INTERNATIONAL SEMINAR LONG TUNNELS

Size: px
Start display at page:

Download "INTERNATIONAL SEMINAR LONG TUNNELS"

Transcription

1 INTERNATIONAL SEMINAR LONG TUNNELS Desafío para el Diseño, Construcción y Operación Challenges for Design, Construction and Operation Construction of long road s in Norway including the Lærdal Chief Scientist Professor Eivind Grøv SINTEF/NTNU and SKAVA when in Chile Past President Norwegian Tunnelling Society Past Vice President ITA 17, 18 y 19 de Octubre 2012 Santiago, Chile PIARC CHILE

2 Construction of long road s in Norway Long traffic s in Norway 3 of the 10 longest road s in the world are in Norway 30 (++) road s are longer than 5 km Appr. 10 of these are subsea s Appr. 5 are longer than 10km 2 railway s are longer than 10 km, dating back to the nineties and the seventies Plans are under preparation for Follo-Ski 2 x 20 km rail way s Rogfast 2 x 25 km sub sea road to -390 Ryfast 2 x 14,3km sub sea

3 Construction of long road s in Norway Motivation for our study: How to better plan the physical construction of long s Tunnelling, short or long s is basically a matter of logistics It is the master minding of careful and intelligent logistics and planning Often this is the contractors competitive edge Having reached that recognition does it really matter whether the is 5 or 25 km long? The challenge is: how to achieve an industrial production process when there is one access for all works to be done. Is it relevant to leave the solely to complete excavation works?

4 Construction of long road s in Norway Key-issues to be focused during construction: Health and safety aspects Ventilation Mucking out/transportation Initial support become permanent support Time schedule How to improve these aspects? Problem defined as; limited access & confined space

5 Project Type of project Tunnel length Construction of long road s in Norway Overburde n Tunnel width Number of exits/entran ces Number of working faces Maximum length of face Constructio n time (mobilisatio n to opening of the s) Lærdal Road Folgefo nn Road Bømlafj ord Sub sea road Eiksun d Subsea road Atlanterh avs Subsea road Frøya Subsea road Korgfjel let Road Steigen Romerikspo rten Oslofj ord Road Railway Subsea road Gudvang en Road 24.5 km 11 km 7.9 km km km 5.3 km km m km m km 1400 m >800 m rock cover for 20 km 9 m (dual lane, single tube) adit 8 m (dual lane, single tube) 262 meter below sea level, min. 35 m rock cover 11 m (triple lanes single tube) 287 meter below sea level Partly 11.5 m and partly 9.5 m (single tube, 2/3 lanes) 245 m below sea level. Approxima tely 40 m rock cover 11 m (single tube, mostly three lanes) 164 m below sea level. Rock cover m. 8 m (single tube, two lanes) 10 to 250 m 134 m below sea level (min. 32 m rock cover) 8 m 7 m 11 m 11 m (three lanes) adits adit Approx. 9 km July 1995 Novemb er 2000 Approx. 6 km May 1997 May 2001 Approx. 4 km Septemb er Decembe r 2001 Approx. 5 km February 2003 February 2008 Approx. 3 km. August 2006 spring 2009 (planned) Approx. 8 m 2.6 km 4.5 km 4.3 km 3.6 km 3 km 6 km January June 2000 October 2001 Septemb er August August 1999 April June Opened in December 1991

6 Construction of long road s in Norway Project Lingvang Breidal Tyin Svea Dividalen Troll Langevann, IVAR Type of project Water transfer Water transfer Headrace Coal transport Access to radar site Subsea pipeline Water transfer Tunnel length 8.9 km 10 km 11,3 km 5.7 km 9.8 km 7.5 km 7.8 km Tunnel width 5 m 5 m 7 m 3.6 m (18 m 2 ) m (25 m 2 ) (20 m 2 ) m Overburden Approximately 600 m Up to 1000 m rock cover. Up to 600 m (half of is below a glacier) 180 m below sea level (7m piercing) Number of exits/entrances Number of working faces Maximum length of face adit 1 1 (+ 1 adit for air and dump site) adit (?) (?) 8.9 km 5 km 4.4 km 5.7 km 9.8 km 3.6 km 4 km (?) Tunnelling method Construction time (mobilisation to opening of the s) Notes Drill & blast Drill & blast Drill & blast Drill & blast Drill & blast Drill & blast October 2001 September 2003 November 2002 December 2003 Started in permafrost September 1990 September m height difference or 1 : 7 uphill October 1991 January 1996 Lowest level 240 m below sea level Drill & blast April1997 November 2002

7 Construction of long road s in Norway A crucial parameter when it comes to long s, large cross sections width > 8m: Room for efficient loading, transportation and mucking out, no need for niches Sufficient ventilation and large size vent ducts, two way Multitasking in terms of several activities taking place simultaneously as the face is progressing Whilst small cross sections: Lack of room makes the entire logistic exercise difficult

8 Construction of long road s in Norway Norwegian contract practice On one hand: The Owner carries the risk for the ground conditions The Owner is responsible for the collection of information on ground conditions. All information is disclosed to the tendering contractors for their own interpretation. The Owner provides his interpretation of the situation in terms of estimates on quantities on rock support, grouting etc. Whilst: The Contractor carries the risk for the appropriate and efficient handling of the works and focus on improving his technical and organizational performance. The contracts include regulations for extension of construction time based on actually performed quantities, Standard capacities, or equivalent time system.

