1 Practical Completion Report Inspection date 1 st January Client Mohit Vir Job Details Address Lot 3349 Limone street Aveley. W.A. Photograph shows the front elevation of the residence. DESCRIPTION OF THE PREMISES The property in question is a freestanding, single storey, full brick, metal roofed building constructed on a concrete slab floor. It is situated on a level site at a similar height to the street. The weather at the time of my inspection was intermittent showers. The level of completed construction at the residence is considered to be close to Practical Completion. Preamble I attended the residence to undertake a Practical Completion assessment prior to handover to the owner.
2 About This Report SHS Building Consultants practical completion report identifies defects and incomplete elements in the readily accessible areas of the building. The intention of this report is to provide a list of workmanship concerns at the current stage of construction. The report is non-invasive and is a visual inspection only. The terms and conditions provided to the client prior to inspection should be read in conjunction with this report. The consultant will compare the standard of finish and workmanship with prevailing acceptable industry standards. The report represents SHS building consultants expert building opinion and attempts to identify common defects apparent at the time of the inspection most notably those that may occur in the future as a result of defective installation. The report should not be considered exhaustive and it is noted that builder remains responsible for the identification and rectification of their own and their contractors defective building work. The report does not deal with any contractual issues including whether or not the builder has used or installed a specific brand of tile, tap, appliance, etc. or has built the home to the contracted design. The report does not deal with certification of the building or specific building compliance unless noted. However this report will reference specific building code requirements and Australian Standards when assessing the building for workmanship and acceptable trade practices. The report does not provide details of the method, extent or cost of any remedial work required. The client is made aware that the fit for purpose and design requirements as well as expected performance requirements for all building components including alternative solutions and common building components and installations are not able to be reasonably assessed for the purposes of a pre handover report. Please refer to our terms and conditions which are provided to the client before the date of inspection for clarification on accessible areas, method of inspection and other information relating to the inspection and report. This report does not replace the builders warranty and is not a compliance report. An important note on the identification of defective building work If the builder disputes that an item within this report is defective and he is of the opinion that the item does in fact meet BCA (NCC), manufacturer installation guides or Australian Standard requirements evidence supporting that view must be provided. If the item is a Deemed-to- Satisfy or Alternative Solution, the testing process and a statement regarding how the item complies with the performance requirements of the BCA will need to be provided. All Manufacturer installation requirements are considered mandatory and items are considered defective if they are not installed in accordance with the manufacturer s installation requirements. Items not installed in accordance with the manufacturer installation requirements are generally not covered by the manufacturer s warranty. Australian Standards are referenced within this report as both a means of establishing what is acceptable industry practice and also (for building standards referenced within the BCA) compliance with the BCA. The method used to determine defective building work is in accordance with The Building Commission of Western Australia guidelines. As such this report may be used an expert witness report at the building commission or in court.
3 A note on acceptable viewing positions The inspection of the finished surfaces and appliances at the residence was undertaken in accordance with accepted industry practice. The accepted industry practice for inspecting defects and surfaces is outlined within Standards and Tolerance Guide 2007 which illustrates: Diagram F: Normal viewing position for the inspection of painting defects is 1.5m from the wall, floor and ceiling and 600mm from fixtures and appliances. The inspection was undertaken on a sunny day with all lights that were illuminating the surface being diffused and not glancing off or parallel to the surface. The contract has not been reviewed therefore no comment has been provided on the contents of the agreement between builder and client. For the purposes of establishing incomplete work items that are not usually included within a completed home have not been assessed in regards to level of completion. All installed items have been inspected regardless of whether the client of the builder supplied or installed them. This report has been provided to the client and as such any correspondence from the builder must be directed to the client. If the client or builder wishes to engage SHS Building Consultants to provide comment on replies to this report a further fee will be applicable. No fee is payable by the client for verbal clarification regarding an item within this report.
4 Walls (Item 1) I observed that weepholes were not installed above the window head and sill flashings and also to the base of all cavity masonry walls at 1.2m centres. Australian Standard Masonry structures Weepholes states: Weepholes Weepholes shall be provided wherever it is necessary to drain moisture from or through masonry construction. Where flashings are incorporated in the masonry, weepholes shall be provided in the masonry course immediately above the flashing, at centres not exceeding 1200 mm. It is noted that all brick cavities require weepholes to prevent moisture build up (from condensation and / or water entering within the cavity around openings and window / door glazing etc) and that all openings greater than 1m wide require weepholes. It is further noted that the existence of sill or header flashings was not able to be confirmed. However flashings which extend over brick wall cavities are required to all wall openings and window headers not protected by an eave, regardless of size, in accordance with The Building Code of Australia. Further work required: Weepholes are required to be installed to all window flashings not protected by an eave.to direct moisture out of the cavity around wall openings in accordance with Australian Standard (Item 2) I observed that some of the face bricks throughout the residence and in particular the garage are affected by vanadium staining as indicated by the yellow / green colour to the brick walls as well as mortar residue. Vanadium staining in brickwork is a term that describes minerals and salt residue left behind as moisture evaporates from bricks. It is a normal process of the bricks drying and it is my opinion that bricks affected by staining should be cleaned prior to hand over and again near the end of the builders defect liability period if it reappears. Australian Standard 3700-Masonry Structures Cleaning states: Masonry shall be cleaned and stains removed, as necessary, in such a manner that the work is not damaged. Particular care shall be taken to protect adjacent work from the effects of any acid used in cleaning. Care shall be taken when using high-pressure water cleaners not to damage mortar joints and masonry units. Further work required: The face brick walls should be cleaned in accordance with Australian Standard It is noted that the brick manufacturer s installation guide has the correct procedure for cleaning bricks affected by vanadium and other staining as well as residue from building work and that the common practice of using of hydrochloric acid is not recommended by most brick manufacturers as it usually results in further (and irremovable) staining.
