECIFICATION FOR ADJUSTING OR REBUILDING MANHOLES, CATCH BASINS, DITCH INLETS AND VALVE CHAMBERS Works and Emergency Services CITY OF TORONTO WATER AND WASTEWATER SERVICES STANDARD CONSTRUCTION SPECIFICATIONS TS 408 November 2010 AMENDMENTS TO OPSS 408 (OCT 89) CONSTRUCTION SPECIFICATION FOR ADJUSTING

More information

Operations and Supply Chain Management Prof. G. Srinivisan Department of Management Studies Indian Institute of Technology, Madras

Operations and Supply Chain Management Prof. G. Srinivisan Department of Management Studies Indian Institute of Technology, Madras Operations and Supply Chain Management Prof. G. Srinivisan Department of Management Studies Indian Institute of Technology, Madras Module No - 1 Lecture No - 22 Integrated Model, ROL for Normal Distribution

More information

DIGITAL VERSION. Microsoft EXCEL Level 2 TRAINER APPROVED

DIGITAL VERSION. Microsoft EXCEL Level 2 TRAINER APPROVED DIGITAL VERSION Microsoft EXCEL 2013 Level 2 TRAINER APPROVED Module 4 Displaying Data Graphically Module Objectives Creating Charts and Graphs Modifying and Formatting Charts Advanced Charting Features

More information

Assembly Instructions

Assembly Instructions QSM-BSB3 Railway Station Building - TEMPLETON Assembly Instructions MAIN PARTS DIAGRAM LAMP ROOM END WALL BUILDING FRONT PLATFORM SIDE STORE ROOM END WALL WAITING AREA REAR WALL INTERNAL WALL (x2) MAIN

More information

DeltaV Enclosures. DeltaV Whitepaper. January 2013 Page 1

DeltaV Enclosures. DeltaV Whitepaper. January 2013 Page 1 January 2013 Page 1 DeltaV Enclosures This document describes the types of DeltaV Enclosures available from Emerson Process Management, since the version 11 release of DeltaV. The details of the Enclosures,

More information

PMP Exam Preparation Course Project Time Management

PMP Exam Preparation Course Project Time Management Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,

More information

HOUSE BUILDING DIGEST

HOUSE BUILDING DIGEST HOUSE BUILDING DIGEST (Procedures and Terminologies) Creating Enabling Environment for Affordable Housing for All This is an attempt by BMTPC to provide useful but often ignored information about multifarious

More information

ENR202 Mechanics of Materials Lecture 1A Slides and Notes

ENR202 Mechanics of Materials Lecture 1A Slides and Notes Slide 1 Copyright Notice Do not remove this notice. COMMMONWEALTH OF AUSTRALIA Copyright Regulations 1969 WARNING This material has been produced and communicated to you by or on behalf of the University

More information

PROJECT PARTNERING ARRANGEMENT FOR DELIVERY OF A TIGHT-SCHEDULED PROJECT

PROJECT PARTNERING ARRANGEMENT FOR DELIVERY OF A TIGHT-SCHEDULED PROJECT PROJECT PARTNERING ARRANGEMENT FOR DELIVERY OF A TIGHT-SCHEDULED PROJECT Chris Hill and John Rodgers School of Environment and Development, Sheffield Hallam University. S1 1WB, UK The paper reports a case

More information

Open-Web Truss Long Span Installation Guidelines

Open-Web Truss Long Span Installation Guidelines TECHNICAL BULLETIN #301 Open-Web Truss Long Span Installation Guidelines RedBuilt has maintained a policy of manufacturing and marketing products of the highest quality to our customers. We guarantee the

More information

NOMINAL SIZE. (mm) 6ft extension ft extension ft extension ft extension 3720

NOMINAL SIZE. (mm) 6ft extension ft extension ft extension ft extension 3720 NOMINAL SIZE (mm) 6ft extension 1860 8ft extension 2480 10ft extension 3100 12ft extension 3720 Thank you for purchasing your new Robinsons greenhouse. We recommend you familiarise yourself with the instructions

More information

M i c h i g a n Accessible Homes

M i c h i g a n Accessible Homes M i c h i g a n Accessible Homes RAMP DESIGN The first and most critical aspect of an accessible home is getting into it. Usually, there are one or more steps up to an entrance, which make getting into

More information

5/15/2013. Approved Course Title 2010 Existing Building Code Chapters Florida Building Code, Existing Building. Chapters

5/15/2013. Approved Course Title 2010 Existing Building Code Chapters Florida Building Code, Existing Building. Chapters 2010 Florida Building Code, Existing Building A Code for Existing Buildings Approved Course Title 2010 Existing Building Code Chapters 10-14 Chapters 10-14 Module Objectives Chapter 1 Administration Chapter