9 Construction of long road s in Norway Risk sharing principle

10 Construction of long road s in Norway Project references

11 Construction of long road s in Norway The Lærdal, - the longest road in the world, and open for general public traffic

12 Construction of long road s in Norway Implemented in the Lærdal Tunnel Rock Crystals Zhongnanshan Tunnel, China, The worlds longest twin tube : 18 km

13 Construction of long road s in Norway Sectional completion-lærdal Most of the permanent rock support was installed at or close to the face. The lower part of the road embankment was replaced every week to be able to have an appropriate transport surface. Work was going on continuously with the construction of the ditch and with the installation of drainage pipes, cable canals and cables. Twice a year the permanent road embankment was established in addition to the first layer of asphalt. This was the permanent road construction, but approval was granted for use in the construction period.

14 Construction of long road s in Norway Entrance to the 11 km long Folgefonn

15 Construction of long road s in Norway Sectional completion - Folgefonn Blast and excavate the and the ditch simultaneously. Install all permanent rock support at the face, or at least before the installation of the ventilation duct. Install all equipment in the ditch in sections of m. Utilize the excavated rock as road embankment. A temporary asphalt layer to be laid allowing transport to take place on a covered surface. Installation works, except rock support, were not allowed to take place closer than 400m from the face.

16 Construction of long road s in Norway The Bømlafjord sub-sea south of Bergen 7,9 km long sub sea Reaches to - 240m At the steepest inclined 8,5% One contractor at each side

17 Construction of long road s in Norway Sectional completion - Bømlafjord subsea The contractor completed sections with length of approximately 1000 m. Due to the poor quality of the rock all blasted rock needed to be replaced, and the sectional completion included a complete re-establishing of the road embankment. The completion included rock support, ditches, drain pipes, man holes, cable canals and electrical/fiber-optic cables. The completion included also a first layer of asphalt.

18 Construction of long road s in Norway Bømlafjord, - disadvantages of not using sectional completion experienced by the second contractor A permanent sand filter facility had to be established outside the to clean drainage water due to large production of fines. The material in the road embankment of the temporary road in the was crushed due to the load from the heavy traffic. Additional ventilation fans due to large amounts of dust and exhaust air. Dirty working conditions affected negatively the Health and Safety aspects in the. Frequent local replacement of road embankment to maintain construction traffic.

19 Construction of long road s in Norway The feedback from owners and contractors: Significant challenge to the contractor in planning his works Increased manning and demand on equipment Improved Health&Safety during construction Owners report time savings Reduced cleaning of interior Contractors valued aspects related to transport and hauling, increased efficiency, reduced maintenance on equipment and tear & wear Everyday production increased The contract has to address specific instructions, time and incentives

20 Construction of long road s in Norway Time is money in the ling industry! Potential advance rate (good fair rock conditions, easy or no pregrouting, min. support): 4,8 m net penetration per round, 2 rounds per day, 6 days per week: 58 m/week High intensity pre-grouting, increased support: 2 rounds per every 2 nd day: 29 m/week Very poor rock: 1 round per day, net penetration 2,5 m: 15 m/week Projects have had up to 175m/week with drilll&blast Various comparisons done suggest a factor from 3-10 more cost efficient ling in Norway! Lærdals appr. 8.2 mill Euro per km Romeriksporten railway appr. 16 mill Euro per km One needs to ask WHY!!!

21 Construction of long road s in Norway Aspects to be focused during construction High capacity equipment, multi-skilled workmen at the ling face allowing high utilisation of the equipment. Adaptability to the actual ground conditions, careful following-up of the encountered rock mass by mapping and classification for a best fit of rock support measures. Observation of the ground behaviour by visual surveying and physical measurements if required fulfilling the intentions of the Observational method. Installation of permanent rock support as close to the face as practically possible fulfilling the criteria for permanent support work.

22 Construction of long road s in Norway Unique Co-operation at the site Constructive cooperation between the representatives of the involved parties. Experienced professionals participating in the decision making. Solve conflicts at construction site by negotiation after the technical issues have been settled.

23 Construction of long road s in Norway Hard rock environment The Scandinavian host rock varies from poor to extremely good rock. Folding, faulting and high tectonic stresses influence the quality of the rock Weakness zones can exhibit great variation in quality, Q-values may vary from extremely poor to good The width of such zones may vary from a few centimeters to tens of meters Permeability may vary significantly The CHALLENGE: to deal with frequently changing ground conditions It is typical Hard Rock not necessarily Good Rock

24 Construction of long road s in Norway Conclusions! Take care of your logistics! All parties benefit from a reduced construction period! Sectional completion is a way to secure this goal for long construction Sustainability and CO2 emission are issues to keep in mind also The ultimate goal of our efforts: Reduce the construction time on overall, not sub optimize single activities Thank you for your kind attention!

