1 Building Codes and Ordinances ARC 227 Week 6 Fire Resistive Construction Instructor: Rick Staub, AIA Phone:

2 Fire Resistive Construction Passive Fire Resistance passive protection is built into the building structure and provides a barrier between the structure and the fire. Active Fire Resistance active protection (fire sprinklers) respond to fire by activation of systems to contain or suppress fire and smoke to allow the structure to remain intact for a longer period of time than without protection while allowing occupants to escape Chapter 7 deals with passive fire protection Chapter 9 with active Two primary functions of Fire Resistive Construction First protection of the building structure, such protection is typically applied to the building structural members Second separation of spaces to prevent the spread of fire or smoke within a building and the spread of fire between buildings. The protection of spaces addresses fire or smoke impacts on larger scale building systems like such as floors, walls and ceilings as well as openings within these systems. Fire Area is defined as the aggregate floor area enclosed and bounded by fire walls, exterior walls and floors/roofs.

3 Fire Resistive Construction Trade-Offs between active and passive protection The code allows trade-offs between provisions of active versus passive fire protection for example 1-hour structural protection requirements can be offset by provision of sprinklers for certain occupancies. where active systems are required by code in relationship for given criteria, such as heights and area limits, then the provision of the active systems in lieu of passive is generally not allowed. Trade-offs imply a voluntary selection by the designer of how to provide the required degree of fire resistance. When code provisions otherwise require active systems they are thus not available to offset passive requirements

4 Fire Resistive Construction Fire Resistive Ratings Section 702 defines the fire-resistance rating as the period of time that a building element, component or assembly maintains the ability to confine a fire, continues to perform a given structural function, or both as determined by tests or methods described in section 703 The rating is given in hours Components, materials and assemblies are tested in a controlled environment to replicate real fire situations. ASTM American Society of Testing and Materials Test E 119 Section allows designers to use several alternative methods to show compliance with fireresistive criteria. Use ratings as recognized by Underwriters Laboratory - UL Section 720 and Table 720 shows prescriptive assemblies and their various ratings. Section 721 lets you calculate your own ratings based on formula for various materials.

5 Fire Resistive Construction Exterior Walls Section 704 Projections - Section governs the extent of allowable projections according o their relationship to the property line. projections include such elements as eave overhangs, cornices and balconies that extend beyond the floor area. projections are limited in two ways: -1/3 the length of the required fire-separation distance can project toward the property line - 12 max. projection into the area The combustibility of a projection is the same as required by the wall rating Multiple Buildings Section When two or more buildings are on a site it is assumed that an imaginary line is drawn between Refer to table 601 and 602 for required ratings. Courtyard buildings more than one-story are treated the same way, an imaginary property line must be drawn and ratings applied per the Tables. the imaginary lines do not need to be equal. Section Explains that buildings greater than 5 from the property line can assume that danger of fire is from the inside only. Buildings less than 5 from the property line assume fire danger from both sides and therefore ratings apply to both side of the exterior wall.

6 Fire Resistive Construction Exterior Walls, cont. Section 704 Openings - Section and Review table Vertical separation of openings Section Vertical exposure Section requires protection of openings in any wall that extends above an adjacent roof. Less than 15 vertically above the roof of an adjacent building on the same lot need to be protected Parapets Section makes a general statement that parapets shall be provided at exterior walls of a building. The purpose is to impede the spread of fire from one building to another. Exceptions reduce or eliminate need for a parapet. Typically need to extend 30 above the adjacent roof. No openings (skylights, hatches) with 5 of roof edge in R + M; 10 for others Summary: 1. the wall satisfies the fire-separation distance criteria per table the building area is less than 1,000 s.f. on any floor 3. the roof construction is entirely non-combustible or of at least 2-hour construction 4. the roof framing construction is protected from fire from the inside 5. for residential a fire-barrier is provided by sheathing the underside of the roof framing or the roof sheathing is non-combustible for 4

7 Exterior Walls, cont.

8 Section 705 Fire Resistive Construction Fire Walls Fire Wall A fire-resistance rated wall having protected openings, which restricts the spread of fire and extends, continuously from the foundation to or through the roof, with sufficient structural stability under fire conditions to allow collapse of construction on either side without collapse of the wall. - structural stability Fire wall must stand if adjacent wall collapse - requires fire walls to be constructed of non-combustible materials except in Type V construction. Ratings for fire walls - based on the occupancies, for most a 3-hour wall is required. Table allows 2-hours in type II and V for certain occupancies Where different occupancies are separated by a fire wall the more restrictive applies Review table Horizontal Continuity specifies that fire walls are to be continuous horizontally from exterior wall to exterior wall and extend 18 beyond the exterior surface of the exterior walls. Some exceptions Vertical Continuity requires that the fire walls be continuous vertically from the building foundation to a point at least 30 above adjacent roofs.

9 Fire Resistive Construction Fire Walls

10 Fire Resistive Construction Fire Barriers Section 706 Fire Barrier A fire-resistance-rated vertical or horizontal assembly of materials designed to restrict the spread of fire in which openings are protected. fire barriers are similar to fire walls but with simpler criteria. They are used to separate vertical exit enclosures from other egress components, to separate different occupancies, or to divide a single occupancy into different fire areas. Required fire-resistance ratings for fire barriers are determined by their use. Ratings for barriers used in egress protection are rated per the applicable sections in Chapter 10 Egress Fire barriers are to be continuous between floor levels and extend to abutting adjacent interior or exterior walls. Prevent both smoke and fire, some penetrations are allowed but must be protected. Top of the floor assembly to the underside of the deck above. Continuous through concealed spaces. Supporting floor should have the same fire-resistance rating as the barrier

