Structural Inspection

Size: px
Start display at page:

Download "Structural Inspection"

Transcription

1 General: Background: An inspection and structural analysis have been performed for the purpose of evaluating the buildings structural systems and components. A full set of structural drawings was utilized for our inspection and analysis. The inspection was done on May 12, All observable structural systems were inspected for conformance with the original design drawings and for any signs of distress or other conditions which could compromise the building s structural integrity. Many structural elements were covered with finishes or insulation and thus not accessible for inspection. Physical layout: The L shaped building is configured with two sloped roof classroom wings and a high roof gymnasium at their intersection. The wings have a gable profile with a 1 in 12 slope and a ridge running down the center. The south wing terminates into the south side of the east west wing with roof valleys at their intersection. The gym roof is shed configuration with a 1 in 12 slope to the south. Foundations: Description: Foundations are conventional concrete footings founded on undisturbed native soils or compact fill. Building columns are founded on concrete spread footings that are typically 3 0 square by 12 deep. Highly loaded columns have larger footings. Spread footings at perimeter walls are buried with top of footing at 3 0 below exterior grade. 8 concrete foundation walls are utilized around building perimeter. 1 2 wide by 8 deep concrete strip footings are located below foundation wall at classroom wing end walls, stair alcove foundation walls, interior concrete walls, and perimeter walls of gym. Other foundation walls have no strip footing but instead span between column spread footings which are typically spaced at 14 0 on center. Condition: The foundation is buried and could not be inspected but appeared to be performing adequately. Foundation failure would result in settlements that would be evident in the superstructure and no such distress was observed. The foundation system should have a remaining useful life of years. The building floor is a 5 thick concrete slab on grade reinforced with welded wire fabric. The slabs condition was good with no sign of unusual cracking, settlement, or other deficiencies. Remaining Life Expectancy: The slab should have a remaining useful life of 25 years. Roof Framing: Description: The classroom wings are framed with tongue and groove timber decking spanning between glue laminated wood beams. 4x6 nominal decking is orientated parallel to the roof ridge and typically spans 14 0 between beams. Decking is supported by 7 x22 ¾ deep glue laminated beams. Each beam is supported by two June 2005 Glacier Valley Elementary School Condition Survey Report Page 34 of 178

2 pipe steel columns, one at exterior wall and the other at corridor wall. A reduced depth section of beam cantilevers over the corridor wall to ridge at centerline of building. The reduced beam depth allows maximum clearance for mechanical ductwork running below beam and above the corridor ceiling. The gym high roof is framed with tongue and groove timber decking spanning between glue laminated wood beams. 3x6 nominal size decking is orientated east west and typically spans 9 5 ½ between beams. Decking is supported by 11 x 39 deep glue laminated beams. Each beam is supported by two pipe steel columns, one at each end. Inspections indicated the condition of gym roof framing was good. The only framed floor area is a small mechanical mezzanine at south side of gym. This area is essentially an extension of the classroom wing roof framing. Condition: Inspections indicated the condition of classroom wing roof framing was fair. The majority of roof beams were exposed and showed no signs of excessive checking, splitting or distress. The majority of roof decking was obscured. In classrooms, acoustical ceiling tile was adhered directly to bottom of decking and foil faced insulation attached to bottom of decking prevented inspection above the suspended corridor ceilings. The only decking available for inspection were sections that had been replaced during the latest re roof. Past roof leaks had allowed moisture to penetrate and rot some areas of decking. Pieces of the rotted decking had fallen to the suspended corridor ceiling and were observed during our inspection. It was apparent that some areas of decking had experienced severe rot. The replacement decking was exposed from underside and appeared to be in very good condition. The extent of decking that needed to be replaced and the severity of rot observed in the fragments found on top of corridor ceilings leaves some uncertainty about the condition and long term performance of original decking. We understand a complete inspection was done at the time of last re roof and that all questionable decking was replace at this time. We assume all compromised sections of decking were repaired or replaced during the last re roof. The gymnasium roof beams were exposed to view and easy to inspect. They showed no signs of excessive checking, splitting or distress. Most of the decking was obscured by ceiling tile but a section over mechanical mezzanine was exposed and in good condition. Remaining Life Expectancy: The classroom wing roof framing system should have a remaining useful life of years. The gym roof framing system should have a remaining useful life of years. June 2005 Glacier Valley Elementary School Condition Survey Report Page 35 of 178

3 Structural Analysis Results and Deficiencies A structural analysis has been completed based on information contained in the original construction drawings and confirmed during our on site inspections. The analysis was based on the 2003 International Building Code. The following deficiencies were found. June 2005 Glacier Valley Elementary School Condition Survey Report Page 36 of 178

4 Typical roof decking and glue laminated beam The original building was designed for a roof snow load of 40 psf. The current code roof snow load is a minimum of 50 psf. A check of the decking and framing indicates that the members typically have the reserve capacity to resist the additional 10 psf. The exception is in the inside corner of the building in the roof framing over the toilets and janitor rooms. Both the existing decking and glue laminated beams are overstressed by 30%. The deck spans in this area should be reduced by adding new glue laminated beams centered between each of the existing beams. This will result in an increase in the capacity of the decking and reduce the loads on the existing beams. The existing valley beam should be replaced with a new glue laminated beam to increase the capacity of the framing. New 3 diameter pipe columns and 2 0 square footings at interior wall locations will be needed. $15,000. See architectural deficiency items for additional costs. June 2005 Glacier Valley Elementary School Condition Survey Report Page 37 of 178