25

D&B versus TBM some case stories

D&B versus TBM some case stories D&B versus TBM some case stories TBM Applications II Bergen, June 6 th and 7 th Project Manager Anne Kathrine Kalager Case stories Two different Projects Considerations regarding excavation method: New

More information

The Stendafjellet Rock Quarry and Underground Waste Disposal site

The Stendafjellet Rock Quarry and Underground Waste Disposal site The Stendafjellet Rock Quarry and Underground Waste Disposal site Frode Siljeholm Arnesen, MSc. Senior Engineering Geologist Multiconsult ASA, Bergen, Norway Stendafjellet Rock Quarry and Underground Waste

More information

MTR Shatin to Central Link Contract 1103 Hin Keng to Diamond Hill Tunnels Hong Kong, China

MTR Shatin to Central Link Contract 1103 Hin Keng to Diamond Hill Tunnels Hong Kong, China MTR Shatin to Central Link Contract 1103 Hin Keng to Diamond Hill Tunnels Hong Kong, China Project Director, VINCI Construction Grands Projets Shatin to Central Link Phases 1 & 2 SCL 1103 Shatin to Central

More information

Vest Process Propane Cavern Project, Norway

Vest Process Propane Cavern Project, Norway Vest Process Propane Cavern Project, Norway Fig 1: The rock cavern for propane storage. To meet the increasing demands for propane storage volume at the Mongstad reffinery plant, an additional underground

More information

How to achieve faster drifting in mining, some aspects. SME Denver February 2007 Gunnar Nord Atlas Copco Rock Drill AB Sweden

How to achieve faster drifting in mining, some aspects. SME Denver February 2007 Gunnar Nord Atlas Copco Rock Drill AB Sweden How to achieve faster drifting in mining, some aspects SME Denver February 2007 Gunnar Nord Atlas Copco Rock Drill AB Sweden Comparison of objectives Objectives for the tunnel builder To make the tunnel

More information

The project. The Follo Line Project is currently the largest transport

The project. The Follo Line Project is currently the largest transport The project 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111

More information

Semmering Base Tunnel Large Caverns in Challenging Conditions

Semmering Base Tunnel Large Caverns in Challenging Conditions Semmering Base Tunnel Large Caverns in Challenging Conditions M. Proprenter ic consulenten ZT GesmbH, Vienna, Austria. O. K. Wagner ÖBB - Austrian Federal Railways, Graz, Austria. ABSTRACT: Semmering Base

More information

Internal report no. 2217

Internal report no. 2217 Internal report no. 2217 Sub project H: Technical installations Particle Cleaning in Norwegian Road Tunnels Summary: Norway s road network has become more and more dependent on tunnels. The challenge of

More information

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan West Rail Tsing Kwai Tunnel Location of major Tunnel Portal West Rail Tsing Kwai Tunnel Construction Features -

More information

MODERN PRE-INJECTIONS IN UNDERGROUND CONSTRUCTION WITH MICROCEMENTS AND LIQUID COLLOIDAL SILICA FOR WATER INGRESS REDUCTION AND GROUND IMPROVEMENT

MODERN PRE-INJECTIONS IN UNDERGROUND CONSTRUCTION WITH MICROCEMENTS AND LIQUID COLLOIDAL SILICA FOR WATER INGRESS REDUCTION AND GROUND IMPROVEMENT MODERN PRE-INJECTIONS IN UNDERGROUND CONSTRUCTION WITH MICROCEMENTS AND LIQUID COLLOIDAL SILICA FOR WATER INGRESS REDUCTION AND GROUND IMPROVEMENT Karl Gunnar Holter M.Sc. Engineering Geology Technical

More information

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES SEMMERING BASE TUNNEL LOGISTIC CHALLENGES Dipl.-Ing. Michael Proprenter ic consulenten ZT GmbH Vienna, Austria Mail: m.proprenter@ic-group.org Dipl.-Ing. Oliver K. Wagner ÖBB - Austrian Federal Railways

More information

TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck. Gerhard HARER

TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck. Gerhard HARER TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck Gerhard HARER 2 Project overview Koralm railway Part of the Baltic-Adriatic Core Network Corridor, which is one of the most

More information

SPECIAL PROVISION Description of Project, Scope of Contract, and Sequence of Work

SPECIAL PROVISION Description of Project, Scope of Contract, and Sequence of Work 2004 Specifications CSJ: 0932-01-076 SPECIAL PROVISION Description of Project, Scope of Contract, and Sequence of Work 1.0 Description of Project 1.1. General. This project provides for the widening of

More information

SECTION EXCAVATION AND FILL

SECTION EXCAVATION AND FILL SECTION 02315 EXCAVATION AND FILL PART 1 GENERAL 1.01 SUMMARY A. Furnish labor, materials, equipment, and incidentals necessary to perform excavation, backfill, grading, and slope protection required to

More information

Passage under Lövstavägen at Bypass Stockholm From Design to Realization

Passage under Lövstavägen at Bypass Stockholm From Design to Realization Passage under Lövstavägen at Bypass Stockholm From Design to Realization Roslin Mattias 1, Borio Luca 2 and Tomas Hellström 3 1 Swedish Transport Administration, Solna Strandväg 98, 171 54 Solna, mattias.roslin@trafikverket.se

More information

THE GROUNDBREAKING TUNNEL

THE GROUNDBREAKING TUNNEL Gotthard Base Tunnel, Switzerland Allplan Engineering in practice THE GROUNDBREAKING TUNNEL In Amsteg, where two adits meet two tunnel tubes, the 3D model created with Allplan Engineering was very useful

