Whittier Bridge/I-95 Improvement Project. Public Information Meeting
|
|
- Karin Watson
- 6 years ago
- Views:
Transcription
1 Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013
2 Agenda: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Introduce the Design-Build Team Current Project Schedule Design Project Overview (review purpose, goals & scope) Developments since last public meeting Construction Construction phasing\sequence, Staging Areas Hours of work Mitigation of Impacts Communications program Contact Information
3 Design-Build Team Construction Contractors: Walsh Construction and McCourt Construction formed the Walsh-McCourt Joint Venture (JV1) With lead designer subconsultant HNTB Corporation Specialty Subconsultants include: Green International Affiliates, Inc. Survey, drainage, structural design Shadley Associates, P.C. Landscape Architecture Regina Villa Associates, Inc. Public outreach Public Archaeology Laboratory - Cultural resources Genesis Structures, Inc. Erection & demolition engineering
4 Current Project Schedule
5
6
7 DESIGN Project Overview & Design Developments
8 Project Description & Purpose Replace the structurallydeficient John Greenleaf Whittier Bridge carrying I- 95 over the Merrimack River Improve I-95 from Exit 57 (Rte. 113) to Exit 60 by widening the roadway, improving ramp geometry, upgrading drainage & lighting systems
9 Project Goals Improve safety Provide bridge that meets all current standards Improve traffic flow Improve air quality by reducing congestion Support non-motorized modes of transportation
10 Overall Project Map
11 New Whittier Bridge WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Network tied arch main spans Two new parallel structures, each carrying 4 lanes plus shoulders Shared Use Path (SUP) on NB structure with connections along approaches
12
13
14
15 Shared Use Path
16
17
18
19 Pine Hill (Ferry Rd) Bridge
20 Evans Place (Main St) Bridge
21 Rte. 110 Bridge
22 Abandoned RR Bridges
23 Design Changes & Refinements Since Last Public Meeting CCTV Cameras along SUP Evans Place Bridge - Alternative Superstructure Type & Span Whittier Bridge Pier Configuration Transparent barrier on NB Whittier SUP barrier Proposal to replace existing fan wall with new modular wall
24 Base Technical Concept Pier Configuration Piers with vertical columns and arch supported on cantilevered cap beam
25 Revised Pier Design WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Piers with sloping columns to provide support directly beneath arches
26 Transparent Fence on Shared Use Path Barrier on the Whittier Bridge
27 Relocation of Existing Wall adjacent to Laurel Road WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT
28 Existing Fan Wall Adjacent to Laurel Road
29 Comparision of Alternatives
30 Retaining Wall Finish WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT
31 CONSTRUCTION Phasing/sequence, Hours of Work, Mitigation of Impacts
32 Construction Construction Phasing/Sequencing Staging Areas Hours of Work Mitigation of Impacts a. Traffic\Real Time Traffic Management System b. Environmental c. Construction Noise d. Navigation channel
33 Traffic Maintenance Requirements I-95 NB & SB 3 lanes to be provided during peak travel times For I-95 NB: a. Single lane closure, Monday-Thursday 7:00 PM 5:00 PM b. Two lane closure, Monday-Thursday 10:00 PM 7:00 AM For I-95 SB: a. Single lane closure, Monday-Thursday 9:00 AM 6:00 AM b. Two lane closure, Monday-Thursday 9:00 PM 6:00 AM No lane closures during holiday weekends and summer weekends
34 Route 110 Single lane closure allowed: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Traffic Maintenance Requirements, cont d Monday-Friday 9:00 AM 3:00 PM Monday-Thursday 8:00 PM 6:00 AM All weekend (Saturday & Sunday) & holiday closures require MassDOT approval Evans Place Alternating traffic (with flaggers) allowed: Monday-Friday 9:00 AM 3:00 PM Route 110/I-95 NB On-Ramp Shall remain open between Memorial Day & Labor Day Pine Hill Road Alternating traffic in single lane, using temporary traffic signals, until new bridge constructed (There will be exceptions to the above, which will require MassDOT approval & public notifications will be issued prior to any changes)
35 Real Time Traffic Management System
36 Real Time Traffic Management System
37 Erection of the Whittier Bridge Approach spans become supply path for arch erection
38 Erection of the Whittier Bridge Arch deck erected with Mi-Jacks Arch ribs erected with small cranes
39 Erection of the Whittier Bridge Approach spans Mi-Jacks Arch span Mi-Jack, cranes
40 Erection of the Whittier Bridge Approach spans become supply path for arch erection
41 Erection of the Whittier Bridge Arch deck erected with Mi-Jacks Arch ribs erected with small cranes
42 COMMUNICATIONS PROGRAM
43 Communications Program Update stakeholders on project progress Website E-blast updates/advisories Social media Press advisories Business coordination, as necessary Abutter/coordination meetings and briefings as necessary
44 Project Website WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT
45
46 Project Contact Information Project website: Stephanie Boundy, MassDOT Public Outreach Coordinator office phone: (857)