5 Roof Covering (Item 3) The front parapet wall has been fitted with a flashing which does not extend to cover all sides of the wall. Where gaps exist the gaps have been filled with flexible sealant. Flexible sealant is expected to deteriorate over time with U.V light and weathering as well as cracks resulting from differential building movement which will lead to water entry in coming years. Further work required: Replace the flashing so that all four sides of the parapet are covered and that flexible sealant alone is not relied upon for the purposes of water proofing. (Item 4) A flashing above the front entry has been installed backwards with the mini break bending away from the wall. The gap has been filled with flexible sealant and the sealant has begun to crack. Further work required: Remove the flashing and install a new flashing in accordance with accepted industry practice and the manufacturer s installation requirements. (Item 5) The client is made aware that as a result of the design of the metal roof covering special care must be taken to ensure that even a small amount of debris does not collect on the roof and prohibit rain water escaping the outlets. I am of the opinion that a more efficient design would have eliminated the need for extensive and costly maintenance. A regular roof and gutter cleaning schedule should be implemented to ensure that debris does not cause water to overflow into the roof cavity. Areas of special note to be monitored include the valley gutter at the front of the residence which has been installed on top of the final roof sheet (water passing over the ribs will likely enter the roof cavity if a small amount of debris collects at this location or if rain fall is particularly heavy.) It is noted that the manufacturer (Lysacht) requires full coverage of each adjoining roof sheet and that at this location the rib of the underlying sheet is exposed. Another notable area to be monitored is the front parapet wall where two valleys discharge into a single gutter with a single outlet with no overflow provision. I am of the opinion that water entry at these locations as a result of heavy rainfall would be considered the result of defective building work as there is no overflow provision to the parapet wall gutter. Until such time as the roof leaks I am unable to consider the work to be defective. However the client should be aware that roof leaks at the aforementioned locations are likely and should they occur an experienced building consultant will be able attribute at least part of the resultant damage to the design of the roof covering. It is noted that should water entry occur at these locations the performance requirements of the Building Code of Australia would not be considered to have been met and therefore defective building work would be implied. Cleaning (Item 6) The entire residence and all building components should be cleaned prior to handover to ensure that all window frames, cabinetry, tiled surfaces, glass and all other building components are presented in a clean and as new condition. I note that most of the window frames have plaster residue. Special care should be taken not to damage powder coated window frames and the like. Further work required: Professionally clean the entire residence prior to handover.
6 General (Item 7) The sealant to one of the ensuite shower recess wall junctions has not been smoothed over and has therefore not adhered to the face of the tiles at the top of the wall tiles. The sealant to the splashback tiles within the shower ensuite is incomplete and does not extend to the end of the tiles over the vanity. I consider that to be effective to prevent water entry and to provide a suitable aesthetic the sealant should be removed and replaced or extended to provide a suitable amount of cover. (Item 8) The painting and paint preparation at the residence was observed to be incomplete. There are several areas of paint which is missing (a hole in the rear portico ceiling, the gaps between rails and shelving in several of the robes and the kitchen pantry). For the purposes of a practical completion inspection not all painted surfaces to the entire residence were inspected for workmanship and it is noted that the work is not yet considered complete. The painting and preparation of all surfaces to be painted by the builder in accordance with the contract should be completed in a neat and tradesman like manner. (Item 9) The front gutter is filled with building debris which is blocking the gutter and interrupting the flow of water from the roof. The gutters should be cleaned of all debris prior to handover. (Item 10) The gutter at the front of the residence has been installed before the render was applied to the wall. As a result the render has been installed around the gutter and is uneven in places. It is expected that the render will crack around the gutter due to the the metal expanding and contracting with changes in air temperature. The uneven render is directly over the front entry and detracts from the finished product. I am of the opinion the area should be rectified to prevent future cracking and provide a suitable aesthetic. (Item 11) The pins to the hinges of the ensuite door require pushing down into the hinge. (Item 12) The grout to the ensuite shower recess floor is a different colour in places. It is unclear whether it is the tile showing through or discoloration to the grout. Notwithstanding the cause I am of the opinion that to achieve a suitable aesthetic the grout should be re-installed so that variation in colour no longer exists. (Item 13) The ceiling mounted brackets to the garage tilt panel door have been cut with a grinder, are of different sizes and are sharp to the touch. I am of the opinion that the brackets have not been installed in manner which the manufacturer of the doors would find acceptable. Therefore I do not consider the brackets to be acceptable and I consider the sharp edges of the poorly cut brackets to be a safety (cut) risk. I note that the brackets are also unpainted. (Item 14) The main bathroom window is damaged at the top of the frame as viewed form outside. I am of the opinion that the window is not of a merchantable quality as a result of the damage. It is my opinion that the window frame should be rectified so that the window is in an as new condition prior to handover. (Item 15) There are several areas where the internal slab is uneven and not smooth. Notably ply wood extends from under the bedroom 2 window. It is expected that the slab should be installed so that any future floor coverings will not be adversely affected or require rectification work to the slab in order to install the flooring. It is noted that some levelling agents may be required, depending on the choice of floor coverings to correct slight dips and valleys within the slab and that this is accepted industry practice and not considered the builders responsibility (if he has not been asked to install the floor covering.) By reading this comment the client should
7 not consider that the slab should be perfectly smooth and level prior to handover, only that lumps of concrete, pieces of ply and the like should be removed prior to handover to enable the neat installation of floor coverings.. I trust this report is of assistance. If you have any questions regarding this report please contact me. Builders Registration SHS Building Consultants
8 Photograph 1 shows no weepholes above a sill flashing. Photograph 2 shows a wall flashing has been installed with the break away from the wall. Note that the sealant has already cracked at this location. Note also that the flashing is allowing water between the wall and the flashing as indicated by the orange arrow.