11 Section 707 Fire Resistive Construction Shafts Shaft An enclosed space extending through one or more stories of a building, connecting vertical openings in successive floors, or floors and roof. Shaft enclosures differ from fire barriers in that they typically enclose shafts extending through several floors. Shafts are often constructed of the same materials as barriers but the required ratings for shafts and vertical exit enclosures are usually determined by the number of floors that they connect. Per all shafts need to be protected. 2- hours required if extending for 4 floors or more 1- hour if less than 4 floors (shaft ratings should be equal to those of the required floor assembly but not more than 2- hours) exceptions read carefully 1. openings in residential units extending less than 4 stories need not be enclosed. 2. escalators or stairs not used as egress components (if sprinklered ) do not need protection 3. pipe, vent or conduit penetrations protected at the floor and ceiling according to section need not be protected. 4. ducts protected per do not need to be protected 5. atriums in offices and malls do not need specific shaft protection but a whole lot of other stuff 6. Chimneys do not need to be in a shaft but concealed spaces must be fire blocked 7. openings less than 2-stories that are not part of egress do not need to be protected 8. ramps in parking garages can be open 9. openings connecting mezzanines with space below do not need protection 10. expansion joints at floors and walls do not need to be enclosed but must be protected per 712 as for similar penetrations.

12 Fire Resistive Construction Shafts Section 707 Shafts can not have multiple purposes you can not use a vertical exit enclosure as your duct run Where ducts enter or exit a shaft a fire damper is required so when there is a fire the damper closes to keep the integrity of the shaft rating. Laundry and waste shafts must be separated from the rest of the building by 1-hour rated access rooms at each floor level they usually dump into a room in the basement these rooms require sprinklers. Elevator shafts elevator shafts shall be constructed as other shafts adds the concept of lobbies to the mix. A rated lobby is required when an elevator opens onto an exit access corridor exceptions to lobby requirements 1. when building lobby levels are sprinklered in office the entry lobby can be open 2. with a fully sprinklered building less than 4 stories above the lowest level of firedepartment access lobbies may be eliminated

13 Section 708 Fire Resistive Construction Fire Partitions Fire Partition A vertical assembly of materials designated to restrict the spread of fire in which openings are protected Fire partitions are the next level of fire-resistive wall construction below fire walls and barriers. They typically have 1-hour fire-resistance ratings and are primarily used per section for separations between dwelling units and guest rooms; per section for separation of tenants in a covered mall and per section for exit corridors. Fire partitions have the same requirements for penetrations, openings and ductwork Fire partitions are to extend to the structure above and below with the following exceptions 1. When the floor is 1-hour rated the partition need not extend into the crawl space below. 2. When the room side fire rated membrane of a corridor extends to a fire-resistive floor or ceiling above, the corridor ceiling may be protected. 3. When the walls and ceiling form a tunnel the fir-rating need not extend above the top of the ceiling assembly. 4. In a covered mall building, partitions do not need to go to the structure between tenant spaces 5. In Group R-2, the fire partion does not need to continue up into attic space

14 Section 709 Fire Resistive Construction Smoke Barriers Smoke barrier A continuous membrane, either vertical or horizontal, such as a wall, floor, or ceiling assembly, that is designed and constructed to resist the movement of smoke. Section 709 treats smoke barriers as fire barriers, but with emphasis on restricting the migration of smoke. Smoke barriers are required to have a 1-hour rating with 20 minute opening protection. smoke barriers need to be continuous through concealed spaces unless they abut assemblies that will resist the passage of smoke, such as walls meeting fire-rated ceiling assemblies.

15 Section 710 Fire Resistive Construction Smoke Partitions Smoke partitions are not required to be rated unless they are required in a rated assembly. Continuity is required from floor to underside of deck above Openings Doors and windows should be self-closing and resist the spread of smoke from once space to another louvered doors are not allowed Joints and penetrations shall be sealed to eliminate the passage of smoke Smoke dampers are required for ductwork

16 Fire Resistive Construction Horizontal Assemblies Section 711 Horizontal assemblies are floor and ceiling/roof assemblies that require a fire-resistance rating. Their required fire resistance rating is determined by their use. The rating is primarily determined by the fire resistance rating based on type of construction as dictated in Table 601. When separating occupancies or dividing a single occupancy into fire areas, the fire resistance rating of the horizontal assembly must be examined against the requirements of Table Horizontal assemblies have the same continuity requirements as for vertical assemblies. Penetrations, joints and ducts are to be protected as for vertical assemblies allows in 1-hour rated horizontal assemblies with crawl space or attic to be removed - Unprotected skylights are allowed in a roof as long as they meet the requirements of the adjacent structure in Any structural members or walls supporting a horizontal assembly must have at least the same fire-resistance rating.

17 Fire Resistive Construction Penetrations and joint Systems Section 712 This section requires that penetrations be protected to maintain the fire-resistive integrity of the assembly being penetrated. The governing criteria for protection are that they prevent the passage of flame and hot gases into or through an assembly. Two types of penetrations 1. thru penetration passes completely through the entire assembly 2. membrane penetration only passes thru a portion of the assembly. Sleeves securely fastened to the assembly Any space between the sleeve and the penetrating item or the sleeve and the assembly must be protected by an approved fire-stop material concrete grout can be used around concrete wall penetrations Electrical outlets on either side of a rated assembly shall be staggered not less than 24, or not less than the depth of the wall cavity that is filled with cellulose loose fill or mineral fiber insulation or solid blocking. protection of penetrations in horizontal assemblies is more restrictive than vertical assemblies because heat and smoke tend to rise. Higher rated stop system is required recessed lights can not reduce the ratings of ceilings special rated fixtures

18 Section Fire Resistive Construction Penetrations and joint Systems Fire-resistant joint systems This section requires expansion, seismic movement and construction control joints to be treated in a similar manner to a penetration. The goal is that joints do not compromise the fire-resistive capabilities f the horizontal or vertical assemblies where they occur. Joints in fire-rated assemblies are to be fire tested to match the assembly rating. Joints are tested before and after movement to verify that they meet the requirements either way. joints at the intersection of floor assemblies and at exterior curtain walls are included in this section. Installed to prevent the spread of flame and hot gases