More information

Pump storage hydro power plant (PSKW) Reißeck

Pump storage hydro power plant (PSKW) Reißeck Roland Schorn Short description The new pump storage power plant (PSKW) Reißeck II represents an expansion of the already existing group of power plants, Malta and Reißeck/Kreuzeck in Carinthia. The new

More information

SELECTION OF CONSTRUCTION METHODS IN ROCK TUNNELING

SELECTION OF CONSTRUCTION METHODS IN ROCK TUNNELING SELECTION OF CONSTRUCTION METHODS IN ROCK TUNNELING Dipl. Ing. Josef Daller ic consulenten ZT GmbH Vienna, Austria Mail: j.daller@ic-group.org Abstract For construction of long infrastructure tunnels in

More information

Peter J Tarkoy, PhD, Geotechnical and Construction Consultant

Peter J Tarkoy, PhD, Geotechnical and Construction Consultant T he technology developed for the boring of declines, first employed in coal mine applications, has been transferred to allow the boring of penstock declines for hydropower schemes. In recent years, the

More information

Challenges in designing a complex urban tunnel in Tehran metropolitan (Arash-Esfandiar-Niayesh) Islamic Republic of Iran

Challenges in designing a complex urban tunnel in Tehran metropolitan (Arash-Esfandiar-Niayesh) Islamic Republic of Iran Challenges in designing a complex urban tunnel in Tehran metropolitan (Arash-Esfandiar-Niayesh) Islamic Republic of Iran Presented by : Majid Sadeghi, Project Manager Aliakbar Golshani, Project Consultant

More information

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations.

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 1.0 PURPOSE To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 2.0 BACKGROUND Excavation activities are highly dangerous and thus require adequate planning

More information

Annex V Concrete Structures Removal Plan

Annex V Concrete Structures Removal Plan Appendix D Annex V Concrete Structures Removal Plan Figure V1 Lower Granite Sequences of Concrete Removal and Cofferdam Figure V2 Little Goose Sequence of Concrete Removal and Cofferdam Figure V3 Lower

More information

The government of the SOCIALIST REPUBLIC OF VIETNAM HO CHI MINH CITY PEOPLE S S COMMITTEE TUNNEL JAPAN. Official Development Assistance

The government of the SOCIALIST REPUBLIC OF VIETNAM HO CHI MINH CITY PEOPLE S S COMMITTEE TUNNEL JAPAN. Official Development Assistance 0 The government of the SOCIALIST REPUBLIC OF VIETNAM HO CHI MINH CITY PEOPLE S S COMMITTEE TUNNEL JAPAN Official Development Assistance 1 TUNNEL Sub-Sector (Civil) IMAGE OF TUNNEL ENTRANCE 2 Traffic in

More information

SUB-SLAB DIAGNOSTICS

SUB-SLAB DIAGNOSTICS SUB-SLAB DIAGNOSTICS John W. Anderson, Jr. Quality conservation Spokane, WA ABSTRACT Sub-slab diagnostics have eluded most radon contractors because 90% of installed systems work OK. the contractors are

More information

The Drainage Basin. From Peaks of Colorado to Mexico 1,400 miles Drains 242,000 square miles of Western US Colored River because of sediments

The Drainage Basin. From Peaks of Colorado to Mexico 1,400 miles Drains 242,000 square miles of Western US Colored River because of sediments HOOVER DAM Need arose to control the Colorado River flow and the cycles of flood and drought. Responsibility fell on the Department of the Interior s Bureau of Reclamation Colorado River Compact History

More information

BRILLIANT EXPANSION PROJECT

BRILLIANT EXPANSION PROJECT BRILLIANT EXPANSION PROJECT Utilizes power tunnel 120 MW Capacity 500 GWh Energy Transmission link to Brilliant Terminal Station Will reduce TGP downstream Intake Transmission Link Transmission Link Extent

More information

FAST-Tunn Future Advanced Steel Technology for Tunnelling

FAST-Tunn Future Advanced Steel Technology for Tunnelling FAST-Tunn Future Advanced Steel Technology for Tunnelling Chief scientist/professor Eivind Grøv, SINTEF/ NTNU Project manager FAST-Tunn Background Innovative idea The aim is to increase cutter life by

More information

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

SECTION IV. PIPELINE EXCAVATION AND BACKFILL SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include

More information

Stack Parking Surface Mounted Stackers

Stack Parking Surface Mounted Stackers 1 / 6 Stack Parking Surface Mounted Stackers swiss-park V-2 Comfort The V-2 is designed to park cars of any size thanks to its vertical adjustability. It will accommodate cars as tall as the garage ceiling

More information

Construction Specification for General Excavation

Construction Specification for General Excavation Engineering & Construction Services Division Standard Specifications for Road Works TS 2.10 September 2018 for General Excavation Table of Contents TS 2.10.01 SCOPE... 2 TS 2.10.02 REFERENCES... 2 TS 2.10.03

More information

Tunnel. Immersed Tunnels

Tunnel. Immersed Tunnels Tunnel Tunnels are underground spaces, usually, in a tubular shape with substantial lengths. They can either be man-made or natural and can be used as passageways, storages, carriageways and utility ducts.

