Procurement Options for NZ Construction Contracts

Size: px
Start display at page:

Download "Procurement Options for NZ Construction Contracts"

Transcription

1 1 P a g e Tool Box Resource Procurement Options for NZ Construction Contracts A wide variety of contract arrangements have evolved in NZ for use on construction contracts. The following describes the most common types used in the procurement of construction services. Form Description Traditional Tender Commonly used in open tenders the traditional tender is used where there is a requirement to go to the market with a comprehensive set of construction documents including detailed design drawings and schedules of quantities used for pricing purposes. The traditional tender is favoured by Principals who wish to be advised with some certainty of the likely tender process outcome, and by design teams who favour completing the design prior to the involvement of the contractor. In a traditional tender the Principal is usually represented by a Lead Designer or Engineer to the Contract who represents the authority under the contract from whom the contractor takes instruction/direction. Its main disadvantage is that such tendering can attract low entry price bidding which may result from the competitive tendering process where unequal bidders are included on the tender list. Commonly tainted by main contractors for its focus on low entry price ; this can convert into a high exit price outcome if there are major discrepancies in the tender documents. Principals would need to ensure its Design Team is well briefed and that the Lead Designer coordinates the various design inputs giving special attention to design clashes between the design elements/ disciplines. Errors made by the design team become the Principals responsibility under the contract and if design is poorly managed can be the leading reason for cost blow out on a project. Although used in publicly notified tenders it would be wise to pre qualify bidders to ensure the bids received are obtained from sound, appropriate and experienced contractors who can demonstrate capability to carry out and complete the works. If nothing else this provides a level playing field for tenderers. Negotiated Tender The tender aspect of this arrangement relates to the calling of competitive sub trade prices which are used to compile an overall contract price. Generally P&G and Margin costs are negotiated at fair market rates verified by a Professional QS. Negotiated Tender arrangements are preferred by Principals who have determined who their construction partner will be either through previous favourable relationships or because of other drivers such as: Reputation Project Scale Specialist Nature of the Work Proven delivery

2 2 P a g e Tool Box Resource Cost Reimbursable Cost Reimbursable Contracts are used where the scope of work is difficult to ascertain at the time the contract works need to start on site or in the case (i.e. Leaky Buildings) where it is impossible to determine the scope or pricing of particularly (although not exclusively)remedial works. Pure Cost Reimbursable Contracts have no fixed price component except for Margin but hybrid versions do surface from time to time. The basic principle behind Cost Reimbursable Contracts is that you only pay for the work that has to be done. Design Build Design Build contracting transfers design risk to the contractor who thus assumes a single point of accountability in the delivery of the project. Design Build allows contractors to provide buildability input to the design and generally is welcomed by Principals who desire certainty over time/cost/quality outcomes. In any Design Build contract or derivative thereof the design team although employed by the contractor and taking instruction from the contractor has a professional duty of care to provide the Principal with an indemnity that the design has been completed to the same norms as if the Principal engaged and directed the designer in a direct relationship. An example of DB is the City Library Building in Wellington. Novated Design Build Novation is a term used to describe the transfer of design responsibility to the contractor at a point of time during the design development and usually, although not always, prior to construction work commencing on site. Novated Design Build contracts are used where the Principal wishes to appoint the design team and progress the design up to a point that such direct control and input is satisfactory to the Principals wishes but that the preference moving forward is to transfer design development risk to the contractor. Novated Design Build Contracts have to be carefully thought through and documented to ensure common understanding of who carries what design risk. Although some Principals attempt and prefer to have the contractor accept all design risk from day one of design it is in fact unreasonable to expect the contractor to accept risk on matters he has had no input to and scant knowledge of. This in fact becomes fertile ground for contractual disputes and adversarial relationships. It should be expected that the contractor will price the design as it is presented immediately prior to novation on the basis and understanding that the Principal warrants that the design is correct, fit for purpose and compliant with the design brief and mandatory codes. If problems arise as a result of the design prior to novation being incomplete or incorrect then the Principal will carry that risk. If problems arise after the design has been novated to the contractor and such issues relate to design development under the contractors guidance and instruction and relates to design requirements introduced by the contractor then risk rests with the contractor of any consequences as a result of any change. A project example of Novated DB is Westpac Stadium in Wellington.