19 Fire Resistive Construction Structural members Section 715 Structural members and assemblies shall comply with the required fire-resistance rating per Table 601 and 602 supporting structural elements can not be less than the members they are supporting Columns, Girders, Beams if supporting multiple floors /roof than entire element needs to be protected individually protected on all sides. protection needs to be continuous if only supporting one story then can be encased or protected by a membrane, such as a ceiling or floor can not embed anything into the required protection layer no wires, conduits, etc. Exterior Load bearing walls reminder to review both tables 601 and 602 most restrictive is the one to follow

20 Fire Resistive Construction Opening Protectives Section 715 The requirements of this section for opening in a fire-resistive construction allow for the opening protectives to have different ratings than those for the wall. Tables and lists the requirements Opening protective are typically tested components glazed window systems or fire doors Fire doors are required to be self closing and latched (meaning when they are closed they can not be pushed open by fire drafts). Doors should be closed under most circumstances, can be on magnetic hold opens that release to close when an alarm is activated. Glazing in protected openings is limited by the code based on tested performance and the area of glazed openings. Wire glass can be installed with required thickness. High performance glazing can also be used much more expensive See Table

21 Fire Resistive Construction Opening Protectives

22 Structural Fire rating - diagram

23 Prescriptive Solutions

24 Prescriptive Solutions

25 Prescriptive Solutions

26 Prescriptive Solutions

27 Prescriptive Solutions

2012 IBC Inspection of Fire-Resistance Rated Floors, Ceilings and Roofs

2012 IBC Inspection of Fire-Resistance Rated Floors, Ceilings and Roofs Class Outline Inspection of Fire-resistance-Rated Floors, Ceilings and Roofs Based on 2012 International Building Code (IBC) Introduction Determining fire resistance Test standards Definitions Alternate

More information

2012 IBC Inspection of Fire-Resistance Rated Floors, Ceilings and Roofs

2012 IBC Inspection of Fire-Resistance Rated Floors, Ceilings and Roofs Accreditation 2012 IBC Inspection of Fire-resistance-Rated Floors, Ceilings and Roofs Based on 2012 International Building Code The International Code Council has been accredited as an Authorized Provider

More information

2015 IBC Inspection of Fire-Resistance Rated Floors, Ceilings and Roofs

2015 IBC Inspection of Fire-Resistance Rated Floors, Ceilings and Roofs Class Outline Inspection of Fire-Resistance-Rated Floors, Ceilings and Roofs Based on 2015 International Building Code, (IBC ) Introduction Determining fire resistance Test standards Definitions Alternate

More information

FIRE AND SMOKE PROTECTION FEATURES

FIRE AND SMOKE PROTECTION FEATURES CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials, systems and assemblies used for structural fire resistance and fire-resistance-rated

More information

FS , 712, 713, 714

FS , 712, 713, 714 VERTICAL OPENINGS STUDY GROUP REPORT TO CTC MEETNG CHICAGO, IL JUNE 28-29, 2012 PUBLIC COMMENTS CTC Code Change Proposal FS50-12 was Approved as Modified as shown below - No public comments for the Group

More information

FIRE AND SMOKE PROTECTION FEATURES

FIRE AND SMOKE PROTECTION FEATURES CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials, systems and assemblies used for structural fire resistance and fire-resistance-rated

More information

FIRE AND SMOKE PROTECTION FEATURES

FIRE AND SMOKE PROTECTION FEATURES CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials, systems and assemblies used for structural fire resistance and fire-resistance-rated

More information

IBC FIRE SAFETY. Code Change No: FS1-07/08. Original Proposal SECTION 702 DEFINITIONS

IBC FIRE SAFETY. Code Change No: FS1-07/08. Original Proposal SECTION 702 DEFINITIONS DOCUMENTATION IBC FIRE SAFETY Code Change No: FS1-07/08 Sections: 702.1, 704.8.2, 706.7 Proponent: Philip Brazil, PE, Reid Middleton, Inc., representing himself SECTION 702 DEFINITIONS 702.1 Definitions.

More information

Fire Inspection and Code Enforcement, 7 th Edition. Chapter 6 Building Construction: Components Inspector II

Fire Inspection and Code Enforcement, 7 th Edition. Chapter 6 Building Construction: Components Inspector II Fire Inspection and Code Enforcement, 7 th Edition Chapter 6 Building Construction: Components Today we will Discuss fire walls, party walls, fire partitions, and curtain walls Discuss roof types and coverings

More information

WOOD USE IN NONCOMBUSTIBLE BUILDINGS

WOOD USE IN NONCOMBUSTIBLE BUILDINGS INTRODUCTION The National Building Code of Canada (NBCC) 1 requires that some buildings be of noncombustible construction under its prescriptive requirements. Its use in certain types of buildings such

More information

How to Prepare Your LSE Report

How to Prepare Your LSE Report LSE Rule Category Required Documentation Information Comments / Applicable Code Sections/ 10.1 Building Height Provide the Building height in Feet Provide the number of stories above grade Helpful Hints

More information

SPARTANBURG COUNTY BUILDING CODES DEPARTMENT

SPARTANBURG COUNTY BUILDING CODES DEPARTMENT SPARTANBURG COUNTY BUILDING CODES DEPARTMENT PLAN REVIEW CHECK LIST REQUIREMENTS FOR COMMERCIAL BUILDING PERMITS Plan Review Coordinator Kris Brannon 864-596-3180 366 N. Church St Room 500 Spartanburg,

More information

2017 Commercial Building Code

2017 Commercial Building Code 2017 Commercial Building Code Wisconsin Amendments and Significant Changes Department of Safety and Professional Services Robin Zentner, P.E. Section Chief, Safety and Commercial Building Inspection Division

More information

Module 8: Ontario Building Code Fire and Spatial Separations

Module 8: Ontario Building Code Fire and Spatial Separations Ontario Building Code (OBC) 1. Fire Separations 2. Fire Resistance Ratings By Classification 3. Fire Resistance Ratings By Adjacent Use 4. Fire Resistance Ratings By Specific Space 5. Fire Resistance Ratings

More information

FCIA Webinar Gypsum Wall Patching

FCIA Webinar Gypsum Wall Patching FCIA Webinar Gypsum Wall Patching Firestop Contractors International Association Hillside, IL +1-708-202-1108 - office Bill McHugh bill @ fcia.org Nestor Sanchez, USG Corp. nsanchez@usg.com DIIM Firestopping

More information

What is a Won-Door FireGuard Door?