47 Thank You for Attending!
Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury
Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury EAE No. 14427 http://whittierbridge.mhd.state.ma.us/ Public Meeting 12.07.11 Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury
More informationWelcome! Route 1 Viaduct Rehabilitation Project Chelsea Project File No
Welcome! Route 1 Viaduct Rehabilitation Project Chelsea Project File No. 605287 25% Design Public Hearing Chelsea City Hall January 24, 2018 6:30 p.m. Introduction Welcome & Introductions by MassDOT PM
More informationDecember 19, 2012 ADDENDUM NO. 11. To Prospective Bidders and Others on:
601096-12 December 19, 2012 ADDENDUM NO. 11 To Prospective Bidders and Others on: Technical/Price Proposals Postponed To: Thursday, January 17, 2013 @ 2:00 PM Transmitting the following Documents and Clarifications:
More informationI-91 Viaduct Public Information Briefing
I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 9 September 13, 2017 Agenda Welcome and Presenter Introductions Update on Construction and Demolition
More informationAtlantic Street Bridge Project CTDOT Project Nos (Phase 1) & (Phase 2)
Atlantic Street Bridge Project CTDOT Project Nos. 135-326 (Phase 1) & 135-301 (Phase 2) Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement City of Stamford www.atlanticstreetbridge.com
More informationIntroductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House
May 22, 2018 1 Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House Rendering of Trail and Community Improvements at Project Completion 2
More informationCHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO.
CHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO. 5 Agenda: 1. Welcome/Introductions 2. Progress & Updates Since Previous
More informationRt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016
Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb
More informationRt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening
Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening March 5, 2009 Nicholas J. Roper NOVA District Bridge Engineer Robert F. Price Resident Administrator of Loudoun/ Prince William Construction
More informationInnovative Fisheries Protection for MassDOT Design-Build Projects. Frank Welch Resident Engineer MassDOT District 4 Construction
Innovative Fisheries Protection for MassDOT Design-Build Projects Frank Welch Resident Engineer MassDOT District 4 Construction Agenda Design Build Process Overview Design Build Project Examples: I-95
More informationI-91 Viaduct Public Information Briefing
I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown
More informationNew Governor Harry W. Nice Memorial Bridge (US 301) Will Pines, P.E.
New Governor Harry W. Nice Memorial Bridge (US 301) Will Pines, P.E. Director of Project Development April 9, 2018 www.newnicebridge.com 1 Project Background Construction dates: March 1938 December 1940
More informationPROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012
PROJECT UPDATE Rendering View from the City of Chesapeake Elizabeth River Boat Landing and Park looking across the Elizabeth River at Portsmouth CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA The new 5,375
More informationAGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.
Route 15/29 SBL Bridge Superstructure Replacement & Widening Existing Structure Scope Accelerated Procedure Staging (Superstructure) Preparatory Work (Substructure) NOVA District Questions EXISTING STRUCTURE
More informationMAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0
MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2018.05 EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 The bid opening date is Thursday March 15, 2018 at 11:00 a.m. The following changes
More informationEvanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201
Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October
More informationReconstruction Project Update
I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial
More informationVT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017
VT 14 East Montpelier Bridge Project Informational Meeting February 22, 2017 Welcome & Introductions VTrans Mark Sargent, Project Manager Wayne Symonds, Structures Program Manager Chris Barker, Resident
More informationI-70 over SR 121 Bridge Slide Construction and Engineering
I-70 over SR 121 Bridge Slide Construction and Engineering March 6, 2018 Kevin Gorak, American Structurepoint Pete Jerrell, Walsh Construction Project Overview Project Location I-70 in Richmond, IN Project
More informationCONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/01/2017 to 10/07/2017
AECOM Field Office 3550 Water Street, NW Under the Key Bridge North Abutment REHABILITATION OF FRANCIS SCOTT KEY BRIDGE FROM ROSSLYN, ARLINGTON, VIRGINIA TO GEORGETOWN WASHINGTON, DC. DC Contract No.:
More informationPattullo Bridge Replacement Project. Cost Report
Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...
