1 LEED Application Guide for Multiple Buildings and On-Campus Building Projects For Use with 2009 LEED Rating Systems for Design and Construction and Operations and Maintenance Released October 31, 2011 Appendix B: AGMBC Applicability for Credits and Prerequisites in the LEED 2009 Existing Buildings: Operations & Maintenance Rating System

2 How to read this table: Table 2 summarizes the prerequisites and credits in the LEED 2009 Existing Buildings: Operations & Maintenance rating system for which this guidance is applicable. The Campus Credit column contains a C for credits and prerequisites that are eligible to be included as campus credits in a master site. This column will be blank for those that may be pursued separately by each LEED project within the LEED campus boundary. The Group Credit column contains a G for credit and prerequisites that have group application guidance that must be followed if pursued in a group project certification. This column will be blank for those where compliance must be demonstrated on an individual building basis for all buildings within a group project. This table is intended for reference only. Many credits and prerequisites have additional conditions that must be met to be eligible as a campus or group credit. The credit-level application guidance that follows addresses every credit and prerequisite within the 2009 LEED for Existing Buildings: Operations & Maintenance rating system.

3 CAMPUS CREDIT GROUP CREDIT Table 2. AGMBC Applicability for Credits and Prerequisites in the LEED 2009 Existing Buildings: Operations & Maintenance Rating System RATING SYSTEM ELIGIBILITY LEED FOR EXISTING BUILDINGS: OPERATIONS & MAINTENANCE CREDIT CREDIT NAME SUSTAINABLE SITES SSc1 LEED Certified Design and Construction G SSc2 Building Exterior and Hardscape Management Plan C G Integrated Pest Management, Erosion Control and Landscape SSc3 Management Plan C G SSc4 Alternative Commuting Transportation G SSc5 Site Development- Protect or Restore Habitat C G SSc6 Site Development- Stormwater Quantity Control C G SSc7.1 Heat Island Reduction- Nonroof C G SSc7.2 Heat Island Reduction- Roof G SSc8 Light Pollution Reduction C G WEp1 WEc1.1 WATER EFFICIENCY Minimum Indoor Plumbing Fixture and Fitting Efficiency Water Performance Measurement- Whole Building WEc1.2 Water Performance Measurement- Submetering G WEc2 Additional Indoor Plumbing Fixture and Fitting Efficiency G WEc3 Water Efficient Landscaping C G WEc4.1 Cooling Tower Water Management- Chemical Management G WEc4.2 Cooling Tower Water Management- Non-potable Source G EAp1 EAp2 EAp3 ENERGY AND ATMOSPHERE Energy Efficiency Best Management Practices- Planning, Documentation and Opportunity Assessment Minimum Energy Efficiency Performance Fundamental Refrigerant Management EAc1 Optimize Energy Performance G EAc2.1 Existing Building Commissioning- Investigation and Analysis G EAc2.2 Existing Building Commissioning- Implementation G EAc2.3 Existing Building Commissioning- Ongoing Commissioning G EAc3.1 Performance Measurement- Building Automation System C G EAc3.2 Performance Measurement System- System-level Metering EAc4 On-site and Off-site Renewable Energy G EAc5 EAc6 Enhanced Refrigerant Management Emissions Reduction Reporting MATERIALS AND RESOURCES MRp1 Sustainable Purchasing Policy C G G

4 MRp2 Solid Waste Management Policy C G MRc1 Sustainable Purchasing- Ongoing Consumables G MRc2 Sustainable Purchasing- Durable Goods G MRc3 Sustainable Purchasing- Facility Alterations and Additions G MRc4 Sustainable Purchasing- Reduced Mercury in Lamps G MRc5 Sustainable Purchasing- Food G MRc6 Solid Waste Management- Waste Stream Audit MRc7 Solid Waste Management- Ongoing Consumables G MRc8 Solid Waste Management- Durable Goods G MRc9 Solid Waste Management- Facility Alterations and Additions G IEQp1 INDOOR ENVIRONMENTAL QUALITY Minimum Indoor Air Quality Performance IEQp2 Environmental Tobacco Smoke (ETS) Control C G IEQp3 Green Cleaning Policy C G IEQc1.1 Indoor Air Quality Best Management Practices- Indoor Air Quality Management Plan G IEQc1.2 Indoor Air Quality Best Management Practices- Outdoor Air Delivery Monitoring IEQc1.3 Indoor Air Quality Best Management Practices- Increased Ventilation IEQc1.4 Indoor Air Quality Best Management Practices- Reduced Particulates in Air Distribution IEQc1.5 IEQc2.1 IEQc2.2 IEQc2.3 IEQc2.4 Indoor Air Quality Best Management Practices- Indoor Air Quality Management for Facility Alterations and Additions Occupant Comfort- Occupant Survey Controllability of Systems- Lighting Occupant Comfort- Thermal Comfort Monitoring Daylight and Views IEQc3.1 Green Cleaning- High Performance Cleaning Program C G IEQc3.2 IEQc3.3 Green Cleaning- Custodial Effectiveness Assessment Green Cleaning- Purchase of Sustainable Cleaning Products and Materials IEQc3.4 Green Cleaning- Sustainable Cleaning Equipment G IEQc3.5 Green Cleaning- Indoor Chemical and Pollutant Source Control IEQc3.6 Green Cleaning- Indoor Integrated Pest Management C G INNOVATION IN OPERATIONS IOc1 Innovation in Operations C G IOc2 LEED Accredited Professional G IOc3 Documenting Sustainable Building Cost Impacts C G REGIONAL PRIORITY RPc1 Regional Priority C G Not eligible as campus or group credit for all compliance options. Please refer to application guidance for details. G G

5 SS Credit 1: LEED Certified Design and Construction The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the All of the buildings within the group must have been previously certified to achieve this credit. SS Credit 2: Building Exterior and Hardscape Management Plan The plan may be implemented on a campus-wide basis. Each project must confirm that the plan has been followed during the individual performance period. The credit requirements apply to the area within the LEED project boundary. The same plan may be applied to all of the buildings on the site. SS Credit 3: Integrated Pest Management, Erosion Control and Landscape Management Plan The plan may be implemented on a campus-wide basis. Each project must confirm that the plan has been followed during the individual performance period. The credit requirements apply to the area within the LEED project boundary. The same plan may be applied to all of the buildings on the site.

6 SS Credit 4: Alternative Commuting Transportation The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the The credit requirements may be met by performing one survey that encompasses all of the regular building occupants in all of the buildings within the LEED project boundary. Alternatively, a single survey may be conducted for each individual building and the results may be aggregated. SS Credit 5: Site Development - Protect or Restore Habitat The development footprints of all projects contained within the LEED campus boundary (including those projects not pursuing LEED certification) must be included in the credit calculations. The credit requirements apply to the area within the LEED project boundary. SS Credit 6: Site Development - Stormwater Quantity Control Credit compliance may be achieved by using a campus ongoing stormwater management plan and annual inspection program. The stormwater runoff calculations must account for the total campus area. The reduction requirements must be met at the LEED campus boundary. The credit requirements apply to the area within the LEED project boundary.

