TWEED HEADS HOSPITAL REDEVELOPMENT STAGE 3
|
|
- Virgil Casey
- 6 years ago
- Views:
Transcription
1 TWEED HEADS HOSPITAL REDEVELOPMENT STAGE 3 PROJECT MANAGER S REPORT NO. 15 TO PLANNING AND DEVELOPMENT COMMITTEE Prepared by February 2001
2 TWEED HEADS HOSPITAL STAGE 3 REDEVELOPMENT PROJECT MANAGER S REPORT NO. 15 I N D E X 1.0 EXECUTIVE SUMMARY OVERVIEW OF PROJECT LAND & LEGALS TWEED HEADS HOSPITAL AUTHORITIES TWEED HEADS COUNCIL DESIGN PROJECT BRIEF...4 VALUE MANAGEMENT STUDY PROGRESS REPORT CONSTRUCTION EARLY WORKS Bugalwena Early Civil Works MAIN CONTRACT WORKS PROGRAMME MASTER PROGRAMME FINANCIAL PROJECT BUDGET Bugalwena Early Civil Works Main Contract RISK MANAGEMENT OPERATIONAL MATTERS PHOTOGRAPHS APPENDIX A PAGE KIRKLAND S COST REPORT NO APPENDIX B WALTER CONSTRUCTION GROUP LIMITED REPORT NO APPENDIX C TRACEY BRUNSTROM & HAMMOND PTY LTD PROGRAMMING REPORT...17 Tweed Heads Hospital - Stage 3 Redevelopment Page 2
3 1.0 EXECUTIVE SUMMARY 1.1 Overview of Project The two early works contracts have both achieved practical completion. Practical Completion of Bugalwena was granted on 24 January 2001 with three post completion variations (1. a security screen around the reception counter 2. alter existing flagpole to incorporate a crossbar 3. supply and install signs within building). The builder has completed the post completion variations. The Hospital has taken possession of the building. The Early Civil Works reached Practical Completion on 29 January No complaints have arisen from the Tweed Heads District Hospital regarding works on site and the staff has been cooperative with the changes taking place. Construction on the Main Contract is progressing well. Addendum No. 8, which was held back during the tender period, has been priced and Page Kirkland and Walter s have established an agreed price. The Financial Board and NRAHS have approved the price. Walter Construction Group Limited completed the importation of the fill for the building platform and has begun digging service and footing trenches. Sewerage drainage and electrical conduit laying has commenced along with strip and pad footing concrete pours. Zone A & B slabs have been poured and columns and lift wall to Zone A also complete. Level 2 deck in Zone A has just been completed. Overall the project is meeting the milestone dates to achieve the target completion date. The Design team is now focussing on completing the documentation for the alteration works, which has been reviewed and amendments are currently being incorporated. 2.0 LAND & LEGALS 2.1 Tweed Heads Hospital Nil to report. 3.0 AUTHORITIES 3.1 Tweed Heads Council The removal of the tops of the trees from the river bank, at the request of the Carefight and Qld Fire & Rescue Authority to allow a more direct landing path, has taken place. Tweed Heads Hospital - Stage 3 Redevelopment Page 3
4 4.0 DESIGN 4.1 Project Brief Design documentation for the refurbishment works is currently being finalised. The drawings and specification are at 95% completion. The drawings and specification have been reviewed and been sent back to DPWS for coordination and amendment. In conjunction with finalising the refurbishment contract documents, the design team is now responding to requests for information from Walter s. 4.2 Value Management Study No further Value Management Study s are envisaged at this stage. 4.3 Progress Report Refurbishment Documentation is now complete, however a final check will be required prior to going to tender and any minor outstanding amendments incorporated Main Contract DPWS is continuing to RFIs and documentation clarifications North and East Car park Documentation will commence Sam Macri March, 2001 Ph. (02) Fax (02) CONSTRUCTION 5.1 Early Works Bugalwena Status The building has achieved completion with post completion variations completed. Tweed Heads Hospital - Stage 3 Redevelopment Page 4
5 Programme The project finished behind schedule however delays caused by suppliers and other factors outside the control of the builder were considered. The Builder s extensions of time claims (without cost) have been approved up until the date of Practical Completion. Variations Five variation claims have been submitted from Huck s Building Pty Ltd. Numbers 1, 2 & 3 relate to the underground services and the other two are design issues. No.1 Relocate route of services $4, No.2 Footing piers to corner of building to compensate for services $ No.3 Claim for delay for conflicting survey information for above $ No.4 Supply and install stormwater pits to paved area $ No.5 Supply and fit vinyl floor waste to disabled WC $ $6, Three post completion variations have been submitted from Huck s Building Pty Ltd. No.6 Modification of flagpole $ No.7 Installation of security screen to reception counter $2, No.8 Installation of signs $ $3, All of the above variations have been verified by Page Kirkland Partnership as fair and