CMPA Campus Wide Solar Array Installation 2 of 4
|
|
- Clementine Davis
- 6 years ago
- Views:
Transcription
1 Reference 27
2
3 This Campus Master Plan Amendment was adopted by the Board of Regents Facilities and Land Management Committee at the June 2013 Board of Regents meeting and placed on the consent agenda for the full board approval. The Board of Regents denied passage of the amendment due to two main concerns regarding the installation of a solar array on campus: aesthetics and price. Since the June meeting, UAF has worked diligently to address these concerns. Site Consideration UAF considered several other locations and configurations before determining the slope below the Butrovich building as the ideal and only practical location for a 1MWdc photovoltaic installation. The other locations consisted of the following sites: 1) smaller distributed building and roof mounted solar array, 2) the wedge shaped slope below Tanana Loop combined with land near the railroad tracks and agricultural farm with similar solar exposures, and 3) vacant land on the north side of the university. In considering these sites, they were either not cost effective per kwh, required custom engineering at each location to prevent damage to the existing facilities, were physically too far away from the campus power grid connection point, or were deemed swampy and of the wrong aspect for solar collection to be seen as viable options to pursue. The wedge shaped slope directly below the Butrovich Building and the Greenhouse and above Tanana Loop is an ideal location and orientation for the proposed 1MWdc solar array. It has a gentle 10 degree south facing slope that provides unobstructed solar exposure year round. It has been clear of any trees and brush for several decades so uneven settling due to permafrost is unlikely. In addition, UAF has already conducted geotechnical studies and core samples in numerous areas throughout the hill so the soil conditions are well understood. Another benefit of this location is the critical proximity to the campus wide power grid located in the adjacent utilidor that transects this slope. This proximity reduces interconnection costs and line losses for this solar array. The anticipated 4-acre footprint of the 1MWdc solar array can be built and still accommodate the new service access road on the southwest side of the Butrovich Building, a 12 wide ski trail corridor relocation easement along lower fence line and Tanana Loop, and an adequate buffer between the existing terrain park to the east. The hill itself has been the site of several excavations in recent years, has had its ground cover disrupted on numerous occasions, and harbors an invasive weed, bird vetch. During construction of the array, UAF proposes to eradicate the bird vetch and re-vegetate the slope with native ground cover. The end result will be a hillside that provides an energy resource for the university while creating a more uniform and attractive slope. Mandatory grounds maintenance will be provided around the array during the summer to ensure a consistent appearance and proper function of the photovoltaic equipment. Description This site was selected for its large, unobstructed south-facing slope, which provides the ideal location for solar generation. No other site on campus offers an area large enough to contain a solar array of this magnitude. This site is directly above a section of utilidor which will connect generated power from the solar array to the power grid. Aesthetic concerns raised by Board of Regents include potential glare for aircraft and the type of fence surrounding the array. UAF submitted an Obstruction Evaluation Airport Airspace Analysis with the Federal Aviation Administration (FAA) to ensure that the project does not pose a danger to pilots or air traffic control. A formal determination by the FAA was made in August The FAA ruled that the installation of a solar array in this location poses no hazard to air navigation. A copy of the determination is attached. CMPA Campus Wide Solar Array Installation 2 of 4
4 The array is required to be fenced for safety reasons. It is important that only authorized personnel working on the array or maintaining the grounds be within the array area. The current fence design planned for the project is designed to blend with the botanical garden and UAF farm fencing concepts for an aesthetically pleasing, yet secure enclosure. A concept of the fence is attached to this document. Amendment Impact This amendment impacts the existing 2010 CMP in potential future use of the land. The land was designated to be used for trails and ecosystem research as desired by professors. It had no concrete use or buildings designated for the area. The trails impacted by the construction of the solar array will be rerouted as part of the project. Potentially, the solar array could be used for research by engineering students and the community as a study in alternative energy production in a northern climate. Policy Compliance This amendment complies with Regents Policy in that it provides a guideline for land use in a designated area. 1. Projected enrollment and other factors affecting the need for facilities and infrastructure: there is no impact on projected enrollment or other factors affecting the need for facilities and infrastructure. This is an infrastructure project. 2. General areas for land acquisition and disposal: no land is being acquired or disposed of for this project. 3. The general location of new or upgraded infrastructure, including roads, parking, pedestrian circulation, transit circulation, and utilities: the proposed solar array would impact the ski trail that traverses the field. It is proposed that the ski trail be relocated parallel to the road and run to the south of the array. 4. Demolition of buildings, structures, and facilities: no buildings or structures will need to be demolished to accomplish this project. The only impact to facilities will be the need to relocate the ski trail. 5. General location, size, and purpose of new buildings, structures, and facilities: the anticipated footprint of the array is shown in the attached sketch. There are no outbuildings or other structures required as a part of this project. 6. Guidelines for landscaping: the array will be fenced to prevent unauthorized entry. The fence aesthetics will be coordinated with the campus architect. The owner of the array will be responsible for all maintenance of the landscaping and the fence. 7. General location and intent for open spaces, plazas, etc.: As this is not a building, there will be no open space incorporated. 8. Guidelines for signage, both freestanding and on buildings and structures: any permanent signage will be constructed in accordance with exterior UAF sign requirements. 9. Architectural guidelines for all buildings, structures, and facilities: this project consists of a solar array, a similar photo of which is attached. Solar arrays have a visual impact in that they are panels mounted on short bases, all facing south. UAF is working with the University Architect to ensure the project follows the draft Architectural Guidelines for this type of structure. CMPA Campus Wide Solar Array Installation 3 of 4
