Jane Addams Elementary School S Avenue H Chicago, IL 60617
|
|
- Valerie Morton
- 6 years ago
- Views:
Transcription
1 00 S Avenue H Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item with identical rank and total the quantity into a single line, regardless of item location (for location data, see the detailed report). Assessors rate each facility item by visual observation only; they do not test the operation of equipment or perform destructive testing of walls, ceilings or floors. Each facility item is ranked on a -point scale: rank means the item is in new or in good condition and no work is required while rank means the item has failed and has lead to an immediate life safety condition¹. The remaining ranks choices generally mean that the item requires regular maintenance (rank or ) or full replacement (rank, 3 or ). For additional detail and definition on rank values as they relate to each assessed item, please visit the "CPS Guide to Biennial Facility Assessments" found on the Facilities Standards webpage under CPS Policies and Guidelines at Definitions for Quantity, Unit, Cost and Campus Total can be found at the end of this report. Campus Summary Building ame ear Constructed umber of Floors Building Area (Sq Ft) Assessed eed Main 9 3,3 $,0,0 Addition 99 3,99 $,3 Annex 99 3,3 $3, Leased 90 3,00 $,99 Modular 99,9 $,3 Modular 99,9 $,0 Modular , $33, SITE $,03 Campus Total,3 $3,0,39 Building: Main Category: Building Exterior Entrance Entrance Control - Audio EA Exterior Doors - Exterior Steel Door EA $,9 Exterior Doors - Exterior Wood Door EA $,3 Exterior Doors - Exterior Wood Door EA $9 Exterior Doors - Transom Lite EA $ Exterior Doors - Transom Lite 3 EA $9 Exterior Stairs - Concrete LF $,0 Exterior Stairs - Concrete 90 LF $,39 Exterior Stairs - Concrete 00 LF Exterior Stairs - Stone 0 LF $, Stair Handrail - Steel_Stair Handrail LF $0 Stair Handrail - Steel_Stair Handrail 0 LF ADDAMS Page of 3 Assessment Date: //0
2 Building: Main Category: Building Exterior Foundation 00 S Avenue H Chicago, IL 0 Foundation - Concrete 0 LF $,9 Foundation - Concrete 99 LF Superstructure - Concrete 3,3 SF Lighting Roof System Walls Windows Exterior Lighting - Parapet or Roof Mounted EA $3, Exterior Lighting - Wall Mounted EA $,030 Exterior Lighting - Wall Mounted EA $, Chimney - Metal Flue LF $,3 Coping - Stone 0 LF $,3 Downspouts - Interior Downspouts LF $,99 Parapet - " - 30" Height 0 LF $,3 Parapet - " - 30" Height 0 LF $,0 Parapet - Parapet > 30" 93 LF $,9 Roof - Asphalt Gravel Ballast 0 SF 3 $3, Roof - Asphalt Gravel Ballast 3,39 SF $3,0 Roof - Asphalt Gravel Ballast 3 SF $,3 Roof Structure - Steel with Clay Tile Arch,03 SF Cheek-Wall - Concrete SF $3 Cheek-Wall - Concrete SF $3 Cheek-Wall - Stone 0 SF $, Exterior Walls - Brick 0 SF $,3 Exterior Walls - Brick,3 SF $09,99 Exterior Walls - Stone-Cast,0 SF $0, Guard - Guards wire guard SF $,09 Lintels - Steel LF $,9 Lintels - Stone LF Windows - Decorative SF Windows - Sash Aluminum SF $,09 Windows - Sash Lexan, SF $0,09 Building Exterior Subtotal: $,03 ADDAMS Page of 3 Assessment Date: //0
3 Building: Main Category: Electrical System Emergency System 00 S Avenue H Chicago, IL 0 Automatic Transfer Switch EA $ Emergency A/C Power - Corridors and Stairs,9 SF $ Emergency A/C Power - Gym, SF $9 Emergency A/C Power - Students Toilets,0 SF $3 Exit Signs - Corridors and Stairs EA $,3 Exit Signs - Gym EA $,33 Security System - CCTV 3,3 SF $9, Security System - Intrusion Detection 3,3 SF $,9 Main Service Power Distribution Independent Electrical Service for emergency power EA Main Electrical Service - 00 A 0/0/3PH EA $, PA System 3,3 SF $0,3 Lighting and Power Panels - 00 A EA $,393 Lighting and Power Panels - Above 00 A EA $,9 Main Distribution Panels amp EA $ Main Distribution Panels - Greater than 00 amp EA $30 Main Distribution Panels - Less than 0 amp EA $,9 Electrical System Subtotal: $,3 Building: Main Category: Safty System Fire Alarm Fire Alarm Panel EA $9, Fire Alarm Strobe Lights 3,3 SF $, Fire Alarm_System 3,3 SF $,33 Safty System Subtotal: $,09 Building: Main Category: Mechanical System ADDAMS Page 3 of 3 Assessment Date: //0
4 Building: Main Category: Mechanical System Air Handling Systems 00 S Avenue H Chicago, IL 0 Air Handling Unit- Built Up- Single Zone w/ Air Tunnel- Steam Coils cfm EA $, Air Handling Unit- Package Single Zone- Indoor- Steam Coils - Less than 00 cfm EA $,00 Air Intake 3 EA $,9 Auxiliaries cfm EA $, Auxiliaries - Less than 00 cfm EA Indoor Return Fans- Centrifugal Squirrel Cage CFM EA $, Reheat Boxes - Reheat Boxes with Steam Coil EA $,30 Return Duct Work - Masonry and Ducts- Missing or Existing Shaft 00 LF Zone Dampers EA $,99 Boiler Systems Heating Devices Temperature Control Ventilation Boiler Auxiliary- Steam Boiler HP EA $,09 Chemical Feed System EA $,0 Chemical Feeder EA $,0 Combustion Dampers EA $ Condensate Pump EA $,0 Feed Water Pumps and Tank EA $, on Condensing- Water Tube- Flexible Tube- Force Draft- Steam Boiler HP EA $, Piping - Condensate Pipe- Steel 300 LF $ Piping - Steam Pipe- Steel 300 LF $ Steam Traps EA $,3 Vacuum Pump EA $, Cabinet Heaters - With Steam Coil EA $, Radiators - Steam 3 EA $3, Unit Heater - Gas EA $ Wall Heater - Electric 9 EA $,0 Pneumatic System 3,3 SF $,9 Thermostats - Pneumatic 0 EA Exhaust Fans- Indoor CFM EA $, Exhaust Fans- Indoor CFM EA $9 Mechanical System Subtotal: $,3 ADDAMS Page of 3 Assessment Date: //0
5 Building: Main Category: Plumbing System Hot Water 00 S Avenue H Chicago, IL 0 Gas Heater BTU/HR EA $30 Gas Heater - Less than 0000 BTU/HR EA $30 Hot Water Storage Tank_Gas - Less than 00 Gallons EA $ Piping Pumps Domestic Piping-Cold Water from Risers to Fixtures 3,3 SF $,3 Domestic Piping-Cold Water Horizontal Lines 3,3 SF $, Domestic Piping-Cold Water Risers 3,3 SF $, Domestic Piping-Hot Water from Risers to Fixtures 3,3 SF $,9 Domestic Piping-Hot Water Horizontal Lines 3,3 SF $, Domestic Piping-Hot Water Return Lines 3,3 SF $, Domestic Piping-Hot Water Return Risers 3,3 SF $, Sanitary Piping 3,3 SF $, Storm Piping 3,3 SF $, Vent Piping 3,3 SF $,00 Pumps - Domestic Booster Pump-Simplex EA $, Pumps - Sump-Duplex EA $,3 Plumbing System Subtotal: $, Building: Main Category: Classrooms Computer Lab ( room) AC Units EA 3 $,3 Casework LF Ceiling - Plaster/Drywall 9 SF Chalk Board 30 LF $, Charging Station EA Doors - Wood Doors inclu hw EA Floor - Tile 9 SF $, Lighting - Pendent/Surface EA Storage/ Closet SF Walls - Plaster/Drywall,30 SF Wireless System EA ADDAMS Page of 3 Assessment Date: //0
6 Building: Main Category: Classrooms Library ( room) 00 S Avenue H Chicago, IL 0 AC Units EA 3 $,3 Ceiling - Plaster/Drywall 9 SF Doors - Wood Doors inclu hw EA Floor - Carpet 9 SF Lighting - Pendent/Surface EA Walls - Plaster/Drywall,03 SF Office ( room) AC Units EA 3 $,0 Ceiling - Plaster/Drywall SF Doors - Wood Doors inclu hw EA Floor - Tile SF $30 Lighting - Pendent/Surface EA Marker Board LF Storage/ Closet 9 SF Walls - Plaster/Drywall SF (0 rooms) AC Units 0 EA 3,3 Casework 0 LF Ceiling - Plaster/Drywall,390 SF $,0 Ceiling - Plaster/Drywall,0 SF Chalk Board LF $,3 Chalk Board LF Doors - Wood Doors inclu hw 0 EA Floor - Wood 9 SF $,900 Floor - Wood, SF Lighting - Pendent/Surface 0 EA Marker Board 0 LF Storage/ Closet 0 SF Walls - Metal Panel,03 SF Walls - Plaster/Drywall, SF $,0 Walls - Plaster/Drywall,3 SF Science ( room) AC Units EA 3 $,0 Casework LF Ceiling - Plaster/Drywall 9 SF Doors - Wood Doors inclu hw EA ADDAMS Page of 3 Assessment Date: //0