What is a Won-Door FireGuard Door? What is a Won-Door FireGuard Door?. A horizontal sliding accordion fire door that meets all IBC requirements for use in a means of egress and has fire ratings up to 3 hours. A Reference Guide to special

More information

2015 IBC Exit Systems

2015 IBC Exit Systems Objectives 2015 IBC Exit Systems Based on the 2015 International Building Code Upon completion, participants will be better able to: Determine those means of egress components that are defined as exits

More information

Interior FRT Wood. References to ICC Building Codes

Interior FRT Wood. References to ICC Building Codes Interior FRT Wood References to ICC Building Codes Table of Contents International Building Code (IBC) 1 International Residential Code (IRC) 6 International Mechanical Code (IMC) 7 INTERNATIONAL BUILDING

More information

2003 International Residential Building Code

2003 International Residential Building Code 2003 International Residential Building Code Section R305 Ceiling Height Habitable rooms, hallways, corridors, bathrooms, toilet rooms, laundry rooms and basements shall have a ceiling height of not less

More information

CHAPTER 26 PLASTIC SECTION BC 2601 SECTION BC 2603 GENERAL FOAM PLASTIC INSULATION

CHAPTER 26 PLASTIC SECTION BC 2601 SECTION BC 2603 GENERAL FOAM PLASTIC INSULATION CHAPTER 26 PLASTIC SECTION BC 2601 GENERAL 2601.1 Scope. These provisions shall govern the materials, design, application, construction and installation of foam plastic, foam plastic insulation, plastic

More information

Comparison of the life safety elements of the 1997 UBC and the IBC 2000.

Comparison of the life safety elements of the 1997 UBC and the IBC 2000. Comparison of the life safety elements of the 1997 UBC and the IBC 2000. Introduction The Building Performance Research Institute s mission is primarily one of education on building safety and performance.

More information

E2-09/ (IFC [B] )

E2-09/ (IFC [B] ) Code Technology Committee 2010 Final Action Agenda The following are code changes and public comments to be considered at the 2010 Dallas Final Action Hearings that are related to the CTC Area of Study

More information

INTERIOR ENVIRONMENT

INTERIOR ENVIRONMENT CHAPTER 12 INTERIOR ENVIRONMENT SECTION 1201 GENERAL 1201.1 Scope. The provisions of this chapter shall govern ventilation, temperature control, lighting, yards and courts, sound transmission, room dimensions,

More information

General Residential Code Requirements

General Residential Code Requirements Residential building code review will be based on compliance with the requirements of the Louisiana State Uniform Construction code in accordance with ACT 12 of the 2005 First Extraordinary Session of

More information

SECTION : FIRE WALL AND FIRE SUPPRESSION REGULATIONS FOR R1-Z, R-2, R-3 ZONING AND PDD CATEGORIES

SECTION : FIRE WALL AND FIRE SUPPRESSION REGULATIONS FOR R1-Z, R-2, R-3 ZONING AND PDD CATEGORIES SECTION 500.110: FIRE WALL AND FIRE SUPPRESSION REGULATIONS FOR R1-Z, R-2, R-3 ZONING AND PDD CATEGORIES A. Purpose. The intent of this regulation is to amend the current adopted edition of the International

More information

CHAPTER 26 PLASTIC SECTION 2601 SECTION 2603 GENERAL FOAM PLASTIC INSULATION

CHAPTER 26 PLASTIC SECTION 2601 SECTION 2603 GENERAL FOAM PLASTIC INSULATION CHAPTER 26 PLASTIC SECTION 2601 GENERAL 2601.1 Scope. These provisions shall govern the materials, design, application, construction and installation of foam plastic, foam plastic insulation, plastic veneer,

More information

Exception: All layers of single and multilayer reflective plastic core foil insulation shall comply with Section 2604.

Exception: All layers of single and multilayer reflective plastic core foil insulation shall comply with Section 2604. 1. Fiberboard insulation shall comply with Chapter 23. 2. Foam plastic insulation shall comply with Chapter 26. 3. Duct and pipe insulation and duct and pipe coverings and linings in plenums shall comply

More information

CALIFORNIA COMMERCIAL BUILDING INSPECTOR CONTENT OUTLINE 01. GENERAL ADMINISTRATION 6% Project Administration 1%

CALIFORNIA COMMERCIAL BUILDING INSPECTOR CONTENT OUTLINE 01. GENERAL ADMINISTRATION 6% Project Administration 1% CALIFORNIA COMMERCIAL BUILDING INSPECTOR CONTENT OUTLINE EXAM ID: I1 80 multiple-choice questions 3-1/2-hour time limit Open book 01. GENERAL ADMINISTRATION 6% 0101. Project Administration 1% Verify that

More information

2012 IBC Exit Systems

2012 IBC Exit Systems Accreditation Based on the 2012 International Building Code The International Code Council has been accredited as an Authorized Provider by the International Association for Continuing Education and Training

More information

CHAPTER 6 TYPES OF CONSTRUCTION

CHAPTER 6 TYPES OF CONSTRUCTION CHAPTER 6 TYPES OF CONSTRUCTION SECTION 61 GENERAL 61.1 Scope. The provisions of this chapter shall control the classification of buildings as to type of construction. SECTION 62 CONSTRUCTION CLASSIFICATION

More information

Outcomes of ICC Tall Wood Ad Hoc Committee: Proposals and Discussion

Outcomes of ICC Tall Wood Ad Hoc Committee: Proposals and Discussion Outcomes of ICC Tall Wood Ad Hoc Committee: Proposals and Discussion DES605 Sam Francis, C.B.O. Senior Director, National Programs American Wood Council Paul Coats, P.E., C.B.O. Southeast Regional Manager

