Saudi Aramco General Bid Slates (GBS)

Size: px
Start display at page:

Download "Saudi Aramco General Bid Slates (GBS)"

Transcription

1 Saudi Aramco General Bid Slates (GBS) Copyright 2015, Saudi Aramco. All rights reserved.

2 Agenda Saudi Aramco Contracting Strategy Saudi Aramco General Bid Slate (GBS) General Bid Slate Work Types 2

3 Saudi Aramco Contracting Strategy Lump Sum Procure Build (LSPB) Project Funding BID Reimbursable/ Unit Rate Reimbursable/ Unit Rate LUMP SUM PROCURE BUILD Project Proposal Detailed Design Materials Procurement Construction Lump Sum Turn Key (LSTK) Project Funding Reimbursable/ Unit Rate LUMP SUM TURNKEY Project Proposal Detailed Design Materials Procurement Construction 3

4 Saudi Aramco General Bid Slate (GBS) One-time Prequalification Only GBS contractors will be invited to bid Contractors capable of executing a specific work within a certain financial category Contractors are prequalified according to: - Financial Strength - Experience - Performance - Resources - Equipment - Quality and Safety 4

5 General Bid Slate (GBS) Work Types (1/2) - In-plant - Onshore Pipelines - Electrical Work - Civil Infrastructure & Underground Utilities - Buildings - Residential Housing - Site Preparation & Temporary Facilities - Marine Infrastructure - Water Treatment 5

6 General Bid Slate (GBS) Work Types (2/2) - Cathodic Protection - Power Transmission Lines - Communication Inside-plant (ISP) - Communication Outside-plant (OSP) - Communication Systems Integration - Security Systems Integration - Process Control Systems Integration - Offshore Facilities 6

7 In-Plant GBS Oil & Gas processing plants their upgrade & revamp, refinery plants, petrochemical plants, plant utilities (water, nitrogen, air, and steam), power generation and bulk plants & storage tanks. 7

8 Onshore Pipelines GBS Cross Country Hydrocarbon Pipelines. Water Injection Pipelines. Well Site Trunk Lines and Flow-lines to Gas-Oil Separation Plants (GOSP). Oil & Gas pump stations 8

9 Electrical Work GBS Electrical substations, power distribution grids, installation of transformers and circuit breakers/ switchgear. 9

10 Civil Infrastructure & Underground Utilities GBS Highways and city roads, bridges and tunnels. Underground Utilities: - Underground piping and electrical utilities district cooling plant - storm water construction - drilling water wells - water and sanitary sewer distribution - drainage underground systems. Fire protection systems including fire station. 10

11 Site Preparation & Temporary Facilities GBS Site preparation: Clearing & grubbing, rough grading, leveling and compaction. Landscaping (hard &soft): Paved areas such as streets & sidewalks, traffic circle, etc. Temporary Facilities: - Temporary access roads, storm drainage system. - Temporary security fences and gates. Temporary Camps: - Portable housing, water supply and treatment system - Temporary fire station, utilities. 11

12 Buildings GBS Office and commercial buildings, clinics, schools, laboratories, dining halls, support shop buildings, and security gates. High-Rise Buildings having more than 12 floors, Iconic landmarks/buildings and hospitals. 12

13 Residential Housing GBS Housing and residential compounds Associated community utilities, and services such as: schools, community buildings, and parks 13

14 Marine Infrastructure Sea ports, docks, marine berths, piers, trestles and bridges Capable of performing all works related to : - Pile driving, deep foundations, landfilling, - Dredging, concrete work, structural elements fabrication, breakwaters, - Floating jetties, pontoons, quay walls, mooring piles, and rock revetments. Source: 14

15 Water Treatment GBS Water treatment plants and distribution systems including the installation of new, and the expansion of existing systems. Source: 15

16 Cathodic Protection Galvanic anodes and impressed current Cathodic Protection (ICCP) system installation and related power distribution lines. Source: ff-automation.com 16

17 Power Transmission Lines GBS Power transmission lines (69 KV and above) all associated site preparation and earth works. 17

18 Communication Inside-plant (ISP) GBS Remote terminal units (RTU), SCADA systems, outside plant interface work and control systems Telephone switching, fiber optic inside plant, transmission systems and radio systems. Security system related to facilities Source: 18

19 Communication Outside-plant (OSP) GBS Outside plant (OSP) fiber optic Conduits and terminals, and associated earth work with all necessary facilities fittings Source: 19

20 Communication Systems Integration GBS Data network, fiber and transmission, telephone switching, Uninterruptable power supply (UPS), Remote terminal unit (RTU) and radio installations and equipment. Source: 20

21 Security Systems Integration GBS Long Range Detection and Assessment System (LRDAS), Security Access Control System (SACS), Radio-frequency identification (RFID), Plate Recognition System (PRS) work and Intrusion Detection & Assessment System (IDAS) work that includes Microwave Intrusion Detection System (MIDS) CCTV System, Fiber Optic Fence Sensing System (FOFSS). Source: 21