7 Building: Main Category: Classrooms Science ( room) 00 S Avenue H Chicago, IL 0 Floor - Terrazzo 9 SF Lighting - Pendent/Surface EA Marker Board 0 LF Walls - Plaster/Drywall,03 SF Work Sink EA $39 Special Program ( room) AC Units EA 3 $,0 Ceiling - Plaster/Drywall 33 SF Chalk Board LF $,3 Doors - Wood Doors inclu hw EA Floor - Wood 33 SF Lighting - Pendent/Surface EA Marker Board LF Walls - Plaster/Drywall SF $,9 Classrooms Subtotal: $, Building: Main Category: Rooms (Other Than Classrooms) Administrative Suites/Offices AC Unit EA 3 $,3 Ceiling - Lay-in SF Ceiling - Plaster/Drywall SF $,33 Ceiling - Plaster/Drywall 3 SF Doors - Steel Doors incl hw EA Doors - Wood Doors inclu hw EA Floor - Concrete 3 SF Floor - Tile SF $90 Floor - Tile SF Lighting - Metal Halide/Sodium Vapor EA Lighting - Pendent/Surface EA Power Distribution EA Storage/ Closet SF Walls - Plaster/Drywall 09 SF $3, Walls - Plaster/Drywall SF $,300 ADDAMS Page of 3 Assessment Date: //0
8 Building: Main Category: Rooms (Other Than Classrooms) Administrative Suites/Offices 00 S Avenue H Chicago, IL 0 Walls - Plaster/Drywall,000 SF Gymnasia Ceiling - Plaster/Drywall, SF Doors - Wood Doors inclu hw EA Floor - Wood, SF Lighting - Metal Halide/ High Pressure Sodium EA Sound System EA Stage 399 SF $,30 Stage Curtain EA Stage Lighting System EA Walls - Structural Glazed Tile,3 SF Mechanical/ Service Rooms Air Tunnel, SF $0, Boiler Room,33 SF $9,90 Crawl Space - Unfinished,30 SF $33, Janitor's Closet 0 SF $9 Mechanical/ Service Rooms 900 SF $, Storage Room 03 SF $,30 Storage Room 3 SF Vaults 0 SF Restroom Accessories, SF Ceiling - Plaster/Drywall 0 SF $,903 Ceiling - Plaster/Drywall SF Doors - Wood Doors inclu hw EA Floor - Tile Ceramic/ Porcelain, SF $,3 Floor Drain EA Hand Dryer 9 EA Lavatory EA Lighting - Metal Halide/Sodium Vapor EA Lighting - Pendent/Surface EA Partitions EA $, Partitions 9 EA Urinals EA Walls - Plaster/Drywall SF $3 Walls - Plaster/Drywall SF $9 ADDAMS Page of 3 Assessment Date: //0
9 Building: Main Category: Rooms (Other Than Classrooms) Restroom 00 S Avenue H Chicago, IL 0 Walls - Structural Glazed Tile 30 SF $,9 Walls - Structural Glazed Tile 0 SF Water Closet EA Rooms (Other Than Classrooms) Subtotal: $9,0 Building: Main Category: Building Interior Corridor Ceiling - Plaster/Drywall, SF $,90 Ceiling - Plaster/Drywall,3 SF Doors - Wood Doors include hw EA Drinking Fountains - Single Fountain EA Floor - Tile/Sheet,90 SF $,0 Lighting - Pendent/Surface EA Student Lockers 0 EA Student Lockers 3 EA Walls - Plaster/Drywall, SF Walls - Structural Glazed Tile, SF Safety Stairs Camera Viewing Station EA Security Cameras EA Ceiling - Plaster/Drywall 0 SF $,39 Ceiling - Plaster/Drywall 9 SF $,99 Floor - Terrazzo, SF Handrails LF Lighting - Pendent/Surface EA Stairs - Terrazzo 00 LF Walls - Plaster/Drywall,3 SF $,0 Building Interior Subtotal: $33,0 ADDAMS Page 9 of 3 Assessment Date: //0
10 00 S Avenue H Chicago, IL 0 Total Building Cost $,0,0 Building: Addition Category: Building Exterior Entrance Exterior Doors - Exterior Steel Door EA $,9 Foundation Lighting Roof System Walls Windows Foundation - Concrete 03 LF Superstructure - Concrete 3,99 SF Exterior Lighting - Wall Mounted EA Chimney - Metal Flue LF $3, Coping - Stone 03 LF $,0 Downspouts - Interior Downspouts 3 LF $,03 Parapet - " - 30" Height 03 LF Roof - Asphalt Gravel Ballast 3,99 SF $0,93 Roof Structure - Concrete 3,99 SF Exterior Walls - Brick 3,0 SF $0, Exterior Walls - Stone-Cast 03 SF $,3 Lintels - Steel LF Windows - Sash Aluminum Double-pane SF Building Exterior Subtotal: $, Building: Addition Category: Electrical System Emergency System Emergency Battery Packs - Corridors and Stairs EA $03 Emergency Battery Packs - Lunchrooms EA $ Exit Signs - Corridors and Stairs EA $0 Exit Signs - Lunchroom EA $99 ADDAMS Page 0 of 3 Assessment Date: //0
11 Building: Addition Category: Electrical System Power Distribution 00 S Avenue H Chicago, IL 0 Lighting and Power Panels - Above 00 A EA $9 Main Distribution Panels - Less than 0 amp EA $03 Electrical System Subtotal: $,0 Building: Addition Category: Safty System Fire Alarm Sprinkler System Fire Alarm Strobe Lights 3,99 SF $, Sprinkler Heads 3,99 SF Sprinkler Piping 3,99 SF $3 Wet Sprinkler System 3,99 SF $,09 Safty System Subtotal: $3,0 Building: Addition Category: Mechanical System Air Conditioning Air Handling Systems Boiler Systems Chiller-Air Cooled-Scroll Type-Roof Mounted - Less than 0 tons EA $3,9 Pipes - Chilled Water Pipe- Copper 00 LF $9 Air Handling Unit-Package Single Zone- Indoor- Hot Water and Chilled Water Coils - Less EA $3,30 than 00 cfm Air Intake EA $, Auxiliaries - Less than 00 cfm EA Boiler Auxiliary- on Condensing Hot Water Boiler MBH EA $99 Chemical Pot Feeder EA Combustion Dampers EA Glycol Feed System EA Hot Water Pump EA on Condensing- Cast Iron- Force Draft- Hot Water Boiler MBH EA $99 ADDAMS Page of 3 Assessment Date: //0
12 Building: Addition Category: Mechanical System Boiler Systems 00 S Avenue H Chicago, IL 0 Water Fill System EA Heating Devices Mechanical Plumbing Temperature Control Ventilation Cabinet Heaters - With Hot Water Coil EA $09 Chilled Water Pump - Less than 0 EA $, Hot Water Pump - Less than 0 EA $, Hydronic Supply and Return - Copper 0 LF $3, Pneumatic System 3,99 SF $,09 Thermostats - Pneumatic EA Exhaust Fans- Roof Mounted CFM EA $9 Exhaust Fans- Roof Mounted CFM EA $, Exhaust Fans- Roof Mounted CFM EA $9 Type I Exhaust Hood- Kitchen EA $, Mechanical System Subtotal: $, Building: Addition Category: Plumbing System Piping Domestic Piping-Cold Water Horizontal Lines 3,99 SF $9 Domestic Piping-Hot Water Horizontal Lines 3,99 SF $3 Domestic Piping-Hot Water Return Lines 3,99 SF $ Sanitary Piping 3,99 SF $3,3 Storm Piping 3,99 SF $3,3 Vent Piping 3,99 SF $, Plumbing System Subtotal: $,00 Building: Addition Category: Rooms (Other Than Classrooms) ADDAMS Page of 3 Assessment Date: //0
13 Building: Addition Category: Rooms (Other Than Classrooms) Administrative Suites/Offices 00 S Avenue H Chicago, IL 0 Ceiling - Plaster/Drywall SF Doors - Steel Doors incl hw EA Floor - Tile SF Lighting - Lay-in EA Power Distribution EA Walls - Concrete Block SF Kitchen Ceiling - Lay-in SF Doors - Steel Doors incl hw EA Floor - Tile SF $, Lighting - Lay-in EA Walls - Concrete Block,09 SF Lunch & Multipurpose Room Mechanical/ Service Rooms Ceiling - Lay-in,0 SF Doors - Steel Doors incl hw 3 EA Floor - Tile,0 SF Lighting - Lay-in EA Market Board LF Serving Line LF Walls - Concrete Block,3 SF Walls - Metal Panel SF Boiler Room 0 SF Storage Room 9 SF Restroom Accessories 9 SF Ceiling - Plaster/Drywall 9 SF Doors - Steel Doors incl hw EA Floor - Tile SF Floor - Tile Ceramic/ Porcelain SF $0 Floor Drain EA Hand Dryer EA Lavatory EA Lighting - Pendent/Surface EA Student Lockers EA ADDAMS Page 3 of 3 Assessment Date: //0
