1 Construction Cost Estimate - GATRA / Town of Plymouth Plymouth Intermodal Transit Center Plymouth, MA Prepared for: Fennick McCredie Architecture 65 Franklin Street, Boston, MA June 3, 2015

2 Project Details Basis of Estimate This estimate has been prepared at the request of Fennick McCredie Architecture and is to provide a Schematic Design Cost Estimate for the construction of the proposed intermodal transit center, located in Plymouth, MA. The estimate is based upon measured quantities and built-up rates prepared from the Schematic Design drawings issued to RLB on May 29th, prepared by Fennick McCredie Architecture. Where information was insufficient, assumptions and allowances were made based wherever possible on discussions with the architect and engineers. It is assumed that the project will be competitively bid by four to six general contractors and that the awarded contractor and all subcontractors will be required to pay prevailing wage rates. pricing is based on June 2014 costs. A Design / Estimating Contingency of 10.0% has been included, and Construction Cost Escalation has also been included at 8.0%. s Specifically Included Please refer to estimate detail s Specifically Excluded. Hazardous materials abatement. Excavation in rock and/or contaminated soils. Excavation within ground water table. Removal / relocation of existing utility pole and overhead power. Deep foundation systems. Site utilities diversions and upgrades, unless noted otherwise. Interior fit-out to leasable tenancies (by Tenant). Security systems (none indicated). Costs associated with phasing the works, including out of hours work. Photovoltaics and other renewable energy resources. Furniture, and Equipment (FF&E). Murals and works of art. Special testing & inspections. Utility tap fees and charges. Permits & plan review fees. Construction management fees. Owner's contingency. Construction phase contingency. Land and legal costs. Architectural, Engineering and other professional fees. Geotechnical, traffic and all other studies. s marked as "" in the estimate. Escalation beyond Q Documents Please refer to basis of estimate Page 1 of 47

3 Location Summary GFA: Gross Floor Area Location GFA Cost/ Cost P PUBLIC PARKING B BUSWAY TC TRANSIT CENTER V VISITOR CENTER LSM LSABLE SPACE; MEZZANINE LS2 LSABLE SPACE; LEVEL 2.5 S SITE CONSTRUCTION MARGINS & ADJUSTMENTS Phasing / Temporary Works General Conditions Bonds and Insurances Overhead and Profit Design / Estimating Contingency Escalation - Q ESTIMATED NET COST ESTIMATED TOTAL COST 9.0 % 2.7 % 4.5 % 10.0 % 8.0 % 122, , ,15 1, , , , , $74.29 $ ,542,156 2,593, , , , ,525 1,700,584 $12,784,128 $1,150,572 $376,237 $643,992 $1,495,493 $1,319,578 $17,770,000 Page 2 of 47

4 Divisions/Elements Summary Gross Floor Area: 172,084 Cost/ Cost 02 Existing Conditions G1020 Site Demolition and Relocations G1040 Hazardous Waste Remediation Existing Conditions 7 $7 184,046 $184, Concrete A1010 Standard Foundations A1030 Slab on Grade A2020 Basement Walls B1010 Floor Construction B1020 Roof Construction B2010 C1010 Partitions C1030 C2010 Stair Construction 04 Masonry B2010 C1010 Partitions 05 Metals B1010 Floor Construction B1020 Roof Construction B2010 C1030 C2020 Stair Finishes Concrete Masonry Metals $ $ $ , , ,131 2,379,173 27, , ,560 3,150 12,625 $5,181,842 69,696 36,432 $106, , , ,395 1,196, ,400 $2,209, Wood, Plastics, and Composites B1010 Floor Construction B1020 Roof Construction C1030 Wood, Plastics, and Composites $0.25 9,600 11,000 22,820 $43, Thermal and Moisture Protection A1030 Slab on Grade B1010 Floor Construction B1020 Roof Construction B2010 B3010 Roof Coverings ,752 24,335 26,688 94,450 57,588 Page 3 of 47

5 Divisions/Elements Summary Gross Floor Area: 172,084 Cost/ Cost C1030 D2040 Rain Water Drainage Thermal and Moisture Protection $ ,042 6,510 $319, Openings B2010 B2020 Exterior Windows B2030 Exterior Doors C1010 Partitions C1020 Interior Doors C Finishings B2010 C1010 Partitions C1030 C2020 Stair Finishes C3010 Wall Finishes C3020 Floor Finishes C3030 Ceiling Finishes 10 Specialties C1030 Openings Finishings Specialties $ $ $ , ,560 62,600 12,155 51, ,100 $530,915 22,696 59,408 82,036 14,655 26, ,006 84,481 $407, ,497 $158, Equipment E1030 Vehicular Equipment E1090 Other Equipment Equipment 1.54 $ ,000 $265, Special Construction F1030 Special Construction Systems Special Construction 0.17 $ ,800 $28, Conveying Equipment D1010 Elevators & Lifts Conveying Equipment 1.74 $ ,000 $300, Fire Suppression D4010 Sprinklers Fire Suppression 9 $9 101,943 $101,943 Page 4 of 47

6 Divisions/Elements Summary Gross Floor Area: 172,084 Cost/ Cost 22 Plumbing D2010 Plumbing Fixtures D2020 Domestic Water Distribution D2030 Sanitary Waste D2040 Rain Water Drainage D2090 Other Plumbing Systems Plumbing 23 Heating, Ventilating, and Air Conditioning D3020 Heat Generating Systems D3030 Cooling Generating Systems D3040 Distribution Systems D3090 Other HVAC Systems & Equipment Heating, Ventilating, and Air Conditioning 26 Electrical D5010 Electrical Service & Distribution D5020 Lighting and Branch Wiring D5090 Other Electrical Systems G4010 Electrical Distribution Electrical 27 Communications D5030 Communications & Security 28 Electronic Safety and Security D5030 Communications & Security 31 Earthwork A1010 Standard Foundations A1020 Special Foundations A1030 Slab on Grade G1010 Site Clearing G1030 Site Earthwork 32 Exterior Improvements G2010 Roadways G2020 Parking Lots G2030 Pedestrian Paving Communications Electronic Safety and Security Earthwork $ $ $ $ $ $ ,510 46, ,680 63,711 8,500 $274,186 18,500 56, ,845 21,638 $262, , ,490 68,625 95,988 $541,093 11,000 $11,000 41,725 $41,725 91,716 77,945 20, ,680 $905, ,831 50,000 80,407 Page 5 of 47

7 Divisions/Elements Summary Gross Floor Area: 172,084 Cost/ Cost G2040 G2050 Site Development Landscaping Exterior Improvements $ ,288 6,758 $624, Utilities G1020 Site Demolition and Relocations G3010 Water Supply G3020 Sanitary Water G3030 Storm Sewer G3090 Other Site Mechanical Utilities G4010 Electrical Distribution G4020 Site Lighting MARGINS & ADJUSTMENTS Phasing / Temporary Works General Conditions Bonds and Insurances Overhead and Profit Design / Estimating Contingency Escalation - Q Utilities ESTIMATED NET COST ESTIMATED TOTAL COST 9.0 % 2.7 % 4.5 % 10.0 % 8.0 % $1.67 $74.29 $ ,000 7,700 82, ,010 1,050 29,850 25,000 $287,485 $12,784,128 $1,150,572 $376,237 $643,992 $1,495,493 $1,319,578 $17,770,000 Page 6 of 47

8 Location Divisions/Elements P PUBLIC PARKING GFA: 122,857.0 Cost/: $ Concrete A1010 Standard Foundations 1 Concrete to spread footing; 5,000 psi 2 Concrete to strip footing; 5,000 psi 3 Concrete to grade beam; 5,000 psi 4 Bar reinforcement to spread footing 5 Bar reinforcement to strip footing 6 Bar reinforcement to grade beam 7 Formwork to spread footing 8 Formwork to strip footing 9 Formwork to grade beam Standard Foundations A2020 Basement Walls 23 Concrete to knee wall; 5,000 psi 25 Bar reinforcement to knee wall 27 Formwork to knee wall 42 Allowance for elevator pit Basement Walls B Floor Construction Concrete to topping slab on metal deck; 5,000 psi Mesh reinforcement to topping slab Place and finish topping slab Allowance for joints Precast concrete suspended double tee's Precast concrete column; approx. 36" x 24" Precast concrete column; approx; 36" x 36" Precast concrete lite wall; 12" thick Precast concrete shear wall; 12" thick Precast concrete inverted tee; 36" deep Expansion joint Allowance for miscellaneous toppings, curbs, etc Floor Construction B1020 Roof Construction 41 Precast concrete roof; stair / elevator shaft Roof Construction B Precast concrete spandrel panel; allow 12" thick Lb Lb Lb Lb , ,35 1, , , , , , , , , , , , , $3.19/ , $0/ $17.29/ $0.11/ ,925 59,660 2,090 71,996 37,621 1,315 35,869 17,788 2,790 $392,054 12,635 14,695 26,213 7,500 $61,043 4,066 1,237 2, ,009, ,650 49, , ,050 95,600 41,850 25,230 $2,123,901 13,567 $13, ,425 Page 7 of 47

