1 Page 1 of 4 Quality Control Checklist Index Interim Turnover Check List THIS CHECKSHEET IS NOT INTENDED TO BE ALL INCLUSIVE BUT TO BE A GUIDE TO CRITICAL ISSUES AND CAUSE QUESTIONS TO BE ASKED. 1. Gilbane, Trade Contractor and Owner agree on any subdivision of the facility for partial occupancy, where required. 2. CM and Trade Contractor agree on what is required to be turned over to allow the beneficial use of the spaces/equipment in each identified area. Mechanical space and equipment. Access routes for Owner and Trade Contractor. Safety considerations for occupants. Safety considerations for Trade Contractor personnel in occupied areas. Security control for Trade Contractor and Owner personnel. Maintenance and operation responsibilities. 3. Trade Contractor completes the physical construction. Trade Contractor final examines work for conformance to requirements. Trade Contractor correct errors and omissions found. 4. Gilbane maintains the Rolling Completion List (RCL) of items requiring action for conformance to requirements. Trade Contractor completes RCL items. RCL signed off by Trade Contractor and Gilbane. 5. Owner and A/E inspect work and items found added to RCL. 6. Trade Contractor notifies Gilbane in writing that work is complete and ready for final inspection. Trade Contractor includes a list of outstanding RCL items with explanation of
2 Page 2 of 4 why each is not complete. Trade Contractor includes completion schedule for each item. 7. Gilbane concurs with the Trade Contractor's notice or: Gilbane notifies the Trade Contractor of disagreement with status. Gilbane notifies the Trade Contractor of RCL items remaining that are not acceptable for the Final RCL. Trade Contractor remedies the objections and requests final inspection again. 8. Gilbane requests Final RCL inspection to Owner including: Description of the work, equipment, systems, interiors or the like to be inspected. Location description by building, floor, room. Any limiting information required to clarify scope the scope of the inspection. Any outstanding RCL items with explanation and schedule for completion. 9. Gilbane, Owner, Trade Contractor and A/E when available make Final RCL inspection of work. Include review of all components and system operation. Identify RCL items to complete prior to interim turnover. Gilbane issue official Final RCL. Include if not complete. 1. Incomplete RCL items. 2. Identification tagging and labeling. 3. Material certifications. 4. Standard test reports and/or test acceptance documents. 5. Specific report of all unique tests required by the design documents. 6. Executed motor check out sheets. 7. Signed off RCL and A/E errors and omission logs.
3 Page 3 of 4 8. Documentation and/or schedule of training. 9. Executed local regulatory agency documentation. 10. As-built drawings, including marked prints of Architects contract documents and approved shop drawings or as required. 11. Control documentation and diagrams. 12. Operation and maintenance manuals. 13. Warranties Start dates and duration. Manufacturer, vendor, subcontractor, trade contractor name, telephone number and contact person. List of any spare parts/attic stock turned over to Owner. For systems subject to validation, all original backup documentation created in the construction and installation process. 10. Gilbane fills out Certificate of Substantial Completion (CSC) Assign an identification number Get Owner and A/E concurrence with date of substantial completion. List all warranty start dates different from the Substantial Completion date. Include completion schedule of Final RCL items. Project Manager execute. 11. Gilbane fills out Interim Turnover Notice (ITN) Assign same number as CSC Include any Red Tag's required for equpment being turned over. Project Manager execute. Submit to Owner with backup documentation. 12. Owner reviews, approves and returns to Gilbane. 13. Gilbane notify Trade Contractor ('s):
4 Page 4 of 4 Confirm turnover and warranty start dates. Identify Owner/Gilbane requirements for access. Send copies of Substantial Completion Certificate and Interim Turnover Notice. Send copy of official Final RCL. 14. Trade Contractor ('s) confirms schedule of completion of Final RCL items. Trade Contractor ('s) submits request for reduction in retainage. Value of Final RCL items withheld from line items for future payment. Trade Contractor completes items as scheduled. Final RCL signed off by Trade Contractor, Gilbane and Owner 15. Gilbane approves value of Final RCL items. Twice value withheld in line items for payment. Forward the retainage reduction to Owner for approval. Requisition for Final RCL items approved after Gilbane approval of completion.