14 Building: Addition Category: Rooms (Other Than Classrooms) Restroom 00 S Avenue H Chicago, IL 0 Walls - Concrete Block 0 SF Walls - Structural Glazed Tile 3 SF Water Closet EA Rooms (Other Than Classrooms) Subtotal: $,3 Building: Addition Category: Building Interior Corridor Ceiling - Lay-in SF Doors - Steel Doors incl hw EA Floor - Tile/Sheet SF Lighting - Lay-in EA Stairs - Terrazzo LF Walls - Structural Glazed Tile, SF Safety Camera Viewing Station EA Security Cameras EA Building Interior Subtotal: Total Building Cost $,3 Building: Annex Category: Building Exterior Entrance Entrance Control - Audio EA Exterior Doors - Exterior FRP Door 3 EA $,9 Exterior Doors - Exterior Steel Door 3 EA $, Exterior Doors - Transom Lite EA $ Foundation Foundation - Concrete LF Superstructure - Steel 3,3 SF ADDAMS Page of 3 Assessment Date: //0
15 Building: Annex Category: Building Exterior Foundation 00 S Avenue H Chicago, IL 0 Lighting Roof System Walls Windows Exterior Lighting - Wall Mounted EA $ Exterior Lighting - Wall Mounted EA $, Chimney - Metal Flue 3 LF Coping - Metal 0 LF Downspouts - Exterior Downspouts 0 LF $,99 Downspouts - Interior Downspouts LF $3 Roof - Metal SF $,3 Roof - Metal,000 SF Roof - Modified Bitumen SF $,09 Roof Structure - Steel / Metal Deck/ Concrete Topping 3,0 SF Canopy - Metal SF $ Cornice - Metal Projecting 9 LF Exterior Walls - Brick, SF Curtain wall - Louver 00 SF Guard - Guards perforated, SF $9, Lintels - Steel LF $,0 Windows - Sash Aluminum Double-pane, SF $,9 Building Exterior Subtotal: $,0 Building: Annex Category: Electrical System Emergency System Automatic Transfer Switch EA $ Emergency A/C Power - Corridors and Stairs,0 SF Emergency A/C Power - Students Toilets,3 SF $ Exit Signs - Corridors and Stairs EA $, Main Service Independent Electrical Service for emergency power EA $,9 ADDAMS Page of 3 Assessment Date: //0
16 Building: Annex Category: Electrical System Main Service 00 S Avenue H Chicago, IL 0 Main Electrical Service - 00 A and 0/0/3PH EA $3,0 Power Distribution Lighting and Power Panels - 00 A EA $,9 Lighting and Power Panels - Above 00 A 3 EA $,9 Main Distribution Panels amp EA $ Electrical System Subtotal: $,3 Building: Annex Category: Safty System Fire Alarm Fire Alarm Panel EA $, Fire Alarm Strobe Lights 3,3 SF $,99 Sprinkler System Sprinkler Heads 3,3 SF Sprinkler Piping 3,3 SF $,3 Wet Sprinkler System 3,3 SF $3,33 Safty System Subtotal: $,93 Building: Annex Category: Mechanical System Air Handling Systems Air Handling Unit-Package Single Zone- Indoor- Hot Water Coils - Less than 00 cfm EA $3,30 Air Intake EA $, Auxiliaries - Less than 00 cfm EA Boiler Systems Boiler Auxiliary- on Condensing Hot Water MBH EA $,093 Chemical Pot Feeder EA $ Combustion Dampers EA $ Glycol Feed System EA $39 on Condensing- Water Tube- Flexible Tube- Force Draft- Hot Water Boiler - Less than 00 MBH EA $,99 ADDAMS Page of 3 Assessment Date: //0
17 Building: Annex Category: Mechanical System Boiler Systems 00 S Avenue H Chicago, IL 0 Heating Devices Mechanical Plumbing Cabinet Heaters - With Hot Water Coil EA $, Unit Heater - Hot Water EA $ Hot Water Pump - Less than 0 EA $, Hydronic Supply and Return - Copper 0 LF $3, Unit Ventilation Unit Ventilators- Floor Mounted- Hot Water w/ DX Cooling Coil & w/ Self Contained Compressors 0 EA $, Ventilation Exhaust Fans- Roof Mounted CFM EA $9 Exhaust Fans- Roof Mounted CFM EA $, Mechanical System Subtotal: $9,09 Building: Annex Category: Plumbing System Hot Water Gas Heater - Less than 0000 BTU/HR EA $30 Piping Domestic Piping-Cold Water Horizontal Lines 3,3 SF $3,9 Domestic Piping-Hot Water Horizontal Lines 3,3 SF $,3 Domestic Piping-Hot Water Return Lines 3,3 SF $,9 Sanitary Piping 3,3 SF $,0 Storm Piping 3,3 SF $, Vent Piping 3,3 SF $,33 Plumbing System Subtotal: $, Building: Annex Category: Classrooms ADDAMS Page of 3 Assessment Date: //0
18 Building: Annex Category: Classrooms Music Room ( room) 00 S Avenue H Chicago, IL 0 Casework 3 LF $,0 Ceiling - Lay-in 0 SF $,3 Doors - Steel Doors incl hw EA $30 Floor - Tile/Sheet 0 SF $ Lighting - Lay-in 9 EA $,0 Marker Board LF $33 Walls - Concrete Block 3 SF $,0 Walls - Plaster/Drywall 3 SF $, Office ( room) Casework 3 LF $,0 Ceiling - Lay-in 0 SF $,3 Doors - Steel Doors incl hw EA $30 Floor - Tile/Sheet 0 SF $ Lighting - Lay-in 9 EA $,0 Marker Board LF $33 Walls - Concrete Block SF $,3 Walls - Plaster/Drywall 9 SF $ ( rooms) Casework LF $, Ceiling - Lay-in, SF $,9 Doors - Steel Doors incl hw EA $,0 Floor - Tile/Sheet, SF $,3 Lighting - Lay-in EA $, Marker Board LF $3,9 Walls - Concrete Block,00 SF $,3 Walls - Plaster/Drywall 3,0 SF $,3 Classrooms Subtotal: $,00 Building: Annex Category: Rooms (Other Than Classrooms) Administrative Suites/Offices Ceiling - Plaster/Drywall 3 SF $ Doors - Steel Doors incl hw EA $30 Floor - Tile/Sheet 3 SF $3 ADDAMS Page of 3 Assessment Date: //0
19 Building: Annex Category: Rooms (Other Than Classrooms) Administrative Suites/Offices 00 S Avenue H Chicago, IL 0 Lighting - Lay-in EA $3 Power Distribution EA $,9 Walls - Concrete Block 3 SF $ Walls - Plaster/Drywall 3 SF $ MDF_IDF Doors - Steel Doors incl hw EA $30 Finishes 3 SF $9 Ventilation and Cooling EA $, Mechanical/ Service Rooms Janitor's Closet 30 SF $ Mechanical/ Service Rooms SF $3,9 Storage Room SF $ Restroom Accessories, SF $0,0 Ceiling - Plaster/Drywall, SF $,0 Doors - Steel Doors incl hw EA $30 Floor - Concrete Epoxy/ Painted,3 SF $99 Floor - Tile/Sheet SF $ Floor Drain EA $,9 Hand Dryer EA $90 Lavatory EA $,3 Lighting - Lay-in EA $,309 Partitions 0 EA $,99 Urinals EA $,0 Walls - Concrete Block 3,3 SF $9, Water Closet EA $3,9 Rooms (Other Than Classrooms) Subtotal: $,33 Building: Annex Category: Building Interior Corridor Ceiling - Lay-in,0 SF $,0 Doors - Steel Doors incl hw EA $, ADDAMS Page 9 of 3 Assessment Date: //0
20 Building: Annex Category: Building Interior Corridor 00 S Avenue H Chicago, IL 0 Drinking Fountains - Double Fountain EA $33 Floor - Tile Ceramic/ Porcelain 3 SF $,3 Floor - Tile/Sheet,3 SF $ Lighting - Lay-in EA $,9 Walls - Concrete Block,0 SF $,03 Safety Security Cameras 3 EA $ Security Cameras EA Building Interior Subtotal: $, Total Building Cost $3, Building: Leased Category: Electrical System Emergency System Exit Signs - Corridors and Stairs EA Exit Signs - Multipurpose Room 3 EA Power Distribution Lighting and Power Panels - 00 A EA Electrical System Subtotal: Building: Leased Category: Safty System Fire Alarm Fire Alarm Strobe Lights 3,00 SF Safty System Subtotal: Building: Leased Category: Mechanical System ADDAMS Page 0 of 3 Assessment Date: //0