9 Location Divisions/Elements P PUBLIC PARKING (continued) GFA: 122,857.0 Cost/: $ C C Allowance for precast concrete vertical fins Partitions Precast concrete stair / elevator shaft Reinforced concrete partition wall; allow 8" thick Precast concrete wheelstop Masonry C Metals B B C Partitions CMU Partition; allow 8" thick Floor Construction Structural steel floor framing Metal floor deck; 2" thick Shear studs Base plates and anchor bolts Partitions Concrete Partitions Masonry Allowance for miscellaneous steel, plates, and connections Metal stud exterior wall framing Metal mesh facade screen Floor Construction Architectural vertical metal fin / blade; allow 36" centers (stainless steel) Architectural horizontal fin / blade; allow 24" centers (wood) Metal handrail to spandrel panel Elevator pit ladder Allowance for miscellaneous metals T T , , , , , , , ,92 2, , $6.10/ $2.29/ $0.03/ $29.50/ $0.30/ $0.30/ 4, , $0.90/ $0/ , $9.42/ 111,900 $749, ,400 62,560 $280,960 3,150 $3,150 $3,624,000 36,432 $36,432 $36,432 90,156 5,409 2,706 8,000 4,516 $110,787 12, ,565 $122, , , ,275 1,500 92,142 $1,156,967 Page 8 of 47

10 Location Divisions/Elements P PUBLIC PARKING (continued) GFA: 122,857.0 Cost/: $ C Stair Finishes 4'-0" Wide metal pan stair w/- concrete filled treads and landings, including guardrails Stair Finishes Thermal and Moisture Protection B B B C Floor Construction Metals Spray-applied fireproofing to underside of structural steel framing / metal deck Floor Construction Fiber cement siding Roof Coverings Roofing membrane; stair / elevator Aluminum fascia capping Allowance for miscellaneous trims and flashings Allowance for miscellaneous caulking and sealing Allowance for miscellaneous fire-proofing Openings B C C Exterior Doors Roof Coverings Thermal and Moisture Protection Double leaf fully glazed door, including frame, finish, and hardware Single leaf fire-rated door, including frame, finish, and hardware Exterior Doors Partitions Fixed interior window Interior Doors Double leaf hollow metal door, including frame, finish, and hardware Single leaf hollow metal door, including frame, finish, and hardware Partitions FT/R Pr Pr , , , , , $0.40/ $11.72/ 2.50 $0.04/ $0.16/ $0.04/ $0/ $0.74/ 7, , $0.09/ $0.03/ 3, , ,560 $49,560 $1,440,020 4,508 $4,508 20,236 $20,236 2,713 1, $4,854 30,713 30,713 $61,426 $91,024 7,000 4,000 $11,000 3,575 $3,575 3,000 19,200 Page 9 of 47

11 Location Divisions/Elements P PUBLIC PARKING (continued) GFA: 122,857.0 Cost/: $ Single leaf fire-rated door, including frame, finish, and hardware Interior Doors Finishings B C C C C C C Gypboard wall lining to metal stud framing Partitions Gypboard partition; standard Gypboard partition; fire-rated Allowance for miscellaneous painting Stair Finishes Concrete floor sealer to stair treads and landings Wall Finishes Paint finish to gypboard wall lining Paint finish to CMU partition Floor Finishes Ceramic floor tile; restrooms Ceramic floor tile; ground floor elevator lobby VCT Flooring; parking office Concrete floor sealer; plant rooms, etc Ceramic tile floor base; restrooms Ceramic tile floor base; ground floor elevator lobby Rubber floor base; plant rooms, etc Rubber floor base; parking office Linemarking; parking bays Openings Partitions Stair Finishes Wall Finishes Linemarking; miscellaneous (hatching, logos, arrows, etc) Ceiling Finishes Gypboard ceiling system; restrooms Gypboard ceiling; ground floor elevator lobby Floor Finishes 1 2, , , , , , , , , , $0.38/ $0.49/ 1.50 $0.02/ $0.44/ 0 $0/ 0 $0.02/ $0.17/ $0.47/ ,000 $46,200 $60,775 3,036 $3,036 30,192 24,288 $54,480 61,429 $61,429 2,030 $2,030 16,344 4,858 $21,202 13,472 6, ,410 5,024 2,080 1, ,062 13,500 $58,092 6,736 3,232 Page 10 of 47

12 Location Divisions/Elements P PUBLIC PARKING (continued) GFA: 122,857.0 Cost/: $ ACT Ceiling system; parking office Ceiling Finishes Finishings 10 Specialties C Restroom accessories; toilet partition cubicle (std) 100 Restroom accessories; toilet partition cubicle (ADA) 109 Restroom accessories; urinal partition screen 101 Restroom accessories; grab rail 102 Restroom accessories; toilet tissue dispenser 103 Restroom accessories; sanitary liner dispenser 104 Restroom accessories; sanitary napkin receptacle 105 Restroom accessories; hand dryer 106 Restroom accessories; soap dispenser 107 Restroom accessories; robe hook 108 Restroom accessories; mirror 130 Allowance for concrete filled steel bollards 131 Allowance for fire extinguishers 85 Allowance for interior signage 11 Equipment E1030 Vehicular Equipment Parking equipment; pay station (pay on foot) Specialties Parking equipment; ticket dispenser / pay station Parking equipment; boom gate Vehicular Equipment E1090 Other Equipment 136 Snow melt system - Excluded Other Equipment Equipment 14 Conveying Equipment D1010 Elevators & Lifts 139 Passenger elevator; (4) stop Elevators & Lifts Conveying Equipment , $0.09/ $1.72/ 1, , , $0.99/ $0.99/ 25, , , $0.85/ $0.85/ 120, $0.98/ $0.98/ 680 $10,648 $210,917 4,000 4, ,200 1, , ,150 31,500 7,400 61,429 $122,214 $122,214 75,000 20,000 10,000 $105,000 $105, ,000 $120,000 $120,000 Page 11 of 47

13 Location Divisions/Elements P PUBLIC PARKING (continued) GFA: 122,857.0 Cost/: $ Fire Suppression D Sprinklers 6" DVCA Allowance for backflow preventer assembly Fire department connections 2-1/2" FDV Standpipe, black steel welded - 4" Standpipe drain, black steel threaded - 2" Fire department piping, underground- 4" Sprinkler piping, black steel threaded - assume avg. 1-1/2" Sprinkler head - pendant Allowance for undesigned fire suppression to parking structure offices and storage Sprinklers Plumbing D D D Plumbing Fixtures Water closet - ADA Water closet Urinal Lavatory Allowance for undesigned fixtures - connection only Domestic Water Distribution Domestic water meter - 2" Domestic water fixture rough-in Fire Suppression Plumbing Fixtures Domestic water hot and cold piping, copper type L - 2-1/2" Domestic water hot and cold piping, copper type L - 1" Domestic water hot and cold piping, copper type L - 1/2" Piping insulation Electric water heater, with solenoid shut-off valve - 40 gal, 4.5 Allowance for corresponding equipment - including recirculation pump, expansion tank, air seperator etc Domestic Water Distribution Sanitary Waste Floor drain - 4" Allowance for gas/oil interceptors Allowance for sanitary fixture rough-in , , , , $0.37/ $0.37/ 1, , , , $0.14/ 1, , $0.19/ , ,500 3,750 2,000 15,000 8, ,087 4, ,230 $45,261 $45,261 3,300 4,400 1,000 6,000 2,000 $16, ,900 4,492 3,559 4,468 2,416 2,750 1,500 $23,835 23,400 5,000 2,600 Page 12 of 47