5 10. Environmental and cultural issues, ADA access, and energy conservation: this project will demonstrate UAF s commitment to sustainable energy production concurrent with planning for a replacement solid fuel Combined Heat and Power plant. The project also demonstrates UAF s commitment to a complete energy portfolio. This is an infrastructure project with very limited access, so ADA access will not be an issue. 11. The relationship of the campus to its surroundings and coordination with local government land use plans and ordinances: no ordinances or land use issues need to be addressed. 12. General priorities for capital projects: this project will not impact the campus capital 10-year plan or priorities. Supporting Documents Campus Master Plan, Figure 3.4 as revised Master Planning Committee recommendation FAA Determination Letter Dated 8/21/2013 (w/ Sectional and Topo Maps) Approvals A CMPA requires approval by the full Board of Regents. CMPA Campus Wide Solar Array Installation 4 of 4
6
7
8 Mail Processing Center Federal Aviation Administration Southwest Regional Office Obstruction Evaluation Group 2601 Meacham Boulevard Fort Worth, TX Issued Date: 08/21/2013 Aeronautical Study No AAL-230-OE Amber McDonough Siemens Industry Inc 5333 Fairbanks St STE B Anchorage, AK ** DETERMINATION OF NO HAZARD TO AIR NAVIGATION ** The Federal Aviation Administration has conducted an aeronautical study under the provisions of 49 U.S.C., Section and if applicable Title 14 of the Code of Federal Regulations, part 77, concerning: Structure: Solar Panel UAF PV Array Location: Fairbanks, AK Latitude: N NAD 83 Longitude: W Heights: 550 feet site elevation (SE) 12 feet above ground level (AGL) 562 feet above mean sea level (AMSL) This aeronautical study revealed that the structure does not exceed obstruction standards and would not be a hazard to air navigation provided the following condition(s), if any, is(are) met: It is required that FAA Form , Notice of Actual Construction or Alteration, be e-filed any time the project is abandoned or: At least 10 days prior to start of construction (7460-2, Part I) X Within 5 days after the construction reaches its greatest height (7460-2, Part II) Based on this evaluation, marking and lighting are not necessary for aviation safety. However, if marking/ lighting are accomplished on a voluntary basis, we recommend it be installed and maintained in accordance with FAA Advisory circular 70/ K Change 2. This determination expires on 02/21/2015 unless: (a) (b) (c) the construction is started (not necessarily completed) and FAA Form , Notice of Actual Construction or Alteration, is received by this office. extended, revised, or terminated by the issuing office. the construction is subject to the licensing authority of the Federal Communications Commission (FCC) and an application for a construction permit has been filed, as required by the FCC, within 6 months of the date of this determination. In such case, the determination expires on the date prescribed by the FCC for completion of construction, or the date the FCC denies the application. Page 1 of 4
9 NOTE: REQUEST FOR EXTENSION OF THE EFFECTIVE PERIOD OF THIS DETERMINATION MUST BE E-FILED AT LEAST 15 DAYS PRIOR TO THE EXPIRATION DATE. AFTER RE-EVALUATION OF CURRENT OPERATIONS IN THE AREA OF THE STRUCTURE TO DETERMINE THAT NO SIGNIFICANT AERONAUTICAL CHANGES HAVE OCCURRED, YOUR DETERMINATION MAY BE ELIGIBLE FOR ONE EXTENSION OF THE EFFECTIVE PERIOD. This determination is based, in part, on the foregoing description which includes specific coordinates, heights, frequency(ies) and power. Any changes in coordinates, heights, and frequencies or use of greater power will void this determination. Any future construction or alteration, including increase to heights, power, or the addition of other transmitters, requires separate notice to the FAA. This determination does include temporary construction equipment such as cranes, derricks, etc., which may be used during actual construction of the structure. However, this equipment shall not exceed the overall heights as indicated above. Equipment which has a height greater than the studied structure requires separate notice to the FAA. This determination concerns the effect of this structure on the safe and efficient use of navigable airspace by aircraft and does not relieve the sponsor of compliance responsibilities relating to any law, ordinance, or regulation of any Federal, State, or local government body. Any failure or malfunction that lasts more than thirty (30) minutes and affects a top light or flashing obstruction light, regardless of its position, should be reported immediately to (800) so a Notice to Airmen (NOTAM) can be issued. As soon as the normal operation is restored, notify the same number. If we can be of further assistance, please contact our office at (907) On any future correspondence concerning this matter, please refer to Aeronautical Study Number 2013-AAL-230-OE. Signature Control No: ( DNE ) Robert van Haastert Specialist Attachment(s) Map(s) Page 2 of 4
10 TOPO Map for ASN 2013-AAL-230-OE Page 3 of 4
11 Sectional Map for ASN 2013-AAL-230-OE Page 4 of 4
Section 7.25 REGULATION OF SOLAR FARMS AND SOLAR PANELS
Section 7.25 REGULATION OF SOLAR FARMS AND SOLAR PANELS This amendment Solar Energy is hereby added to the Montcalm Township Zoning Ordinance to state as follows: A. INTENT AND PURPOSE This section is
More information12/04/15 AC 70/7460-1L CHAPTER 13. MARKING AND LIGHTING WIND TURBINES
CHAPTER 13. MARKING AND LIGHTING WIND TURBINES 13.1 Purpose. This chapter provides guidelines for the marking and lighting of wind turbine farms. These guidelines are applicable to single wind turbines
More informationCITY OF ST. MICHAEL WRIGHT COUNTY, MINNESOTA ORDINANCE NO THE CITY COUNCIL OF THE CITY OF ST. MICHAEL HEREBY ORDAINS:
CITY OF ST. MICHAEL WRIGHT COUNTY, MINNESOTA ORDINANCE NO. 1507 AN ORDINANCE AMENDING SECTION 155.073 OF THE ST. MICHAEL CODE TO ADD DEFINITIONS FOR SOLAR ENERGY SYSTEMS, AND ADD COMMUNITY SOLAR GARDEN
More informationPage 1 of 6 770-54 Wind and solar energy systems. [Added 6-15-2009 by Ord. No. 2009-06] A. Purpose and intent. It is the general purpose and intent of the City to balance the need for clean, renewable
More informationCITY OF SCANDIA ORDINANCE NO. 193
CITY OF SCANDIA ORDINANCE NO. 193 AN ORDINANCE AMENDING ORDINANCE NO. 122, THE SCANDIA DEVELOPMENT CODE, CHAPTER 1, SECTION 4.2 DEFINITIONS AND CHAPTER 2, SECTION 4.33 -- PASSIVE SOLAR ENERGY SYSTEMS The
More informationORDINANCE NO. BE IT ORDAINED by the City Council of the City of Waukee:
ORDINANCE NO. AN ORDINANCE TO AMEND CHAPTER 300, ZONING ORDINANCE, CITY OF WAUKEE, IOWA, BY AMENDING SECTION 301.8 TO ADD PROVISIONS REGULATING SOLAR ENERGY SYSTEMS BE IT ORDAINED by the City Council of
More informationCity of Rome, NY Site Plan Review Application Checklist Consult Chapter 80 of the City of Rome Code of Ordinances.