22 Process Control System Integration GBS Distributed Control Systems (DCS), Supervisory Control and Data Acquisition System (SCADA), Process Automation Systems (PAS), Emergency Shutdown System (ESD), Vibration Monitoring System (VMS), Remote Terminal Unit (RTU). Installation of system cabinet, marshalling, network or server cabinets, Consoles and/or operator/ engineering workstations or servers. 22

23 Offshore Facilities GBS Offshore jackets and Platforms Subsea pipelines, subsea cables (including HV and umbilical cables) Major hook-up works 23

24 THANK YOU 24

CONSULTANT REGISTRATION SYSTEM (CRS) SPECIALISATION CATEGORY. CE - Civil Engineering Construction. - Building Construction

CONSULTANT REGISTRATION SYSTEM (CRS) SPECIALISATION CATEGORY. CE - Civil Engineering Construction. - Building Construction Capacity (RM) GRADE G1 not exceeding 100,000.00 G2 not exceeding 500,000.00 G3 not exceeding 1,000,000.00 G4 not exceeding 3,000,000.00 G5 not exceeding 5,000,000.00 G6 not exceeding 10,000,000.00 G7 not

More information

Engineering Procurement Construction Management

Engineering Procurement Construction Management Engineering Procurement Construction Management About Us Since the foundation of EMTA in 1974, our mission was to be one of the most respected companies in the Power Generation, Distribution & Transmission,

More information

Tabulated overview of the obligation to submit the use and occupancy notice or building design documentation and to apply for use and occupancy permit

Tabulated overview of the obligation to submit the use and occupancy notice or building design documentation and to apply for use and occupancy permit Tabulated overview of the obligation to submit the use and occupancy or building and to apply for use and occupancy Building Code Annex 2 Building Activity Erection Construction Remodelling Expansion by

More information

UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management)

UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management) UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management) DESIGN PHASE PROJECTS BCT - Building Program Development and Design for Maintenance and Administration

More information

Pre-Qualification Certificate

Pre-Qualification Certificate Nordic Utility Pre-Qualification System Pre-Qualification Certificate Awarded to Registration number: 984 277 032 Sellihca Id: Sellihca Qualification hereby confirms that is now fully registered as a supplier

More information

Onshore terminal plants

Onshore terminal plants Onshore terminal plants Norconsult experience covers engineering consultancy services within development of new facilities (Green plants) and live plant modifications (Brown plants) For Green terminal

More information

Polaris. Company Profile. consulting company Limited. ...earth s reference point

Polaris. Company Profile. consulting company Limited. ...earth s reference point Polaris consulting company Limited Company Profile...earth s reference point About Polaris We wish to introduce our company as a renowned Swamp, Land and Off-shore Surveying Company which has carried

More information

PREQUALIFICATION APPLICATION INSTRUCTIONS

PREQUALIFICATION APPLICATION INSTRUCTIONS PREQUALIFICATION APPLICATION INSTRUCTIONS Please read the following instructions carefully as incomplete applications will not be processed. COMPLETE AND RETURN ALL SECTIONS OF THE APPLICATION PACKAGE.

More information

Constructability Guidelines

Constructability Guidelines Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final

More information

Trans Mountain Expansion Project Overview

Trans Mountain Expansion Project Overview Trans Mountain Expansion Project Overview 1 Proposed Expansion Project $6.8-billion capital cost Expand capacity to 890,000 bpd Project scope 980 kms new pipe 12 new pump stations 19 new tanks 3 new tanker

More information

Gorgon Project Briefing Rick Robinson Director Perth Operations Kellogg Joint Venture. Perth, November

Gorgon Project Briefing Rick Robinson Director Perth Operations Kellogg Joint Venture. Perth, November Gorgon Project Briefing Rick Robinson Director Perth Operations Kellogg Joint Venture Perth, November 27 2008 Downstream Scope LNG Plant 3 x 5 mtpa LNG processing trains using APCI technology 2 x 180,000

More information

PREQUALIFICATION APPLICATION INSTRUCTIONS

PREQUALIFICATION APPLICATION INSTRUCTIONS PREQUALIFICATION APPLICATION INSTRUCTIONS Please read the following instructions carefully as incomplete applications will not be processed. COMPLETE AND RETURN ALL SECTIONS OF THE APPLICATION PACKAGE.

More information

Floating Production / Offshore solutions for tough challenges

Floating Production / Offshore solutions for tough challenges Floating Production / Offshore solutions for tough challenges siemens.com/answers Siemens Sectors and Divisions Energy Healthcare Industry Infrastructure & Cities Divisions Fossil Power Generation Wind

More information

PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD. LCB File No. R May 14, Section 1. NAC is hereby amended to read as follows:

PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD. LCB File No. R May 14, Section 1. NAC is hereby amended to read as follows: PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD LCB File No. R090-08 May 14, 2008 EXPLANATION Matter in italics is new; matter in brackets [omitted material] is material to be omitted. AUTHORITY: 1,

More information

MARINE WORKS SHAFA AL NAHDAH SHAFA AL NAHDAH. shafaconstruction.com. SHAFA - UAE (HEAD OFFICE) SHAFA Al Nahdah Building Contracting LLC

