INDOT/ACPA Technical Committee 2009 Specification Revisions 2009 Test Method Revisions Studies
|
|
- Cassandra Stafford
- 6 years ago
- Views:
Transcription
1 PCCP Workshop INDOT
2 INDOT/ACPA Technical Committee 2009 Specification Revisions 2009 Test Method Revisions Studies
3 INDOT/ACPA Technical Committee Materials Management FHWA Construction Management District Construction District Testing Research Industry Specifications Test Methods Miscellaneous Problems Cost Savings Items
4 Concrete Mix Criteria Minimum Cement Content reduced from 440 lbs/yd 3 to 400 lbs/yd 3 Phase I JTRP study on Optimization of Mixture Proportions indicated no compromise to strength, durability or performance
5 Concrete Mix Designs New Trial Batches for material and source changes: Very expensive Time consuming for Contractor and INDOT Has caused delays in contracts
6 Concrete Mix Designs Streamline the Process Reduce the number of Trial Batches because of change in materials or sources Allow more mixtures to be used without a Trial Batch Volume (ft 3 ) One yd 3 Materials SSD Weight (lb) A Air I 0 O Batch B Cement J P 508 C Fly Ash K 70.5 Q 71 D Water L Paste (E) Aggregate (F) G H Total (E + F) 27.0 Fine Aggregate Coarse Aggregate T(29gal)24 2 M R 1115 N S 1810
7 Concrete Mix Designs QC/QA PCCP (501) Submit CMDS to DTE on spreadsheet for approval CMDS used to conduct Trial Batch Volume (ft 3 ) One yd 3 Materials SSD Weight (lb) A Air I 0 O Batch B Cement J P 508 C Fly Ash K 70.5 Q 71 D Water L Paste (E) Aggregate (F) G H Fine Aggregate Coarse Aggregate T(29gal)24 2 M R 1115 N S 1810 Total (E + F) 27.0
8 Concrete Mix Designs Trial Batch conducted Contractor submits Trial Batch results with the CMDS Eliminate CMDT
9 Concrete Mix Designs CMDP submitted 3 working days prior to production
10 Change in Materials New CMDS with Trial Batch or Verification Cement source and type Pozzolan source or type Coarse aggregate source or type Admixture type
11 Change in Materials Verification Contractor and INDOT tests on first day of production Acceptance tests may be used for verification Production may continue until flexural strength tests are completed Minimum 570 psi
12 Change in Materials Verification Does not meet 570 psi Stop Production Failed Material
13 Adjustments in Materials Requires new CMD Submittal Admixture source Admixture product of the same type and from the same source Fine aggregate source Target unit weight due to change in aggregate properties Fine to total aggregate ratio beyond ±3% Increase in cement content
14 Adjustments in Materials Trial Batch not required CMDS submitted to DTE for approval as CMDP one work day prior to production
15 Other Adjustments Allowed Admixture dosage rate Fine to total aggregate ratio within ± 3% No Trial Batch required No DTE notification
16 Trial Batch Concrete produced at plant by proportioning tolerances of (b) Concrete produced in lab ASTM C 192
17 Trial Batch Requirements Air Content % to 10.0% Plastic Unit Weight -- within ± 3.0% of CMDS target W/C Ratio -- within ± of CMDS target and does not exceed Flexural Strength -- minimum of 570 psi at 7 days for average of two beams
18 No Trial Batch Minimum cement content of 564 lbs/yd 3 and target W/C ratio of Class C concrete in accordance with 702 using class AP coarse aggregate
19 Non QC/QA PCCP Changes or Adjustments that require new CMDS to be submitted: Cement source or type Pozzolan source or type Aggregate source or type Admixture source or type Addition or deletion of an admixture Proportioning of concrete Trial Batch for High Early Strength Concrete only
20 PCCP Patching Same as 501
21 Dowel Bars & Tie Bars Epoxy coated bars protected from exposure to ultraviolet light and moisture during storage Once placed into work, epoxy coated bars shall not be exposed to ultraviolet light for a total of more than 21 days prior to placement of concrete
22 AASHTO/ASTM Revisions 2009 Review all test methods for revisions Materials Management District/Production Labs Independent Assurance Program Qualified Technician Program Training
23 AASHTO T 121 Unit Weight Strike off plate is required instead of the strike off bar
24 AASHTO T 23 Making and Curing Test Specimens in the Field Warning added Hydraulic cementitious mixtures may cause burns to exposed skin and tissue upon long exposure
25 ASTM C 173 Air Content by Volumetric Method Requires scoop to be moved around the perimeter of the bowl opening to ensure even distribution of concrete with minimal segregation
26 Certified Ready Mixed Plant Program NRMCA Plant Certification More frequent scale calibrations 2 year cycle for inspection of plant Voluntary INDOT inspection
27 Certified Ready Mixed Plant Program Delivery Vehicles included 14 month cycle for certification
28 Aggregates - CAPP Certified Sources 193 Sand & Gravel 104 Stone 70 Sand, Gravel, & Stone 8 Slag - 11
29 CAPP SOURCES
30 CERTIFIED MATERIALS Stone Natural Sand Gravel Blast Furnace Slag Steel Slag -- 16
31 AASHTO T 84 Fine Aggregate Specific Gravity
32 Fine Aggregate Specific AASHTO T 84 Subjective Gravity/Absorption Influenced by Operator Unable to predict slumps in concrete -- absorption
33 SS Detect Fine Aggregate Specific Gravity
34 Sample is mixed by orbital motion Water added at 8 μl per injection for ¾ to 1 hours depending on absorption
35 Infrared light source tuned to water Stops when water is detected
