1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

Size: px
Start display at page:

Download "1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities."

Transcription

1 SECTION SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Project information. 2. Work covered by Contract Documents. 3. Phased construction. 4. Work by Owner. 5. Work under separate contracts. 6. Future work. 7. Purchase contracts 8. Salvage requirements. 9. Owner-furnished products. 10. Contractor-furnished, Owner-installed products. 11. Access to site. 12. Coordination with occupants. 13. Work restrictions. 14. Specification and drawing conventions. 15. Miscellaneous provisions. B. Related Requirements: 1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities. 1.3 PROJECT INFORMATION A. Project Identification: <Insert Project identifier such as Project name and number>. 1. Project Location: <Insert Project location (street address, city, and state)>. B. Owner: <Insert name and address of Owner>. 1. Owner's Representative: <Insert name and contact information for Owner's representative>. AE Project #: <%Project Number%> Summary

2 C. Architect: <Insert name and contact information for Architect>. D. Architect's Consultants: The Architect has retained the following design professionals who have prepared designated portions of the Contract Documents: 1. <Insert title of design discipline>: <Insert name and contact information for consultant>. E. Other Owner Consultants: The Owner has retained the following design professionals who have prepared designated portions of the Contract Documents: 1. <Insert title of design discipline>: <Insert name and contact information for consultant>. <Insert title of design discipline> has prepared the following portions of the Contract Documents: a. <Insert description of scope of service for other Owner consultant>. F. Contractor: <Insert name and contact information for Contractor> has been engaged as Contractor for this Project. G. Construction Manager: <Insert name and contact information for Construction Manager>. 1. Construction Manager has been engaged for this Project to serve as an advisor to Owner and to provide assistance in administering the Contract for Construction between Owner and[ each] Contractor, according to a separate contract between Owner and Construction Manager. 2. Construction Manager for this Project is Project's constructor. The terms "Construction Manager" and "Contractor" are synonymous. H. Design-Builder: <Insert name and contact information for Design-Builder>. 1. Design-Builder has been engaged for this Project to provide architectural and engineering services and to serve as Project's constructor. The terms "Design-Builder" and "Contractor" are synonymous. I. Project Web Site: A project Web site administered by [Architect] [Owner] [Construction Manager] [Contractor] will be used for purposes of managing communication and documents during the construction stage. 1. See Section "Project Management and Coordination." for requirements for [establishing] [administering] [and] using the Project Web site. 1.4 WORK COVERED BY CONTRACT DOCUMENTS A. The Work of Project is defined by the Contract Documents and consists of the following: AE Project #: <%Project Number%> Summary

3 1. <Insert a brief description of Project indicating the size, code classification for occupancy and construction type, and general description of major building assemblies>. B. Type of Contract: 1. Project will be constructed under a single prime contract. 2. Project will be constructed under coordinated, concurrent multiple contracts. a. <Insert name of the Contract>. 1.5 PHASED CONSTRUCTION A. The Work shall be conducted in <Insert number> phases, with each phase substantially complete as indicated: 1. Phase <Insert designation>: <Briefly describe work of this phase> Work of this phase shall commence [within <Insert number of days> after the Notice to Proceed] [by <Insert date>] and be substantially complete and ready for occupancy [within <Insert number of days>] [after the Notice to Proceed] [after commencement of construction of this phase] [by <Insert date>]. 2. Phase <Insert designation>: The remaining Work shall be substantially complete and ready for occupancy at time of Substantial Completion for the Work. B. Before commencing Work of each phase, submit an updated copy of Contractor's construction schedule showing the sequence, commencement and completion dates[, and move-out and - in dates of Owner's personnel] for all phases of the Work. 1.6 WORK BY OWNER A. General: Cooperate fully with Owner so work may be carried out smoothly, without interfering with or delaying work under this Contract or work by Owner. Coordinate the Work of this Contract with work performed by Owner. B. Preceding Work: Owner will perform the following construction operations at Project site. Those operations are scheduled to be substantially complete before work under this Contract begins. 1. <Insert a brief description of work performed by Owner>. C. Concurrent Work: Owner will perform the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract. 1. <Insert a brief description of work performed by Owner>. AE Project #: <%Project Number%> Summary

4 D. Subsequent Work: Owner will perform the following additional work at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract. 1. <Insert a brief description of work performed by Owner>. 1.7 WORK UNDER SEPARATE CONTRACTS A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract or other contracts. Coordinate the Work of this Contract with work performed under separate contracts. B. Preceding Work: Owner [has awarded] [will award] separate contract(s) for the following construction operations at Project site. Those operations are scheduled to be substantially complete before work under this Contract begins. 1. <Insert name of the Contract>: To <Insert name of separate Contractor> [to] [for] <Insert a brief description of work performed under separate contract>. C. Concurrent Work: Owner [has awarded] [will award] [and will assign to Contractor] separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract. 1. <Insert name of the Contract>: To <Insert name of separate Contractor> [to] [for] <Insert a brief description of work performed under separate contract>. D. Subsequent Work: Owner [has awarded] [will award] separate contract(s) for the following additional work to be performed at site following Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract. 1. <Insert name of the Contract>: To <Insert name of separate Contractor> [to] [for] <Insert a brief description of work performed under separate contract>. 1.8 FUTURE WORK A. The Contract Documents include requirements that will allow Owner to carry out future work following completion of this Project; provide for the following future work: 1. <Insert description of future work requiring consideration during construction of the Work of this Contract>. 1.9 PURCHASE CONTRACTS A. General: Owner has negotiated purchase contracts with suppliers of material and equipment to be incorporated into the Work. Owner will assign these purchase contracts to Contractor. AE Project #: <%Project Number%> Summary

5 Include costs for purchasing, receiving, handling, storage if required, and installation of material and equipment in the Contract Sum, unless otherwise indicated. 1. Contractor's responsibilities are same as if Contractor had negotiated purchase contracts, including responsibility to renegotiate purchase and to execute final purchasing agreements. B. Purchase Contracts Information: 1. <Insert product name>: See Section <Insert Section number> "<Insert Section title>." a. Purchase Contract Firm and Representative: <Insert name and contact information for purchase contract firm and representative.> b. Purchase Contract Scope: [Furnishing material] [Material and installation labor] <Insert description of contract>. c. Purchase Status: [Price negotiated by Owner, to be incorporated in the Contract Sum by Contractor; see Section "Allowances" for cash allowance for purchase contract] [Price negotiated and incorporated in the Contract Sum by Contractor] [Product reserved by Owner] [Order placed and deposit paid by Owner] [Order to be placed by Contractor] <Insert description of status of purchase contract>. d. Quantity: <Insert quantity ordered>. e. Other Requirements: <Insert special requirements> SALVAGE REQUIREMENT A. Unless otherwise indicated, demolition waste becomes property of Contractor. B. Unless otherwise indicated, all equipment that must be removed due to interference with work of this contract remains the property of the Owner, and may be salvaged at the Owner's discretion. C. On LEED-certified projects, additional requirements may apply. Consult other sections for specific LEED procedures. D. Owner wishes to salvage, refurbish, and/or reuse the following materials and store and/or reinstall as itemized below. Drawings also may indicate items to be salvaged and stored on Owner's premises and the location of storage. Coordinate all salvage activities with FP&C Project Manager. [Note that salvage disposition may also be treated as a construction alternate: in these situations include salvage information on GMP Exhibit A-2, APPROVED AND ACCEPTED ALTERNATES.] Item No. : Handling [Contractor shall remove and relocate to Owner s designated location] [Contractor shall remove and stockpile on the project site] [Contractor shall refurbish and AE Project #: <%Project Number%> Summary