MARINE WORKS SHAFA AL NAHDAH SHAFA AL NAHDAH. shafaconstruction.com. SHAFA - UAE (HEAD OFFICE) SHAFA Al Nahdah Building Contracting LLC MARINE WORKS shafaconstruction.com SHAFA AL NAHDAH SHAFA - UAE (HEAD OFFICE) SHAFA Al Nahdah Building Contracting LLC Al Manara Tower, ETA Star 23rd Floor, Office no. 2302-04, Business Bay, P.O. Box 252050

More information

Gorgon Project Briefing Rick Robinson Director Perth Operations Kellogg Joint Venture. Karratha, Feb

Gorgon Project Briefing Rick Robinson Director Perth Operations Kellogg Joint Venture. Karratha, Feb Gorgon Project Briefing Rick Robinson Director Perth Operations Kellogg Joint Venture Karratha, Feb 5 2009 Downstream Scope LNG Plant 3 x 5 mtpa LNG processing trains using APCI technology 2 x 180,000

More information

Tony Hey Bechtel Oil, Gas and Chemicals, Inc. June 22, 2010

Tony Hey Bechtel Oil, Gas and Chemicals, Inc. June 22, 2010 Tony Hey Bechtel Oil, Gas and Chemicals, Inc. June 22, 2010 1 Agenda Bechtel Introduction Site Location Wheatstone Project LNG Plant FEED Schedule LNG Plant Scope and Quantities Execution Strategy and

More information

CORROSION ENGINEERING AND CATHODIC PROTECTION

CORROSION ENGINEERING AND CATHODIC PROTECTION UNI EN ISO 9001:2008 QMS certified for activities reported in certify N. K062 CESCOR Srl Via Maniago 12, 20134 MILANO (Italy) +39 02 26412538 fax +39 02 26412546 info@cescor.it www.cescor.it CORROSION

More information

SKADO is a professional consulting firm offering services in. Engineering, Environmental, and. Management Consultancy. It

SKADO is a professional consulting firm offering services in. Engineering, Environmental, and. Management Consultancy. It SKADO is a professional consulting firm offering services in Engineering, Environmental, and Management Consultancy. It specialises in infrastructure planning engineering and economics and is experienced

More information

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT Addendum No. 2 Attachment B Contract Document Revisions Specifications: TABLE OF CONTENTS ADDENDUM NO. 2 Attachment B Contract

More information

E. CONSTRUCTION PROCEDURES

E. CONSTRUCTION PROCEDURES E. CONSTRUCTION PROCEDURES The Project facilities would be constructed in accordance with established electric utility practices, best management practices, final engineering plans, CL&P s specifications

More information

Appendix A Technical Specifications Engineering Services for the Nocatee 230/26kV Substation

Appendix A Technical Specifications Engineering Services for the Nocatee 230/26kV Substation Appendix A Technical Specifications Engineering Services for the Nocatee 230/26kV Substation 1. Scope of Work 1.1. Provide civil and electrical engineering services for the Nocatee 230/26kV Substation.

More information

About Viadukt. Our vision. Our mission

About Viadukt. Our vision. Our mission About Viadukt Viadukt d.d. is the largest construction company in Croatia and in the South East Europe. It was founded in 1947, it employs more than 1 800 employees and is specialized in the execution

More information

Prequalification of Electrical Contractors

Prequalification of Electrical Contractors Prequalification of Electrical Contractors \\ 2018 Application Instructions & Forms Prequalified Electrical Contractors Application Checklist To apply for prequalification of utility type work for Tacoma

More information

395 Express Lanes Project Design-Build Procurement Industry Outreach. March 23, 2016

395 Express Lanes Project Design-Build Procurement Industry Outreach. March 23, 2016 395 Express Lanes Project Design-Build Procurement Industry Outreach March 23, 2016 INTRODUCTIONS Karl Rohrer, Head of Delivery, Transurban Susan Shaw, Regional Transportation Program Director, VDOT Sean

More information

A New Municipal Building for Limerick Township

A New Municipal Building for Limerick Township A New Municipal Building for Limerick Township DOCUMENT 00 9001 - ADDENDUM NUMBER 01 December 9, 2016 Re: A New Municipal Building for Limerick Township From: Kelly Clough Bucher & Associates, Inc. 8 East

More information

Saudi Aramco s Registration and Prequalification for Service Suppliers. Copyright 2016, Saudi Aramco. All rights reserved.