5 Date: October 29, 2002 Project Name GBCo Job# FINAL ACCEPTANCE LETTER Description: All work contracted under XXXXX Trade Contract Agreement No. XXXX between Gilbane and XXXXX Contractors including all contract amendments thereto and further defined as Bid Package XX Warranty Start Date: MM/DD/YYYY This Final Acceptance Letter is issued with reference to Article 9.10 (Final Completion and Final Payment) of the General Conditions of the Contract for Construction AIA document A203, 1990 Edition, between Gilbane and the XXXXXXX. The portion of the Work described above is complete and is in compliance with the requirements of the Drawings and Specifications. All requirements of Article 9.10 have been met and any required documentation is attached. It shall remain the Trade Contractor s responsibility to perform any warranty work during the warranty period. The issuance of this Final Acceptance Letter shall be deemed to be Owner s acknowledgement of satisfactory completion of the portion of the Work described above and shall authorize the release of Final Payment in accordance with Article 9.10 of the General Conditions of the Contract for Construction. Gilbane Building Company: XXXXXXXXX: Construction Manager Date Owner Date XXXXXXXXX: XXXXXX: Applicable A/E Date Trade Contractor Date
Pre-Construction Meeting Minutes
Project Name Project # Project Address Tel: Fax: Gilbane Building Company Pre-Construction Meeting Date Start End Next Meeting Next Time Prepared By Company Purpose Location Next Location General Notes
More informationUSDA - RURAL DEVELOPMENT. Construction Bid, Contracts, Meetings, Change Orders, Closeout
USDA - RURAL DEVELOPMENT Construction Bid, Contracts, Meetings, Change Orders, Closeout RURAL DEVELOPMENT REGULATIONS website http://www.rurdev.usda.gov/home.html State Engineer s Role in Construction
More informationA62 UT PRE-CONSTRUCTION MEETING AGENDA
Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:
More informationA62 PRE-CONSTRUCTION MEETING AGENDA
Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:
More informationG , Request for Proposal Land Survey
G601 1994, Request for Proposal Land Survey AIA Document G601 1994 allows owners to request proposals from a number of surveyors based on information deemed necessary by the owner and architect. G601 1994
More informationAttachment 04 Substantial and Final Completion Approval Form. Project Description Project # Date of Completion Permit # Project Manager Phone #
UCF Design, Construction, and Renovation Standards Attachment 04 Substantial and Final Completion Approval Form Project Description Project # Date of Completion Permit # Phone # Intent: This Substantial
More informationChapter 6, Construction
Chapter 6, Construction CHAPTER CONTENTS 6.1 OWNER-CONTRACTOR AGREEMENT A. Preparation B. Owner Signature C. Award 6.2 PRE-CONSTRUCTION CONFERENCE A. Administration B. Attendees C. Pre-Construction Conference
More informationPre-Construction Conference Discussion Guide
Pre-Construction Conference Discussion Guide This guide is a summary of the topics normally required at the Pre-Construction Conference based upon the Tennessee Board of Regents Designers Manual standard
More informationAPPENDIX D CONSTRUCTION PHASE CRITERIA
A. GENERAL REQUIREMENTS CONSTRUCTION PHASE CRITERIA For the Construction Phase of the Project, the Architect/Engineer (A/E) is responsible for providing project administration for the Owner in accordance
More informationVILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information
VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES Part I: Proposal Information A General Information The Village of Vernon Hills is soliciting proposals for construction
More informationAIA Contract Documents: Retail Price List
A Series (Owner-Contractor) Documents The Prices Below are for Single Purchases and Do Not Include Shipping, Handling and Tax AIA Contract Documents: Retail Price List A101-2007 Standard Form of Agreement
More informationThe construction phase, of course, is the execution of the work as required by the contract documents when the building is finally built.