7 SS Credit 7.1: Heat Island Reduction-Nonroof Option 1: The area of all of the site hardscape contained within the LEED campus boundary (including hardscape associated with projects within the LEED campus boundary that are not pursuing LEED certification) must be included in the calculations. Option 2: All of the parking located within the LEED campus boundary must be included in the calculations. The credit requirements apply to the area within the LEED project boundary. SS Credit 7.2: Heat Island Reduction-Roof The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the The credit requirements apply to the total combined roof area of all of the buildings within the LEED project boundary (total compliant roof area/total roof area).

8 SS Credit 8: Light Pollution Reduction Exterior: Option 1: All projects in the campus must have been previously certified. Option 2: All exterior fixtures within the master project boundary must meet the shielding requirements. Option 3: Trespass requirements must be met at the LEED campus boundary. Interior: Interior lighting control systems may be part of a campus-wide automation system. Include all lighting zones and non-emergency built-in light fixtures. If a campus-wide automation system is not in place, this portion of the credit must be submitted for each individual project. Exterior: If using Option 2 for exterior lighting compliance, the requirements must be met at the LEED project boundary. Interior: Each building within the LEED project boundary must meet the credit requirements for interior lighting individually. WE Prerequisite 1: Minimum Indoor Plumbing Fixture and Fitting Efficiency The prerequisite cannot be pursued as a campus prerequisite. Each LEED project referencing the must pursue the prerequisite individually. Each building within the LEED project boundary must document and meet the prerequisite requirements individually. WE Credit 1.1: Water Performance Measurement - Whole Building The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must have in place permanently installed water metering which measures the total potable water use for the entire building.

9 WE Credit 1.2: Water Performance Measurement - Submetering The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building must have in place permanently installed metering for at least one water subsystem. The water subsystems must be building specific. If the entire site within the LEED project boundary has an irrigation meter or district level cooling tower meter, then this point may be earned without any additional submeters. If the scope of the metering is larger than the project that is being certified, irrigation/cooling tower meters must be owned by the same organization that owns/manages the building. WE Credit 2: Additional Indoor Plumbing Fixture and Fitting Efficiency The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Submittal documentation should represent the total combined water use reduction in all LEED project buildings. The baseline adjustment for year of substantial system completion should be averaged based on all plumbing fixtures in all buildings. WE Credit 3: Water Efficient Landscaping All of the irrigated areas within the LEED campus boundary must be included in the credit calculations in order to document compliance. The credit requirements apply to the area within the LEED project boundary.

10 WE Credit 4.1: Cooling Tower Water Management - Chemical Management The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the The cooling tower water management plan must apply to all of the cooling towers that serve any building within the LEED project boundary. Note that at least one building within the LEED project boundary must be served by a cooling tower in order to attempt this credit. WE Credit 4.2: Cooling Tower Water Management - Non-potable Source The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the The credit requirements apply to all of the cooling towers that serve any building within the LEED project boundary. In aggregate, the makeup water must consist of at least 50% non-potable water. EA Prerequisite 1: Energy Efficiency Best Management Practices - Planning, Documentation and Opportunity Assessment The prerequisite cannot be pursued as a campus prerequisite. Each LEED project referencing the must pursue the prerequisite individually. Each LEED project referencing the must pursue the prerequisite individually. The same process may be used for each building within the LEED project boundary. One report may be submitted that addresses each building individually. Note that systems narrative documentation, preventative maintenance documentation, and building operating plan may be combined for one or more buildings, but spaces with different operating parameters must be addressed separately within the documentation. The results of the ASHRAE Level 1 Walk-Through Analysis must be provided for each individual building.

11 EA Prerequisite 2: Minimum Energy Efficiency Performance The prerequisite cannot be pursued as a campus prerequisite. Each LEED project referencing the must pursue the prerequisite individually. Each building within the LEED project boundary must document and meet the prerequisite requirements individually. EA Prerequisite 3: Fundamental Refrigerant Management The prerequisite cannot be pursued as a campus prerequisite. Each LEED project referencing the must pursue the prerequisite individually. Each LEED project referencing the must pursue the prerequisite individually. Each building within the LEED project boundary must document and meet the prerequisite requirements individually. EA Credit 1: Optimize Energy Performance The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the If all buildings in the group consist of the same space type (as defined by ENERGY STAR or CBECS), the number of points within this credit may be based on a square footage weighted average of the ENERGY STAR ratings or Case 2 calculator EUIs of each building. If the group consists of buildings of different space types, points must be based on the rating of the lowest-performing building.

12 EA Credit 2.1: Existing Building Commissioning- Investigation and Analysis The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must use the same compliance option to meet the credit requirements. One report may be submitted that addresses each building individually. The retrocommissioning, recommisioning or ongoing commissioning plan, report of findings after the completion of the investigation and analysis phase and completed ASHRAE Level II Analysis report must be building specific. EA Credit 2.2: Existing Building Commissioning- Implementation The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must use the same compliance option to meet the credit requirements. One report may be submitted that addresses each building individually. EA Credit 2.3: Existing Building Commissioning- Ongoing Commissioning The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must use the same compliance option to meet the credit requirements. One report may be submitted that addresses each building individually. The documentation must include a summary of the overall commissioning cycle for each building individually.

13 EA Credit 3.1: Performance Measurement Building Automation System A campus-wide building automation system may be used to demonstrate compliance provided that all buildings in the campus are controlled by the system. The preventative maintenance program must address BAS components throughout the campus. The credit requirements may be met by implementing a campus-wide Building Automation System as long as parameters are set for each individual building. Alternatively, if the project does not have a campus-wide Building Automation System, the credit requirements must be met for each building individually. EA Credit 3.2: Performance Measurement System-level Metering This credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Any end use contributing towards the achievement of this credit must be submetered in each individual building. For example, if lighting is one of the largest energy use categories contributing towards credit achievement, lighting must be submetered in each individual building. EA Credit 4: On-site and Off-site Renewable Energy This credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the The credit requirements may be met by aggregating the total energy use, total on-site renewable energy, and total off-site renewable energy certificates from each of the buildings within the LEED project boundary.

14 EA Credit 5: Enhanced Refrigerant Management This credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must meet the credit requirements individually. EA Credit 6: Emissions Reduction Reporting This credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must meet the credit requirements individually. MR Prerequisite 1: Sustainable Purchasing Policy The policy may be implemented on a campus-wide basis and must address any sub-sets of purchasing habits (such as for different project types within the campus). The policy must address the goals, scope and performance metrics for any purchasing credits that any individual projects within the master project intend to pursue. The same purchasing policy may be used for all of the buildings within the LEED project boundary.