3 3 P a g e Tool Box Resource Construction Management Construction Management is a term that describes the primary operating focus of a particular construction company. Put simply Construction Management Firms are skilled and experienced construction supervisors, managers and cost administrators first and foremost and they tend to have no direct labour engaged in the physical works. A more traditional construction company is likely to employ its own labour force for undertaking concrete and carpentry trade work as a minimum. A CM firm may or may not own and operate major plant & equipment but those who operate purely to offer CM services tend to submit the provision to the project of such equipment to a contestable process. The main advantage using Construction Management is claimed to be that it provides transparency in the pricing of all the inputs that make up the physical works. Construction Management firms will be seen alongside traditional builders on many tender lists and like the traditional builder take contractor risk on pricing generally. All the major construction companies, FCC, MZ & Hawkins etc are able to offer CM services as an alternative delivery option. It is, not usually, the preference of companies to promote their CM services on a negotiated basis purporting to offer advantages that are not available in a competitive tender. Pure Construction Management Companies attempt to differentiate themselves from Builders offering CM services but in reality the same result can be achieved from both. Management Contracting Management Contracting can be undertaken by suitably competent individuals or organisations that primarily have the ability to provide high level supervision and administration of the contract works. They are differentiated from CM by their origins, being mainly a professional services delivery firm. MC arrangements can be engaged on the basis of a fixed cost for site supervision plus disbursements basis with an additional nominated % fee for profit based on the overall contract value or on a straight % fee based on the overall contract value. This method of contracting is popular where Principals seek to appoint key personnel to manage the risk on the project delivery without the cost of typical main contractors overhead establishment charges and profit being applied to the value of the physical works. All of the work is separated into work packages typically along the lines of traditional trades (although some work packages such as Base Building works will encompass several trades) and each work package contractor enters into a direct contract with the Principal. The Principal basically accepts the risk on subcontractor performance on the project which under other forms of engagement rests with the contractor. The MC s job is to apply professional diligence to the coordination of the disparate subcontractor inputs and lead the construction services delivery team.

4 4 P a g e Tool Box Resource The MC arrangement offers a cultural shift in managing contracts in that subcontractors are no longer subservient in the contractual hierarchy but instead fulfil the role of a specialist contractor expert in their field. An example of Management Contracting on a major project was the construction of Te Papa, where the work was split into separate specialist packages and coordinated and Managed by a CM. Management Contracting is favoured by Principals who are prepared to absorb an additional layer of risk with the expectation that MC will deliver a cost effective solution. Alliancing Alliancing has been introduced to NZ as a more relevant mechanism for sharing risk and gain on a major project where at the outset it is difficult to accurately assess what all the risks to a project are or going to be. Alliancing requires the Principal, the Design Team and the Contractor to abandon their existing operating structure and combine in an alternative vehicle (similar to a JV) whereby all become equal stakeholders in a single purpose project specific venture. Major projects in infrastructure works are most suited to this model and in recent times Transpower, The Department of Corrections and Transit NZ have all undertaken projects using the Alliancing model. Its primary success is in capturing the intellectual capability of the whole team who all act co jointly in the best interest of the project. Challenges along the way are resolved using the best available expertise inherent in such a team framework and project risks are thus not the sole ownership of any one party. Pain and gain are shared. Preferred Contractor Preferred Contractor Appointments are growing in popularity and are used where it is essential to demonstrate a contestable process in the procuring of a contractor but where the level of documentation is not far enough advanced to call for prices. Preferred Contractor tenders are typically called following a pre-qualification process which is narrowed down to a list comprising of who is adjudged to have the best ability to carry out the proposed works. The tender process usually provides for a weighted attributes submission the scoring of which is notified to the contractors in advance. Using weighted attributes, price alone does not become the determining factor in contractor appointment. Attributes are likely to be: Safety Record Quality, availability and experience of Personnel identified for the project Proposed Methodology & Programme Tendered Preliminary & General costs & Margin to be applied Response to the Contract Conditions applying to the project Tendered Fee for providing consultant contractor inputs The successful contractor once appointed then works with the wider project delivery team to provide buildability advice, confirm methods & programme and call prices for sub trade works.

5 5 P a g e Tool Box Resource The goal is to arrive at a final tender sum that the Principal can accept or reject. The Preferred Contractor is essentially a consultant contractor during this pre construction stage and may require a fee for such involvement separate to the contract. Common Practice sees this fee only collected when the contractor is dismissed from further involvement in the project where the contractor has failed to achieve an acceptable price for the works. An example of Preferred Contractor engagements is the WCC Housing Upgrade Project where this procurement process has delivered good results. General Notes: Every Procurement Option has its own positives and negatives but generally speaking each can serve the purpose for which they were intended. The biggest risk to contract failure is design information and the timely delivery of documents to the project team. There are two major recommendations that apply to all of the above equally: 1. Design Deliverables In recent years an initiative was undertaken to create one industry wide benchmark for design documentation. This was achieved by the Construction Industry Council who in conjunction with all project delivery team stakeholders created the industry benchmark for documentation known as The NZ Construction Industry Council Design Documentation Guidelines. This document has become an invaluable aide to designers, contractors and clients alike and defines design stages and the deliverables required of design stages. Design Stages Concept Design Phase Preliminary Design Phase Developed Design Phase Detailed Design Phase Construction design Phase It is recommended that Conditions of Contract and Procurement Options are referenced back to the CIC Guidelines. 2. Documentation Programme The creation and management of a Documentation Programme for a project should be a high priority on a project. It too often is not. The performance of the contract by parties to the contract often becomes focussed on adherence or otherwise to this document (it is a vital project management tool). The Design Manager of the project should be a defined role and the maintenance of the Documentation Programme should be as important as the attention given to the Construction Programme.