6 reinstall as indicated in the Project documents] [Contractor shall reinstall as indicated in the Project documents]: Salvage Value (assigned by [Contractor] [Owner]): Repeat as necessary. E. Materials and/or items scheduled above for relocation and which are damaged during dismantling or reassembly operations shall be repaired and restored to good operative condition. The Contractor may, at his discretion and upon the approval of the Owner, substitute new materials and/or items of like design and quality in lieu of materials and/or items to be relocated 1.11 OWNER-FURNISHED PRODUCTS A. Owner will furnish products indicated. The Work includes receiving, unloading, handling, storing, protecting, and installing Owner-furnished products[ and making building services connections]. B. Owner-Furnished Products: 1. <Insert description, in separate subparagraphs, for each Owner-furnished product> CONTRACTOR-FURNISHED, OWNER-INSTALLED PRODUCTS A. Contractor shall furnish products indicated. The Work includes unloading, handling, storing, and protecting Contractor-furnished products as directed and turning them over to Owner at Project closeout. B. Contractor-Furnished, Owner-Installed Products: 1. <Insert description, in separate subparagraphs, for each Contractor-furnished, Ownerinstalled product> ACCESS TO SITE A. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project. B. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section. C. Use of Site: Limit use of Project site to [work in areas] [areas within the Contract limits] indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated. AE Project #: <%Project Number%> Summary

7 1. Limits: Confine construction operations to <Insert description of areas where work is permitted>. 2. Limits: Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet (12.2 m) beyond building perimeter; 10 feet (3 m) beyond surface walkways, patios, surface parking, and utilities less than 12 inches (300 mm) in diameter; 15 feet (4.5 m) beyond primary roadway curbs and main utility branch trenches; and 25 feet (7.6 m) beyond constructed areas with permeable surfaces (such as pervious paving areas, stormwater detention facilities, and playing fields) that require additional staging areas in order to limit compaction in the constructed area. 3. Driveways, Walkways and Entrances: Keep driveways[ parking garage,] [ loading areas,] and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. a. Schedule deliveries to minimize use of driveways and entrances by construction operations. b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site. D. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations COORDINATION WITH OCCUPANTS A. Full Owner Occupancy: Owner will occupy site and [existing] [adjacent] building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated. 1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction. 2. Notify Owner not less than [72] <Insert number> hours in advance of activities that will affect Owner's operations. B. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations. Maintain existing exits unless otherwise indicated. 1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction. 2. Provide not less than [72] <Insert number> hours' notice to Owner of activities that will affect Owner's operations. AE Project #: <%Project Number%> Summary

8 C. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work. 1. Architect will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work. 2. Obtain a Certificate of Occupancy from authorities having jurisdiction before limited Owner occupancy. 3. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems serving occupied portions of Work. 4. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work WORK RESTRICTIONS A. Work Restrictions, General: Comply with restrictions on construction operations. 1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction. B. On-Site Work Hours: Limit work in the existing building to normal business working hours of <Insert time> a.m. to <Insert time> p.m., Monday through Friday, unless otherwise indicated. 1. Weekend Hours: <Insert restrictions on times permitted for weekend work>. 2. Early Morning Hours: <Insert restrictions or references to regulations by authorities having jurisdiction for restrictions on noisy work>. 3. Hours for Utility Shutdowns: <Insert Owner's restrictions>. 4. Hours for [Core Drilling] <Insert noisy activity>: <Insert Owner's restrictions>. C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated: 1. Notify [Architect] [Construction Manager] [Owner] not less than [two] <Insert number> days in advance of proposed utility interruptions. 2. Obtain [Architect's] [Construction Manager's] [Owner's] written permission before proceeding with utility interruptions. D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner. 1. Notify [Architect] [Construction Manager] [Owner] not less than [two] <Insert number> days in advance of proposed disruptive operations. AE Project #: <%Project Number%> Summary

9 2. Obtain [Architect's] [Construction Manager's] [Owner's] written permission before proceeding with disruptive operations. E. Nonsmoking Building: As of March 1, 2013, the University of Houston is a non-smoking campus. Smoking is not permitted within the building or on the construction site. F. Controlled Substances: Use of tobacco products and other controlled substances [within the existing building] [on Project site] is not permitted. G. Employee Identification: Owner will provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times. H. Employee Screening: Comply with Owner's requirements for [drug] [and] [background] screening of Contractor personnel working on Project site. 1. Maintain list of approved screened personnel with Owner's representative SPECIFICATION AND DRAWING CONVENTIONS A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows: 1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase. 2. Specification requirements are to be performed by Contractor unless specifically stated otherwise. B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications. C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products: 1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections. 2. Abbreviations: Materials and products are identified by abbreviations [published as part of the U.S. National CAD Standard] [and] [scheduled on Drawings]. 3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual. AE Project #: <%Project Number%> Summary

10 PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION AE Project #: <%Project Number%> Summary

11 University of Houston Insert Project Name SECTION ALLOWANCES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes administrative and procedural requirements governing allowances. 1. Certain items are specified in the Contract Documents by allowances. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when direction will be provided to Contractor. If necessary, additional requirements will be issued by Change Order. B. Types of allowances include the following: 1. Lump-sum allowances. 2. Unit-cost allowances. 3. Quantity allowances. 4. Contingency allowances. 5. Testing and inspecting allowances. C. Related Requirements: 1. Section "Unit Prices" for procedures for using unit prices. 2. Section "Quality Requirements" for procedures governing the use of allowances for testing and inspecting. 1.3 SELECTION AND PURCHASE A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection and purchase of each product or system described by an allowance must be completed to avoid delaying the Work. B. At Architect's request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work. C. Purchase products and systems selected by Architect from the designated supplier. AE Project #: <%Project Number%> Allowances

12 University of Houston Insert Project Name 1.4 ACTION SUBMITTALS A. Submit proposals for purchase of products or systems included in allowances, in the form specified for Change Orders. 1.5 INFORMATIONAL SUBMITTALS A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance. B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance. C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work. 1.6 COORDINATION A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation. 1.7 LUMP-SUM UNIT-COST AND QUANTITY ALLOWANCES A. The costs included in the Allowances shall be determined in accordance with the UGC and SGC except that any claim by Contractor for an adjustment to the GMP based on the cost for allowance work shall be made within a reasonable time after the cost of the allowance is known. B. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Architect under allowance and shall include freight and delivery to Project site. C. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials ordered by Owner under allowance shall be included as part of the Contract Sum and not part of the allowance. D. Unused Materials: Return unused materials purchased under an allowance to manufacturer or supplier for credit to Owner, after installation has been completed and accepted. 1. If requested by Architect, retain and prepare unused material for storage by Owner. Deliver unused material to Owner's storage space as directed. AE Project #: <%Project Number%> Allowances

13 University of Houston Insert Project Name 1.8 CONTINGENCY ALLOWANCES A. Use the contingency allowance only as directed by the contract documents and only by Change Orders that indicate amounts to be charged to the allowance. B. Contractor's overhead, profit, and related costs for products and equipment ordered by Owner under the contingency allowance are included in the allowance and are not part of the Contract Sum. These costs include delivery, installation, insurance, equipment rental, and similar costs. C. Change Orders authorizing use of funds from the contingency allowance will include Contractor's related costs and reasonable overhead and profit margins. D. At Project closeout, credit unused amounts remaining in the contingency allowance to Owner by Change Order. 1.9 TESTING AND INSPECTING ALLOWANCES A. Testing and inspecting allowances include the cost of engaging testing agencies, actual tests and inspections, and reporting results. B. The allowance does not include incidental labor required to assist the testing agency or costs for retesting if previous tests and inspections result in failure. The cost for incidental labor to assist the testing agency shall be included in the Contract Sum. C. Costs of services not required by the Contract Documents are not included in the allowance. D. At Project closeout, credit unused amounts remaining in the testing and inspecting allowance to Owner by Change Order ADJUSTMENT OF ALLOWANCES A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins. 1. Include installation costs in purchase amount only where indicated as part of the allowance. 2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other margins claimed. 3. Submit substantiation of a change in scope of work, if any, claimed in Change Orders related to unit-cost allowances. 4. Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count. AE Project #: <%Project Number%> Allowances