21 00 S Avenue H Chicago, IL 0 Heating Devices Under Floor Heating- Hot Water SF Mechanical System Subtotal: Building: Leased Category: Classrooms Pre School ( rooms) AC Units EA 3 $,3 Casework LF $ Ceiling - Splined,0 SF $,3 Doors - Wood Doors inclu hw EA $,0 Floor - Tile/Sheet,0 SF $, Lighting - Pendent/Surface EA $, Walls - Concrete Block, SF $,39 Classrooms Subtotal: $3,30 Building: Leased Category: Rooms (Other Than Classrooms) Lunch & Multipurpose Room Ceiling - Splined, SF $,9 Doors - Wood Doors inclu hw EA Floor - Tile/Sheet, SF $, Lighting - Pendent/Surface EA $9,3 Walls - Concrete Block, SF $3,3 Walls - Plaster/Drywall, SF $3, Restroom Accessories SF $3 Ceiling - Splined SF $0 Doors - Wood Doors inclu hw EA $30 Floor - Tile/Sheet SF $ Lavatory EA $30 Lighting - Wall Mounted EA $ Walls - Structural Glazed Tile 9 SF $00 Water Closet EA $,3 ADDAMS Page of 3 Assessment Date: //0
22 Building: Leased Category: Rooms (Other Than Classrooms) 00 S Avenue H Chicago, IL 0 Rooms (Other Than Classrooms) Subtotal: $,939 Building: Leased Category: Building Interior Vertical Conveyance Wheelchair Lift - Platform Lift EA $,90 Building Interior Subtotal: $,90 Total Building Cost $,99 Building: Modular Category: Building Exterior Entrance Exterior Doors - Exterior Steel Door 3 EA $, Exterior Stairs - Wood 90 LF $3 Ramp Handrail - Steel_Ramp Handrail LF $3, Ramp Handrail - Steel_Ramp Handrail LF $3 Ramps - Wood Ramp LF $,3 Stair Handrail - Steel_Stair Handrail LF $ Foundation Lighting Roof System Walls Superstructure - Steel,9 SF Exterior Lighting - Wall Mounted EA $ Exterior Lighting - Wall Mounted 3 EA $ Downspouts - Exterior Downspouts LF $9 Roof - Metal,3 SF $,0 Roof Structure - Steel / Metal Deck/ Concrete Topping,9 SF Exterior Walls - Precast Panel Wall,30 SF $, ADDAMS Page of 3 Assessment Date: //0
23 Building: Modular Category: Building Exterior Windows 00 S Avenue H Chicago, IL 0 Guard - Guards perforated SF $3 Windows - Casement Aluminum SF $3 Building Exterior Subtotal: $9,3 Building: Modular Category: Electrical System Emergency System Emergency A/C Power - Corridors and Stairs 9 SF $3 Emergency Battery Packs - Corridors and Stairs 3 EA Exit Signs - Corridors and Stairs EA $9 Power Distribution Lighting and Power Panels - 00 A EA $9 Electrical System Subtotal: $,990 Building: Modular Category: Safty System Sprinkler System Sprinkler Heads,9 SF Sprinkler Piping,9 SF $33 Wet Sprinkler System,9 SF $ Safty System Subtotal: $9 Building: Modular Category: Mechanical System Unit Ventilation Unit Ventilators- Floor Mounted- Electric Heating & DX Cooling Coil W/ Self Contained Compressor EA $,9 ADDAMS Page 3 of 3 Assessment Date: //0
24 Building: Modular Category: Mechanical System 00 S Avenue H Chicago, IL 0 Mechanical System Subtotal: $,9 Building: Modular Category: Plumbing System Hot Water Electric Heater - Less than 0 KW EA $ Piping Domestic Piping-Cold Water Horizontal Lines,9 SF $3 Domestic Piping-Hot Water Horizontal Lines,9 SF $33 Domestic Piping-Hot Water Return Lines,9 SF $ Sanitary Piping,9 SF $, Storm Piping,9 SF $, Vent Piping,9 SF $,9 Plumbing System Subtotal: $,0 Building: Modular Category: Classrooms Kindergarten ( rooms) Casework LF $ Ceiling - Lay-in, SF $3, Chalk Board LF $,3 Doors - Steel Doors incl hw EA Doors - Wood Doors inclu hw EA Floor - Tile Quarry SF $,33 Floor - Tile/Sheet SF $ Lighting - Pendent/Surface EA $,9 Marker Board LF $9 Walls - Metal Panel,3 SF $,99 Classrooms Subtotal: $39,09 Building: Modular Category: Rooms (Other Than Classrooms) ADDAMS Page of 3 Assessment Date: //0
25 00 S Avenue H Chicago, IL 0 Restroom Accessories 90 SF $30 Ceiling - Lay-in 90 SF $0 Doors - Wood Doors inclu hw EA Floor - Tile/Sheet 90 SF $90 Floor Drain EA $, Lavatory EA $39 Lighting - Pendent/Surface EA $ Walls - Metal Panel SF $3,3 Water Closet EA $ Rooms (Other Than Classrooms) Subtotal: $, Building: Modular Category: Building Interior Corridor Ceiling - Lay-in 9 SF $3 Drinking Fountains - Double Fountain EA $33 Floor - Tile/Sheet 9 SF $ Lighting - Pendent/Surface EA $ Walls - Metal Panel 30 SF $3,0 Building Interior Subtotal: $,09 Total Building Cost $,3 Building: Modular Category: Building Exterior Entrance Exterior Doors - Exterior Steel Door 3 EA $, Exterior Stairs - Wood 0 LF $3 Stair Handrail - Steel_Stair Handrail 0 LF $30 Foundation Lighting Superstructure - Steel,9 SF Exterior Lighting - Wall Mounted EA $ ADDAMS Page of 3 Assessment Date: //0
26 Building: Modular Category: Building Exterior Lighting 00 S Avenue H Chicago, IL 0 Exterior Lighting - Wall Mounted EA $, Roof System Walls Windows Downspouts - Exterior Downspouts LF $9 Roof - EPDM/ Synthetic Rubber,3 SF $,0 Roof Structure - Steel / Metal Deck/ Concrete Topping,9 SF Exterior Walls - Precast Panel Wall,30 SF $, Guard - Guards perforated 0 SF $,3 Windows - Sash Aluminum Double-pane 0 SF $9 Building Exterior Subtotal: $, Building: Modular Category: Electrical System Emergency System Emergency Battery Packs - Corridors and Stairs 3 EA Exit Signs - Corridors and Stairs EA $9 Power Distribution Lighting and Power Panels - 00 A EA $9 Electrical System Subtotal: $,9 Building: Modular Category: Safty System Sprinkler System Sprinkler Heads,9 SF Sprinkler Piping,9 SF $33 Wet Sprinkler System,9 SF $ Safty System Subtotal: $9 ADDAMS Page of 3 Assessment Date: //0
27 Building: Modular Category: Mechanical System Unit Ventilation 00 S Avenue H Chicago, IL 0 Unit Ventilators- Floor Mounted- Electric Heating & DX Cooling Coil W/ Self Contained Compressor EA $,9 Mechanical System Subtotal: $,9 Building: Modular Category: Plumbing System Hot Water Electric Heater - Less than 0 KW EA $ Piping Domestic Piping-Cold Water Horizontal Lines,9 SF $3 Domestic Piping-Hot Water Horizontal Lines,9 SF $33 Domestic Piping-Hot Water Return Lines,9 SF $ Sanitary Piping,9 SF $, Storm Piping,9 SF $, Vent Piping,9 SF $,9 Plumbing System Subtotal: $,0 Building: Modular Category: Classrooms Kindergarten ( room) Special Education ( room) Casework LF $0 Ceiling - Lay-in 0 SF $, Doors - Steel Doors incl hw EA $30 Doors - Wood Doors inclu hw EA $30 Floor - Tile/Sheet 0 SF $ Lighting - Lay-in EA $, Marker Board 0 LF $ Storage/ Closet SF $3 Walls - Metal Panel 0 SF $,3 Casework LF $0 ADDAMS Page of 3 Assessment Date: //0
28 Building: Modular Category: Classrooms Special Education ( room) 00 S Avenue H Chicago, IL 0 Ceiling - Lay-in 0 SF $, Doors - Steel Doors incl hw EA $30 Doors - Wood Doors inclu hw EA $30 Floor - Tile/Sheet 0 SF $ Lighting - Lay-in EA $, Marker Board LF $ Storage/ Closet SF $3 Walls - Metal Panel 0 SF $,3 Classrooms Subtotal: $, Building: Modular Category: Rooms (Other Than Classrooms) Restroom Accessories 90 SF $30 Ceiling - Lay-in 90 SF $0 Doors - Wood Doors inclu hw EA Floor - Tile/Sheet 90 SF $90 Floor Drain EA $, Lavatory EA $39 Lighting - Pendent/Surface EA $ Walls - Metal Panel SF $3,3 Water Closet EA $ Rooms (Other Than Classrooms) Subtotal: $, Building: Modular Category: Building Interior Corridor Ceiling - Lay-in 9 SF $3 Drinking Fountains - Double Fountain EA $33 Floor - Tile/Sheet 9 SF $ Lighting - Lay-in EA $9 Walls - Metal Panel SF $3,03 ADDAMS Page of 3 Assessment Date: //0