5 Snow drifting adjacent to Gym roof Areas subject to snow drifting around the higher gymnasium roof do not have the additional reserve capacity to carry the dead loads prescribed by today s codes. The deck spans in these areas should be reduced by adding new glue laminated beams centered between each of the existing beams. This will result in an increase in the capacity of the decking and reduce the loads on the existing beams. New 3 diameter pipe columns and 2 0 square footings at interior wall locations will be needed. $38,000. See architectural deficiency items for additional costs. June 2005 Glacier Valley Elementary School Condition Survey Report Page 38 of 178

6 Lack of lateral load resisting system No lateral load resisting system is present in longitudinal direction of wings. Exterior walls are plywood sheathed and could act as shearwalls, but continuous strip windows prevent a continuous load path and eliminate the possibility of using the exterior walls as shearwalls. Corridor walls are gypsum sheathed and could provide some nominal lateral load resistance, however the gypsum sheathing stops just above the ceiling and therefore can not be used as a shearwall. Preliminary wind and seismic calculations indicate that ½ plywood should be added to one side of each of the corridor walls. The sheathing could either be continuous the length of the corridor or installed only on the 24 walls between classroom entry alcoves at approximately each fourth classroom with a minimum of two walls on each side of the corridors each wing. For the discontinuous wall remedy, tie struts need to be created to transfer the lateral loads into the shear walls. The tie struts can be created by installing Simpson CMST16 continuous straps on top of the decking. Simpson PHD2 hold down anchors should be provided at each end of each wall segment to resist the over turning loads. The hold June 2005 Glacier Valley Elementary School Condition Survey Report Page 39 of 178

7 downs will require the addition of 2 feet square footings at each location. 5/8 drill in adhesive anchors spaced at 32 on center along each of the shear walls is required. $35,000. See architectural deficiency items for additional costs. (photo not available) Insufficient transverse shear walls Shear walls transverse to the direction of the wings are provided on one side of each on the entry corridors. However, the lateral loads exceed the capacity of these shear walls. Additional plywood sheathing should be added to the existing shear walls. This occurs in nine places. The wall on the opposite side of the entry corridors should also be sheathed with ½ plywood each side. This condition occurs in three locations. These walls all tie directly into the existing glue laminated roof beams. Simpson PHD5 hold downs should be provided at each end of these walls. The hold downs are typically located at the existing interior column footings. $17,000. June 2005 Glacier Valley Elementary School Condition Survey Report Page 40 of 178

8 Insufficient sheathing in roof diaphragm to resist lateral loads Description: The initial construction consists of T&G decking without plywood roof diaphragms. In addition, during the re roof project no sheathing was added at that time. The drawings do not indicate how decking is attached. A check of the capacity of the decking diaphragm nailing based on the typical AITC deck nailing methods was done. The typical nailing pattern does not have adequate capacity based on the current shear wall locations. A new layer of ½ sheathing should be applied over all of the existing 3 and 4 T&G decking. It may be feasible to install plywood on the underside of decking if adequate access will be created by other renewal improvements. For example if ceilings, lights and mechanical ductwork will be replaced, it may provide adequate access such that plywood could be attached to underside of roof deck. Another option would be to wait until the next re roof is necessary and install the plywood at this time. $235,000. See architectural deficiency items for additional costs. June 2005 Glacier Valley Elementary School Condition Survey Report Page 41 of 178

STRUCTURAL EVALUATION OF WASHINGTON ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD)

STRUCTURAL EVALUATION OF WASHINGTON ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) STRUCTURAL EVALUATION OF WASHINGTON ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) For WLC Architects Kaiser Building 1300 Potrero Avenue Richmond, CA 94804 By DASSE Design, Inc.

More information

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel

More information

STRUCTURAL EVALUATION OF DOVER ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD)

STRUCTURAL EVALUATION OF DOVER ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) STRUCTURAL EVALUATION OF DOVER ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) For WLC Architects Kaiser Building 1300 Potrero Avenue Richmond, CA 94804 By DASSE Design, Inc. 33 New

More information

ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA Tel: Fax:

ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA Tel: Fax: ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA 02144 Tel: 617.628.1700 Fax: 617.628.1711 March 3, 2016 Mr. Jeff Hoover, Principal Tappe Architects, 6 Edgerly Place

More information

Building Division Informational Handout

Building Division Informational Handout CITY OF SAN JOSÉ, CALIFORNIA Building Division Informational Handout Conventional Light Frame Construction Design Provisions 2007 CBC Handout No. 2-21 Published: 1/1/08 Page 1 of 3 This document summarizes

More information

Structural Design Engineers 120 Montgomery Street, Suite 1410 San Francisco, California / Fax 415/

Structural Design Engineers 120 Montgomery Street, Suite 1410 San Francisco, California / Fax 415/ 120 Montgomery Street, Suite 1410 San Francisco, California 94104 415/781-1505 Fax 415/781-2718 sde@sdesf.com Rajendra Sahai, SE Principal John W. Laws, SE Principal Steven Lepisto, SE Principal STRUCTURAL

More information

STRUCTURAL EVALUATION OF TARA HILLS ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD)

STRUCTURAL EVALUATION OF TARA HILLS ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) STRUCTURAL EVALUATION OF TARA HILLS ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) For WLC Architects Kaiser Building 1300 Potrero Avenue Richmond, CA 94804 By DASSE Design, Inc.