reasonable and have been approved by the NRAHS Early Civil Works Status The Early Works contract has achieved completion including the landscaping and the extra fencing and relocation of windsock pole as requested by Qld Fire and Rescue Authority. Programme The early civil works generally finished in line with the programme. Variations The following variations have been submitted and are approved and exclude GST: No.1 Apply two coat seal to existing sealed surface $ 2, No.2 Installation of Humeceptor pit $10, No.3 Supply & install 70m chainwire fence to helipad $ 2, No.4 Regrading of driveway to TSC requirements $ 1, No.5 Relocation of driveway $ No.6 Relocate windsock pole as requested by Qld Fire $ 1, and Rescue Authority and Careflight. No.7 Supply and install extra 18m of fence and gates $ 1, around helipad as requested by Qld Fire and Rescue Authority and Careflight. Tweed Heads Hospital - Stage 3 Redevelopment Page 5
6 No.8 Additional linemarking to Interim Car Park 2 & $ Walkway as directed by THDH. No.9 Revised landscaping to helipad $22, No.10 Extra temporary fencing for fire egress and access $ to AC plant after hours as requested by THDH. No.11 Reduce 5no. comms conduits to 3no. ($ 1,067.00) Variations Total $41, All above figures are exclusive of GST. 5.2 Main Contract Works Status Works on the Main Contract are progressing well with Walter Construction Limited completing the importation and compaction of fill. Service and footing trenching, service laying, footing/pad/slab concrete pouring and level 2 concrete pouring has begun. The following activities have been completed: Site establishment Initial survey Excavation of subgrade Importation and compaction of fill Zones A & B ground slab Level 2 Zone A slab Programme The Main Contract is progressing well with wet weather causing only minor disruptions. Walter Construction Group have submitted two Extension of Time Claims of two days each which have been evaluated and will be accepted, extending the date for Completion to 10 January Variations The variation in relation to Addendum No. 8 has been agreed at a price of $69,939. It is anticipated that there will be further variation claims submitted in relation to structural steel plus doors and hardware. Refer to Appendix B for Walter Construction Group Limited Report No.3. Tweed Heads Hospital - Stage 3 Redevelopment Page 6
7 6.0 PROGRAMME 6.1 Master Programme TWEED HEADS DISTRICT HOSPITAL REDEVELOPMENT PROGRAMMING REPORT AS AT 27/3/01 The following schedule of dates refers to the status of the major activities of the Master Programme. MILESTONE Master Actual(A)/ DEVELOPMENT APPLICATION Programme Forecast DA Approval 3-Jul-00 6-Sep-00 (A) CONTRACT DOCUMENTATION Complete Documentation of New Clinical Services Building, 1-Sep-00 1-Sep-00 (A) Psych.Unit Complete Documentation of Refurbishment Works 29-Jan Mar-01 TENDER & AWARD Award Early Works (Aboriginal Health, Civil Works) 24-Jul-00 6-Sep-00(A) New Clinical Services Building, Psych.Unit 18-Dec Dec-00 (A) Refurbishment Works 19-Apr-02 From 17-Dec-01 CONSTRUCTION (delay allowance included) Complete Aboriginal Health Building 30-Nov Dec-00 (A) Complete Civil Works/Carpark 15-Mar Jan-01 (A) Contractor s site possession 22-Dec-00 8-Jan-01 (A) Complete New Clinical Services Building & Psych.Unit 23-Feb Feb-02 During the month of March 2001, the following progress was achieved: REFURBISHMENT DOCUMENTATION Comments on the 95% complete documentation have been returned to the Design Team. It was agreed that the 100% documentation will be submitted on 4 April It was also decided to target the completion of the tender & award process by the end of 2001 (current target is 17 December 2001, refer to attached project programme drawing no /B). CONSTRUCTION OF NEW CLINICAL SERVICES BUILDING The following table provides an overview of the time related issues of the contract. ITEM DATE Possession of the site Original Contractual Completion Date Submitted EOT claims (in days) Recommendation for approval of EOT claims (in days) Approved EOT claims (in days) Current Contractual Completion Date 8-Jan-01 4-Jan-01 4 days 4 days 0 days 4-Jan-01 Current Construction Programme A552 REV.A Current Status against planned progress On schedule Progress is measured against the current construction programme A552 REV.A Procurement of trade packages is progressing either on or ahead of programme requirements.. Tweed Heads Hospital - Stage 3 Redevelopment Page 7