6 6 P a g e Tool Box Resource Payment Definitions Type Lump Sum Fluctuating Price (LS) A Lump Sum is agreed based on the Tender Documents but cost increases due to cost escalation are permitted Lump Sum Fixed Price (LSFP) A Lump Sum is agreed based on the Tender Documents and the contractor makes an allowance for cost escalation risk in their price make up. Foreign Exchange Fluctuations are typically a sticking point when agreeing a LSFP and where it is deemed that the contractors FOREX allowance is unacceptable the Principal may elect to retain FOREX risk. Contractors accepting FOREX risk will look to price the cost of obtaining Forward Cover and assess whether they will buy Forward Cover to lock in Exchange Rate pricing or take the commercial risk in house. Guaranteed Maximum Price (GMP) The most commonly misrepresented term of all engagement options. In its purest form is simply an agreed Ceiling Price for the project, one that cannot be exceeded except through Principal requested Variations to the scope of work. Schedule of Rates (SOR) Commonly used on Civils projects where the precise quantity of work cannot be quantified especially where the project contains a number of potential variables. Likely to be seen more on Leaky Building Projects where the actual scope is difficult to assess until the fabric of the building is removed and the extent of the repairs evident. General Note: The above describes the Common Descriptions used as Payment Definitions and it is important to understand the pros and cons that go with each model If you have a project that you need assistance on in defining the most suitable method to go forward rjha limited can assist and navigate you through the options.

Unit 3: The Traditional Procurement Route

Unit 3: The Traditional Procurement Route Unit 3: The Traditional Procurement Route 3.1 Introduction This Unit briefly introduces the main features of the traditional procurement route as a widely used route that provides a good basis for examining

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

ECI: Two-Stage Contracts

ECI: Two-Stage Contracts ECI: Two-Stage Contracts Client and Contractor Considerations Michael Creedon Special Counsel ECI in Infrastructure and Major Projects Summit 2010 Sydney, 17 June 2010 Sessions Outline Introduction /

More information

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods PROCUREMENT 5/21/13 Agenda Common Tendering Systems Procurement Methods 1 Agenda Common Tendering Systems Procurement Methods Common Tendering Systems Competitive / Open-bid: (Qualified) contractors are

More information

CONTRACTS PREPARING THE PRINCIPAL S REQUIREMENTS FOR A CONSTRUCTION PROJECT

CONTRACTS PREPARING THE PRINCIPAL S REQUIREMENTS FOR A CONSTRUCTION PROJECT CONTRACTS PREPARING THE PRINCIPAL S REQUIREMENTS FOR A CONSTRUCTION PROJECT David Nancarrow, Senior Associate Mallesons Stephen Jaques, Melbourne The task of writing down the detailed requirements for

More information

SENIOR PROJECT MANAGER

SENIOR PROJECT MANAGER POSITION Reports To; Direct Reports; Key Relationships; SENIOR PROJECT MANAGER Regional Construction Manager Site Managers, other staff allocated to assigned projects Project Directors, Clients, Consultants,

More information

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical

More information

Planning Construction Procurement. A guide to developing your procurement strategy

Planning Construction Procurement. A guide to developing your procurement strategy Planning Construction Procurement A guide to developing your procurement strategy First published October 2015 Revised October 2016 ISBN: 978-1-98-851707-0 (Online) New Zealand Government Procurement PO

More information

Level 6 NVQ Diploma in Construction Contracting Operations Management

Level 6 NVQ Diploma in Construction Contracting Operations Management Level 6 NVQ Diploma in Construction Contracting Operations Management Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

ALTERNATE FORMS OF PROJECT DELIVERY

ALTERNATE FORMS OF PROJECT DELIVERY ALTERNATE FORMS OF PROJECT DELIVERY 1 INTRODUCTION 1.1 BACKGROUND.1 In the building industry today, conventional methods of project delivery are being challenged by Clients, Consultants and Contractors

More information

ALTERNATIVE CONTRACTING METHODS

ALTERNATIVE CONTRACTING METHODS ALTERNATIVE CONTRACTING METHODS Conventional Design-Bid-Build Design/Build Negotiated General Contractor By Jeff Warner, AIA, LEED AP Principal, ALSC Architects CONVENTIONAL DESIGN-BID-BUILD The most traditional

More information

Member level the optimum standard is given against each activity statement

Member level the optimum standard is given against each activity statement QUANTITY SURVEYING CORE COMPETENCIES 2018 The quantity surveying competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off

More information

Casework Technical Support (Social Welfare - Project Management)

Casework Technical Support (Social Welfare - Project Management) Casework Technical Support (Social Welfare - Project Management) Request for Tenders for Services to MABS NATIONAL DEVELOPMENT The latest date for receipt of tenders is 09 June 2017 Commercial House Westend

More information

Choosing Delivery Method

Choosing Delivery Method Page 1 of 12 Advancing Professional Construction and Program Management Worldwide home contact us site map Search Find-A-CM/PM My Account Sign In Bookstore Career Center Home Choosing Delivery Method Choosing

More information

Estimating specialism core competencies

Estimating specialism core competencies CORE ESTIMATING COMPETENCIES 2015 The estimating competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off to a specific