36 Automated Vacuum Machine Agitates aggregate Vacuums air from sample Agitate 3 min Vacuum 3 22 in. Hg Vacuum 5 27 in. Hg
37 SS Detect Fine Aggregate Specific Gravity Natural Sand good comparison with AASHTO T 84 procedure Stone Sand amount passing No. 200 sieve
38 Volumetric Immersion Method Normal absorptions are relatively small, so a large amount needs to be tested to allow accurate measurement of total absorbed water
39 Fine Aggregate Specific Gravity/Absorption Desired Characteristics Easy to perform Easy to understand Easily re-produced Operator and laboratory independent
40 Volumetric Immersion Method Physically and visually measure: total amount of water absorbed into the sample volume displacement of dry sample volume displacement of saturated sample
41 Volumetric Immersion Large flask 1200 g sample Method Submerge sample in flask Shake and roll flask for 3 min and read after 5 min Repeat and read after 10 min, 30 min, 60 min, 2hr, 4 hr, and 25 ± 1 hr
42 Volumetric Immersion Method Absorptions are much different Specific gravity values are slightly higher
43 Volumetric Immersion Method Impact to PCCP Absorptions Slight adjustments to fine aggregate for yield Slight change to Maximum Theoretical Unit Weight
44 Studies PCCP Joint Study AP Study Sonic Modulus Smoothness Top Size of Aggregate Recycled Concrete Depth of Concrete
45 Premature Distress around Joints 5-10 yr old pavements Longitudinal and transverse joints SR 933 I th St Georgetown Rd.
46
47
48 Possible Solutions Current procedure of initial saw cut, followed by a second saw cut, and then placement of a backer rod may be trapping water in the joint Solution possibly require one 1/8 in. saw cut, leave joint open, and seal joint faces
49 Class AP Coarse Aggregates ITM 210
50 "D" Cracking
51 AP Study Investigate material in the marginal performing aggregates Louisville formation Find a possible predictor for the AP test High insoluble residue High clay content Porosity
52 AP Study -- Sonic Modulus Measure modulus of elasticity Additional information that may be used to evaluate aggregates
53 Sources 92 Stone 62 Gravel 26 BF Slag 4 Districts Crawfordsville - 9 Ft. Wayne - 8 Greenfield - 25 LaPorte - 16 Seymour - 24 Vincennes - 9 AP Aggregate
54 Smoothness Ramps and Turn Lanes included in profilograph requirements design speed of mainline and lengths > 0.1 mi. length Urban Streets & Signalized Locations
55 Smoothness Inertial Profilers Measures IRI which is used in design process Provides smoothness value upon completion of testing More repeatable Good correlation with user response True profile measurement PCCP tines line lasers
56 Smoothness Inertial Profilers Who will do testing Timing of evaluations during construction Incentives related to expected pavement performance Identification and remediation of irregularities such as bumps Complete by June, 2010
57 Top Size of Aggregate Phase II of JTRP study 0n Optimization of Mixture Proportions for Concrete Pavements Reduction in surface area cement AP testing size of freezer rack & molds
58 Recycled Materials Blast Furnace Slag Slag Cement Fly Ash Ground Granulated Blast Furnace Slag Recycled Concrete Subgrades Concrete
59 Recycled Concrete in Concrete Unhydrated cement and fines D-Cracking
60 PCCP Core Length Drainage Layer - No. 8 stone or ACBF ITM Removal of particles not substantially surrounded by mortar Demonstrated to Contractor on each contract STANDARD STEEL RULE VERTICAL SHAFT CARRIAGE DROP SCALES 100 mm (4.0 IN.) BASE Figure # 1
61 Depth of Concrete Provides quicker results Save expense of coring Save time of testing Cost savings by Contractor not having to compensate bid for concrete lost in the subbase material
62 PCCP Rutting
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA April 15, 2011 888.01 General 888.02 Materials 888.03 Concrete Proportioning 888.04
More information9 Concrete Pavement Patching
9 Concrete Pavement Patching Materials Concrete Mix Design Concrete Mix Criteria Trial Batch Demonstration of CMD Acceptance Removal of Concrete Partial Depth Patches Full Depth Patched Placement of Patching
More informationDIVISION 2500 MISCELLANEOUS METHODS OF TEST
TABLE OF CONTENTS DIVISION 2500 MISCELLANEOUS METHODS OF TEST SECTION 2501 PART V... 2500-1 PAGE i SECTION 2501 PART V 2501.1 GENERAL In order to properly monitor materials on a project, follow all applicable
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007
Sheet 1 of 6 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007 Delete SECTION 2501 and replace with the following: SECTION 2501 PART V 2501.1 GENERAL In
More informationSTATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA April 18, 2008 888.01 General 888.02 Materials 888.03 Concrete Proportioning 888.04
More informationSPECIAL PROVISION Portland Cement Concrete
1993 Specifications CSJ 0271-16-117 SPECIAL PROVISION 421---040 Portland Cement Concrete For this project, Item 421, Portland Cement Concrete, of the Standard Specifications, is hereby amended with respect
More informationDIVISION 7 STRUCTURES
DIVISION 7 STRUCTURES Section 701. PORTLAND CEMENT CONCRETE FOR STRUCTURES 701.01 Description. Proportion structural concrete according to this section for the various grades of concrete required on the
More informationPerformance of Ultra-Thin Whitetopping District 58. Neal West, P.E.