More information

Insulation, Fireblocking, Draftstopping and Crawl Space Requirements REVISION DATE: JANUARY 2017

Insulation, Fireblocking, Draftstopping and Crawl Space Requirements REVISION DATE: JANUARY 2017 City of Republic Community Development Department Insulation, Fireblocking, Draftstopping and Crawl Space Requirements REVISION DATE: JANUARY 2017 Insulation Requirements Insulation (2012 IRC Section R302.10.1):

More information

WON-DOOR CORPORATION Won-Door FireGuard Applications

WON-DOOR CORPORATION Won-Door FireGuard Applications WON-DOOR CORPORATION Won-Door FireGuard Applications A Code Analysis WON-DOOR CORPORATION Won-Door FireGuard Applications A Code Analysis THE INTERNATIONAL BUILDING CODE is widely recognized in the United

More information

Protecting Penetrations in Fire Rated Construction

Protecting Penetrations in Fire Rated Construction Protecting Penetrations in Fire Rated Construction NY State Fire Marshals and Inspectors Conference September 7 th Bruce E. Johnson UL Codes and Advisory Services UL and the UL logo are Trademarks of UL

More information

Residential Accessory Structures & Room Additions

Residential Accessory Structures & Room Additions Residential Accessory Structures & Room Additions Planning and Development Services Department Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email:

More information

4. Number of drawings required: ( ) Locations of nearest streets

4. Number of drawings required: ( ) Locations of nearest streets CITY OF MANSFIELD BUREAU OF BUILDING AND CODES 30 NORTH DIAMOND STREET 3RD FLOOR MANSFIELD, OHIO 44902 Phone (419) 755-9688 Fax (419) 755-9453 www.ci.mansfield.oh.us COMMERCIAL BUILDING PLAN REQUIREMENTS

More information

AIR CRE Industrial Building Standards

AIR CRE Industrial Building Standards AIR CRE Industrial Building Standards Established March 1993 AIR CRE 500 N Brand Blvd, Suite 900, Glendale CA, 91203 AIR CRE INDUSTRIAL BUILDING STANDARDS TABLE OF CONTENTS SECTION 1 Introduction P. 1

More information

780 CMR: 9 th Edition Massachusetts State Building Code. Presented to: BSA Codes Committee. DATE: January 20, 2016

780 CMR: 9 th Edition Massachusetts State Building Code. Presented to: BSA Codes Committee. DATE: January 20, 2016 780 CMR: 9 th Edition Massachusetts State Building Code Presented to: BSA Codes Committee DATE: January 20, 2016 This course is registered with AIA CES for continuing professional education. Credit(s)

More information

INTERIOR ENVIRONMENT

INTERIOR ENVIRONMENT CHAPTER 12 INTERIOR ENVIRONMENT > SECTION 1201 GENERAL 1201.1 Scope. The provisions of this chapter shall govern ventilation, temperature control, lighting, yards and courts, sound transmission, room dimensions,

More information

Administrative Changes

Administrative Changes Revised 11/29/06 Knox County Residential Building Codes Significant Changes From The 1995 CABO One And Two Family Dwelling Code To The 2006 International Residential Code All one and two family dwellings

More information

EXIT ACCESS RAMP. An interior ramp that is not a required interior exit ramp.

EXIT ACCESS RAMP. An interior ramp that is not a required interior exit ramp. Coordination with language throughout code 10/05/2011 Stair vs. stairway Repetitive language with stairways and ramps Including ramps when applicable The locations for stair, stairway and ramp as used

More information

UBC. (1997 Edition) (p.1-116) 2-hr. shaft required for

UBC. (1997 Edition) (p.1-116) 2-hr. shaft required for Protection of Shaft Enclosures (Exit Stairs) Protection of Shaft Enclosures (Other Shafts) Comparison on Fire Safety Provisions* (Revised 2/28/03) (S) = Small difference in fire protection, (M) = Moderate

More information

FBC 5 th Edition. General. Update to the Florida Building and Residential Codes Updates to the Florida Building and Residential Codes

FBC 5 th Edition. General. Update to the Florida Building and Residential Codes Updates to the Florida Building and Residential Codes Updates to the Florida Building and presented by T. Eric Stafford T. Eric Stafford & Associates, LLC This material is protected and the property of T. Eric Stafford & Associates, LLC and cannot be reproduced

More information

2/23/2015. Chapter 1 Scope and Administration. General Intent Title Scope Intent. Instructor: Jeff Hyde

2/23/2015. Chapter 1 Scope and Administration. General Intent Title Scope Intent. Instructor: Jeff Hyde Florida Building Code Existing Building, 5 th Edition 2014 Instructor: Jeff Hyde Chapter 1 Scope and Administration Chapter 2 Definitions Chapter 3 Compliance Methods Chapter 4 Prescriptive Compliance

More information

Typical Finished Basement Details

Typical Finished Basement Details Albemarle County, Virginia Typical Finished Basement Details Based on the 2012 Virginia Residential Code Finished basements must be constructed in conformance with these details. For requirements, details

More information

Approved Items IBC-Means of Egress

Approved Items IBC-Means of Egress Important Changes to the 2018 IBC for R-2 (Apartments) Green - Favorable Action for Multifamily Construction Red - Unfavorable Action for Multifamily Construction Yellow - Item of interest to Multifamily

More information

Assemblies Evaluated For 1. Non Axial Load Bearing Wall 2. Transverse Load Capacity 3. Fire Resistance 4. Abuse Resistance

Assemblies Evaluated For 1. Non Axial Load Bearing Wall 2. Transverse Load Capacity 3. Fire Resistance 4. Abuse Resistance Pei Evaluation Service is an accredited ISO Standard 17065 Product Certifier, accredited by the IAS. This Assembly Evaluation Report represents a product that Pei ES has Evaluated. This Assembly Evaluation