Saudi Aramco s Registration and Prequalification for Service Suppliers. Copyright 2016, Saudi Aramco. All rights reserved. Saudi Aramco s Registration and Prequalification for Service Suppliers Copyright 2016, Saudi Aramco. All rights reserved. Objective - Registration Process Overview of Saudi Aramco s General Bid Slates

More information

Buildings Construction Procurement Strategy

Buildings Construction Procurement Strategy Buildings Construction Procurement Strategy Update January 2013 Disclaimer: This presentation is given for information only and cannot be considered as binding Ref. F4E_D_264U97 1 Agenda 1. Overview of

More information

TAXABLE PAYMENTS FACTSHEET. If you run a business in the building and. construction industry then you ll soon need

TAXABLE PAYMENTS FACTSHEET. If you run a business in the building and. construction industry then you ll soon need If you run a business in the building and construction industry then you ll soon need to do your Taxable Payments reporting. This factsheet contains a summary of the key tax changes surrounding taxable

More information

Building Services / MEPF Scopes

Building Services / MEPF Scopes Building Services / MEPF Scopes Mechanical Air conditioning Refrigerant Plant Compression Chillers Absorption Chillers Heat Pumps (Chilled water and Hot Water) Cooling Towers Chemical Treatment Air Conditioning

More information

Siemens at LNG 16 News from Siemens Energy Oil & Gas

Siemens at LNG 16 News from Siemens Energy Oil & Gas Siemens at LNG 16 News from Siemens Energy Oil & Gas www.siemens.com Contents: 02 More efficiency fewer emissions: E-LNG 03 Built-in availability: All-Electric LNG Dear readers, we kindly welcome you to

More information

Harness the power of Corpac for your next project.

Harness the power of Corpac for your next project. Corpac Steel Products is a leading global supplier and trader of pipe and steel products, specializing in line pipe, standard pipe, OCTG, conduit and structural products. Our experience in supplying complex,

More information

FROM THE CEO. Sameh Masry

FROM THE CEO. Sameh Masry An infrastructure utility Group of Companies specializing in the construction and operation & maintenance of water, power and transport systems. FROM THE CEO Sameh Masry Looking at the development and

More information

TABLE OF CONTENTS. (Δ = Rev 11/15) Update #7

TABLE OF CONTENTS. (Δ = Rev 11/15) Update #7 TABLE OF CONTENTS ( = Rev 11/15) Update #7 INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-4 International Suite of Codes (New) B-9 Record Drawings B-10 Variance Procedure

More information

TABLE OF CONTENTS. (Δ = Rev 04/17) Update #8

TABLE OF CONTENTS. (Δ = Rev 04/17) Update #8 TABLE OF CONTENTS ( = Rev 04/17) Update #8 INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-4 International Suite of Codes B-9 As-Builts and Record Drawings B-10 Variance

More information

Appendix A: Project Characteristics

Appendix A: Project Characteristics Gorgon Fourth Train Expansion Proposal Appendix A: Project Characteristics Appendices Project Characteristics A Key Characteristics table has been prepared to describe the elements of the Foundation Project

More information

DESIGN. DEVELOP. DELIVER. CAPABILITY STATEMENT

DESIGN. DEVELOP. DELIVER. CAPABILITY STATEMENT DESIGN. DEVELOP. DELIVER. CAPABILITY STATEMENT Mining & Industrial Switchgear Kiosk Substations Water Infrastructure Projects Project Management Slurry Management Systems Pumping Solutions Fire Protection

More information

Millennium Line Broadway Extension Project. Cost Report

Millennium Line Broadway Extension Project. Cost Report Millennium Line Broadway Extension Project Cost Report March 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...

More information

INSTALLATION, REPAIRS AND IMPROVEMENTS TO REAL PROPERTY

INSTALLATION, REPAIRS AND IMPROVEMENTS TO REAL PROPERTY BULLETIN NO. 008 Issued May 1998 Revised June 2005 THE RETAIL SALES TAX ACT INSTALLATION, REPAIRS AND IMPROVEMENTS TO REAL PROPERTY This bulletin explains the application of retail sales tax (RST) by businesses

More information

PROJECT DESCRIPTION CHAD EXPORT PROJECT SUPPORTING DOCUMENTS - VOLUME DECOMMISSIONING

PROJECT DESCRIPTION CHAD EXPORT PROJECT SUPPORTING DOCUMENTS - VOLUME DECOMMISSIONING CHAD EXPORT PROJECT SUPPORTING DOCUMENTS - VOLUME 1 8.0 DECOMMISSIONING This section provides an overview of the decommissioning activities that will be undertaken after construction and after each facility

More information

Engineering Standard. Saudi Aramco DeskTop Standards

Engineering Standard. Saudi Aramco DeskTop Standards Engineering Standard 18 November 2006 Piping Standards Committee Members Nasri, Nadhir Ibrahim, Chairman Dib, Tony Georges, Vice Chairman Balhareth, Nasser Mohammad Bannai, Nabeel Saad Fadley, Gary Lowell

More information

KJO Work Categories List

KJO Work Categories List 1 APM01 Study of all Sub-Sea Flowlines 2 APM02 PAS 55 or ISO 55000 Asset Performance Management 3 APM03 Specialist Engineering Service for Asset Performance Management 4 Aviation Services AV01 Rental &

More information

ADDENDUM #1 TO THE SPECIFICATION FOR THE CONSTRUCTION OF THE 115KV STONEBREAK RD. TRANSITION STATION THE TOWN OF MALTA AND A PORTION OF THE 115KV