14 Location Divisions/Elements P PUBLIC PARKING (continued) GFA: 122,857.0 Cost/: $ Sanitary and vent piping, cast iron - 4" 420 Sanitary and vent branch piping - assume avg. 2" 422 Garage waste risers, cast iron - 4" Sanitary Waste D2040 Rain Water Drainage 424 Storm drain piping - 4" 306 Storm drain piping - 6" 307 Roof drains - 4" 427 Roof drains - 6" Rain Water Drainage D2090 Other Plumbing Systems 372 Coordination and management 373 Fees and bonds Other Plumbing Systems 23 Heating, Ventilating, and Air Conditioning D3020 Heat Generating Systems 428 Boilers - allowance 125 MBH 429 Boiler hook-ups D3030 Hot water circulation pumps - allowance Expansion tank - allowance Air seperator - allowance Cooling Generating Systems Plumbing Heat Generating Systems 434 Chiller - allowance of 50 tons 435 Chiller hook-ups 436 Chilled water pumps - allowance 437 Pump hook-ups 438 Expansion tank - allowance 439 Air seperator - allowance Cooling Generating Systems D3040 Distribution Systems 431 Pump hook-ups 440 Allowance for ductless split systems - ACC/AC 444 Allowance for refrigerant piping 441 Rooftop condenser - allowance 443 Hot water heaters $0.47/ $0.10/ $0.03/ $0.93/ 5, , , $0.08/ 40, , , $0.23/ , , ,040 2,122 5,832 $57,994 4,152 3,282 3, $11,784 3,000 1,250 $4,250 $114,563 5,000 1,500 2, $9,250 20,000 3,750 3, $28, ,000 3,000 10,000 1,200 Page 13 of 47

15 Location Divisions/Elements P PUBLIC PARKING (continued) GFA: 122,857.0 Cost/: $ Cabinet unit heaters 447 Exhaust fans 448 Allowance for chilled water distribution - assume avg. 1-1/4" 449 Allowance for hot water distribution - assume avg. 1-1/4" 450 Pipework insulation 451 Allowance for ductwork 453 Allowance for diffusers, registers grille - assume 1/200 Distribution Systems D3090 Other HVAC Systems & Equipment 374 Rigging and handling 375 Coordination and management 376 Fees and bonds 377 Temporary heating/cooling Other HVAC Systems & Equipment 26 Electrical D5010 Electrical Service & Distribution 259 Generator - Excluded (not shown) 313 Main switchboard - 1,200 A, 120/208V Main cabinet with meter Distribution panel - 800A, 120/208V Panelboard - 200A, 120/208V Panelboard - 100A, 120/208V Panelboard LCRP - allowance 100A Heating, Ventilating, and Air Conditioning Feeder A Feeder A Feeder A Allowance for power to mechanical charging stations Allowance for mechanical connections Electrical Service & Distribution D5020 Lighting and Branch Wiring 328 Light Fixture Type F1 - LED pendant garage 331 Light Fixture Type F3-4 ft Fluorescent wraparound 332 Light Fixture Type F4-4 ft Fluorescent strip with wireguard 333 Light Fixture Type F5-4 ft LED with occupancy sensor 350 Light Fixture Type F8 - allowance 336 Light Fixture P1- LED double head pole mounted Lb , $0.45/ 0 $0.09/ $0.85/ 18, , , , , , $0.99/ , ,250 11,250 4,500 5, $55,596 5,000 2,000 1,500 2,569 $11,069 $104,165 18,000 5,000 12,000 5,000 3,000 1,500 24,500 13,000 14,490 5,000 20,000 $121,490 37,600 2,200 1,350 7,700 1,400 10,500 Page 14 of 47

16 Location Divisions/Elements P PUBLIC PARKING (continued) GFA: 122,857.0 Cost/: $ D G Light Fixture P1- LED triple head pole mounted Light Fixture - Exit sign Light Fixture - Emergency battery unit with double heads Switches Wiring to lighting points Duplex receptacle Duplex receptacle - GFI Duplex receptacle - GFI, WP Wiring to branch power points Allowance for undesigned lighting, controls and branch power Other Electrical Systems Coordination and management Fees and bonds Temporary power Grounding and bonding Electrical Distribution Lighting and Branch Wiring Other Electrical Systems Allowance for secondary feeder - 3 sets of 4#600KCMIL (4) 4" C Allowance for communication feeder - (2) 4" C only Allowance for feeder to existing building - (4) 4" C only Allowance for feeder to traffic control - (1) 4" C only Communications D Communications & Security Electrical Distribution Allowance for additional communications infrastructure Electronic Safety and Security D Communications & Security Fire alarm - control panel Fire alarm - annunciator Fire alarm - remote alarm indicator Fire alarm - monitor module Fire alarm - control module Electrical Communications & Security Communications , , , , $0.99/ $0.49/ $0.77/ $3.24/ $0.08/ $0.08/ 6, , ,000 4,250 6, , ,200 18,429 $121,264 6,000 2,500 17,208 34,417 $60,125 33,408 7,840 49,840 3,500 $94,588 $397,467 10,000 $10,000 $10,000 3,000 1, Page 15 of 47

17 Location Divisions/Elements P PUBLIC PARKING (continued) GFA: 122,857.0 Cost/: $ Fire alarm - manual pull station 356 Fire alarm - horn/strobe 357 Fire alarm - horn/stobe, WP 360 Fire alarm - smoke detector 363 Wiring to fire alarm points 379 Security Systems - Excluded Communications & Security Electronic Safety and Security 31 Earthwork A1010 Standard Foundations 201 Excavate for foundations 202 Backfill to foundations using excavated materials 200 Remove and dispose spoil from site Standard Foundations A1020 Special Foundations 203 Deep foundation system - Excluded Special Foundations Earthwork 32 Exterior Improvements G2050 Landscaping 234 Trees - Excluded (assume not required) Landscaping Exterior Improvements PUBLIC PARKING , , , $0.12/ $0.12/ $0.37/ $0.37/ $53.25/ , ,500 $14,460 $14,460 17,016 2,838 26,004 $45,858 $45,858 $6,542,156 Page 16 of 47

18 Location Divisions/Elements B BUSWAY GFA: 41,214.0 Cost/: $ Concrete A1010 Standard Foundations 1 Concrete to spread footing; 5,000 psi 2 Concrete to strip footing; 5,000 psi 3 Concrete to grade beam; 5,000 psi 4 Bar reinforcement to spread footing 5 Bar reinforcement to strip footing 6 Bar reinforcement to grade beam 7 Formwork to spread footing 8 Formwork to strip footing 9 Formwork to grade beam Standard Foundations A1030 Slab on Grade 10 Concrete to slab on grade; 5,000 psi (allow 5" thick) 110 Concrete to structural slab on grade; 5,000 psi (allow 7" thick) 11 Bar reinforcement to structural slab on grade 12 Mesh reinforcement to slab on grade 13 Formwork to slab on grade 14 Place and finish slab on grade Allowance for joints Reinforced concrete refuge island A2020 Basement Walls 23 Concrete to knee wall; 5,000 psi 24 Concrete to ramp / retaining wall; 5,000 psi 25 Bar reinforcement to knee wall 26 Bar reinforcement to ramp / retaining wall 27 Formwork to knee wall 28 Formwork to ramp / retaining wall 42 Allowance for elevator pit Slab on Grade Basement Walls B1010 Floor Construction 20 Precast concrete suspended double tee's 111 Allowance for miscellaneous toppings, curbs, etc Floor Construction Lb Lb Lb Lb Lb Lb , ,35 1, , , , , , , , ,07 2, , , , $9.51/ $7.24/ , $7.09/ $5.01/ 162,925 59,660 2,090 71,996 37,621 1,315 35,870 17,789 2,790 $392,056 76,361 44,650 52,144 23,405 8,440 61,821 30, $298,312 12,635 47,500 14,695 55,285 26, ,260 7,500 $292, ,370 5,034 $206,404 Page 17 of 47

19 Location Divisions/Elements B BUSWAY (continued) GFA: 41,214.0 Cost/: $ B C Metals C C Roof Construction Precast concrete roof; stair / elevator shaft Partitions Precast concrete stair / elevator shaft Elevator pit ladder Allowance for miscellaneous metals Stair Finishes Roof Construction Partitions Concrete 4'-0" Wide metal pan stair w/- concrete filled treads and landings, including guardrails Stair Finishes Thermal and Moisture Protection A B C Slab on Grade Vapor barrier (occupied spaces) Rigid insulation; allow 2" thick (occupied space) Roof Coverings Roofing membrane; stair / elevator Aluminum fascia capping Allowance for miscellaneous trims and flashings Allowance for miscellaneous caulking and sealing Allowance for miscellaneous fire-proofing Finishings C Allowance for miscellaneous painting Metals Slab on Grade Roof Coverings Thermal and Moisture Protection FT/R , , , , , , , $0.33/ $6.64/ $35.81/ 1, $0.79/ 1, $1.33/ $2.12/ $0.35/ $0.12/ $0/ $0.97/ 0 $0/ 13,568 $13, ,600 $273,600 $1,476,028 1,500 30,911 $32,411 54,840 $54,840 $87,251 2,400 11,998 $14,398 2,714 1, $4,855 10,304 10,304 $20,608 $39,861 20,607 $20,607 Page 18 of 47

