Transcription
1 City of Bozeman Construction Site Management Program Best Management Practice (BMP) Manual for Construction Sites Version 6 June 30, 2017
2 Blank Page 2
3 Section 1 - Overview Table of Contents Manual Introduction 5 Permit Types 7 Local Erosion and Sediment Control Requirements 9 Operational and Administrative Controls 11 Section 2 - Perimeter Control Foam Wattle with Apron 13 Straw Wattle 15 Silt Fence 19 Compacted Earthen Berm 23 Sediment Trap 27 Section 3 - Infrastructure Protection Inlet Protection 31 Tracking Control 33 Dewatering from Excavated Areas and Wells 37 Section 4 - Pollutant Management Concrete Washout and Waste Management 41 Section 5 Final Stabilization Measures Post Construction Feature 47 Disturbed Area 53 Section 6 Single-Family Residential Single-Family Home Construction Site Protection Plan 55 3
4 Notes 4
5 Overview Manual Introduction This manual provides Best Management Practices (BMP) designed to mitigate pollution generated from construction activities. The City of Bozeman encourages developers, engineers, and contractors to use this resource to develop and implement required stormwater permits further detailed on Page 4. Stormwater is rain and snowmelt that flows over hard surfaces and landscapes that does not infiltrate into the ground. Stormwater picks up pollutants, such as sediment, trash, animal waste, fertilizers, oils, hydrocarbons, and grease, as it moves over these surfaces. Stormwater then enters curb inlets, passes through a network of underground pipes, and dumps into local rivers without treatment. The City of Bozeman works to improve the quality of stormwater runoff to ensure local waterways stay healthy enough so residents can safely fish, recreate, and swim. One of the largest local stormwater pollution sources is uncontrolled stormwater runoff from unprotected construction sites. Stormwater runoff from unprotected construction sites carries sediment and other pollutants offsite, causing degradation of rivers and infrastructure. A one-acre construction site can lose tons of sediment to erosion per year. It is important that construction professionals manage stormwater on their sites to navigate the City s development process, avoid enforcement penalties, and ensure Bozeman continues to be The Most Livable Place. Image 1 Stormwater dumping into Bozeman Creek Image 2 Clogged stormwater pipe from construction 5
6 Notes 6
7 Overview Permit Types The City of Bozeman requires that project owners have an approved stormwater permit before initiating construction activities. Staff encourages submitters to schedule a pre-submittal meeting where minimum expectations, recommendations, and areas of concern are identified, decreasing preparation, approval, and implementation efforts. Staff review, comment on, and, when deemed adequate, approve all stormwater permits. Project owners that do not submit or submit inadequate permits will not receive a building permit until one of the following is approved: Single-family home construction: Project owners must submit a Single-Family Erosion and Sediment Control Construction Permit. There is no fee associated with this permit. Multi-family, commercial, utility, demolition, and paving projects with a total land disturbance less than one acre: Project owners must submit an Erosion and Sediment Control Construction Permit - Sites Less than 1 Acre. There is no fee associated with this permit. See the Attachments section for a detachable permit. **Presubmittal meeting with staff is highly encouraged. Multi-family, commercial, utility, demolition and paving projects with a total land disturbance greater than one acre: Project owners must submit a Montana Department of Environmental Quality (MDEQ) Notice of Intent, Stormwater Pollution Prevention Plan, and a Notice of Termination to the City of Bozeman and MDEQ. There is no City of Bozeman fee associated with this permit. See the Attachments section for a detachable permit. **Presubmittal meeting with staff is highly encouraged. Image 3 Construction-related pollution event Image 4 Clogged stormwater inlet from construction 7
8 Notes 8
9 Overview Local Erosion and Sediment Control Requirements The City of Bozeman requires that project owners meet the following local erosion and sediment control requirements when preparing and enacting a stormwater permit for their site. They exist to provide a consistent message to contractors, improve permit content, and promote cleaner sites. Project owners must: 1. Protect inlets: Inlets receiving site runoff require BMPs that filter stormwater before flowing into underground infrastructure. Approved options include drop inlet protection. 2. Contain disturbed areas: Project boundaries require BMPs that contain stormwater flowing from disturbed areas. Approved options include foam wattle, straw wattle, silt fence, and compacted earthen berm. 3. Mitigate tracking: Exit points require BMPs that prevent the tracking of debris offsite. Approved options include angular rock and a cattle guard/rock hybrid trackpads. 4. Control concrete waste: Concrete activities require BMPs that allow for the containment and disposal of pollutants generated through masonry activities to prevent environmental contamination. Common regulated activities include concrete pours, masonry tool washing, and curb cutting. Approved options include reusable/disposable products, prefabricated roll-offs or containers, lined below-ground containment, and lined above ground containment. 5. Contain material stockpiles: Material stockpiles, not already contained within an existing perimeter control, require perimeter BMPs that prevent erosion and displacement of loose material. Approved options include foam wattle, straw wattle, silt fence, compacted earthen berm, and tarps/plastic sheeting. 6. Manage dewatering flows: Pumping activities require BMPs that filter water before entering underground infrastructure or waterways. Approved options include filter treatment units, land application, or wells. Dewatering discharges to state waters are a permitted activity under the authority of the MDEQ. 7. Protect post-construction stormwater features: Post-construction stormwater features, such as retention and detention ponds, require BMPs that protect and stabilize their side slopes and bases during and after construction activities. Approved BMPs include riprap, reinforced fore-bays, check dams, crimped straw mulch, and rolled erosion control products. 8. Stabilize disturbed areas: Disturbed areas require BMPs that prevent erosion of barren ground. Approved options include surface roughening, crimped straw mulch, wood mulch, rolled erosion control products, riprap, and sod. 9
10 Notes 10