14 University of Houston Insert Project Name B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit. 1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of work has changed from what could have been foreseen from information in the Contract Documents. 2. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 EXAMINATION A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement. 3.2 PREPARATION A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work. 3.3 SCHEDULE OF ALLOWANCES A. Allowance No. <Insert number>: [Lump-Sum] [Unit-Cost] [Quantity] [Contingency] [Testing and Inspecting] Allowance: Include the sum of <Insert dollar or quantity amount of allowance>: Include <Insert allowance description> as specified in Section <Insert Section number> "<Insert Section title>"[ and as shown on Drawings]. 1. This allowance includes [material cost] [receiving, handling, and installation] [and] [Contractor overhead and profit]. 2. Coordinate quantity allowance adjustment with corresponding unit-price requirements in Section "Unit Prices." END OF SECTION AE Project #: <%Project Number%> Allowances

15 University of Houston Master Construction Criteria SECTION UNIT PRICES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes administrative and procedural requirements for unit prices. B. Related Requirements: 1. Section "Contract Modification Procedures" for procedures for submitting and handling Change Orders. 2. Section "Quality Requirements" for general testing and inspecting requirements. 1.3 DEFINITIONS A. Unit price is an amount incorporated in the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased. 1.4 PROCEDURES A. Unit prices include all necessary material, plus cost for delivery, installation, insurance,overhead, and profit. B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections. C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor. D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price. AE Project #: <%Project Number%> Unit Prices

16 University of Houston Master Construction Criteria PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 SCHEDULE OF UNIT PRICES A. Unit Price No. <Insert unit-price number> - <Insert unit-price item>: 1. Description: <Insert unit-price item description> according to Section <Insert Section number> "<Insert Section title>." 2. Unit of Measurement: <Insert unit of measurement>. 3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in Section "Allowances." END OF SECTION AE Project #: <%Project Number%> Unit Prices

17 ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes administrative and procedural requirements for alternates. 1.3 DEFINITIONS A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. 1. Alternates described in this Section are part of the Work only if enumerated in the Agreement. 2. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternate into the Work. No other adjustments are made to the Contract Sum. 1.4 PROCEDURES A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project. 1. Include as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of alternate. B. Notification: Immediately following award of the Contract, each party involved shall be notified in writing of the status of each alternate, in particular whether alternates have been accepted, rejected, or deferred for later consideration. Notification shall include a complete description of negotiated revisions to alternates. C. Execute accepted alternates under the same conditions as other work of the Contract. D. Schedule: A schedule of alternates is included at the end of this Section. Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate. AE Project #: <%Project Number%> Alternates

18 PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 SCHEDULE OF ALTERNATES A. Alternate No. <Insert number>: <Insert title of alternate>. 1. Base Bid: <Insert brief description of base-bid requirement> [as indicated on Sheet <Insert title of sheet>] [and] [as specified in Section <Insert Section number> "<Insert Section title>."] 2. Alternate: <Insert brief description of alternate requirement> [as indicated on Sheet <Insert title of sheet>] [and] [as specified in Section <Insert Section number> "<Insert Section title>."] END OF SECTION AE Project #: <%Project Number%> Alternates

19 Copyright 2010 by The American Institute of Architects (AIA) SECTION SUBSTITUTION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes administrative and procedural requirements for substitutions. B. Related Requirements: 1. Section "Allowances" for products selected under an allowance. 2. Section "Alternates" for products selected under an alternate. 3. Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers. 1.3 DEFINITIONS A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor. 1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms. 2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner. --No substitutions for convenience are allowed. 1.4 ACTION SUBMITTALS A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles. 1. Substitution Request Form: Use [facsimile of form provided in Project Manual]. 2. Documentation: Show compliance with requirements for substitutions and the following, as applicable: a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable. AE Project #: <%Project Number%> Substitution Procedures

20 b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution. c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified. d. Product Data, including drawings and descriptions of products and fabrication and installation procedures. e. Samples, where applicable or requested. f. Certificates and qualification data, where applicable or requested. g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners. h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated. i. Research reports evidencing compliance with building code in effect for Project, from ICC-ES. j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery. k. Cost information, including a proposal of change, if any, in the Contract Sum. l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated. m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results. 3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later. a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work. b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated. AE Project #: <%Project Number%> Substitution Procedures

21 1.5 QUALITY ASSURANCE A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers. 1.6 PROCEDURES A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions. PART 2 - PRODUCTS 2.1 SUBSTITUTIONS A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals. 1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements: a. Requested substitution is consistent with the Contract Documents and will produce indicated results. b. Requested substitution provides sustainable design characteristics that specified product provided. c. Substitution request is fully documented and properly submitted. d. Requested substitution will not adversely affect Contractor's construction schedule. e. Requested substitution has received necessary approvals of authorities having jurisdiction. f. Requested substitution is compatible with other portions of the Work. g. Requested substitution has been coordinated with other portions of the Work. h. Requested substitution provides specified warranty. i. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved. B. Substitutions for Convenience: Not allowed. PART 3 - EXECUTION (Not Used) END OF SECTION AE Project #: <%Project Number%> Substitution Procedures

22 SECTION CONTRACT MODIFICATION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. B. The Contractor's attention is specifically directed, but not limited, to the following documents for additional requirements: 1. Uniform General Conditions for Construction Contracts, State of Texas, 2010 (UGC). 2. The University of Houston s Supplemental General Conditions and Special Conditions for Construction. 1.2 SUMMARY A. Section includes administrative and procedural requirements for handling and processing Contract modifications. Construction Manager shall develop and implement a system acceptable to Owner for the preparation, review and processing of Change Proposals, contingency and allowance expenditure authorizations, Change Orders, and requests for information, in accordance with the UGC and SGC. B. Related Requirements: 1. Section "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award. 1.3 MINOR CHANGES IN THE WORK A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710, "Architect's Supplemental Instructions" or similar form. 1.4 PROPOSAL REQUESTS A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications. 1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change. 2. Within time specified in Proposal Request or 14 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change. AE Project #: <%Project Number%> Contract Modification Procedures

23 a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities. b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. c. Include costs of labor and supervision directly attributable to the change. d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time. e. Quotation Form: Use forms provided by Owner. Sample copies are included in the Owner s Supplementary General Conditions for Construction. B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect. 1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time. 2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities. 3. Indicate applicable delivery charges, equipment rental, and amounts of trade discounts. 4. Include costs of labor and supervision directly attributable to the change. 5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time. 6. Comply with requirements in Section "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified. 7. Proposal Request Form: Use form provided by Owner. Sample copy is included in the Owner s Supplementary General Conditions for Construction. 1.5 ADMINISTRATIVE CHANGE ORDERS A. Allowance Adjustment: See Section "Allowances" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances. B. Unit-Price Adjustment: See Section "Unit Prices" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect measured scope of unit-price work. 1.6 CHANGE ORDER PROCEDURES A. On Owner's approval of a Work Changes Proposal Request, Architect will issue a Contract Change Order for signatures of Owner and Contractor on Owner s standard form. AE Project #: <%Project Number%> Contract Modification Procedures

24 1.7 CONSTRUCTION CHANGE DIRECTIVE A. [Construction] [Work] Change Directive: [Architect] [Construction Manager] may issue a [Construction] [Work] Change Directive on [form included in Project Manual]. [Construction] [Work] Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. 1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time. B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive. 1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION AE Project #: <%Project Number%> Contract Modification Procedures