More information

Technical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction

Technical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction Technical Report II The Office Building Rendering courtesy of DAVIS Brett Miller Dr. Gannon Construction 10/16/2013 Executive Summary This technical report analyzes key features of The Office Building

More information

VARIOUS TYPES OF SLABS

VARIOUS TYPES OF SLABS VARIOUS TYPES OF SLABS 1 CHOICE OF TYPE OF SLAB FLOOR The choice of type of slab for a particular floor depends on many factors. Economy of construction is obviously an important consideration, but this

More information

Prepared by Andrew Panda. EXPANDA Fence System

Prepared by Andrew Panda. EXPANDA Fence System Prepared by Andrew Panda EXPANDA Fence System Index 1.Introduction Page 3 2.Background Page 4 3. Existing Fence Systems Page 5 4.Features 4.1 Packaging Page 6-8 4.2 Rubber flaps Page 9 4.3 Exclusion Zone

More information

ALTERNATE DESIGN METHODOLOGY FOR UNREINFORCED MASONRY BUILDINGS

ALTERNATE DESIGN METHODOLOGY FOR UNREINFORCED MASONRY BUILDINGS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LABC 8808 Effective: 01-01-2011 DOCUMENT NO. P/BC 2011-053 Revised: Previously Issued As: P/BC 2008-053 I. GENERAL ALTERNATE DESIGN METHODOLOGY

More information

Welcome to lecture 4 of Topic 2.9. In this lecture we focus on Phase 2 of the Project Management Lifecycle the planning phase

Welcome to lecture 4 of Topic 2.9. In this lecture we focus on Phase 2 of the Project Management Lifecycle the planning phase Welcome to lecture 4 of Topic 2.9. In this lecture we focus on Phase 2 of the Project Management Lifecycle the planning phase 1 The main aim of the planning phase of the project management lifecycle is

More information

December 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE

December 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE December 25, 17 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and

More information

MATERIAL HANDLING CHAPTER OUTLINE

MATERIAL HANDLING CHAPTER OUTLINE 3 MATERIAL HANDLING CHAPTER OUTLINE 3.1 Introduction and Meaning 3.2 Objectives of Material Handling 3.3 Principles of Material Handling 3.4 Selection of Material Handling Equipments 3.5 Evaluation of

More information

.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.

.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications. SECTION 31 22 00- GRADING 1.0 GENERAL.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.. 2 Excavate to exact line and grade as

More information

ATTACHED/DETACHED GARAGE BUILDING PERMIT APPLICATION

ATTACHED/DETACHED GARAGE BUILDING PERMIT APPLICATION Community Development 1050 W Romeo Rd Romeoville, IL 60446-1329 (815) 886-7200 Fax #: (815) 886-2724 Email: buildinginspections@romeoville.org ATTACHED/DETACHED GARAGE BUILDING PERMIT APPLICATION Property

More information

PROJECT TIME PLANNING. Process and Bar Chart Technique

PROJECT TIME PLANNING. Process and Bar Chart Technique PROJECT TIME PLANNING Process and Bar Chart Technique Definition of Planning Planning is the process of thinking systematically about the future in order to decide what our goals are, and how we are going

More information

CU Boulder Village Center-Dining & Community Commons

CU Boulder Village Center-Dining & Community Commons CU Boulder Village Center-Dining & Community Commons Best Building Project Specialty Contractor $2 - $6 Million University of Colorado Boulder was looking to upgrade services they provide to students at

More information

Time study is not rocket science, but it is possible to get in big-time trouble with incorrect application. Briefly,

Time study is not rocket science, but it is possible to get in big-time trouble with incorrect application. Briefly, Jackson Productivity Research Inc. 843-422-1298 Contact me for help with your project. Also, for on-line articles on this and similar subjects, click on http://jacksonproductivity.com/artts.htm http://jacksonproductivity.com

More information

NOVEMBER 2016 GRANDWALL. retaining walls installation guide

NOVEMBER 2016 GRANDWALL. retaining walls installation guide NOVEMBER 2016 GRANDWALL retaining walls installation guide RETAINING WALL INSTALLATION GUIDE RETAINING WALL information Austral Masonry Grandwall retaining wall blocks are an ideal choice for retaining

More information

Game Theory and Economics Prof. Dr. Debarshi Das Department of Humanities and Social Sciences Indian Institute of Technology, Guwahati

Game Theory and Economics Prof. Dr. Debarshi Das Department of Humanities and Social Sciences Indian Institute of Technology, Guwahati Game Theory and Economics Prof. Dr. Debarshi Das Department of Humanities and Social Sciences Indian Institute of Technology, Guwahati Module No. # 03 Illustrations of Nash Equilibrium Lecture No. # 01

More information

Reinforced concrete double walls

Reinforced concrete double walls Reinforced concrete double walls Build faster, pay less. Strength in building technology Uses The Kerkstoel reinforced double walls consist of two slabs of reinforced concrete joined to each other by lattice

More information

NOMINAL SIZE. (mm) 6ft extension ft extension ft extension ft extension 3720

NOMINAL SIZE. (mm) 6ft extension ft extension ft extension ft extension 3720 NOMINAL SIZE (mm) 6ft extension 1860 8ft extension 2480 10ft extension 3100 12ft extension 3720 Thank you for purchasing your new Robinsons greenhouse. We recommend you familiarise yourself with the instructions

More information

B. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans.

B. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans. SECTION 1400 - CONCRETE PAVEMENT 1401 SCOPE. This section governs the furnishing of all labor, equipment, tools, and materials and the performance of all work necessary to construct concrete pavement.

More information

A Handbook of thermal bridging details incorporating aircrete blocks

A Handbook of thermal bridging details incorporating aircrete blocks A Handbook of thermal bridging details incorporating aircrete blocks Book 1 Thermal bridging solutions for external wall partial fill cavity details and full fill party wall details Prepared for the Aircrete

More information

18. Wall rebar arrangement

18. Wall rebar arrangement 18. Wall rebar arrangement 1) Sequence of rebar arrangement The worker is not allowed to change the rules and instructions of reinforcement without permission. All the reinforcement should be in accordance

More information

Reinforced concrete double walls

Reinforced concrete double walls Reinforced concrete double walls HOW YOUR BUILDING WORKS TAKES PLACE FASTER WHILE YOUR COSTS REMAIN LOW DOUBLE WALLS Strength in building technology The Kerkstoel reinforced double walls consist of two

More information

Professor Christina Romer SUGGESTED ANSWERS TO PROBLEM SET 1

Professor Christina Romer SUGGESTED ANSWERS TO PROBLEM SET 1 Economics 2 Spring 2017 rofessor Christina Romer rofessor David Romer SUGGESTED ANSWERS TO ROBLEM SET 1 1.a. The opportunity cost of a point on your economics exam is 2 points on your chemistry exam. It

More information

SECTION 1208 CHAIN LINK FENCING DESCRIPTION

SECTION 1208 CHAIN LINK FENCING DESCRIPTION SECTION 1208 CHAIN LINK FENCING 1208-1 DESCRIPTION This item covers the requirements for furnishing materials and constructing new chain link fences and gates in accordance with the details included herein

More information

PROGRESS REPORT NAMILANGI SCHOOL PROJECT PHASE III

PROGRESS REPORT NAMILANGI SCHOOL PROJECT PHASE III ZAMBIA OFFICE PROGRESS REPORT NAMILANGI SCHOOL PROJECT PHASE III December,2016 1 P a g e BACKGROUND In 2014, Lions Aid Norway (LAN) in partnership with Lions District 413, Zambia embarked on a project

More information

Basic Measuring and Calculations. Formulas, Workings Hints and Tips

Basic Measuring and Calculations. Formulas, Workings Hints and Tips Basic Measuring and Calculations Formulas, Workings Hints and Tips Start by writing down the formula When working out mathematics Ensure you show all working out (Marks will be awarded for working out)

More information

SPECIFICATION FOR PRECAST/ COMPOSITE CONCRETE FLOORS/ ROOF DECKS SECTION E60

SPECIFICATION FOR PRECAST/ COMPOSITE CONCRETE FLOORS/ ROOF DECKS SECTION E60 SPECIFICATION FOR SECTION E60 A 2007-09-26 S.W. Revision Date Issue Authorised By Approved for Issue SW Date 24.09.07 clarkebond Page 1 of 6 To be read with Preliminaries/ General Conditions. GENERAL 10

More information

3D PRINTED PARTS FOR ENGINEERING AND OPERATIONS APPLICATIONS NATHAN LUCERO

3D PRINTED PARTS FOR ENGINEERING AND OPERATIONS APPLICATIONS NATHAN LUCERO 3D PRINTED PARTS FOR ENGINEERING AND OPERATIONS APPLICATIONS NATHAN LUCERO PRINTED PARTS AND THE FABRICATION GAP Facade engineering is a balance of using standard stock shapes when possible and introducing

More information

DE-SPAN Design Guideline. Manufactured 100% indoors. Under 100% controlled conditions.