8 As at 27 March 2001, construction progress is assessed as being on schedule. The main work face is Level 2 superstructure. Construction progress is summarised on the following table: Area - Activity Progress Status ZONE A FRP LEVEL 2 SLAB 95% -1 d ZONE B Inground Drainage & Services 80% -11 d ZONE B FRP COLS LEVEL 1-LEVEL 2 30% +5 d ZONE C EXCAV & FRP FTG BEAMS & PADS 40% -5 d ZONE C BLOCKWORK TO U/S LEVEL 1 SLAB GRID L/M 80% -2 d ZONE D FRP RAFT SLAB 55% -2 d ZONE D FRP COLS LEVEL 1-LEVEL 2 20% +5 d Attached is a detailed status of the onsite works as at 27/3/01. The critical path at this early phase is passing through the vertical elements and slabs to Level 3. Two EOT claims have been submitted on grounds of inclement weather and TBH have recommended their approval. DECANTING Discussions are held with the Program Director, the Hospital Project Officer and APP in order to finalise the decanting programme. It was agreed however that although the decanting programme will eventually form part of the refurbishment documentation, it will not be included at this stage as it is still evolving. CONCLUSION The status of the project as at 27 March 2001 is assessed as being in accordance with the requirements of the Master Programme. TRACEY BRUNSTROM & HAMMOND PTY LTD Programmer Refer to Appendix C for Tracey Brunstrom & Hammond Pty Ltd Programming Report 7.0 FINANCIAL 7.1 Project Budget Refer to Appendix A for Page Kirkland s Cost Report No. 14. The project is forecast to complete on budget at $32,960, Bugalwena The final Contract Sum for the Bugalwena Contract is $373, excl. GST. Currently, the approved variations total $10, excl. GST as mentioned previously Early Civil Works As the Early Civil Works Contract is now complete, we envisage that there will be no further variation claims submitted. Currently, the approved variations total $42, excl. GST Main Contract The Contract price for the Main Contract is $15,432, excl. GST. To date there has been one variation claim submitted ($69,939.00). Tweed Heads Hospital - Stage 3 Redevelopment Page 8
9 8.0 RISK MANAGEMENT A PROCUREMENT RISK MANAGER S REPORT March 2001 ACTIVITIES UNDERTAKEN BY PRM IN PREVIOUS PERIOD A1 TWEED HEADS HOSPITAL REDEVELOPMENT: STAGE 3 A1.1 Assist with arrangement for and lead C21 Evaluation Meeting. Issued notes of meeting to Max Tonkin, Senior Executive for the Principal A1.2 Complete performance reports for APP, PK, TBH, DPWS/HPI, Huck s & Wills. A1.3 Confirm contract details for Huck s & Wills to Long Service Payments corporation. A1.4 Certify payments to Rice Daubney, Tracey Brunstrom Hammond, APP, Walter Constructions and Wills Excavations. A1.5 Issue advice to APP re format and system for tracking variations to Main Contract. A1.6 Processed Unconditional Undertaking from Walter constructions for Prepayment. A1.7 Review and comment on draft documents for Tower Block & H Wing Conversions. A2 KINGSCLIFF COMMUNITY HEALTH CENTRE A2.1 Complete performance reports for Thomson Adsett. A3 B MURWILLUMBAH HOSPITAL Nil action. EXPECTED ACTIVITIES TO BE UNDERTAKEN BY PRM IN NEXT MONTH B1 TWEED HOSPITAL REDEVELOPMENT : STAGE 3 B1.1 Attend C21 Contract Evaluation Meeting. B1.2 Certify payments, variations and extensions of time to consultants and contractors. B1.3 Provide advice on C21 contractual issues. B2 KINGSCLIFF COMMUNITY HEALTH CENTRE B2.1 Certify payment to consultant. B3 B3.1 Nil. MURWILLUMBAH HOSPITAL REDEVELOPMENT IAN NORRIS Procurement Risk Manager Tweed Heads Hospital - Stage 3 Redevelopment Page 9
10 9.0 OPERATIONAL MATTERS Early Works The Aboriginal and Torres Strait Islander Health Centre is fully operational. A review of the landscaping from the civil works package will be undertaken, in conjunction with the Project Manager, prior to the end of the maintenance period. Main Contract The project team continues to liaise with the construction contractor regarding a variety of issues, including site access and work outside the contractor s area. Some cars on the site (both fleet and personal) were dirtied by a substance from the construction site. This is in the process of being resolved. Refurbishments Some minor planning details have been confirmed with the design team. Further discussions are underway with the Health Service staff regarding the inclusion of the Clinical Training Unit in the design. Commissioning The Commissioning Management Committee has formed and has started to address the wide range of activities required for the smooth transition for the occupation and operation of the new facility Richard Christensen 27/03/01 Project Officer Tweed Heads Hospital - Stage 3 Redevelopment Page 10
11 10.0 PHOTOGRAPHS MAIN CONTRACT: Zone A Ground Slab Prepared for concrete pouring MAIN CONTRACT: Zone B Ground Slab prepared for concrete pouring Tweed Heads Hospital - Stage 3 Redevelopment Page 11
12 MAIN CONTRACT: Zone A columns MAIN CONTRACT: Zone D footings and pads Tweed Heads Hospital - Stage 3 Redevelopment Page 12
13 MAIN CONTRACT: Zone A Stair Wall MAIN CONTRACT: Zone D Slab ready for concrete pouring Tweed Heads Hospital - Stage 3 Redevelopment Page 13
14 MAIN CONTRACT: Zone A Level 2 Deck being formed MAIN CONTRACT: Pouring Zone B columns Tweed Heads Hospital - Stage 3 Redevelopment Page 14
15 APPENDIX A PAGE KIRKLAND S COST REPORT No. 16 Please refer to the file attachment 2318COST.XLS. Tweed Heads Hospital - Stage 3 Redevelopment Page 15