15 MR Prerequisite 2: Solid Waste Management Policy The policy may be implemented on a campus-wide basis and must address any sub-sets of waste management habits (such as for different project types within the campus). The same waste management policy may be used for all of the buildings within the LEED project boundary. MR Credit 1: Sustainable Purchasing - Ongoing Consumables The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Submittal documentation should represent the total combined ongoing consumable purchases for all LEED project buildings. MR Credit 2: Sustainable Purchasing Durable Goods The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Submittal documentation should represent the total combined durable goods purchases for all LEED project buildings

16 MR Credit 3: Sustainable Purchasing Facility Alterations and Additions The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the At least one qualifying facility alteration or addition is required to have occurred in at least one of the buildings within the LEED project boundary during the performance period in order to attempt this credit, i.e., it is not required for a facility alteration or addition to occur in each building within the LEED project boundary. However, if this credit is attempted, the purchases pertaining to all qualifying facility alterations and additions that occurred in any building within the LEED project boundary during the performance period must be included in the credit calculations. MR Credit 4: Sustainable Purchasing Reduced Mercury in Lamps The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Submittal documentation should represent the total combined bulb purchases for all LEED project buildings. MR Credit 5: Sustainable Purchasing Food The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Submittal documentation should represent the total combined food purchases for all LEED project buildings.

17 MR Credit 6: Solid Waste Management - Waste Stream Audit The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the A waste audit must be performed for each individual building within the LEED project boundary. MR Credit 7: Solid Waste Management - Ongoing Consumables The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Submittal documentation should represent the total combined ongoing consumables waste for all LEED project buildings. MR Credit 8: Solid Waste Management Durable Goods The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Submittal documentation should represent the total combined durable goods waste for all LEED project buildings.

18 MR Credit 9: Solid Waste Management Facility Alterations and Additions The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the At least one qualifying facility alteration or addition is required to have occurred in at least one of the buildings within the LEED project boundary during the performance period in order to attempt this credit, i.e., it is not required for a facility alteration or addition to occur in each individual building within the LEED project boundary. However, if this credit is attempted, the waste pertaining to all qualifying facility alterations and additions that occurred in any building within the LEED project boundary during the performance period must be included in the credit calculations. IEQ Prerequisite 1: Minimum Indoor Air Quality Performance The prerequisite cannot be pursued as a campus prerequisite. Each LEED project referencing the must pursue the prerequisite individually. Each building within the LEED project boundary must document and meet the prerequisite requirements individually.

19 IEQ Prerequisite 2: Environmental Tobacco Smoke (ETS) Control Eligible as a campus credit using Option 1 Only: The smoking prohibition policy may be implemented on a campuswide basis. In order to document prerequisite compliance, provide evidence of signage communicating the exterior smoking policy for the entire campus. Option 1 Only: Designated smoking areas located anywhere on the project site must be located at least 25 feet away from building entrances and openings. The prerequisite requirements for interior smoking rooms must be met for each individual building within the LEED project boundary. All other options: Each building within the LEED project boundary must document and meet the prerequisite requirements individually. IEQ Prerequisite 3: Green Cleaning Policy The policy may be implemented on a campus-wide basis and must address any sub-sets of green cleaning habits (such as for different project types within the campus). The same green cleaning policy may be used for all of the buildings within the LEED project boundary. Different space types must be addressed separately in the policy as needed. IEQ Credit 1.1: Indoor Air Quality Best Management Practices- Indoor Air Quality Management Program The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the One IAQ audit may be performed that encompasses all of the buildings within the LEED project boundary. The same protocols used to manage significant pollutant sources may be used for all of the buildings within the LEED project boundary. A plan must be established to address all of the IAQ issues with each of the buildings. The protocol for receiving and responding to occupant IAQ complaints must encompass each of the buildings.

20 IEQ Credit 1.2: Indoor Air Quality Best Management Practices- Outdoor Air Delivery Monitoring The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must document and meet the credit requirements individually. IEQ Credit 1.3: Indoor Air Quality Best Management Practices- Increased ventilation The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must document and meet the credit requirements individually. IEQ Credit 1.4: Indoor Air Quality Best Management Practices- Reduced Particulates in Air Distribution The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must document and meet the credit requirements individually.

21 IEQ Credit 1.5: Indoor Air Quality Best Management Practices- Indoor Air Quality Management for Facility Alterations and Additions The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the The same IAQ management plan may be used for each of the buildings within the LEED project boundary. The plan must be implemented for each of the applicable facility alterations or additions that occur in any of the buildings. IEQ Credit 2.1: Occupant Comfort - Occupant Survey The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must document and meet the credit requirements individually. IEQ Credit 2.2: Controllability of Systems - Lighting The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must document and meet the credit requirements individually.

22 IEQ Credit 2.3: Occupant Comfort- Thermal Comfort Monitoring The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must document and meet the credit requirements individually. IEQ Credit 2.4: Daylight and Views The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Each building within the LEED project boundary must document and meet the credit requirements individually. IEQ Credit 3.1: Green Cleaning- High Performance Cleaning Program The program may be implemented on a campus-wide basis and must address any sub-sets of green cleaning habits (such as for different project types within the campus). The same high performance green cleaning program may be used for all of the buildings within the LEED project boundary. Different space types must be addressed separately in the program as needed.

23 IEQ Credit 3.2: Green Cleaning - Custodial Effectiveness Assessment The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the A separate APPA cleanliness audit must be performed for each individual building with the LEED project boundary. IEQ Credit 3.3: Green Cleaning- Purchase of Sustainable Cleaning Products and Materials The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Submittal documentation should represent the total combined cleaning product purchases for all LEED project buildings. IEQ Credit 3.4: Green Cleaning - Sustainable Cleaning Equipment The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the Submittal documentation should represent the total combined cleaning equipment inventories and purchases for all LEED project buildings.

24 IEQ Credit 3.5: Green Cleaning - Indoor Chemical and Pollutant Source Control The credit cannot be pursued as a campus credit. Each LEED project referencing the may pursue the All of the entrances from the outdoors for each building within the LEED project boundary must have installed entryway systems in place in order to achieve this credit. IEQ Credit 3.6: Green Cleaning - Indoor Integrated Pest Management The plan may be implemented on a campus-wide basis. Each project must confirm that the plan has been followed during the individual performance period. The same Indoor Integrated Pest Management plan may be used for all of the buildings within the LEED project boundary. All buildings are required to comply with the plan 100% of the time during the performance period. If one building does not fully comply with the plan during the performance period, the credit may not be achieved. IO Credits: Innovation in Operations s Campus-wide strategies may be documented as such, but strategies that apply to individual buildings must be documented for every building. Campus-wide strategies may be documented as such, but strategies that apply to individual buildings must be documented for every building. The sustainable building cost impacts may be documented at the portfolio level. Alternatively, each individual building may document the sustainable building cost impacts separately. Note that there is no change to the requirements for achieving exemplary performance under the applicable credits.

25 RP Credits: Regional Priority Master site credits are not eligible for Regional Priority Credits. When the credit is awarded at the project level, the project will achieve the regional priority credit. If the LEED project boundary encompasses two or more zip codes, the zip code containing the largest portion of the boundary should be used for selection of eligible regional priority credits. If the LEED project boundary encompasses two or more zip codes, the zip code containing the largest portion of the boundary should be used for selection of eligible regional priority credits.