More information

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings Building Safety Department 400-2 nd Street South St. Cloud, MN 56301 (320) 255-7239 A building permit is required for any accessory

More information

Jackson Crossing Located in Alexandria, VA. Technical Report 1 Michael Bologna

Jackson Crossing Located in Alexandria, VA. Technical Report 1 Michael Bologna Jackson Crossing Located in Alexandria, VA Technical Report 1 Michael Bologna Structural Option Advisor: Dr. Linda Hanagan September 11, 2015 Table of Contents Executive Summary.3 Introduction 4 Purpose..4

More information

SECTION WOOD FRAMING. A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents.

SECTION WOOD FRAMING. A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents. SECTION 06110 WOOD FRAMING PART 1 GENERAL 1.1 SUMMARY A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents. B. Products Installed But Not Supplied

More information

WALL CONSTRUCTION CHAPTER 6

WALL CONSTRUCTION CHAPTER 6 CHAPTER 6 WALL CONSTRUCTION SECTION R601 GENERAL R601.1 Application. The provisions of this chapter shall control the design and construction of all walls and partitions for all buildings. R601.2 Requirements.

More information

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity System Codes and Criteria Design Codes and Standards The design code used is the Wisconsin Administrative Code along with the State of Wisconsin Department of Commerce-Safety & Buildings Chapters Comm

More information

Attachment A. USG Minimum Design and Construction Requirements for Wood Framed Structures

Attachment A. USG Minimum Design and Construction Requirements for Wood Framed Structures Attachment A USG Minimum Design and Construction Requirements for Wood Framed Structures 1. General Design Criteria 1.1. Per Adopted Georgia State Minimum Standard Building Code 1.2. Minimum Live Loads

More information

SECTION WOOD FRAMING. A. Includes But Not Limited To: 1. Furnish and install wood framing and blocking as described in Contract Documents.

SECTION WOOD FRAMING. A. Includes But Not Limited To: 1. Furnish and install wood framing and blocking as described in Contract Documents. SECTION 06 1100 WOOD FRAMING PART 1 - GENERAL 1.1 SUMMARY A. Includes But Not Limited To: 1. Furnish and install wood framing and blocking as described in Contract Documents. B. Products Installed But

More information

FIGURE R502.2 FLOOR CONSTRUCTION

FIGURE R502.2 FLOOR CONSTRUCTION CHAPTER 5 FLOORS 11 I SECTION R501 GENERAL R501.1 Application. The provisions of this chapter shall control the design and construction of the floors for all buildings including the floors of attic spaces

More information

On Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866)

On Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866) TECHNICAL NOTE On Cold-Formed Steel Construction $5.00 Light Gauge Steel Engineers Association Washington, D.C. 20005 Toll Free (866) 465-4732 www.lgsea.com DESIGN OF BY-PASS SLIP CONNECTORS IN COLD-FORMED

More information

90% Design Submittal Structural Calculations Parking Garage CDRL

90% Design Submittal Structural Calculations Parking Garage CDRL NORTH METRO RAIL LINE PROJECT Thornton Crossroads at 104 th Avenue Station 90% Design Submittal Structural Calculations Parking Garage CDRL 03-037.11.06 June 2, 2017 Prepared by: Regional Rail Partners

More information

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report Michael A. Troxell Structural Option Advisor: Professor Parfitt College of Business Administration Oct. 5, 2005 Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

More information

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage The following list of code requirements is intended to assist you in complying with the Code of Public

More information

Part 1: Vocabulary Select the best answer and write the corresponding letter in the space provided.

Part 1: Vocabulary Select the best answer and write the corresponding letter in the space provided. Name: Date: References: Architecture: Residential Drafting and Design (Chapter 18) at http://www.g wonlinetextbooks.com/. ***Use the classroom Username and Password to access the textbook, not your personally

More information

1. The subfloor must be structurally sound and able to withstand live and dead loads with a deflection limitation of L/360.