More information

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SCOPE A. This work shall consist of the underground construction of a pipeline across the state right-ofway, or other facility as indicated on the plans and as

More information

UNDERGROUND CHARACTERISATION AND RESEARCH FACILITY ONKALO ANTTI IKONEN, MIA YLÄ-MELLA, TIMO ÄIKÄS POSIVA Oy Olkiluoto, Finland

UNDERGROUND CHARACTERISATION AND RESEARCH FACILITY ONKALO ANTTI IKONEN, MIA YLÄ-MELLA, TIMO ÄIKÄS POSIVA Oy Olkiluoto, Finland UNDERGROUND CHARACTERISATION AND RESEARCH FACILITY ONKALO ANTTI IKONEN, MIA YLÄ-MELLA, TIMO ÄIKÄS POSIVA Oy 27160 Olkiluoto, Finland 1. Introduction ABSTRACT Posiva s repository for geological disposal

More information

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected. Microtunnelling Building infrastructures and power supply systems underground, while life above continues unaffected. 2 Comprehensive Microtunnelling Solutions A reliably functioning infrastructure which

More information

D-Raintank. Forward-Looking Rainwater Drainage. Collecting Drainage Saving

D-Raintank. Forward-Looking Rainwater Drainage. Collecting Drainage Saving D-Raintank Forward-Looking Rainwater Drainage Collecting Drainage Saving The D-Raintank effectively solves the problem of local drainage of rainwater! Illustration of the trend of area requirement in Germany

More information

Asphalt on Concrete Base with Waterproofing Membrane

Asphalt on Concrete Base with Waterproofing Membrane CABLES CANNOT BE IN DIRECT CONTACT WITH THE WATERPROOFING MEMBRANE! CABLES WILL BURNOUT, AND THE MEMBRANE WILL MELT. 7 5 4 6 1 2 3 NOTES: 1) CLEAN CONCRETE SURFACE 2) HOT MEMBRANE WATERPROOFING 3) ASPHALTIC

More information

Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China

Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China Qing-Long Cui, Ph.D. student Co-authors: Ye-Shuang Xu, Shui-Long Shen*, Huai-Na

More information

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS Dipl.-Wirt.Ing. Oliver Freudenreich Friedr. Ischebeck GmbH phone: ++49 2333 8305-0 Loher Str. 31 79 fax: ++49 2333 8305-55 e-mail: freudenreich@ischebeck.de D-58256 Ennepetal www.ischebeck.com INNOVATIVE

More information

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS CS-2-01. GENERAL: Trench excavation shall conform with the City Standard Specifications. In general a trench is defined as an excavation in which

More information

Underground Waste Depositing at Odda, Norway

Underground Waste Depositing at Odda, Norway Underground Waste Depositing at Odda, Norway Anne Hommefoss, MSc. Engineering Geologist Multiconsult ASA, Oslo, Norway Underground Waste Depositing at Odda Anne Hommefoss Stakeholders Owner: Boliden Odda

More information

Global Leaders in Tunnel Ventilation

Global Leaders in Tunnel Ventilation Global Leaders in Tunnel Ventilation Fläkt Woods - The Group Leaders in Air Movement Fläkt Woods is the industry leader in air movement technology, providing innovative solutions worldwide. Our extensive

More information

SECTION GENERAL EXCAVATION

SECTION GENERAL EXCAVATION 02210-1 of 11 SECTION 02210 GENERAL EXCAVATION 02210.01 GENERAL A. Description 1. General excavation shall include but not necessarily be limited to, excavation and grading for general site work, roadways,

More information

Appendix 15 Estimated costs of dams

Appendix 15 Estimated costs of dams Appendix 15 Estimated costs of dams September 2014 Brown Hill Keswick Creek Stormwater Management Plan Part B Report Earth Dam Site 1 BROWN HILL CREEK DAM COST ESTIMATE FOR EARTH DAM ( OPTION 1) AT SITE

More information

Loss Control TIPS Technical Information Paper Series

Loss Control TIPS Technical Information Paper Series Loss Control TIPS Technical Information Paper Series Innovative Safety and Health Solutions SM Understanding Subsidence Subsidence of the land, which is defined as the loss of surface elevation due to

More information

Bridge Life Cycle Optimisation

Bridge Life Cycle Optimisation Closing Seminar 14-15 May, 2012 Malmö LIFE CYCLE COST CALCULATION OF CONCRETE BRIDGE DECK SURFACE STRUCTURES M. Sc. Sami Noponen 1 In the life cycle cost analysis The essential data is The investment cost

More information

Design of Izmir Bay Crossing Bridge

Design of Izmir Bay Crossing Bridge Design of Izmir Bay Crossing Bridge Burak Kurtman Dpt. Manager of Bridge Group, Yüksel Project International, Ankara, Turkey Tel: +90 (312) 4957000 E-mail: bkurtman@yukselproje.com.tr Abstract The Izmir

More information

Figure Inlet protection (Source: Minnesota DOT)

Figure Inlet protection (Source: Minnesota DOT) 3.9 INLET PROTECTION Figure 3.14. Inlet protection (Source: Minnesota DOT) Overview Description: A manufactured protective device or barrier used to trap sediment at a storm drain surface or curb inlet.