29 Building: Modular Category: Building Interior 00 S Avenue H Chicago, IL 0 Building Interior Subtotal: $3,900 Total Building Cost $,0 Building: Modular 3 Category: Building Exterior Entrance Exterior Doors - Exterior Steel Door EA $,9 Foundation Lighting Roof System Walls Windows Foundation - Masonry LF Superstructure - Steel 9, SF Exterior Lighting - Wall Mounted EA $,00 Exterior Lighting - Wall Mounted EA $,30 Downspouts - Exterior Downspouts 9 LF $3,90 Roof - PVC Membrane 9, SF $,33 Roof Structure - Steel / Metal Deck/ Concrete Topping 9, SF Exterior Walls - Precast Panel Wall 0 SF $ Exterior Walls - Precast Panel Wall,0 SF $33,9 Guard - Guards perforated SF $3,0 Windows - Sash Aluminum Double-pane SF $,9 Building Exterior Subtotal: $9,0 Building: Modular 3 Category: Electrical System Emergency System Emergency A/C Power - Corridors and Stairs SF $0 Emergency Battery Packs - Corridors and Stairs EA $,3 ADDAMS Page 9 of 3 Assessment Date: //0
30 Building: Modular 3 Category: Electrical System Emergency System 00 S Avenue H Chicago, IL 0 Exit Signs - Corridors and Stairs 0 EA $,9 Power Distribution Lighting and Power Panels - 00 A EA $,393 Electrical System Subtotal: $,93 Building: Modular 3 Category: Safty System Sprinkler System Sprinkler Heads 9,9 SF Sprinkler Piping 9,9 SF $, Wet Sprinkler System 9,9 SF $,9 Safty System Subtotal: $, Building: Modular 3 Category: Mechanical System Unit Ventilation Unit Ventilators- Floor Mounted- Electric Heating & DX Cooling Coil W/ Self Contained Compressor EA $9,9 Mechanical System Subtotal: $9,9 Building: Modular 3 Category: Plumbing System Hot Water Electric Heater - Less than 0 KW EA $,3 Piping Domestic Piping-Cold Water Horizontal Lines 9, SF $,39 Domestic Piping-Hot Water Horizontal Lines 9, SF $,9 Domestic Piping-Hot Water Return Lines 9, SF $, Sanitary Piping 9, SF $9,00 ADDAMS Page 30 of 3 Assessment Date: //0
31 Building: Modular 3 Category: Plumbing System Piping 00 S Avenue H Chicago, IL 0 Storm Piping 9, SF $,3 Vent Piping 9, SF $,3 Plumbing System Subtotal: $3,9 Building: Modular 3 Category: Classrooms ( rooms) Casework 0 LF $,00 Ceiling - Lay-in, SF $, Chalk Board 0 LF $,0 Doors - Wood Doors inclu hw EA $, Floor - Tile/Sheet, SF $, Lighting - Lay-in EA $,9 Marker Board LF $,99 Storage/ Closet SF $, Walls - Metal Panel 9, SF $9, Classrooms Subtotal: $3,0 Building: Modular 3 Category: Rooms (Other Than Classrooms) Mechanical/ Service Rooms Mechanical/ Service Rooms 90 SF $ Restroom Accessories SF $, Ceiling - Lay-in SF $,99 Doors - Wood Doors inclu hw EA $,0 Floor - Tile/Sheet SF $ Floor Drain EA $,3 Hand Dryer EA $90 Lavatory EA $,3 Lighting - Pendent/Surface EA $3 Partitions EA $3,3 ADDAMS Page 3 of 3 Assessment Date: //0
32 Building: Modular 3 Category: Rooms (Other Than Classrooms) Restroom 00 S Avenue H Chicago, IL 0 Urinals EA $,3 Walls - Metal Panel, SF $3, Water Closet EA $,03 Rooms (Other Than Classrooms) Subtotal: $,3 Building: Modular 3 Category: Building Interior Corridor Ceiling - Lay-in SF $,0 Doors - Steel Doors incl hw EA $,0 Drinking Fountains - Double Fountain EA $ Floor - Tile/Sheet SF $3 Lighting - Lay-in EA $, Walls - Metal Panel,3 SF $, Safety Security Cameras EA $9 Building Interior Subtotal: $,3 Total Building Cost $33, SITE Category: Site Athletic Civil/Drainage Lighting EA $, Lighting EA $9,9 Surface - Asphalt,0 SF $39,030 Surface - atural 39, SF $3, Civil/ Drainage - Catch Basin EA Civil/ Drainage - Site Drain EA $30 Civil/ Drainage - Site Manhole EA ADDAMS Page 3 of 3 Assessment Date: //0
33 00 S Avenue H Chicago, IL 0 SITE Category: Site Civil/Drainage Fencing Landscape Parking Lot Playground Sidewalks Signage Fencing - Chain Link 30 LF $,90 Fencing - Chain Link LF $ Fencing - ew Standard Ornamental LF Fencing - ew Standard Ornamental 3,0 LF $0,3 Benches EA $,0 Irrigation 00,9 SF Landscape - Grass 0,3 SF $99, Landscape - Hardscape- Concrete, SF $, Parkway trees EA Planting Beds/ Area,09 SF $9,9 Play Area - Asphalt/ Hardscape 3,9 SF $0,9 Retaining Wall - Concrete 0 SF $3 Retaining Wall - Concrete,9 SF $,93 Retaining Wall - Masonry SF $,0 Trash Receptacles EA $,9 Lighting - Pole Mounted EA $, Surface - Asphalt 00 SF $,00 Surface - Asphalt, SF $, Trash Enclosure - Chain Links 0 SF $, Vehicular Screening 0 LF $,0 Equipment - Combo 3- EA $,09 Surface - Square Rubber Mats, SF $39,9 Sidewalks - Internal Walks 9 LF $0,9 Sidewalks - Perimeter Sidewalks 0 SF $,33 Sidewalks - Perimeter Sidewalks 0, SF $,00 Flag Pole - Flag Pole EA $, Marquee - Free Standing Back lighted w/ LED EA ADDAMS Page 33 of 3 Assessment Date: //0
34 SITE Category: Site 00 S Avenue H Chicago, IL 0 Site Subtotal: $,03 Total Site Cost $,03 Campus Total ² ³ $3,0,39 ¹ It is very rare for assessors to find a feature in this condition. If assessors do, they are required to report it immediately to CPS, and CPS addresses it immediately. Thus, no features will be ranked in this report; by the time the report is compiled, they have been resolved. ² As stated above, Total Assessed Campus eed does not include the addition of features not already in a particular facility, such as programmatic improvements, school-wide ADA compliance, air conditioning, space reconfiguration or construction to alleviate overcrowding; these items are treated as separate capital needs. The Total Assessed Campus eed includes current deficiencies and is based on current unit cost estimates; it does not reflect a complete project cost. ³ The overall condition of different items can change after an assessment date due to many variables, including newly occurring deficiencies, renovation or repairs and cost changes. These dollar figures in this report are estimates only and are based solely on the data that was collected as of the assessment date in the footer below. Definitions Quantity means, for each item, the total number (or amount) of that item that exists and was evaluated. Unit means the generally accepted standard unit of measure for each item. Some items, like doors, are measured individually and use the unit of measurement EA for each. Other items, like chimneys, are measured in terms of linear feet ( LF ). Still other items, like flooring, are generally measured in square feet ( SF ). Cost means a basic estimate for each item needing some level of repair or replacement. Cost does not include all expenses that would be necessary to complete a repair or replacement project. This is because, depending on the item and on the overall scope of a construction project, repair/replacement projects can include additional costs such as destructive testing, environmental needs, discovered conditions, and additional work triggered by building codes. For the same reason, the Total Campus eed listed at the end of this report reflects only a portion of what it would actually cost to repair/replace all of the listed features. Campus Total also does not reflect features that do not yet exist at a particular facility, such as: programmatic improvements, school-wide ADA compliance, air conditioning, space reconfiguration, or construction to alleviate overcrowding; these are viewed as separate capital needs. ADDAMS Page 3 of 3 Assessment Date: //0