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015 for Inspecting and Certifying Buildings and Works Building Control Regulations 1997 to 2015 September, 2016 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1

More information

ICES Core Cost Engineering Competencies

ICES Core Cost Engineering Competencies COST ENGINEERING CORE COMPETENCIES 2018 The quantity surveying competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off

More information

Request for Proposals Strategic Planning Facilitation

Request for Proposals Strategic Planning Facilitation Request for Proposals Strategic Planning Facilitation Deadline for Submission: March 6, 2019 1 Section 1: Terms and Conditions 1.1 Issuing Department or Division Department of Operations 1.2 Synopsis or

More information

From Uncertainty to Certainty; How Clients can Improve their Experience of the Construction Process

From Uncertainty to Certainty; How Clients can Improve their Experience of the Construction Process From Uncertainty to Certainty; How Clients can Improve their Experience of the Construction Process www.provelio.com Summary This paper is an independent project manager s critique of two projects. One

More information

Template for ToR for Transaction Advisory Services

Template for ToR for Transaction Advisory Services Template for ToR for Transaction Advisory Services Addendum 1 Prepared by Genesis Analytics 4 December 2013 PPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services

More information

NZS 3916:2013. Conditions of contract for building and civil engineering Design and construct NZS 3916:2013. New Zealand Standard

NZS 3916:2013. Conditions of contract for building and civil engineering Design and construct NZS 3916:2013. New Zealand Standard New Zealand Standard Conditions of contract for building and civil engineering Design and construct Superseding (in part) NZS 3910:2003 NZS 3916:2013 COMMITTEE REPRESENTATION This Standard was prepared

More information

Derlin Construction Limited QUALITY POLICY MANUAL ISO 9001:2008

Derlin Construction Limited QUALITY POLICY MANUAL ISO 9001:2008 Derlin Construction Limited QUALITY POLICY MANUAL ISO 9001:2008 Copy Number Issued to CONTROLLED / UNCONTROLLED Uncontrolled manuals are current at time of issue but will not be updated. Document history.

More information

The Changing Face of Quantity Surveying Practices in Construction Industry

The Changing Face of Quantity Surveying Practices in Construction Industry The Changing Face of Quantity Surveying Practices in Construction Industry YESHWANTH BABU REDDY School of Architecture and Building Deakin University Table of Contents: 1.1 Background... 2 1.2 Introduction...

More information

POSITION DESCRIPTION TEAM LEADER, COMMUNICATIONS, ENGAGEMENT AND COMMUNITY RELATIONS

POSITION DESCRIPTION TEAM LEADER, COMMUNICATIONS, ENGAGEMENT AND COMMUNITY RELATIONS Team Classification Position Objective Communications Western Water Enterprise Agreement Band 7 Level A Level D FIXED TERM ROLE Hands-on leadership role. Coordination, development and delivery of business

More information

1. INTRODUCTION The Mining Qualification Authority (MQA) is a public entity established in terms of section 45 of the Mine Health and Safety Act, Act No. 29 of 1996 (MHSA) and is a Sector Education and

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

Report on Effectiveness of the Construction Manager at Risk Project Delivery Method

Report on Effectiveness of the Construction Manager at Risk Project Delivery Method Report on Effectiveness of the Construction Manager at Risk Project Delivery Method The project management plans described below, establish several elements or criteria for university project staff to

More information

Construction Project Delivery Methods Overview and Comparison. Operations Division

Construction Project Delivery Methods Overview and Comparison. Operations Division Construction Project Delivery Methods Overview and Comparison Operations Division 1 Four Types of Delivery Methods Design/Bid/Build (CM Multi-Prime) CM at Risk Design/Build Lease/Leaseback 2 Considerations

More information

Structural Engineering & Civils Scope of Services

Structural Engineering & Civils Scope of Services Structural Engineering & Civils Scope of Services 1.0 General The scope of services set out below is indicative and are not intended to be exhaustive. This scope of service should be read in conjunction

More information

Conception Design Construction Operation.

Conception Design Construction Operation. 4 Development Process and Procurement 4.1 The development process by which the project moves from the earliest ideas to the final completion of the facilities and their use can be considered as having

More information

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 Background A Task Force established by CIC Comprising Government, Clients, Consultants,

More information

INSTITUTION OF CIVIL ENGINEERS (ICE) SCOTLAND WRITTEN SUBMISSION

INSTITUTION OF CIVIL ENGINEERS (ICE) SCOTLAND WRITTEN SUBMISSION INSTITUTION OF CIVIL ENGINEERS (ICE) SCOTLAND WRITTEN SUBMISSION Introduction and background The Institution of Civil Engineers is a global membership organisation which qualifies civil engineers, exchanges

More information

Framework Information Day

Framework Information Day Framework Information Day 11 th July 2017 http://www.southernconstructionframework.org.uk Agenda Welcome What will we cover today Who and what we are Duties, performance and the mini competition process

More information

SCOPE OF WORK FOR PROFESSIONAL SERVICES: HET POSTHUYS ELECTRICAL UPGRADE

SCOPE OF WORK FOR PROFESSIONAL SERVICES: HET POSTHUYS ELECTRICAL UPGRADE ANNEXURE A T: +27 21 462 4502 F: +27 21 462 4509 E: info@sahra.org.za South African Heritage Resources Agency - Head Office 111 Harrington Street Cape Town P.O. Box 4637 Cape Town 8001 SCOPE OF WORK FOR

More information

Single or multi-sourcing model?