More information

ArmorFlex. Articulating Concrete Block Revetment System

ArmorFlex. Articulating Concrete Block Revetment System ArmorFlex Articulating Concrete Block Revetment System ArmorFlex ASTM-validated system lets you design with confidence ArmorFlex is in a class by itself. Developed for high-scour, high-flow applications,

More information

CONSTRUCTION MANUAL 2.5 x 5 UNITS

CONSTRUCTION MANUAL 2.5 x 5 UNITS CONSTRUCTION MANUAL 2.5 x 5 UNITS www.neelco.com 8328-D Traford Lane, Springfield, VA 22152 703 913 7858 T-WALL Retaining Wall System CONSTRUCTION Manual Contents Part I earthwork... 1 The Structure depends

More information

The Follo Line Project METHOD DEVELOPMENT: TOWARDS A MORE SUSTAINABLE RAILWAY

The Follo Line Project METHOD DEVELOPMENT: TOWARDS A MORE SUSTAINABLE RAILWAY The Follo Line Project METHOD DEVELOPMENT: TOWARDS A MORE SUSTAINABLE RAILWAY 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111

More information

JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018

JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018 JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018 On Maintenance of Traffic Details Sheet No. 46 there is a note that states I-49 Stage Construction is to be Completed Prior to Beginning Work on Hwy.

More information

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project South Coast Water District Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project Board of Directors January 14-15, 2013 Overview of Construction Plan Highlights of Kiewit s Construction

More information

Project: King Abdulaziz International Airport KAIA 2

Project: King Abdulaziz International Airport KAIA 2 Project: King Abdulaziz International Airport KAIA 2 Jeddah, KSA King Abdulaziz International Airport Phase 1 Development Project Project Newsletter Client / Owner: Saudi Binladin Group 30 November 2013.

More information

CROSSRAIL INFORMATION PAPER D24 TUNNELLING DURATION AND CONSTRUCTION STRATEGY

CROSSRAIL INFORMATION PAPER D24 TUNNELLING DURATION AND CONSTRUCTION STRATEGY CROSSRAIL INFORMATION PAPER TUNNELLING DURATION AND CONSTRUCTION STRATEGY This paper sets out the proposed Crossrail tunnel construction strategy and duration. It will be of particular relevance to those

More information

Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways

Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways Hong Kong Section of the Guangzhou-Shenzhen-Hong Kong Express Rail Link Supplementary Information In the meeting of the

More information

ENVIRONMENTAL MANAGEMENT PLAN FOR DALPATPUR STONE QUARRY AT VILLAGE DALPUTPUR TEHSIL KHURAI AND DISTRICT SAGAR [MP], AREA (0.

ENVIRONMENTAL MANAGEMENT PLAN FOR DALPATPUR STONE QUARRY AT VILLAGE DALPUTPUR TEHSIL KHURAI AND DISTRICT SAGAR [MP], AREA (0. ENVIRONMENTAL MANAGEMENT PLAN FOR DALPATPUR STONE QUARRY AT VILLAGE DALPUTPUR TEHSIL KHURAI AND DISTRICT SAGAR [MP], AREA (0.920ha) 1.1 Introduction The subject quarry is proposed for metal stone on 0.920

More information

Figure (12.1) Foundation Grouting

Figure (12.1) Foundation Grouting Chapter 12 - Foundation Grouting 12. Foundation Grouting 12.1. Introduction: The construction of structures on weak ground often requires the soil to be improved in order to ensure the safety and the stability

More information

ILC ASIAN DRAFT SCHEDULE

ILC ASIAN DRAFT SCHEDULE ILC ASIAN DRAFT SCHEDULE K Foraz, M Gastal & J Osborne Many thanks to all contributors Objectives and scope To provide a target baseline construction schedule for the 2 Asian sample sites Address remarks

More information

406 - PIPE SEWERS - MTC FORM 406

406 - PIPE SEWERS - MTC FORM 406 406 - - MTC FORM 406 INDEX 406.1 GENERAL Types of Pipe Pipe Strength, Rigid Pipes Polyethylene Pipe Strength - Rigid or Flexible Pipe Strength and Treatment, Flexible Pipes Selection of Type, Strength

More information

maximum mobility, easy operation.

maximum mobility, easy operation. EN get started RM 70GO! 2.0 compact crushing maximum mobility, easy operation. 2.0 70GO! EN starting out COMPACT DESIGN, MAXIMUM OUTPUT With the RM 70GO! 2.0 high-performance crusher RUBBLE MASTER presents

More information

PRELIMINARY VENTILATION AND COOLING DURING THE CONSTRUCTION OF THE BRENNER BASE TUNNEL

PRELIMINARY VENTILATION AND COOLING DURING THE CONSTRUCTION OF THE BRENNER BASE TUNNEL - 29 - PRELIMINARY VENTILATION AND COOLING DURING THE CONSTRUCTION OF THE BRENNER BASE TUNNEL A. Busslinger (*), R. Insam (**) (*) HBI Haerter AG, Switzerland (**) BBT SE, Austria ABSTRACT With a length

More information

TUNNEL CONSTRUCTION GUIDELINES 05 - GUIDANCE NOTE ON PRE-EXCAVATION GROUTING FOR

TUNNEL CONSTRUCTION GUIDELINES 05 - GUIDANCE NOTE ON PRE-EXCAVATION GROUTING FOR TUNNEL CONSTRUCTION GUIDELINES 05 - GUIDANCE NOTE ON PRE-EXCAVATION GROUTING FOR UNDERGROUND CONSTRUCTION IN HARD ROCK PRINCIPLES & DESIGN ELEMENTS INTRODUCTION In underground hard rock construction, ground