L1C4: Commercial Building Fundamentals Lesson 7 Study Guide Construction The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally
More information(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet
(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet Project Name: UM Project # Design Professional: Meeting Place: Meeting Time:
More informationAudio Sessions. Session 5 MEETINGS. Construction Contract Administration Education Program
Audio Sessions Session 5 MEETINGS Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org This presentation
More informationOwner s Representative SCOPE OF SERVICES
Owner s Representative SCOPE OF SERVICES Scope of Services DeMaria s steady growth has enabled the construction of more sophisticated buildings through various methods and services. As your Owners Representative,
More informationPROJECT NAME SECTION GENERAL COMMISSIONING REQUIREMENTS
PART 1 - GENERAL 1.1 SUMMARY A. The Owner has contracted an independent Commissioning Authority. The Commissioning Authority is an independent and knowledgeable third party, hired to verify that the systems
More informationAppendix D University of Maine System. Supplementary Requirements to AIA Document B Standard Form of Architect s Services
Appendix D University of Maine System Supplementary Requirements to AIA Document B201-2007 Standard Form of Architect s Services This document provides the Architect s scope of services only and must be
More information[JURISDICTION] S AMENDMENTS TO AIA DOCUMENT B , STANDARD FORM OF ARCHITECT S SERVICES: DESIGN AND CONTRACT ADMINISTRATION
[JURISDICTION] S AMENDMENTS TO AIA DOCUMENT B141-1997, STANDARD FORM OF ARCHITECT S SERVICES: DESIGN AND CONTRACT ADMINISTRATION ARTICLE 2.1. PROJECT ADMINISTRATION SERVICES. Paragraph 2.1.2. Paragraph
More informationREQUEST FOR PROPOSAL. Construction Management Services Not at Risk
REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk
More informationINSTRUCTIONS FOR USING THE MICHIGAN SCHOOL BUSINESS OFFICIALS ( MSBO ) PROTOTYPE FORM OWNER/ARCHITECT AGREEMENT WITH CONSTRUCTION MANAGER COORDINATION
INSTRUCTIONS FOR USING THE MICHIGAN SCHOOL USINESS OFFICIALS ( MSO ) PROTOTYPE FORM OWNER/ARCHITECT AGREEMENT WITH CONSTRUCTION MANAGER COORDINATION Please be advised that the purpose of this Instruction
More informationATTACHMENT D SCOPE OF SERVICES
ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.
More informationAPPLICABILITY/ACCOUNTABILITY:
SUBJECT: Effective Date: Procedure Number: Substantial and Final Completion 10/31/16 FS 2016 FS0021 Supersedes: Page Of 1 4 Responsible Authority: Associate Vice President, Administration and Finance (Facilities
More informationDUKE UNIVERSITY CONSTRUCTION STANDARDS
1 23 08 00 Commissioning of HVAC Systems 1. GENERAL A. GENERAL PROVISIONS 1. Drawings and general provisions of the Contract, including General Conditions and Division - 1 Specifications Sections, apply
More information1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES
TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING
More informationActivation, Transition & Close Out Step 7. July 13, 2012
Activation, Transition & Close Out Step 7 July 13, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES
SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 032 TITLE: SQS PLAN AND SURVEILLANCE PROCESS
More informationDocument B252TM 2007
Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation
More informationChapter 1, Introduction
Chapter 1, Introduction CHAPTER CONTENTS 1.1 THE DESIGNERS MANUAL A. Purpose B. Contents 1.2 THE DIVISION OF FACILITIES PLANNING 1.3 THE UNIVERSITY AS OWNER A. The Owner B. Owner Agency 1.4 CAPITAL IMPROVEMENTS
More informationContract No DFW Fire Station #5 HVAC System Replacement. Document Title: TABLE OF CONTENTS Section:
Document Title: TABLE OF CONTENTS Section: 00 01 10 Incorporated into the contract documents will be the Dallas Fort Worth International Airport Standard Technical Specification Book: Published June 01,
More informationManage Deliverables - Construction Step 6 February 2015
Manage Deliverables - Construction Step 6 February 2015 1 Construction Phase Step 1: Needs Development Step 2: Scope Development Step 3: Selection of Design Team Step 4: Design Phase Step 5: Selection
More informationSECTION SUBSTITUTION PROCEDURES
SECTION 01 25 00 SECTION 01 25 00 PART ONE: GENERAL 1.1 Related Documents 1.1.2 Construction Documents and general provisions of the Agreement Between Owner and Construction Manager and consultant and
More informationCONTRACT SERVICES PHASE 1: PRE-CONSTRUCTION
PHASE 1: PRE-CONSTRUCTION Schematics Phase Based upon program requirements and design parameters, D&J will establish conceptual budget and preliminary schedule for the project, which will highlight specific
More information1.07 SUPPLEMENTS PRODUCTS (NOT USED) EXECUTION (NOT USED) END OF SECTION
1.07 SUPPLEMENTS d. Complete using typewriter or electronic printing. 3. Include detailed lubrication instructions and diagrams showing points to be greased or oiled; recommend type, grade, and temperature
More informationOPERATING POLICY MANUAL
Page 1 of 7 Section 1. PURPOSE This policy is to explain the review process that the Bedford Regional Water Authority ( Authority ) utilizes for water and sewer developer projects planned within the service
More informationREQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components
REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility RFP Components CLIENT: TradePort International Corporation, Operators of John C. Munro
More informationDRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL
1.1 GENERAL When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and maintain an effective Quality Control Program that details the methods and
More informationGuidelines. Facility Permit
Facility Permit Guidelines The Vancouver Airport Authority (YVRAA) operates its own building or construction permit process called the Facility Permit (FAP) process. Facility Permits are required for all
More informationINSPECTION SYSTEM REQUIREMENTS
MILITARY SPECIFICATIONS MIL-I-45208A INSPECTION SYSTEM REQUIREMENTS This specification has been approved by the Department of Defense and is mandatory for use by all Agencies. 1. SCOPE 1.1 Scope. This
More informationSECTION CONTRACTOR QUALITY CONTROL
SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within
More informationRequest for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION
Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION May 19, 2015 The Addison Public Library invites you to submit a reply to this Request for
More informationProcedure Yes; No; greater than
Procedure 1. Project manager (PM) notifies facilities information coordinator of forecasted substantial completion date one month prior to reaching substantial completion. 2. PM completes the project information
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES
SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:
More informationWest Valley Library Parking Lot Repair with Porous Asphalt
RFQ-066 Request for Quote for West Valley Library Parking Lot Repair with Porous Asphalt Susan Miller Facilities Manager Yakima Valley Libraries April 3, 2017 RFQ NAME: ISSUING AGENCY: West Valley Library
More informationTITLE 15: BUILDINGS AND CONSTRUCTION GENERAL PROVISIONS
TITLE 15: BUILDINGS AND CONSTRUCTION Chapter 15.01 GENERAL PROVISIONS 15.02. OREGON MECHANICAL SPECIALTY CODE ADOPTION 15.04. DANGEROUS BUILDINGS CODE 15.05. UNIFORM CODE FOR BUILDING CONSERVATION 15.06.
More informationOWNER USER INTEGRITY MANAGEMENT SYSTEM WRITTEN DESCRIPTION CHECKLIST AB-512(b)
Company Name: Written Description of QMS Title and Rev. Status: Person who is responsible for preparing the owner s QMS written description: Name: Title: Telephone No.: ( ) Fax No.: ( ) Cell No.: ( ) E-Mail:
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September
More informationCONSTRUCTION PROCEDURES MANUAL PROJECT
CONSTRUCTION PROCEDURES MANUAL ADMINISTRATIVE SCHOOL DISTRICT #1 BEND LaPINE PUBLIC SCHOOLS (DATE) Page 1 ADMINISTRATIVE SCHOOL DISTRICT #1 BEND LaPINE PUBLIC SCHOOLS TABLE OF CONTENTS CONTENTS PAGE: 1.0
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES
SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SECTION: WSIP CONSTRUCTION MANAGEMENT PROCEDURE NO.: 010 TITLE: APPLICATIONS FOR PAYMENT APPROVED:
More informationA101 Standard form of agreement between Owner and Contractor-Stipulated sum with instruction sheet wrapped (2017) $55.98
Please note new address! 310 SE 1 Street Miami, Fl 33131 QUESTIONS ABOUT AIA DOCUMENT CONTENT docinfo@aia.org 202.626.7526 Contact: Marilyn Lugo 305.448.7488 WEB: www.aia.org/contractdocs/reference A SERIES
More informationSECTION CLOSEOUT PROCEDURES
SECTION 017700 - PART 1 - GENERAL 1.1 SUMMARY A. Section includes requirements for contract closeout, including, but not limited to, the following: 1. Substantial Completion procedures. 2. Final Completion
More informationWebinar Project Close Out. December 14, 2017 / 10:00 - Noon
Welcome to Project Close Out We will begin shortly. (for higher quality, dial a number based on your current location) To listen to this webinar: 1.669.900.6833 or + 1.408.638.0968 Access Code: 393.375.631
More informationChapter 3 Other Stakeholders Duties
Chapter 3 Other Stakeholders Duties Everyone involved in the special inspection process has a responsibility to perform their agreed upon duties correctly and in a timely fashion during the project. In
More informationState Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund
State Historic Preservation Office Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund April 2014 Table of Contents Conflict of Interest... 3 Floodplains... 3 Hazardous
More informationSPECIAL SPECIFICATION 1184 Testing, Training, Documentation, Final Acceptance, and Warranty
1993 Specifications CSJ 0074-05-086, etc. SPECIAL SPECIFICATION 1184 Testing, Training, Documentation, Final Acceptance, and Warranty 1. Description. Perform or furnish testing, training, documentation,
More informationTownship of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement
Township of Severn REQUEST FOR PROPOSAL Architectural & Professional Services Fire Station Replacement Deadline for proposal submission is June 15, 2017 at 2:00 p.m. Contact Person: Tim Cranney Director
More informationContents. 1. Certification of Materials 2. Supply of Materials
September 2013 1 Contents 1. Certification of Materials 2. Supply of Materials 2 1. CERTIFICATION OF MATERIALS The European standard which specifies the different types of inspection documents supplied
More informationNTA Metropolitan Mass Transit System. To: All Bidders Re: Tender 055/2017 for the Signaling and Train Control of the Red Line Project. Addendum No.