9 Photograph 3 shows colour differentiation of the floor tiles in the bathroom shower recess. Photograph 4 shows the fascia requires cleaning.
10 Photograph 5 shows the slab is not prepared for the floor covering in bedroom 2. Photograph 6 shows gaps between the shelving and rails.
11 Photograph 7 shows debris in the gutters. Photograph 8 shows excessive use of sealant at the front parapet wall.
12 Photograph 9 shows a poorly installed valley gutter at the front of the residence. Water entry over the sides of the sheet laps during heavy rainfall is expected at this location.
KEVIN BURNS HOMES PRACTICAL COMPLETION REPORT VISUAL BUILDING INSPECTION REPORT
KEVIN BURNS HOMES PRACTICAL COMPLETION REPORT VISUAL BUILDING INSPECTION REPORT No. 764 CLIENT: PROPERTY ADDRESS: Jindalee DATE: 25 November 2016 WEATHER: Fine ARRIVAL TIME: 8.15am DEPARTURE TIME: 10.30am
More informationProperty Address: Sample.Prehandover.report
Web Page: www.inspectdirect.com.au INSPECT DIRECT Pty Ltd Property Address: Sample.Prehandover.report Building Construction Advice Inspection Report This is not a Pest Inspection Stage of construction:
More informationKEVIN BURNS BUILDING INSPECTIONS REGISTERED BUILDER PRE-PURCHASE VISUAL STRUCTURAL INSPECTION REPORT No. 822
KEVIN BURNS BUILDING INSPECTIONS REGISTERED BUILDER 6163 PRE-PURCHASE VISUAL STRUCTURAL INSPECTION REPORT No. 822 CLIENT: Talavera PROPERTY ADDRESS: Mindarie DATE: 20 April 2017 TIME: 9.00am WEATHER: Fine
More informationDetermination 2007/10
Determination 2007/10 Refusal of a code compliance certificate for additions to a building with timber weatherboards, profiled metal and monolithic cladding systems at 283 Maitai Valley Road, Nelson 1.
More informationINSPECT DIRECT Pty Ltd
Web Page: www.inspectdirect.com.au INSPECT DIRECT Pty Ltd Property Address: Sample.Dilapidation.Report Victoria Building Status / Dilapidation Report This is not a Pest Inspection The Building Status /
More informationFix Leaking Balconies Balcony Assessment
Fix Leaking Balconies Balcony Assessment Customer Details: Mr May 45 Anystreet Melbourne Assessments Repairs Date of inspection: Conditions: Assessor: 26 June 2017 Dry Luke O'Neill Registered Builder DBL-C
More informationStandard Inclusions for
Standard Inclusions for Preliminaries Soil test Contour Survey & Site Assessment Property Service Information Working Drawings Building permit and application fees Engineering Site & Connections Connections
More informationFIX & WATERPROOFING INSPECTION REPORT & DEFECTS LIST. Lot 426 Sample Tce, Mernda
FIX & WATERPROOFING INSPECTION REPORT & DEFECTS LIST Lot 426 Sample Tce, Mernda Call us on: 0430 318 398 info@correctinspections.com.au www.correctinspections.com.au Postal Address: P.O. Box 22 Greensborough
More informationHANDOVER INSPECTION PRE-PURCHASE BUILDING INSPECTION REPORT
PPDoesn t Apply HANDOVER INSPECTION PRE-PURCHASE BUILDING INSPECTION REPORT This Report» Building Inspection Report» House ONLY» House AND Unit» All inspections are standard visual reports in accordance
More informationPainted surfaces not meeting the acceptable performance condition shall be rectified.
8 Finishes/ Interior 8.1 Interior paint surface finish is inconsistent. A painted surface shall be generally uniform and consistent. A properly painted surface shall be assessed by normal viewing from
More informationDeluxe Inclusions for
Deluxe Inclusions for Preliminaries Soil test Contour Survey & Site Assessment Property Service Information Working Drawings Building permit and application fees Engineering Site & Connections Connections
More informationOur standard inclusions.