More information

SECTION EARTHWORK

SECTION EARTHWORK SECTION 310000 PART 1 GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and perform all excavation, backfill, fill and grading required to complete the work

More information

SECTION 303 CULVERTS

SECTION 303 CULVERTS 303.01 Scope - This section covers the construction of pipe culverts. 303.01.01 Definitions for the purposes of this section, the following general terms are defined as follows: a) Backfilling means the

More information

100% Payment. 105% Payment #

100% Payment. 105% Payment # CRUSHED AND STOCKPILED GRAVEL ROAD SURFACING AGGREGATE (3-17-2017) Please delete the first two pages of this document (the user note) prior to putting the spec into a contract Specification User Note:

More information

Select Subgrade Material, Compacted

Select Subgrade Material, Compacted 314.1 GENERAL B314 SHOULDER, SELECTED SUBGRADE, AND STOCKPILING OPSS.PROV 314 Granular materials meeting the requirements of OPSS.PROV 1010 are obtained from pits and quarries, and recycled materials.

More information

rapid tunnelling thanks to efficient SePArAtion. Low-impact mechanized tunnelling: Integrated solutions.

rapid tunnelling thanks to efficient SePArAtion. Low-impact mechanized tunnelling: Integrated solutions. herrenknecht AG utility tunnelling Traffic tunnelling SEPARATION PLANTS HERRENKNECHT SEPARATION PLANTS KEEP IT FLOWING. RAPID TUNNELLING THANKS TO EFFICIENT SEPARATION. Low-impact mechanized tunnelling:

More information

An alternative mining method at the Kvannevann Mine, northern Norway

An alternative mining method at the Kvannevann Mine, northern Norway Caving 2010 Y. Potvin (ed) 2010 Australian Centre for Geomechanics, Perth, ISBN 978-0-9806154-1-8 https://papers.acg.uwa.edu.au/p/1002_17_naevermosand/ An alternative mining method at the Kvannevann Mine,

More information

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Electrical Work. NOV Embankments Over Swamps and Compressible Soils GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification

More information

APPLICATION FOR PIPE OR WIRE OCCUPANCY

APPLICATION FOR PIPE OR WIRE OCCUPANCY APPLICATION FOR PIPE OR WIRE OCCUPANCY Please answer all questions and direct cover letter / project description, completed application, application fee, and three (3) copies of project plans to: AECOM

More information

Crushing Optimizing the Process

Crushing Optimizing the Process Crushing Optimizing the Process Optimizing the Process Methods to combine and simulate technical and economic performance Optimum crushing plant performance is difficult to achieve due the process characteristics.

More information

2019 Semester Terms and Dates Summary

2019 Semester Terms and Dates Summary 2019 Semester Terms and Dates Summary Term Code Term Description Semester Start Date Census Date End of Semester Assessments Due Results Published 1905 Semester 1, 2019 04-03-19 31-03-19 28-06-19 As per

More information

BASE CONSTRUCTION MATERIALS A Aggregate

BASE CONSTRUCTION MATERIALS A Aggregate BASE CONSTRUCTION 2211 AGGREGATE BASE 2211.1 DESCRIPTION This work consists of placing aggregate base. 2211.2 MATERIALS A Aggregate... 3138 Provide the class of aggregate as required by the contract. 2211.3

More information

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics HEKAPLAST PE-HD twin wall cable ducts and cable protection pipes for underground installation HEGLER HEKAPLAST III/ HEKAPLAST: Twin wall cable ducts or cable protection pipes to DIN 696, manufactured from

More information

Section 02 SUBSTRUCTURE

Section 02 SUBSTRUCTURE 02 Section 02 SUBSTRUCTURE 1. Trenches to be level, square and free from loose material and standing water. Steps and sides of foundations must be plumb. 2. All tree roots must be removed. Trench depths

More information

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations.

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations. SPEC-1100 1/9 1.0 PURPOSE This specification describes the minimum requirements for general grading, excavation of earth, rock and solid slag, embankment construction, ditching, use of explosives, and

More information

2.1.4 PROJECT CONSTRUCTION

2.1.4 PROJECT CONSTRUCTION Alignment 2C Alignment 2C is the preferred alternative. The new 36-inch force mains would follow the existing alignment along the existing utility road within the OCSD easement from the Bitter Point Pump

More information

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5B Access Tracks, Hardstanding Areas, Electrical Compounds, Borrow Pit And Cable Laying Construction Method Statement Copyright ESB International

More information

BIRCOsir. Installation Instructions. A number of details must be observed when installing BIRCOsir. For a comprehensive description please read here.