11 Overview Operational and Administrative Controls Introduction Operational and administrative control BMPs help keep construction sites clean and in compliance. The following are things to consider when preparing and implementing a stormwater permit: Communication Ensure all contractors and subcontractors are aware of their roles and responsibilities Site Barrier Utilize site barriers to control the flow of vehicles and equipment. Several types exist, including concrete blocks, construction fencing, and cones. Off-Site Parking Utilize off-site parking to control tracking by reducing vehicle trips onto disturbed areas. Spill Prevention and Response Utilize a spill kit to clean up leaks and spills that occur. All parties should know its location and proper use. Fleet Management Utilize preventative maintenance to identify and eliminate leaks and drips of hydraulic fluid, gas, oil, etc. from equipment and vehicles. Preservation of Existing Vegetation Utilize preservation of existing vegetation techniques to reduce the amount of erodible area on a job site. Street Sweeping Implement a regular street sweeping program to remove all dirt and construction debris from streets, alleys, and parking lots. Good Housekeeping Keep a clean site by developing and adhering to a waste management plan that includes protocols for trash disposal, sanitary facility cleaning, and proper storage of chemicals. Image 5 Site Barrier Image 6 Spill Kit Image 7 Equipment Management Image 8 Tarped stockpile 11
12 Notes 12
13 Introduction Foam wattle slows and ponds stormwater flowing from small construction sites, including ground disturbance, pollutant storage, and material stockpile areas. Various proprietary foam wattles exist and are available from local suppliers. Contractors must consider their site s size, soil condition, and topography before selecting and installing this BMP. Installation Requirements Install foam wattle: Perimeter Control Foam Wattle with Apron before construction activities per the manufacturer s specification perpendicular to the slope trenched 1 below grade and backfilled with compacted soil placed 2 min. away from the toe of stockpiles or slopes installed with ends turned upslope for 2 min. Inspection and Maintenance Image 9 Properly installed straw wattle. Image 9 Properly installed foam wattle with apron Inspect foam wattle weekly, before rain events, and after rain events to ensure it is functioning. If not, complete one of the following tasks: Repair or Replace torn, flattened, pulled out, or unraveled foam wattle. Repair holes by resecuring the netting using wire, twine, or rope. Cut out and replace degraded sections, ensuring to overlap with existing foam wattle. Replace stakes that have been broken, dislodged, or removed using a mallet or hammer. Maintain once sediment accumulation reaches a depth of 3. Remove collected sediment using hand tools. Remove once the site reaches final stabilization. Fill, compact, and vegetate areas of ground disturbance to blend with adjacent ground and throw away or reuse the foam wattle. 13
14 Notes 14
15 Introduction Straw wattle slows and ponds stormwater flowing from small construction sites, including ground disturbance, pollutant storage, and material stockpile areas. Approved straw wattle consists of weedfree straw wrapped in UV-degradable netting. Contractors must consider their site s size, soil condition, and topography before selecting and installing this BMP. Installation Requirements Install straw wattle: Perimeter Control Straw Wattle before construction activities per the following specification perpendicular to the slope trenched 2 below grade and backfilled with compacted soil secured with 16 wooden stakes at alternating 45 angles every 3 and ends turned upslope for 2 min. overlapped with 1 min. when joining two sections placed 2 min. away from the toe of stockpiles or slopes **Note: Not to be installed in areas of concentrated flow Inspection and Maintenance Image 10 Properly installed straw wattle. Inspect straw wattle weekly, before rain events, and after rain events to ensure it is functioning. If not, complete one of the following tasks: Repair or Replace torn, flattened, pulled out, or unraveled straw wattle. Repair holes by resecuring the netting using wire, twine, or rope. Cut out and replace degraded sections, ensuring to overlap with existing straw wattle. Replace stakes that have been broken, dislodged, or removed using a mallet or hammer. Maintain once sediment accumulation reaches a depth of 3. Remove collected sediment using hand tools. Remove once the site reaches final stabilization. Fill, compact, and vegetate areas of ground disturbance to blend with adjacent ground and throw away waste. 15
16 Notes 16
17 17
18 Notes 18
19 Introduction Silt fence slows and ponds stormwater flowing from construction sites, including land disturbance, pollutant storage, and material stockpile areas. Approved silt fence consists of woven geotextile fabric attached to wooden stakes. Contractors must consider their site s size, soil condition, and topography before selecting and installing this BMP. A co-benefit of silt fence is that it functions as an operational control limiting site access. Installation Requirements Install silt fence: Perimeter Control Silt Fence before construction activities per the following specification perpendicular to the slope positioned with stakes on the down gradient side trenched 6 below grade in a J configuration and backfilled with Image 11 Properly installed silt fence compacted soil trenched with 3 min. wooden stakes every 10 with ends turned upslope for 5 min. placed 2 min. away from the toe of stockpiles overlapped with 1 min. when joining two sections **Note: Not to be installed in areas of concentrated flow Inspection and Maintenance Image 1 Properly installed silt fence Inspect silt fence weekly, before rain events, and after rain events to ensure it is functioning. If not, complete one of the following tasks: Repair or Replace ripped, torn, detached, or flattened silt fence. Repair by using a patch or duct tape to cover small holes and a staple gun to re-secure fabric to the stakes. Cut out and replace severely degraded sections, ensuring to overlap with existing silt fence. Replace stakes that have been broken, dislodged, or removed using a mallet or hammer Maintain once sediment accumulation reaches a depth of 1/3 of its height. Remove collected sediment using hand tools. Remove once the site reaches final stabilization. Fill, compact, and vegetate areas of ground disturbance to blend with adjacent ground and throw away waste. 19
20 Notes 20
21 21
22 Notes 22