35 00 S Avenue H Chicago, IL 0 Classroom Summary Current Usage Intended Usage Room Location Room umber Floor Plan Room umber Area (SF) Voice Outlets Data Outlets Elect. Outlets Glazed Window Area Operable Window Area oise Level Window Stop Power Strip Smart- Board Main Computer Lab Library Office Science Special Program Special Education Office nd Floor nd Floor nd Floor st Floor st Floor st Floor st Floor st Floor nd Floor nd Floor nd Floor nd Floor nd Floor nd Floor st Floor Annex Music Room Office st Floor st Floor st Floor st Floor st Floor st Floor st Floor st Floor st Floor A Leased Pre School Pre School Pre School Pre School st Floor st Floor 3 9 Modular Kindergarten Kindergarten Kindergarten Kindergarten st Floor st Floor 0 0 Modular Kindergarten Kindergarten st Floor ADDAMS Page 3 of 3 Assessment Date: //0
36 00 S Avenue H Chicago, IL 0 Classroom Summary Current Usage Intended Usage Room Location Room umber Floor Plan Room umber Area (SF) Voice Outlets Data Outlets Elect. Outlets Glazed Window Area Operable Window Area oise Level Window Stop Power Strip Smart- Board Modular Special Education st Floor Modular 3 st Floor st Floor st Floor st Floor st Floor st Floor st Floor st Floor ADDAMS Page 3 of 3 Assessment Date: //0
Amos Alonzo Stagg Elementary School 7424 S Morgan St Chicago, IL 60621
2 S Morgan St Chicago, IL 21 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationJames E McDade Elementary Classical School 8801 S Indiana Ave Chicago, IL 60619
880 S Indiana Ave Chicago, IL 09 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationCharles H Wacker Elementary School 9746 S Morgan St Chicago, IL 60643
9 S Morgan St Chicago, IL 03 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationJohn T Pirie Fine Arts & Academic Center ES 650 E 85th St Chicago, IL 60619
E 8th St Chicago, IL 19 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationStephen Decatur Classical Elementary School 7030 N Sacramento Ave Chicago, IL 60645
030 Sacramento Ave Chicago, IL 04 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationHenry R Clissold Elementary School 2350 W 110th Pl Chicago, IL 60643
30 W 0th Pl Chicago, IL 03 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationPerkins Bass Elementary School 1140 W 66th St Chicago, IL 60621
0 W th St Chicago, IL 02 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationCharles H Wacker Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationFrederic Chopin Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationHarold Washington Elementary School 9130 S University Ave Chicago, IL 60619
930 S University Ave Chicago, IL 09 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This
More informationMinnie Mars Jamieson Elementary School 5650 N Mozart St Chicago, IL 60659
Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will roll-up each assessed item
More informationGeorge Armstrong International Studies ES 2110 W Greenleaf Ave Chicago, IL 60645
W Greenleaf Ave Chicago, IL Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationJames B Farnsworth Elementary School 5414 N Linder Ave Chicago, IL 60630
Linder Ave Chicago, IL 030 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationDonald Morrill Math & Science Elementary School 6011 S Rockwell St Chicago, IL 60629
0 S Rockwell St Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationJohn D Shoop Math-Science Technical Academy ES S Bishop St Chicago, IL 60643
S Bishop St Chicago, IL 03 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will
More informationInter-American Elementary Magnet School 851 W Waveland Ave Chicago, IL 60613
8 W Waveland Ave Chicago, IL 03 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationWalter S Christopher Elementary School 5042 S Artesian Ave Chicago, IL 60632
42 S Artesian Ave Chicago, IL 2 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report
More informationLouis A Agassiz Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationVelma F Thomas Early Childhood Center
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationEdgar Allan Poe Elementary Classical School S Langley Ave Chicago, IL 60628
Facility Assessment Report This report contains the detailed findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility item by visual observation
More informationJames B Farnsworth Elementary School 5414 N Linder Ave Chicago, IL 60630
544 Linder Ave Chicago, IL 60630 Facility Assessment Report This report contains the detailed findings of a facility assessment completed on the date noted in the document footer below. Assessors rate
More informationThomas J Higgins Elementary Community Academy S Morgan St Chicago, IL 60643
Facility Assessment Report Thomas J Higgins Elementary Community Academy This report contains the detailed findings of a facility assessment completed on the date noted in the document footer below. Assessors
More informationHorace Greeley Elementary School 832 W Sheridan Rd Chicago, IL 60613
832 W Sheridan Rd Chicago, IL 3 Facility Assessment Report This report contains the detailed findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each
More informationEugene Field Elementary School 7019 N Ashland Ave Chicago, IL 60626
79 Ashland Ave Chicago, IL 6626 Facility Assessment Report This report contains the detailed findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each
More informationWalter Q Gresham Elementary School
Facility Assessment Detail This report contains the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationPaul Laurence Dunbar Career Academy High School 3000 S King Dr Chicago, IL 60616
Facility Assessment Report This report contains the detailed findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility item by visual observation
More informationOle A Thorp Elementary Scholastic Academy 6024 W Warwick Ave Chicago, IL 60634
Facility Assessment Report This report contains the detailed findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility item by visual observation
More informationFACILITY COMPONENTS - ELEMENTARY SCHOOL
SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Two stalls fewer than minimum standard. Parking and Access - Service / Delivery 2.0 1.0 0.16 Parking and Access - Staff 1.0 3.0 0.24 Thirty-seven stalls
More informationAppendix J - Custom Uniformat for EDU Migration
Appendix J - Custom Uniformat for EDU Migration Nr. MTC Uniformat for VFA.facility Life (Years) Weight (1-100) Out of Scope Cost Y/N 1 A Substructure 150 N 2 A10 Foundations 150 N 3 A1010 Standard Foundations
More informationFACILITY COMPONENTS - ELEMENTARY SCHOOL
SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Five fewer bus stalls than minimum standard. Parking and Access - Service / Delivery 1.0 1.0 0.08 No delivery parking adjacent to delivery entrance. Parking
More informationDeficiency ID Qty UoM Priority. K Play Area Requires Impact Resistant Material Ea. 2