ADDENDUM #1 TO THE SPECIFICATION FOR THE CONSTRUCTION OF THE 115KV STONEBREAK RD. TRANSITION STATION THE TOWN OF MALTA AND A PORTION OF THE 115KV ADDENDUM #1 TO THE SPECIFICATION FOR THE CONSTRUCTION OF THE 115KV STONEBREAK RD. TRANSITION STATION IN THE TOWN OF MALTA AND A PORTION OF THE 115KV LUTHER FOREST STATION IN THE TOWN OF STILLWATER SARATOGA

More information

Procurement Plan for Yunnan Highway Asset Management Project (Revis 2017)

Procurement Plan for Yunnan Highway Asset Management Project (Revis 2017) Public Disclosure Authorized Procurement Plan for Yunnan Project (Revis 2017) Number Contract Number Contract Name Contract Content Contract Value CNY (10k) US$ (million) Total 78710 118.36 A. Civil Works

More information

Plant, Seawater Intake &Discharge(1/7)

Plant, Seawater Intake &Discharge(1/7) Plant, Seawater Intake &Discharge(1/7) YEAR PROJECT NAME PROJECT DESCRIPTION CONTRACTOR 2013 for Zwitina Combined Cycle Add-On PJ 250MW Combined cycle power plant Intake & Discharge facilities for Algeria

More information

8/26/ Sign in 2. Fill out the evaluations 3. Candy Hander Outer 4. Time Keeper 5. Flip Charter 6. Ask Questions

8/26/ Sign in 2. Fill out the evaluations 3. Candy Hander Outer 4. Time Keeper 5. Flip Charter 6. Ask Questions The Language of Utilities and Energy Management Part 1 Professor KW Therm, PE, CEM University of Iowa September 11, 2016 Orlando, FL 1. Sign in 2. Fill out the evaluations 3. Candy Hander Outer 4. Time

More information

Marine Facilities for LNG Carrier Transfer Alternatives

Marine Facilities for LNG Carrier Transfer Alternatives 2.3.3.2 Marine Facilities for LNG Carrier Transfer Alternatives Two alternatives were considered for the marine facilities to support the transfer of LNG between the LNG carriers and onshore storage tanks.

More information

22.1 ISSUES OBJECTIVES POLICIES RULES PERFORMANCE STANDARDS 10

22.1 ISSUES OBJECTIVES POLICIES RULES PERFORMANCE STANDARDS 10 22 NETWORK UTILITIES 22.1 ISSUES 3 22.2 OBJECTIVES 4 22.3 POLICIES 4 22.4 RULES 6 22.5 PERFORMANCE STANDARDS 10 Whanganui District Plan (15 January 2018) Chapter 22 Network Utilities 22-1 22 NETWORK UTILITIES

More information

Utility and service uses are subject to the following regulations: (1) Utility or government installation other than listed.

Utility and service uses are subject to the following regulations: (1) Utility or government installation other than listed. SEC. 51-4.202. UTILITY AND SERVICE USES. Utility and service uses are subject to the following regulations: (1) Utility or government installation other than listed. Definition: (i) A utility other than

More information

BUREAU Joe Iuviene, AIA January 20, 2017

BUREAU Joe Iuviene, AIA January 20, 2017 architectural BUREAU Joe Iuviene, AIA January 20, 2017 Alterations & Additions NEW TOWN HALL for TOWN OF AUSTERLITZ 816 State Route 203, Spencertown, New York 12165 ADDENDUM NO. 1 This addendum amends

More information

ENGINEERING DESIGN & IMPROVEMENT STANDARDS

ENGINEERING DESIGN & IMPROVEMENT STANDARDS ENGINEERING DESIGN & IMPROVEMENT STANDARDS 2016 Prepared by: Engineering Division For latest edition of these Improvement Standards, refer to City of Visalia website at: www.visalia.city/engineeringdocuments

More information

ECP SECONDARY COMMISSIONING REQUIREMENTS

ECP SECONDARY COMMISSIONING REQUIREMENTS Document Number: ECP 11-0002 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0002 SECONDARY COMMISSIONING REQUIREMENTS EPN, LPN, SPN This standard details the commissioning requirements

More information

DRAFT Subject to modifications

DRAFT Subject to modifications TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 7 From: Date: Staff July 17, 2009 Council Meeting Subject: Florida Power and Light Company Riviera Beach Energy

More information

COMPLETE REVISION January Process Industry Practices Electrical. PIP ELIGD000 Grounding Installation Details

COMPLETE REVISION January Process Industry Practices Electrical. PIP ELIGD000 Grounding Installation Details COMPLETE REVISION January 2010 Process Industry Practices Electrical PIP ELIGD000 Grounding Installation Details PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process

More information

Federal Project No.: NONE

Federal Project No.: NONE Schedule of Items Page: 2 0001 BASE BID- STA. 10+00-23+00 0010 513 00100 0020 517 00101 MOBILIZATION LUMP SUM LUMP SUM CONSTRUCTION SURVEYING (CONSTRUCTION) 0030 301 00110 LUMP SUM LUMP SUM CLRING AND