Single or multi-sourcing model? Outsourcing 2007/08 Single and multi-sourcing models Anthony Nagle and Alistair Maughan, Morrison & Foerster www.practicallaw.com/8-380-6567 Once an organisation decides to outsource, one of its biggest

More information

Invitation to Tender. Development Legal Services. August 2015

Invitation to Tender. Development Legal Services. August 2015 Development Legal Services August Contents 1. Important notices... 3 1.1. Confidentiality... 3 1.2. Accuracy of information and liability of SLH... 3 1.3. Canvassing... 4 1.4. Non-collusion... 5 1.5. Copyright...

More information

TECHNICAL EVALUATION

TECHNICAL EVALUATION ANNEX C TECHNICAL EVALUATION 1 Technical Bid Format The technical bid must address clearly and in sufficient depth the points that are subject to the evaluation criteria against which the bid will be evaluated

More information

TasNetworks Policy. Procurement Policy. Version Number 1 June Overview of this Policy. Tasmanian Networks Pty Ltd (ACN )

TasNetworks Policy. Procurement Policy. Version Number 1 June Overview of this Policy. Tasmanian Networks Pty Ltd (ACN ) TasNetworks Policy Procurement Policy Version Number 1 June 2014 Overview of this Policy The purpose of this policy is to establish TasNetworks policy position in relation to procurement of goods and services

More information

APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

APPENDIX A. This is the current form of relationship the Council has with its repairs and voids contractors, and is familiar with its operation.

APPENDIX A. This is the current form of relationship the Council has with its repairs and voids contractors, and is familiar with its operation. APPENDIX A 1. Options Appraisal A. Traditional contracting The key points in a traditional contract are: Can potentially obtain the best prices available in the market at tender stage, although care has

More information

BID REQUEST. External Quality Assessment Services against the Fair Trade Tourism Standard and Certification System March 2018

BID REQUEST. External Quality Assessment Services against the Fair Trade Tourism Standard and Certification System March 2018 BID REQUEST External Quality Assessment Services against the Fair Trade Tourism Standard and Certification System March 2018 Contact: Ana Lemmer. E: ana@fairtrade.travel. T:012 342 2945 1. Bid Overview

More information

A step-by-step guide to writing your fleet policy

A step-by-step guide to writing your fleet policy A step-by-step guide to writing your fleet policy Fleet Policy A step-by-step guide to writing a fleet policy Any organisation with a company vehicle fleet knows that its day-to-day operation raises a

More information

Construction Documents Education Program

Construction Documents Education Program PLANNING AND PRE-DESIGN THE CONSTRUCTION SPECIFICATIONS INSTITUTE 110 South Union Street, Suite 100 Alexandria, VA 22314-3351 www.csinet.org CDEP 1.0.1: 03-1 Copyright Materials This presentation is protected

More information

Forms of Procurement. Traditional Form of Procurement

Forms of Procurement. Traditional Form of Procurement Forms of Procurement Chapter 1 of the Handbook refers to the importance of the form of procurement used by the client in determining the planning and scheduling outputs produced by the s planning team.

More information

Microgeneration Installation Standard: MIS 3007

Microgeneration Installation Standard: MIS 3007 Microgeneration Installation Standard: MIS 3007 REQUIREMENTS FOR MCS CONTRACTORS UNDERTAKING THE DESIGN, SUPPLY, INSTALLATION, SET TO WORK, COMMISSIONING AND HANDOVER OF A HEATING SYSTEM CONTAINING A MICRO-COGENERATION

More information

CAPITAL PROJECTS: PROCUREMENT & TENDERING STRATEGIES

CAPITAL PROJECTS: PROCUREMENT & TENDERING STRATEGIES Client Guide CAPITAL PROJECTS: PROCUREMENT & TENDERING STRATEGIES ABOUT THIS GUIDE: This quick reference guide is intended as an outline of the key procurement and strategies to be considered when undertaking

More information

Audit report Written statement of response to the audit report from the health service CEO

Audit report Written statement of response to the audit report from the health service CEO 1.1 Background From 26 June 2016, hospitals and health services mandated under Schedule 1 and 5 of the Health Services Act 1988 (Vic) must comply with the new Health Purchasing Victoria (HPV) Health Purchasing

More information

Commercial Planning Core Competencies PLANNING CORE COMPETENCIES 2018

Commercial Planning Core Competencies PLANNING CORE COMPETENCIES 2018 PLANNING CORE COMPETENCIES 2018 The competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off to a specific standard,

More information

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA PROGRESSIVE DESIGN-BUILD Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA ADVANTAGES/DISADVANTAGES DESIGN BID BUILD (HARD BID) The traditional project delivery method, which customarily