More information

2010 National Building Code Adoption and Associated Process Changes

2010 National Building Code Adoption and Associated Process Changes Building Inspection City of Moncton 655 Main Street Moncton, NB E1C 1E8 Phone: (506) 856-4375 Fax: (506) 856-4348 Bulletin No. 14 From: Randy Richard Date: February 9, 2015 Subject: 2010 National Building

More information

BC BUILDING CODE ERRATA

BC BUILDING CODE ERRATA BC BUILDING CODE ERRATA The following changes should be made to print and offline copies of the 2012 BC Codes. The 2012 BC Codes subscription products include these changes. Highlighted text is used in

More information

2015 IBC Update. Copyright 2014 International Code Council #1000PDF15 1

2015 IBC Update. Copyright 2014 International Code Council #1000PDF15 1 Goal 2015 IBC Update Based on the International Building Code (IBC ) The goal is to familiarize building officials, fire officials, plans examiners, inspectors, design professionals, contractors, and others

More information

CITY OF CALABASAS RESIDENTIAL PLAN REQUIREMENTS 1 OF 5 8/2017 PLAN INFORMATION

CITY OF CALABASAS RESIDENTIAL PLAN REQUIREMENTS 1 OF 5 8/2017 PLAN INFORMATION 1 PLAN INFORMATION Residential plans must be legible and capable of digital scanning. All sheets shall be the same size and distinctly labeled with a sheet title and number. The minimum dimension of the

More information

Residential Building Inspections

Residential Building Inspections Residential Building Inspections Foundations, Grade Beams, Pile Caps, Foundation Pads 1. All trenches or excavations and formwork shall be in accordance with the size(s) and configuration(s) as per approved

More information

City of Des Moines. Permit and Development Center 602 Robert D Ray Drive Des Moines, IA Phone: Fax:

City of Des Moines. Permit and Development Center 602 Robert D Ray Drive Des Moines, IA Phone: Fax: City of Des Moines Permit and Development Center 602 Robert D Ray Drive Des Moines, IA 50309 Phone: 515-283-4200 Fax: 515-283-4270 This Code Analysis Form must be completed and returned with the Building

More information

Code Requirements for Existing Buildings. R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617)

Code Requirements for Existing Buildings. R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) Code Requirements for Existing Buildings R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com R.W. Sullivan Engineering (RWS) was established in 1945 and currently

More information

WoodWorks. Learning Objective. Presentation Overview. Fire Protection II Requirements for rated assemblies and common detailing

WoodWorks. Learning Objective. Presentation Overview. Fire Protection II Requirements for rated assemblies and common detailing WoodWorks Fire Protection II Requirements for rated assemblies and common detailing Scott Lockyear, PE Learning Objective Discuss the type of rated assembly requirements in the International Building Code.

More information

Boulder City NV Prepared by (Print Name) Signature Date

Boulder City NV Prepared by (Print Name) Signature Date City of Boulder City Community Development Department Building & Safety Division 401 California Avenue Boulder City, NV 89005-2600 702-293-9282 (Main Line) 702-293-9392 (Fax) 2009 International Energy

More information

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

SPACE TYPE: OUTSIDE PARKING (STRUCTURE) SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.

More information

The Building Codes A.R.E. Building Design and Construction Exam Prep

The Building Codes A.R.E. Building Design and Construction Exam Prep Know Thy Codes! The Building Codes Building Codes The Code of Hammurabi 4000bc Developed 19 th and 20 th c. Codes define what you can and can t do Allowable area and height based on degree of danger Fire

More information

One and Two Family Additions

One and Two Family Additions One and Two Family Additions An addition to a house, duplex, garage, or an accessory structure requires a building permit prior to performing any construction. Building Department & Permit Office Mon-Fri

More information

Chapter 4-16 SPECIAL DESIGN STANDARDS FOR TYPE V CONSTRUCTION

Chapter 4-16 SPECIAL DESIGN STANDARDS FOR TYPE V CONSTRUCTION Chapter 4-16 SPECIAL DESIGN STANDARDS FOR TYPE V CONSTRUCTION Sections: 4-16-01 PURPOSE 4-16-02 APPLICABLE AREA 4-16-03 CONSTRUCTION AND OCCUPANCY 4-16-04 UPPER BUILDING AREA, HEIGHT, NUMBER OF STORIES

More information

2018 APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES)

2018 APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) 2018 APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) (Reproduce the following data on the building plans sheet 1 or 2) Name of Project: Address:

More information

1 AND 2 FAMILY DWELLING REQUIREMENTS

1 AND 2 FAMILY DWELLING REQUIREMENTS PLAN REQUIREMENTS: 1 AND 2 FAMILY DWELLING REQUIREMENTS All residential plans including additions and attached garages shall be designed to the current edition of the International Residential Code. Plans

More information

BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS

BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS Please note: This construction plan component list is to be used as a guide to assist you with your project. There may be elements unique to your project not

More information

SIDEWALK & RAILING REPLACEMENT BOARD OF ED BUILDING

SIDEWALK & RAILING REPLACEMENT BOARD OF ED BUILDING PROJECT: 25 E 5 S SALT LAKE CITY, UTAH 84111 CODE ANALYSIS APPLICABLE CODES 675 E. 5 S. Suite 4 DFCM PROJECT NUMBER: 182782 DFCM CONTRACT NUMBER: 18793 STRUCTURAL ENGINEER: REAVELEY ENGINEERS + ASSOCIATES

More information

SPECIAL DETAILED REQUIREMENTS BASED ON USE AND OCCUPANCY

SPECIAL DETAILED REQUIREMENTS BASED ON USE AND OCCUPANCY CHAPTER 4 SPECIAL DETAILED REQUIREMENTS BASED ON USE AND OCCUPANCY SECTION 401 SCOPE 401.1 Detailed use and occupancy requirements. In addition to the occupancy and construction requirements in this code,

More information

A Closer Look Inspection Service 2015 IECC Residential DFW area handout

A Closer Look Inspection Service 2015 IECC Residential DFW area handout 103.2 Information required on construction documents 1. Designation of the Thermal Building Envelope on the plans 2. Insulation Material and their R Value 3. Fenestration U and SHGC values 4. Area weighted