1. The subfloor must be structurally sound and able to withstand live and dead loads with a deflection limitation of L/360. HARDWOOD FLOOR Read First These suggestions represent generally accepted procedures for successful installation of Maxxon Products. These instructions may be followed, modified or rejected by the owner,

More information

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2) Inspection of Fabricators (1704.2) Furnish inspection reports (1704.2.1) - Fabricators that have not been approved Provide a Certificate of Compliance (1704.2.2) - Approved Fabricators Steel Construction

More information

Project. San Jose City College Physical Education Building. Prepared For. Prepared By PLACE IMAGE HERE. Ken Bauer, AIA Principal

Project. San Jose City College Physical Education Building. Prepared For. Prepared By PLACE IMAGE HERE. Ken Bauer, AIA Principal Project San Jose City College Physical Education Building PLACE IMAGE HERE Prepared For Ken Bauer, AIA Principal LPAS 2484 Natomas Park Drive Sacramento, CA 95833 916.443.0335 Prepared By Steve Ratchye,

More information

Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report

Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report 1 THE ODYSSEY ARLINGTON, VA Aaron Snyder Structural Option Advisor: M. Kevin Parfitt, PE Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report Executive

More information

WALL CONSTRUCTION CHAPTER 6

WALL CONSTRUCTION CHAPTER 6 CHAPTER 6 WALL CONSTRUCTION SECTION R601 GENERAL R601.1 Application. The provisions of this chapter shall control the design and construction of all walls and partitions for all buildings. R601.2 Requirements.

More information

Tier 1 Assessment Linderman Gymnasium Polson, MT

Tier 1 Assessment Linderman Gymnasium Polson, MT Tier 1 Assessment Linderman Gymnasium Polson, MT June 15, 2018 Prepared by: 128 W. ALDER ST SUITE a MISSOULA, MT 59802 (406) 274-7671 June 15, 2018 Mr. Paul Bishop Paradigm v.2.0 125 ½ W. Main Street RE:

More information

Connaught. Facility Audit report for: Connaught Regina, SK. Report Created: Page 1 of 20

Connaught. Facility Audit report for: Connaught Regina, SK. Report Created: Page 1 of 20 Connaught Facility Audit report for: Connaught Regina, SK Report Created: 2012-04-02 Page 1 of 20 Facility Details Facility Connaught Address: Location: Regina, SK Facility Zone: 8 Grade Configuration:

More information

Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation SCI Project Number:

Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation SCI Project Number: 27 June 2016 Mr. Shane Chism, AIA Breckenridge Group 4625 E. Fort Lowell Road Tucson, Arizona 85712 Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation

More information

THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND CONDOMINIUMS

THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND CONDOMINIUMS THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE II RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING

More information

STRUCTURAL EVALUATION OF JOHN F. KENNEDY HIGH SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD)

STRUCTURAL EVALUATION OF JOHN F. KENNEDY HIGH SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) STRUCTURAL EVALUATION OF JOHN F. KENNEDY HIGH SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) For WLC Architects Kaiser Building 1300 Potrero Avenue Richmond, CA 94804 By DASSE Design, Inc. 33

More information

VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.)

VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.) DIVISION 94 VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.) SEC. 91.9401. PURPOSE. (Amended by Ord. No. 172,592, Eff. 6/28/99,

More information

PLYWOOD FLOATING FLOOR

PLYWOOD FLOATING FLOOR PLYWOOD FLOATING FLOOR Read First These suggestions represent generally accepted procedures for successful installation of Enka Building Products. These instructions may be followed, modified, or rejected

More information

DIVISION: WOOD, PLASTICS AND COMPOSITES SECTION: STRUCTURAL PANELS REPORT HOLDER: ENERCEPT, INC.

DIVISION: WOOD, PLASTICS AND COMPOSITES SECTION: STRUCTURAL PANELS REPORT HOLDER: ENERCEPT, INC. 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 1780 Reissued 11/2017 This report is subject to renewal 11/2019. DIVISION: 06 00

More information

THE FLORIDA BUILDING CODE

THE FLORIDA BUILDING CODE THE FLORIDA BUILDING CODE 1. According to the Florida Building Code, spiral stairway treads must all be identical and rise must be sufficient enough to provide a headroom of minimum. A. 6'- 4" B. 6'- 6"

More information

SPECIAL INSPECTION AGREEMENT FORM

SPECIAL INSPECTION AGREEMENT FORM CITY OF TRACY DEVELOPMENT & ENGINEERING SERVICES 333 CIVIC CENTER PLAZA, TRACY, CA 95376 P :( 209) 831-6400 F :( 209) 831-6439 http://www.ci.tracy.ca.us SPECIAL INSPECTION AGREEMENT FORM Prior to issuance

More information

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program ENTRY FORM DVASE 2014 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M Buildings $2M-$10M Other Structures Under $5M Buildings

More information

Stone and Masonry Veneer

Stone and Masonry Veneer Stone and Masonry Veneer R703.7 Stone and masonry veneer, general. Stone and masonry veneer shall be installed in accordance with this chapter, Table R703.4 and Figure R703.7. These veneers installed over

More information

MAIN FLOOR PLAN. #G x 14 x 8 Shed - Chicken Coop By SDS-CAD Specialized Design Systems 10'-0" 3'-0" 1'-0" 14'-0" 14'-0" 1'-0" 6'-0" 3'-0"