More information

SEPARATED PROJECT DELIVERY SYSTEMS

SEPARATED PROJECT DELIVERY SYSTEMS SEPARATED PROJECT DELIVERY SYSTEMS Separated (aka Traditional) The traditional delivery method typically involves three sequential project phases: The design phase, which requires the services of a designer

More information

Building Control (Amendment) Regulations MBCA Guidance Document

Building Control (Amendment) Regulations MBCA Guidance Document Building Control (Amendment) Regulations 2014 Contents 1. Introduction 4 2. Legislative Background 5 3. Definitions 6 4. Process 7 5. Documents at tender stage 8 6. Building Control Management System 9

More information

Job Title Quantity Surveyor/Estimator (Capital Programme) Job Grade This post is graded at Grade 9 Reports to Head of Development Direct Reports

Job Title Quantity Surveyor/Estimator (Capital Programme) Job Grade This post is graded at Grade 9 Reports to Head of Development Direct Reports Job Description and Person Specification Job Title Quantity Surveyor/stimator (Capital Programme) Job Grade This post is graded at Grade 9 Reports to Head of Development Direct Reports Other Resources

More information

Prescription of qualifications. ARB Criteria at Parts 1, 2 and 3

Prescription of qualifications. ARB Criteria at Parts 1, 2 and 3 Prescription of qualifications ARB Criteria at Parts 1, 2 and 3 Approved: January 2010 Effective From: 2011/2012 Introduction Under the Architects Act 1997, the Architects Registration Board (ARB) has

More information

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan

More information

NZS 3917:2013. Conditions of contract for building and civil engineering Fixed term NZS 3917:2013. New Zealand Standard

NZS 3917:2013. Conditions of contract for building and civil engineering Fixed term NZS 3917:2013. New Zealand Standard New Zealand Standard Conditions of contract for building and civil engineering Fixed term Superseding (in part) NZS 3910:2003 NZS 3917:2013 COMMITTEE REPRESENTATION This Standard was prepared under the

More information

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell:

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell: CONSTRUCTION MANAGEMENT By GREEN PLANET SERVICES Lesley Padayachee Cell: 084 525 4720 Lesley.gpes@gmail.com 5 th FEBRUARY 2013 CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process

More information

Slide Headings Bullet Points Key Messages Time (mins)

Slide Headings Bullet Points Key Messages Time (mins) Overall Duration hour 5 mins Total Number of Slides 36 Plan for Practical No. Exercises Duration 8 minutes Timing within Presentation Slides 33, 34, and 35 relate to the practical exercise Reference Material

More information

Final May Corporate Governance Guideline

Final May Corporate Governance Guideline Final May 2006 Corporate Governance Guideline Table of Contents 1. INTRODUCTION 1 2. PURPOSES OF GUIDELINE 1 3. APPLICATION AND SCOPE 2 4. DEFINITIONS OF KEY TERMS 2 5. FRAMEWORK USED BY CENTRAL BANK TO

More information

Why Use an Architect?

Why Use an Architect? Architects Can Help Interpret Your Dreams Into A Built Reality Architects provide a service that extends well beyond producing a set of drawings. An architect will listen to your dreams, your aspirations,

More information

Procurement Process: Architects & Professional Engineering Services. Procurement.

Procurement Process: Architects & Professional Engineering Services. Procurement. Procurement Process: Architects & Professional Engineering Services Procurement www.novascotia.ca/tenders Updated: February 2017 Table of Contents Contents INTRODUCTION:... 3 APPLICATION:... 3 SCOPE of

More information

Clarification No

Clarification No Clarification No 9-13.5.15 Invitation to Tender For The HALL FOR CORNWALL Capital Redevelopment Project for Architect-led Design Team Services RIBA Stage 2 7 Project Reference Number: HFC2015 9.1 Which

More information

DESIGN IS GOOD BUSINESS

DESIGN IS GOOD BUSINESS PROJECT DELIVERY: AN INTRODUCTION A profound design process eventually makes the patron, the architect, and every occasional visitor in the building a slightly better human being. JUHANI PALLASMAA The

More information

PROCUREMENT: TIPS AND PITFALLS. Jeremy Taitinger Sean Ward

PROCUREMENT: TIPS AND PITFALLS. Jeremy Taitinger Sean Ward PROCUREMENT: TIPS AND PITFALLS Jeremy Taitinger Sean Ward Procurement Procurement is an important process for municipalities to ensure they obtain competitive bids and proposals representing the best available

More information

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification Structure 4 Centre requirements 6 Support for candidates 6 Links to National Standards / NOS

More information

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification Structure 4 Centre requirements 6 Support for candidates 6 Links to National Standards / NOS

More information

Level 7 NVQ Diploma in Construction Site Management. Qualification Specification

Level 7 NVQ Diploma in Construction Site Management. Qualification Specification Level 7 NVQ Diploma in Construction Site Management Qualification Specification ProQual 2016 Contents Page Introduction 3 Qualification profile 3 Qualification Structure 4 Centre requirements 6 Support

More information

APPENDIX T.2 SACPCMP The South African Council for the Project and Construction Management Professions