Performance of Ultra-Thin Whitetopping District 58 Neal West, P.E. District 58 State Project 026-03-0036 FERRIDAY - RED GUM ROUTE US 65 CONCORDIA PARISH Contractors Prime Contractor: D&J Construction Co.,
More informationA balance, large pans, molds, volumetric flask, tampers, rods, concrete mixing equipment, slump cone, drying fans and ovens.
Specific Gravity, Absorption and Unit Weight of PCC Aggregates and Mixing and Casting of PCC Cylinders OBJECTIVE: EQUIPMENT: To determine the weight/volume properties of aggregates used in the making of
More informationStanford University Facilities Design Guidelines SECTION Pervious Concrete Paving
SECTION 32 13 43 Pervious Concrete Paving PART 1 GENERAL 1.1 RELATED WORK Current Caltrans Standard Specification Sections A. SECTION 31 10 00 Site Preparation B. SECTION 31 00 00 Earthwork C. SECTION
More informationConcrete Field Testing Technician Study Guide
Concrete Field Testing Technician Study Guide ASTM C 172 SAMPLING FRESH CONCRETE 1. The maximum allowable time between obtaining the first and final portions of a composite sample is minutes. (Section
More informationTruck Mixer, Agitator and Front Discharge Concrete Carrier. Standards. TMMB Printing
Truck Mixer, Agitator and Front Discharge Concrete Carrier Standards TMMB 100-01 2001 Printing Your Choice is Complete New Standards provide for mixing performance evaluated truck mixers with a size for
More informationNelson Testing Laboratories
in Elmhurst, Illinois, USA has demonstrated proficiency for the testing of construction materials and has conformed to the requirements established in AASHTO R 18 and the AASHTO Accreditation policies
More informationPERFORMANCE-RELATED SPECIAL PROVISION FOR HIGH PERFORMANCE CONCRETE MIX DESIGNS FOR CONCRETE SUPERSTRUCTURE (Tollway)
PERFORMANCE-RELATED SPECIAL PROVISION FOR HIGH PERFORMANCE CONCRETE MIX DESIGNS FOR CONCRETE SUPERSTRUCTURE (Tollway) Effective: October 12, 2012 Revised: June 14, 2013 DESCRIPTION This work consists of
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990
KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 90P-270 Sheet 1 of 5 SECTION PAVEMENT PATCHING Page 591, Section. Delete the Section and replace with
More informationExperimental Case Study Demonstrating Advantages of Performance Specifications Karthik Obla 1 Fernando Rodriguez 2 and Soliman Ben Barka 3
Experimental Case Study Demonstrating Advantages of Performance Specifications Karthik Obla 1 Fernando Rodriguez 2 and Soliman Ben Barka 3 NRMCA is working on an initiative to evolve specifications from
More informationMinnesota Concrete Flatwork Specifications for Local Government Agencies
Minnesota Concrete Flatwork LTAP Concrete Flatwork Specifications Mn Concrete Flatwork Specifications for Local MN Concrete Flatwork Agencies Approved for use on Local Government Agency Projects and State
More informationTolerances- Section
Tolerances- Section 346-6.4 Do not add water to delivered concrete when it is within the target Range for slump 1 346-6.4 Tolerances: Meet the following tolerances from target values for plastic concrete
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION
Sheet 1 of 5 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION Delete SECTION 403 and replace with the following: SECTION 403 ON GRADE CONCRETE 403.1 DESCRIPTION
More information2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT
2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT SECTION 501 PORTLAND CEMENT CONCRETE PAVEMENT 501.01 GENERAL. This item consists of constructing a concrete pavement (with or without reinforcement)
More informationNRMCA is working on. Experimental Case Study Demonstrates Advantages of Performance Specifications
Experimental Case Study Demonstrates Advantages of Performance Specifications By Karthik Obla, Director of Research and Materials Engineering Fernando Rodriguez, Laboratory Manager and Soliman Ben Barka,
More informationROAD COMMISSION FOR OAKLAND COUNTY SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE
ROAD COMMISSION FOR OAKLAND COUNTY SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE RCOC/CONST:SH/JO PAGE 1 OF 9 a. Description. This special provision establishes Portland
More informationRecommended Specifications For Portland Cement Pervious Pavement
Recommended Specifications For Portland Cement Pervious Pavement Foreword Portland Cement Pervious Concrete Pavements have become increasingly popular as a method to meet water quality water run off regulations
More informationENGINEERING MATERIALS Assignment #8: Concrete Mix Design
14.310 ENGINEERING MATERIALS Assignment #8: Concrete Mix Design PROBLEM #1: GIVEN: Concrete is required for a pavement slab that will be exposed to severe freeze-thaw climate as well as deicing chemicals.