MAIN FLOOR PLAN. #G x 14 x 8 Shed - Chicken Coop By SDS-CAD Specialized Design Systems 10'-0 3'-0 1'-0 14'-0 14'-0 1'-0 6'-0 3'-0 10'-0" BUILDING CONTRACTOR/HOME OWNER TO REVIEW AND VERIFY ALL DIMENSIONS, SPECS, AND CONNECTIONS BEFORE CONSTRUCTION BEGINS. BARN TO BE BUILT AS PER LOCAL CODE REQUIREMENTS 14'-0" BWP BWP BWP ABWP 101

More information

PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION

PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION An overview of costing strategies for wood framed construction elements CREATING A PROJECT ENDLESS POSSIBILITIES COMPATORS LIST A FLOOR Cast in Place

More information

STRUCTURAL CONDITION ASSESSMENT

STRUCTURAL CONDITION ASSESSMENT STRUCTURAL CONDITION ASSESSMENT ALLEN JAY ROCK GYM 1201 FAIRFIELD ROAD HIGH POINT, NC Prepared for: Prepared by: Guilford County Schools 617 West Market Street Greensboro, NC Adrian S. Durham, PE, SE,

More information

GARAGE MAIN FLOOR PLAN

GARAGE MAIN FLOOR PLAN BUILDING CONTRACTOR/HOME OWNER TO REVIEW AND VERIFY ALL DIMENSIONS, SPECS, AND CONNECTIONS BEFORE CONSTRUCTION BEGINS. SHED TO BE BUILT AS PER IRC, UBC OR CURRENT LOCAL CODE To the best of my knowledge

More information

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan Brief Building Overview: 200 Minuteman Park stands as a 200,000 square foot Class A office building in Andover, Massachusetts, worth roughly $15,000,000. Although the building has a large square footage,

More information

The Passive Fire Protection Handbook

The Passive Fire Protection Handbook The Passive Fire Protection Handbook The UK s comprehensive guide to passive fire protection Chapter Ceilings, Floors and Roofs AUGUST 0 The Passive Fire Protection Handbook Contents Chapter : Introduction

More information

GARAGE MAIN FLOOR PLAN

GARAGE MAIN FLOOR PLAN BUILDING CONTRACTOR/HOME OWNER TO REVIEW AND VERIFY ALL DIMENSIONS, SPECS, AND CONNECTIONS BEFORE CONSTRUCTION BEGINS. SHED TO BE BUILT AS PER IRC, UBC OR CURRENT LOCAL CODE To the best of my knowledge

More information

David A. Walenga Technical Assignment #1

David A. Walenga Technical Assignment #1 Executive Summary Contained in this report is design information related to the structural system of the Residence Inn by Marriot located in Stamford, Connecticut. Specifically, this report covers: code

More information

SPECIAL INSPECTION AGREEMENT

SPECIAL INSPECTION AGREEMENT PART 1 STATEMENT OF SPECIAL INSPECTIONS When special inspection is required to be performed in accordance with International Building Code Chapter 17, a building permit cannot be issued until a statement

More information

GARAGE MAIN FLOOR PLAN

GARAGE MAIN FLOOR PLAN 30 year dimensional shingles and Metal Verticle siding over structural sheathing. Nailing schedule is " on ends 12" on centers d nails. Trusses are engineered on 24" and framing is 2" x " on 1" centers.

More information

RESIDENTIAL DETACHED ACCESSORY STRUCTURES

RESIDENTIAL DETACHED ACCESSORY STRUCTURES RESIDENTIAL DETACHED ACCESSORY STRUCTURES *A Building permit is required for any alteration or addition to any existing building or structure. MN State Building Code Section 1300.0120 Subpart 1 Permit

More information

Structural Redesign Gravity System

Structural Redesign Gravity System Redesign Gravity System Design Considerations A composite floor system was used for this design to maximize the efficiency of the material being used. This type of system requires less material and provides

More information

STATEMENT OF SPECIAL INSPECTION FORM

STATEMENT OF SPECIAL INSPECTION FORM Project Title: Permit #: Project Address: STATEMENT OF SPECIAL INSPECTION FORM This Statement of Special Inspections is submitted in fulfillment of the requirements of CBC Sections 1704 and 1705. Special

More information

Custom 22' x 40' - 16' Tall Garage Plan #g227 By SDS-CAD Specialized Design Systems

Custom 22' x 40' - 16' Tall Garage Plan #g227 By SDS-CAD Specialized Design Systems P O Box 34 Mendon, Utah Custom 22' x 40' - 16' Tall Garage Plan #g22 By Page 1 Title Page Page 2 Main Floor Plan Page 3 Foundation Plan Page 4 Elevation Views Page 5 Framing and Details Page 6 Typical

More information

SECTION R614 STRUCTURAL INSULATED PANEL WALL CONSTRUCTION

SECTION R614 STRUCTURAL INSULATED PANEL WALL CONSTRUCTION Section R614 Add new section to read as shown: (RB34-06/07) SECTION R614 STRUCTURAL INSULATED PANEL WALL CONSTRUCTION R614.1 General. Structural insulated panel (SIP) walls shall be designed in accordance

More information

#G445 Plans, 48'x28' x 10' detached garage with bonus room By SDS-CAD Specialized Design Systems