LEED Application Guide for Multiple Buildings and On Campus Building Projects

LEED Application Guide for Multiple Buildings and On Campus Building Projects LEED Application Guide for Multiple Buildings and On Campus Building Projects For Use with 2009 LEED Rating Systems for Design and Construction and Operations and Maintenance Released October 31, 2011

More information

500 WEST PUTNAM AVENUE GREENWICH, CT

500 WEST PUTNAM AVENUE GREENWICH, CT LEED-CI ANALYSIS June 2015 500 WEST PUTNAM AVENUE GREENWICH, CT To learn more please visit the sustainability section of our website: www.slgreen.com or contact Jay Black, SL Green s director of sustainability

More information

Synergies & Trade-offs: IP category

Synergies & Trade-offs: IP category Synergies & Trade-offs: IP category Integrative Process (IP) Related Synergies and Trade-offs IPc Integrative Process LTc Access to Quality Transit LTc Reduced Parking Footprint SSc Heat Island Reduction

More information

LEED for Existing Buildings:

LEED for Existing Buildings: LEED for Existing Buildings: Operations and Maintenance 101 0 Agenda 1. Overview of changes to LEED-EBOM 2009 3. Assessing Building Opportunities Building Exterior and Site Water Efficiency Energy & Atmosphere

More information

LEED 2009 FOR EXISTING BUILDINGS OPERATIONS AND MAINTENANCE ACP DOCUMENTATION GUIDANCE FOR PROJECTS OUTSIDE THE U.S.

LEED 2009 FOR EXISTING BUILDINGS OPERATIONS AND MAINTENANCE ACP DOCUMENTATION GUIDANCE FOR PROJECTS OUTSIDE THE U.S. LEED 2009 FOR EXISTING BUILDINGS OPERATIONS AND MAINTENANCE ACP DOCUMENTATION GUIDANCE FOR PROJECTS OUTSIDE THE U.S. October 2011 This is a draft document and can be used only in the interim until LEED

More information

2016 LEED Equivalency Analysis for Stanford Campus

2016 LEED Equivalency Analysis for Stanford Campus 6 LEED Equivalency Analysis for Stanford Campus Analysis performed by: Moira Hafer, LEED AP O+M Office of Sustainability Department of Sustainability & Energy Management Stanford University Category Type

More information

LEED LEED. Leadership in Energy and Environmental Design. A voluntary, consensus-based. high-performance, sustainable buildings and neighborhoods

LEED LEED. Leadership in Energy and Environmental Design. A voluntary, consensus-based. high-performance, sustainable buildings and neighborhoods LEED An Introduction to LEED V3 2009 LEED Leadership in Energy and Environmental Design A voluntary, consensus-based national standard for developing high-performance, sustainable buildings and neighborhoods

More information

A Building Commissioning Overview. Presented by: Goetting & Associates Commissioning

A Building Commissioning Overview. Presented by: Goetting & Associates Commissioning A Building Commissioning Overview Presented by: Goetting & Associates Commissioning www.goettingcx.com What is the Definition of Commissioning? Building Commissioning is a Quality Assurance Process of

More information

LEED CERTIFICATION PROJECT REVIEW REPORT

LEED CERTIFICATION PROJECT REVIEW REPORT LEED CERTIFICATION PROJECT REVIEW REPORT How to Interpret this Report Purpose Leadership in Energy and Environmental Design (LEED) was designed by the US Green Building Council to encourage and facilitate

More information

LEED Project Delivery Process Manual Appendices

LEED Project Delivery Process Manual Appendices LEED Project Delivery Process Manual Appendices November 2016 Second Edition Appendices Page Appendix 1: Other Alberta Requirements and Green Building Standards 3 Appendix 2: Integrated Design Process

More information

LEED Reference Guide for Green Building Operations and Maintenance, 2009 Edition (first edition)

LEED Reference Guide for Green Building Operations and Maintenance, 2009 Edition (first edition) For the documents titled: LEED Reference Guide for Green Building Operations and Maintenance, 2009 Edition (first edition) Note: This document contains addenda to the reference guide listed above and will

More information

LEED 2009 for New Construction and Major Renovations

LEED 2009 for New Construction and Major Renovations LEED 2009 for New Construction and Major Renovations Bayshore District Operations Building Project Checklist 4.28.6 20 4 0 Sustainable Sites Possible Points: 26 Y? N d/c Notes: Y C Prereq Construction

More information

THERMA-FUSER VARIABLE AIR VOLUME DIFFUSER SYSTEMS

THERMA-FUSER VARIABLE AIR VOLUME DIFFUSER SYSTEMS SUSTAINABLE DESIGN FORM 010.901 REV 1211 THERMA-FUSER VARIABLE AIR VOLUME DIFFUSER SYSTEMS SUSTAINABLE DESIGN GUIDE StopWaste.Org LEED-NC Platinum Energy Foundation LEED-CI Platinum Adobe East Tower LEED-EB

More information

LEED 2009 for Commercial Interiors. Presented by: Colleen McCafferty LEED AP Roselia Harris LEED AP

LEED 2009 for Commercial Interiors. Presented by: Colleen McCafferty LEED AP Roselia Harris LEED AP LEED 2009 for Commercial Interiors Presented by: Colleen McCafferty LEED AP Roselia Harris LEED AP Homes Commercial Interiors Core & Shell New Construction Schools Healthcare Existing Building Operations

More information

Errata Sheet. LEED for Schools Reference Guide First Edition for the document titled:

Errata Sheet. LEED for Schools Reference Guide First Edition for the document titled: Errata Sheet for the document titled: LEED for Schools Reference Guide First Edition 2007 Notes: Updates to this document are posted on the LEED for Schools Rating System page and the Reference Guide electronic

More information

Green Guide for Health Care Version 2.2 Operations Section, 2008 Revision Comparison with GGHC Version 2.2, January 2007

Green Guide for Health Care Version 2.2 Operations Section, 2008 Revision Comparison with GGHC Version 2.2, January 2007 Green Guide for Health Care Version 2.2 Operations Section, 2008 Revision Comparison with GGHC Version 2.2, January 2007 2.2 Mod New 0 79 42 Green Guide for Health Care Version 2.2 Operations Section,

More information

LEED -Existing Buildings. Crescent Ridge Corporate Center I

LEED -Existing Buildings. Crescent Ridge Corporate Center I LEED -Existing Buildings Crescent Ridge Corporate Center I LEED Leadership in Energy and Environmental Design The U.S. Green Building Council is a coalition of leaders in the building industry promoting

More information

Green Building Rating System For Commercial Interiors

Green Building Rating System For Commercial Interiors Green Building Rating System For Commercial Interiors Version 2.0 *Updated December 2005 November 2004 *With revised EA section for projects registered after June 26, 2007. LEED for Commercial Interiors

More information

ULMA S COMPROMISE & CONTRIBUTION TO LEED CERTIFICATION

ULMA S COMPROMISE & CONTRIBUTION TO LEED CERTIFICATION ULMA S COMPROMISE & CONTRIBUTION TO LEED CERTIFICATION UNDERSTANDING LEED Leadership in Energy and Environmental Design- LEED is an internationally recognized green building certification system, providing

More information

1) MERV (Minimum Efficiency Reporting Value) is relevant to which ASHRAE standards in LEED v4? (Choose 2)