More informationMichael Nelson, P.E. Concrete Engineer INDOT Office of Materials Management. February 19, 2019
Michael Nelson, P.E. Concrete Engineer INDOT Office of Materials Management February 19, 2019 Topics: Specification updates Partial depth patching Optimized mix designs SPR-4210 in-place strength QC/QA
More informationSPECIAL SPECIFICATION 4491 Type CAC Concrete
2004 Specifications SPECIAL SPECIFICATION 4491 Type CAC Concrete 1. Description. Remove unsound concrete and replace with Type CAC, calcium aluminate concrete for ultra high early strength concrete repairs.
More information< ~ -n~rtz, Concrete Engineer Office of Materials
Minnesota Department of Transportation MEMO Office of Materials Mailstop 645 1400 Gervais Avenue Maplewood, MN 55109 'stribution 57, 612, 618, 650 ~ < ~ -n~rtz, Concrete Engineer Office of Materials Implementation
More informationINDIANA DEPARTMENT OF TRANSPORTATION MATERIALS AND TESTS DIVISION
Revised 9-01-02 INDIANA DEPARTMENT OF TRANSPORTATION MATERIALS AND TESTS DIVISION CONTRACTOR QUALITY CONTROL PLANS ITM No. 803-02P 1.0 SCOPE. 1.1 This procedure covers the preparation of a QCP by a Contractor.
More informationDIVISION 2500 MISCELLANEOUS METHODS OF TEST
TABLE OF CONTENTS DIVISION 2500 MISCELLANEOUS METHODS OF TEST SECTION 2501 PART V... 2500-1 PAGE i SECTION 2501 PART V 2501.1 GENERAL In order to properly monitor materials on a project, follow all applicable
More information2501 PART V SECTION 2501 PART V
SECTION 2501 PART V 2501.1 GENERAL In order to properly monitor materials on a project, follow all applicable procedures as outlined in the KDOT Construction Manual, Part V. This includes, but is not limited
More informationPCC Pavement Mix Proportioning and Strength
Supplemental Technical Specification for PCC Pavement Mix Proportioning and Strength SCDOT Designation: SC-M-501 (03/08) 1. SCOPE 1.1. This supplemental technical specification describes materials and
More informationPennoni Associates, Inc.
in Bethlehem, Pennsylvania, USA has demonstrated proficiency for the testing of construction materials and has conformed to the requirements established in AASHTO R 18 and the AASHTO Accreditation policies
More informationINTEGRALLY COLORED CONCRETE [DECORATIVE CONCRETE PAVING]
Note to Specifier: The Admixture Systems business of BASF Corporation previously conducted business as Degussa Admixtures, Inc. and Master Builders, Inc. BASF has launched the Master Builders Solutions
More informationSPECIAL SPECIFICATION 3157 Cold Processed - Recycled Paving Material (RPM) for Use as Aggregate Base Course
1993 Specifications SPECIAL SPECIFICATION 3157 Cold Processed - Recycled Paving Material (RPM) for Use as Aggregate Base Course 1. Description. This Item, Cold Processed - Recycled Paving Material (RPM),
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION
Sheet 1 of 6 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION Delete SECTION 2501 and replace with the following: SECTION 2501 PART V 2501.1 GENERAL In
More informationSECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.
SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721
More informationDIVISION II CONSTRUCTION AND MATERIAL SPECIFICATIONS SECTION 2700 STRUCTURES
DIVISION II CONSTRUCTION AND MATERIAL SPECIFICATIONS SECTION 2700 STRUCTURES APPROVED AND ADOPTED THIS 23RD DAY OF MAY 2001 KANSAS CITY METROPOLITAN CHAPTER OF THE AMERICAN PUBLIC WORKS ASSOCIATION 2701
More informationSECTION ASPHALT PAVING
SECTION 321216 ASPHALT PAVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Hot-mix asphalt paving. 1.2 PRE-INSTALLATION MEETINGS A. Pre-installation Conference: Conduct conference at Project site.