More informationPEAK RUNOFF RATES (CUBIC FEET PER SECOND)
Water Quality Swales would be provided in the median where space is available. The existing inside lanes of the northbound and southbound roadway from south of Route 110 in Amesbury to the northern project
More informationChapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction
Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the
More informationExpo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013
Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Meeting Agenda Pre-Construction Meeting Meeting Purpose and Format Project Status Update Introduction of Construction Contractor
More informationWell Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.
Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan
More informationSINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.
SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT Srdjan Brasic, M.Sc., P.Eng. UMA Engineering Ltd. Paper prepared for presentation at the Technical
More informationConstructability Guidelines
Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final
More informationNortheast Bridge Preservation Partnership Meeting
Northeast Bridge Preservation Partnership Meeting Superstructure Preservation Strategies Aetna Viaduct Superstructure Repairs Route I-84 City of Hartford, CT State Project No. 63-648 David A. Cutler, P.E.
More informationConceptual Design Report
Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE
More information3.0 Project Alternatives
Whittier Bridge/I-95 Improvement Project EA/DEIR 3.0 Project Alternatives 3.1 INTRODUCTION This chapter provides a summary analysis of the potential project alternatives for the Whittier Bridge/I-95 Improvement
More informationMay 26, Required Attendance Yes_X_ No MEMORANDUM. Mr. Don Silies Attn: Mr. John Jacobs. Salvija Hofheimer. Project Showing
Project No.: 0264-122-108, C508, B602-5, B616, D604-5 UPC 57048 City of Norfolk and City of Virginia Beach Order #J66 Contract ID #C0000057048C08 Required Attendance Yes_X_ No MEMORANDUM TO: FR: RE: Salvija
More informationIMPROVING I 81 IN MARYLAND
IMPROVING I 81 IN MARYLAND April 25, 2017 Stephen A. Bucy, P.E. Improving I 81 in Maryland Overview: Facts SHA s Comprehensive I 81 Strategy Current Phase 1 Widening Project Update Closing Improving I
More informationPUBLIC INFORMATION MEETING June 24, 2015
Gallows Road (RTE. 650) over Arlington Boulevard (RTE. 50) Fairfax County Bridge Rehabilitation, Preventive Maintenance and Pier Repairs Phase 1 - Project No. 0650-029-235; UPC 106956, Pier Repair Phase
More informationCONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 06/04/2017 to 06/10/2017
AECOM Field Office Water Street, NW Under Key Bridge along Water Street, NW REHABILITATION OF FRANCIS SCOTT KEY BRIDGE FROM ROSSLYN, ARLINGTON, VIRGINIA TO GEORGETOWN WASHINGTON, DC. DC Contract No.: DCKA-2014-C-0074
More informationWELCOME. Public Meeting for I-35 / I-44 Interchange. October 6, 2015
WELCOME Public Meeting for I-35 / I-44 Interchange October 6, 2015 TEAM INTRODUCTIONS PURPOSE OF THIS MEETING is to present the alternative alignments for the I-35/I-44 and I-35/NE 63rd Street Interchanges
More informationCITY OF TACOMA Tacoma Rail
CITY OF TACOMA Tacoma Rail ADDENDUM NO. 2 DATE: May 11, 2015 REVISIONS TO: Request for Bids Specification No.: TR15-0215F SR-509 TRACK UPGRADES NOTICE TO ALL BIDDERS: This addendum is issued to clarify,
More informationDETROIT RIVER INTERNATIONAL CROSSING STUDY MAG
DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG Meeting September 5 th, 2006 1 Agenda 1. Study Update 2. Construction Staging for Tunneling 3. Other Business 2 Deep Borehole Program 3 Status Update - Engineering
More informationASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa
2014 HDR Architecture, 2014 HDR, Inc., all rights reserved. ASCE STRUCTURAL ENGINEERING CONFERENCE Ames Iowa WHAT DO YOU DO IF YOU HAVE MORE PROJECT THAN BUDGET? DESIGN BUILDER SELECTION METHOD Fixed Price
More informationNEWINGTON-DOVER WELCOME
NEWINGTON-DOVER Spaulding Turnpike / Little Bay Bridge Project WELCOME SENH/NH-ASCE Joint Meeting September 28, 2011 VHB, Inc. Presentation Outline Introduction Project Overview Bridge Design Considerations
More informationInterstate 66 Widening from. RFQ Information Meeting. January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager
Interstate 66 Widening from Gainesville to Haymarket RFQ Information Meeting January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager John C. Daoulas, P.E. APD Project Manager and POC Introduction
More informationTRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES
TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES The District of West Vancouver requires a Traffic Management Plan (TMP) to be submitted for acceptance by the Land Development
More informationAgenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014
Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend
More informationAPPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES
APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES Massachusetts Department of Transportation Highway Division I-95 / Whittier Bridge Replacement Type Study Report 6. Evaluation of
More informationActive Traffic Management in Michigan. Patrick Johnson, P.E. HNTB Michigan Inc.