City of Rome, NY Site Plan Review Application Checklist Consult Chapter 80 of the City of Rome Code of Ordinances. *Note: For specific information regarding development within the Griffiss Business Redevelopment
More informationSOLAR ENERGY FARMS AND SOLAR ENERGY SYSTEMS
Chapter XI SOLAR ENERGY FARMS AND SOLAR ENERGY SYSTEMS 1. Purpose Rev. 06-07-17; Ord. 752 A. The purpose of this Chapter is to maintain the City s attractiveness, protect the safety of the people, and
More informationCHARTER TOWNSHIP OF PORT HURON
CHARTER TOWNSHIP OF PORT HURON 3800 Lapeer Road Phone: (810) 987-6600 Port Huron Twp., Michigan 48060 Fax: (810) 987-6712 www.porthurontownship.org KLavigne@PortHuronTownship.org MEMORANDUM To: Chairman
More informationSOLAR ENERGY SYSTEMS APPLICATION
For reasonable accommodations or alternative formats please contact 311 at 612-673-3000. People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000. TTY users call 612-673-2157
More information9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:
SECTION 9. COMMERCIAL WIND ENERGY FACILITIES 9.1 Purpose. The purpose of this Section 9 of the Zoning Bylaw is to provide by special permit for the construction and operation of commercial wind facilities
More informationCARLTON COUNTY RENEWABLE ENERGY ORDINANCE #32
CARLTON COUNTY RENEWABLE ENERGY ORDINANCE #32 Adopted: December 1, 2017 Carlton County Renewable Energy Ordinance # 32 Table of Contents ARTICLE 1. TITLE, AUTHORITY, PURPOSE, SCOPE AND SEVERABILITY...
More informationMorgan County Planning Commission. Petition for: Text Amendment. Article 7, Regulations for Specific Uses
Staff Report Morgan County Planning Commission Petition for: Text Amendment Applicant: Applicant s Agent: Zoning Ordinance: Morgan County Zoning Ordinance Article 7, Regulations for Specific Uses Summary
More informationORDINANCE NO
CITY OF NORTH BRANCH STATE OF MINNESOTA COUNTY OF CHISAGO ORDINANCE NO. 211-14 AN ORDINANCE AMENDING THE NORTH BRANCH ZONING ORDINANCE BY ADDING STANDARDS AND DEFINITIONS FOR SOLAR ENERGY SYSTEMS, SOLAR
More informationORDINANCE NO. 465 BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF HUXLEY, IOWA:
ORDINANCE NO. 465 AN ORDINANCE AMENDING THE MUNICIPAL CODE OF THE CITY OF HUXLEY, IOWA, BY AMENDING THE ZONING ORDINANCE TO ADD NEW SECTION 165.47 PROVIDING REGULATIONS FOR SOLAR ENERGY SYSTEMS BE IT ORDAINED
More informationLIST OF APPENDICES. Archaeological/Historical Quality Review Correspondence
Brazos Valley Disposal Facili Permit Application Parts I & II, Appendices LIST OF APPENDICES Part IIl Appendix A - Correspondence A-I. A-2. A-3. Land Use Analysis ArchaeologicalHistorical Quality Review
More informationA Local Law amending Chapter Section 139, The Zoning Law of the Town of Lysander, New York.
Local Law No. 2 of 2017 A Local Law amending Chapter Section 139, The Zoning Law of the Town of Lysander, New York. Be it enacted by the Town Board of the Town of Lysander, Onondaga County, New York, as
More informationCHAPTER 725. Solar Farms.