1) MERV (Minimum Efficiency Reporting Value) is relevant to which ASHRAE standards in LEED v4? (Choose 2) 1) MERV (Minimum Efficiency Reporting Value) is relevant to which ASHRAE standards in LEED v4? (Choose 2) A. 52.2-2007 B. 55-2010 C. 62.1-2010 D. 90.1-2010 E. 189.1 Answer A and C. 52.2-2007 - ASHRAE Standard

More information

Analysis 1. LEED Analysis of Laboratory Buildings. Penn State School of Forest Resources University Park, PA

Analysis 1. LEED Analysis of Laboratory Buildings. Penn State School of Forest Resources University Park, PA Analysis 1 LEED Analysis of Laboratory Buildings Background The LEED program (Leadership in Energy and Environmental Design) established by the U.S. Green Building Council is becoming the standard by which

More information

Genentech Building 20 Office LEED-CI Gold XL CONSTRUCTION

Genentech Building 20 Office LEED-CI Gold XL CONSTRUCTION Genentech Building 20 Office LEED-CI Gold Above and Beyond A LEED Gold 50,00 s.f. tenant improvement, the space was originally designed with a goal to achieve LEED silver certification. Innovative approaches

More information

Green Building Rating System For Commercial Interiors. Version 2

Green Building Rating System For Commercial Interiors. Version 2 Green Building Rating System For Commercial Interiors Version 2 November 2004 Leadership in Energy and Environmental Design (LEED ) Buildings fundamentally impact people s lives and the health of the planet.

More information

LEED NC (Version ) Credit Guide The University of Texas at Austin

LEED NC (Version ) Credit Guide The University of Texas at Austin INTRODUCTION This Credit Guide is intended to serve as a guideline for project teams to understand the University s sustainability goals and priorities and how they relate to LEED credits. The University

More information

GSA Public Buildings Service. GSA LEED Applications Guide

GSA Public Buildings Service. GSA LEED Applications Guide GSA Public Buildings Service GSA LEED Applications Guide February 2005 Acknowledgements The authors of the GSA LEED Applications Guide would like to thank Mr. David B. Eakin, Chief Engineer in the Office

More information

EnOcean Technology and LEED Enabling Sustainability

EnOcean Technology and LEED Enabling Sustainability Rev A 2010-01-22 Prepared by Building Intelligence Group LLC: Paul Ehrlich, PE Jeffrey Seewald, PE (651) 204-0105 info@buildingintelligencegroup.com www.buildingintelligencegroup.com Building Intelligence

More information

LEED v4 for Homes, Residential Project Summary and Checklist One and Two Family New Construction

LEED v4 for Homes, Residential Project Summary and Checklist One and Two Family New Construction LEED v4 for Homes, Residential Project Summary and Checklist One and Two Family New Construction Summary Date of Application Path Project Project Address Owner Architect Third Party Third Party Provider

More information

LEED Reference Guide for Green Interior Design and Construction, 2009 Edition (first edition)

LEED Reference Guide for Green Interior Design and Construction, 2009 Edition (first edition) For the document titled: LEE Reference Guide for Green Interior esign and Construction, 2009 Edition (first edition) Note: This document contains addenda to the reference guide listed above and will be

More information

EA PREREQUISITE 2: MINIMUM ENERGY PERFORMANCE

EA PREREQUISITE 2: MINIMUM ENERGY PERFORMANCE THRESHOLD ATTEMPTED LEED 29 for New Construction and Major Renovations EA PREREQUISITE 2: MINIMUM ENERGY PERFORMANCE Project # 138123 Jacobs Hall All fields and uploads are required unless otherwise noted.

More information

CALGreen 2013 Tier Comparison to LEED v4

CALGreen 2013 Tier Comparison to LEED v4 CG-2016 5.106.1 SSp1 All projects must have a SWPP plan that meets State national Pollution CALGreen and LEED v4 are equivalent. Storm Water Soil Loss Discharge Elimination (NPEDS) Prevention Plan The

More information

NAVY LEED COMMISSIONING NAVFAC Symposium 1 December 2010 David Bylund AIA LEED-AP Architects Hawaii

NAVY LEED COMMISSIONING NAVFAC Symposium 1 December 2010 David Bylund AIA LEED-AP Architects Hawaii NAVY LEED COMMISSIONING 2010 NAVFAC Symposium 1 December 2010 David Bylund AIA LEED-AP Architects Hawaii INTRODUCTION LEED v3 Navy & Sustainability Commissioning Lessons Learned LEED v3 LEED v3 LEED v3

More information

LEED And Your Indoor Environment

LEED And Your Indoor Environment LEED And Your Indoor Environment An overview of LEED v3 and Indoor Air Quality David McCauley, CIE Council Certified Indoor Environmentalist ACAC CIE #1008005 USGBC's Mission To transform the way buildings

More information

LEED-EB Project Case Study: JohnsonDiversey Headquarters

LEED-EB Project Case Study: JohnsonDiversey Headquarters LEED-EB Project Case Study: JohnsonDiversey Headquarters CONTENTS HOW TO USE THIS CASE STUDY... II INTRODUCTION TO JOHNSONDIVERSEY...4 CULTIVATING AN ORGANIZATIONAL COMMITMENT TO LEED-EB...5 ACHIEVING

More information

LEED version 4 Leadership in Energy and Environmental Design

LEED version 4 Leadership in Energy and Environmental Design LEED version 4 Leadership in Energy and Environmental Design United States Green Building Council Founded in 1993, the United States Green Building Council (USGBC) was the first Green Building Council

More information

The Leadership in Energy and Environmental Design-Existing Buildings Certification of the Art and Architecture Building

The Leadership in Energy and Environmental Design-Existing Buildings Certification of the Art and Architecture Building The Leadership in Energy and Environmental Design-Existing Buildings Certification of the Art and Architecture Building Nicholas Alanen Lauren Berent Jason rinsky Emily Thomas Environ 302 April 20, 2009

More information

WMU Facility Life Cycle Design Guidelines Update (Approved by VP Van Der Kley & Facilities Management on 4/28/16)

WMU Facility Life Cycle Design Guidelines Update (Approved by VP Van Der Kley & Facilities Management on 4/28/16) Update (Approved by VP Van Der Kley & Facilities Management on 4/28/16) Developed by Sustainable Design Committee: Christopher Caprara, Devon Miller, Carolyn Noack, Eleonora Philopoulos, Kelsey Pitschel,

More information

Green Building Rating System

Green Building Rating System An Introduction to the U.S. Green Building Council and the LEED TM Green Building Rating System March 2004 U.S. Green Building Council The nation's foremost coalition of leaders from across the building

More information

75% 40% reduction in water consumption. 43% 68% 90%

75% 40% reduction in water consumption. 43% 68% 90% HOLOKE EIGHTH FLOOR CAMPUS SERVICE CENTER 75 Mount Auburn Street, Cambridge, MA 02138 LEED-CI V3 GOLD The Harvard Campus Service Center LEED CI project is an interior renovation of existing office space

More information

Case Study: Element PROJECT DESCRIPTION

Case Study: Element PROJECT DESCRIPTION Case Study: Element PROJECT DESCRIPTION Project type: Project gross SF: Number of keys: Location: Hotel (Hospitality), extended-stay prototype Varies, prototypical SF: 79,035 SF gross Varies, prototypical:

More information

LEED for Commercial Interiors

LEED for Commercial Interiors LEED-CI LEED for Commercial Interiors Kim Lam Renee Webley What is the LEED-CI Rating System? The benchmark for tenant improvements of new or existing office space. An integrated design tool that sets

More information

Planning for LEED. Leadership in Energy and Environmental Design

Planning for LEED. Leadership in Energy and Environmental Design Planning for LEED Leadership in Energy and Environmental Design LEED and related logo is a trademark owned by the U.S. Green Building Council and is used by permission Planning for LEED LEED Building Types

More information

8 Green Building Certification Credits

8 Green Building Certification Credits 8 Green Building Certification Credits San Francisco Stormwater Management Requirements and Design Guidelines Stormwater management can help project proponents achieve green building certification credits.