Active Traffic Management in Michigan Patrick Johnson, P.E. HNTB Michigan Inc. Active Traffic Management (ATM) Active Traffic Management Strategies: Dynamic Lane Use Dynamic Shoulder Use Queue Warning
More informationM6 J16-19 Smart Motorway. Kate Beirne Highways England Michael Robinson Jacobs Julian Wilson Carillion Kier JV
M6 J16-19 Smart Motorway Kate Beirne Highways England Michael Robinson Jacobs Julian Wilson Carillion Kier JV Introduction Scheme Update Progress Current Status Delivery timescales Environment Construction
More informationUC Press Building 2120 Berkeley Way Berkeley, CA
CONSTRUCTION NOISE REDUCTION PROGRAM FOR: UC Press Building 2120 Berkeley Way Berkeley, CA RGD Project #: 17-057 PREPARED FOR: Berkeley Way, LLC 1958A University Ave. Berkeley, CA 94704 PREPARED BY: Harold
More informationBow Concord I-93 Improvements City of Concord Transportation Policy Advisory Committee
Bow Concord I-93 Improvements City of Concord Transportation Policy Advisory Committee December 15, 2016 Agenda Project History / Project Development Process Traffic Modeling Alternatives Development o
More informationMaritime Work Plan for the High Rise Bridge Construction
Maritime Work Plan for the High Rise Bridge Construction Version 6, 10/3/2018 I 64 Southside Widening & High Rise Bridge, Phase 1 Chesapeake, Virginia Design Build Project State Project No.: 0064 131 811,
More informationProject Overview. Wilson Boulevard over Route 50 Bridge Rehabilitation. Get Involved. Public Information Meeting. Contact Information
Get Involved VDOT representatives will review and evaluate any information received as a result of the public information meeting. The comment sheet in this brochure is provided to assist in making your
More informationMAINE MEDICAL CENTER
MAINE MEDICAL CENTER Construction Projects at the East Tower, Visitor Garage, Central Utility Plant Construction Management Plan December 15, 2017 Prepared for: Portland Department of Planning & Urban
More informationSECTION 55A1 ROBINSON TOWNSHIP, WASHINGTON COUNTY
WEEK ENDING SEPTEMBER 14, 2018 SECTION 55A1 ROBINSON TOWNSHIP, WASHINGTON COUNTY Contractor: Independence Excavating, Inc 1. Work Shift Day shift (M-F) with Saturday as a makeup day. 2. Traffic Candor
More informationAPPROACHES AND BRIDGE OVER TYE RIVER (RTE. 29 NBL) RFP QUESTIONS AND ANSWERS-REVISION 2
Project: APPROACHES AND BRIDGE OVER TYE RIVER (RTE. 29 NBL) PROJECT: 0029-005-130, C501, B645 RFP QUESTIONS AND ANSWERS-REVISION 2 Date: 12/04/09 Approaches and Bridge over Tye River (Rte. 29 NBL) Subject:
More informationHighway 417 Bridge Replacement
Highway 417 Bridge Replacement West of Maitland Avenue to East of Island Park Drive Hampton Iona Community Group June 6, 2006 7:00 p.m. to 9:00 p.m. Overview of Project Area MAITLAND CLYDE CARLING WBL
More informationPulaski Skyway Rocker-Bent Investigation Contract at Span 47 and 97
Pulaski Skyway Rocker-Bent Investigation Contract at Span 47 and 97 Route U.S. 1 & 9 (Pulaski Skyway) Contract No. 051183160 Town of Jersey City, Hudson County City of Newark, Essex County PRE-BID MEETING