23 Introduction Perimeter Control Compacted Earthen Berm Compacted earthen berms slow, pond, and divert stormwater flowing from construction sites, including ground disturbance, pollutant storage, and material stockpile areas. Approved compacted earthen berms consist of soil or stone. Contractors must consider their site s size, soil condition, and topography before selecting, sizing, and installing this BMP. Often, contractors use compacted earthen berms to divert stormwater to a sediment trap. Installation Requirements Install compacted earthen berms: before construction activities per the following specification installed with a height of 2 min. and width of 3 min. and ends turned upslope for 5 min. stabilized with crimped mulch or surface roughening Inspection and Maintenance Inspect compacted earthen berms weekly, before rain events, and after rain events to ensure they are functioning. If not, complete one of the following tasks: Repair washed out, eroded, and flattened compacted earthen berms. Repair with a piece of equipment or hand tool capable of excavating, contouring, and compacting back to its original design. Maintain once sediment accumulation reaches 1/3 of its height. Use equipment or hand tools to remove. Remove once the site reaches final stabilization. Fill, compact, and vegetate areas of ground disturbance to blend with adjacent ground. Image 12 Installed compacted earthen berm Image 13 Conveyance ditch and compacted earthen berm 23
24 Notes 24
25 25
26 Notes 26
27 Introduction Perimeter Control Sediment Trap Sediment traps capture and hold stormwater flowing from construction sites, including ground disturbance, pollutant storage, and material stockpile areas. Approved sediment traps consist of an excavated area with an armored overflow. Contractors must consider their site s size, soil condition, and topography before selecting, sizing, and installing this BMP. Installation Requirements Install sediment traps: before construction activities per the following specification installed with an overflow consisting of rip-rap underlain with a nonwoven geotextile designed with a volume of 1,890 cubic feet (70 CY) of storage per acre of contributing drainage area maximizing distance between the inlet and armored outlet to facilitate settling Inspection and Maintenance Inspect sediment traps weekly, before rain events, and after rain events to ensure they are functioning. If not, complete one of the following tasks: Repair washed out or eroded sediment traps. Repair with a piece of equipment or hand tool capable of excavating, contouring, and compacting back to its original design. Maintain once sediment accumulation reaches 2/3 of its height. Use equipment or hand tools to remove. Remove once the site reaches final stabilization or transition to post-construction BMP. Fill, compact, and vegetate areas of ground disturbance to blend with adjacent ground. Images 14 and 15 Sediment trap and armored overflow 27
28 Notes 28
29 **Note: Taken from MDT s December 2016 Erosion and Sediment Control Best Management Practices Manual 29
30 Notes 30
31 Introduction Infrastructure Protection Inlet Protection Inlet protection filters stormwater before flowing into the City s infrastructure. Inlet protection is the last line of defense, and the City requires its use to be in conjunction with other erosion and sediment control BMPs. Premanufactured devices designed to drop inside inlets are the only approved types. Multiple options exist online and at local retailers. Installation Requirements Install inlet protection: before construction activities per the manufacturer s specification Inspection and Maintenance Image 16 Properly installed drop inlet protection. Image taken from Inspect inlet control weekly, before rain events, and after rain events to ensure it is functioning. If not, complete one of the following tasks: Replace damaged inlet protection. Maintain by removing accumulated sediment using equipment or hand tools. Remove once the site reaches final stabilization. 31
32 Notes 32
33 Introduction Offsite tracking control removes sediment from vehicle tires before exiting construction sites. The City allows two types. Both utilize geotextile and 3-6 angular rock. One option includes a cattle guard platform. Contractors must consider their site s volume of traffic, underlying soil condition, and site constraints before selecting and installing this BMP. Approved Options 1. Install angular rock: Infrastructure Protection Tracking Control before construction activities per the following specification underlain with a geotextile for separation between undisturbed soils and rock surfaced with 1 min. depth of 3-6 angular rock designed with a length that allows two full tire rotations 2. Install cattle guard and cobble hybrid: before construction activities per the following specification underlain with a geotextile for separation between undisturbed soils and rock designed with a 12 min. by 20 min. cattle guard with sediment capture bay below surfaced with 1 min. depth of 3-6 angular rock Inspection and Maintenance Image 17 Properly installed cattle guard entrance Inspect tracking control weekly, before rain events, and after rain events to ensure it is functioning. If not, complete one of the following tasks: Maintain once the aggregate and cattle guard fill with sediment. Refresh the surface by turning over the aggregate. Remove once there is a permanently stabilized site entrance. Fill, compact, and vegetate areas of ground disturbance to blend with adjacent ground. 33
34 Notes 34
35 35
36 Notes 36
37 Introduction Infrastructure Protection Dewatering from Excavated Areas and Wells Dewatering controls manage and treat pumped water before it flows into infrastructure or waterways. Contractors must consider the expected volume of water, duration, and site condition before selecting and installing dewatering BMPs. Approved Options 1) Well Dewatering Used to lower the water table during utility line and foundation installation. Achieved through the use of well(s) and pumps tied together in a network that discharge to a predetermined location(s). Discharge location(s) may include waterways, stormwater infrastructure, or vegetated lands. Installation requirements include: placed within 15 x 15 undisturbed area contained initial turbid discharge (purging of well) reinforced discharge location preventing erosion 2) Excavation Dewatering Used to remove accumulated water from an excavation. Achieved through the placement of a pump in the excavation, which pushes water through a hose, filter, and then a predetermined discharge location(s). Discharge location(s) may include stormwater infrastructure and vegetated lands. Installation requirements include: Proprietary bag, cartridge, or media treatment unit with a 1 micron filter capability. Rain for Rent and Baker Corporation are examples of companies that manufacture treatment units capable of meeting this standard. Maintenance and Install Requirements Inspect routinely to ensure dewatering controls are functioning and resulting in a clear discharge. If not, halt dewatering immediately and: Image 18 Proprietary bag filtration unit Maintain treatment unit per manufacturer s recommendation. Monitor and Maintain discharge location(s) if any noticeable erosion is identified by moving the hose or refortifying the ground surface using 3-6 cobble or stone. Remove once the site reaches final stabilization and is no longer required. Fill, compact, and seed areas of ground disturbance to blend with adjacent ground. 37