#G445 Plans, 48'x28' x 10' detached garage with bonus room By SDS-CAD Specialized Design Systems Architectural asphalt shingles and horizontal True Wood 7" Reveal siding over structural panel. Nailing schedule is 6" on ends 12" on centers 6d nails. Trusses are engineered on Bonus attic trusses 24"

More information

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: ROOFING AND SIDING PANELS REPORT HOLDER: FOUR SEASONS BUILDING PRODUCTS, LLC

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: ROOFING AND SIDING PANELS REPORT HOLDER: FOUR SEASONS BUILDING PRODUCTS, LLC 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 2229 Reissued 05/2018 This report is subject to renewal 05/2019. DIVISION: 07 00

More information

Nortrax Section David Manchester Road, Ottawa NON-STRUCTURAL METAL FRAMING 16 May 2014 Page 1

Nortrax Section David Manchester Road, Ottawa NON-STRUCTURAL METAL FRAMING 16 May 2014 Page 1 16 May 2014 Page 1 PART 1 GENERAL 1.1 DESCRIPTION This section specifies steel studs wall systems, shaft wall systems, ceiling or soffit suspended or furred framing, wall furring, fasteners, and accessories

More information

Southwest Housing, Arizona State University

Southwest Housing, Arizona State University Prepared by KSENIA TRETIAKOVA Structural Option 01.09.2012 Architectural Engineering Pennsylvania State University 2012 Southwest Housing, Arizona State University Technical Report #3 Lateral System 01.09.2012

More information

Diaphragms 2. Design Process. Design Process. Diaphragms are the roofs and floors of the upper stories

Diaphragms 2. Design Process. Design Process. Diaphragms are the roofs and floors of the upper stories Diaphragms 2 Design Process Diaphragms are the roofs and floors of the upper stories They are assumed to act as a beam (usually a deep beam with substantial shear deformation) Design Process Sheathing

More information

Custom 30 x 48-14' Tall Garage Plan #g226 By SDS-CAD Specialized Design Systems

Custom 30 x 48-14' Tall Garage Plan #g226 By SDS-CAD Specialized Design Systems P O Box 34 Mendon, Utah Custom 30 x 48-14' Tall Garage Plan #g226 By Page 1 Title Page Page 2 Main Floor Plan Page 3 Foundation Plan Page 4 Elevation Views Page 5 Framing and Details Page 6 Typical Section

More information

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Executive Summary:, located in Pigeon Forge, Tennessee, is designed as a multifunctional space and

More information

1000 CONNECTICUT AVENUE

1000 CONNECTICUT AVENUE 1000 CONNECTICUT AVENUE Gea Johnson Structural Option Faculty Advisor: Dr. Hanagan September 23, 2011 Revised: December 16, 2011 Washington DC Technical : Existing Conditions Table of Contents Executive

More information

Framing Methods Structural Components

Framing Methods Structural Components Framing Methods Structural Components Balloon Framing *Balloon framing or Eastern framing the exterior studs run from the top of the foundation to the top of the highest level. Benefits of this type of

More information

SECTION PLATE CONNECTED WOOD TRUSSES

SECTION PLATE CONNECTED WOOD TRUSSES SECTION 06173 PLATE CONNECTED WOOD TRUSSES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Shop fabricated wood trusses for roof and floor framing. 2. Bridging, bracing, and anchorage. B. Related Sections:

More information

Administrative Changes

Administrative Changes Revised 11/29/06 Knox County Residential Building Codes Significant Changes From The 1995 CABO One And Two Family Dwelling Code To The 2006 International Residential Code All one and two family dwellings

More information

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012)

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012) Gaines Charter Township 8555 Kalamazoo Ave SE Caledonia MI 49316 PH: 616 698-6640 Fax: 616 698-2490 www.gainestownship.org Building Department Statement of Special Inspections Michigan Building Code 2012

More information

HOLDOWN & STRAP SCHEDULE

HOLDOWN & STRAP SCHEDULE SHEAR WALL SCHEDULE STRUCTURAL DESIGN CRITERIA GOVERNING CODE SOIL BEARING PRESSURE HOLDOWN & STRAP SCHEDULE MARK SHEATHING SHEATH BOTH SIDES NAILS EDGE SPACING NOTES MARK SW 7/" OSB NO 8d " OC - A SW

More information

Modular Wood Framing Goes Vertical

Modular Wood Framing Goes Vertical Modular Wood Framing Goes Vertical By: Troy Bean, P.E., S.E. DCI Engineers January 2013 The Wood Products Council is a Registered Provider with. Credit(s) earned on completion of this program will be reported

More information

NCMA TEK RESIDENTIAL DETAILS FOR HIGH WIND AREAS. TEK 5-11 Details (2003)

NCMA TEK RESIDENTIAL DETAILS FOR HIGH WIND AREAS. TEK 5-11 Details (2003) NCM TEK National Concrete Masonry ssociation an information series from the national authority on concrete masonry technology RESIDENTIL DETILS FOR HIGH WIND RES TEK 5-11 Details (2003) Keywords: architectural

More information

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2011 LARC)

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2011 LARC) Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2011 LARC) Plan Check Submittal Date: Plan Check #: Permit App.# Job Address: Applicant: Phone: ( ) P.C. Engineer: Phone:

More information

Danielle Shetler - Structural option Courtyard by Marriott Lancaster, PA

Danielle Shetler - Structural option Courtyard by Marriott Lancaster, PA Structural Analysis Overview: During the structural analysis of the in Lancaster, Pa, a redesign of the lateral and gravity system from masonry bearing and shear walls to a staggered truss system was performed.