20 Location Divisions/Elements B BUSWAY (continued) GFA: 41,214.0 Cost/: $62.94 C3020 Floor Finishes 128 Linemarking; parking bays 129 Linemarking; miscellaneous (hatching, logos, arrows, etc) Floor Finishes C3030 Ceiling Finishes 241 Exterior grade curved ceiling at transit entrance Ceiling Finishes Finishings 10 Specialties C Allowance for concrete filled steel bollards 131 Allowance for fire extinguishers 85 Allowance for interior signage 11 Equipment E1030 Vehicular Equipment 132 Parking equipment; pay station (pay on foot) Parking equipment; ticket dispenser / pay station Parking equipment; boom gate 14 Conveying Equipment D1010 Elevators & Lifts Specialties Vehicular Equipment Equipment 140 Passenger elevator; (6) stop w/-rear opening doors Elevators & Lifts Conveying Equipment 21 Fire Suppression D4010 Sprinklers 278 6" DVCA 279 Allowance for backflow preventer assembly 280 Fire department connections /2" FDV 282 Fire department piping,underground- 8" 414 Standpipe drain, black steel threaded - 2" 284 Fire department piping, underground- 4" 285 Sprinkler piping, black steel threaded - assume avg. 1-1/2" , , $0.07/ $2/ $1.59/ $0.87/ $0.87/ 25, , , $1.33/ $1.33/ 180, $4.37/ $4.37/ 3, , , , ,562 1,500 $3,062 42,000 $42,000 $65,669 13,500 1,600 20,607 $35,707 $35,707 25,000 20,000 10,000 $55,000 $55, ,000 $180,000 $180,000 1,500 3,750 2,000 3,000 5, ,088 4,380 Page 19 of 47

21 Location Divisions/Elements B BUSWAY (continued) GFA: 41,214.0 Cost/: $ Sprinkler head - pendant Allowance for undesigned fire suppression to parking structure offices and storage Sprinklers Plumbing D D D D Plumbing Fixtures Water closet - ADA Water closet Lavatory Domestic Water Distribution Domestic water meter - 2" Domestic water fixture rough-in Incoming water service, black steel underground - 4" Fire Suppression Plumbing Fixtures Domestic water hot and cold piping, copper type L - 2-1/2" Domestic water hot and cold piping, copper type L - 1" Domestic water hot and cold piping, copper type L - 1/2" Piping insulation Electric water heater, with solenoid shut-off valve - 40 gal, 4.5 Allowance for corresponding equipment - including recirculation pump, expansion tank, air seperator etc Domestic Water Distribution Sanitary Waste Floor drain - 4" Floor cleanout Allowance for gas/oil interceptors Allowance for sanitary fixture rough-in Sanitary piping, underground - 4" Sanitary and vent branch piping - assume avg. 2" Garage waste risers, cast iron - 4" Rain Water Drainage Storm drain piping, underground - 15" Storm drain piping - 4" Storm drain piping, underground - 6" Storm drain piping, underground - 10" Storm drain piping - 6" Sanitary Waste , $0.81/ $0.81/ 1, , , $0.11/ 1, , $0.41/ , $1.32/ ,254 $33,327 $33,327 2,200 1,100 1,200 $4, ,200 2,975 2,519 2,246 1,772 1,238 2,750 1,500 $16,950 5,850 1,600 5, ,180 1,038 2,888 $54,356 7,600 4,153 5,640 17,876 3,283 Page 20 of 47

22 Location Divisions/Elements B BUSWAY (continued) GFA: 41,214.0 Cost/: $ Storm drain piping, underground - 12" 307 Roof drains - 4" 427 Roof drains - 6" Rain Water Drainage D2090 Other Plumbing Systems 372 Coordination and management 373 Fees and bonds Other Plumbing Systems Plumbing 23 Heating, Ventilating, and Air Conditioning D3020 Heat Generating Systems 428 Boilers - allowance 125 MBH 429 Boiler hook-ups Hot water circulation pumps - allowance Expansion tank - allowance Air seperator - allowance Heat Generating Systems D3030 Cooling Generating Systems 434 Chiller - allowance of 50 tons 435 Chiller hook-ups Chilled water pumps - allowance Pump hook-ups Expansion tank - allowance Air seperator - allowance Cooling Generating Systems D3040 Distribution Systems 431 Pump hook-ups 440 Allowance for ductless split systems - ACC/AC 444 Allowance for refrigerant piping 441 Rooftop condenser - allowance 443 Hot water heaters 445 Cabinet unit heaters 447 Exhaust fans 448 Allowance for chilled water distribution - assume avg. 1-1/4" 449 Allowance for hot water distribution - assume avg. 1-1/4" 450 Pipework insulation 451 Allowance for ductwork Lb $1.26/ $0.10/ $3.20/ 5, , , $0.22/ 40, , , $0.69/ , , ,025 3, $51,927 3,000 1,250 $4,250 $131,983 5,000 1,500 2, $9,250 20,000 3,750 3, $28, ,000 3,000 10,000 1, ,250 11,250 4,500 5,796 Page 21 of 47

23 Location Divisions/Elements B BUSWAY (continued) GFA: 41,214.0 Cost/: $ Allowance for diffusers, registers grille - assume 1/200 Distribution Systems D3090 Other HVAC Systems & Equipment 374 Rigging and handling 375 Coordination and management 376 Fees and bonds 377 Temporary heating/cooling Other HVAC Systems & Equipment Heating, Ventilating, and Air Conditioning 26 Electrical D5020 Lighting and Branch Wiring 328 Light Fixture Type F1 - LED pendant garage 329 Light Fixture Type F1A - LED pendant garage 330 Light Fixture Type F2-4 ft LED 331 Light Fixture Type F3-4 ft Fluorescent wraparound Light Fixture Type F4-4 ft Fluorescent strip with wireguard Light Fixture Type F5-4 ft LED with occupancy sensor Light Fixture Type F6 - Elevator pit light Light Fixture Type F7 - LED pendant garage Light Fixture - Exit sign Light Fixture - Emergency battery unit with double heads Switches Wiring to lighting points Duplex receptacle Duplex receptacle - GFI Duplex receptacle - GFI, WP Quad receptacle Wiring to branch power points Allowance for undesigned lighting, controls and branch power Lighting and Branch Wiring D5090 Other Electrical Systems 368 Coordination and management 369 Fees and bonds Other Electrical Systems Electrical 5, , $1.35/ 0 $0.26/ $2.52/ $2.32/ $0.21/ $2.53/ 350 $55,596 5,000 2,000 1,000 2,569 $10,569 $103,665 24,800 14,500 7,650 1,400 4, ,200 2,750 4, , ,600 6,182 $95,657 6,000 2,500 $8,500 $104,157 Page 22 of 47

24 Location Divisions/Elements B BUSWAY (continued) GFA: 41,214.0 Cost/: $ Electronic Safety and Security D5030 Communications & Security 349 Fire alarm - control panel 351 Fire alarm - annunciator 352 Fire alarm - remote alarm indicator 457 Fire alarm - monitor module 353 Fire alarm - control module 354 Fire alarm - manual pull station 355 Fire alarm - strobe 356 Fire alarm - horn/strobe 357 Fire alarm - horn/stobe, WP 358 Fire alarm - knox box 359 Fire alarm - exterior beacon 360 Fire alarm - smoke detector 361 Fire alarm - heat detector 362 Fire alarm - tamper switch, flow switch 363 Wiring to fire alarm points 379 Security Systems - Excluded Communications & Security 31 Earthwork A1010 Standard Foundations 201 Excavate for foundations Electronic Safety and Security Backfill to foundations using excavated materials Remove and dispose spoil from site Standard Foundations A1020 Special Foundations 203 Deep foundation system - Excluded Special Foundations G1030 Site Earthwork 212 Excavate existing fill beneath proposed slab on grade 213 Imported structural fill to building platform 214 Remove and dispose excavated spoil from site Site Earthwork Earthwork , , ,18 3, , , , , $2/ $2/ $1.11/ $4.44/ $5.56/ 3,000 1, , , ,200 9,000 $21,485 $21,485 17,016 2,838 26,004 $45,858 24,424 91,590 67,166 $183,180 $229,038 Page 23 of 47