25 <%Project Name%> SECTION PAYMENT PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. B. The Contractor's attention is specifically directed, but not limited, to the following documents for additional requirements: 1. Uniform General Conditions for Construction Contracts, State of Texas, 2010 (UGC). 2. The University of Houston s Supplemental General Conditions and Special Conditions for Construction. 1.2 SUMMARY A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment. B. Related Requirements: 1. Section "Allowances" for procedural requirements governing the handling and processing of allowances. 2. Section "Unit Prices" for administrative requirements governing the use of unit prices. 3. Section "Contract Modification Procedures" for administrative procedures for handling changes to the Contract. 1.3 SCHEDULE OF VALUES A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule. 1. Coordinate line items in the schedule of values with other required administrative forms and schedules, including the following: a. Application for Payment forms with continuation sheets. b. Submittal schedule. c. Items required to be indicated as separate activities in Contractor's construction schedule. 2. Submit the schedule of values to Architect at earliest possible date, but no later than 14 days before the date scheduled for submittal of initial Application for Payment. AE Project #: <%Project Number%> Payment Procedures

26 <%Project Name%> 3. Subschedules for Phased Work: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values coordinated with each phase of payment. 4. Subschedules for Separate Elements of Work: Where the Contractor's construction schedule defines separate elements of the Work, provide subschedules showing values coordinated with each element. B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section. 1. Identification: Include the following Project identification on the schedule of values: a. Project name and location. b. Name of Architect. c. Architect's project number. d. Contractor's name and address. e. Date of submittal. 2. Arrange schedule of values consistent with format of AIA Document G Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with Project Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum. a. Include separate line items under Contractor and principal subcontracts for Project closeout requirements in an amount totaling five percent of the Contract Sum and subcontract amount. 4. Round amounts to nearest whole dollar; total shall equal the Contract Sum. 5. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed. a. Differentiate between items stored on-site and items stored off-site. If required, include evidence of insurance. 6. Allowances: Provide a separate line item in the schedule of values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities. 7. Each item in the schedule of values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item. AE Project #: <%Project Number%> Payment Procedures

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

TRUMAN STATE UNIVERSITY SITE IMPROVEMENTS, KIRK BLDG, MISSOURI HALL & STUDENT REC CENTER LTD RENOVATIONS

TRUMAN STATE UNIVERSITY SITE IMPROVEMENTS, KIRK BLDG, MISSOURI HALL & STUDENT REC CENTER LTD RENOVATIONS SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

BOWIE STATE UNIVERSITY CAR PARKING LOT

BOWIE STATE UNIVERSITY CAR PARKING LOT BOWIE STATE UNIVERSITY CAR PARKING LOT TECHNICAL SPECIFICATIONS 100% CD SUBMISSION NOVEMBER 2, 2018 Prepared by WHITNEY, BAILEY COX & MAGNANI, LLC 300 East Joppa Road, Suite 200 Baltimore, Maryland 21286

More information

UNIVERSITY OF ROCHESTER DIVISION 01 SPECIFICATIONS April 15, 2015

UNIVERSITY OF ROCHESTER DIVISION 01 SPECIFICATIONS April 15, 2015 SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

TRUMAN STATE UNIVERSITY BALDWIN HALL, PERSHING BLDG AND VIOLETTE HALL ROOFING & EXT. RENOV.

TRUMAN STATE UNIVERSITY BALDWIN HALL, PERSHING BLDG AND VIOLETTE HALL ROOFING & EXT. RENOV. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. CSB 7th Floor Orthopaedic Surgery Office Renovation Phase 2 SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information

University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no Set no. project manual.

University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no Set no. project manual. University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no. 1801.01 07 12 2018 Set no. project manual. University of Oklahoma Sarkeys Energy Center Atriums Waterproofing

More information

RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT

RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT PROJECT MANUAL RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT CITY OF RICHMOND Richmond, Virginia Architect s Project No. 563107 ARCHITECT/ENGINEER RICHMOND, VIRGINIA A/E s Project No. 563107 set

More information

CHAPEL HILL TOWN HALL RENOVATIONS UPPER LEVEL, SOUTH CHAPEL HILL, NORTH CAROLINA

CHAPEL HILL TOWN HALL RENOVATIONS UPPER LEVEL, SOUTH CHAPEL HILL, NORTH CAROLINA SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

OSNI PONCA OFFICE REMODEL

OSNI PONCA OFFICE REMODEL OSNI PONCA OFFICE REMODEL PROJECT MANUAL OCTOBER 2016 SCHEMMER PROJECT NO. 06571.002 OSNI PONCA OFFICE REMODEL TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000115 LIST OF DRAWING

More information

NMSU Carlsbad Campus Main Building and Computer Building DDC Control Upgrade. Project Manual Technical Specifications Review Submittal May 12, 2017

NMSU Carlsbad Campus Main Building and Computer Building DDC Control Upgrade. Project Manual Technical Specifications Review Submittal May 12, 2017 NMSU Carlsbad Campus Main Building and Computer Building DDC Control Upgrade NMSU Facilities and Services Department P.O. Box 30001 Las Cruces, NM 88003-8001 Project Manual Technical Specifications Review

More information

PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION

PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION CITY OF PENSACOLA November 2018 SECTION 011000- SUMMARY OF WORK PART 1 - GENERAL 1.1 DOCUMENTS A. Drawings and general

More information

Hard Rock Hotel and Casino - Tulsa Casino 3 and Suite Hotel Exterior Painting Bid Issue Issue Date: 18 March 2013 Project Number

Hard Rock Hotel and Casino - Tulsa Casino 3 and Suite Hotel Exterior Painting Bid Issue Issue Date: 18 March 2013 Project Number Hard Rock Hotel and Casino - Tulsa Casino 3 and Suite Hotel Exterior Painting Issue Date: 18 March 2013 Project Number 13-201.1 9400 Gateway Drive, Suite B Reno, NV 89521 775.852.3977 (p) 775.852.6543

More information

George Washington Middle School - HVAC Replacement 100% Construction Documents May 7, 2018 TABLE OF CONTENTS

George Washington Middle School - HVAC Replacement 100% Construction Documents May 7, 2018 TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS 011000 SUMMARY 012500 SUBSTITUTION PROCEDURES 012900 PAYMENT PROCEDURES 013100 PROJECT MANAGEMENT AND COORDINATION 013200 CONSTRUCTION PROGRESS DOCUMENTATION

More information

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT PROJECT MANUAL. Commonwealth Architects

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT PROJECT MANUAL. Commonwealth Architects CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia 23223 PROJECT MANUAL PERMIT SET FEBRUARY 27, 2017 Commonwealth Architects 101 Shockoe Slip Richmond, VA 23219 CITY

More information

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia PROJECT MANUAL BID SET April 4, 2018

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia PROJECT MANUAL BID SET April 4, 2018 CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia 23223 PROJECT MANUAL BID SET April 4, 2018 Commonwealth Architects 101 Shockoe Slip, Fl 3 Richmond, VA 23219 CITY

More information

SPECIFICATIONS. September 27, 2016 Bid Set

SPECIFICATIONS. September 27, 2016 Bid Set SPECIFICATIONS September 27, 2016 Bid Set CITY HALL SUITE 100 & 102 RENOVATIONS TABLE OF CONTENTS (Refer to Project Book under separate cover for additional requirements) SPECIFICATIONS DIVISION 1 - GENERAL

More information

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX BID PACKAGE #1 SITE WORK

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX BID PACKAGE #1 SITE WORK HOSKINS ARCHITECTURE, LLC 1827 1 ST AVENUE NORTH, SUITE 104 BIRMINGHAM, ALABAMA 35203 205.321.4122 ADDENDUM NO. 1 PROJECT: BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX BID PACKAGE #1 SITE WORK

More information

1. Division 1 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Division 1 Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. CFA A HVAC PROJECT SECTION 01100 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

SPECIFICATIONS. Permit Set RICHMOND CITY HALL: SUITE 110 RENOVATIONS. City of Richmond, Virginia Architect s Project No

SPECIFICATIONS. Permit Set RICHMOND CITY HALL: SUITE 110 RENOVATIONS. City of Richmond, Virginia Architect s Project No SPECIFICATIONS Permit Set RICHMOND CITY HALL: SUITE 110 RENOVATIONS ARCHITECT RICHMOND, VIRGINIA MECHANICAL, PLUMBING, FIRE PROTECTION, AND ELECTRICAL ENGINEERS GLEN ALLEN, VIRGINIA A/E s Project No. 563109

More information

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax ADDENDUM 707 Minnesota Ave., Suite 506 Kansas City, Kansas 66101 Tel. 913.287.1900 Fax. 816.300.4102 www.wskfarch.com A r c h i t e c t u r e I n t e r i o r D e s i g n I l l u s t r a t I o n P l a n

More information

1) Unified School District No. 489 reserves the right to reject any or all bids and to waive any informalities in the bid procedure.