16 APPENDIX B WALTER CONSTRUCTION GROUP LIMITED REPORT NO. 3 Tweed Heads Hospital - Stage 3 Redevelopment Page 16
17 APPENDIX C TRACEY BRUNSTROM & HAMMOND PTY LTD PROGRAMMING REPORT Tweed Heads Hospital - Stage 3 Redevelopment Page 17
GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015
GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations
More informationSIEA LUNGGA POWER STATION RETAINING WALL
SIEA LUNGGA POWER STATION RETAINING WALL 1. Glossary In this scope of work the following abbreviations and definitions apply. Term AS 3000 AS 3600 AS 3700 Boundary Lines AS 4678 Brick Works Contract Contractor
More informationCONTRACT ADDENDUM # 1
date: January 5, 09 project: Bear River Bleachers CONTRACT ADDENDUM # by: Design West Architects subject: Revisions The Work shall be carried out in accordance with the following supplemental instructions
More informationCost Monitoring & EoT
Cost Monitoring & EoT MONITOR YOUR PROGRESS TRACKING CURVES Planned vs Actual How your project performance is monitored by the Engineer Earned Value Analysis (EVA) evaluates project s cost performance
More informationCONCRETE SLABS Job Ready Checklist
CONCRETE SLABS Job Ready Checklist This list is to be reviewed by the Builder/Superintendent to verify that the job site is ready for the Trade Contractor to arrive and begin work. Check box when complete
More informationPlease acknowledge receipt of this Addendum No. 01 on the Bid Schedule submitted with your sealed Bid
Bids for the construction of the Westar Place, PH 2 (), will be received by the City of Westerville, Ohio until the closing date and time of 3:00 p.m. (local time) on Wednesday, December 12, 2018 and will
More informationBreakout Session: CPM Scheduling
Breakout Session: CPM Scheduling The Full Potential of the CPM Scheduling Process Brandon Howell January 29, 2019 LAYTONCONSTRUCTION.COM 2 nd most common cause of disputes in 2016 was poorly drafted or
More informationHobart Industry Briefing for the Redevelopment Royal Hobart Hospital (RRHH) Project Monday 31 st August 2015
Hobart Industry Briefing for the Redevelopment Royal Hobart Hospital (RRHH) Project Monday 31 st August 2015 Agenda Hobart Industry Briefing 1. Introduction 2. Overview of Project Scope 3. Project Timing
More informationPROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404
LDG Consulting Providing Orientation, Direction, and Execution to the Design, Construction, and Real Estate Industries REPORT INFORMATION Date: February 25, 2015 Owner s Rep: Alrich Lynch Electronic Copy:
More informationContract No. EX CS001 - Construction of an Annex to Baptist Lui Ming Choi Secondary School at Yuen Wo Road, Shatin, New Territories.
- Part A: Project Particulars Section Section 1 Construction of New Annex Section 2 Conversion works Contract Period Commencement Date Completion Date Revised Completion Date 730 days 28/12/2015 26/12/2017
More informationIssham Services Ltd. (E) Representative Jenny Mills 6. Richard Egan & Associates
Page 1 of 4 SM 03 PROJECT : STEENSWAY 17 (Phase 3) PROJECT CODE : 1719 RE : MINUTES OF SITE MEETING No 03 DATE : 11.09.2017 Attention Designation Firm Contact Stavros Nicolaou Client Issham Services Ltd.
More informationBuildings Construction Procurement Strategy
Buildings Construction Procurement Strategy Update March 2012 Disclaimer: This presentation is given for information only and cannot be considered as binding Ref. F4E_D_24Y2K9 Agenda 1. Overview of the
More informationAddendum # 4 August 9, 2018
Addendum # 4 August 9, 2018 Richards Consulting & Associates Limited R.R.3 Red Deer, Alberta T4N 5E3 Phone: 403-886-2919 Fax: 403-886-2733 PROJECT: Connector Building Phase 2, Lac La Biche, Alberta THIS
More informationREQUEST FOR SEALED BIDS No
REQUEST FOR SEALED BIDS No. 2018-013 Project: Granger Site Development Phase 2 Issued: December 19, 2018 CONTENTS Section 1. Bid Announcement and General Information Section 2. Bid Specifications and Bid
More informationThe Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings:
GRAVESEND CAMPUS 1.0 LEARNING & SKILLS COUNCIL 1.1 Application In Principle The Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings: Gravesend Campus;
More informationFisher Street Public Car. Park
A Capital Solution in a Stimulus World 24 August 2011 David Niven Fairfield City Council Fairfield City Western Sydney Council Population 179,929 2006 Census Figure id Community Profile Fairfield City
More informationDRINKING WATER QUALITY MANAGEMENT PLAN 2013/2014 REPORT HINCHINBROOK SHIRE COUNCIL SP62
HINCHINBROOK SHIRE COUNCIL SP62 PO BOX 366 INGHAM QLD 4850 Phone: (07) 4776 4600 Email: council@hinchinbrook.qld.gov.au Version No: A Authorised By: Water and Sewerage Current Version Date: 19/11/2014
More informationINSPECTION PLAN. 4. Multiple inspections may be necessary for each element of the Work Stages listed in the template for Targeted Inspections.