More informationDIVISION 400 CONCRETE
TABLE OF CONTENTS DIVISION 400 CONCRETE PAGE 401 CONCRETE...400-1 401.1 DESCRIPTION...400-1 401.2 MATERIALS...400-1 401.3 CONCRETE MIX DESIGN...400-1 401.4 MORTAR AND GROUT...400-8 401.5 COMMERCIAL GRADE
More informationSECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION
ARDEX GUIDE SPECIFICATION ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) Cast-In-Place Concrete to Receive the ARDEX Concrete Management Systems including ARDEX Self-Leveling Underlayments SECTION 03 30 00
More informationSection CONCRETE SIDEWALKS. 1. Payment for concrete sidewalks is on square foot basis.
PART 1 GENERAL 1.01 SUMMARY A. This Section includes the following: Section 02775 1. Reinforced concrete sidewalks. 2. Wheelchair Ramps. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for concrete
More informationAdmixtures-Section 924
Admixtures-Section 924 - Qualified Products List - Types include: - Air Entraining - Water-Reducing (Type A) - Accelerating (Type C) - Water-Reducing & Retarding (Type D) - Water-Reducer & Accelerating
More informationSECTION 347 PORTLAND CEMENT CONCRETE CLASS 1 (NON-STRUCTURAL)
Section 347 SECTION 347 PORTLAND CEMENT CONCRETE CLASS 1 (NON-STRUCTURAL) 1 Version 1.0-7/20/06 1 Class 1 Non-Structural Structural vs- Nonstructural? 2 Photographs of concrete structures and a sidewalk.
More informationGlossary of Terms - A -
Glossary of Terms - A - AASHTO - American Association of State Highway and Transportation Officials. ABRASION - A test for determination of resistance of aggregate to abrasion conducted as per AASHTO Test
More informationIllinois Tollway Concrete Research Update
Illinois Tollway Concrete Research Update Steve Gillen Tollway Deputy Program Manager of Materials NCC Spring Meeting April 22, 2014 How The Move Illinois Capital Program is Driving the Future for Concrete
More informationSTRUCTURAL CONCRETE - LIGHTWEIGHT
SPECIAL PROVISION May 27, 2010 Add Section 03312: PROJECT #MP-I15-6(178)245 PIN #7037 SECTION 03312S STRUCTURAL CONCRETE - LIGHTWEIGHT PART 1 GENERAL 1.1 SECTION INCLUDES A. Materials and procedures for
More informationPERVIOUS CONCRETE PAVEMENT
October 2012 PERVIOUS CONCRETE PAVEMENT This document serves as an introduction to the design considerations for Pervious Concrete Pavement when it is part of a stormwater management plan. DESIGNER NOTES:
More informationMSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS
219-1.1 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION This item consists of a base course composed of crushed recycled concrete aggregate, crushed to meet a particular gradation,
More informationCIVE.3100 ENGINEERING MATERIALS ASSIGNMENT #8: CONCRETE MIX PROPORTIONING
PROBLEM #1: GIVEN: Concrete is required for a pavement slab that will be exposed to moderate freeze-thaw climate as well as deicing chemicals. A specified compressive strength of 4,000 psi is required
More informationAPPENDIX I NASP TEST PROTOCOLS
APPENDIX I NASP TEST PROTOCOLS I-1 I-2 I-3 I-4 NASP STRAND BOND TEST (DRAFT) Standard Test Method to Assess the Bond of 0.5 in. (12.7 mm) and 0.6 in. (15.24 mm) Seven Wire Strand with Cementitious Materials
More informationSPECIAL SPECIFICATION 3048 Permeable Concrete
2004 Specifications CSJ 0713-02-007 SPECIAL SPECIFICATION 3048 Permeable Concrete 1. Description. Furnish permeable concrete with hydraulic cement and chemical admixture for use in permeable concrete pavements.
More informationINSTRUCTIONS FOR COMPLETING THE TE-45 FORM:
INSTRUCTIONS FOR COMPLETING THE TE-45 FORM: 1. SAMPLE ID - This is a number generated by CMS when sample information is inputted into the system. 2. TYPE OF INSPECTION - Typically this will be a Control
More informationSTATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 898 QC/QA CONCRETE FOR STRUCTURES October 21, 2011
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 898 QC/QA CONCRETE FOR STRUCTURES October 21, 2011 898.01 Description 898.02 Definitions And Referenced Specifications 898.03 Materials
More informationTACAMP 2014 CONCRETE. Presented by Rick Wheeler
TACAMP 2014 CONCRETE Presented by Rick Wheeler HISTORY OF CONCRETE 2000 years and still working Concrete is the longest lasting Man-made construction material The Roman Pantheon is the largest (43.4m dia.)