1) Unified School District No. 489 reserves the right to reject any or all bids and to waive any informalities in the bid procedure. Prospective bidders: The Board of Education, Unified School District No. 489, will receive bids for the fabrication and construction of two pre-manufactured metal building in the designated area at the

More information

TOWNES + architects, P.A.

TOWNES + architects, P.A. TOWNES + architects, P.A. 2421 North 12th Avenue, Pensacola, Florida 32503 Telephone: (850) 433-0203 Florida Registration AA-26001051 PROJECT MANUAL City of Pensacola Fleet Maintenace Garage Re ovation

More information

SSM Project: Centennial School District Issued for Bid AC Unit Replacements 05/16/2014 Klinger and Log College Middle Schools

SSM Project: Centennial School District Issued for Bid AC Unit Replacements 05/16/2014 Klinger and Log College Middle Schools Division Section Title SPECIFICATIONS GROUP General Requirements Subgroup DIVISION 01 GENERAL REQUIREMENTS 011000 SUMMARY 012500 SUBSTITUTION PROCEDURES 012600 CONTRACT MODIFICATION PROCEDURES 012900 PAYMENT

More information

VAE VIEW ELEMENTARY WINDOW REPLACEMENT West 1600 North Layton, UT Specifications. Construction Documents

VAE VIEW ELEMENTARY WINDOW REPLACEMENT West 1600 North Layton, UT Specifications. Construction Documents VAE VIEW ELEMENTARY WINDOW REPLACEMENT 1750 West 1600 North Layton, UT 84041 Specifications 19 March 2018 TABLE OF CONTENTS DIVISION 00 PREREQUIREMENT AND CONTRACTING REQUIREMENTS A101 A201 A310 A312 G701

More information

Project Manual. Beaverton School District Beaverton High School Gymnasium Improvement Beaverton, Oregon. Issue date: December 21st 2017

Project Manual. Beaverton School District Beaverton High School Gymnasium Improvement Beaverton, Oregon. Issue date: December 21st 2017 Project Manual Beaverton School District Beaverton High School Gymnasium Improvement Beaverton, Oregon Issue date: December 21st 2017 18241 Beaverton High School Gymnasium Improvement TABLE OF CONTENTS

More information

RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS Willow Park Drive Suite 200 Naples, FL 34109

RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS Willow Park Drive Suite 200 Naples, FL 34109 RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS 6610 Willow Park Drive Suite 200 Naples, FL 34109 MAY 23, 2012 NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS

More information

PROJECT MANUAL POINT BLANK RANGE & GUN SHOP. 600 Corporate way Knoxville, TN. Bid/Permit Set

PROJECT MANUAL POINT BLANK RANGE & GUN SHOP. 600 Corporate way Knoxville, TN. Bid/Permit Set PROJECT MANUAL POINT BLANK RANGE & GUN SHOP 600 Corporate way Knoxville, TN Bid/Permit Set Division Section Title SPECIFICATIONS GROUP DIVISION 01 - GENERAL REQUIREMENTS 011000 SUMMARY 012600 CONTRACT

More information

University Apartments on Brooklyn PROJECT MANUAL

University Apartments on Brooklyn PROJECT MANUAL Section 011000 - Summary PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Project information. 2. Work covered by Contract Documents. 3. Phased construction. 4. Work under separate contracts. 5. Access

More information

SECTION PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01600 - PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

ENTRY SECURITY MODIFICATIONS

ENTRY SECURITY MODIFICATIONS Rio Rancho Public Schools ENTRY SECURITY MODIFICATIONS Volume 2 of 2 Divisions 01 through 28 Mountain View Middle School Project Number 083105-16-002 Rio Rancho Cyber Academy Project Number 083018-16-001

More information

1. Instructions to Bidders AIA Document A701, 1997 Section of the above referenced IFB is hereby amended and restated as follows:

1. Instructions to Bidders AIA Document A701, 1997 Section of the above referenced IFB is hereby amended and restated as follows: Segments 3, 4, 6 and 7 Pier Repairs Invitation for Bids (IFB) Project/Contract #C4962 Addendum # 1 November 30, 2018 To All Bidders: 1. Instructions to Bidders AIA Document A701, 1997 Section 5.3.1.3 of

More information

SPECIFICATIONS May 25, Ellicott Station Redevelopment Brewery Building - 40 Ellicott Street Ellicott Street Batavia, New York United States

SPECIFICATIONS May 25, Ellicott Station Redevelopment Brewery Building - 40 Ellicott Street Ellicott Street Batavia, New York United States SPECIFICATIONS May 25, 2018 Ellicott Station Redevelopment Brewery Building - 40 Ellicott Street Ellicott Street Batavia, New York United States Ellicott Station Development, LLC 500 Seneca Street Suite

More information

LCCC MAIN PLANT BOILER BURNER UPGRADES

LCCC MAIN PLANT BOILER BURNER UPGRADES LCCC MAIN PLANT BOILER BURNER UPGRADES FOR Laramie County Community College (LCCC) 1400 East College Drive Cheyenne, WY 82007 ENGINEERS Cator, Ruma & Associates 420 West Lincolnway Cheyenne, WY 82001 PROJECT

More information

1ARCHITECTURE TABLE OF CONTENTS

1ARCHITECTURE TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 0102 COVER 00 0107 SEALS PAGE 00 0111 TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS 01 1000 01 2000 01 2100 01 2300 01

More information

PROJECT MANUAL. Phi Delta Theta Phase NW 13 th Street Corvallis, OR Varitone Architecture LLC

PROJECT MANUAL. Phi Delta Theta Phase NW 13 th Street Corvallis, OR Varitone Architecture LLC PROJECT MANUAL Phi Delta Theta Phase 2 120 NW 13 th Street Corvallis, OR 97330 Varitone Architecture LLC 231 SW 2nd Ave. PO Box 3420 Albany, Oregon 97321 Project Contacts Owner Phi Delta Theta Chapter

More information

RICHMOND PUBLIC SCHOOLS

RICHMOND PUBLIC SCHOOLS PROJECT MANUAL RICHMOND PUBLIC SCHOOLS E.S.H. GREENE ELEMENTARY SCHOOL CONSTRUCTION PROJECT DEPT. OF EDUCATION NO. 123-144-00-100 DIVISION 1 (DRAFT SPECIFICATIONS) PREPARED BY RRMM ARCHITECTS ARCHITECTURE

More information

***Specifications***

***Specifications*** STEM 2 Greenhouse Project Bid No. B17-14 ***Specifications*** Bid RFI Questions Due: Tuesday, July 11, 2017 2:00PM Gale Stevens, Buyer gasteven@cabrillo.edu BID DOCUMENTS: GALE STEVENS, BUYER 831-477-5613

More information

Project Manual. Unitarian Universalist Congregation of Princeton 50 Cherry Hill Road Princeton, New Jersey Lot: 11 Block: 5201