More information

First Revision No NFPA [ Section No ]

First Revision No NFPA [ Section No ] First Revision No. 1001-NFPA 5000-2015 [ Section No. 7.2.5.6.8 ] Global FR-6108 7.2.5.6.8 Exterior Nonbearing Walls. Exterior nonbearing walls tested shall be permitted when tested in accordance with,

More information

Managing Vertical Fire Spread in Multi-Story Buildings Through Effective Perimeter Fire Barrier Systems

Managing Vertical Fire Spread in Multi-Story Buildings Through Effective Perimeter Fire Barrier Systems Managing Vertical Fire Spread in Multi-Story Buildings Through Effective Perimeter Fire Barrier Systems March 21, 2018 2016 Owens Corning. All Rights Reserved. Thermafiber, Inc. All Rights Reserved. This

More information

E d u c a t i o n a l S e m i n a r s f o r B u i l d i n g & R e s i d e n t i a l C o d e

E d u c a t i o n a l S e m i n a r s f o r B u i l d i n g & R e s i d e n t i a l C o d e I N D E X E d u c a t i o n a l S e m i n a r s f o r B u i l d i n g & R e s i d e n t i a l C o d e Title Course Number *Seminar Length (days) Pg. Class Scheduling Policies 8 International Building Code

More information

Prescriptive Checklist for the 2015 Washington State Energy Code

Prescriptive Checklist for the 2015 Washington State Energy Code Prescriptive Checklist for the 2015 Washington State Energy Code Chapter 51-11R WAC STATE BUILDING CODE ADOPTION AND AMENDMENT OF THE 2015 EDITION OF THE INTERNATIONAL ENERGY CONSERVATION CODE, RESIDENTIAL

More information

Fire Behaviour in Different Building Types

Fire Behaviour in Different Building Types ^ Fire Behaviour in Different Building Types Agenda Single Storey Steel Frame High Rise Purpose Built Domestic Modern Construction Materials / Methods Converted Buildings Evacuations Building design shapes

More information

JC Code & Construction Consultants, Inc. Advanced 2010 FBC Update Ch. 1 to 16

JC Code & Construction Consultants, Inc. Advanced 2010 FBC Update Ch. 1 to 16 JC Code & Construction Consultants, Inc. Advanced 2010 FBC Update Ch. 1 to 16 Welcome! This course is designed to provide an overview of the most significant changes to the 2010 edition of the Florida

More information

AKF Group LLC. A. Vernon Woodworth FAIA

AKF Group LLC. A. Vernon Woodworth FAIA AKF Group LLC 780 CMR 9 th Edition: Major Changes AKF T A. Vernon Woodworth FAIA 3/14/17 Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion

More information

GENERAL PLAN REVIEW REQUIREMENTS

GENERAL PLAN REVIEW REQUIREMENTS GENERAL PLAN REVIEW REQUIREMENTS Cover Letter A letter (or an authorized pre-printed form) authorizing CCIS to perform the Plan Review is required. CCIS performs plan reviews for the ICC International

More information

2012 INTERNATIONAL CODES SIGNIFICANT CHANGES

2012 INTERNATIONAL CODES SIGNIFICANT CHANGES 2012 INTERNATIONAL CODES SIGNIFICANT CHANGES TIM PATE CHIEF BUILDING OFFICIAL CITY AND COUNTY OF BROOMFIELD 2012 IRC 1. Section R302.1 has been modified to allow reduced fire separation distances when

More information

Feature Zone IECC 2009 IECC

Feature Zone IECC 2009 IECC Feature Zone 3 2006 IECC 2009 IECC Window U factor 0.65 0.50 Skylight U factor 0.65 0.65 Window SHGC 0.40 0.30 Ceiling R value 30 30 Wood frame R value 13 13 Mass wall R value 1 5 5/8 Floor R value 19

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-07 84 00 (May 2010) Change 1-08/13 ------------------------ Preparing Activity: USACE Superseding UFGS-07 84 00 (October 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

HOT SPRINGS FIRE DEPARTMENT EVALUATION OF DOWNTOWN LEGACY STRUCTURES Savoy Hotel Thompson Building Dugan Stewart Building May 16, 2012

HOT SPRINGS FIRE DEPARTMENT EVALUATION OF DOWNTOWN LEGACY STRUCTURES Savoy Hotel Thompson Building Dugan Stewart Building May 16, 2012 HOT SPRINGS FIRE DEPARTMENT EVALUATION OF DOWNTOWN LEGACY STRUCTURES Savoy Hotel Thompson Building Dugan Stewart Building May 16, 2012 0 On May 16,, 2012 Hot Springs Firefighters conducted an evaluation

More information

Analysis of Changes for the 5 th Edition (2014) of the Florida Codes

Analysis of Changes for the 5 th Edition (2014) of the Florida Codes Analysis of Changes for the 5 th Edition (2014) of the Florida Codes Changes to the Florida Building Code, Existing Building This Analysis of Changes for the 5 th Edition (2014) of the Florida Codes is

More information

Advanced Ventilation for Residential applications FBC Res 2010.

Advanced Ventilation for Residential applications FBC Res 2010. Advanced Ventilation for Residential applications FBC Res 2010. Course Description Review of the Residential Ventilation requirements in the Florida Building Code, Residential 2010. I. Introduction Dean

More information

Applying the Building Code During Design

Applying the Building Code During Design Applying the Building Code During Design A Step-By-Step Process AIA Learning Units The Salt Lake City CSI Chapter is a Registered Provider with The American Institute of Architects Continuing Education

More information

CITY OF DANA POINT. COMMUNITY DEVELOPMENT, BUILDING AND SAFETY Golden Lantern, Suite 209 Dana Point, CA

CITY OF DANA POINT. COMMUNITY DEVELOPMENT, BUILDING AND SAFETY Golden Lantern, Suite 209 Dana Point, CA CITY OF DANA POINT COMMUNITY DEVELOPMENT, BUILDING AND SAFETY 33282 Golden Lantern, Suite 209 Dana Point, CA 92629 949 248-3594 www.danapoint.org B005 COM STRUCT 2016 CALIFORNIA CODES CODE CYCLE 01/01/2017

More information

1. Frozen food warehouses used solely for storage of Class I and II commodities where protected by an approved automatic sprinkler system.