More informationCost Implications of Rapid Renewal Projects
Cost Implications of Rapid Renewal Projects Discussion on Total Project Cost Michael P. Culmo VP Transportation and Structures CME Associates, Inc. REALITY In general, bid prices for ABC are higher than
More informationLesner Bridge Replacement
Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on
More informationReview of Plans and Specs from a Constructability Perspective
Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability
More informationCONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 08/12/2018 to 08/18/2018
AECOM Field Office 3550 Water Street, NW Under the Key Bridge North Abutment REHABILITATION OF FRANCIS SCOTT KEY BRIDGE FROM ROSSLYN, ARLINGTON, VIRGINIA TO GEORGETOWN, WASHINGTON, DC. DC Contract No.:
More informationIronton Russell Bridge Project
Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationSmarter Work Zones Webinar Series
Smarter Work Zones Webinar Series Webinar #12: Integrating Technology Applications Massachusetts DOT Todd Peterson and Neil Boudreau April 26, 2016 1:00-2:30pm EST Efficiency through technology and collaboration
More informationAccelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents
Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents Washington State s Skagit River Bridge Emergency Slide Bijan Khaleghi
More informationBRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT)
SPECIAL PROVISION August 31, 2009 PROJECT # S-R399(42) PROJECT # S-R399(59) PIN # 6697/7236 SECTION 03253S BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) Add Section 03253S: PART
More informationExpansion joint replacement using the Mini-Fly-Over system to minimise impacts on traffic
19th IABSE Congress Stockholm, 21-23 September 2016 Expansion joint replacement using the Mini-Fly-Over system to minimise impacts on traffic Thomas Spuler, Colm O Suilleabhain Mageba SA, Bulach, Switzerland
More informationAGENDA REPORT. To: Attachments: 1. Site Location and Outreach Map 2. Recommended Permit Conditions 3. Fencing Location
9 Meeting Date: May 8, 2018 Item Number: D 6 To: From: Subject: AGENDA REPORT Honorable Mayor & City Council Robert Welch, Acting City Engineer Raj Patel, City Building Official ASBESTOS ABATEMENT PERMIT
More informationMaine Turnpike Authority FINAL 4-year Capital Investment Plan ( )
Total preliminary Value for Project shown in initial year is for project duration. Projects have been listed in each year there are major Preliminary 4.8 Beech Ridge Road Underpass Repairs York $410,000
More informationCommunity Advisory Panel Meeting #
Community Advisory Panel Meeting # 4 11.07.18.. Agenda Welcome and Introductions Outreach Materials Update Work Plan Update Community Conversations Alternative Review Charleston/Meadow Exhibits and 3D
More informationMAY 4, Noise Barrier Presentation NE Quadrant Smith Avenue, Cherry Hill Circle NOISE BARRIER ABUTTER MEETING. Tech Environmental, Inc.