More information

HELPING HVAC PROFESSIONALS TAKE THE LEED ACHIEVING LEED CERTIFICATION

HELPING HVAC PROFESSIONALS TAKE THE LEED ACHIEVING LEED CERTIFICATION HELPING HVAC PROFESSIONALS TAKE THE LEED ACHIEVING LEED CERTIFICATION Green proof of performance pays Sustainable design saves energy, opens doors and improves building status The rapidly growing segment

More information

PROJECT DESIGN EVALUATION AND APPROVAL PROCESS DESIGN AND CONSTRUCTION STANDARD

PROJECT DESIGN EVALUATION AND APPROVAL PROCESS DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL 1.01 General Requirements A. These guidelines are intended to provide a framework to evaluate building projects for the University of Texas at Austin to: 1. Verify the feasibility of options

More information

LEED Reference Guide for Green Building Operations and Maintenance, 2009 Edition (first edition)

LEED Reference Guide for Green Building Operations and Maintenance, 2009 Edition (first edition) For the documents titled: LEED Reference Guide for Green Building Operations and Maintenance, 2009 Edition (first edition) Note: This document contains addenda to the reference guide listed above and will

More information

Cleveland Heights University Heights High School Eco Charrette Report May 16, 2014

Cleveland Heights University Heights High School Eco Charrette Report May 16, 2014 Cleveland Heights University Heights High School Eco Charrette Report May 16, 2014 Prepared by Laura Steinbrink EXECUTIVE SUMMARY The Lay Facilities Committee ( LFC ) members on the Sustainability Working

More information

PROPOSED SAN FRANCISCO GREEN BUILDING CODE AMENDMENTS 2016 Edition

PROPOSED SAN FRANCISCO GREEN BUILDING CODE AMENDMENTS 2016 Edition PROPOSED SAN FRANCISCO GREEN BUILDING CODE AMENDMENTS 2016 Edition Chapter 1 GENERAL SECTION 101 GENERAL 101.1 Title. These regulations shall be known as the California San Francisco Green Building Standards

More information

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma LEED Green Building Certification The purpose of the LEED Green Building Rating is to provide a national standard that aims to improve environmental, health and economic performance of buildings using

More information

A. The project is intended to achieve LEED Certification at the Silver Level per the U.S. Green Building Council LEED for Schools 2007 rating system.

A. The project is intended to achieve LEED Certification at the Silver Level per the U.S. Green Building Council LEED for Schools 2007 rating system. SECTION 23 01 01 HVAC LEED REQUIREMENTS PART 1 -GENERAL 1.1 WORK INCLUDES A. Compliance with LEED project requirements. B. Coordination of LEED construction phase activities. C. Data gathering of construction

More information

Alpen Windows - LEED Impact Analysis

Alpen Windows - LEED Impact Analysis ALPEN WINDOWS MATERIALS: Energy Efficient Windows Alpen Windows - LEED Impact Analysis SECTION I. PRODUCT IDENTIFICATION Product Name: Alpen Windows Manufacturer: Alpen High Performance Products 6268 Monarch

More information

Research Analysis: Building Envelope and LEED Credits Introduction

Research Analysis: Building Envelope and LEED Credits Introduction : Building Envelope and LEED Credits Introduction Green buildings are no longer a new idea and are quickly becoming the trend in the slowly changing industry of building construction. Even though the essence

More information

SACRAMENTO County New Animal Care Facility LEED Elements

SACRAMENTO County New Animal Care Facility LEED Elements Construction Activity Pollution Prevention We reduced pollution from construction activities by controlling soil erosion, waterway sedimentation, and airborne dust generation by creating an Erosion and

More information

LEED Existing Buildings Operations & Maintenance

LEED Existing Buildings Operations & Maintenance LEED Existing Buildings Operations & Maintenance Deb Frank, LEED AP BD+C Emily Andrews, LEED AP O+M Presenter: deborah.frank@mobot.org, 314-577-0279 Presenter: emily.andrews@mobot.org, 314-577-0854 U.S.

More information

ADMINISTRATIVE BULLETIN

ADMINISTRATIVE BULLETIN City and County of San Francisco Department of Building Inspection Edwin M. Lee, Mayor Tom C. Hui, S.E., Director ADMINISTRATIVE BULLETIN NUMBER DATE: SUBJECT: TITLE: AB-093 Effective January 1, 2017.

More information

SUSTAINABLE BUILDING DESIGN

SUSTAINABLE BUILDING DESIGN SUSTAINABLE BUILDING DESIGN LEED and HVAC How Trane can help. HVAC and LEED 2009 BUILDING DESIGN AND CONSTRUCTION (BD+C)... Building on its past success, the U.S. Green Building Council (USGBC), the nonprofi

More information

LEED Leadership in Energy and Environmental Design

LEED Leadership in Energy and Environmental Design LEED Leadership in Energy and Environmental Design United States Green Building Council (USGBC) Founded in 1993, the United States Green Building Council (USGBC) was the first Green Building Council formed

More information

USGBC & LEED. A Summary of the LEED Development as a primer for LEED ND

USGBC & LEED. A Summary of the LEED Development as a primer for LEED ND USGBC & LEED A Summary of the LEED Development as a primer for LEED ND US Green Building Council USGBC Basic USGBC information LEED (Leadership in Energy and Environmental Design GBCI (Green Building Certification

More information

Developer s Guide to LEED NC in the Meadowlands

Developer s Guide to LEED NC in the Meadowlands Developer s Guide to LEED NC in the Meadowlands Developer s Guide to LEED NC in the Meadowlands New Jersey Meadowlands Commission Center for Architecture and Building Science Research at NJIT February

More information

Balco, Inc. PC Series Partition Closure Systems

Balco, Inc. PC Series Partition Closure Systems Balco, Inc. PC Series Partition Closure Systems Applicable Rating Systems: CI - Commercial Interiors RETAIL CI - Retail, Commercial Interiors Balco, Inc. PC Series Partition Closure Systems Contributes

More information

One That is Already Built.