Our standard inclusions. We pride ourselves on offering you certainty on a fixed price that includes everything you need in your new home. Before you make a final choice on your new home, check that all
More informationBUILDING REPORT. 123 Anywhere Street Suburb City. Prepared for: Client NON INVASIVE
0 NON INVASIVE BUILDING REPORT 123 Anywhere Street Suburb City Prepared for: Client 1 Following your instructions we visited the above property on the 11/06/12 to carry out a non-invasive building inspection
More informationExecutive Inclusions PRELIMINARIES:
Executive Inclusions PRELIMINARIES: Planning, Building Rules Consent & Development Approval Payment of CITB Levy Building Indemnity Insurance Public Liability Insurance during instruction Footings Inspection
More informationVerve Inclusions. 3 Corporate Avenue Rowville VIC T 1800 SIENNA E
Verve 3 Corporate Avenue Rowville VIC T 1800 SIENNA E info@siennagroup.com.au Kitchen B F K C I E D J A G Kitchen A: Laminated finish to kitchen benchtops with 32mm thick square edge, selected from the
More informationProject Specifications
Project Specifications Unit 1, 2 & 3 / 1 Carmen Street, NEWPORT These specifications form part of the building contract. The owner shall therefore ensure that the project specifications are fully and accurately
More informationRegarding the refusal to issue a code compliance certificate for a 13-year-old house at 14 Patsy O Hara Place, Swanson, Auckland
Determination 2011/077 Regarding the refusal to issue a code compliance certificate for a 13-year-old house at 14 Patsy O Hara Place, Swanson, Auckland 1. The matter to be determined 1.1 This is a determination
More informationWEATHERTIGHTNESS (INVASIVE MOISTURE TESTING) ASSESSMENT
WEATHERTIGHTNESS (INVASIVE MOISTURE TESTING) ASSESSMENT 1 INTRODUCTION Inspection Date: 24 TH August 2016 Job No:47126 Property Inspected: 1-51 Watford Street Christchurch Weather Conditions: Fine Prepared
More informationHome Inclusions $410, HOME & LAND PACKAGE MARCOOLA Land Content $ MARCOOLA. 4 Bedroom 2 Bathroom Multiple living zones Alfresco
HOME & LAND PACKAGE MARCOOLA Land Content $180000.00 $410,000.00 Please note: actual façade may vary slightly from picture. MARCOOLA 4 Bedroom 2 Bathroom Multiple living zones Alfresco Double Lockup Garage
More informationRegarding the code-compliance of a channel drain around the foundation of a house and garage at 533 Waitoki Road, Wainui, Auckland
Determination 2011/095 Regarding the code-compliance of a channel drain around the foundation of a house and garage at 533 Waitoki Road, Wainui, Auckland 1. The matter to be determined 1.1 This is a determination
More informationRegarding the refusal to issue a code compliance certificate for a 6-year-old house at 4 Korotaha Terrace, Rothesay Bay, Auckland
Determination 2016/051 Regarding the refusal to issue a code compliance certificate for a 6-year-old house at 4 Korotaha Terrace, Rothesay Bay, Auckland Summary This determination is concerned with the
More informationInclusions FRAMING GARAGE FIXED SITE COSTS & CONNECTIONS EXTERNAL. 90mm pine wall frames with stabilised pine roof trusses
Inclusions FRAMING 90mm pine wall frames with stabilised pine roof trusses GARAGE Brick veneer garage including sectional overhead door to front (garage size product specific) Painted fibrous cement sheet
More information160.F1 PROPERTY INSPECTION REPORT 6 Vitoria St, Sebastopol, 3356 INSPECTION DETAILS Registered Practitioners Signature:
www.sherspec.com 6 Vitoria St, Sebastopol, 3356 160.F1 PROPERTY INSPECTION REPORT INSPECTION DETAILS Registered Practitioners Name: Rudolf Venema Registered Practitioners Signature: Practitioners Registration
More informationDUO Contemporary- Ash 1
Renders are indicative only. - Min Block Width 186sqm Build Size DUO 186 - Contemporary- Ash 1 4 2 1 1 1 1 DUO 186(B) 12.5 Min Block Width 4 2 2 186sqm Build Size 1 1 1 ens ensuite master bed pavilion
More informationRefusal of a code compliance certificate for a building with a monolithic cladding system at 1758 Cust Road, Canterbury
Determination 2007/9 Refusal of a code compliance certificate for a building with a monolithic cladding system at 1758 Cust Road, Canterbury 1. The matter to be determined 1.1 This is a determination under
More informationDESIGNER INCLUSIONS DISPLAY CENTRE LOCATIONS SOUTH WEST NORTH WEST HEAD QUARTERS HOOTHOMES.COM.AU. Hillcroft Estate 28 Dowie Street CLAYMORE NSW 2559
DISPLAY CENTRE LOCATIONS SOUTH WEST Hillcroft Estate 28 Dowie Street CLAYMORE NSW 2559 On Display Boston 30 (Nautica Facade) Newbrook Estate 10 Kingsbury Street AIRDS NSW 2560 On Display Kensington 28
More informationDetermination 2012/010
Determination 2012/010 Regarding the refusal of code compliance certificates for a 12-year-old house with monolithic cladding and a 7-year-old pergola addition at 12 Diana Avenue, Gisborne 1. The matter
More informationLOT 25 Blueleaf Place. Brookfield $511,879 SUMMARY
RENDERS ARE INDICATION ONLY Home size 27sq Land Size 512m2 LOT 25 Blueleaf Place Brookfield 5 2 2 $511,879 SUMMARY Land Price: $219,000 House Price: $292,879 (Fixed Price) Land Size: 512m2 House Size:
More informationVISUAL HANDOVER INSPECTION REPORT
VISUAL HANDOVER INSPECTION REPORT Complies with Australian Standard AS 4349-2007 Inspection of Buildings Part 1: Pre-Purchase Inspections - Residential Buildings - Appendix "C" Inspection Date: 2018 Exclusively
More informationSCHEDULE OF INCLUSIONS
SCHEDULE OF INCLUSIONS GENERAL Builders and Home Warranty Insurance/Builders Indemnity Insurance covered. Public Liability and Workers Comm covered during the project. 6 years structural warranty on the
More informationWeatherproofing Masonry For Northern Climates
The enduring strength, beauty and performance of a brick wall assembly is critically dependant on three components: design, workmanship and materials. If even one of these factors has not been diligently
More informationInspect Direct Pty Ltd
What do we inspect? Inspection includes a moisture check of the building for water leakage, dampness and missing insulation. We look at all areas of the building including the exterior and interior of
More informationInspect Direct Pty Ltd
What do we inspect? Inspection includes a moisture check of the building for water leakage, dampness and missing insulation. We look at all areas of the building including the exterior and interior of
More informationThis report is produced without prejudice.