38 Notes 38
39 39
40 Notes 40
41 Introduction Pollutant Management Concrete Washout and Waste Management Concrete washout is a toxic slurry generated from the washing of mixer chutes, pump trucks, and other masonry equipment. Contractors must consider their sites expected volume of washout and site constraints before selecting and installing one of the following approved BMPs. Approved Options 1) Reusable or Disposable Product 2) Prefabricated Roll Off or Container 3) Lined Below Ground Containment 4) Lined Above Ground Containment Installation Requirements Install concrete washouts: before concrete and masonry work per this manual or manufacturer s specification clearly marked with signage stating Concrete Washout Area of adequate capacity and structure to prevent spill and splash over Maintenance and Inspection Requirements Inspect concrete washouts before and after rain events to ensure they are functioning. If not, complete one of the following: Image 19 Reusable or disposable product Image 20 Prefabricated roll off Repair if the liner is leaking or washout is in a state of disrepair. Maintain when the facility reaches 75% capacity. Remove or evaporate clear washout water. Remove or recycle all solids and dispose into a roll off dumpster, haul trailer, or solid waste receptacle. Remove concrete washout once the site reaches stabilization and is no longer required. If applicable, fill, compact, and seed areas of ground disturbance to blend with adjacent ground. 41
42 Notes 42
43 43
44 Notes 44
45 45
46 Notes 46
47 Introduction Final Stabilization Measures Post Construction Feature A post construction feature is an engineered pond designed and constructed to capture, infiltrate, and treat polluted stormwater flowing from roads, yards, parking lots, and driveways. The proper installation, stabilization, and maintenance of a post construction feature is necessary to ensure it functions properly, reducing negative impacts on local waterways. Once excavated, the City requires that post construction feature s side slopes and basin bottoms are stabilized using an erosion control product. Installation Requirements Install erosion control product: immediately after the post construction is constructed throughout the entire feature, including side slopes and bottom per the following specification Maintenance and Inspection Requirements Contractors must inspect erosion control products before and after rain events to ensure they stay secured to the ground and adequately stabilize disturbed areas. If not, complete the following: Repair if the erosion control product has loosened, is no longer covering disturbed area, or is in a state of disrepair. Image 19 Properly stabilized post construction feature 47
48 Notes 48
49 **Note: Taken from MDT s December 2016 Erosion and Sediment Control Best Management Practices Manual 49
50 Notes 50
51 **Note: Taken from MDT s December 2016 Erosion and Sediment Control Best Management Practices Manual 51
52 Notes 52
53 Final Stabilization Measures Disturbed Area Introduction Stabilization measures reduce erosion, increase infiltration, shorten slope lengths, slow the flow of water, and minimize raindrop impact of disturbed areas during and after construction activities. Stabilization measures can be temporary or permanent depending on their type and application. Approved Options 1. Surface Roughening: Consists of 3 min. depressions running perpendicular to slopes using equipment, such as a grouser or sheep s foot. 2. Crimped Straw Mulch: Consists of weed-free straw with a 12 min. length evenly distributed at a rate of 4000 lbs/acre and crimped into the soil. Straw blowers and hand broadcasting are useful distribution methods. Flat shovels and disc plows work well for crimping. Image 20 Surface Roughening Image 21 Crimped Straw Mulch 3. Wood Mulching: Consists of shredded wood and compost evenly distributed. Apply wood mulch and compost to a depth of Rolled Erosion Control Products: Consists of biodegradable erosion control blanket composed of fibers such as jute, straw, coconut, or a combination of straw and coconut fibers. Installation criteria to consider: anchor slots, overlapping adjacent blankets, check dams, and staking. See page 47 for an installation specification. Image 22 Wood Mulching 5. Sod: Immediately stabilizes disturbed areas. Consider sod type, soil preparation, soil amendments, and irrigation until establishment. Image 23 Erosion Control Product 53
54 Notes 54
55 Single-Family Residential Single-Family Home Construction Site Protection Plan Stage of Construction and Timming of BMP Implementation # Minimum Expectation Stage 1 - Foundation Stage 2 - Utilities Stage 3 - Structure Stage 4 - Flat Work Stage 5 - Landscaping 1 Protect Inlets 2 Contain Disturbed Area 3 Mitigate Tracking 4 Control Concrete Waste 5 Contain Material Stockpiles 6 Manage Dewatering Flows Example BMPs Drop inlet protection // Cost: $100 (reusable) Foam wattle, straw wattle, silt fence, or earthen berm // Cost: $50 - $100 (reusable) Gravel drive entrance // Cost: $150 Prefabricated roll-off or lined container // Cost: $20-$30 Tarp or within perimeter control // Cost: $25-$50 Land apply or filter unit // Cost: ~$500 7 Stabilize Disturbed Area Sod // Cost: n/a Contain Disturbed Area Straw Wattle Control Concrete Waste Washout Bag Protect Inlets Drop Inlet Protection Manage Dewatering Flows Filter Unit Mitigate Tracking Gravel Drive Entrance Stabilize Disturbed Area Sod 55
56 Notes 56
57 Single-Family Residential Single-Family Home Construction Site Protection Plan 57
Best Management Practice (BMP) Guidance Manual
Best Management Practice (BMP) Guidance Manual INTRODUCTION BMP examples in this guide provide ways to meet erosion and sediment control requirements. Best Management Practices are not limited to these
More informationSingle Family Residential Construction Erosion/Sediment Control Standards
Single Family Residential Construction Erosion/Sediment Control Standards Introduction: This booklet contains standard plans and procedures sufficient for typical building construction. It is not intended
More informationConstruction Best Management Practices Handbook BEST MANAGEMENT PRACTICES
Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN
More informationCommon Construction-Site BMPs Quick Reference Guide
Common Construction-Site BMPs Quick Reference Guide Installation and Inspection Requirements For more information visit the Town of Truckee Clean Water Program Website: http://www.townoftruckee.com/engineering/clean-water-program
More informationInlet Protection. Fe= (Depends on soil type)
3.4 DESIGN CRITERIA: KEY CONSIDERATIONS Evaluate drainage patterns to ensure inlet protection will not cause flooding of roadway, property or structures Never block entire inlet opening Size according
More informationRock Sock (RS) Rock Sock height.