Project Manual. Unitarian Universalist Congregation of Princeton 50 Cherry Hill Road Princeton, New Jersey Lot: 11 Block: 5201 Project Manual for Alterations & Building Addition to: Unitarian Universalist Congregation of Princeton 50 Cherry Hill Road Princeton, New Jersey Lot: 11 Block: 5201 SCHEMATIC DESIGN ISSUE NOT FOR CONSTRUCTION

More information

THE FORUM ROME, GEORGIA FOR FLOYD COUNTY PROJECT MANUAL (BALLROOM AND CONCESSIONS) Construction Documents

THE FORUM ROME, GEORGIA FOR FLOYD COUNTY PROJECT MANUAL (BALLROOM AND CONCESSIONS) Construction Documents THE FORUM ROME, GEORGIA FOR FLOYD COUNTY PROJECT MANUAL (BALLROOM AND CONCESSIONS) Construction Documents Architect s Project Number: 420.01.01 Issued: November 11, 2016 PEACOCK a r c h i t e c t s 5525

More information

WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS BEXAR COUNTY ARENAS - FENCING PACKAGE

WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS BEXAR COUNTY ARENAS - FENCING PACKAGE PROJECT MANUAL / TECHNICAL SPECIFICATIONS WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS - FENCING PACKAGE 3201 E. HOUSTON STREET SAN ANTONIO, TEXAS 78219 OCTOBER 6, 2017 HUMBERTO SALDANA & ASSOCIATES, INC.

More information

WINDOW REPLACEMENT FOR ARCHITECT'S NO NORWOOD ELEMENTARY SCHOOL. A. Project Name: Window Replacement for Norwood Elementary School.

WINDOW REPLACEMENT FOR ARCHITECT'S NO NORWOOD ELEMENTARY SCHOOL. A. Project Name: Window Replacement for Norwood Elementary School. WINDOW REPLACEMENT FOR ARCHITECT'S NO. 2638 NORWOOD ELEMENTARY SCHOOL DOCUMENT 00 9113A - ADDENDUM NO. 1 1.1 PROJECT INFORMATION A. Project Name: Window Replacement for Norwood Elementary School. B. Owner:

More information

PROJECT MANUAL UNIVERSITY HALL BOILER REPLACEMENT PROJECT NO. EM 610

PROJECT MANUAL UNIVERSITY HALL BOILER REPLACEMENT PROJECT NO. EM 610 PROJECT MANUAL For UNIVERSITY HALL BOILER REPLACEMENT PROJECT NO. EM 610 Prepared For: UNIVERSITY OF COLORADO AT COLORADO SPRINGS September 27, 2010 Prepared By: SCHENDT ENGINEERING CORP. 2912 Beacon Street

More information

New Mexico State University Herritage Farm Interpretive Trail

New Mexico State University Herritage Farm Interpretive Trail PROJECT MANUAL PROJECT MANAGER: SHELLEY ZIVKOVICH 575-646-1991 shelleyz@nmsu.edu New Mexico State University Herritage Farm Interpretive Trail APRIL 28, 2017 PROJECT #206-88 WDG ARCHITECTS 1014 South Main

More information

RICHMOND PUBLIC SCHOOLS

RICHMOND PUBLIC SCHOOLS PROJECT MANUAL RICHMOND PUBLIC SCHOOLS NEW MIDDLE SCHOOL CONSTRUCTION ON HULL STREET CONSTRUCTION PROJECT DEPT. OF EDUCATION NO. 123-108-00-100 DIVISION 1 (DRAFT SPECIFICATIONS) PREPARED BY RRMM ARCHITECTS

More information

PROJECT SPECIFICATIONS. for. Grossmont Community College. Main Chiller Plant Repair. El Cajon, CA. Bid Number B18.014

PROJECT SPECIFICATIONS. for. Grossmont Community College. Main Chiller Plant Repair. El Cajon, CA. Bid Number B18.014 PROJECT SPECIFICATIONS for Grossmont Community College El Cajon, CA Bid Number B18.014 Grossmont College Specification TOC 07/11/2018 DIVISION 01 GENERAL REQUIREMENTS 01 10 00 ~ Summary 01 14 00 ~ Work

More information

A. Section includes administrative and procedural requirements for substitutions.

A. Section includes administrative and procedural requirements for substitutions. SPECIFICATIONS NO. XX-XX-XXX-XX SECTION 01 25 00 - SUBSTITUTION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information

SECTION PRODUCT REQUIREMENTS PART 1 GENERAL 1.1 RELATED DOCUMENTS

SECTION PRODUCT REQUIREMENTS PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 01 60 00 PRODUCT REQUIREMENTS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS SECTION 016000 - PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes administrative and procedural requirements for selection of products for use in Project; product delivery, storage,

More information

DREW UNIVERSITY SPECIFICATIONS ARCHITECTURAL & M.E.P. HALL OF SCIENCES LABORATORY 129 AND 133 RENOVATION. 36 Madison Avenue Madison, New Jersey

DREW UNIVERSITY SPECIFICATIONS ARCHITECTURAL & M.E.P. HALL OF SCIENCES LABORATORY 129 AND 133 RENOVATION. 36 Madison Avenue Madison, New Jersey SPECIFICATIONS ARCHITECTURAL & M.E.P. DREW UNIVERSITY HALL OF SCIENCES LABORATORY 129 AND 133 RENOVATION 36 Madison Avenue Madison, New Jersey NK Project #2199.000 ISSUED FOR REVIEW March 09, 2018 95 Washington

More information

Willow Oak Veterinary Hospital

Willow Oak Veterinary Hospital Project Manual For Willow Oak Veterinary Hospital Durham, North Carolina Linton Architects Project #1219 September 11, 2013 Linton Architects 331 West Main Street, Suite 608 Durham, North Carolina 27701

More information

DeKalb County Library Dunwoody Library Staff Area Renovation

DeKalb County Library Dunwoody Library Staff Area Renovation PROJECT MANUAL DeKalb County Library Dunwoody Library Staff Area Renovation OWNER: DeKalb County Library Email: kimbroj@dekalblibrary.org Contact: Jackee Kimbro 404-508-719-, ext. 2236 ARCHITECT: MEP ENGINEER:

More information

University of South Florida Health Center MDL-0114 Building Reroofing USF Project No. PF

University of South Florida Health Center MDL-0114 Building Reroofing USF Project No. PF University of South Florida Health Center MDL-0114 Building Reroofing USF Project No. PF154317843202 Project Manual October 31, 2017 October 31, 2017 Project Manual For University of South Florida Health

More information

Beverly Gardens Park City of Beverly Hills, CA. Block #9: Elm Foothill Garden

Beverly Gardens Park City of Beverly Hills, CA. Block #9: Elm Foothill Garden Beverly Gardens Park Block #9: SPECIFICATIONS 100% CD / BID SET TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS SECTION No. TITLE 011000.Summary. 3 012213.Unit Prices...1 012500.Substitution Procedures

More information

CITY OF COLLEGE PARK. BADGETT STADIUM FACILITY 2336 COLLEGE STREET College Park, Georgia Fulton County PROJECT MANUAL. Construction Documents

CITY OF COLLEGE PARK. BADGETT STADIUM FACILITY 2336 COLLEGE STREET College Park, Georgia Fulton County PROJECT MANUAL. Construction Documents Metrocorp Development Enterprises, Inc. Program Management Development Consultants Construction Managers Civil Engineers Globalizations & Emerging Markets 3707 Main Street, Ste. No. 15 College Park, Georgia

More information

Robert M. Ball Conference Room Renovation Project

Robert M. Ball Conference Room Renovation Project ROBERT M. BALL BUILDING SOCIAL SECURITY ADMINISTRATION CAMPUS WOODLAWN, MARYLAND Robert M. Ball Conference Room Renovation Project Specifications Prepared for: General Services Administration Region 3