Web Page: www.inspectdirect.com.au / www.buildinginspectionmelbourne.net INSPECT DIRECT Pty Ltd Property Address: Sample Report Victoria Building Construction Advice Inspection Report This is not a Pest
More informationINSPECTOR GROUP PTY LTD
Website: http://www.inspectorgroup.com.au Inspector's email: peter@inspectorgroup.com.au Inspector: Peter Hopfinger Building Surveyor & Timber Pest Inspector Registration Number: 2194 Mob: 0414 607 240
More informationBathrooms. Custom cabinetry INCLUDED
Designer Inclusions Kitchen Stone bench tops INCLUDED 20mm Caesarstone kitchen bench tops A large choice of colours Bathrooms Custom cabinetry INCLUDED Note: wall hung vanity and stone bench top not included
More information1. The matters to be determined. 2. The building work and background
Determination 2017/017 Regarding the compliance of a concrete ramp to a door threshold and the refusal to issue a code compliance certificate for a house at 16 Pathways Drive, Kerikeri Summary The determination
More informationRENDERS ARE INDICATION ONLY. Land. Home size 26sq. 28 Ajay Way, Kurunjang LEGACY 26 $545,500 ACTUAL HOUSE IMAGE PRESENTED BY
RENDERS ARE INDICATION ONLY Land 28 Ajay Way, Kurunjang LEGACY 26 $545,500 Home size 26sq 5 2 2 ACTUAL HOUSE IMAGE Home Size 26sq Land Size 451m2 FUSION 27 5 2 2 Plans and illustrations are for marketing
More informationDetermination 2011/056
Determination 2011/056 Regarding compliance of brick veneer and proposed remedial work to windows to a house at 50 Karner Drive, RD6, Te Puke (to be read in conjunction with Determination 2008/100) 1.
More informationInspection Date: 10/11/2015
This is a visual only Building Inspection & Report carried out in accordance with AS4349.0 Handover REPORT (hereinafter called the Report ) Inspection Date: 10/11/2015 Property Address: 41 sample Circuit
More informationPo Box Chartwell 3248 Hamilton Free Ph
Po Box 12660 Chartwell 3248 Hamilton Free Ph 0800 223 556 Email tony@kiwiinspections.co.nz INTRODUCTION Independent building inspection report on 12 Holly Place, Rototuna North, Hamilton This report has
More informationREPORT ON DOMESTIC BUILDING WORK
justinspections building inspection service 1234 SAMPLE STREET CITY REPORT ON DOMESTIC BUILDING WORK Page 1 of 7 Pre-Purchase Inspections Owner-Builder Reports Quality Assurance Dispute Resolution Litigation
More informationAS Interpretation of External Waterproofing as it applies to Melbourne, Class 1 buildings
AS4654.2 Interpretation of External Waterproofing as it applies to Melbourne, Class 1 buildings Climate Zone: 6 Wind Class: N1 Membrane Types: Liquid Applied Class II and Class III as defined and tested
More informationkitchen excellence $450 With the Largest Stone Kitchen Island bench available in Perth only Fully Ducted Reverse Cycle Air Conditioning
your home - your choice kitchen excellence With the Largest Sne Island bench available in Perth hurry limited time L I V I N G BRN 8867 24 Hour Sales Hotline 9202 5225 contentliving.com.au exclusive offer
More informationMAINTENANCE PLAN Wing Village Hall, Morcott Road, Wing, Oakham LE15 8SA
MAINTENANCE PLAN Roof Covering Roof slates Yearly Maintenance & Finishes 1 1, 8 & 13 Timber fascia and soffit boards Slates in good condition, some have been replaced during routine maintenance of roof.
More informationCustomer Specification
Customer Specification Hamilton Gardens, Elgin Plots 55-59, 87, 201-223 & 260-305 Page 1 Walls External walls will be of timber frame construction with external leaf of render block-work, or feature timber
More informationKitchen. Bathrooms, Powder rooms & ensuites. Preliminary. Laundry. Post Construction
Zest Inclusions Kitchen Select from a range of 600mm stainless steel gas cooktops. Select from a rnge of 600mm stainless steel underbench oven. 600mm canopy rangehood in stainless steel. Rangehood ducted
More informationHomebuyers Survey. Final Report. Mr Client. A Home, A Street, A Town. 3rd July 2014
Homebuyers Survey Final Report Mr Client A Home, A Street, A Town 3rd July 2014 Alpine Water Management Ltd Dorset House Regent Park Kingston Road Leatherhead KT22 7PL Tel: 0845 319 9 319 www.alpinedamp.co.uk
More informationVisual Property Inspection Report Complies with Australian Standard AS
Visual Property Inspection Report Complies with Australian Standard AS 4349.1-2007 Solicitor/Company Sample Street Mr & Mrs Purchaser Alpha Building Services Pty Ltd Trading As Inspect It >> ABN 47 103
More informationWorld Inspection Network
64725 Acanto Dr Guest house Carriage garage Exterior pool Interior pool Cracked tiles in the Master bath Sauna Page 1 of 16 Moisture damage on the West gym wall outside the Sauna Improper plumbing connection
More informationaccess INCLUSIONS With our Access range of inclusions, you can move in and just enjoy living.
access INCLUSIONS access INCLUSIONS Here at BOLD, we know all about creating utmost liveability on any budget. We believe in providing more for less, packing in space and style at budget friendly prices.