BIRCOsir. Installation Instructions. A number of details must be observed when installing BIRCOsir. For a comprehensive description please read here. Page 54 Installation Instructions A number of details must be observed when installing. For a comprehensive description please read here. To guarantee smooth operation and compliance with the requirements

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

The Aizhai Suspension Bridge is

The Aizhai Suspension Bridge is INTERNATIONAL DESIGN & CONSTRUCTION: BRIDGES Mountain grown Hilly terrain contributes mightily to China bridge By Yinbo Liu, Ph.D., P.E., Guoping Chen, Shulong He and Yongjian Zhang, Ph.D. Contributing

More information

Installation Guidelines

Installation Guidelines 815 NE 172 nd Avenue Vancouver, WA 98684 877-694-0141 Installation Guidelines Installation steps include job planning, layout, excavating and preparing the soil subgrade, applying geotextiles (optional),

More information

Redi Rock Specification and Installation Manual

Redi Rock Specification and Installation Manual Redi Rock Specification and Installation Manual 1.0 General Scope This Specification covers the Design, Materials and Installation of Redi Rock modular block Retaining and Freestanding Wall systems as

More information

1 HB By Representative Greer. 4 RFD: Transportation, Utilities and Infrastructure. 5 First Read: 03-MAR-15. Page 0

1 HB By Representative Greer. 4 RFD: Transportation, Utilities and Infrastructure. 5 First Read: 03-MAR-15. Page 0 1 HB62 2 164367-2 3 By Representative Greer 4 RFD: Transportation, Utilities and Infrastructure 5 First Read: 03-MAR-15 Page 0 1 2 ENROLLED, An Act, 3 To amend Section 37-15-2 of the Code of Alabama 4

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG

DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG Meeting September 5 th, 2006 1 Agenda 1. Study Update 2. Construction Staging for Tunneling 3. Other Business 2 Deep Borehole Program 3 Status Update - Engineering

More information

Technical Documentation

Technical Documentation Technical Documentation Underground Container F-Line 1.500L, 3.000L, 5.000L, 7.500L, 10.000L 1. Location 1.1. Position to buildings The excavation space must not be within the minimum distance to buildings,

More information

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006

More information

HUDSON TUNNEL PROJECT

HUDSON TUNNEL PROJECT HUDSON TUNNEL PROJECT NORTH BERGEN COMMUNITY MEETING Lido Restaurant 2600 Tonnelle Avenue North Bergen, NJ January 30, 2018 6:00-8:00 PM Agenda Project Overview Construction Activities in North Bergen

More information

DIFFICULT GROUND SOLUTIONS:

DIFFICULT GROUND SOLUTIONS: Tunnelling April/May 2016 www.tunnellingjournal.com journal The international journal for the tunnelling industry SEE PAGE 6 SEE PAGE 12 SEE PAGE 27 WORLD NEWS MONITOR PROGRESS CUTTER CARE HIGHLIGHTS FROM

More information

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group Best Practices for Building High-Performance Resource Roads Road Drainage Developed by: The Roads and Infrastructure Group THIS GUIDE IS INTENDED FOR EQUIPMENT OPERATORS CONSTRUCTION CONTRACTORS FIELD

More information

New Bridge over Llobregat River

New Bridge over Llobregat River New Bridge over Llobregat River Marcos J. Pantaleón, Roberto Revilla and Patricia Olazábal Apia XXI S.A., Santander, Spain ABSTRACT: Located on the road which communicates the port and the airport of Barcelona,

More information

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 2 SPECIAL BENCHING AND SIDEHILL EMBANKMENT FILLS Geotechnical Bulletin GB2

More information

Tunnel Ventilation System Design and Air Quality. Peter Gehrke and Andrew Purchase

Tunnel Ventilation System Design and Air Quality. Peter Gehrke and Andrew Purchase Tunnel Ventilation System Design and Air Quality Peter Gehrke and Andrew Purchase Summary of Our Input Primarily - how does the choice of in-tunnel criteria and operational strategies affect the system

More information

CHAPTER 3 EXCAVATIONS

CHAPTER 3 EXCAVATIONS 7-3-1 7-3-1 CHAPTER 3 EXCAVATIONS SECTION: 7-3-1: Permit Requirements 7-3-2: Bond Required 7-3-3: Subject and Excluded Excavations 7-3-4: Standards 7-3-5: Protection of Public 7-3-6: Relocation and Protection

More information

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS Section Page 13-1 GENERAL... 13.1 13-1.01 Preservation of Property... 13.1 13-1.02 Overloading, Pavement Protection & Repair... 13.1 13-2 REMOVING EXISTING

More information

B510-5 REMOVAL-PAVEMENT WORK OPSS 510. CDED B Removal CDED B Reclaim Asphalt Pavement

B510-5 REMOVAL-PAVEMENT WORK OPSS 510. CDED B Removal CDED B Reclaim Asphalt Pavement B510-5 OPSS 510 510-5.1 GENERAL This section is for Pavement Work removal tender items. The work covered by these tender items includes the removal and disposal of materials. 510-5.2 REFERENCES CDED B510-0

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 7.4 PERMEATION GROUTING 7.4.1 Definitions 7.4.1.1 Geotechnical Data Report (GDR)

More information

Presentation Outline

Presentation Outline St. John s Tunnel Rehabilitation A Demonstration of Successful Fast- Track Design and Construction Christopher P. Russell, P.E. Shannon & Wilson Inc., Staff Engineer Gregory R. Fischer, Ph.D., P.E. Shannon

More information

Effect of Niche-Tunnel Face Distance and Excavation Time in Tunnel Construction

Effect of Niche-Tunnel Face Distance and Excavation Time in Tunnel Construction Effect of Niche-Tunnel Face Distance and Excavation Time in Tunnel Construction Erion Periku 1 Fan River Hydro Power Project, Aydiner Construction Co., Lezhe, Albania ABSTRACT Estimated time and costs

More information