More information

Project Manual OVERLAND PARK BRANCH & ESIS RELOCATION. for

Project Manual OVERLAND PARK BRANCH & ESIS RELOCATION. for Project Manual OVERLAND PARK BRANCH & ESIS RELOCATION for Chubb Floor 4 34 Corporate Woods 10950 Grandview Drive Overland Park KS 66210 Issued for Bid & Permit July 18, 2016 SECTION 000110 TABLE OF CONTENTS

More information

[FIELDHOUSE] FLOOR R E P L A C E M E N T FLAGSTAFF, AZ

[FIELDHOUSE] FLOOR R E P L A C E M E N T FLAGSTAFF, AZ [FIELDHOUSE] FLOOR R E P L A C E M E N T FLAGSTAFF, AZ P R O J E C T M A N U A L VOLUME 1 OF 1 1729 EAST OSBORN ROAD PHOENIX, AZ 85016 CD ISSUANCE NAU PROJECT NO.: 09.0330.171 LIGHTVOX PROJECT NO.: 3001.16.01

More information

ruby ridge terrace apartments

ruby ridge terrace apartments p r o j e c t m a n u a l for: ruby ridge terrace apartments 550 South, 12th Street 89801 Re-Bid Package 01 May 14, 2014 TABLE OF CONTENTS 1. Title page 2. Table of Contents 3. Invitation to Bid 4. Bid

More information

ELECTRICAL CONSULTANT

ELECTRICAL CONSULTANT INFRASTRUCTURE BUILDINGS 36 & 41 GROSSMONT COLLEGE GROSSMONT CUYAMACA COMMUNITY COLLEGE DISTRICT #B19.005 CLIENT 8800 Grossmont College Drive El Cajon, CA 92021 ELECTRICAL CONSULTANT Johnson Consulting

More information

Illinois State University Softballl Dugout Replacement Normal, Illinois

Illinois State University Softballl Dugout Replacement Normal, Illinois Illinois State University Softballl Dugout Replacement Normal, Illinois Issue for Bid ISU Project No. 10611 DLR Group Project No. 22-11116-10 July 1, 2016 NOTICE: These documents are instruments of professional

More information

Project Manual For: SOUTHWEST WISCONSIN TECHNICAL COLLEGE. Building 300 Administration Fire Protection Bronson Blvd. Fennimore, WI 53809

Project Manual For: SOUTHWEST WISCONSIN TECHNICAL COLLEGE. Building 300 Administration Fire Protection Bronson Blvd. Fennimore, WI 53809 Project Manual For: SOUTHWEST WISCONSIN TECHNICAL COLLEGE Building 00 Administration Fire Protection 00 Bronson Blvd. Fennimore, WI 0 PRA Project No. 00-0 SWTC Project No. -0 July 0 00-0 TITLE PAGE 00

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

CONTRACTOR S PROPOSAL

CONTRACTOR S PROPOSAL WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS ALL ITEMS MUST BE COMPLETED BY CONTRACTOR CALL NUMBER CONTRACTOR S NAME CONTRACTOR S FEIN BID AMOUNT DBE GOAL (%) WV LICENSE NUMBER PREQUALIFICATION

More information

Scope of Repair Davenport Grade School Roof Repair

Scope of Repair Davenport Grade School Roof Repair Scope of Repair Grade School Roof Repair Prepared for: Graehm Wallace Perkins Coie LLP 1201 Third Avenue, Suite 4900 Seattle, WA 98101-3099 Date of Issuance: March 19, 2018 SECTION 011000 SUMMARY OF WORK

More information

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR PROJECT MANUAL FOR Ogden Regional Medical Center 5475 South 500 East Ogden, UT 84405 for MountainStar Healthcare Construction Documents NJRA Architects, Inc. 5272 South College Dr. Murray, Utah 84123 Telephone:

More information

The Town will coordinate with the adjacent property Owner for access allowing work to the East side of the building.

The Town will coordinate with the adjacent property Owner for access allowing work to the East side of the building. ADDENDUM #1 EXTERIOR REPAIRS YOUTH SERVICES BUREAU 63 LINDEN STREET MANCHESTER, CT 06040 BID #15/16-68 S/P+A PROJECT NO. 15.207 DATE: March 15, 2016 The following changes to the Drawings and Project Specifications

More information

Grossmont-Cuyamaca College District Bldg. D Central Chilled Water Loop Tie-in SPECIFICATION MANUAL CUYAMACA COLLEGE, EL CAJON, CA

Grossmont-Cuyamaca College District Bldg. D Central Chilled Water Loop Tie-in SPECIFICATION MANUAL CUYAMACA COLLEGE, EL CAJON, CA Grossmont-Cuyamaca College District SPECIFICATION MANUAL CUYAMACA COLLEGE, EL CAJON, CA PREPARED FOR: Cuyamaca College PREPARED BY: SC Engineers, Inc. 17075 Via Del Campo San Diego, CA 92127 P: 858.946.0333

More information

PROJECT MANUAL VOLUME ONE EOP Project # August 17, 2018

PROJECT MANUAL VOLUME ONE EOP Project # August 17, 2018 PROJECT MANUAL VOLUME ONE EOP Project # 201732 August 17, 2018 KCTCS System Office Renovation MECHANICAL ROOM EQUIPMENT DEMOLITION 300 N. Main St. Versailles, Kentucky 40383 ARCHITECT EOP Architects 201

More information

AWT 9TH FLOOR IMPROVEMENTS CITY OF ANAHEIM, CALL CENTER CREDIT & BILLING DEPARTMENTS, ANAHEIM, CA TECHNICAL SPECIFICATIONS AUGUST 2, 2018

AWT 9TH FLOOR IMPROVEMENTS CITY OF ANAHEIM, CALL CENTER CREDIT & BILLING DEPARTMENTS, ANAHEIM, CA TECHNICAL SPECIFICATIONS AUGUST 2, 2018 CITY OF ANAHEIM, CALL CENTER CREDIT & BILLING DEPARTMENTS, ANAHEIM, CA TECHNICAL SPECIFICATIONS AUGUST 2, 2018 ROBERT BORDERS & ASSOCIATES. General Conditions AIA A201 by reference. TABLE OF CONTENTS DIVISION

More information

PROJECT MANUAL WAYNE STATE UNIVERSITY FACILITIES PLANNING & MANAGEMENT DESIGN SERVICES 5454 CASS AVENUE DETROIT, MICHIGAN 48202

PROJECT MANUAL WAYNE STATE UNIVERSITY FACILITIES PLANNING & MANAGEMENT DESIGN SERVICES 5454 CASS AVENUE DETROIT, MICHIGAN 48202 PROJECT MANUAL FACILITIES PLANNING & MANAGEMENT DESIGN SERVICES 5454 CASS AVENUE DETROIT, MICHIGAN 48202 ROOF REPLACEMENT SCHOOL OF SOCIAL WORK BUILDING 5447 WOODWARD AVENUE, DETROIT, MICHIGAN 48202 WSU

More information

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications

More information

County of Elko, Nevada Requirements, Specifications and Contract Documents. Mechanical System Upgrade, Project Manuel. Jackpot, Elko County, Nevada

County of Elko, Nevada Requirements, Specifications and Contract Documents. Mechanical System Upgrade, Project Manuel. Jackpot, Elko County, Nevada 1 County of Elko, Nevada Requirements, Specifications and Contract Documents for Jackpot Recreation Center Mechanical System Upgrade 2016 Project in Jackpot, Elko County, Nevada Department of Community

More information

AWT 2ND FLOOR IMPROVEMENTS CITY OF ANAHEIM, HOUSING AUTHORITY & WORKPLACE, ANAHEIM, CA TECHNICAL SPECIFICATIONS OCTOBER 24, 2017

AWT 2ND FLOOR IMPROVEMENTS CITY OF ANAHEIM, HOUSING AUTHORITY & WORKPLACE, ANAHEIM, CA TECHNICAL SPECIFICATIONS OCTOBER 24, 2017 CITY OF ANAHEIM, HOUSING AUTHORITY & WORKPLACE, ANAHEIM, CA TECHNICAL SPECIFICATIONS OCTOBER 24, 2017 ROBERT BORDERS & ASSOCIATES. General Conditions AIA A201 by reference. TABLE OF CONTENTS DIVISION 1