More informationExample Schedule of Condition Report
1 INTERIOR Ground Garage Ceiling Timber members. Members appear to be in a fair and reasonable condition with no signs of any penetration marks noted. Walls Flank wall Brickwork. Part solid construction,
More informationClassic Living INCLUSIONS
INCLUSIONS All construction to National, State and local building codes Brick Veneer construction with iron or tiled roof Engineers soil test and site assessment Contour Survey Engineers slab design Timber
More informationYour home. Dream it. Do it. Dec 17. Affinity Inclusions. wincrest.com.au
Your home Dream it Do it Dec 17 Affinity Inclusions PRE CONSTRUCTION Site contour survey to Australian Height Datum (A.H.D.) level by registered surveyor Preparation of working drawings Complying Development
More informationHOME & LAND $946,000 LOT 155 THE HILLS ESTATE BOX HILL BRONTE 182
LOT 155 THE HILLS ESTATE BOX HILL BRONTE 182 FACADE IS AN ARTIST IMPRESSION ONLY. SOME VARIATION TO WINDOW POSITIONS, MATERIALS USED AND COLOURS MAY BE REQUIRED. PLEASE SEE DRAWINGS AND INCLUSIONS FOR
More informationCHAPTER 1: Tolerances
CONTENTS 1.1 MASONRY 1.2 INTERNAL WALLS AND CEILINGS 1.3 JUNCTIONS 1.4 FLOORS 1.5 DOORS AND WINDOWS 1.6 SKIRTINGS 1.7 FINISHES AND FITTED FURNITURE 1.8 EXTERNAL WORKS 5 Chapter 1 FUNCTIONAL REQUIREMENTS
More informationPowder Coated Merino. Colorbond Dune. Concrete Tiles- Concrete Tiles Slate Grey Finish. Colorbond Paperbark. Concrete Tiles- Concrete Tile -
Colorbond Dune Powder Coated Merino Colorbond Paperbark Concrete Tiles- Concrete Tile - Concrete Tiles Slate Grey Finish Dulux Whisper White PCWF6 Concrete Tiles- Concrete Tile - Dulux Beige Royal Half
More informationPROFESSIONAL ENGINEERING INSPECTIONS, INC. P. O. BOX HOUSTON, TEXAS (713)
PROFESSIONAL ENGINEERING INSPECTIONS, INC. P. O. BOX 271492 HOUSTON, TEXAS 77277 http://www.profengineering.com (713) 664-1264 June 19, 2000 Mr. Samuel Underdog 329 Castle Dr. Houston TX 77018 Dear Mr.
More informationproposed dwelling fjm homes lot 7 wrinklers drive scamander tasmania 7215 concept design jennifer binns Building Areas
fjm homes scamander tasmania 7215 concept design Building Areas first floor 183.44 garage 39.58 ground floor 37.56 deck 37.45 porch 8.95 306.99 jennifer binns BUILDING DESIGN level 1 avery house, 48 cecilia
More informationThe Australian Catalog Content is compiled by Cadsoft Australia, for any further information contact:
The Australian Catalog Content is compiled by Cadsoft Australia, for any further information contact: don@cadsoftaustralia.com.au Phone 0412 410003 Walls Internal Walls Catering for Pre Fab and Stick built
More informationRefusal of a code compliance certificate for a building with a monolithic cladding system: House 9
Refusal of a code compliance certificate for a building with a monolithic cladding system: House 9 1 THE DISPUTE TO BE DETERMINED 1.1 This is a determination of a dispute referred to the Chief Executive
More informationFUNCTIONAL REQUIREMENTS
FUNCTIONAL REQUIREMENTS FUNCTIONAL REQUIREMENTS 7.6 BALCONIES Workmanship i. All workmanship must be within the tolerances defined in Chapter 1 of this manual. ii. All work is to be carried out by a technically
More informationResidential Pre-handover Inspection Report
, trading as Melbourne Property Inspections P/L 356 Collins Street MELBOURNE VIC 3000 Phone: (13)0088-6525 Mobile: 0414-184-686 Email: info@melbournepropertyinspectionscomau ABN: 95 477 052 614 Residential
More informationBuilding Report. Report Commissioned By: The Purchaser. Property Address: Sample Street Tempe. Report Number:11121
Phone: 0417 696 277 Fax: 1300 726 643 Email: restwell67@bigpond.com Web: www.restwellpropertyinspections.com.au Building Consultancy License BC 1219 ABN 121 350 801 A Division of Restwell Building Services
More information1 BASE HOME CONSTRUCTION SPECIFICATIONS: TOWNHOMES 5-13-2015 Note: Specifications noted below may change based on selected options. Verify upgrades from the base specifications with the option sheets and
More informationSNAGGING REPORT. Plot 19 Snag Close Unfinished Avenue Oxford OX90 1AB. for. Mr T & Mrs N Sample
SNAGGING REPORT on Plot 19 Snag Close Unfinished Avenue Oxford OX90 1AB for Mr T & Mrs N Sample Prepared By: Marshalls Chartered Surveyors Rochester House The Grange Farm Eynsham Road Oxford OX2 9NH Tel:
More informationMAJOR DEFECTS BUILDING SURVEY REPORT
MAJOR DEFECTS BUILDING SURVEY REPORT XXXXXX Road Bedminster Bristol BS3 XXX Prepared for Mr XXXXXXX July 2017 T J Maggs MRICS MAGGS AND ALLEN 22 Richmond Hill Clifton Bristol BS8 1BA 0117 973 4049 survey@maggsandallen.co.uk
More informationProperty and Earthquake Assessment
Property and Earthquake Assessment Report by: Vendors: Iain Whyte Kyla Hurley & Philip Tubby Contact Number: 03 3134939 Address: 14 Taiwhenua Street Site was visited for inspection on 11.06.2015 to undertake
More informationCall us now on or visit us on The Total Package
Call us now on 1300 881 689 or visit us on www.abbottbuild.com.au The Total Package The First Glance Contemporary Façade options to suit all styles Steel sectional garage door with two controls Colorbond