Rock Sock (RS) SC-5 Description A rock sock is constructed of gravel that has been wrapped by wire mesh or a geotextile to form an elongated cylindrical filter. Rock socks are typically used either as
More informationSection 208. SOIL EROSION AND SEDIMENTATION CONTROL
208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01. Description. This work consists of installing and maintaining erosion and sedimentation controls to minimize soil erosion and control
More informationStormwater Management Permit Application LESS Than One Acre. Public Works Department st Ave East Kalispell, Montana (406)
Public Works Department 201 1 st Ave East Kalispell, Montana 59901 (406) 758-7720 Note: This permit is separate from any permits required by the Montana Department of Environmental Quality. A State Stormwater
More informationAppendix B Construction SWPPP Short Form
Appendix B Construction SWPPP Short Form Projects falling within the thresholds listed below may use this short form instead of preparing a formal Construction Stormwater Pollution Prevention Plan (SWPPP).
More informationEROSION CONTROL GENERAL NOTES EC JAN 2017 C.B.
EROSION CONTROL GENERAL NOTES EC - 000 EROSION CONTROL GENERAL NOTES EC - 001 INSTALL TEMPORARY DRIVEWAY CULVERT IF THERE IS A ROADSIDE DITCH PRESENT EXISTING PAVEMENT OR APPROVED ACCESS POINT OR AS PRACTICABLE
More informationStorm Drain Inlet Protection
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
More informationPerformance Standards Compliance Checklist
Truckee Meadows Regional Stormwater Quality Management Program Performance Standards Compliance Checklist The checklist that follows identifies the BMPs that can be used at construction sites to meet each
More informationCity of Doral 8401 NW 53 rd Ter. Doral, FL 33166
City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 Project Address: (305) 593-6700 Permit Number: National Pollution Discharge Elimination System (NPDES) Construction Site Erosion and Sedimentation Control
More informationThe Good, The Bad, and The Ugly
Overview The Good, The Bad, and The Ugly Stormwater Regulations for the Construction Industry Seminar March 20, 2012 Wendy Terlizzi Arizona Department of Transportation Office of Environmental Services
More information2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1
2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 There are three ways to accomplish urban soil erosion and sedimentation control: Allow erosion to take place and then control sediment
More informationConstruction Stormwater Best Management Practices
Marin County Stormwater Pollution Prevention Program San Rafael, California November 12, 2015 Construction Stormwater Best Management Practices The mention or image of any product or service is for illustrative
More informationCity of West Sacramento Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects
Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects Project Name: Page intentionally left blank. - 2 - What is this document for? The City s Phase II MS4 NPDES General Permit
More informationOrganic Filter Tubes. Fe= (Depends on soil type)
3.6 Sediment Control Description: Organic filter tubes are comprised of an open weave, mesh tube that is filled with a filter material (compost, wood chips, straw, coir, aspen fiber, or a mixture of materials).
More informationIN T R A / M IN T R A M
SPRING MESA SUBDIVISION CONSTRUCTION PLANS A PART OF SECTION 35, TOWNSHIP 2 SOUTH, RANGELINE 70 WEST, 6th. PRINCIPAL MERIDIAN. CITY OF ARVADA, COUNTY OF JEFFERSON, STATE OF COLORADO COVER SHEET MARTIN
More informationCITY OF CHICO. Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects. Project Address: Building Permit Number:
CITY OF CHICO Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects Project Address: Building Permit Number: What is this document for? The City s Phase II MS4 NPDES General
More informationConcrete Waste Management
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
More informationAPPENDIX C DURING CONSTRUCTION BMP TABLES
APPENDIX C DURING CONSTRUCTION BMP TABLES Table C.1 Table C.2 Table C.3 Erosion Prevention BMPs Sediment Control BMPs Stormwater Runoff and Ground Control Measures STORM WATER QUALITY DESIGN MANUAL Appendix
More informationBuilding Better Storm Water Quality
Building Better Storm Water Quality s Storm Water Pollution Prevention Guidelines for Development Construction Projects City of El Segundo 350 Main Street (310) 524-2380 El Segundo, California 90245 Introduction
More informationMETROPOLITAN UTILITIES DISTRICT No Page: 1 of 10
Page: 1 of 10 A. GENERAL Erosion control measures such as silt fence, inlet filters and soil stabilization blankets and matting, incorporated into underground pipeline construction projects, help prevent
More informationSchedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw
Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw 6410 2006 The Erosion and Sediment Control plan should seek (i) to protect the soil surface from erosion where possible and (ii) capture
More informationProject Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering)
Compliance Assistance Program Checklist 1 Start of Construction Stormwater Self-Certification Checklist Note: This checklist must be completed and submitted to the DEM no later than 30 days after initiating
More informationConstruction Phasing Bad
Construction Entrances Construction Phasing Remove mud and dirt from the tires of construction vehicles before they enter a paved roadway. Propoerly size entrance BMP's for all anticipated vehicles. Make
More informationAPPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS
APPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS City of Bradenton January 2017 1 INTRODUCTION This appendix to the City of Bradenton Department of Public Works and Utilities Utility Specifications
More informationContractors, Illicit Discharges, & Best Management Practices. Chris Allen Stormwater Inspector
Contractors, Illicit Discharges, & Best Management Practices Chris Allen Stormwater Inspector What is an Illicit Discharge? Georgetown County Stormwater Ordinance defines an Illicit Discharge as: Any activity
More informationBest Management Practices (BMPs) for Construction Sites & Home Remodeling Projects
Best Management Practices (BMPs) for Construction Sites & Home Remodeling Projects Stormwater Program Department of Public Works City of Rancho Santa Margarita 22112 El Paseo Rancho Santa Margarita, CA
More informationUnderstanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)
Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department
More informationBowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP)
Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) SMP-11 PLANNING CONSIDERATIONS: Design Life: 1 yr Acreage
More informationWater Pollution Control for Work in Sensitive Areas
Water Pollution Control for Work in Sensitive Areas 10-1. WATER POLLUTION CONTROL The Contractor is advised that failure to fully comply with the provisions of this Section, and all requirements listed
More informationPost Construction Erosion Controls
Post Construction Erosion Controls Erosion Control Permanent Controls Native Vegetation Preservation Hydroseeding & Soil Stabilizers Soil Roughening Soil Stabilizers Geotextiles Vegetation is the Best
More informationPART 1 GENERAL REQUIREMENTS
PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...