More information

LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, Sacramento, CA Phone (916) FAX (916) Purchasing Department

LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, Sacramento, CA Phone (916) FAX (916) Purchasing Department LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, 95825 Phone (916) 568-3071 FAX (916) 568-3145 Purchasing Department Sacramento City College American River College Cosumnes River College Folsom Lake

More information

Main Building Auditorium

Main Building Auditorium Main Building Auditorium Theatre and Lighting Upgrade Moberly Area Community College 101 College Avenue Moberly, Missouri This document contains all necessary instructions and specifications to perform

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Northern Lights Park and Ride Lot

Northern Lights Park and Ride Lot PROJECT MANUAL For the Northern Lights Park and Ride Lot Central Ohio Transit Authority (COTA) Cleveland Avenue Columbus, Ohio BID SET June 5, 2017 Page 1 of 2 06/05/17 DESIGN TEAM Owner/Project Manager:

More information

GENERAL REQUIREMENTS

GENERAL REQUIREMENTS CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 01001-1 PART 1 GENERAL 1.1 Work Covered By Contract Documents.1 Work covers, in general terms: demolition, removals, site preparation and complete construction

More information

SECTION PAYMENT PROCEDURES

SECTION PAYMENT PROCEDURES SECTION 012900 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and other Division 01 Specifications Sections apply

More information

PROJECT TITLE PAGE ORANGEWALLstudios

PROJECT TITLE PAGE ORANGEWALLstudios Wahl Marine Boat Procurement and Contracting Documents 17 April 2017 DOCUMENT 00 01 01 - PROJECT TITLE PAGE PROJECT MANUAL VOLUME 1 Project: Fred Wahl Marine Boat Shop Client: Jim Zimmer Fred Wahl Marine,

More information

Baseball Performance Development Center A Prevailing Wage Project

Baseball Performance Development Center A Prevailing Wage Project June 30, 2016 Baseball Performance Development Center A Prevailing Wage Project PROJECT MANUAL Owner CENTRAL MICHIGAN UNIVERISTY 206 Combined Services Building Mount Pleasant, Michigan PROJECT NUMBER 15-231

More information

SECTION SUPPLEMENTARY GENERAL CONDITIONS

SECTION SUPPLEMENTARY GENERAL CONDITIONS SECTION 00800 SUPPLEMENTARY GENERAL CONDITIONS PART 1 - GENERAL 1.1 SCOPE OF WORK In general, the Work consists of application of a fluid applied membrane, installation of new tapered insulation, installation

More information

Surgical Associates Commercial Remodel

Surgical Associates Commercial Remodel ADDENDUM Project Name: Studio 951 Project No.: 17-012 Surgical Associates Commercial Remodel Addendum No.: 01 Issue Date: 6 December 2017 This Addendum serves to clarify, revise and supersede information

More information

QUALITY REQUIREMENTS

QUALITY REQUIREMENTS SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

CONTRACT CONDITIONS AND SPECIFICATIONS. HMH - Dunn Refresh. for the renovation of

CONTRACT CONDITIONS AND SPECIFICATIONS. HMH - Dunn Refresh. for the renovation of CONTRACT CONDITIONS AND SPECIFICATIONS for the renovation of HMH - Dunn Refresh East - Level 7, 8, 9, and 10 Phase 1 6585 Fannin Street Houston, Texas Issuedfor forpermit Construction Issue and Bid 15

More information

REQUEST FOR PROPOSALS TO FIT OUT FIRST FLOOR RETAIL TENANTS AT THE GLOBAL CENTER FOR HEALTH INNOVATION

REQUEST FOR PROPOSALS TO FIT OUT FIRST FLOOR RETAIL TENANTS AT THE GLOBAL CENTER FOR HEALTH INNOVATION REQUEST FOR PROPOSALS TO FIT OUT FIRST FLOOR RETAIL TENANTS AT THE GLOBAL CENTER FOR HEALTH INNOVATION. INTRODUCTION Levy Premium Foodservice Limited Partnership (the Owner ) is requesting interested firms

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

AIR CONDITIONING SYRACUSE JUNIOR HIGH SCHOOL

AIR CONDITIONING SYRACUSE JUNIOR HIGH SCHOOL PROJECT MANUAL FOR AIR CONDITIONING DAVIS SCHOOL DISTRICT 1450 S. 2000 W. Syracuse, UT 84075 January 2017 BLANK PAGE TABLE OF CONTENTS DIVISION 01 GENERAL CONDITIONS 01 1000 Summary 01 2900 Payment Procedures

More information

Scope of Work Bid Package C-8 - West Overhead Doors

Scope of Work Bid Package C-8 - West Overhead Doors Scope of Work Bid Package C-8 - West Overhead Doors CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,

More information

C. The Work consists of office suite renovations in the second floor of the Missouri State Capitol. The Work includes:

C. The Work consists of office suite renovations in the second floor of the Missouri State Capitol. The Work includes: SECTION 011000- SUMMARY OF WORK PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general prov1s1ons of the Contract including General and Supplementary Conditions and Division 1 Specification Sections

More information

Document Synopses by Series

Document Synopses by Series Document Synopses by Series AIA Contract Documents are divided into six alphanumeric series by document use or purpose: A Series: Owner/Contractor Agreements B Series: Owner/Architect Agreements (p. 13)

More information

DIVISION 1- GENERAL REQUIREMENTS

DIVISION 1- GENERAL REQUIREMENTS DIVISION 1- GENERAL REQUIREMENTS This division contains the following elements: 1.1 General 1.2 Summary of Work 1.3 Administration 1.4 Quality 1.5 Temporary Facilities 1.6 Products 1.7 Execution 1.8 Closeout

More information

Scope of Work Bid Package C-4 - West Polished Concrete

Scope of Work Bid Package C-4 - West Polished Concrete Scope of Work Bid Package C-4 - West Polished Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,

More information

ANTELOPE VALLEY COLLEGE PALMDALE AIRPORT TERMINAL REMODEL

ANTELOPE VALLEY COLLEGE PALMDALE AIRPORT TERMINAL REMODEL PALMDALE AIRPORT TERMINAL REMODEL 21000 20 TH STREET EAST, PALMDALE, CA 93550 for ANTELOPE VALLEY COMMUNITY COLLEGE DISTRICT 3041 WEST AVENUE K LANCASTER, CALIFORNIA 93536-5436 PROJECT MANUAL AUGUST 15,

More information

Facilities Planning and Construction (FP&C)

Facilities Planning and Construction (FP&C) Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:

More information

Façade Access Upgrade Project

Façade Access Upgrade Project University of California Hastings College of Law Façade Access Upgrade Project 200 McAllister Street, San Francisco, CA 94102 Project Number 12042.04 ITB #56-0160 (Revised) August 20, 2015 PROJECT MANUAL

More information

DIVISION 10 - SPECIALTIES Toilet, Bath, and Laundry Accessories Fire Extinguishers

DIVISION 10 - SPECIALTIES Toilet, Bath, and Laundry Accessories Fire Extinguishers DIVISION 01 GENERAL REQUIREMENTS 012500 Substitution Procedures 012600 Contract Modification Procedures 013100 Project Management and Coordination 013150 Requests for Information 013200 Construction Progress

More information

SECTION SUBSTITUTION PROCEDURES

SECTION SUBSTITUTION PROCEDURES SECTION 01 25 00 SECTION 01 25 00 PART ONE: GENERAL 1.1 Related Documents 1.1.2 Construction Documents and general provisions of the Agreement Between Owner and Construction Manager and consultant and

More information

Student Services & Classroom Addition

Student Services & Classroom Addition SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for quality assurance and quality control. B. Testing and inspecting services

More information