Date: 12 th July 2017 #1069265 To: All Bidders Re: Tender 055/2017 for the Signaling and Train Control of the Red Line Project Addendum No. 5 Addendum no. 5 is issued for inclusion into the tender documents.
More informationAIA Contract Documents
AIA Contract Documents Availability by series Series Document # Former # Document Title Family Software Paper DOD aia.org A101 2007* A101 2007 SP* A101 2017 A102 2007* A111 1997 A102 2017 A103 2007* A114
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.00 10 (November 2016) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 00.00 10 (February 2010) UNIFIED FACILITIES GUIDE
More informationNote #2: Refer to Commercial Permitting Handbook 2016 Denver Building and Fire Code for asbestos regulations.
CITY & COUNTY OF DENVER COMMUNITY PLANNING & DEVELOPMENT BUILDING PERMIT POLICY Subject: PREPARATORY DEMOLITION, NON-STRUCTURAL FRAMING, ELECTRICAL, MECHANICAL, PLUMBING, FIRE SUPPRESSION, AND FIRE ALARM
More informationBUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME
BUILDING ENCLOSURE COMMISSIONING PLAN For The PROJECT NAME Building Enclosure Commissioning Plan Overview The purpose of the Building Enclosure Commissioning Plan is to provide a clear and concise roadmap
More informationDIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE
DIVISION 1 GENERAL REQUIREMENTS SECTION 01 32 16 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. All drawings and technical specifications, Notice to Bidders, Instructions and Information to Bidders, Bid Proposal
More informationSubmission, Review and Approval of Construction Documents Submission and Review of a Completed Application for Permit
Building Code The Florida State University Building Code Administration Program (BCA) was established in 2001 and is responsible for ensuring that all construction activities on FSU owned facilities are
More informationROLES AND RESPONSIBILITIES
Audio Sessions Session 2 ROLES AND RESPONSIBILITIES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationBULLETIN 34: BUILDING ENVELOPE SERVICES APPROPRIATE PROFESSIONAL PRACTICE
200-4010 Regent Street Burnaby BC V5C 6N2 Canada Telephone: (604) 430-8035 Toll Free Canada-wide: 1-888-430-8035 Facsimile: (604) 430-8085 BULLETIN 34: BUILDING ENVELOPE SERVICES APPROPRIATE PROFESSIONAL
More informationDocument B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition
Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN
More informationStandard Form of Agreement Between Owner and Contractor where the basis
AIA Rochester - A Chapter of The American Institute of Architects 205 St. Paul Street, 1st Floor, Rochester, NY 14604 (585) 232-7650Telephone Office Hours: Monday Friday 9:00AM 2:00 PM Please call before
More informationDESIGN AND CONSTRUCTION STANDARDS OUTLINE SPECIFICATIONS
SECTION 01 91 13 GENERAL COMMISSIONING REQUIREMENTS GENERAL The University of South Alabama is officially and formally committed to the concept of Commissioning all new buildings and major renovations.
More informationInstallation of sanitary sewers, storm sewers and water piping requires the issuance of a Building Permit prior to commencement of installation.