More informationMix Design & Construction -1-
Mix Design & Construction -1- AGENDA RCC Mix Design RCC Mix Production RCC Construction Process -2- THE FINAL SURFACE TYPE WILL DICTATE THE NECESSARY TECHNIQUES & EQUIPMENT NEEDED TO BE SUCCESSFUL Natural
More informationSCOPE OF ACCREDITATION TO ISO/IEC 17025:2005
SCOPE OF ACCREDITATION TO ISO/IEC 17025:2005 TOLUNAY-WONG ENGINEERS, INC 10710 Sam Houston Parkway West, Suite 100 Houston, TX 77031 Patricia Hodgkins Phone: 504 202 7541 Valid To: February 29, 2020 Certificate
More informationWiss, Janney, Elstner Associates, Inc.
in Northbrook, Illinois, USA has demonstrated proficiency for the testing of construction materials and has conformed to the requirements established in AASHTO R 18 and the AASHTO Accreditation policies
More information1. Cast-in place structural concrete including footers, foundations, and other non-slab applications. 2. Formwork 3. Reinforcement
SECTION 03 31 00 - CAST-IN-PLACE STRUCTURAL CONCRETE PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Cast-in place structural concrete including footers, foundations, and other non-slab applications.
More informationMETHOD OF TEST FOR CEMENT CONTENT FOR PORTLAND CEMENT CONCRETE PAVEMENTS
STATE OF CALIFORNIA BUSINESS, TRANSPORTATION AND HOUSING AGENCY DEPARTMENT OF TRANSPORTATION DIVISION OF ENGINEERING SERVICES Transportation Laboratory 5900 Folsom Blvd. Sacramento, California 95819-4612
More informationSECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES
GUIDE SPECIFICATION SECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES PART 1 - SCOPE 1.01 WORK INCLUDED: 1.1.1 This guide covers the
More information2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.
JOB GUIDE CONCRETE PAVING INSPECTION 1. Review Contract and Plans: Obtain plans and special provisions and study them in detail. Attend the pre-construction meeting. Attend the pre-paving meeting. 2. Determine
More informationDIVISION 6 PORTLAND CEMENT CONCRETE PAVEMENTS. Section 601. PCC PAVEMENT MIXTURES
DIVISION 6 PORTLAND CEMENT CONCRETE PAVEMENTS Section 601. PCC PAVEMENT MIXTURES 601.01 601.01 Description. Concrete will consist of a mixture of Portland cement, blended Portland cement, cement substitutes,
More informationSPECIAL PROVISION Portland Cement Concrete
1995 Metric SPECIAL PROVISION 421---028 Portland Cement Concrete For this project, Item 421, Portland Cement Concrete, of the Standard Specifications, is hereby amended with respect to the clauses cited
More informationHANDS-ON TRAINING: MATERIALS AND MIX DESIGN
Fundamentals of Concrete HANDS-ON TRAINING: MATERIALS AND MIX DESIGN LEARNING OBJECTIVES Upon completing this program, the participant should be able to: 1. Identify the common materials used for concrete
More informationMASS PER CUBIC FOOT (METER), YIELD, AND AIR CONTENT (GRAVIMETRIC) OF FRESHLY MIXED CONCRETE (Kansas Test Method KT-20)
5.9.20 MASS PER CUBIC FOOT (METER), YIELD, AND AIR CONTENT (GRAVIMETRIC) OF FRESHLY MIXED CONCRETE (Kansas Test Method ) 1. SCOPE This method of test covers the procedure for determining the mass per cubic
More informationQUALITY ASSURANCE PROGRAM
QUALITY ASSURANCE PROGRAM FOR CONSTRUCTION and CITY OF LAREDO JUNE 2005 2005 by Texas Department of Transportation (512) 506-5803 All Rights Reserved TABLE OF CONTENTS SECTION 1 - INTRODUCTION... 3 1.1
More informationLong Life Concrete Pavements Wisconsin s Experiences. Kevin W. McMullen, P.E. President
Long Life Concrete Pavements Wisconsin s Experiences Kevin W. McMullen, P.E. President HIGH PERFORMANCE CONCRETE PAVEMENT OR Long Life Concrete Pavements FHWA Goals for HPCP Increasing the service life.