DE-SPAN Design Guideline. Manufactured 100% indoors. Under 100% controlled conditions. DE-SPAN Design Guideline Manufactured 100% indoors. Under 100% controlled conditions. DE-SPAN DE-SPAN is a rigid-portal framed bridge system. Modules are designed with a horizontal deck to support soil

More information

Environmental Studies Lab: Expansion. East Coast, USA

Environmental Studies Lab: Expansion. East Coast, USA Environmental Studies Lab: Expansion East Coast, USA Codi Shine Revised Thesis Proposal Dr. Anumba 1/17/2014 Executive Summary The goal for this whole proposal is schedule acceleration. The first analysis

More information

PROGRESS JAIPUR PH-II AS ON 20 JULY 2018

PROGRESS JAIPUR PH-II AS ON 20 JULY 2018 1. Mobilisation of manpower and material is progressively improving at site. The present labour strength is 345 and will progressively increased to 400 plus by end Jul 18. 2. Progress of Work:- The following

More information

Rounding a method for estimating a number by increasing or retaining a specific place value digit according to specific rules and changing all

Rounding a method for estimating a number by increasing or retaining a specific place value digit according to specific rules and changing all Unit 1 This unit bundles student expectations that address whole number estimation and computational fluency and proficiency. According to the Texas Education Agency, mathematical process standards including

More information

Introduction to Control Charts

Introduction to Control Charts Introduction to Control Charts Highlights Control charts can help you prevent defects before they happen. The control chart tells you how the process is behaving over time. It's the process talking to

More information

A CLIENT S GUIDE WHERE TO START WHAT HAPPENS ON SITE WHAT ARE THE BENEFITS. 10 Advantages of. Design Build

A CLIENT S GUIDE WHERE TO START WHAT HAPPENS ON SITE WHAT ARE THE BENEFITS. 10 Advantages of. Design Build A CLIENT S GUIDE WHERE TO START WHAT HAPPENS ON SITE WHAT ARE THE BENEFITS 10 Advantages of Design Build WHERE TO START Welcome. I prepared this guide after seeing so many people struggle with understanding

More information

SPECIFICATIONS FOR STRUCTURAL EXCAVATION

SPECIFICATIONS FOR STRUCTURAL EXCAVATION SPECIFICATIONS FOR STRUCTURAL EXCAVATION 1.0 DESCRIPTION The Work shall consist of:.1 Excavation and removal of material for the placement of foundations, substructure units, approach slabs, transition

More information

GRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY

GRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY Province of the EASTERN CAPE EDUCATION NATIONAL SENIOR CERTIFICATE GRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY MARKS: 200 TIME: 3 hours *CVLTDM* This question paper consists of 13 pages, including 3 answer

More information

Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best.

Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best. Concrete Placement Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best. Above-grade pours require lifting equipment. Most

More information

Study Guide Final Exam, Microeconomics

Study Guide Final Exam, Microeconomics Study Guide Final Exam, Microeconomics 1. If the price-consumption curve of a commodity slopes downward how can you tell whether the consumer spends more or less on this commodity from her budget (income)?

More information

PLANNING & SCHEDULING

PLANNING & SCHEDULING PLANNING & SCHEDULING 1 Planning & Scheduling Planning: Process of choosing the method and order of work Scheduling: Process of determining the interrelationship of associated timings of operations. 2

More information

Woodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017

Woodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017 Woodbridge Redevelopment Update CLC Meeting #6 Wednesday, December 13, 2017 1. Introductions Agenda 2. Project Updates 3. Construction Updates Progress to Date What s Happening Now 3 Month Schedule 4.

More information

Section CONCRETE SIDEWALKS. 1. Payment for concrete sidewalks is on square foot basis.

Section CONCRETE SIDEWALKS. 1. Payment for concrete sidewalks is on square foot basis. PART 1 GENERAL 1.01 SUMMARY A. This Section includes the following: Section 02775 1. Reinforced concrete sidewalks. 2. Wheelchair Ramps. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for concrete

More information

The factors of a successful industrial construction process

The factors of a successful industrial construction process The factors of a successful industrial construction process Jeroen van der Tas Royal BAM Groep nv Runnenburg 9, 3981 AZ Bunnik, The Netherlands 1. INTRODUCTION In the late 80s and early 90s, people at

More information

CI/SfB. (Ff2) June 2007 CIVIL E NGINEERING PRODUCTS STEPOC SYSTEM. innovators in masonry

CI/SfB. (Ff2) June 2007 CIVIL E NGINEERING PRODUCTS STEPOC SYSTEM.  innovators in masonry CI/SfB (Ff2) June 2007 CIVIL E NGINEERING PRODUCTS STEPOC SYSTEM www.forticrete.co.uk innovators in masonry STEPOC SYSTEM THE FASTER, MORE E CONOMICAL WAY TO BUILD WALLS WITH EXCEPTIONAL STRENGTH Stepoc

More information

Safety on Heights: Our Policy

Safety on Heights: Our Policy 11/17/14 Safety on Heights: Our Policy Only volunteers over the age of 18 are allowed to work on heights of more than six feet off the ground. This includes all work on scaffolds. Only volunteers who are

More information