CHAPTER 725 Solar Farms. The following provisions shall apply to all solar farms in Carroll County, IL. A Solar Farm is defined as a power station using photovoltaic modules and inverters for utility electricity
More informationSECTION ENERGY SYSTEMS (WIND AND SOLAR)
Section 1107.18 Page 1 SECTION 1107.18 ENERGY SYSTEMS (WIND AND SOLAR) 1107.18 SUBD. 1. PURPOSE. The purpose of this Section is to establish standards and procedures by which the installation and operation
More informationHAGAR COURT ARCHITECTURAL GUIDELINES DRAFT 3 September 14, 2004
A. Overview of the Approval Process HAGAR COURT ARCHITECTURAL GUIDELINES DRAFT 3 September 14, 2004 Under the provisions of Article 16 of the Covenants, Conditions, and Restrictions of Hagar Court, a process
More informationTOWNSHIP OF STURGIS ST. JOSEPH COUNTY MICHIGAN ORDINANCE NO ADOPTED: October 1, EFFECTIVE: October 22, 2018
TOWNSHIP OF STURGIS ST. JOSEPH COUNTY MICHIGAN ORDINANCE NO. 2018-1 ADOPTED: October 1, 2018 EFFECTIVE: October 22, 2018 An Ordinance to add provisions for large solar energy systems to the Township Zoning
More informationPublic Notice of Application for Permit
US Army Corps of Engineers Alaska District ANCHORAGE Regulatory Division (1145) CEPOA-RD Post Office Box 6898 JBER, Alaska 99506-0898 Public Notice of Application for Permit PUBLIC NOTICE DATE: July 31,
More informationTHERFORE, the Board of Supervisors hereby adopts the following amendments to the Zoning Ordinance by adding the following:
AN ORDINANCE OF THE TOWNSHIP OF LONGSWAMP TOWNSHIP, BERKS COUNTY, PENNSYLVANIA, AMENDING THE TOWNSHIP ZONING ORDINANCE TO ADD ARTICLE VIIA WHICH PROVIDES PROVISIONS FOR THE REGULATION OF SOLAR ENERGY SYSTEMS
More information6.6 RESIDENTIALLY-SCALED, LAND-BASED WIND ENERGY CONVERSION FACILITIES
6.6 RESIDENTIALLY-SCALED, LAND-BASED WIND ENERGY CONVERSION FACILITIES 6.6.1 Purpose and Intent It is the express purpose of this Section to accommodate residentially-scaled, land-based wind energy conversion
More informationCITY OF TONKA BAY COUNTY OF HENNEPIN STATE OF MINNESOTA ORDINANCE NO
CITY OF TONKA BAY COUNTY OF HENNEPIN STATE OF MINNESOTA ORDINANCE NO. 2017- AN ORDINANCE AMENDING CHAPTER X, ZONING, SECTION 1011, GENERAL DEVELOPMENT AND PERFORMANCE STANDARDS WIND ENERGY CONVERSION SYSTEMS
More informationBelow are the existing regulations for solar uses included in the Charlotte County Zoning Ordinance. All proposed amendments are marked in red.
Below are the existing regulations for solar uses included in the Charlotte County Zoning Ordinance. All proposed amendments are marked in red. Index Sec. 10-23. Solar Energy Systems Article 9. Use Matrix
More informationAddition to Section 4 - Special Use Regulations
Large-Scale Ground-Mounted Solar Photovoltaic Installations Addition to Section 4 - Special Use Regulations 4.4 Large Scale Ground-Mounted Solar Photovoltaic Installations 4.4.1 Purpose The purpose of
More informationCharter Township of Garfield Grand Traverse County
Charter Township of Garfield Grand Traverse County 3848 VETERANS DRIVE TRAVERSE CITY, MICHIGAN 49684 PH: (231) 941-1620 FAX: (231) 941-1588 SPECIAL USE PERMIT APPLICATION APPLICANT INFORMATION Name: Address:
More informationCellular Antenna Site Application Requirements
Cellular Antenna Site Application Requirements Prior to allowing installation or utilization of an antenna site on University of Colorado Boulder property, please ensure the following: 1. Before completing
More informationTown of Worcester Local Law No. 1 of 2018 Solar Energy Systems
Town of Worcester Local Law No. 1 of 2018 Solar Energy Systems I. Title: This local law shall be referred to as the Local Law to Regulate Solar Energy Systems in the Town of Worcester II. Enactment: This
More informationDRAFT Commercial Solar Bylaw November 8, 2011
145-28. Commercial Solar Photovoltaic Installations A. Purpose This bylaw is to encourage the use of solar energy systems and protect solar access consistent with MGL 40A 9B and with the Green Communities
More informationChapter 750 WIND POWER GENERATION FACILITIES
Chapter 750 WIND POWER GENERATION FACILITIES 750.01 Purpose 750.02 Definitions 750.03 Designated Areas 750.04 Permitted Uses 750.05 Conditional Uses 750.06 Construction Standards 750.07 Application Requirements
More informationMEETING DATE: ADOPTED ON EARTH DAY: APRIL 22, 2008 AGENDA ITEM COMMENTARY
TOWNSHIP OF GALLOWAY DEPARTMENT OF COMMUNITY DEVELOPMENT PLANNING BOARD ZONING BOARD OF ADJUSTMENT 300 E. JIMMIE LEEDS ROAD, GALLOWAY, NJ 08205 (609) 652-3700 EXT. 315 FAX: (609) 652-5259 Tiffany A. Cuviello,
More informationCHAPTER 2 THE PROPOSED ACTION
CHAPTER 2 THE PROPOSED ACTION 2.0 INTRODUCTION The proposed action(s) must ensure that the Afton Lincoln County Airport complies with minimum FAA and WYDOT design recommendations for a parallel taxiway
More informationThe current note, which was approved by the county Commission on March 20, 2018, restricts the plat as follows:
Page 1 of 13 STAFF REPORT BW Cypress & Powerline 043-MP-15 A request to amend the note on the plat has been filed with the Planning and Development Management Division. This plat was approved by the Broward
More informationSidewalk Regulations. Table of Contents
Sidewalk Regulations Table of Contents Section 1. Purpose and Intent... 2 Section 2. Pedestrian Sidewalk, Driveway Apron and Curb and Guttering Requirements... 2 Section 3. Sidewalk Provision Criteria...