MAY 4, 2011 Noise Barrier Presentation NE Quadrant Smith Avenue, Cherry Hill Circle 1 Introductions Agenda Overview of Interchange Project Overview of noise barrier process Fundamentals of sound & proposed
More informationBridge Fire Lake County MP 282 Turnpike over CR 561. Aran Lessard Florida s Turnpike Enterprise Structures Maintenance
Bridge Fire Lake County MP 282 Turnpike over CR 561 Aran Lessard Florida s Turnpike Enterprise Structures Maintenance Location Accident and Incident Response Monday 12/14/2009 Accident and Incident Response
More information811 Emerson St. - Demolition & Site Prep
811 Emerson St. - Demolition & Site Prep 811 Emerson St. Evanston, IL 60201 CA Focus Evanston Property Owner, LLC General Contractor Owner Architect Construction Management Plan Phase I January 24t h,
More informationIronton Russell Bridge Project
Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015
More informationIronton Russell Bridge Project
Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place
More informationNEPA and Design Public Hearings
NEPA and Design Public Hearings Monday, December 5, 2016 Washington-Lee High School 1301 N. Stafford Street Arlington, VA 22201 Thursday, December 8, 2016 Mary Ellen Henderson Middle School 7130 Leesburg
More informationConstruction Coordination & Management Planning MassDOT-Highway/MBTA. 495/MetroWest Partnership Briefing July 11, 2018
Construction Coordination & Management Planning MassDOT-Highway/MBTA 495/MetroWest Partnership Briefing July 11, 2018 Overview The Construction Coordination and Management Planning exercise was a 100-day
More informationTable of Contents. List of Appendices
Table of Contents Page Executive Summary 3 Description of Project 3 TMP Roles and Responsibilities 3 Area Engineer 3 Communications Office 4 TMP Monitoring 4 Existing and Future Conditions 4 Traffic Counts
More informationNew Stadium Project. Construction Activity Mitigation Program. January 22, 2014
New Stadium Project Construction Activity Mitigation Program January 22, 2014 Construction Mitigation Plan Introduction It is the primary goal of HHRM, JV to minimize negative effects on traffic and the
More informationTilikum Crossing Transit Bridge. Portland, OR
Tilikum Crossing Transit Bridge Portland, OR Technical Information Size of Project: The Tilikum Crossing Transit Bridge is 1,720 ft. long and required 24,000 cy total concrete Strength Requirements: The
More informationIronton Russell Bridge Project
Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September
More informationDesign-Build for Improvements to the Amherst Island Ferry Docks Public Information Centre April 2017 Please Sign In
WELCOME Design-Build for Improvements to the Amherst Island Ferry Docks Public Information Centre April 2017 Please Sign In PURPOSE OF THIS MEETING Rankin Construction Inc. (RCI) and their design consultant
More informationRiverside County Transportation Commission RFP Number TP ATTACHMENT 4-1 WORK BREAKDOWN STRUCTURE
TP ATTACHMENT 4-1 WORK BREAKDOWN STRUCTURE TP Attachment 4-1 Work Breakdown Structure Page 1 The following Work Breakdown Structure (WBS) must be the basis for organizing all Work under the Contract Documents
More informationRiverside County Transportation Commission RFP Number TP ATTACHMENT 4-1 WORK BREAKDOWN STRUCTURE
TP ATTACHMENT 4-1 WORK BREAKDOWN STRUCTURE TP Attachment 4-1 Work Breakdown Structure Page 1 The following Work Breakdown Structure (WBS) must be the basis for organizing all Work under the Contract Documents
More informationConstruction Cost Estimation Preparation Manual (Metric Units)
07/25/2001 Construction Cost Estimation Preparation Manual (Metric Units) July 2001 Prepared by Cost Estimating Unit Program Support Services 07/25/2001 Table of Contents Section Page 1.0 Introduction
More informationExhibit G. Construction Mitigation Plan
Exhibit G Construction Mitigation Plan Construction Period Mitigation 1. A construction period mitigation plan shall be prepared by the applicant for approval by the Public Works Department prior to issuance
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationNORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR
NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR0013844 & BR0013129 COLUMBIA, CHEROKEE COUNTY, SOUTH CAROLINA I-85 UNDERPASS PROJECT (1) REPLACEMENT OF EXISTING I-85 UNDERPASS BRIDGE MILEPOST SB-141.35 DOT/AAR
More informationDESIGN PUBLIC HEARING MAY 16, 2013 ABIGAIL ADAMS MIDDLE SCHOOL WEYMOUTH, MASSACHUSETTS 6:30 PM FOR THE PROPOSED BRIDGE REPLACEMENT PROJECT
DESIGN PUBLIC HEARING MAY 16, 2013 AT ABIGAIL ADAMS MIDDLE SCHOOL WEYMOUTH, MASSACHUSETTS 6:30 PM FOR THE PROPOSED BRIDGE REPLACEMENT PROJECT STATE ROUTE 3A OVER FORE RIVER Project File No. 604382 Bridge
More informationOHIO TURNPIKE AND INFRASTRUCTURE COMMISSION
MAINTENANCE OF TRAFFIC NOTES 431606 - MOT Notes - Addendum 1.dwg; 10/22/15-3:25pm MAINTENANCE OF TRAFFIC MAINTENANCE OF TRAFFIC SEQUENCE: THESE PLANS ARE BASED ON THE FOLLOWING SUGGESTED SEQUENCE OF CONSTRUCTION.