25 Location Divisions/Elements B BUSWAY (continued) GFA: 41,214.0 Cost/: $ Exterior Improvements G2050 Landscaping 234 Trees - Excluded (assume not required) Landscaping Exterior Improvements 33 Utilities G3030 Storm Sewer 239 Underslab / perimeter drainage; 6" perforated PVC Storm Sewer Utilities BUSWAY $0.75/ $0.75/ $62.94/ 30,760 $30,760 $30,760 $2,593,931 Page 24 of 47

26 Location Divisions/Elements TC TRANSIT CENTER GFA: 1,15 Cost/: $ Concrete A1030 Slab on Grade 10 Concrete to slab on grade; 5,000 psi (allow 5" thick) 12 Mesh reinforcement to slab on grade 13 Formwork to slab on grade 14 Place and finish slab on grade 15 Allowance for joints Slab on Grade Concrete 04 Masonry B CMU Backup to siding; allow 8" thick Masonry 05 Metals B1020 Roof Construction 38 Structural steel roof framing 39 Metal roof deck; 2" thick 40 Allowance for miscellaneous steel, plates, and connections C Allowance for miscellaneous metals 06 Wood, Plastics, and Composites C Allowance for wood blocking / rough carpentry Roof Construction Metals Wood, Plastics, and Composites 07 Thermal and Moisture Protection A1030 Slab on Grade 114 Vapor barrier (occupied spaces) 115 Rigid insulation; allow 2" thick (occupied space) Slab on Grade B1020 Roof Construction 118 Rigid insulation; allow 3" thick T T , ,15 1,15 3, ,15 1,15 1,15 1, $6.68/ $6.68/ $60/ $60/ 4, , $12.19/ 0.75 $0.75/ $12.94/ 1.50 $1.50/ $1.50/ $3.00/ ,401 1, , $7,695 $7,695 69,696 $69,696 $69,696 12, $14, $864 $14,911 1,728 $1,728 $1, ,880 $3, Page 25 of 47

27 Location Divisions/Elements TC TRANSIT CENTER (continued) GFA: 1,15 Cost/: $ B B C Spray-applied fireproofing to underside of structural steel framing / metal deck Roof Construction Fiber cement siding Roof Coverings Roofing membrane; transit center Rigid insulation Aluminum fascia capping Allowance for green roof to transit center Allowance for miscellaneous trims and flashings Allowance for miscellaneous caulking and sealing Allowance for miscellaneous fire-proofing Openings B B C Exterior Windows Fixed window unit Exterior Doors Roof Coverings Thermal and Moisture Protection Exterior Windows Double leaf fully glazed door, including frame, finish, and hardware Single leaf hollow metal door, including frame, finish, and hardware Exterior Doors Interior Doors Single leaf hollow metal door, including frame, finish, and hardware Interior Doors Finishings B Gypboard wall lining on furring to CMU backup Openings Pr , ,15 1, , $1.32/ $33.61/ $6.97/ $0/ $45.40/ $79.38/ 7, , $7.47/ 1, $1.39/ $88.23/ 4.00 $13.44/ 633 $1,519 38,722 $38,722 1, ,280 5, $8, $576 $52,300 91,440 $91,440 7,000 1,600 $8,600 1,600 $1,600 $101,640 15,488 $15,488 Page 26 of 47

28 Location Divisions/Elements TC TRANSIT CENTER (continued) GFA: 1,15 Cost/: $ C1010 Partitions 54 Gypboard partition; standard Partitions C3010 Wall Finishes 57 Paint finish to gypboard wall lining Wall Finishes C3020 Floor Finishes 66 Porcelain floor tile; transit center 65 Concrete floor sealer; plant rooms, etc 72 Porcelain tile floor base; transit center 71 Rubber floor base; plant rooms, etc Floor Finishes C3030 Ceiling Finishes 79 ACT Ceiling system; transit center Ceiling Finishes Finishings 10 Specialties C Allowance for interior signage 11 Equipment E1030 Vehicular Equipment 134 Transit equipment; ticket machine Specialties Vehicular Equipment Equipment 13 Special Construction F1030 Special Construction Systems 137 Interior fit-out and miscellaneous finishes; transit center Special Construction Systems Special Construction 21 Fire Suppression D4010 Sprinklers 277 Allowance for undesigned fire suppression to transit center Sprinklers Fire Suppression , , ,15 1, $4.28/ 1.20 $1.28/ $11.21/ 4.50 $2.21/ $32.43/ 0 $0/ $0/ 35, $91.15/ $91.15/ $25.00/ $25.00/ 2.50 $2.50/ $2.50/ 4,928 $4,928 1,478 $1,478 10, , $12,917 2,543 $2,543 $37, $576 $ ,000 $105,000 $105,000 28,800 $28,800 $28,800 2,880 $2,880 $2,880 Page 27 of 47

29 Location Divisions/Elements TC TRANSIT CENTER (continued) GFA: 1,15 Cost/: $ Plumbing D2010 Plumbing Fixtures 270 Allowance for fixtures to transit center Plumbing Fixtures Plumbing 23 Heating, Ventilating, and Air Conditioning D3040 Distribution Systems 440 Allowance for ductless split systems - ACC/AC 444 Allowance for refrigerant piping 445 Cabinet unit heaters Distribution Systems Heating, Ventilating, and Air Conditioning 26 Electrical D5020 Lighting and Branch Wiring 330 Light Fixture Type F2-4 ft LED 331 Light Fixture Type F3-4 ft Fluorescent wraparound 332 Light Fixture Type F4-4 ft Fluorescent strip with wireguard 339 Light Fixture - Emergency battery unit with double heads 340 Switches 341 Wiring to lighting points 342 Duplex receptacle 343 Duplex receptacle - GFI 344 Duplex receptacle - GFI, WP 345 Quad receptacle 346 Wiring to branch power points 348 Allowance for undesigned lighting, controls and branch power Lighting and Branch Wiring Electrical 27 Communications D5030 Communications & Security 347 Tele/data oultets - conduit and backbox only Communications & Security Communications 28 Electronic Safety and Security D5030 Communications & Security 352 Fire alarm - remote alarm indicator 354 Fire alarm - manual pull station , $4.34/ $4.34/ 6, $7.60/ $7.60/ $9.33/ $9.33/ $0.87/ $0.87/ ,000 $5,000 $5,000 6,000 2, $8,750 $8,750 1,800 1,600 1, , , $10,748 $10,748 1,000 $1,000 $1, Page 28 of 47

30 Location Divisions/Elements TC TRANSIT CENTER (continued) GFA: 1,15 Cost/: $ Fire alarm - horn/strobe 360 Fire alarm - smoke detector 363 Wiring to fire alarm points 379 Security Systems - Excluded Communications & Security Electronic Safety and Security 32 Exterior Improvements G2050 Landscaping 234 Trees - Excluded (assume not required) Landscaping Exterior Improvements TRANSIT CENTER , $2.51/ $2.51/ $391.47/ ,500 $2,895 $2,895 $450,973 Page 29 of 47

31 Location Divisions/Elements V VISITOR CENTER GFA: 1,960.0 Cost/: $ Concrete A1030 Slab on Grade 10 Concrete to slab on grade; 5,000 psi (allow 5" thick) 12 Mesh reinforcement to slab on grade 13 Formwork to slab on grade 14 Place and finish slab on grade 15 Allowance for joints Slab on Grade Concrete 05 Metals B Metal stud exterior wall framing C Allowance for miscellaneous metals Metals 06 Wood, Plastics, and Composites B Floor Construction Architectural exterior column C Allowance for wood blocking / rough carpentry Floor Construction Wood, Plastics, and Composites 07 Thermal and Moisture Protection A1030 Slab on Grade 114 Vapor barrier (occupied spaces) 115 Rigid insulation; allow 2" thick (occupied space) Slab on Grade B Fiber cement siding C Allowance for miscellaneous caulking and sealing , , , , , , , , , , $6.44/ $6.44/ 6.00 $4.90/ 0.75 $0.75/ $5.65/ $1.33/ 1.50 $1.50/ $2.83/ $3.01/ $8.16/ ,738 1, ,940 1,470 $12,626 $12,626 9,595 $9,595 1,470 $1,470 $11,065 2,610 $2,610 2,940 $2,940 $5, ,915 $5,898 15,990 $15, Page 30 of 47