PRACTICE NOTE 4 INSPECTION PLAN 1. The primary reference in relation to Inspection Plans is the Code of Practice for Inspecting and Certifying Buildings and Works, current at the time the Inspection Plan
More informationPROGRESS REPORT NAMILANGI SCHOOL PROJECT PHASE III
ZAMBIA OFFICE PROGRESS REPORT NAMILANGI SCHOOL PROJECT PHASE III December,2016 1 P a g e BACKGROUND In 2014, Lions Aid Norway (LAN) in partnership with Lions District 413, Zambia embarked on a project
More informationSUNCHASER VACATION VILLAS FAIRMONT RESORT RECREATION CENTRE FAIRMONT HOT SPRINGS, BC
SUNCHASER VACATION VILLAS FAIRMONT RESORT RECREATION CENTRE FAIRMONT HOT SPRINGS, BC PROGRESS DRAW 1 October 26 th, 2015 LTA Consultants Inc. Professional Quantity Surveyors & Construction Cost Consultants
More informationIronton Russell Bridge Project
Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationArchitectural Design and Build Process. A Client Guide
Architectural Design and Build Process A Client Guide This guide has been prepared to summarise the various stages of a new-build residential design & construction process. It identifies important tasks
More informationDATE: October 6, 2016 FILE: /CV TO: Chair and directors Comox Valley Regional District (Comox Strathcona waste management) board
Staff report DATE: October 6, 2 FILE: 36-2/CV TO: Chair and directors Comox Valley Regional District (Comox Strathcona waste management) board FROM: Debra Oakman, CPA, CMA Chief Administrative Officer
More informationCity of San Pablo Community Development Department Building Inspection Division Plan Review & Permit Requirements
Table of Contents City of San Pablo Community Development Department Building Inspection Division Plan Review & Permit Requirements General Requirements Application & Processing Procedures o Plan Requirements
More informationDRINKING WATER QUALITY MANAGEMENT PLAN 2015/2016 REPORT HINCHINBROOK SHIRE COUNCIL SP62
HINCHINBROOK SHIRE COUNCIL SP62 PO BOX 366 INGHAM QLD 4850 Phone: (07) 4776 4600 Email: council@hinchinbrook.qld.gov.au Version No: A Authorised By: Water and Sewerage Current Version Date: 20/09/2016
More informationNelson Hospital Redevelopment. Proposed Approach to Business Case Development
1. Background 1.1 Introduction Nelson Hospital Redevelopment Proposed Approach to Business Case Development Nelson Marlborough District Health Board (NMDHB) is seeking to prepare a business case for the
More informationProject Budget and Schedule Status Report
Item 58 Transit Program Project Budget and Schedule Status Report Construction Committee October 16, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments
More informationDS3 System Services Project Plan Detailed Design and Implementation Phase
DS3 System Services Project Plan Detailed Design and Implementation Phase Dated: 20/5/2015 Executive Summary The System Services work stream within the DS3 Programme relates to the procurement of services
More informationTENDER BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 2
TENDER 2334-2019 BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 2 This addendum shall be read in conjunction with and considered as an integral part of the Tender Contract 2334-2019. Revisions
More informationIronton Russell Bridge Project
Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015
More informationSecond Avenue Subway
Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St
More informationBRIDGE DISTRICT. City of West Sacramento. Phase 1 Infrastructure Improvement Project. Monthly Status Report
BRIDGE DISTRICT Phase 1 Infrastructure Improvement Project (for work completed thru November 2011) Cover Photo: Joint Utility Trench installation along Fifth Street just north of Bridge Street. Page 1
More informationVia Internet Site Posting- 1 Page + attachments. Addendum No. 3 Tender Call No Closing Date: 12:00 NOON (LOCAL TIME) December 19, 2017
Michael Pacholock Director Purchasing and Materials Management Division City Hall, 18 th Floor, West Tower 100 Queen Street West Toronto, Ontario M5H 2N2 Joanne Kehoe Manager Construction Services December
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationContract No. EX CS001 - Construction of an Annex to Baptist Lui Ming Choi Secondary School at Yuen Wo Road, Shatin, New Territories.
- Part A: Project Particulars Section Section 1 Construction of New Annex Section 2 Conversion works Contract Period Commencement Date Completion Date Revised Completion Date 730 days 28/12/2015 26/12/2017
More informationPROGRESS R E P O R T M A R C H
PROGRESS REPORT MA RCH 2 019 SCOPE The scope of this document covers the all activities and the relevant tests and studies conducted to foresee the progress of The Gardens project, identify the problems
More informationHis Worship Mayor Don Darling and Members of Common Council. SUBJECT: Project Performance Update Safe, Clean Drinking Water Project
COUNCIL REPORT M&C No. 2016-214 Report Date August 12, 2016 Meeting Date August 22, 2016 Service Area Saint John Water His Worship Mayor Don Darling and Members of Common Council SUBJECT: Project Performance
More informationInclude this form in your application submittal.