More informationSECTION EROSION CONTROLS
SECTION 31 25 13 EROSION CONTROLS PART 1 GENERAL 1.1 SUMMARY A. Section Includes installing, maintaining and removing: 1. Silt Fence. 2. Temporary Construction Entrances. 3. Diversion Channels. 4. Sediment
More informationSECTION 11 PART I STORMWATER QUALITY PROTECTION Definitions / Acronyms 11-3 PART 1 CONSTRUCTION PRACTICES
SECTION 11 PART I STORMWATER QUALITY PROTECTION CONTENTS Page 11-1 Definitions / Acronyms 11-3 PART 1 CONSTRUCTION PRACTICES 11-2 Stormwater Pollution Prevention Plan (SWPPP) 11-3 11-3 Erosion and Sediment
More informationConstruction Site Runoff (CSR) Permit Application Permit Fee $150.00
Construction Site Runoff (CSR) Permit Application Permit Fee $150.00 Site Address or Lot and Subdivision: Applicant Name: Applicant s E-Mail: Applicant s Address: Telephone: (office) City, State, ZIP (cell)
More informationPHASE 1 UPDATES TO DESIGN AND CONSTRUCTION STANDARDS INITIAL DRAFT FOR. Chapter 6 EROSION PREVENTION AND SEDIMENT CONTROL
PHASE 1 UPDATES TO DESIGN AND CONSTRUCTION STANDARDS INITIAL DRAFT FOR Chapter 6 EROSION PREVENTION AND SEDIMENT CONTROL Reader Notes (1/18/17 draft) CWS has drafted proposed changes to Chapter 6 to incorporate
More informationSUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields
4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater
More informationCity of Glendale Stormwater Management Plan Checklist
City of Glendale Stormwater Management Plan Checklist Project: Title of Plan: Date: Date of Plan: Reviewer: Most Recent Revision: Criteria Yes No Identify a SWMP Administrator and an alternate - The SWMP
More informationBMP: Concrete Waste Management
BMP: Concrete Waste Management Prevent or reduce the discharge of pollutants to storm water from concrete waste by conducting washout off-site, performing on-site washout in a designated area, and training
More informationStraw Bale Barrier. - Along the face and at grade breaks of exposed and erodible slopes to shorten slope length and spread runoff as sheet flow
Straw Bale Barrier SE-9 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control
More informationStorm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water
Storm Water Permitting Requirements for Construction Activities John Mathews Storm Water Program Manager Division of Surface Water Why Permit Storm Water? Impacts During Construction Not an issue until
More informationErosion Control Inspection Form
Project Name Address Inspection Date Time Name of Certified Erosion Sediment Lead (CESCL) or qualified inspector if less than one acre Print Name: Approximate rainfall amount since the last inspection
More informationSTANDARD CONSTRUCTION DETAILS EROSION CONTROL REVISED - JANUARY 2018
STANDARD CONSTRUCTION DETAILS REVISED - JANUARY 2018 TABLE OF CONTENTS STORM WATER POLLUTION PLAN NOTES - - - - - - - - - - - - - - - - - - - - - - - - - SD-EC01 SILT FENCE NOTES - - - - - - - - - - -
More informationOutline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control
Inspecting Construction Site BMPs Kristin Kerr EOA, Inc. Outline of Presentation Back to Basics Erosion and Sediment Control Good Site Non-Stormwater Run-on and Run-off Control Construction Inspection
More informationFigure Inlet protection (Source: Minnesota DOT)
3.9 INLET PROTECTION Figure 3.14. Inlet protection (Source: Minnesota DOT) Overview Description: A manufactured protective device or barrier used to trap sediment at a storm drain surface or curb inlet.
More informationSediment Control Practices
Sediment Control Practices SMP-05 Temporary Diversions, Berms or Ditches Symbol TD Description These temporary drains offer features such as conveyance for runoff down cut or fill slopes, subsurface drains
More informationACTIVITY: Silt Fence ES 14
Targeted Constituents Significant Benefit Partial Benefit Low or Unknown Benefit Sediment Heavy Metals Floatable Materials Oxygen Demanding Substances Nutrients Toxic Materials Oil & Grease Bacteria &
More informationSTORM WATER POLLUTION PREVENTION PLAN TEMPLATE
STORM WATER POLLUTION PREVENTION PLAN TEMPLATE Cover Page Certifications Project, Owner, Operator, SWPPP Preparer, Date, Project Dates Signed by RIDOT (Owner) and CONTRACTOR (as Operator) of Contents Introduction
More informationCITY OF FARGO SPECIFICATIONS EROSION AND SEDIMENT CONTROL
EROSION AND SEDIMENT CONTROL PART 1 DESCRIPTION OF WORK The work to be completed under this section of the Specifications and the accompanying plans shall include all labor, materials, and equipment necessary
More informationHome Remodeling Projects
Should your project require a Standard Urban Stormwater Mitigation Plan (SUSMP), please see the City of Pomona s Standard Urban Stormwater Mitigation Plan (SUSMP) Pamphlet Best Management Practices For
More informationConcrete Waste Management
Objectives EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Objective
More informationEarth Dikes and Drainage Swales
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
More informationEROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY
31 25 00 EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY A. Erosion and sedimentation control shall be provided by the Contractor for all areas of the site denuded or otherwise disturbed
More informationConstruction Site Inspections
Construction Site Inspections Keep The Mud Out of The Creek Barry Tonning, Tetra Tech Inspections help to identify and correct problems! Inspection requirements Must inspect site every 14 days (LA) Some
More informationStraw Bale Barrier. Parallel to a roadway to keep sediment off paved areas
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
More informationPlanning & Building Department. Requirements for Erosion and Sediment Control
Planning & Building Department 455 County Center, 2nd Floor Redwood City, California 94063 Tel: 540/863-4161/Fax: 650/363-4849 Mail Drop PLN122 plngbldg@smcgov.org http://planning.smcgov.org Requirements
More informationSECTION B. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities.