More informationSlab Replacement in Urban Areas
Slab Replacement in Urban Areas High-Early-Strength Concrete Craig Hennings, Executive Director Southwest Concrete Pavement Association Aug 29 2012 California Many Urban Areas 50,000 Lane Miles 16,000
More informationIS : Dr. S. RAVIRAJ
CONCRETE MIX PROPORTIONING IS 10262 : 2009 Dr. S. RAVIRAJ Professor of Civil Engineering JSS Science and Technology University S.J. College of Engineering Mysuru 570 006 ravirajs@sjce.ac.in 1 Introduction
More informationTruck Mixer, Agitator and Front Discharge Concrete Carrier. Standards. Endorsed by and Affiliated with. TMMB Printing
Truck Mixer, Agitator and Front Discharge Concrete Carrier Standards Endorsed by and Affiliated with TMMB 100-05 2005 Printing Your Choice is Complete New Standards provide for mixing performance evaluated
More informationPerformance Engineered Mixtures So what
Performance Engineered Mixtures So what 1 An Emphasis on Durability What do I want? How do I get what I want with what I have? How do I know? What Do We Want? The pavement owner wants: Strong enough Crack
More informationFHWA-Central Federal Lands Highway Division
in Denver, Colorado, USA has demonstrated proficiency for the testing of construction materials and has conformed to the requirements established in AASHTO R 18 and the AASHTO Accreditation policies established
More informationSECTION 904 AGGREGATES
SECTION 904 AGGREGATES 904.01 Aggregates. Aggregates shall consist of natural or manufactured materials produced from but not limited to limestone, dolomite, gravels, sandstones, steel furnace slag (SF),
More informationWorkshop Introduction
Quality in the Concrete Paving Process Workshop Introduction Module 8-21 Instructors Dennis Dvorak Jim Grove Mike Praul FHWA Resource Center (708) 283-3542 dennis.dvorak@dot.gov ATI Inc. / FHWA Office
More informationSECTION PORTLAND CEMENT CONCRETE PAVEMENT. All subsurface utilities must be inspected, tested, and accepted prior to any paving.
SECTION PORTLAND CEMENT CONCRETE PAVEMENT 1. DESCRIPTION This specification shall govern for the construction of Portland cement concrete pavement on a prepared subgrade or base course, in accordance with
More informationINDIANA. So how do you make hot mix asphalt? Basics of HMA Pavement Performance. Basics of a Good Road Hot Mix Asphalt Pavement Materials Selection
Basics of a Good Road Hot Mix Asphalt Pavement Materials Selection Presented at 2004 Road School By M. Dudley Bonte March 10, 2004 Basics of HMA Pavement Performance Appropriate Specifications Adequate
More informationOHD L-54 STANDARD METHOD OF TEST FOR MAKING, CURING, AND TESTING CEMENT-TREATED BASE FIELD SAMPLES
STANDARD METHOD OF TEST FOR MAKING, CURING, AND TESTING CEMENT-TREATED BASE FIELD SAMPLES Oklahoma D.O.T. Page 1 of 7 1 SCOPE 1.1 This method covers procedures for making, curing, and testing cylindrical
More informationSCOPE OF ACCREDITATION TO ISO/IEC 17025:2005. HTS, INC. CONSULTANTS 416 Pickering Houston, TX Terry J. Jackson, P.E. Phone:
SCOPE OF ACCREDITATION TO ISO/IEC 17025:2005 HTS, INC. CONSULTANTS 416 Pickering Houston, TX 77206 Terry J. Jackson, P.E. Phone: 713 692 8373 Valid To: October 31, 2018 Certificate Number: 0029.01 In recognition
More informationDEVELOPMENT OF A SPECIFICATION FOR LOW CRACKING BRIDGE DECK CONCRETE IN VIRGINIA
DEVELOPMENT OF A SPECIFICATION FOR LOW CRACKING BRIDGE DECK CONCRETE IN VIRGINIA Virginia DOT Workshop Charlottesville, VA Harikrishnan Nair, Ph.D., P.E, VTRC Senior Research Scientist October 4, 2017
More informationITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING
AFTER NOVEMBER 1, 2008 ITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING 252.1 Description. This work shall consist of a stabilized base course composed of a mixture of the existing bituminous
More informationBeyond Water-Cement Ratio and Strength. Patrick Harrison Vice President Structural Services, Inc.
Beyond Water-Cement Ratio and Strength Patrick Harrison Vice President Structural Services, Inc. High compressive strengths Low water/cementitious ratios Low slump Water Coarse Cement Fine Concrete
More informationMETHOD OF MAKING AND CURING CONCRETE TEST SPECIMENS IN THE FIELD FOP FOR AASHTO T 23
METHOD OF MAKING AND CURING CONCRETE TEST SPECIMENS IN THE FIELD FOP FOR AASHTO T 23 Scope This procedure covers the method for making, initially curing, and transporting concrete test specimens in the
More informationCONCRETE MIX DESIGN WORKSHOP FOR NORMAL CONCRETE MIXTURES 3/21/2017 1
53 th Quality Concrete School New Mexico State University Concrete Mix Design Workshop January 13 14, 2017 CONCRETE MIX DESIGN WORKSHOP FOR NORMAL CONCRETE MIXTURES 3/21/2017 1 Mix Design is the Recipe
More informationDIVISION 400 CONCRETE
TABLE OF CONTENTS DIVISION 400 CONCRETE SECTION 401 - GENERAL CONCRETE... 400-1 402 - STRUCTURAL CONCRETE... 400-14 403 - ON GRADE CONCRETE... 400-17 404 - CONCRETE FOR PRESTRESSED CONCRETE MEMBERS...