PRE-APPLICATION FORM PLEASE NOTE: A pre-application conference is required prior to submittal on all applications. The purpose of the pre-application conference is to determine if the application is ready
More informationMARK TURTON MCIOB, MAPM
MARK TURTON MCIOB, MAPM Southside (6 th Floor) 105 Victoria Street Westminster London SW1E 6QT 0870 9917749 info@somersetconsult.com BRIEF SUMMARY Mark is a Construction Industry /Contract Manager with
More informationAppendix C. Construction Programme
Appendix C Construction Programme Activity ID Activity Name Orig Dur Planned Start Planned Finish Revision 2 827d 14-Oct-13 31-Jul-16 0d Preliminaries 827d 14-Oct-13 31-Jul-16 0d Total Float Contract Key
More informationGreater New Haven Water Pollution Control Authority. New Haven, Connecticut
Greater New Haven Water Pollution Control Authority New Haven, Connecticut Plans and Specifications for the Construction of CWF 2016-07 RE-BID - CSO Reduction Utilizing Green Infrastructure - West River
More informationINSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST
Village of Vernon Hills Community Development Department - Building Division 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http://www.vernonhills.org INSPECTION TIMING
More informationDRINKING WATER QUALITY MANAGEMENT PLAN 2016/2017 REPORT HINCHINBROOK SHIRE COUNCIL SP62
HINCHINBROOK SHIRE COUNCIL SP62 PO BOX 366 INGHAM QLD 4850 Phone: (07) 4776 4600 Email: council@hinchinbrook.qld.gov.au Version No: A Authorised By: Water and Sewerage Current Version Date: 01/12/2017
More informationNAPA SANITATION DISTRICT
NAPA SANITATION DISTRICT PSOMAS COMPANY - TASK ORDER No. 25 HEADWORKS EQUIPMENT REHAB-REPLACE PROJECT (CIP 17726) Date: July 25, 2018 Issued under Professional Services Agreement dated ---------, 2018.
More informationThe Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings:
GRAVESENDCAMPUS 1.0 LEARNING & SKILLS COUNCIL 1.1 Application In Principle The Application in-principle (AIP) was approved by the LSC on the 9 th May 2007 for the following buildings: Gravesend Campus;
More informationDetailed Estimating-Introduction. Dr. Al-Hammad
Detailed Estimating-Introduction By Dr. Al-Hammad Outline Introduction Successful Construction Estimating The Detailed Estimating Procedure The stretch - out - Length concept (SOL) Site Work and Excavation
More informationWetar Expansion Update September 2015
For ASX Market Release: 15 September 2015 Wetar Expansion Update September 2015 HIGHLIGHTS Mining and earthworks associated with the 25,000 tonne per annum copper cathode expansion project are well advanced
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Design & Construction REQUEST FOR PROPOSAL Third Party Testing and Special Inspections Parking Lots and Ramps Arts Campus Parking Reconfiguration Phase 2 Project #0674501 Addendum
More informationProject Budget and Schedule Status Report
Item 52 Transit Program Project Budget and Schedule Status Report Construction Committee June 19, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments 3 Crenshaw/LAX
More informationGainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703)
Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA 20155 Phone (703) 754-6750 Work Request # UNDERGROUND DISTRIBUTION FACILITIES AGREEMENT (FOR COMMERCIAL CUSTOMER) Developer/Builder/Owner
More informationIIM RAIPUR. Development of Phase I Campus including building for IIM Raipur at Naya Raipur
MONTHLY PROGRESS REPORT IIM RAIPUR Development of Phase I Campus including building for IIM Raipur at Naya Raipur (PMC by Naya Raipur Development Authority) MONTHLY PROGRESS REPORT AS ON 31 st MAY -2017
More informationEvanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201
Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October
More informationCherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12
SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and
More informationBUREAU Joe Iuviene, AIA January 20, 2017
architectural BUREAU Joe Iuviene, AIA January 20, 2017 Alterations & Additions NEW TOWN HALL for TOWN OF AUSTERLITZ 816 State Route 203, Spencertown, New York 12165 ADDENDUM NO. 1 This addendum amends
More informationSPECIFICATION FOR PRECAST/ COMPOSITE CONCRETE FLOORS/ ROOF DECKS SECTION E60
SPECIFICATION FOR SECTION E60 A 2007-09-26 S.W. Revision Date Issue Authorised By Approved for Issue SW Date 24.09.07 clarkebond Page 1 of 6 To be read with Preliminaries/ General Conditions. GENERAL 10
More informationSMMUSD LINCOLN MIDDLE SCHOOL ATHLETIC FIELD PROJECT
ADDENDUM 01 SMMUSD LINCOLN MIDDLE SCHOOL ATHLETIC FIELD PROJECT 06/08/2017 DSA NO. A03-117787/File No.19-96 Prepared By DLR Group Project No. 75-07256-24 SECTION 00 91 00 GENERAL ADDENDUM 01 1.01 The following
More informationCity of Westerville Guide to Commercial Inspections
City of Westerville Guide to Commercial Inspections FOOTINGS - After the excavation, with the form work and any required reinforcing steel in place. All footings shall have loose soil removed, reinforcing
More informationCIC Guidelines Detailed Design
Version 1.0 / August 2016 Stage 5 of 8 Approval: Of previous stage, design documentation, updated programme and cost plan. List matters from previous stage to be addressed in current stage. Documentation:
More informationChristopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule
Christopher Glinski Construction Management AE Senior Thesis Appendix B Project Summary /Detailed Schedule 74 Task Name ation 1 Project 546 days Mon 5/3/04 Mon 6/26/06 29 Design 243 days Mon 5/3/04 Fri
More informationStatus of ITER Buildings construction and next procurement steps
Status of ITER Buildings construction and next procurement steps Laurent Schmieder Site, Buildings and Power Supplies Project Manager IBF/15 DIRECTORY IBF/15 March 25-27 March 25-27, 2015 Palais du Pharo
More informationAPPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES
Appendix A RFP No. 894-2014 Page 1 of 1 Template Version: SrC120131129 - Consulting Services RFP APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Revision: 2014-09-22 DEFINITION OF
More informationa) Seek clarification from the Department for Transport in respect of future core funding for the work of the Strategic Transport Forum.