Development and Infrastructure Department 50 Dickson St., 3rd Floor, P.O. Box 669 Cambridge, Ontario. N1 R 5W8 519.621.0740; TTY 519.623.6691 Site Service Installation - Rational Sampling Program RE: Building
More informationPROCEDURE FOR REQUESTING A BUILDING PERMIT
PROCEDURE FOR REQUESTING A BUILDING PERMIT A. CHECKLIST OF REQUIREMENTS FOR BUILDING PERMIT APPLICATION: The following checklist indicates the requirements based on the type of Building Permit being requested.
More informationAcceptance and Testing for Quality Turnover to Sustainable Operations & Maintenance
Acceptance and Testing for Quality Turnover to Sustainable Operations & Maintenance PAUL M. RASCHILLA, PARTNER M B A, E P M, C H C, C B C P, L E E D A P, C M V P, C S D P AKF GROUP LLC AKF Group LLC is....
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction February 26, 2015 Re: Request for Proposals- Commissioning Services College of Public Health Building - Fit Out Fifth Floor University of Iowa The
More informationSECTION QUALITY CONTROL
SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.
More informationSECTION BASIC ELECTRICAL REQUIREMENTS
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions, apply to work of this section. 1.2 SUMMARY A. This section specifies
More informationAIA Contract Documents Price List
The American Institute of Architects AIA Contract Documents Price List All products may be purchased from your local AIA Contract Documents Distributor or by calling (800) 365-2724 1/9/2018 Document No.
More informationDocument B101 TM. Standard Form of Agreement Between Owner and Architect
Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year Two Thousand and BETWEEN the Architect s client identified as the Owner: Capitol
More informationCapital Projects Group Mechanical Work Commissioning Specification
Capital Projects Group Mechanical Work Commissioning Specification Specification 20 05 40 Revision 0 Date: August 2018 Mechanical Work Commissioning Specification Specification 20 05 40 Publication Date:
More informationFlorida Cleanroom Systems
Florida Cleanroom Systems Design Build Projects / Project Quality Control Plan (PQCP) Quality Control / Quality Assurance Manual May 2010 1 TABLE OF CONTENTS Section 1: Introduction 3 1.1 Defining Plan
More informationFacilities Planning and Construction (FP&C)
Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:
More informationCommunications Contractor QA/QC Plan Sample
Communications Contractor QA/QC Plan Sample Selected pages (not a complete plan) QA/QC Plan Sample Project-Specific Quality Plan Quality Manual Communications Standards & Inspection Forms Contact: Ed Caldeira
More informationAIA Contract Documents
AIA Contract Documents Availability by series Series Document # Former # Document Title Software Available at AIAOC DOD aia.org A101 2007* A101 2007 SP* A101 2017 A102 2007* A111 1997 A102 2017 A103 2007*
More informationFacilities Planning Policy & Procedure #20
Facilities Planning Policy & Procedure #20 TITLE: OBJECTIVE AND PURPOSE RESPONSIBILITY MINOR PROJECTS To establish a procedure for proper initiation, implementation, filing and closeout for projects included
More informationDEAN + TYLER + BURNS ARCHITECTURE
DEAN + TYLER + BURNS ARCHITECTURE May 17, 2017 Community Safe Room for the City Springville 580 Indian Crest Drive Indian Springs, AL 35124 tel.: 205.427.7890 email: m@rchitecture-e.com ADDENDUM NO. 3
More informationNEBRASKA INVESTMENT FINANCE AUTHORITY LOW INCOME HOUSING TAX CREDIT PROGRAM FINAL COST CERTIFICATION PROCEDURES MANUAL
NEBRASKA INVESTMENT FINANCE AUTHORITY LOW INCOME HOUSING TAX CREDIT PROGRAM FINAL COST CERTIFICATION PROCEDURES MANUAL 20145 2014 FINAL COST CERTIFICATION PROCEDURES MANUAL Nebraska Investment Finance
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 11/05/2018
SECTION 01 9113 - GENERAL COMMISSIONING REQUIREMENTS GENERAL 1.1 SUMMARY The Owner has retained an independent Commissioning Authority (CxA) to coordinate commissioning activities for this project. The
More informationEXHIBIT A INDEX TO TECHNICAL SPECIFICATIONS DOCUMENT FOLLOWS
EXHIBIT A INDEX TO TECHNICAL SPECIFICATIONS (Attach list of Technical Specifications.) DOCUMENT FOLLOWS Exhibit A EXHIBIT B LIST OF DRAWINGS (Attach List of Drawings) DOCUMENT FOLLOWS Exhibit B EXHIBIT
More informationFURNITURE, FURNISHINGS AND EQUIPMENT BID DOCUMENTS
FURNITURE, FURNISHINGS AND EQUIPMENT BID DOCUMENTS FOR ORCHARD HILL ELEMENTARY SCHOOL 380 Foster Street SOUTH WINDSOR, CONNECTICUT 06074 TOWN OF SOUTH WINDSOR BID NO. 1617 031 DEPARTMENT OF ADMINISTRATIVE
More informationSECTION QUALITY REQUIREMENTS
SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.