More information

APPLICATION FOR PIPE OR WIRE OCCUPANCY

APPLICATION FOR PIPE OR WIRE OCCUPANCY APPLICATION FOR PIPE OR WIRE OCCUPANCY Please answer all questions and direct cover letter / project description, completed application, application fee, and three (3) copies of project plans to: AECOM

More information

CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOR UNDERGROUND UTILITIES

CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOR UNDERGROUND UTILITIES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 507 JULY 1991 CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOR UNDERGROUND UTILITIES 507.01 SCOPE 507.02 REFERENCES 507.03 Not Used 507.04 Not Used

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016 Cleveland Opportunity Corridor Project Section 3 Subcontractor Informational Meeting August 12, 2016 Agenda Welcome and Opening Remarks Project Overview Prequalifications & Work Types Procurement Overview

More information

Introduction. Affected Environment. Environmental Setting. Section 3.11 Public Services and Utilities. Public Services.

Introduction. Affected Environment. Environmental Setting. Section 3.11 Public Services and Utilities. Public Services. Section 3.11 Public Services and Utilities Introduction This section identifies and evaluates issues related to public services (e.g., law enforcement) and utilities (e.g., electric service). The Affected

More information

Introduction to Plant Bulks

Introduction to Plant Bulks Introduction to Plant Bulks Chapter 17 Introduction to Plant Bulks... 17-3 List of Plant Bulks... 17-3 G2 ICARUS Corporation, 1998. 17-2 ICARUS Reference ICARUS Corporation, 1998. G2 Chapter 17: Introduction

More information

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

Saudi Aramco s Prequalification Process Passport to Opportunity. October 25, 2016

Saudi Aramco s Prequalification Process Passport to Opportunity. October 25, 2016 Saudi Aramco s Prequalification Process Passport to Opportunity October 25, 2016 Overview 1. Safety Moment 2. Current Business Demand 3. Prequalification Process 4. The General Bid Slate Program 5. Registration

More information

Partnering for reliable distribution

Partnering for reliable distribution Published by and copyright 013: Siemens AG Infrastructure & Cities Sector Smart Grid Division Humboldtstr. 59 90459 Nuremberg, Germany Further information is available from our Customer Support Center

More information

TABLE OF CONTENTS Public Safety Building

TABLE OF CONTENTS Public Safety Building DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary

More information

DIVISION OF FACILITIES CONSTRUCTION AND MANAGEMENT ARCHITECTURAL/ENGINEER/HIGH PERFORMANCE BUILDING FEES EFFECTIVE DATE: December 12, 2017

DIVISION OF FACILITIES CONSTRUCTION AND MANAGEMENT ARCHITECTURAL/ENGINEER/HIGH PERFORMANCE BUILDING FEES EFFECTIVE DATE: December 12, 2017 DIVISION OF FACILITIES CONSTRUCTION AND MANAGEMENT ARCHITECTURAL/ENGINEER/HIGH PERFORMANCE BUILDING FEES EFFECTIVE DATE: December 12, 2017 I. PURPOSE To provide a standard for a reasonable A/E/HPBS consultant

More information

UPCOMING CONSTRUCTION PROJECTS 3 rd Quarter 2017 (Project & Construction Management)

UPCOMING CONSTRUCTION PROJECTS 3 rd Quarter 2017 (Project & Construction Management) UPCOMING CONSTRUCTION PROJECTS 3 rd Quarter 2017 (Project & Construction Management) Rail Spur at Bayport Terminal Construction of approximately 6500 track feet of rail at the Bayport Terminal. This rail

More information

Port of Long Beach Port Master Plan Overview December 22, 2008

Port of Long Beach Port Master Plan Overview December 22, 2008 Port of Long Beach Port Master Plan Overview December 22, 2008 PORT OF LONG BEACH PORT MASTER PLAN OVERVIEW INTRODUCTION In 1978 the California Coastal Commission certified the Port of Long Beach Port

More information

Power and Energy Systems Engineering

Power and Energy Systems Engineering Engineering Planning Project Management Operations Support Provided By J. J. Bergeron & Company, Inc. 1900 Veterans Memorial Blvd. Suite 205 Metairie, La. 70005 Power and Energy Systems Engineering Services

More information

ATTACHMENT A - TECHNICAL SPECIFICATIONS 1.1 GENERAL REQUIREMENTS

ATTACHMENT A - TECHNICAL SPECIFICATIONS 1.1 GENERAL REQUIREMENTS ATTACHMENT A - TECHNICAL SPECIFICATIONS 1.1 GENERAL REQUIREMENTS 1.1.1 A ground-mounted, single-axis tracking photovoltaic (PV) power plant is to be constructed as specified herein. The Vendor shall be

More information

BASELINE SCHEDULE NARRATIVE REPORT

BASELINE SCHEDULE NARRATIVE REPORT NORTH QUEENS PROJECT- 20 INCH STEEL 350 PSIG GAS Contract No.: 44000048281 Contractor: NETWORK INFRASTRUCTURE INCORPORATED CPM Scheduling Consultant: HSE Contractors Inc. BASELINE SCHEDULE NARRATIVE REPORT