32 Location Divisions/Elements V VISITOR CENTER (continued) GFA: 1,960.0 Cost/: $ Allowance for miscellaneous fire-proofing Openings B C C Exterior Windows Fixed window unit Partitions Aluminum framed storefront system Interior Doors Thermal and Moisture Protection Exterior Windows Partitions Single leaf fully glazed door, including frame, finish, and hardware Interior Doors Finishings B C C C Gypboard wall lining to metal stud framing Wall Finishes Paint finish to gypboard wall lining Floor Finishes Openings Wall Finishes Floor finish to leasable tenancy; excluded (tenant improvement) Floor Finishes Ceiling Finishes Ceiling finish to leasable tenancy; excluded (tenant improvement) Ceiling Finishes Special Construction F Special Construction Systems Finishings Interior fit-out and miscellaneous finishes; leasable tenancy - excluded (tenant improvement) Special Construction Systems Special Construction 1, , , , , , $0/ $11.67/ $21.49/ $4.38/ 4, $4/ $27.91/ 1.50 $1.22/ 1.20 $0.98/ $2.20/ 490 $980 $22,868 42,120 $42,120 8,580 $8,580 4,000 $4,000 $54,700 2,399 $2,399 1,919 $1,919 $4,318 Page 31 of 47

33 Location Divisions/Elements V VISITOR CENTER (continued) GFA: 1,960.0 Cost/: $ Fire Suppression D4010 Sprinklers 285 Sprinkler piping, black steel threaded - assume avg. 1-1/2" 286 Sprinkler head - pendant Sprinklers Fire Suppression 22 Plumbing D2020 Domestic Water Distribution 296 Allowance for branch piping connection for leasable areas Domestic Water Distribution D2030 Sanitary Waste 302 Allowance for branch piping connection for leasable areas Sanitary Waste Plumbing 23 Heating, Ventilating, and Air Conditioning D3040 Distribution Systems 442 Fan coil units -allowance 451 Allowance for ductwork 452 Ductwork insulation Electrical D5010 Allowance for diffusers, registers grille - assume 1/200 Electrical Service & Distribution Distribution Systems Heating, Ventilating, and Air Conditioning 456 Future tenant distribution - Excluded Electrical Service & Distribution D5020 Lighting and Branch Wiring 332 Light Fixture Type F4-4 ft Fluorescent strip with wireguard 338 Light Fixture - Exit sign 339 Light Fixture - Emergency battery unit with double heads 340 Switches 341 Wiring to lighting points 342 Duplex receptacle 346 Wiring to branch power points 348 Allowance for undesigned lighting, controls and branch power Lighting and Branch Wiring Electrical Lb , $3.30/ $3.30/ $2/ $0.15/ $1.17/ 2, $4.44/ $4.44/ $1.92/ $1.92/ 5,340 1,125 $6,465 $6,465 2,000 $2, $300 $2,300 2,000 3,675 1,275 1,750 $8,700 $8,700 1, , $3,769 $3,769 Page 32 of 47

34 Location Divisions/Elements V VISITOR CENTER (continued) GFA: 1,960.0 Cost/: $ Electronic Safety and Security D5030 Communications & Security 352 Fire alarm - remote alarm indicator 354 Fire alarm - manual pull station 356 Fire alarm - horn/strobe 363 Wiring to fire alarm points 379 Security Systems - Excluded Communications & Security Electronic Safety and Security 32 Exterior Improvements G2050 Landscaping 234 Trees - Excluded (assume not required) Landscaping Exterior Improvements VISITOR CENTER 1, $7/ $7/ $68.10/ $1,115 $1,115 $133,476 Page 33 of 47

35 Location Divisions/Elements LSM LSABLE SPACE; MEZZANINE GFA: 1,294.0 Cost/: $ Concrete B1010 Floor Construction 16 Concrete to topping slab on metal deck; 5,000 psi 17 Mesh reinforcement to topping slab 18 Place and finish topping slab 19 Allowance for joints Floor Construction C2010 Stair Construction 96 Reinforced concrete stair on grade (exterior feature entry stair) Stair Construction Concrete 05 Metals B1010 Floor Construction 33 Structural steel floor framing 34 Metal floor deck; 2" thick 36 Allowance for miscellaneous steel, plates, and connections Floor Construction B Metal stud exterior wall framing C Allowance for miscellaneous metals 06 Wood, Plastics, and Composites B1010 Floor Construction 244 Architectural exterior column C1030 Metals Floor Construction 246 Architectural trim / molding at top of columns 82 Allowance for wood blocking / rough carpentry Wood, Plastics, and Composites T T , , , , , , $11.19/ $9.76/ $20.95/ 4, , $106.33/ 6.00 $4.31/ 0.75 $0.75/ $111.39/ $5.40/ $9.85/ $15.25/ 7,296 2,231 3,719 1,240 $14,486 12,625 $12,625 $27, ,956 7,437 6,200 $137,593 5,581 $5, $971 $144,145 6,990 $6,990 10,800 1,941 $12,741 $19,731 Page 34 of 47

36 Location Divisions/Elements LSM LSABLE SPACE; MEZZANINE (continued) GFA: 1,294.0 Cost/: $ Thermal and Moisture Protection B B C Floor Construction Spray-applied fireproofing to underside of structural steel framing / metal deck Floor Construction Fiber cement siding Allowance for miscellaneous caulking and sealing Allowance for miscellaneous fire-proofing Openings B C Aluminum framed storefront system Exterior glazed guardrail (balcony) Exterior glazed guardail (exterior entry stair) Finishings B C C C Gypboard wall lining to metal stud framing Stair Finishes Feature finish to exterior feature entry stair Wall Finishes Paint finish to gypboard wall lining Floor Finishes Wood decking to balcony; leasable tenancy Thermal and Moisture Protection Openings Stair Finishes Wall Finishes Floor finish to leasable tenancy; excluded (tenant improvement) Floor Finishes 2, , , , , $4.79/ $7.19/ $0/ $12.48/ $45.52/ $51.12/ $96.64/ 1.50 $8/ $9.76/ 1.20 $0.86/ $12.46/ 6,197 $6,197 9,301 $9, $648 $16,146 58,900 $58,900 37,800 28,350 $66,150 $125,050 1,395 $1,395 12,625 $12,625 1,116 $1,116 16,125 $16,125 Page 35 of 47

37 Location Divisions/Elements LSM LSABLE SPACE; MEZZANINE (continued) GFA: 1,294.0 Cost/: $ C Ceiling Finishes Exterior grade ceiling system; leasable tenancy (balcony) Ceiling finish to leasable tenancy; excluded (tenant improvement) Ceiling Finishes Special Construction F Special Construction Systems Finishings Interior fit-out and miscellaneous finishes; leasable tenancy - excluded (tenant improvement) Special Construction Systems Fire Suppression D Sprinklers Special Construction Sprinkler piping, black steel threaded - assume avg. 1-1/2" Sprinkler head - pendant Plumbing D D Domestic Water Distribution Sprinklers Fire Suppression Allowance for branch piping connection for leasable areas Sanitary Waste Domestic Water Distribution Allowance for branch piping connection for leasable areas Sanitary piping, underground - 4" Kitchen waste piping, cast iron - 4" Heating, Ventilating, and Air Conditioning D Distribution Systems Fan coil units -allowance Hot water heaters Finned tube radiation Allowance for ductwork Ductwork insulation Sanitary Waste Allowance for diffusers, registers grille - assume 1/200 Plumbing Distribution Systems Heating, Ventilating, and Air Conditioning Lb 1, , , $8.31/ $32.47/ $2.96/ $2.96/ $1.55/ $8.29/ $9.84/ 2, $10.18/ $10.18/ 10,750 $10,750 $42,011 3, $3,825 $3,825 2,000 $2, ,470 1,960 $10,730 $12,730 2, ,500 2, ,050 $13,170 $13,170 Page 36 of 47

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding

More information

SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM)

SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) Construction Criteria The unit costs for the Physical Fitness Center (Exercise Room) space type are based on the construction quality and design features in

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies MasterFormat LEVEL TWO NUMBERS AND TITLES Introductory Information 00001 Project Title Page 00005 Certifications Page 00007 Seals Page 00010 Table of Contents 00015 List of Drawings 00020 List of Schedules

More information

LASALLE - BACKUS EDUCATION CAMPUS

LASALLE - BACKUS EDUCATION CAMPUS INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS USACE / NAVFAC / AFCEC / NASA UFGS-09 06 00 (May 2009) Change 1-11/13 ----------------------------- Preparing Activity: USACE Superseding UFGS-09 06 90 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