SECTION 01 5713 TEMPORARY EROSION AND SEDIMENT CONTROL PART 1 GENERAL 1.01 SECTION INCLUDES A. Prevention of erosion due to construction activities. B. Prevention of sedimentation of waterways, open drainage
More informationCity of Daphne Standard Operating Guidance (SOGs) For Storm Drain System Management
Standard Operating Guidance (SOGs) For Storm Drain System Management Phase II MS4 Creating a Clean Water Future. Standard Operating Guidance (SOGs) For Storm Drain System Management The City of Daphne
More informationCITY OF URBANA CLASS 2 EROSION CONTROL PERMIT STANDARD DETAILS
CITY OF URBANA CLASS 2 EROSION CONTROL PERMIT STANDARD DETAILS CLASS 2 EROSION CONTROL PERMIT STANDARDS TABLE OF CONTENTS EROSION CONTROL PRACTICES FLOW CHART 1 EROSION CONTROL PERMIT FORM 2 EXAMPLE EROSION
More informationSTANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL
STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL Section Number Title 801 GENERAL 802 STANDARD METHODS OF EROSION AND SEDIMENT
More informationEROSION CONTROL REQUIREMENTS
COMMUNITY DEVELOPMENT DEPARTMENT BUILDING DIVISION 345 N. El Dorado Street Stockton, CA 95202 209-937-8561 Fax 209-937-8893 www.stocktongov.com EROSION CONTROL REQUIREMENTS PROJECT INFORMATION: Permit
More informationGENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ
GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ *THE BELOW NOTES ARE COMMONLY USED IN SE&SC PLAN APPLICATIONS THE NOTES MAY BE EDITED AS APPROPRIATE FOR PROJECT BEING DEVELOPED
More informationB. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies.
The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language
More informationPlease print or type.
SOIL EROSION AND SEDIMENTATION CONTROL PERMIT APPLICATION 6-18-07 Ann kjjkjkff- ANN ARBOR CHARTER TOWNSHIP 3792 Pontiac Trail, Ann Arbor, Michigan 48105-9656 Phone (734) 663-3418 Website: www.aatwp.org
More informationSE-6 GRAVEL BAG BERM. Objectives. Potential Alternatives
Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Materials and Waste Management - WM DESCRIPTION AND PURPOSE A gravel
More informationSECTION EROSION AND SEDIMENTATION CONTROLS
SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL
More informationKristin Kerr EOA, Inc. Construction Inspection Workshop February 1, 2017
Construction Site Inspection Checklist Kristin Kerr EOA, Inc. Construction Inspection Workshop February 1, 2017 Inspection Checklist Required to track data on checklist electronically Illicit Discharge
More informationA. Each Contractor shall comply with the requirements outlined in these documents.
Section 000700 Stormwater Management Plan for Aurora Public Schools PART 1 GENERAL 1.0 DESCRIPTION A. Each Contractor shall comply with the requirements outlined in these documents. PART 2 PRODUCTS Not
More informationTypical Local Erosion Control Requirements (Storm Water Management Authority, Inc.)
Module 2: Selection of Controls and Site Planning for Construction Site Erosion Prevention Robert Pitt Department of Civil, Construction, and Environmental Engineering University of Alabama Tuscaloosa,
More informationADDENDUM NUMBER TWO. A. SECTION ADVERTISEMENT FOR BIDS 1. REVISE Sealed Bid Date/Time/Location paragraph to read as follows:
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS SECTION 00 91 11.02 ADDENDUM NUMBER TWO June 22, 2016 TO: PLANHOLDERS SUBJECT: PCT TRUCK STAGING PROJECT PROJECT NO. 091606 CONTRACT NO. 070287 This
More informationPreventing Storm Water Pollution: What We Can Do. ~Fleet Maintenance~
~Fleet Maintenance~ FUELING GENERAL GUIDELINES DISPOSAL METHODS Maintain vehicles and equipment in designated areas. Clean fueling areas often using approved methods. DO NOT top off fuel tank. Know location
More informationConstruction Entrance / Construction Road Stabilization Alturnamats & Versamats Dewatering Dandy Dewatering Bag / Dirt Bag...
CONTENTS Construction Entrance / Construction Road Stabilization... 1 Alturnamats & Versamats... 1 Dewatering... 8 Dandy Dewatering Bag / Dirt Bag... 8 Diversion Dike... 10 Diversion Dike of Compacted
More informationInstallation and Maintenance of Erosion Control BMPs
Installation and Maintenance of Erosion Control BMPs Or Common BMPs Applications Specifications Installation Problems Maintenance Utility Design Professionals Clarifications, proactive problem solving
More informationPart IV(b) Best Management Practices for Erosion, Sediment, and Velocity Control Continued. Good Housekeeping Practices
Part IV(b) Best Management Practices for Erosion, Sediment, and Velocity Control Continued Good Housekeeping Practices Inlet Protection Consist of a variety of manufactured sediment barriers and products
More informationChapter 2: Selecting Best Management Practices (BMPs)
Chapter 2: Selecting Best Management Practices (BMPs) 2.1 - Temporary versus Permanent BMPs The same level of care should be taken to select both temporary BMPs and permanent BMPs. The same level of care
More informationTown of Friday Harbor PO Box 219 / Friday Harbor / WA / (360) / fax (360) /
Town of Friday Harbor PO Box 219 / Friday Harbor / WA / 98250 (360) 378-2810 / fax (360) 378-5339 / www.fridayharbor.org LAND CLEARING, GRADING, OR FILLING PERMIT APPLICATION APPLICATION DATE GRD No. APPLICANT/FRANCHISE
More informationNo. 6 December, Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads
No. 6 December, 1995 Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads Steve Holaday, Wisconsin Dept. of Natural Resources, and Jeff Martin, Dept. of Forestry, UW-Madison BMPs
More informationBlock and gravel filters can be used where velocities are higher. Reduces the amount of sediment leaving the site.