Strategic Transport Forum 15 th December 2017 englandseconomicheartland@b uckscc.gov.uk Agenda Item 6: Draft Business Plan Recommendation: It is recommended that the Forum: a) Seek clarification from the
More informationDesign Guidelines. pegasus-town.co.nz
Design Guidelines pegasus-town.co.nz Welcome to Pegasus Town These guidelines have been developed to help make your home-building process as easy as possible. The contents provide you, or your designer
More informationLandscaping and Fencing
Landscaping and Fencing Fences, driveways, paving, retaining walls, landscaping & other garden features To be read in conjunction with General Requirements: A guide to building on properties containing
More informationProject Budget and Schedule Status
Item Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee February 20, 2014 & Schedule Performance Summary Chart Slide # Project
More informationWorking Together to Deliver High Levels of Construction Quality
Working Together to Deliver High Levels of Construction Quality Construction Quality Reviews by NHBC NHBC has developed a programme focusing on construction quality that will help the house building industry
More informationCARVER ELEMENTARY SCHOOL PROJECT January 2017 Monthly Status Report
CARVER ELEMENTARY SCHOOL PROJECT January 2017 Monthly Status Report Project: Current Phase: Construction Construction Type: New Construction Construction Start Date: 03Oct2016 Building Size (New): 112,350
More informationCIVIC CENTER NORTH PUMP STATION AND JOHN DUCKETT PUMP STATION STANDBY GENERATOR REPLACEMENT PROJECT
FOR BIDDING ONLY MARIN COUNTY, CALIFORNIA CIVIC CENTER NORTH PUMP STATION AND JOHN DUCKETT PUMP STATION STANDBY GENERATOR REPLACEMENT PROJECT JOB NO. 10300-11/-09 VOLUME 4: DRAWINGS NOVEMBER 2011 DISTRICT
More informationInitial Analysis, Planning and Calculation of Vertical Delivery in High-rise Building Construction
P P Periodica Polytechnica Architecture 48(2), pp. 87-92, 2017 https://doi.org/10.3311/ppar.10833 Creative Commons Attribution b Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise
More informationTown of Kingsville. Building Department
Town of Kingsville Building Department GUIDE TO ACCESSORY STRUCTURES AND DECKS FOR BUILDING PERMITS www.kingsville.ca 2017 Disclaimer: The fees and by-law information compiled within this guide are for
More informationSchedule Guidance Document
Schedule Guidance Document Version: 1.2 Effective Date: August 20, 2013 Contents 1. Purpose... 1 2. Applicability and Basic Requirements... 2 3. Baseline Schedule... 3 3.1. General... 3 3.2. Schedule Work
More information(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet
(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet Project Name: UM Project # Design Professional: Meeting Place: Meeting Time:
More informationSANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016
FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 1 ACTIVE PROJECTS Santa Ana College Central Plant, Infrastructure and Mechanical Upgrades 2 COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements
More informationDIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012
2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include
More information1. CLARIFICATIONS FOLLOWING SITE INSPECTION HELD ON 13 th February 2018
1. CLARIFICATIONS FOLLOWING SITE INSPECTION HELD ON 13 th February 2018 1.1 Restoration works of the present building fronting street shall be in keeping with the approved Restoration Method Statement
More informationAddendum! Project No: HFX A0 Client Project No: MISC Project: MacAulay Sports Field Project Date: March 23, 2015 Addendum No: 2
Addendum! Project No: HFX-00222868-A0 Client Project No: MISC-14-06 Project: MacAulay Sports Field Project Date: March 23, 2015 Addendum No: 2 The following information supplements and/or supersedes the
More informationUTILITY COORDINATION FOR CAPITAL IMPROVEMENTS PROJECTS
DIVISION V SECTION 5900 UTILITY COORDINATION FOR CAPITAL IMPROVEMENTS PROJECTS Best Management Practices (March 17, 2010) APWA 5900 March 2010 DIVISION V DESIGN CRITERIA 5900 Utility Coordination for Capital
More informationNEW MNIR DESIGN INTERNATIONAL OPEN DESIGN COMPETITION COST PLAN ANALYSIS MNIR REDEVELOPMENT ELEMENTAL COST PLAN
NEW MNIR DESIGN INTERNATIONAL OPEN DESIGN COMPETITION COST PLAN ANALYSIS MNIR REDEVELOPMENT ELEMENTAL COST PLAN 1 SUBSTRUCTURE 4 278 780,63 Substructure 1 Item 2 SUPERSTRUCTURE 26 039 623,47 2A Frame 1
More informationStandard Provisions for Multiple Dwelling Developments. Stage 1 Project Plan
Standard Provisions for Multiple Dwelling Developments Stage 1 Project Plan Version 1.1 8 June 2012 Contents Standard Provisions for Multiple Dwelling Developments Stage 1 Contents... 2 Revision History...