More informationessentials INCLUSIONS
essentials INCLUSIONS essentials INCLUSIONS WHAT OTHER BUILDERS CALL UPGRADES WE INCLUDE AS STANDARD Including all the essentials to help make your house a home, we pride ourselves on offering only the
More informationHome Inclusions or Domainehomes.com.au
Home Inclusions 13 64 69 or Domainehomes.com.au Home Inclusions Your new inclusions begin here Home Inclusions Box Hill Lux 18 Narrow Site Inclusions Costs & Basix Slab Up to "H1" Australian standard engineered
More informationStucco Moisture Inspection Report
Website:www.ibgoodinspector.com E-Mail:support@ibgoodinspector.com January 11, 2006 Stucco Moisture Inspection Report Property Address 123 Our Street OurTown, USA 12345 Report Ordered By: Mr. & Mrs. Client
More informationsiting, building and design guidelines April 2017 Newgate, Tarneit Design Guidelines
siting, building and design guidelines April 2017 1 2 INTRODUCTION PROCESS These present a series of measures designed to protect the design integrity of your new house at that will support the value of
More informationAlabama Home Inspections
Cover Page Property Inspection Report 1000 Sample Dr., Sampletown USA Inspection prepared for: Report Sample Inspection Date: 1/21/2010 Time: 400pm Size: Approx. 2,200sf Weather: Cloudy 62 Inspector: Bobby
More informationSUMMARY 1234 Main St.Loudon TN Buyer Name 08/28/2018 9:00AM
SUMMARY 1234 Main St.Loudon TN 37774 Buyer Name 08/28/2018 9:00AM Dusty Jameson TN Home Inspector License #00123, TN WDI License #104158 Inspector Cluseau's Home Inspection Service 865-691-6158 dustyjameson@gmail.com
More informationAwning Certification RISE
Awning Certification Following the 17 reported incidents of awning collapses including the unfortunate accident in Balgowlah in 1998, Department of Local Government recommends all councils to engage building
More informationResidential Handover Inspection Report
, trading as Melbourne Property Inspections P/L 356 Collins Street MELBOURNE VIC 3000 Phone: (13)0088-6525 Mobile: 0414-184-686 Email: info@melbournepropertyinspections.com.au ABN: 95 477 052 614 Residential
More informationThe Pattison. At a Glance m Study m. 17.
The Pattison At a Glance... 321.8m 2 4 + Study 2.0 2 21.566 m Please Note: The floor plan provided is for illustrative purposes only and is not drawn precisely to scale. However, the overall length and
More informationThe Banksia. At a Glance m Study m. 18.
The Banksia At a Glance... 350.1m 2 4 + Study 2.0 20.870 m Please Note: The floor plan provided is for illustrative purposes only and is not drawn precisely to scale. However, the overall length and width
More informationRefusal of a code compliance certificate for a building with a brick veneer and monolithic cladding system at 47 San Bernadino Drive, Henderson
Refusal of a code compliance certificate for a building with a brick veneer and monolithic cladding system at 47 San Bernadino Drive, Henderson 1. The dispute to be determined 1.1 This is a determination
More informationBUILDING INSPECTION. Mar 16, 2015 PROPERTY ADDRESS Killymoon Drive Hope Island, QLD 4212, Australia. 1 of 44
BUILDING INSPECTION Complies with Australian Standard AS 4349.1-2007 Inspection of Buildings Part 1: Pre-Purchase Inspections of Residential Buildings - Appendix C Mar 16, 2015 PROPERTY ADDRESS 1075 Killymoon
More informationSAMPLE REPORT Location:
Stucco Check Inspections, LLC Invasive Stucco Inspection Prepared for: SAMPLE REPORT Location: Sample Houston, TX PHONE: 713.319.5751 EMAIL: Info@stuccocheck.com I. INTRODUCTION 1.1 PURPOSE: Enclosed is
More informationcjd N02 Canon Hill Crescent - Scope Of Refurbishment Works September 2014 External
External 1 Driveway & Forecourt Entry Remove / replace existing iron gate (new modernised iron design). Remove / replace existing brick columns & up stands (new block with plaster finish). Remove / replace
More informationCall us now on or visit us on The Builders Range Package
Call us now on 1300 881 689 or visit us on www.abbottbuild.com.au The Builders Range Package The First Glance Contemporary Façade options to suit all styles Steel sectional garage door with two controls
More informationSCHEDULE OF CONDITION IN RESPECT OF HEN & CHICKENS 143 DEANSGATE BOLTON BL1 1EX ON BEHALF OF PUNCH TAVERNS. Prepared by:
SCHEDULE OF CONDITION IN RESPECT OF HEN & CHICKENS 143 DEANSGATE BOLTON BL1 1EX ON BEHALF OF Prepared by: McBains Cooper Consulting Ltd 120 Old Broad Street London EC2N 1AR Tel No: 020 7786 7900 Fax No:
More informationMAIN & AUX/ASSOCIATED UNIT - Specification
MAIN & AUX/ASSOCIATED UNIT - Specification General Inclusions Contour Survey. All BA council fees, portable long service leave fees and QBCC fees. Construction Insurance. Soil Test. Engineered waffle slab
More informationStorm Damage Assessment Report For: 1234 Example Street., Houston, TX 77002
Storm Damage Assessment Report For: 1234 Example Street., Houston, TX 77002 Prepared For: Miriam Saliba nspection Date: 9/6/2017 Prepared By: Adam Wells TREC License # 21140 105 E Spreading Oaks Ave, Friendswood,
More information1. Supply, delivery, engineering and installation of new storage equipment.