1. Frozen food warehouses used solely for storage of Class I and II commodities where protected by an approved automatic sprinkler system. Draft curtains are typically used in warehouses, aircraft hangars and large industrial plants to contain or channel smoke that rises to the ceiling in a fire. They can keep the smoke from rolling across

More information

Fire Safety and Performance of Wood in Multi-Residential and Commercial Buildings. Boris Iskra Forest & Wood Products Australia

Fire Safety and Performance of Wood in Multi-Residential and Commercial Buildings. Boris Iskra Forest & Wood Products Australia Fire Safety and Performance of Wood in Multi-Residential and Commercial Buildings Boris Iskra Forest & Wood Products Australia This Presentation 1. Fire Hazard Properties Building Code of Australia Volume

More information

Fairfax County, Virginia

Fairfax County, Virginia Fairfax County, Virginia Typical Finished Basement Details Based on the 2009 International Residential Code CONTENTS General Requirements... 2 Emergency Escape and Rescue... 2 Wall Construction... 3 Floor/ceiling

More information

PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT. Construction requirements for LOWER LEVEL DEVELOPMENT. in residential dwellings

PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT. Construction requirements for LOWER LEVEL DEVELOPMENT. in residential dwellings PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT Construction requirements for LOWER LEVEL DEVELOPMENT in residential dwellings January 2018 contents GENERAL INFORMATION... 3 BUILDING CODE REQUIREMENTS...

More information

June 7, 2012 PARTIES INTERESTED IN HVAC DUCT ENCLOSURE ASSEMBLIES

June 7, 2012 PARTIES INTERESTED IN HVAC DUCT ENCLOSURE ASSEMBLIES June 7, 2012 TO: PARTIES INTERESTED IN HVAC DUCT ENCLOSURE ASSEMBLIES SUBJECT: Revisions to the Acceptance Criteria for Metallic HVAC Duct Enclosure Assemblies, Subject AC179-0612-R1 (MB/CA) Dear Colleague:

More information

BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018)

BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018) BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018) PERMIT SUBMITTAL CHECKLIST: Signed and completed Building Permit application form. A separate Electrical permit is required from

More information

BUILDING CODE COMMISSION

BUILDING CODE COMMISSION Ruling No. 02-22-877 Application No. 2002-19 BUILDING CODE COMMISSION IN THE MATTER OF Subsection 24(1) of the Building Code Act, S.O. 1992, c. 23, as amended. AND IN THE MATTER OF Sentences 3.3.1.2.(3),

More information

IECC 2015 with Hawaii Amendments COMMERCIAL DESIGN CHECKLIST

IECC 2015 with Hawaii Amendments COMMERCIAL DESIGN CHECKLIST IECC 2015 with Hawaii Amendments COMMERCIAL DESIGN CHECKLIST ENVELOPE REQUIREMENTS Project: Date: Instructions RECOMMENDED: List performance values, note exceptions that were applied, or provide other

More information

PENNSAFE BUILDING INSPECTION SERVICES LLC Deck and Roof Cross Section Submittal

PENNSAFE BUILDING INSPECTION SERVICES LLC Deck and Roof Cross Section Submittal PENNSAFE BUILDING INSPECTION SERVICES LLC Deck and Roof Cross Section Submittal Roof Size: Width: Length: Roof Type: Gable: Hip: Shed: Roof Pitch: (check one) Trusses: Rafters: Spacing of Trusses or Rafters:

More information

INTERIOR FINISHES CHAPTER 8

INTERIOR FINISHES CHAPTER 8 CHAPTER 8 INTERIOR FINISHES SECTION 801 GENERAL 801.1 Scope. Provisions of this chapter shall govern the use of materials used as interior finishes, trim and decorative materials. 801.2 Interior wall and

More information

Chapter 2: Foundation

Chapter 2: Foundation Chapter 2: Foundation Crawlspace [V502.1.2] [V502.1.2] [V502.1.3] Vents. Vents in the crawlspace help keep floor insulation and floor framing dry. Crawlspace vents also reduce the potential for radon buildup

More information

Inspection Checklist Residential Building Final July 2016

Inspection Checklist Residential Building Final July 2016 Inspection Checklist Residential Building Final July 2016 This Inspection Checklist reflects code requirements of the 2015 International Residential Code (IRC), 2015 Uniform Plumbing Code (UPC), 2014 National

More information

Following are the NMHC/NAA Recommendations for the ICC Online Consensus Voting which opens on February 8 th, 2016:

Following are the NMHC/NAA Recommendations for the ICC Online Consensus Voting which opens on February 8 th, 2016: Following are the NMHC/NAA Recommendations for the ICC Online Consensus Voting which opens on February 8 th, 2016: These recommendations are only for those issues that are of concern to the multifamily

More information

PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION

PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION Permit No. 175 Beaver Drive, P.O. Box 486 DuBois, PA 15801 Phone: 814-375-1111 Fax: 814-375-1117 Toll Free: 855-PENNSAF LOCATION OF PROPOSED

More information

RESIDENTIAL NEW CONSTRUCTION PLAN REVIEW CHECKLIST

RESIDENTIAL NEW CONSTRUCTION PLAN REVIEW CHECKLIST This list is provided as a guide to help you understand the information that must be contained on the construction drawings. This list is not all-inclusive of all building codes but is used as a general

More information

Only required in new home construction

Only required in new home construction Fire Protection of Lightweight Floor Systems Options & questions to consider y p q August 9, 2011 1:00 PM Presented by Bryan Heitzmann Training & Education Development Specialist, PHRC Act 1 of 2011 /

More information