CODE COMPLIANCE PLAN REVIEW PROCEDURES

CODE COMPLIANCE PLAN REVIEW PROCEDURES CODE COMPLIANCE PLAN REVIEW PROCEDURES 1. All construction for state agencies on state-owned or state leased-purchased properties or facilities are to submit design documents for code compliance plan reviews

More information

Construction Summary

Construction Summary Construction Summary Project Name Item of Work Base Building Add-ons Total Cost Code Site Development $ 18,150.00 $ - $ 18,150.00 Landscaping $ 500.00 $ - $ 500.00 Cast-in-place Concrete $ 7,806.00 $ -

More information

Property Condition Assessment

Property Condition Assessment Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072

More information

General Conditions 39,522 5, ,292 26,050 75,921 1, Labor hours

General Conditions 39,522 5, ,292 26,050 75,921 1, Labor hours Basic Edition Standard Estimate Report Page 1 Name 1000 General Conditions 1107 Professional Consultant 10 Surveying 1.00 day 600.000 /day 600 - - - - - - 600 Professional Consultant 600 600 8.00 hours

More information

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS St. Louis County Department of Public Works Division of Code Enforcement HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS This guide is intended to provide the homeowner or contractor with the

More information

RESIDENTIAL BUILDING REQUIREMENTS

RESIDENTIAL BUILDING REQUIREMENTS RESIDENTIAL BUILDING REQUIREMENTS Residential Building Requirements This is an informational booklet with some of the general residential construction requirements taken from the codes adopted by Campbell

More information

PLANS REVIEW CRITERIA - COMMERCIAL BUILDINGS

PLANS REVIEW CRITERIA - COMMERCIAL BUILDINGS PLANS REVIEW CRITERIA - COMMERCIAL BUILDINGS NOTE: Building Code compliance is the obligation of design professionals and/or contractors. Plan review and inspection guidelines are to be used to ensure

More information

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

Facilities Condition Assessment Qualcomm Stadium

Facilities Condition Assessment Qualcomm Stadium Qualcomm Stadium Facilities Condition Assessment Qualcomm Stadium Facilities Condition Assessment AECOM San Diego, California April 2011 Qualcomm Stadium Qualcomm Stadium Facilities Condition Assessment

More information

THE CONSTRUCTION SUPERVISOR

THE CONSTRUCTION SUPERVISOR City of Aurora Building Inspections 15151 E Alameda Pkwy Aurora, CO 80012 (303) 739-7420 THE CONSTRUCTION SUPERVISOR When a building permit has been issued for any construction within the City, the Supervisor

More information

Additions and Renovations to Saint Robert Bellarmine Parish Center and Narthex 9/16/14 Outline Design Development Specification

Additions and Renovations to Saint Robert Bellarmine Parish Center and Narthex 9/16/14 Outline Design Development Specification Additions and Renovations to Saint Robert Bellarmine Parish Center and Narthex 9/16/14 Outline Design Development Specification Division 1 Division 2 Division 3 Construction Type Type III B, Not suppressed,

More information

Administrative Changes

Administrative Changes Revised 11/29/06 Knox County Residential Building Codes Significant Changes From The 1995 CABO One And Two Family Dwelling Code To The 2006 International Residential Code All one and two family dwellings

More information

Training Certification Categories

Training Certification Categories Training Certification Categories Residential Residential Building Inspector structures are free from hazardous structural conditions and comply with the UCC. Duties include inspection of footings and

More information

Pembridge The Country Club Collection TOWNHOMES AT CRYSTAL SPRINGS

Pembridge The Country Club Collection TOWNHOMES AT CRYSTAL SPRINGS Pembridge The Country Club Collection TOWNHOMES AT CRYSTAL SPRINGS STANDARD FEATURES LIST Foundation Concrete walls 4 concrete floor slab Interior basement unfinished Standard nine foot foundation walls

More information

Building Inspection Report

Building Inspection Report Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941

More information

MODULAR BUILDING SPECIFICATIONS

MODULAR BUILDING SPECIFICATIONS Use Group A - Assembly B Business E Education I - Institutional Construction Type Type II Non Combustible Type V - Wood Floor 12 Outrigger Frame with Cross members Frame: 12 Perimeter Steel Main Beams

More information

SECTION COOLING TOWER

SECTION COOLING TOWER PART 1 GENERAL 1.1 SECTION INCLUDES A. Mechanical induced draft Cooling Tower B. Controls C. Ladder and handrails 1.2 REFERENCES SECTION 23 65 00 COOLING TOWER A. ANSI/AFBMA 9 - Load Rating and Fatigue

More information

Date Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection

Date Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection Slab on Grade & Basements: A capillary break is installed on top of all footings Slab / Pre-Drywall / Thermal Inspection A minimum of 4" of clean or washed gravel (0.5" diameter or greater) is placed over

More information

Davis Frame Co., Inc. Construction Budget Considerations

Davis Frame Co., Inc. Construction Budget Considerations Davis Frame Co., Inc. Construction Budget Considerations ITEM BID 1 BID 2 BID 3 MISCELLANEOUS COSTS Surveying Building Permit Engineering Fees Interest on Construction Loan Property Taxes Hazard & Liability

More information

KETTERING ICE ARENA STRUCTURAL & MEP STUDY

KETTERING ICE ARENA STRUCTURAL & MEP STUDY KETTERING ICE ARENA STRUCTURAL & MEP STUDY PREPARED BY: HEAPY ENGINEERING MECHANICAL ELECTRICAL COMMISSIONING TECHNOLOGY 1400 WEST DOROTHY LANE DAYTON, OHIO 45409-1310 HEAPY PROJECT NO. 2013-07046 MARCH,

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

One and Two Family Additions

One and Two Family Additions One and Two Family Additions An addition to a house, duplex, garage, or an accessory structure requires a building permit prior to performing any construction. Building Department & Permit Office Mon-Fri

More information

Manufacturing Facilities Proposal

Manufacturing Facilities Proposal Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business

More information

INTERIOR ENVIRONMENT

INTERIOR ENVIRONMENT CHAPTER 12 INTERIOR ENVIRONMENT > SECTION 1201 GENERAL 1201.1 Scope. The provisions of this chapter shall govern ventilation, temperature control, lighting, yards and courts, sound transmission, room dimensions,

More information

John T Pirie Fine Arts & Academic Center ES 650 E 85th St Chicago, IL 60619

John T Pirie Fine Arts & Academic Center ES 650 E 85th St Chicago, IL 60619 E 8th St Chicago, IL 19 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

OFFICE OF EDUCATIONAL FACILITIES FLORIDA BUILDING CODE SECTION 423 APPLICATION MATRIX

OFFICE OF EDUCATIONAL FACILITIES FLORIDA BUILDING CODE SECTION 423 APPLICATION MATRIX 423.1 Scope: Public educational facilities 423.2 Public schools and community colleges general requirements 423.2.1 Owner 423.2.2 Exemption from local requirements 423.2 Code enforcement 423.3.1 School

More information

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good. EAST LYME HIGH SCHOOL Located at 30 Chester Field Road, East Lyme, Connecticut 06333, the High School s original structure was built in 1967. An addition and alterations occurred in 1973. The building

More information

2003 International Residential Building Code

2003 International Residential Building Code 2003 International Residential Building Code Section R305 Ceiling Height Habitable rooms, hallways, corridors, bathrooms, toilet rooms, laundry rooms and basements shall have a ceiling height of not less

More information

Velma F Thomas Early Childhood Center

Velma F Thomas Early Childhood Center Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Jane Addams Elementary School S Avenue H Chicago, IL 60617

Jane Addams Elementary School S Avenue H Chicago, IL 60617 00 S Avenue H Chicago, IL 0 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

The Inspection Process. Waxhaw N.C.