More informationULDA Decision Notice
ULDA Decision Notice Site Address Bowen St, Roma Real property description Lot 143 AP15786 Type of approval UDA development approval subject to conditions Aspects of development Reconfiguring a Lot with
More informationPrestage Farms Subcontractor and Vendor Outreach Fair
Prestage Farms Subcontractor and Vendor Outreach Fair Architecture Interiors Engineering Construction December 13, 2016 www.epsteinglobal.com Agenda Epstein s Role Project Description Project Location
More informationIronton Russell Bridge Project
Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place
More informationWayleave Application for Non-Queensland Rail Service
Wayleave Application for Non-Queensland Rail Service This form may only be used for applications lodged in the 2018-19 financial year Form Instructions This form contains important information on how to
More informationIronton Russell Bridge Project
Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationTENDER WELLCOX ACCESS ROAD ADDENDUM 1
TENDER 2336-2019 WELLCOX ACCESS ROAD ADDENDUM 1 This addendum shall be read in conjunction with and considered as an integral part of the Tender Contract 2336-2019. Revisions supersede the information
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More information1. Meeting minutes from the pre-bid conference are attached for inclusion in the Bid Documents.
PROJECT NO. 13-130.03 Splash Pad at Lakeside Park ADDENDUM #4 `` Splash Pad at Lakeside Park Pell City, AL WBA No. 13-130.03 OWNER: City of Pell City 1905 First Ave. North Pell City, AL 35125 ph. (205)338-2244
More informationCONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY
CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition
More informationManagement Plan: Hazardous Materials Removal & Demolition
Management Plan: Hazardous Materials Removal & Demolition Kingswood School (Upper Site), Corby 1.0 Introduction 1.1 Background Lambert Smith Hampton has been instructed by Northamptonshire County Council
More informationCLIENTS GUIDE ARCHITECTURE PROCESS. Architecture Urban design Interior Planning. FM ARCHITECTURE
CLIENTS GUIDE ARCHITECTURE PROCESS FM ARCHITECTURE www.fmarchitecture.com.au Architecture Urban design Interior Planning Undertaking a building project can be a daunting task, especially if you haven t
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationCONCRETE FOOTINGS AND WALLS Job Ready Checklist
CONCRETE FOOTINGS AND WALLS Job Ready Checklist This list is to be reviewed by the Builder/Superintendent to verify that the job site is ready for the Trade Contractor to arrive and begin work. Check box
More informationTHE KEY ELEMENTS OF QUANTITY SURVEYING WORK
THE KEY ELEMENTS OF QUANTITY SURVEYING WORK A Presentation to the Institution of Surveyors of Uganda by Tom Joseph Mukasa BSc, MSc, MRICS, ICIOB, AISU 2016 1. The following are key elements (divided into
More informationNewark & Sherwood Local Development Framework Local Development Scheme
Newark & Sherwood Local Development Framework Local Development Scheme SEPTEMBER 2018 CONTENTS 1 Introduction 2 LDF Proposed Documents 3 Delivery & Review Appendix Appendix A Local Development Scheme Timetable
More informationPort KC RFP NORTHLAND PARK BUILDING V
Port KC RFP NORTHLAND PARK BUILDING V 1. The RFP refers to landscaping plans. However, it does not appear that the landscaping plans were issued with the rest of the RFP. Will these be issued with an addendum?
More informationTENDER BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 1
TENDER 2334-2019 BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 1 This addendum shall be read in conjunction with and considered as an integral part of the Tender Contract 2334-2019. Revisions
More informationTechnical Assignment 2
Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive
More informationADDENDUM #1 TO THE SPECIFICATION FOR THE CONSTRUCTION OF THE 115KV STONEBREAK RD. TRANSITION STATION THE TOWN OF MALTA AND A PORTION OF THE 115KV
ADDENDUM #1 TO THE SPECIFICATION FOR THE CONSTRUCTION OF THE 115KV STONEBREAK RD. TRANSITION STATION IN THE TOWN OF MALTA AND A PORTION OF THE 115KV LUTHER FOREST STATION IN THE TOWN OF STILLWATER SARATOGA
More informationStrategy for Future Wheel-Trans Taxi Service Contracts
For Action Strategy for Future Wheel-Trans Taxi Service Contracts Date: January 24, 2019 To: TTC Board From: Chief Service Officer Summary With over 44,000 active customers, Wheel-Trans is the third largest
More information