More information

Cathodic Protection. Cathodic Protection for Pipelines, Storage Tanks and Process Industrial Plant Assets - 2 days. Major Benefits of Attending

Cathodic Protection. Cathodic Protection for Pipelines, Storage Tanks and Process Industrial Plant Assets - 2 days. Major Benefits of Attending Cathodic Protection Cathodic Protection for Pipelines, Storage Tanks and Process Industrial Plant Assets - 2 days 2018 Major Benefits of Attending APPRECIATE the fundamentals of Cathodic Protection design

More information

Buildings Construction Procurement Strategy

Buildings Construction Procurement Strategy Buildings Construction Procurement Strategy Update March 2012 Disclaimer: This presentation is given for information only and cannot be considered as binding Ref. F4E_D_24Y2K9 Agenda 1. Overview of the

More information

CIBL Categories of Work Classification Guidelines

CIBL Categories of Work Classification Guidelines 11 May 06 CIBL Categories of Work Classification Guidelines The following is provided as guidelines for classifying design, engineering and construction work. Project examples are provided for reference

More information

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017 Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.

More information

Section 6 - Bill of Quantities Bill Nr. 1 Preliminaries

Section 6 - Bill of Quantities Bill Nr. 1 Preliminaries Bill Nr. 1 Preliminaries Bill Nr. 1 PRELIMINARIES NOTES : (1) The work shall be done during day time and night time according to CAM/ADA requirements. (2) If CAM decides to cancel any s listed in the Bills

More information

How Do We Build the Efficient, Secure, Cost Effective Power Grid of Tomorrow? The Answer: Smart Grid. Bernard Norton Manager Energy Automation

How Do We Build the Efficient, Secure, Cost Effective Power Grid of Tomorrow? The Answer: Smart Grid. Bernard Norton Manager Energy Automation How Do We Build the Efficient, Secure, Cost Effective Power Grid of Tomorrow? The Answer: Smart Grid Bernard Norton Manager Energy Automation Transpower 2040 Conference Christchurch, 18 th June 2009 Ideas

More information

Division D CONSTRUCTION

Division D CONSTRUCTION Division D CONSTRUCTION Overview of the division This Division comprises establishments primarily engaged in construction work mainly by accepting an order, or for self-construction (construction for the

More information

1. Sign in 2. Fill out the evaluations 3. Candy Hander Outer 4. Time Keeper 5. Flip Charter 6. Ask Questions

1. Sign in 2. Fill out the evaluations 3. Candy Hander Outer 4. Time Keeper 5. Flip Charter 6. Ask Questions The Language of Utilities and Energy Management Part 1 1. Campus Utility Systems 2. Energy Terms 3. Water & Waste Water Terms 4. Electrical Production & Distribution Terms 5. Data Network Terms 6. Q/A

More information

Our goal is to be the best, not necessarily the biggest, contracting organization on Earth. Peter Kiewit

Our goal is to be the best, not necessarily the biggest, contracting organization on Earth. Peter Kiewit KIEWIT MEXICO Kiewit s roots can be traced back to 1884, when two brothers took a dream, some bricks, and a little bit of mortar and built the foundation for what would become one of the largest and most

More information

MERCED COUNTY CAMPUS PARKWAY SEGMENT 2

MERCED COUNTY CAMPUS PARKWAY SEGMENT 2 MERCED COUNTY BID LIST CAMPUS PARKWAY SEGMENT 2 CONTRACT 2017191 The bidder must provide unit prices for each bid item listed below, based on the specified unit of measure. The unit price for each item

More information

Han MK, Business Development (Power Generation), 23rd March 2010 ABB Power and Automation Days ABB in Power Generation

Han MK, Business Development (Power Generation), 23rd March 2010 ABB Power and Automation Days ABB in Power Generation Han MK, Business Development (Power Generation), 23rd March 2010 ABB Power and Automation Days ABB in Power Generation Content ABB Power Generation ABB Solutions for Power Generation ABB Solutions for

More information

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title TABLE OF CONTENTS CONTRACT DOCUMENTS 00001 Inside Title Page 00003 Table of Contents 00004 List of Drawings 00020 Invitation to Bid 00100 Instructions to Bidders 00300 Bid 00500 Agreement 00610 Construction

More information

BRIDGE DISTRICT. City of West Sacramento. Phase 1 Infrastructure Improvement Project. Monthly Status Report

BRIDGE DISTRICT. City of West Sacramento. Phase 1 Infrastructure Improvement Project. Monthly Status Report BRIDGE DISTRICT Phase 1 Infrastructure Improvement Project (for work completed thru November 2011) Cover Photo: Joint Utility Trench installation along Fifth Street just north of Bridge Street. Page 1

More information

VIRGINIA UTILITY PROTECTION SERVICE, INC. Title: Ticket Entry - Work Type List Working Document

VIRGINIA UTILITY PROTECTION SERVICE, INC. Title: Ticket Entry - Work Type List Working Document Printed copies are for reference only. Please refer to the electronic copy for the latest version. Purpose: To provide instructions for editing the work type list through Newtin administrator accounts

More information

City of Redding Construction Standards Index

City of Redding Construction Standards Index City of Redding Construction Standards Index A. Purpose and Reference Documents... A1 B. Modifications to the Standard Specifications for Public Works Construction (Greenbook)... B1 I. Streets Materials...