APPENDIX T.2 SACPCMP The South African Council for the Project and Construction Management Professions APPENDIX T.2 SACPCMP The South African Council for the Project and Construction Management Professions The South African Council for the Project and Construction Management Professions (SACPCMP) Registration

More information

Invitation to Tender

Invitation to Tender Part 1 Covering letter Invitation to Tender Activity: IDINO-0112 Panel for Research Organization(s) Dear Tenderer, As managing contractor for Innovation for Indonesia s School Children (INOVASI), PT Palladium

More information

AN OWNER S GUIDE TO PROJECT DELIVERY METHODS: CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA

AN OWNER S GUIDE TO PROJECT DELIVERY METHODS: CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA AN OWNER S GUIDE TO PROJECT DELIVERY METHODS: CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA PREFACE This document is an introductory guide for owners who face the choice of delivery methods for their

More information

POLICY DOCUMENT. Contracts Management Policy (Version 3.0) BM>SMC>Board

POLICY DOCUMENT. Contracts Management Policy (Version 3.0) BM>SMC>Board POLICY DOCUMENT Contracts Management Policy 2018 (Version 3.0) BM>SMC>Board Policy Review Schedule Date first Approved: Last Approved by the Board: January 2017 Date of Next Review: January 2018 Policy

More information

SUPPLY CHAIN MANAGEMENT AND PROVIDER PAYMENTS POLICY

SUPPLY CHAIN MANAGEMENT AND PROVIDER PAYMENTS POLICY Introduction With the advent of the Apprenticeship Reforms in 2017, Skills Edge has identified the need to ensure the appropriate breadth and depth of provision to meet the diverse needs of our employers.

More information

5.0 Appendix 1- Capital Costing Guidelines

5.0 Appendix 1- Capital Costing Guidelines 5.0 Appendix 1- Capital Costing Guidelines This section provides additional methodology and defines the terminology expected as part of the submission of the Capital Costing required by Part F Feasibility

More information

GUIDE FOR EVALUATION PROCEDURES FOR EMPLOYMENT OF CONSULTANTS UNDER JAPANESE ODA LOANS

GUIDE FOR EVALUATION PROCEDURES FOR EMPLOYMENT OF CONSULTANTS UNDER JAPANESE ODA LOANS GUIDE FOR EVALUATION PROCEDURES FOR EMPLOYMENT OF CONSULTANTS UNDER JAPANESE ODA LOANS Japan International Cooperation Agency (JICA) December 2006 (Amended December 2009) version 1.0 CONTENTS INTRODUCTION...i

More information

Project phases II. Tendering-constructionoperation

Project phases II. Tendering-constructionoperation Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 04.03.2015 Project phases time Inception initiation Preliminary analysis

More information

CDM 2015 Regulations Frequently Asked Questions (FAQ s) (Last updated January 2016)

CDM 2015 Regulations Frequently Asked Questions (FAQ s) (Last updated January 2016) Document title ICE Health & Safety Expert Panel: CDM 2015 Regulations Frequently Asked Questions (FAQ s) (Last updated January 2016) Introduction The following questions and answers have been put together

More information

COMMERCIAL MANAGEMENT COMPETENCIES Estimating

COMMERCIAL MANAGEMENT COMPETENCIES Estimating Formulation of a cost estimate through to submission of a tender document to a client, including co-ordination with planning, procurement, surveying and management. To exhibit knowledge of all civil engineering

More information

B Ability To be able, without supervision, to perform relevant functions and be able to supervise other less experienced staff

B Ability To be able, without supervision, to perform relevant functions and be able to supervise other less experienced staff COMMERCIAL MANAGEMENT COMPETENCIES 2013 QUANTITY SURVEYING SPECALIST COMPETENCIES 2013 The competencies introduced in 2013 are split into core and specialist competencies. For instance the quantity surveying

More information

Role Profile. Role Title: Head of Compliance. Directorate: Housing Services. Department: Property Services. Team: Compliance.

Role Profile. Role Title: Head of Compliance. Directorate: Housing Services. Department: Property Services. Team: Compliance. Role Profile Role Title: Head of Compliance Directorate: Housing Services Department: Property Services Team: Compliance Role Identifiers: - Career Ladder: Management - Level: Manager Level 3 - Function:

More information

Constructive Expertise. Is Design-Build the right choice. March for you? March i -

Constructive Expertise. Is Design-Build the right choice. March for you? March i - Constructive Expertise Is Design-Build the right choice for you? March 2010 Is Design-Build the right choice for you? Constructive Expertise March 2010 - i - Contents Page 1.00 Introduction: Is Design-Build

More information

CIPS Exam Report for Learner Community:

CIPS Exam Report for Learner Community: CIPS Exam Report for Learner Community: Qualification: Diploma in Procurement and Supply Unit: D2: Business Needs in Procurement and Supply Exam series: November 2016 Question 1 Learning Outcome 1 Q1(a)

More information

Project Delivery Systems

Project Delivery Systems Project Delivery Systems National Society of Professional Engineers Alaska Society of Professional Engineers 2011 Western and Pacific Region Annual Meeting and Conference Jeffrey Callahan April 1, 2011