One That is Already Built. Montgomery County Planning Board 2009 Growing Smarter Speaker Series Thursday, February 12 th, 2009 Green Building: Today s Practices Tomorrow s Challenges Carl Elefante, FAIA, LEED AP Principal Director

More information

Sustainable Facilities Policy

Sustainable Facilities Policy Sustainable Facilities Policy In response to the Governor s request, as the Chair of the State of Wisconsin Building Commission, to recognize and address the sustainable design and construction of state

More information

University of California, Santa Cruz. Campus Green Building Baseline Narrative

University of California, Santa Cruz. Campus Green Building Baseline Narrative University of California, Santa Cruz Campus Green Building Baseline Narrative Submitted To: University of California Office of the President Facilities Administration Planning, Design and Construction

More information

Matuto. Global Entry Collection. Manufacturer Brand MasterFormat Number. Mohawk Group Hard Surface Resilient Tile Flooring PRODUCT ATTRIBUTES

Matuto. Global Entry Collection. Manufacturer Brand MasterFormat Number. Mohawk Group Hard Surface Resilient Tile Flooring PRODUCT ATTRIBUTES Matuto Global Entry Collection Manufacturer Brand MasterFormat Number Mohawk Group Hard Surface 09 65 19 Resilient Tile Flooring PRODUCT ATTRIBUTES Preconsumer Recycled Content 0.0% Postconsumer Recycled

More information

High Panel - KC129. Karastan. MasterFormat Number: Sheet Carpeting

High Panel - KC129. Karastan. MasterFormat Number: Sheet Carpeting MANUFACTURING / EXTRACTION LOCATIONS Manufacturing Location: Landrum, SC, 29356 PRODUCT ATTRIBUTES Closed Loop / Take Back Program: ReCover Program Recyclable: 100% TVOC Range: 0.5 mg/m3 or less CERTIFICATIONS/LABELS/DECLARATIONS

More information

Green Globes for New Construction Course Number: GBIGGNCFeb16

Green Globes for New Construction Course Number: GBIGGNCFeb16 Columbia Square, Portland OR The Green Building Initiative AIA Provider Number: G478 Green Globes for New Construction Course Number: GBIGGNCFeb16 Date Recorded: 4/26/16 Presenter: Dianne Elliott Kevin

More information

LEED Green Associate Appendix

LEED Green Associate Appendix LEED Green Associate Appendix Green Resource Links: Websites, Publications & Blogs USGBC & GCBI Organizational Chart Six Steps to Certification Flow Chart LEED Rating Systems & Reference Guide Chart Certification

More information

Light Control and LEED

Light Control and LEED Light Control and LEED How light control helps achieve LEED certification in new construction and major renovations of commercial buildings AIA Program Number LCAL10 1.0 Learning Unit HSW/SD Approved by

More information

Energy Reduction Strategy Through 2020

Energy Reduction Strategy Through 2020 Through 2020 Revised: August 2017 Executive Summary Auburn University is a land, sea and space grant university established in 1856. The university consists of 11,629,000 square feet on 1,840 acres and

More information

LEADERSHIP IN ENERGY AND ENVIRONMENTAL DESIGN

LEADERSHIP IN ENERGY AND ENVIRONMENTAL DESIGN LEADERSHIP IN ENERGY AND Leadership in Energy and Environmental Design (LEED) Green Building Rating System is a third-party certification for the design, construction and operation of environmentally friendly

More information

LEED for Homes Project Checklist

LEED for Homes Project Checklist LEED for Homes Project Checklist Builder Name: Project Team Leader: Home Address (Street/City/State): Project Description Adjusted Certification Thresholds Building Type: Project type: Certified: 45.0

More information

Environmental Stewardship Conference October 05, 2013 Energy Water and Sustainability (EWaS) Program

Environmental Stewardship Conference October 05, 2013 Energy Water and Sustainability (EWaS) Program Environmental Stewardship Conference October 05, 2013 Energy Water and Sustainability (EWaS) Program Agenda EWaS Overview History Who is EWaS? Mission EWaS Standards & Tools Energy Efficiency HVAC equipment

More information

Close Up - BC379. Bigelow. MasterFormat Number: Sheet Carpeting

Close Up - BC379. Bigelow. MasterFormat Number: Sheet Carpeting MANUFACTURING / EXTRACTION LOCATIONS Manufacturing Location: Chatsworth, GA 30705 PRODUCT ATTRIBUTES Pre-Consumer Recycled Content: 28% Post-Consumer Recycled Content: 0% Closed Loop / Take Back Program:

More information

BUILDING PERFORMANCE PARTNERSHIP PARTICIPANT HANDBOOK

BUILDING PERFORMANCE PARTNERSHIP PARTICIPANT HANDBOOK BUILDING PERFORMANCE PARTNERSHIP PARTICIPANT HANDBOOK Last Updated April 2012 TABLE OF CONTENTS Overview 1 Section 1 ENERGY STAR s Portfolio Manager (For Commercial Buildings) 2 Sharing Access to Portfolio

More information

An ordinance amending Chapter 52, Administrative Procedures for the Construction Codes,

An ordinance amending Chapter 52, Administrative Procedures for the Construction Codes, 6-28-11 ORDINANCE NO. An ordinance amending Chapter 52, Administrative Procedures for the Construction Codes, Chapter 53, Dallas Building Code, and Chapter 57, Dallas One- and Two-Family Dwelling Code,

More information

Tenant Design and Construction Requirements

Tenant Design and Construction Requirements Tenant Design and Construction Requirements Design Requirements for Selected Proposer The Bruce C. Bolling Municipal Building is carefully designed in close coordination with the Dudley Vision Task Force

More information

NPCA SUSTAINABILITY RESOURCE. Precaster s Guide to. LEED v4. National Precast Concrete Association. 1 PRECASTER S GUIDE TO LEED v4 precast.

NPCA SUSTAINABILITY RESOURCE. Precaster s Guide to. LEED v4. National Precast Concrete Association. 1 PRECASTER S GUIDE TO LEED v4 precast. NPCA SUSTAINABILITY RESOURCE Precaster s Guide to LEED v4 National Precast Concrete Association 1 PRECASTER S GUIDE TO LEED v4 precast.org Precaster s Guide to LEED v4 If you haven t worked on a LEED Leadership

More information

Thermiser Insulated Rolling Doors Comprehensive Guide to Earning LEED v4 Credits

Thermiser Insulated Rolling Doors Comprehensive Guide to Earning LEED v4 Credits Thermiser Insulated Rolling Doors Comprehensive Guide to Earning LEED v4 Credits 1 Thermiser Insulated Rolling Doors Earning LEED v4 Credits Cookson s Thermiser Insulated Rolling Doors can provide a significant

More information

Comparative Analysis of Realized Energy Efficiency for LEED- Designed Building

Comparative Analysis of Realized Energy Efficiency for LEED- Designed Building Comparative Analysis of Realized Energy Efficiency for LEED- Designed Building August 19, 2016 City of Edmonton Office of Energy Management 9744 45 Avenue NW Edmonton Alberta Prepared by: Nafisa Mahbub,

More information

Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal

Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal The following documentation provides an example submittal for the LEED-NC v2.1 Energy & Atmosphere Credit 1 (EAc1). This sample EAc1 submittal

More information

THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS:

THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS: ORDINANCE NO. 18 4 S 7 4 An ordinance adding Division 97 to Article I, Chapter IX and amending Division 4 of Article 8, Chapter IX of the Los Angeles Municipal Code to establish the City of Los Angeles