More information

Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempêtes PIANC WG 101

Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempêtes PIANC WG 101 Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempêtes PIANC WG 101 Guidelines for environmental impacts of vessels InCom

More information

THE POWER TO PROTECT

THE POWER TO PROTECT THE POWER TO PROTECT Corrtrol-Hitech Sdn. Bhd. is jointly owned by Corrtrol Sdn. Bhd. of Malaysia and Hitech Engineering Materials and Systems Ltd registered in the UK. The company combines the engineering

More information

TECHNICAL SPECIFICATIONS TABLE OF CONTENTS SUMMARY SERIES PRELIMINARIES & GENERAL REQUIREMENTS SPECIFICATIONS

TECHNICAL SPECIFICATIONS TABLE OF CONTENTS SUMMARY SERIES PRELIMINARIES & GENERAL REQUIREMENTS SPECIFICATIONS TECHNICAL SPECIFICATIONS TABLE OF CONTENTS SUMMARY PART 1 PART 2 PART 3 PART 4 PART 5 PART 6 PART 7 SERIES 100 - PRELIMINARIES & GENERAL REQUIREMENTS SPECIFICATIONS CIVIL WORKS SPECIFICATIONS BUILDING

More information

As of DECEMBER LETTERS OF NO OBJECTION Ascension Parish

As of DECEMBER LETTERS OF NO OBJECTION Ascension Parish 17012009 AT&T b/w 3031 To place a new fiber optic cable for service at 3460 Hwy 44 (+11) Through Byers Engineering & 3043 17021025 Entergy Gulf States Louisiana, LLC 2242+00 To install two (2) poles and

More information

3.12 UTILITIES Introduction Environmental Setting

3.12 UTILITIES Introduction Environmental Setting 3.12 UTILITIES 3. Affected Environment and Environmental Analysis 3.12 UTILITIES 3.12.1 Introduction This section addresses the potential for impacting public utilities within the Port, the Main Channel,

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities

More information

FACILITY COMPONENTS - MIDDLE SCHOOL

FACILITY COMPONENTS - MIDDLE SCHOOL SITE AREAS Parking and Access - Buses 2.0 2.0 0.30 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 1.0 3.0 0.22 Four fewer stalls

More information

Modified FY ,100, ,329,791

Modified FY ,100, ,329,791 Retail/North Andrews Gardens Neighborhood Improvement Program Expenses Through FY 4 Modified FY 5 Budget FY 26-21 North Andrews Gardens Neighborhood Improvement Project 21,524,34 22,75,757 --- 6,1, 6 ---

More information

2014 Adopted. Capital Improvement

2014 Adopted. Capital Improvement 2016 2014 Adopted Adopted Annual BudgetBudget Capital Improvement MDC The Metropolitan District Hartford, CT Overview Summary The Capital Improvement Program (CIP) budget is based upon the MDC s comprehensive

More information

PO. Box 4708, Al-Hofuf, Saudi Arabia, Tel: , Fax: Website:

PO. Box 4708, Al-Hofuf, Saudi Arabia, Tel: , Fax: Website: PO. Box 4708, Al-Hofuf, Saudi Arabia,.31982 Tel: +966 3 5933555, Fax: +966 3 5944555 Email: info@msg.com.sa Website: www.msg.com.sa Table of Contents Item Description 01. Introduction 02. CEO Message 03.

More information

FURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP

FURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP A. TECHNICAL INFORMATION OF OUR FOUNDATION WORKS The major types of our foundation works (with illustrative diagram, where applicable) are set out below: 1. Bored piles 0.80m 3.5m pile shaft By Grabbing

More information

SECTION 13 WATER SYSTEMS

SECTION 13 WATER SYSTEMS TABLE OF CONTENTS SECTION 13 WATER SYSTEMS 13.1 PURPOSE AND DEFINITIONS... 1 13.1.1 Purpose... 1 13.1.2 DOU Water System... 1 13.1.3 Definitions... 1 13.2 GENERAL REQUIREMENTS... 6 13.2.1 Authority and

More information

1. Provide a revised bid form (attached to this addendum 11)

1. Provide a revised bid form (attached to this addendum 11) Philadelphia Regional Port Authority 3460 North Delaware Ave. 2 nd Floor Philadelphia, PA 19134 July 6, 2018 To: All Bidders From: Kate Bailey Director of Procurement Re: ADDENDUM NO. 11 Project 18-038.1

More information

To The Property Owners, Tenants Re: Invitation to Attend a Public Information Centre Spruce Street and Briercrest Avenue Reconstruction

To The Property Owners, Tenants Re: Invitation to Attend a Public Information Centre Spruce Street and Briercrest Avenue Reconstruction March 7, 2016 To The Property Owners, Tenants Re: Invitation to Attend a Public Information Centre Spruce Street and Briercrest Avenue Reconstruction The City of Cambridge is proposing to reconstruct Spruce

More information