More information

SECTION STEEL DECKING

SECTION STEEL DECKING SECTION 05 31 00 STEEL DECKING SPEC WRITER NOTE: 1. Delete text between // // not applicable to project. Edit remaining text to suit project. 2. Refer to Section 05 36 00, COMPOSITE METAL DECKING for floor

More information

Table 3. Detailed Comparison of Structural Provisions of IRC 2000 and 1997 NEHRP (Continued)

Table 3. Detailed Comparison of Structural Provisions of IRC 2000 and 1997 NEHRP (Continued) 2000 IRC 1997 NEHRP Section Provision Section Provision Comments CHAPTER 3 BUILDING PLANNING R301 DESIGN CRITERIA R301.2.2 Seismic Provisions R301.2.2.1 Determination of Seismic Design Category R301.2.2.1.1

More information

FDA OC/ORA Office Building

FDA OC/ORA Office Building FDA OC/ORA Office Building Table of Contents Executive Summary... 3 Introduction... 4 Structural System... 5 Foundation:... 5 Floor System:... 7 Building 31:... 7 Building 32:... 9 Columns... 10 Lateral

More information

COURTYARD INFILL STRUCTURE DESIGN

COURTYARD INFILL STRUCTURE DESIGN COURTYARD INFILL STRUCTURE DESIGN Executive Summary The existing design for the courtyard within the G wing is for a cast-in-place concrete structure. The design being proposed within this analysis is

More information

Structural Technical Report #2 By Robert Whitaker

Structural Technical Report #2 By Robert Whitaker Structural Technical Report #2 By Robert Whitaker Robert Whitaker Structural ~ Parfitt Parkview at Bloomfield Station Bloomfield, NJ 10-31-05 Executive Summary This report covers the comparative redesign

More information

Temecula Medical Center Temecula, CA

Temecula Medical Center Temecula, CA Temecula Medical Center Temecula, CA Technical Assignment #2 Sean F. Beville The Pennsylvania State University Architectural Engineering Structural Option Senior Thesis Project Student Advisor: Thomas

More information

4.6 Procedures for Connections

4.6 Procedures for Connections 4.6 Procedures for Connections This section provides Tier 2 evaluation procedures that apply to structural connections: anchorage for normal forces, shear transfer, vertical components, interconnection

More information

one structural behavior, systems, and design ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SUMMER 2015 lecture

one structural behavior, systems, and design ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SUMMER 2015 lecture ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SUMMER 2015 lecture one structural behavior, systems, and design Introduction 1 www.greatbuildings.com Syllabus & Student Understandings

More information

CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures

CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE - 268-5161 Residential Accessory Structures This information has been compiled for the benefit of any person

More information

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2014 LARC)

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2014 LARC) Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2014 LARC) Plan Check Submittal Date: Plan Check #: Permit App.# Job Address: Applicant: Phone: ( ) Plan Check Engineer:

More information

DIVISION 5 METALS SECTION COLD-FORMED METAL FRAMING

DIVISION 5 METALS SECTION COLD-FORMED METAL FRAMING DIVISION 5 METALS SECTION 05 40 00 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 092216 - NON-STRUCTURAL METAL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Minimum required percentage of length of braced wall band on each storey 4

Minimum required percentage of length of braced wall band on each storey 4 C-10 Supplementary Guidelines on Applicability and Scope Table C1 b (continued) Braced Wall Panels for High Wind or High Seismic Loads Building with normal weight construction: 0.8 kpa q 1/50 wind load

More information

SEATTLE CENTRAL COLLEGE BROADWAY PERFORMANCE HALL SEATTLE, WASHINGTON STRUCTURAL EVALUATION FOR PREPARED BY PCS STRUCTURAL SOLUTIONS

SEATTLE CENTRAL COLLEGE BROADWAY PERFORMANCE HALL SEATTLE, WASHINGTON STRUCTURAL EVALUATION FOR PREPARED BY PCS STRUCTURAL SOLUTIONS STRUCTURAL EVALUATION FOR SEATTLE CENTRAL COLLEGE BROADWAY PERFORMANCE HALL SEATTLE, WASHINGTON PREPARED BY PCS STRUCTURAL SOLUTIONS NOVEMBER 1, 2017 17-733 TABLE OF CONTENTS Page I. PREFACE ii II. EXECUTIVE

More information

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE:

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: IRC CODE UPDATES TO: RESIDENTIAL BUILDING CONTRACTORS FROM: GARY STABER, BUILDING OFFICIAL SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: 6/1/2003 INTERNATIONAL RESIDENTIAL CODE (IRC) APPLICABILITY:

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

one structural behavior, systems and design Course Description Course Description Syllabus & Student Understandings statics mechanics of materials

one structural behavior, systems and design Course Description Course Description Syllabus & Student Understandings statics mechanics of materials ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SUMMER 2014 lecture one Syllabus & Student Understandings structural behavior, systems and design Introduction 1 Architectural Structures

More information

DIVISION: WOOD, PLASTICS AND COMPOSITES SECTION: STRUCTURAL PANELS REPORT HOLDER: EVALUATION SUBJECT: STRUCTURAL PANELS

DIVISION: WOOD, PLASTICS AND COMPOSITES SECTION: STRUCTURAL PANELS REPORT HOLDER: EVALUATION SUBJECT: STRUCTURAL PANELS 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 2182 Reissued 08/2018 This report is subject to renewal 06/2019. DIVISION: 06 00

More information

ESCONDIDO FIRE DEPT TRAINING MANUAL Section Truck Module Page 1 of 10 Building Construction Roof Types Revised

ESCONDIDO FIRE DEPT TRAINING MANUAL Section Truck Module Page 1 of 10 Building Construction Roof Types Revised Truck Module Page 1 of 10 BASIC ROOF TYPES The following roof types will summarize the majority of different types of roofs found within the City of Escondido and surrounding areas. There are several others,

More information

SECTION NON-STRUCTURAL METAL FRAMING

SECTION NON-STRUCTURAL METAL FRAMING SECTION 09 22 16 PART 1 - GENERAL 1.1 DESCRIPTION A. This section specifies steel studs wall systems, shaft wall systems, ceiling or soffit suspended or furred framing, wall furring, fasteners, and accessories

More information

UCC Permit Application Procedures

UCC Permit Application Procedures How do I apply for a permit? UCC Permit Application Procedures 1. Please complete the CodeMaster Pan Review Application 2. Please provide the scope of work description and/or construction documents/plans.

More information

Structural Conditions Assessment of Current Lapeer District Schools Administration Building 250 Second Street, Lapeer, Michigan

Structural Conditions Assessment of Current Lapeer District Schools Administration Building 250 Second Street, Lapeer, Michigan November 2, 2015 Melissa A. Malcolm Library Director Lapeer District Library 201 Village West Dr S Lapeer, MI 48446 RE: Structural Conditions Assessment of Current Lapeer District Schools Administration

More information

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No 000130 1 PURPOSE: Professional Engineering Consultants, P.A. (PEC) was engaged by University of Kansas Design & Construction Management to perform an assessment of Stouffer Place Apartment Building 20

More information

WALL CONSTRUCTION CHAPTER 6

WALL CONSTRUCTION CHAPTER 6 CHAPTER 6 WALL CONSTRUCTION SECTION R601 GENERAL R601.1 Application. The provisions of this chapter shall control the design and construction of all walls and partitions for all buildings (see Section

More information

Garage/Accessory Structures

Garage/Accessory Structures Garage/Accessory Structures City of New Prague Building Inspections Department 118 Central Ave N New Prague, MN 56071 (952) 758-4401 Fax (952) 758-1149 Requirements for submitted Building Plans Signed

More information

Earth and Engineering Sciences Building University Park, Pennsylvania

Earth and Engineering Sciences Building University Park, Pennsylvania Executive Summary The Earth and Engineering Sciences building is a 4 story educational and laboratory facility. An additional basement level is located below grade and provides the foundation for the East

More information

TECHNICAL REPORT 1. Structural Concepts / Structural Existing Conditions. Penn State Hershey Medical Center Children s Hospital. Hershey, Pennsylvania

TECHNICAL REPORT 1. Structural Concepts / Structural Existing Conditions. Penn State Hershey Medical Center Children s Hospital. Hershey, Pennsylvania TECHNICAL REPORT 1 Structural Concepts / Structural Existing Conditions Penn State Hershey Medical Center Children s Hospital Matthew V Vandersall The Pennsylvania State University Architectural Engineering

More information

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee The Structural Redesign of Boyds Bear Country and its Related Systems Included in this Presentation: Background and Existing System Proposal Problem / Solution Structural System Redesigns Pre-cast Concrete

More information

SFR SUBMITTAL REQUIREMENTS

SFR SUBMITTAL REQUIREMENTS A. FEES DUE AT TIME OF PERMIT APPLICATION The following non-refundable fees will be collected at the time of application for all residential projects. 1. Building Plan Check Fee B. CODES The City of Oak

More information

Mandatory Wood Frame Soft-story Retrofit Program STRUCTURAL DESIGN GUIDELINES

Mandatory Wood Frame Soft-story Retrofit Program STRUCTURAL DESIGN GUIDELINES INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LAMC Division 93 Effective: 11/22/15 DOCUMENT NO.: P/BC 2014-137 Revised: 06/07/16 Previously Issued As: N/A Mandatory Wood Frame Soft-story

More information

International Code Council

International Code Council International Code Council ICC 400-2012 edition Standard on the Design and Construction of Log Structures Public Comments Draft #1 The ICC Standard Development Committee on Log Structures (IS-LOG committee)

More information