INLET PROTECTION From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.state.ma.us/dep/brp/stormwtr/files/esfull.pdf Definition: A sediment filter or an excavated
More informationEXAMPLES OF GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ
EXAMPLES OF GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ *THE BELOW NOTES ARE EXAMPLES OF COMMONLY USED IN SE&SC PLAN APPLICATIONS THE NOTES MAY BE EDITED AS APPROPRIATE FOR
More informationDiversion Dikes. Fe=0.95
2.2 Diversion Dike Erosion Control Description: A diversion dike is a compacted soil mound, which redirects runoff to a desired location. The dike is typically stabilized with natural grass for low velocities
More informationEROSION CONTROL AND GRADING PERMIT APPLICATION
EROSION CONTROL AND GRADING PERMIT APPLICATION COMMUNITY DEVELOPMENT DEPARTMENT 1735 MONTGOMERY STREET OROVILLE, CA 95965 530-538-2420 FAX (530) 5382426 www.cityoforoville.org APPLICATION DATE PERMIT FEE
More informationWAKULLA SITE PLANNING
WAKULLA CIVIL SURVEYING SITE PLANNING TRAFFIC CONTROL PLAN WAKULLA ARRAN ROAD WIDENING & RESURFACING UTILITY CONTACT LIST NO. DATE: APPR. REVISION: DATE: CIVIL SURVEYING SITE PLANNING GENERAL NOTES WAKULLA
More informationPaving and Grinding Operations
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
More informationCity of El Centro. Erosion and Sediment Control Plan Review Checklist. Reviewer: Review Date:
City of El Centro Erosion and Sediment Control Plan Review Checklist Project: Reviewer: Review Date: If an item below is marked No, the Erosion and Sediment Control Plan (Plan) either does not provide
More informationSECTION STORMWATER POLLUTION PREVENTION
PART 1 - GENERAL 1.01 WORK INCLUDED SECTION 02133 STORMWATER POLLUTION PREVENTION A. Prohibit illicit discharge (non-rainwater) into the storm drain system. B. Construct any and all necessary systems to
More informationLAND DISTURBANCE PERMIT
SPRINGVILLE CITY Application Date: 110 South Main Springville, UT 84663 Permit Number: (801) 491-2780 Caselle #2208 Project Name: Project Address: LAND DISTURBANCE PERMIT Priority Site Owner s Name Phone
More informationSECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY
1. PURPOSE: SECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY The purpose of this policy is to establish procedures to facilitate compliance with federal, state and local stormwater regulations
More informationSECTION EROSION AND SEDIMENTATION CONTROL
SECTION 02160 EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.1 RELATED DOCUMENTS A. The Contractor shall be held to have read all Bidding Requirements; all of the General Conditions and Supplementary
More informationThe Construction General Permit and Erosion Prevention and Sedimentation Control
The Construction General Permit and Erosion Prevention and Sedimentation Control Presented at the Tennessee Gas Association Conference April 23, 2008 More than thirty years ago, two-third of the nation's
More informationStorm Water Pollution Prevention Plan (SWP3) Checklist
. Summit Soil and Water Conservation District Storm Water Pollution Prevention Plan (SWP3) Checklist Modified from the Ohio EPA SWP3 Checklist (Revised January 2017) SITE NAME: REVIEWER: DATE RECEIVED:
More informationSECTION 903 EROSION CONTROL
SECTION 903 EROSION CONTROL Delete this Section in its entirety and replace with the following: SECTION 903 EROSION CONTROL 903-1 DESCRIPTION: This work consists of providing all; administrative, labor,
More informationMINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014
MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341 Adopted April 24, 2014 Effective June 6, 2014 EROSION CONTROL RULE 1. POLICY. It is the policy of
More informationConcrete Waste Management WM-8
Standard Symbol BMP Objectives Soil Stabilization Sediment Control Tracking Control Wind Erosion Control Non-Storm Water Management Materials and Waste Management Definition and Purpose Appropriate Applications
More informationTips with Creation of your Erosion and Sediment Control Plan
Tips with Creation of your Erosion and Sediment Control Plan By Chris Droste, CESCO Senior Erosion Control Specialist Westmoreland Conservation District Forming Your Narrative Use the DEP checklist. Page
More informationCITY UTILITIES DESIGN STANDARDS MANUAL
CITY UTILITIES DESIGN STANDARDS MANUAL () September 2017 Page Chapter 1 Acronyms and Definitions 1.01 Purpose 1 1.02 Acronyms 1 1.03 Definitions 3 Chapter 2 Introduction 2.01 Purpose 1 2.02 Applicability
More information2010 California Green Building Standards Code. Residential and Non-Residential Development
2010 California Green Building Standards Code Residential and Non-Residential Development Stormwater Management (Site Development) Requirements Engineering, Surveying & Permit Services Department 2700
More informationSC-07 STORM DRAIN INLET PROTECTION
Greenville County Technical Specification for: SC-07 STORM DRAIN INLET PROTECTION 1.0 Storm Drain Inlet Protection 1.1 Description Provide Storm Drain Inlet Protection at all existing and newly installed
More information