More information

LEED-EB: How to achieve certification and reduce operating costs. Ed Iczkowski, Managing Member EFI Commissioning Services, LLC

LEED-EB: How to achieve certification and reduce operating costs. Ed Iczkowski, Managing Member EFI Commissioning Services, LLC LEED-EB: How to achieve certification and reduce operating costs Ed Iczkowski, Managing Member EFI Commissioning Services, LLC ABSTRACT LEED-EB is a performance based green building rating system for existing

More information

LEED. Leadership in Energy and Environmental Design

LEED. Leadership in Energy and Environmental Design LEED Leadership in Energy and Environmental Design GREEN BUILDING In years past, the theory of high performance green buildings was hard to define and the practice even more obscure. All of that is rapidly

More information

Sample Energy Benchmarking Report

Sample Energy Benchmarking Report Sample Energy Benchmarking Report SUBMITTED TO: Name Address City, State, Zip Phone SUBMITTED BY: Sample Program Address City, State, Zip Contact: Name Phone Email March 24 th, 2011 Sponsored by [Utility]

More information

Rating System & Addendum. for New Construction & Major Renovations LEED Canada-NC Version 1.0

Rating System & Addendum. for New Construction & Major Renovations LEED Canada-NC Version 1.0 Rating System & Addendum for New Construction & Major Renovations LEED Canada-NC Version 1.0 December 2004 Introduction The Canada Green Building Council (CaGBC) has been officially established as a national

More information

The Use of Green Building Materials in Construction and their Impact on Rating Systems

The Use of Green Building Materials in Construction and their Impact on Rating Systems The Use of Green Building Materials in Construction and their Impact on Rating Systems Natural Habitat Mario Seneviratne FIMechE., PEng., LEED AP (BD+C), LEED Faculty Member, LEED Mentor. Managing Director

More information

Green Building Ordinance Overview

Green Building Ordinance Overview Green Building Ordinance Overview September, 2013 City of Dallas Sustainable Development and Construction Dallas Green Ordinance 2008 Task Force Recommendations Two-phase implementation strategy Solution

More information

LEED v4 Credit Guidance for Andersen Products LEED for Building Design and Construction: Homes and Multifamily Midrise

LEED v4 Credit Guidance for Andersen Products LEED for Building Design and Construction: Homes and Multifamily Midrise LEED v4 Credit Guidance for Andersen Products LEED for Building Design and Construction: Homes and Multifamily Midrise About LEED Certification The U.S. Green Building Council s LEED green building program

More information

LEED for Homes Mid-Rise 2010 Verification & Submittal Guidelines For Verification Teams

LEED for Homes Mid-Rise 2010 Verification & Submittal Guidelines For Verification Teams LEED for Homes Mid-Rise 2010 Verification & Guidelines For Verification Teams These guidelines summarize the verification and submittal requirements for LEED for Homes Mid-Rise. Roles and Responsibilities:

More information

EA PREREQUISITE 2: MINIMUM ENERGY PERFORMANCE Project # SFPUC Administration Office Building

EA PREREQUISITE 2: MINIMUM ENERGY PERFORMANCE Project # SFPUC Administration Office Building LEED 29 for New Construction and Major Renovations EA PREREQUISITE 2: MINIMUM ENERGY PERFORMANCE Project # 1588 SFPUC Administration Office Building All fields and uploads are required unless otherwise

More information

Sustainable Building Operations & Upgrades

Sustainable Building Operations & Upgrades Sustainable Building Operations & Upgrades LEED for Existing Buildings 2010 Energy / Facilities Connections Conference Brightworks & Glumac Eric Baxter and Todd McGuire 12 May, 2010 The Value Proposition

More information

Building a better tomorrow, today

Building a better tomorrow, today Quality health plans & benefits Healthier living Financial well-being Intelligent solutions Building a better tomorrow, today 2013 Aetna Environmental Report www.aetna.com Our values include putting people

More information

Green Ordinance Implementation City of Dallas, TX

Green Ordinance Implementation City of Dallas, TX Green Ordinance Implementation City of Dallas, TX City of Dallas BUILDING INSPECTION DEPARTMENT Phase 1 Effective Date October 1, 2009 Applications for building permits Structure One ordinance amending

More information

The Costs and Benefits of LEED-NC in Colorado

The Costs and Benefits of LEED-NC in Colorado The Costs and Benefits of LEED-NC in Colorado Prepared for the 225 East 16th Avenue, Suite 650 Denver, CO 80203 www.colorado.gov/rebuildco Prepared By Enermodal Engineering, Inc. 1554 Emerson Street Denver,

More information

This presentation provides: An overview of the 2013 version of Green Globes plus Compliance details on the lighting related provisions this

This presentation provides: An overview of the 2013 version of Green Globes plus Compliance details on the lighting related provisions this This presentation provides: An overview of the 2013 version of Green Globes plus Compliance details on the lighting related provisions this sustainability standard 1 This presentation is protected. 2 This

More information

VOL. 2/ DESIGN+ CONSTRUCTION. Group 1 Projects. Building Design and Performance Standards. University of Hawaii at Manoa

VOL. 2/ DESIGN+ CONSTRUCTION. Group 1 Projects. Building Design and Performance Standards. University of Hawaii at Manoa University of Hawaii at Manoa Building Design and Performance Standards VOL. 2/ DESIGN+ CONSTRUCTION Group 1 Projects To be used by Design and Construction Teams [BLANK] Page 2 of 190 UHM BDPS- D+C GROUP

More information

LEED Analysis of the Knight Management Center. Energy & Atmosphere. Materials & Resources

LEED Analysis of the Knight Management Center. Energy & Atmosphere. Materials & Resources LEED of the Knight Management Center Energy & Atmosphere Materials & Resources Energy & Atmosphere: 17 possible points LEED-NC Scorecard LEED for New Construction v2.2 Registered Project Checklist Project

More information

Columbia Skylights may qualify your project for LEED points in the following categories: Columbia Skylights - Potential Contribution to LEED projects

Columbia Skylights may qualify your project for LEED points in the following categories: Columbia Skylights - Potential Contribution to LEED projects 3.0 Statement Columbia Skylights Statement for New Construction (NC) Version 3.0 Credit Documentation The Leadership in Energy and Environmental Design () Green Building Rating System promotes the adoption

More information

Elemental Excellence Brings Monumental Results. sustainable elements

Elemental Excellence Brings Monumental Results. sustainable elements Elemental Excellence Brings Monumental Results sustainable elements OurMission Ragno recognizes that the continued success of our company relies on the well-being of our employees, our communities and

More information

MEP's Letter of Assurance

MEP's Letter of Assurance MEP's Letter of Assurance Instructions WELL Certification is determined by onsite Performance Verification and documentation, including Letters of Assurance from the appropriate professionals overseeing

More information

McCollum Hall Classroom Renovation Project Profile LEED-CI Gold, August 2007

McCollum Hall Classroom Renovation Project Profile LEED-CI Gold, August 2007 Project Highlights McCollum Hall Classroom Renovation Project Profile LEED-CI Gold, August 2007 > 42.7% reduction in potable water usage achieved with high-efficiency low-flow fixtures > 94.6% of the construction

More information