More information6.5 SMALL WIND ENERGY SYSTEMS
6.5 SMALL WIND ENERGY SYSTEMS 6.5.1 Purpose. The purpose of this subsection is to provide a permitting process for Small Wind Energy Systems (SWES) so that they may be utilized in a cost-effective, efficient,
More informationTOWN OF MARILLA LOCAL LAW NO.2 OF THE YEAR 2017 A Local Law to regulate Solar Energy Systems in the Town. ARTICLE I Enactment and Intent
TOWN OF MARILLA LOCAL LAW NO.2 OF THE YEAR 2017 A Local Law to regulate Solar Energy Systems in the Town ARTICLE I Enactment and Intent ***-1. Title. This chapter shall hereafter be known, cited and referred
More informationCITY OF ORONO HENNEPIN COUNTY, MINNESOTA
CITY OF ORONO HENNEPIN COUNTY, MINNESOTA AN ORDINANCE NO. 119, THIRD SERIES AMENDING ORONO MUNICIPAL CODE CHAPTER 78, THE ORONO ZONING CODE, BY ADDING SECTION 78-1379 ALTERNATIVE ENERGY SYSTEMS THE CITY
More informationWIND ENERGY CONVERSION SYSTEMS APPLICATION
Community Planning and Economic Development Development Services Division 250 South 4 th Street, Room 300 Minneapolis MN 55415-1316 612-673-3000 WIND ENERGY CONVERSION SYSTEMS APPLICATION 535.690. Purpose.
More informationSTAFF REPORT F.P. & L. Welleby Substation 059-MP-83
Page 1 of 11 STAFF REPORT F.P. & L. Welleby Substation 059-MP-83 A request to amend the note on the plat has been filed with the Planning and Development Management Division. The plat was approved by the
More informationTOWNSHIP OF WEYMOUTH ATLANTIC COUNTY NEW JERSEY ORDINANCE NO
TOWNSHIP OF WEYMOUTH ATLANTIC COUNTY NEW JERSEY ORDINANCE NO. 561-2018 AN ORDINANCE AMENDING CHAPTER 155 (LAND USE) OF THE CODE OF THE TOWNSHIP OF WEYMOUTH TO PERMIT THE ADDITION OF A SUSTAINABLE ENERGY
More informationPlanning Commission Staff Report Project Plan Approval Hearing Date: June 24, 2015
Planning Commission Staff Report Project Plan Approval Hearing Date: June 24, 2015 ITEM 4 Provo City s Energy Department requests Final Project Plan approval to rebuild and expand the Energy Department
More informationSection 11.01: Zoning Ordinance Subdivision 9.4: Utility and Communication Uses. 96 Chapter 11: Planning and Development
9.4 Utility and Communication Uses A. Wind Energy Conversion Systems (WECS) 1. Intent. The intent of this Subdivision is to promote safe, effective and efficient use of alternative energy sources and systems
More informationORDINANCE NO. THE LENT TOWNSHIP BOARD OF SUPERVISORS ORDAINS: The following language is hereby added to the Lent Township Zoning Ordinance:
ORDINANCE NO. AMENDING THE LENT TOWNSHIP ZONING ORDINANCE BY ADDING STANDARDS AND DEFINITIONS FOR SOLAR ENERGY SYSTEMS, SOLAR ENERGY FARMS AND FOR THEIR INSTALATION AND USE IN LENT TOWNSHIP THE LENT TOWNSHIP
More informationAN ORDINANCE ADOPTING A SOLAR ENERGY SYSTEM ORDINANCE FOR DEKALB COUNTY
STATE OF ILLINOIS ) )SS COUNTY OF DEKALB ) ORDINANCE 2018-06 AN ORDINANCE ADOPTING A SOLAR ENERGY SYSTEM ORDINANCE FOR DEKALB COUNTY WHEREAS, the DeKalb County Board has determined the need for regulations
More informationDOÑA ANA COUNTY Community Development Department Intra-Departmental Memorandum
DOÑA ANA COUNTY Community Development Department Intra-Departmental Memorandum To: Planning and Zoning Commission Date: April 17, 2012 From: Steve Meadows, Planner Subject: Proposed Wireless Telecommunications
More informationThe remainder of Area C is restricted to 120,535 square feet of office use; and an 894 bed detention facility.