More informationStudent Services & Classroom Addition
SECTION 321216 - ASPHALT PAVING PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationSECTION 402 HOT MIX ASPHALT, HMA, PAVEMENT
SECTION 402 HOT MIX ASPHALT, HMA, PAVEMENT 402.01 Description. This work shall consist of one or more courses of HMA base, intermediate, or surface mixtures and miscellaneous courses for rumble strips,
More information5 Concrete Placement
5 Concrete Placement Testing Entrained Air Slump Strength Water/Cementitious Ratio Mixing Placing Concrete Compressive Test Specimens Curing De-Tensioning Multiple Strand Release Single Strand Release
More informationUse of Brick Masonry from Construction and Demolition Waste as Aggregates in Concrete
Use of Brick Masonry from Construction and Demolition Waste as Aggregates in Concrete Tara Cavalline, PE and David C. Weggel, Ph.D., PE UNC Charlotte 2012 International Concrete Sustainability Conference
More informationItem P-219 Recycled Concrete Aggregate Base Course
Item P-219 Recycled Concrete Aggregate DESCRIPTION 219-1.1 This item consists of a base course composed of recycled concrete aggregate, crushed to meet a particular gradation, constructed on a prepared
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF STRUCTURAL PRECAST CONCRETE
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF STRUCTURAL PRECAST CONCRETE STR:MJF 1 of 8 APPR:JFS:POJ:01-04-19 FHWA:APPR:01-10-19 a. Description. The Contractor
More information1/22/2014. Concrete Mix Design. Concrete Mix Design. Wet Cast (Slump) Combination of Art and Science
Concrete Mix Design Calculations Concrete Mix Design Wet Cast (Slump) Dry Cast (no Slump) Combination of Art and Science 1 3 Water, Cement, & Aggregate As the water to cement ratio increases, the strength
More informationConcrete Mix Design Calculations
Concrete Mix Design Calculations Concrete Mix Design Wet Cast (Slump) Dry Cast (no Slump) Combination of Art and Science 1 3 Water, Cement, & Aggregate As the water to cement ratio increases, the strength
More informationMARSHALL MIX DESIGN PROJECT. [2 nd semester 1433H] CE432-Highway Engineering LABORATORY
MARSHALL MIX DESIGN PROJECT [2 nd semester 1433H] CE432-Highway Engineering LABORATORY Project Details Binder Content (%) Group 1 (Mix 1) Group 2 (Mix 2) Group 3 (Mix 3) Group 4 (Mix 4) Group 5 (Mix 5)
More informationA. Drawings and general provisions of the contract, including General and Supplementary Conditions, apply to this section.
Product Specification for: Rapid Set DOT Repair Mix SECTION 03 01 30 MAINTENANCE OF CAST-IN-PLACE CONCRETE SECTION 03 01 40 MAINTENANCE OF PRECAST CONCRETE SECTION 03 01 50 MAINTENANCE OF CAST DECKS AND
More informationSPECIAL SPECIFICATION 4429 Multiple-Layer Polymer Concrete Overlay
2004 Specifications SPECIAL SPECIFICATION 4429 Multiple-Layer Polymer Concrete Overlay 1. Description. Furnish and place a multi-layer polymer overlay consisting of a crack seal, polymer resin and aggregates.
More information(STRUCTURAL CONCRETE).
S-1 REVISED SCHEDULE OF MATERIALS CONTROL FOR CERTIFIED READY-MIX CONCRETE PLANT PRODUCTION NEW WRITE-UP 02/11/19 DO NOT REMOVE THIS NEW WRITE-UP DATE. IT NEEDS TO STAY IN FOR THE CONTRACTORS. Always use
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION
Sheet 1 of 10 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION Section. Delete the entire Section and replace with this: SECTION AGGREGATES FOR CONCRETE.1
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION
Sheet 1 of 8 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION Delete the entire SECTION 1102 and replace with the following: SECTION 1102 AGGREGATES FOR
More informationWYOMING DEPARTMENT OF TRANSPORTATION. SUPPLEMENTARY SPECIFICATION FOR STRUCTURAL CONCRETE WITH QUALITY CONTROL and QUALITY ACCEPTANCE
WYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR STRUCTURAL CONCRETE WITH QUALITY CONTROL and QUALITY ACCEPTANCE SS-500G Page 1 of 18 This supplementary specification supplements, amends,
More informationSECTION CEMENTITIOUS TREATED CRUSHED ROCK FOR PAVEMENT SUBBASE
SECTION 815 - CEMENTITIOUS TREATED CRUSHED ROCK FOR PAVEMENT SUBBASE ##This section cross-references Sections 175, 306, 801, 812 and 821. If any of the above sections are relevant, they should be included