School and Site Level Deficiencies Site K Play Area Requires Impact Resistant Material 1320 1 Ea. 2 Exterior Basketball Goals Are Damaged And Require Replacement 1322 1 Ea. 4 Bus drop-off area does not
More informationFACILITY COMPONENTS - MIDDLE SCHOOL
SITE AREAS Parking and Access - Buses 2.0 2.0 0.30 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 1.0 3.0 0.22 Four fewer stalls
More informationDeficiency ID Qty UoM Priority. Concrete Walks Are Damaged And Require Replacement ,000 SF 3
School and Site Level Deficiencies Site Concrete Walks Are Damaged And Require Replacement 5539 4,000 SF 3 Bus drop-off area does not have a canopy. 14005 250 LF 5 Paved Play Requires Recoating And Resurfacing
More informationTimberglen Recreation Center Summary
Timberglen Recreation Center Summary Address Building Purpose 3810 Timberglen Road Dallas, TX 75287 Recreation Center Original Year of Construction 2003 Building Area 15,000 SF Inspection Date August 2,
More informationCOOLIDGE SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1940 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1240 ENROLLMENT 2008 652 WARD 4 PROPOSED PROGRAM CAPACITY 1100 Site Plan COOLIDGE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationFacilities Feasibility Study Frederick Douglass HS Condition Assessment
Summary of Findings The Frederick Douglass HS Facility located at 2301 Gwynns Falls Parkway in Baltimore, Maryland, was built in 1927. It comprises 194,249 gross square feet. The total current deficiencies
More informationSimcoe County District School Board. 5yr Condition Assessment 2006/07 to 2010/11. Hillcrest PS (Barrie), 9205
5yr Condition Assessment 2006/07 to 2010/11 Construction Year Area 1951 3,813 Page 1 of 25 1. Architectural / Structural & Site Exec Summary Hillcrest Public School is a two storey structure of masonry
More informationFacilities Feasibility Study Laurence G. Paquin Building Condition Assessment
Summary of Findings The Laurence G. Paquin Building Facility located at 2200 SINCLAIR LANE in Baltimore, Maryland, was built in 1975. It comprises 65,666 gross square feet. The total current deficiencies
More informationPOWELL ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1925 BUILDING AREA 38,500 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 319 WARD 4 PROPOSED PROGRAM CAPACITY 325 Site Plan POWELL - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-3
More informationPROGRAM COST MODEL. for. PEER Tall Buildings Study Concrete Structural Option Los Angeles, California
PROGRAM COST MODEL for PEER Tall Buildings Study Concrete Structural Option Los Angeles, California March 8, 2010 PEER Tall Buildings Study Concrete Structural Option March 8, 2010 CONTENTS Page Nos. Overall
More informationRAYMOND EDUCATION CAMPUS
INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationHarry Stone Recreation Center Summary
Harry Stone Recreation Center Summary Address Building Purpose 2400 Millmar Drive Dallas, TX 75228 Recreation Center Original Year of Construction 1957 (Expansion 2013) Building Area 22,281 SF Inspection
More informationLASALLE - BACKUS EDUCATION CAMPUS
INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationCM ASSIGNMENT OF TEMPORARY FACILITIES see included IU Project Site Requirements
SECTION A CM INSTRUCTIONS TO BIDDERS SECTION B BID CATEGORY DESCRIPTIONS & BID FORMS BC-07: Building HVAC and Plumbing BC-08: Building Electric BC-09: General Trades BC-10: Masonry BC-11: Precast Structural
More informationLake Highlands North Recreation Center Summary
Lake Highlands North Recreation Center Summary Address Building Purpose 9940 White Rock Trail Dallas, TX 75238 Recreation Center Original Year of Construction 1971 Building Area 33,036 SF Inspection Date
More informationFacilities Feasibility Study Matthew A. Henson ES Condition Assessment
Summary of Findings The Matthew A. Henson ES Facility located at 1600 N. Payson Street in Baltimore, Maryland, was built in 1964. It comprises 75,228 gross square feet. The total current deficiencies for
More informationSEATON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More information3. 21st Century Learning A. Districtwide Flexible Learning $600,000 Subtotal $600,000
1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades $300,000 C. Tilden Entrance Upgrades $50,000 D. Door and Glass Improvements $500,000 E. Alert Systems $800,000
More informationHILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School
HILLSIDE ELEMENTARY SCHOOL Overview: The is located at 98 Belmont Drive and consists of a two-story building which has had a number of additions added to it over the years, the latest of which was a two-story
More informationChenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017
Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections
More informationTable of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior
More informationAnalysis 4: Building Reuse
Analysis 4: Building Reuse Introduction The existing was built in 1954 and has clearly outlived its original construction. Current codes and program requirements are no longer met and it was clear that
More informationHERITAGE MIDDLE SCHOOL. Overview: Livingston School District Heritage Middle School
HERITAGE MIDDLE SCHOOL Overview: The is located at 20 Foxcroft Drive and consists of a three-story building with Three-Story Classroom and Multi-Purpose Room Additions completed in 2002. The building has
More informationLOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN
INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS
More informationK.B. Polk Recreation Center Summary
K.B. Polk Recreation Center Summary Address Building Purpose 6801 Roper Street Dallas, TX 75209 Recreation Center Original Year of Construction 1988 Building Area 14,305 SF Inspection Date July 20, 2016
More informationGARFIELD ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1910 BUILDING AREA 58,908 SF CURRENT PROGRAM CAPACITY 446 ENROLLMENT 2008 278 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan GARFIELD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope
More informationExisting Site Aerial Frederick High School Feasibility Study September 5, 2012
Existing Site Aerial Building Developmental History 1981 1966 1939 1977 1978 1955 1966 Exterior Roof: Most of existing roof has multi ply built up roofing. Some areas have gravel ballast, others have cap
More informationSimcoe County District School Board. 5yr Condition Assessment 2006/07 to 2010/11. Warnica PS, 9283
5yr Condition Assessment 2006/07 to 2010/11 Construction Year Area 1964 3,035 Page 1 of 27 1. Architectural / Structural & Site Exec Summary Warnica Public School is a one storey structure of masonry construction
More informationKEY ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1925 BUILDING AREA 52,000 SF CURRENT PROGRAM CAPACITY 320 ENROLLMENT 2008 328 WARD 3 PROPOSED PROGRAM CAPACITY 325 Site Plan KEY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationSPACE TYPE: OUTSIDE PARKING (STRUCTURE)
SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.
More informationOverbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %
8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior
More informationFranklin Hall Renovation TABLE OF Document Indiana University Bloomington
VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...
More informationFacility Condition Assessment: Final Report. University of Delaware Newark Main Campus McKinly Lab Newark, DE 19716
Facility Condition Assessment: Final Report University of Delaware Newark Main Campus McKinly Lab Newark, DE 19716 Submitted by: VFA, Inc. Carlo Pagliarini Project Manager 266 Summer St. Boston, MA 02210-1112
More informationNALLE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationA/E Design Deliverable Checklist
A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic
More informationReilly Elementary School Site Summary
1 Reilly Elementary School Site Summary Address 405 Denson Drive Austin, TX 78752 Number of Permanent Campus Facilities 1 Original Year of Construction 1954 Total Campus Building Area (combined) 41,622
More informationMills Elementary School Site Summary
1 Mills Elementary School Site Summary Address 6201 Davis Lane Austin, TX 78749 Number of Permanent Campus Facilities 1 Original Year of Construction 1998 Total Campus Building Area (combined) 81,368 SF
More informationBVSC BVSC. Midwest Technical Inspections Survey Worksheet. Account / Account Code: Insured: Policy #: Building Data - Section 1
Midwest Technical Inspections Survey Worksheet BVSC BVSC Account / Account Code: Agency: Insured: Policy #: Telephone: Alt. Phone: Building Data - Section 1 Building Name (Entire Valuation) Section Name
More information4.1.3 Project Manual
4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01
More informationDelco Activity Center Site Summary
1 Site Summary Address 4601 Pecan Brook Austin, TX 78724 Number of Permanent Campus Facilities 1 Original Year of Construction 2003 Total Campus Building Area (combined) 60,294 SF Introduction The is located
More informationMarch 2018 Progress. Work Completed, Week Ending 3/23/18:
March 2018 Progress Work Completed, Week Ending 3/23/18: Continued draft curtains and liner panels. Continued running power to hangar doors. Continued installation of bath accessories in the gang bathrooms.
More informationNYC Department of Education
Building Assessment Survey 2017-2018 Asset: HS FOR MATH, SCI & ENGINEERING-M, 240 CONVENT AVENUE, New York, 10031 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2017-12-20
More informationNYC Department of Education
Asset: Building Assessment Survey 2017-2018 PRE-K CENTER @ 132-10 JAMAICA AVENUE - QUEENS, 132-10 JAMAICA AVENUE, New York, 11418 Inspection Id Inspection Type Time In Last Edited SA : Architectural -
More informationMenchaca Elementary School Site Summary
1 Menchaca Elementary School Site Summary Address 12120 Manchaca Road Austin, TX 78704 Number of Permanent Campus Facilities 1 Original Year of Construction 1975 Total Campus Building Area (combined) 60,104
More informationToronto Community Housing Executive Summary 2016/2017. BCA Report. Sample House High FCI
BCA Report Porfolio Development Size Construction TCHC - All Op Units Scattered Units (CHU 20),005 Sq.Ft. 925 Floor Above Grade 2 Divisional Units Page of 43 Description This dwelling unit is a detached
More informationBALLOU SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE
More informationFacility Improvements
CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation
More informationThurgood Marshall Recreation Center Summary
Thurgood Marshall Recreation Center Summary Address Building Purpose 5150 Mark Trail Way Dallas, TX 75232 Recreation Center Original Year of Construction 1970 Building Area 21,300 SF Inspection Date August
More informationGFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1
GFW Schools Task Force Meeting 1/23/19 1 AGENDA 1. Introductions 2. Review of building tours Primary Needs 3. Review Space Programs 4. Review Concept Options District and Facility needs 5. Review Concept
More informationCODE COMPLIANCE PLAN REVIEW PROCEDURES
CODE COMPLIANCE PLAN REVIEW PROCEDURES 1. All construction for state agencies on state-owned or state leased-purchased properties or facilities are to submit design documents for code compliance plan reviews
More informationEvansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data
Evansville Public Schools Facility Assessment Report January 28, 2, 2013 SGN/Wendel Architects, Design Tree Engineering and R.A. Morton Construction Managers were retained by the Evansville Public School
More informationTABLE OF CONTENTS Public Safety Building
DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary
More informationNYC Department of Education
Architectural Inspection Asset: Building Assessment Survey 2017-2018 NYC SCHOOL CONSTR. AUTHORITY - QUEENS, 30-30 THOMSON AVE, New York, 11101 Inspection Id Inspection Type Time In Last Edited SA : Architectural
More informationAsset Overview Report By Asset Name
School District: Coast Mountains Asset: STEWART ELEMENTARY Facility: STEWART ELEMENTARY Asset Number: 107177 Assets are ordered by Asset Name Currency: CAD Statistics FCI Cost: 2,543,413 FCI: 0.59 RI Cost:
More informationFacilities Management Services & Funding Guide Centrally Funded and Recharge Services
Facilities Management Services & Funding Guide Centrally Funded and Recharge Services Table of Contents About the Funding Guide Page 3 Carpenter Shop Page 4 Custodial Services Page 5 Electrical Shop Page
More informationMinuteman Regional Vocational Technical School
Minuteman Regional Vocational Technical School List of Recommendations L1 AAB compliance: Improvements to front entrance (concrete ramps, railings, etc.) Required by AAB cost trigger L2 AAB compliance:
More informationNYC Department of Education
Building Assessment Survey 2017-2018 Asset: P.S. 65 - BROOKLYN, 158 RICHMOND STREET, New York, 11208 Inspection Id Inspection Type Time In Last Edited Architectural - Senior 2018-05-15 11:22 AM 2018-06-12
More informationAlabama Home Inspections
Cover Page Property Inspection Report 1000 Sample Dr., Sampletown USA Inspection prepared for: Report Sample Inspection Date: 1/21/2010 Time: 400pm Size: Approx. 2,200sf Weather: Cloudy 62 Inspector: Bobby
More informationDIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT
TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders
More informationPROCUREMENT AND CONTRACTING DOCUMENTS GROUP
PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders
More informationADDENDUM 2 - JULY 14, 2015
7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures
More informationNYC Department of Education
Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S. 290 - MANHATTAN, 311 EAST 82 STREET, New York, 10028 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior
More informationBeckley-Saner Recreation Center Summary
Beckley-Saner Recreation Center Summary Address Building Purpose 114 West Hobson Avenue, Dallas, TX 75224 Recreation Center Original Year of Construction 1949 Building Area 34,510 SF Inspection Date July
More informationNew Raised Courtyard Terrace Pavers and Retaining Walls. Line of Steps Above. New Wood Framed Stair
Building Program Wall Construction to Remain Religious Education New Wall Construction New Furring on Wall Construction, See Partition Types, Community Room New Galvanized Steel Window Well Patch Wall
More informationSHEPHERD ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1932 BUILDING AREA 79,700 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 355 WARD 4 PROPOSED PROGRAM CAPACITY 400 Site Plan SHEPHERD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationExhibit A Library Shell Construction
Exhibit A Library Shell Construction Library Component Building Requirements Approximately 15,000-17,000 square feet plus 900 square feet for mechanical room and additional space on roof for installation
More informationSchool Without Walls
INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationSPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM)
SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) Construction Criteria The unit costs for the Physical Fitness Center (Exercise Room) space type are based on the construction quality and design features in
More information