More informationOwner's Representative Scope Matrix - D/B Rev 10/28/2013
Ecluded Owner's Representative Scope Matri - D/B Rev 10/28/2013 The following matri is a worksheet to identify required and optional scope for Owner's Representative services. Please identify the scope
More informationEXHIBIT 6 Preconstruction Work
EXHIBIT 6 Preconstruction Work The following tasks shall be accomplished by the CM/GC as part of its obligations during the preconstruction phase. The work is to be coordinated with the services requirements
More informationNAPA SANITATION DISTRICT
NAPA SANITATION DISTRICT PSOMAS COMPANY - TASK ORDER No. 25 HEADWORKS EQUIPMENT REHAB-REPLACE PROJECT (CIP 17726) Date: July 25, 2018 Issued under Professional Services Agreement dated ---------, 2018.
More informationCommissioning Guide. Transportation and Works Building Design and Construction Division
Commissioning Guide Transportation and Works December 13, 2013 TABLE OF CONTENTS 1. COMMISSIONING 12 STEP PROCESS... 1 2. PURPOSE OF THE GUIDE... 2 3. INTENT OF COMMISSIONING... 2 4. DEFINITION OF COMMISSIONING...
More informationDEFINITIONS: The following definitions apply to terms used in this document:
PURPOSE: California Code of Regulations (CCR), Title 24, Part 1, CCR, Chapter 4, Article 1 (Sections 4-211 through 4-220) and Group1, Articles 5 and 6 (Sections 4-331 through 4-344) provide regulations
More informationMott Community College. Independent Contractor Policy and Procedures
Mott Community College Independent Contractor Policy and Procedures Mott Community College Independent Contractor Policy and Procedures Introduction Many Mott Community College departments regularly employ
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.10 20 (February 2010) Changed 1-08/17 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 45 02.10 (November 2008) UNIFIED FACILITIES
More informationBABT 807. A Guide to the Attestation of Equipment to the Machinery Directive by TUV SUD BABT. TUV SUD BABT is a Certification Body of
BABT 807 A Guide to the Attestation of Equipment to the Machinery Directive by TUV SUD BABT TUV SUD BABT is a Certification Body of TUV SUD BABT 2018 Issue: 2 Foreword TUV SUD BABT is the Certification
More informationTASK ORDER FOR CONTINUING CONTRACT CONSTRUCTION MANAGEMENT
TASK ORDER FOR CONTINUING CONTRACT CONSTRUCTION MANAGEMENT FORM INSTRUCTIONS 1) The task order form including attachments is intended to stand alone as an authorization for construction management work
More informationSECTION ADDENDUM NUMBER ONE
Softball Field Repairs and Upgrades 03 February 2012 University of South Carolina Upstate State Project Number: H34-I350 DP3 Architects Project Number: 11124 GENERAL INFORMATION SECTION 00 09 10 ADDENDUM
More informationNOTICE TO BIDDERS FOR
CITY OF SAN LEANDRO STATE OF CALIFORNIA ENGINEERING AND TRANSPORTATION DEPARTMENT NOTICE TO BIDDERS FOR MONARCH BAY DRIVE BRIDGE REPAIR PROJECT NO. 12-144-38-324 BID NO. 12-13.013 1. BID OPENING: The bidder
More informationCONSTRUCTION PHASE PROCEDURES
CONSTRUCTION PHASE PROCEDURES OCTOBER 2001 TABLE OF CONTENTS INTRODUCTION... 1 QUALITY CONTROL/QUALITY ASSURANCE... 1 PARTNERING... 1 PRE-CONSTRUCTION MEETING... 1 SAFETY... 2 RESPONSIBILITIES AND COMMUNICATION...
More information