Page 1 of 18 STAFF REPORT Rowan Replat 013-UP-91 A request to amend the note on the plat has been filed with the Planning and Development Management Division. This plat was approved by the Broward County
More informationMonterey County Planning Commission
Monterey County Planning Commission Meeting: August 13, 2003, 11:00 A.M. Agenda Item: 4 Project Description: Use Permit (Fetter, PLN000670) for the construction of a new 68 foot tall windmill wireless
More informationDESIGN REVIEW COMMITTEE AGENDA ITEM
DESIGN REVIEW COMMITTEE AGENDA ITEM AGENDA DATE: AUGUST 21, 2013 TO: THRU: FROM: SUBJECT: Chair Fox and Members of the Design Review Committee Leslie Aranda Roseberry, Planning Manager Jennifer Le, Senior
More informationBlack Oak Wind Farm Lighting Plan
Black Oak Wind Farm Lighting Plan Turbines Turbines shall have a safety light near the turbine door. The light shall be set on a motion detector and hooded downward. If motion detector lighting is not
More informationDESIGN REVIEW COMMITTEE AGENDA ITEM
DESIGN REVIEW COMMITTEE AGENDA ITEM AGENDA DATE: MAY 1, 2013 TO: THRU: FROM: SUBJECT: Chair Fox and Members of the Design Review Committee Leslie Aranda Roseberry, Planning Manager Jennifer Le, Senior
More informationSubstitute 1 to Ordinance
Substitute 1 to Ordinance 17-044 Solar Energy Systems - new to our code Minor and Major Utilities - amended Revised: NCC Land Use 09/28/17 Page 1 - SES - SOLAR ENERGY SYSTEM Per State Code, renewable energy
More information-01k( Rec.by:DZ. ARTICLE IX - STANDARDS FOR TELECOMMUNICATIONS TOWERS AND ANTENNAS. Section Intent
ARTICLE IX - STANDARDS FOR TELECOMMUNICATIONS TOWERS AND ANTENNAS Section 900 - Intent The intent and purpose of this Article is to establish general guidelines for the sitting of commercial telecommunications
More informationSolar Ready Homes/Solar Oriented Developments Residential Stakeholder Meeting
Solar Ready Homes/Solar Oriented Developments Residential Stakeholder Meeting California Statewide Utility Codes and Standards Program Jon Roberts CTG Energetics Buehler Alumni Center, UC Davis May 13,
More informationProposed Local Law No. 1 for 2018 BE IT ENACTED BY THE TOWN BOARD OF THE TOWN OF BERNE, NEW YORK AS FOLLOWS:
Proposed Local Law No. 1 for 2018 BE IT ENACTED BY THE TOWN BOARD OF THE TOWN OF BERNE, NEW YORK AS FOLLOWS: SECTION 1. Title. This local law may be cited as the Town of Berne Small Scale Solar Energy
More informationThe Georgia Model Solar Zoning Ordinance
The Georgia Model Solar Zoning Ordinance Version 1.0 July 2018 Representatives from Emory Law School, Georgia Institute of Technology, and University of Georgia developed this Model Ordinance in response
More informationLOCAL LAW NO. OF THE YEAR BE IT ENACTED by the Town Board of the Town of Wappinger as follows:
LOCAL LAW NO. OF THE YEAR 2016 BE IT ENACTED by the Town Board of the Town of Wappinger as follows: Section -I: Title: This Local Law shall be known and cited as Adoption of Zoning Provisions for Solar
More informationCHIPPEWA COUNTY LAND AND RELATED RESOURCE MANAGEMENT ORDINANCE SECTION 16 SOLAR POWER MANAGEMENT TABLE OF CONTENTS SUBDIVISION 1.
CHIPPEWA COUNTY LAND AND RELATED RESOURCE MANAGEMENT ORDINANCE SECTION 16 SOLAR POWER MANAGEMENT TABLE OF CONTENTS PAGE SUBDIVISION 1. TITLE 1 SUBDIVISION 2. PURPOSE 1 SUBDIVISION 3. JURISDICTION 1 SUBDIVISION
More information5600. LARGE-SCALE GROUND-MOUNTED SOLAR PHOTOVOLTAIC INSTALLATIONS
To Wit: To see if the Town will vote to amend the Town of Westborough Zoning Bylaws, Article 2, District Regulations, Section 2300, Use Regulations Schedule; and to amend Article 4, Special Regulations
More informationINSTALLING METEOROLOGICAL MONITORING TOWER AT PROPOSED AND EXISTING NUCLEAR FACILITIES
MURRAY AND TRETTEL, INCORPORATED INSTALLING METEOROLOGICAL MONITORING TOWER AT PROPOSED AND EXISTING NUCLEAR FACILITIES Murray and Trettel, Inc. Mark T. Carroll Andrew J. Lotz Heather A. Cramond June 2011
More informationThe attached letter from the City of Pompano Beach indicates no objection to the requested amendment.
Page 1 of 13 STAFF REPORT Lanier Plat 013-MP-12 A request to amend the note on the plat has been filed with the Planning and Development Management Division. This plat was approved by the Broward County
More information# Central States Tower/ Verizon Wireless Special Use Permit & Zoning Variation Project Review for Planning and Zoning Commission
#2015-47 Central States Tower/ Verizon Wireless Special Use Permit & Zoning Variation Project Review for Planning and Zoning Commission Meeting Date: August 19, 2015 Request: Location: Acreage: Existing
More information30A RULES FOR RENEWABLE ENERGY GENERATION
30A RULES FOR RENEWABLE ENERGY GENERATION Policies 16A.4.1 Activities Tables 30A.1 Subdivision Activities Activity Status The operation and maintenance of existing renewable energy generation facilities
More information# 5 ) UN GREENLEAF FARMS HOLDINGS - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING
# 5 ) UN-20-16 GREENLEAF FARMS HOLDINGS - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: March 9, 2016 Item: UN-20-16 Prepared by: Marc Jordan GENERAL
More information#4) UN NUVEDA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING
#4) UN-60-16 NUVEDA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: September 14, 2016 Item: UN-60-16 Prepared by: Robert Eastman GENERAL INFORMATION:
More informationUniform Sign Plan (USP) Gateway Centre 87-USP-003
Uniform Sign Plan (USP) Gateway Centre 87-USP-003 These guidelines are published for informational purposes. A sign permit application must be submitted and a permit issued prior to the installation of
More informationWHEREAS, the proposed Land Management Code (LMC) amendments enhance the design standards to maintain aesthetic experience of Park City; and
Exhibit A Draft Ordinance Ordinance 2019-07 AN ORDINANCE AMENDING THE LAND MANAGEMENT CODE OF PARK CITY, UTAH, AMENDING SECTIONS 15-2.1-6 DEVELOPMENT ON STEEP SLOPES, 15-2.2-3 LOT AND SITE REQUIREMENTS,
More informationMEMORANDUM. Authority and Restrictions under Proposed O.R.C regarding Small Cell Facilities and Wireless Support Structures in the Public Way
MEMORANDUM TO: FROM: Ohio Municipal Corporations Lindsay Miller DATE: January 17, 2018 RE: Authority and Restrictions under Proposed O.R.C. 4939 regarding Small Cell Facilities and Wireless Support Structures
More informationThe ARDEN Group Development Standards 05/17/13 Rezoning Petition No (University City Auto Mall) Site Development Data:
The ARDEN Group Development Standards 05/17/13 Rezoning Petition No. 2013-052 (University City Auto Mall) Site Development Data: --Site Acreage: +/- 39 Ac. --Tax Parcel #: 047-23-108 --Existing Zoning:
More informationTOWN OF SMITHFIELD, RHODE ISLAND PUBLIC HEARING
TOWN OF SMITHFIELD, RHODE ISLAND PUBLIC HEARING NOTICE IS HEREBY GIVEN that the Smithfield Town Council will hold a Public Hearing at the Smithfield Town Hall, 64 Farnum Pike, Smithfield, RI on Tuesday,
More informationLOCAL LAW #4 OF 2018 OF THE TOWN OF TYRE TOWN OF TYRE SOLAR ENERGY LAW
LOCAL LAW #4 OF 2018 OF THE TOWN OF TYRE TOWN OF TYRE SOLAR ENERGY LAW Section 1. Authority This article is enacted pursuant to the authority granted by Section 10(1)(i) of the Municipal Home Rule Law,
More informationPeter Kirk Elementary School Modernization vs. New-in-lieu of Modernization Report
Peter Kirk Elementary School Modernization vs. New-in-lieu of Modernization Report January 2016 Summary In consideration for a potential 2016 Bond measure for the Capital Facilities Program, Kirk Elementary
More informationThis plat is restricted to 20,400 square feet of Boys and Girls Club.
Page 1 of 14 STAFF REPORT Boys and Girls Club Plat 090-MP-97 A request to revise the note on the plat has been filed with the Planning and Development Management Division. This plat was approved by the
More informationBEFORE THE CITY COUNCIL OF THE CITY OF PITTSBURG ) ) ) ) The City Council of the City of Pittsburg DOES ORDAIN as follows:
In the Matter of: BEFORE THE CITY COUNCIL OF THE CITY OF PITTSBURG Ordinance Amending Pittsburg Municipal Code Title 19 (Signs, to Remove the Prohibition on Installation of Billboards and Allow Billboards
More informationRESOLUTION. Councilperson De Bonis, seconded by Councilperson Murphy, introduced the following proposed local law, to be known as Local
RESOLUTION Councilperson De Bonis, seconded by Councilperson Murphy, introduced the following proposed local law, to be known as Local Law No. of 2018, entitled A LOCAL LAW OF THE TOWN OF WASHINGTON, DUTCHESS
More informationEpic Wireless c/o Buzz Lynn (DBA Verizon Wireless) LOCATION: 3080 Vista Boulevard (Refer to Exhibit 1 Vicinity Map)
CASE NUMBER: REQUESTED ACTION(S): PROJECT DESCRIPTION: PROPERTY OWNER: APPLICANT: PCN18-0029 / CU18-0009 Approval of a Conditional Use Permit Conditional Use Permit to allow construction of a new cupola
More informationRETAINING WALL DESIGN GUIDELINES PREPARED FOR: THE CITY OF LAKE FOREST BY:
RETAINING WALL DESIGN GUIDELINES PREPARED FOR: THE CITY OF LAKE FOREST BY: Approved by City Council June 15, 2010 RETAINING WALL DESIGN GUIDELINES A. PURPOSE AND APPLICABILITY The Land Use Element of the
More informationDESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING
DESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING Multi family housing is an increasingly popular form of infill development in Shaker Heights because of the city s built out
More informationCITY OF HARTFORD GUIDELINES FOR SOLAR ON HISTORIC PROPERTIES SECTIONS ADOPTED 2017
CITY OF HARTFORD GUIDELINES FOR SOLAR ON HISTORIC PROPERTIES ADOPTED 2017 SECTIONS 1. OVERVIEW 2. TYPES OF SOLAR 3. PROCEDURES 4. GENERAL GUIDANCE 5. SPECIFIC GUIDANCE: Building-Mounted Solar 6. SPECIFIC
More informationRESIDENTIAL DEVELOPMENT GUIDELINES (RF)
RESIDENTIAL DEVELOPMENT GUIDELINES (RF) Planning Division DENSITY STANDARDS (MMC 17.12.010) Lot Size (applies to the creation of new lots or lot line adjustments) ZONE MINIMUM LOT AREA MINIMUM LOT WIDTH
More informationBOB HOPE AIRPORT REPLACEMENT TERMINAL PROJECT LOCATION BOB HOPE AIRPORT REPLACEMENT TERMINAL PROJECT DESCRIPTION
EXHIBIT A-1 BOB HOPE AIRPORT REPLACEMENT TERMINAL PROJECT LOCATION The Burbank-Glendale-Pasadena Airport Authority (Authority) seeks to develop a 14-gate replacement passenger terminal building and related
More informationThis application has been reviewed by Highway Construction and Engineering Division staff who has no objections to this request.