More informationMaryland Transportation Authority (MDTA)
Maryland Transportation Authority (MDTA) I-95 Major Deck and Superstructure Rehabilitation South of the Fort McHenry Tunnel Northeast Bridge Preservation Partnership Conference September 20, 2016 David
More informationDESIGN AND LAUNCHING OF A REDUNDANT TRUSS OVER RAILROAD YARD
2018 Purdue Road School Transportation Conference Rendering by Touchstone Architecture Martin Furrer, PE, SE March 6, 2018 DESIGN AND LAUNCHING OF A REDUNDANT TRUSS OVER RAILROAD YARD Project Location
More informationDesign-Build Selmon West Extension
TAMPA-HILLSBOROUGH COUNTY EXPRESSWAY AUTHORITY Letter of Clarification No. 1 FOR REQUESTS FOR PROPOSALS Design-Build Selmon West Extension Page 1 of 8 Letter of Clarification No. 1 ~ Date of Letter of
More informationGEOMETRY CONTROL OF PRECAST SEGMENTAL BALANCED CANTILEVER BRIDGES ON THE HUNTER EXPRESSWAY
GEOMETRY CONTROL OF PRECAST SEGMENTAL BALANCED CANTILEVER BRIDGES ON THE HUNTER EXPRESSWAY Introduction Authors Jarrod Hitchcox Associate Technical Director Arcadis Australia Pacific jarrod.hitchcox@arcadis.com
More informationI-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions
I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions General Overview What is the I-65/I-70 North Split Reconstruction Project? The I-65/I-70 North Split Reconstruction Project
More informationDELAWARE RIVER JOINT TOLL BRIDGE COMMISSION EXECUTIVE OFFICES 2492 RIVER ROAD NEW HOPE, PENNSYLVANIA
CONTRACT NO. T-668A, CAPITAL PROJECT 0301A SCUDDER FALLS BRIDGE REPLACEMENT PROJECT NOTICE TO CONTRACTORS September 13, 2016 Sealed bids for Contract No. T-668A, Capital Project 0301A, Scudder Falls Bridge
More informationTorbram Road Improvements From Queen Street East to Bovaird Drive
Torbram Road Improvements From Queen Street East to Bovaird Drive Municipal Class EA Study Public Information Centre No. 1 November 16 2017 6:30 pm 8:30 pm Please sign in so we can keep you updated on
More informationDate: May 4, Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis
MEMORANDUM To: CAJA Environmental Services, LLC Date: From: Subject: Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis LLG
More informationMOSLEY STREET URBANIZATION TH
Public Information Centre 1 (PIC 1) MOSLEY STREET URBANIZATION TH 45 BEACHWOOD ROAD TO STREET Class Environmental Assessment November 29, 2016 Welcome 2 This Public Information Centre will: establish channels
More informationApplication of Accelerated Bridge Construction for Local Agencies
Application of Accelerated Bridge Construction for Local Agencies APWA Public Works Conference November 9, 2017 Dorie Mellon Senior Bridge Engineer, Caltrans Matt Randall Senior Engineer, County of Placer
More informationI-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010
I-405 Sepulveda Pass Widening Project Community Advisory Committee Meeting June 24, 2010 1 MWD LA-29 Project Drilling to install beams for shoring to support excavation at Sunset Bl and Church Ln 2 MWD
More informationTransportation Management Plan
US395, from I-80 to California State Line September 2016 Prepared for: Nevada Department of Transportation Prepared by: CA Group, Inc. Executive Summary The purpose of this project is to expand the Freeway
More informationARCHITECTUS FEBRUARY 2010
ARCHITECTUS PEDESTRIAN AND TRAFFIC MANAGEMENT PLAN FOR DEMOLITION, EXCAVATION AND CONSTRUCTION OF COLLEGE OF FINE ARTS CAMPUS, PADDINGTON FEBRUARY 2010 COLSTON BUDD HUNT & KAFES PTY LTD ACN 002 334 296
More information