More information

Commercial QS Specialism (July 17) QUANTITY SURVEYING SPECIALIST COMPETENCIES 2017

Commercial QS Specialism (July 17) QUANTITY SURVEYING SPECIALIST COMPETENCIES 2017 QUANTITY SURVEYING SPECIALIST COMPETENCIES 2017 The quantity surveying competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must

More information

COMMENTS ON GREEN PAPER ON PPP AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS

COMMENTS ON GREEN PAPER ON PPP AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS COMMENTS ON GREEN PAPER ON PPP AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS 1. General The European Dredging Association is pleased to respond to the Commission Green Paper COM(2004)327. EuDA

More information

ARN Procurement Regulations Utility Sectors 2016

ARN Procurement Regulations Utility Sectors 2016 ARN 2016 Procurement Regulations Utility Sectors 2016 Preamble - Special sector companies are obliged to award assignments in accordance with the provisions of the Aanbestedingswet 2012 (Netherlands Procurement

More information

Auditing of Swedish Enterprises and Organisations

Auditing of Swedish Enterprises and Organisations Auditing of Swedish Enterprises and Organisations March 1st 2018 version 2018:1 1 General Application 1.1 These General Terms govern the relationship between the auditor ( the Auditor ) and the client

More information

Invitation For Expression Of Interest For Providing Project Management Consultancy Services At Vidyasagar Industrial Park at Kharagpur In West Bengal

Invitation For Expression Of Interest For Providing Project Management Consultancy Services At Vidyasagar Industrial Park at Kharagpur In West Bengal Invitation For Expression Of Interest For Providing Project Management Consultancy Services At Vidyasagar Industrial Park at Kharagpur In West Bengal INTRODUCTION West Bengal Industrial Development Corporation

More information

Procurement Documents for Progressive Design-Build Projects

Procurement Documents for Progressive Design-Build Projects Procurement Documents for Progressive Design-Build Projects March 22, 2013 John Awezec, P.E., DBIA HDR Engineering, Inc. John Doller, P.E. Carollo Engineers, Inc. Peter Hughes Executive Director WDBC Model

More information

North American Development Bank. Engagement of Consultants

North American Development Bank. Engagement of Consultants North American Development Bank Engagement of Consultants ENGAGEMENT OF CONSULTANTS This Note has been prepared by the North American Development Bank (the Bank) to assist staff and borrowers in the implementation

More information

Committee Meeting. Procurement Processes for Professional Services and Contractors

Committee Meeting. Procurement Processes for Professional Services and Contractors Citizen s i Oversight Committee Meeting Procurement Processes for Professional Services and Contractors March 2, 2011 1 Procurement Process for Professional Services 2 Procurement Process for Professional

More information

ARCHITECTURAL SERVICES TENDER

ARCHITECTURAL SERVICES TENDER ARCHITECTURAL SERVICES TENDER 14 HYBRID OFFICE/INDUSTRIAL UNITS At Plots 11 & 12, Cornwall Business Park (West) For JAD Developments (Redruth) Ltd 1 Introduction 1.1 Project Information Project Title:

More information

BROAD-BASED BLACK ECONOMIC EMPOWERMENT ACT 53 OF 2003

BROAD-BASED BLACK ECONOMIC EMPOWERMENT ACT 53 OF 2003 BROAD-BASED BLACK ECONOMIC EMPOWERMENT ACT 53 OF 2003 DEPARTMENT OF TRADE AND INDUSTRY CODES OF GOOD PRACTICE ON BLACK ECONOMIC EMPOWERMENT Published under General Notice 112 in Government Gazette 29617

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO Time to Build! What to Expect On Your Upcoming and Journey PRESENTED TO Christopher is an award-winning architect with more than 20 years of diversified architectural experience in design of projects from

More information

SH 183 Managed Lanes Project RFQ Q & A MATRIX #2. (June 4, 2013)

SH 183 Managed Lanes Project RFQ Q & A MATRIX #2. (June 4, 2013) SH 183 Managed Lanes Project RFQ Q & A MATRIX #2 (June 4, 2013) No. Current language states: Project experience provided by a parent or sister company of the Lead Engineering Firm, Lead Contractor or Lead

More information

Sample Social Clauses to Encourage Community Benefits from Waste

Sample Social Clauses to Encourage Community Benefits from Waste Sample Social Clauses to Encourage Community Benefits from Waste What are social clauses and community benefits? 1 The UK Sustainable Development Strategy has set the challenge of making the UK an EU leader

More information

Level 6 NVQ Diploma in Construction Site Management (Construction)

Level 6 NVQ Diploma in Construction Site Management (Construction) Level 6 NVQ Diploma in Construction Site Management (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

ARN2016 Procurement Regulations Utility Sectors 2016

ARN2016 Procurement Regulations Utility Sectors 2016 ARN2016 Procurement Regulations Utility Sectors 2016 Preamble - Special sector companies are obliged to award assignments in accordance with the provisions of the Aanbestedingswet 2012 (Netherlands Procurement

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information