SECTION 10 51 13 - METAL LOCKERS * ALL FIELDS IN [ ] MUST BE EDITED PART 1 - GENERAL 1.1. RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationKOOKABURRA HOMES TWO STOREY HOMES. Standard Inclusions. kookaburrahomes.com.au
KOOKABURRA HOMES Standard Inclusions TWO STOREY HOMES kookaburrahomes.com.au 2 CLASSIC TWO STOREY HOMES STANDARD INCLUSIONS PLANNING AND GENERAL WORKS Fixed price contract 3 month maintenance period Council
More informationSTANDARD SPECIFICATIONS. Page 1
STANAR SPECIFICATIONS Page 1 Page 2 CERTIFICATION AN APPROVALS Complete soil test and engineer s report. Preparation and lodgement of evelopment including drafting of Architectural Plans and all applicable
More informationTHE WISCONSIN TWO STOREY OPULENCE HOW VERY VENTURA
THE WISCONSIN TWO STOREY OPULENCE HOW VERY VENTURA THE WISCONSIN V2 BY VENTURA The Wisconsin V2 is a contemporary two storey family home boasting four bedrooms, three bathrooms and a spacious alfresco.
More informationKOOKABURRA HOMES BRICK HOMES. Standard Inclusions. kookaburrahomes.com.au
KOOKABURRA HOMES Standard Inclusions BRICK HOMES kookaburrahomes.com.au 1 KOOKABURRA HOMES STANDARD INCLUSIONS PLANNING AND GENERAL WORKS Fixed price contract 3 month maintenance period Council application
More informationDeveloped by. 31 Bank Street, West End
ONYX apartments fixtures and Finishes guide. Developed by 31 Bank Street, West End the interiors of ONYX draw inspiration from the local surrounds. the textural darkened joinery and contrasting palette
More informationSECTION BRICKWORK PART I GENERAL
SECTION 04210 BRICKWORK PART I GENERAL 101 Scope General: supply and build the brickwork shown on the drawings or needed to complete the brickwork, including but not limited to the following: Provide all
More informationPink Inspection Services B&R A Division of B&R Constructions Pty. Ltd. ABN
Pink Inspection Services B&R A Division of B&R Constructions Pty. Ltd. ABN 11 001 564 718 Visual Building Inspection Report Commissioned By: XX Purchaser: Property Inspected: XX This Report is provided
More informationDetermination 2013/061
Determination 2013/061 Regarding the issuing of two notices to fix in respect of the code-compliance of a two-coat plaster cladding system to an 11-year-old motel complex at 23/25 Havelock Road, Havelock
More informationSPECIFICATION. for REMEDIAL WORKS. Sparrow Hall Farm Stonea March PE15 0DU
SPECIFICATION for REMEDIAL WORKS to Sparrow Hall Farm Stonea March PE15 0DU Carried out by: PRP UK Limited Catherine House Old Harborough Road Brixworth Northampton NN6 9BH Tel : 01604 889870 Project Number:
More informationSECTION BRICKWORK
SECTION 04210 BRICKWORK THERE ARE NOTES AND CLAUSES IN THE SUSTAINABILITY GUIDE ON THIS TRADE. THIS TRADE SECTION DEPENDS ON COORDINATION BETWEEN THIS SPECIFICATION AND THE FINISHES SCHEDULE AS WELL AS
More informationDetermination 2010/052 Refusal to issue a code compliance certificate for a 6-year old house at 103 Karewa Parade, Papamoa
Determination 2010/052 Refusal to issue a code compliance certificate for a 6-year old house at 103 Karewa Parade, Papamoa 1. The matters to be determined 1.1 This is a determination under Part 3 Subpart
More informationTHE BEST INCLUSIONS ALTI 202
THE BEST INCLUSIONS ALTI 202 WHITE LABEL RANGE WHITE LABEL INCLUSIONS PRELIMINARY WORKS Site Survey, soil test, site inspections as required Building Permit application including applicable fee Full set
More information