Page 1 of 16 STAFF REPORT Port Everglades Plat No. 11 155-MP-88 A request to amend the note on the plat has been filed with the Planning and Development Management Division. This plat was approved by the
More informationUpdate on the Draft EIR on the Proposed Airport Master Plan
1 Update on the Draft EIR on the Proposed Airport Master Plan 1. Summary of Process to Date (Slides 3-4) 2. Proposed Project (Slides 5-8) 3. EIR Alternative (Slides 9-10) 4. Comparison of Differences between
More informationPublic Notice of Application for Permit
US Army Corps of Engineers Alaska District FAIRBANKS FIELD OFFICE Regulatory Division (1145) CEPOA-RD 2175 University Avenue, Suite 201E Fairbanks, Alaska 99709-4927 Public Notice of Application for Permit
More informationAccessory Dwelling Unit Permit Submittal Requirement Checklist (Corte Madera Municipal Code Section 18.31)
PLANNING DEPARTMENT 300 TAMALPAIS DRIVE CORTE MADERA, CA 94925 Accessory Dwelling Unit Permit Submittal Requirement Checklist (Corte Madera Municipal Code Section 18.31) Address of Project Site Definition:
More informationMinimum Standards for Construction of Aircraft Hangars MINIMUM STANDARDS FOR CONSTRUCTION OF AIRCRAFT HANGARS
Minimum Standards for Construction of Aircraft Hangars ARTICLE 1. MINIMUM STANDARDS FOR CONSTRUCTION OF AIRCRAFT HANGARS Section 1. - Purpose Section 2. - Goals Section 3. General Provisions Section 4.
More informationPUBLIC HEARINGS June 6 & 7, 2018
PUBLIC HEARINGS June 6 & 7, 2018 STUDENT HOUSING WEST AGENDA & OUTLINE FOR THIS EVENING Agenda Present Student Housing West Project information. Present information specific to the Student Housing West
More informationSTAFF REPORT Dania Pointe 035-MP-15
Page 1 of 14 STAFF REPORT Dania Pointe 035-MP-15 A request to revise the note on the plat has been filed with the Planning and Development Management Division. This plat was approved by the Broward County
More informationThe existing land use surrounding North Perry Airport can be described as follows:
7.1 INTRODUCTION This land use evaluation will accomplish the following: Identify existing and future land uses in the Airport environs; Document existing land use, future land use, and zoning around the
More informationCONDITIONAL USE PERMITS (CUP):
April 2, 2001 Memo To: From: Re: Telecommunication Service Providers David Less, City Planner CITY REQUIREMENTS FOR TELECOM TOWERS AND ANTENNAS Effective March 2001, the City s new telecommunication ordinance
More informationCITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA PHONE: 727/ FAX: 727/
CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA 34695 PHONE: 727/724-1555 FAX: 727/724-1566 RIGHT-OF-WAY / EASEMENT USE PERMIT DATE SUBMITTED: EXPIRATION DATE: Submit the following to the
More information# Mercyhealth Hospital Project Review for Planning and Zoning Commission
#2017-38 Mercyhealth Hospital Project Review for Planning and Zoning Commission Meeting Dates: December 6, 2017 and January 3, 2018 Requests: 1. Preliminary Planned Unit Development and 2. Special Use
More informationMARTIN COUNTY WIRELESS COMMUNICATION FACILITIES
MARTIN COUNTY WIRELESS COMMUNICATION FACILITIES Section 1. PURPOSE The purpose of the regulations and requirements of this Ordinance are to: Subpart 1. Accommodate the communication needs of the residents
More informationREQUIREMENTS FOR WIRELESS FACILITY PERMIT APPLICATIONS
REQUIREMENTS FOR WIRELESS FACILITY PERMIT APPLICATIONS (A copy of the full Wireless Telecommunication Facilities Ordinance is available upon request) TABLE OF CONTENTS Page I. GENERAL REQUIREMENTS...
More informationARTICLE 11.5 STANDARDS FOR TELECOMMUNICATIONS ANTENNAE AND TOWERS
ARTICLE 11.5 STANDARDS FOR TELECOMMUNICATIONS ANTENNAE AND TOWERS SECTION 1151. PURPOSES. This ordinance is designed and intended to balance the interests of the residents of the City of Duluth, telecommunications
More information# Teckler Boulevard Self Storage Preliminary PUD Project Review for Planning and Zoning Commission
#2014-13 Teckler Boulevard Self Storage Preliminary PUD Project Review for Planning and Zoning Commission Meeting Date: March 19, 2014 and April 2, 2014 Requests: 1. Special Use Permit to allow a Preliminary
More informationGround Mount All All All All All except HM IRO. Ground Mount. Site Plan Review. Building - Zoning Permit
Page: 1 148-35 L. Solar Energy Systems. Intent The purpose of the following regulations is to promote and accommodate the provision of solar energy systems as an environmentally friendly alternative source
More informationORDINANCE OF THE NEWTON COUNTY BOARD OF COMMISSIONERS TO REPEAL CONFLICTING PROVISIONS; AND TO AMEND THE ZONING ORDINANCE OF NEWTON COUNTY, GEORGIA
ORDINANCE OF THE NEWTON COUNTY BOARD OF COMMISSIONERS TO REPEAL CONFLICTING PROVISIONS; AND TO AMEND THE ZONING ORDINANCE OF NEWTON COUNTY, GEORGIA WHEREAS, the Board of Commissioners of Newton County,
More informationLedges East Master Owners Association. Architectural Guidelines for the Community-Wide Areas
Ledges East Master Owners Association Architectural Guidelines All improvements proposed or required to be constructed in Community-Wide Areas (whether located in Commercial Areas or Residential Areas)
More information