The Inspection Process. Waxhaw N.C. The Inspection Process In Waxhaw N.C. This information is provided by the Waxhaw Enforcement Division to assist you in the progression of your project. Nothing in this document should be considered "Code"

More information

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28-

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28- 1 Metz Elementary School Site Summary Address 84 Robert Martinez Jr. Austin, TX 78702 Number of Permanent Campus Facilities 1 Original Year of Construction 1993 Total Campus Building Area (combined) 61,905

More information

BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018)

BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018) BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018) PERMIT SUBMITTAL CHECKLIST: Signed and completed Building Permit application form. A separate Electrical permit is required from

More information

RESIDENTIAL CONSTRUCTION New Dwellings and Additions

RESIDENTIAL CONSTRUCTION New Dwellings and Additions How to Obtain a Building Permit For RESIDENTIAL CONSTRUCTION New Dwellings and Additions MIAMI COUNTY, KANSAS CODE SERVICES DEPARTMENT 201 South Pearl Street, Suite 201 Paola, Kansas 66071-1777 Phone:

More information

BUILDING CODES & DESIGN CRITERIA

BUILDING CODES & DESIGN CRITERIA BUILDING CODES & DESIGN CRITERIA Adopted Building Codes: 2006 International Building Code (IBC) 2006 International Residential Code (IRC) 2006 International Mechanical Code (IMC) 2006 International Plumbing

More information

THE STRATA UNIT May 25, 2008

THE STRATA UNIT May 25, 2008 THE STRATA UNIT May 25, 2008 Over the years, we have been asked time and time again from our experience as a cost consultant and a project manager from both a restoration and renovation point of view What

More information

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will

More information

CONSTRUCTION AND RENOVATION FUNDED BY THE CFI EXAMPLE OF A DETAILED COST ALLOCATION METHOD

CONSTRUCTION AND RENOVATION FUNDED BY THE CFI EXAMPLE OF A DETAILED COST ALLOCATION METHOD CONSTRUCTION AND RENOVATION FUNDED BY THE CFI EXAMPLE OF A DETAILED COST ALLOCATION METHOD March 2009 CONSTRUCTION AND RENOVATION FUNDED BY THE CFI Prepared For: CANADA FOUNDATION FOR INNOVATION 230 QUEEN

More information

DESIGN DEVELOPMENT PHASE

DESIGN DEVELOPMENT PHASE UNIVERSITY OF MICHIGAN DESIGN DELIVERABLES FEBRUARY 2012 As part of the deliverables for formal UM review at each of the major phases of design listed below, the Design Professional shall submit this "Design

More information

Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING

Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING WWW.STOPWASTE.ORG New Addition Consider the following green remodeling options in a new addition.

More information

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco

More information

Edouard AVANT GROVE U I C U I C. Modern Living Made Easy uichomes.com

Edouard AVANT GROVE U I C U I C. Modern Living Made Easy uichomes.com Edouard Modern Living Made Easy uichomes.com - new construction - 3 stories + full basement - 4 bedrooms - 2.5 baths - 2,380 s.f. call 314.881.2333 or e-mail sales@uicstl.com PLAN NTS DECK 13' 0" X 12'-0"

More information

DIVISION PARKING STRUCTURES

DIVISION PARKING STRUCTURES DIVISION 13 00 40 PARKING STRUCTURES 1. Design Requirements 1.1. A parking design professional must be used to provide the functional and structural design of the facility. 1.2. A traffic analysis is required

More information

School Without Walls

School Without Walls INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

GENERAL PLAN REVIEW REQUIREMENTS

GENERAL PLAN REVIEW REQUIREMENTS GENERAL PLAN REVIEW REQUIREMENTS Cover Letter A letter (or an authorized pre-printed form) authorizing CCIS to perform the Plan Review is required. CCIS performs plan reviews for the ICC International

More information

MATERIAL ALLOWANCES AND UNIT PRICES

MATERIAL ALLOWANCES AND UNIT PRICES PART 1 - GENERAL 1.1 SECTION INCLUDES ADDITIONS AND RENOVATIONS TO WEST YORK AREA HIGH SCHOOL - #1231 SECTION 012200 MATERIAL ALLOWANCES AND UNIT PRICES A. Measurement and payment criteria applicable to

More information

James B Farnsworth Elementary School 5414 N Linder Ave Chicago, IL 60630

James B Farnsworth Elementary School 5414 N Linder Ave Chicago, IL 60630 Linder Ave Chicago, IL 030 Facility Assessment Report This report contains a summary of the results from the facility assessment completed on the date noted in the document footer below. This report will

More information

MINIMUM SPECIFICATIONS

MINIMUM SPECIFICATIONS MINIMUM SPECIFICATIONS A) GREENHOUSE STRUCTURE: (EDUCATOR) 30 X 96 Galvanized Steel Frame Consisting of: A. Column Post: Allied 2 x 4 Rectangle 6 Spacing B. Bows: Allied 2 x 3 Rectangle 6 Spacing C. Trusses:

More information

BASEMENT FINISH CONSTRUCTION PLANS REFERENCE: 2015 INTERNATIONAL RESIDENTIAL CODE. PERMITS

BASEMENT FINISH CONSTRUCTION PLANS REFERENCE: 2015 INTERNATIONAL RESIDENTIAL CODE. PERMITS BASEMENT FINISH REFERENCE: 2015 INTERNATIONAL RESIDENTIAL CODE. PERMITS A construction permit is required. A homeowner may perform the construction work on his own property where he resides, without a

More information

CHARTRES COURT Washington Avenue Houston, Texas ChartresCourtHouston.com CHARTRES COURT LLC

CHARTRES COURT Washington Avenue Houston, Texas ChartresCourtHouston.com CHARTRES COURT LLC CHARTRES COURT 713-868 - 7226 5023 Washington Avenue Houston, Texas 77007 ChartresCourtHouston.com CHARTRES COURT LLC Features Open floor concept living/dining with spacious island kitchen Great master

More information

RESIDENTIAL NEW CONSTRUCTION PLAN REVIEW CHECKLIST

RESIDENTIAL NEW CONSTRUCTION PLAN REVIEW CHECKLIST This list is provided as a guide to help you understand the information that must be contained on the construction drawings. This list is not all-inclusive of all building codes but is used as a general

More information

Property Condition Assessment (PCA) Checklist c:\users\joseph\documents\hhc\blog\pca cklist template.doc Friday, August 11, 2006

Property Condition Assessment (PCA) Checklist c:\users\joseph\documents\hhc\blog\pca cklist template.doc Friday, August 11, 2006 FORUM for Historic Harvard Property Assessment (PCA) Checklist c:\users\joseph\documents\hhc\blog\pca cklist template.doc Friday, August 11, 2006 The purpose of this document is to identify in checklist

More information

Total Building Area: 1964 Construction 30,140 square feet 1976 Construction 36,787 square feet 66,927 square feet

Total Building Area: 1964 Construction 30,140 square feet 1976 Construction 36,787 square feet 66,927 square feet FLANDERS ELEMENTARY SCHOOL Located at 167 Boston Post Road, East Lyme, Connecticut the school s original structure was built in 1964 and replaced the Central Office Building as the elementary school. Two

More information

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Franklin County Septic & Zoning permit application: A septic and zoning permit is required for residential or commercial

More information

10/23/2011. Plan Examination. Plan ExaminationPurpose. Catch problems in advance of construction.

10/23/2011. Plan Examination. Plan ExaminationPurpose. Catch problems in advance of construction. Plan Examination 1 Plan ExaminationPurpose 2 Catch problems in advance of construction. 3 1 Discovery of problems in the field results in higher cost. 4 Can a good plan review eliminate all problems in

More information

BUREAU Joe Iuviene, AIA January 20, 2017

BUREAU Joe Iuviene, AIA January 20, 2017 architectural BUREAU Joe Iuviene, AIA January 20, 2017 Alterations & Additions NEW TOWN HALL for TOWN OF AUSTERLITZ 816 State Route 203, Spencertown, New York 12165 ADDENDUM NO. 1 This addendum amends

More information

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW 27 September 2007 prepared by: J. CHRIS EVANS ARCHITECT 3220 E. Terra Alta Blvd. No. 9 Tucson, Arizona 85716 520.319.8835 evansarch@hotmail.com

More information

Facility Improvements

Facility Improvements CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Seasons Business Center New Construction!

Seasons Business Center New Construction! Seasons Business Center New Construction!...Seasons Business Center Stow, Ohio 114,188 SF of High Bay Space 32 Clear Height 80 480 ESFR Sprinklers Tax Abatement Available 8 Reinforced Concrete Floor 271

More information

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT 1 East Franklin Street Phone: 301-790-4163 Third Floor Hagerstown, MD 21740 Fax: 301-791-2650 BUILDING PERMIT APPLICATION FOR RESIDENTIAL ACCESSORY

More information

1. Unified Facilities Criteria - Design: General Building Requirements (UFC ).

1. Unified Facilities Criteria - Design: General Building Requirements (UFC ). 1. GENERAL GUIDANCE REGARDING DESIGN A. Commissary facilities are Department of Defense (DoD) projects, and as such must be constructed in accordance with the following criteria, codes, and standards.

More information

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information

More information

PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION

PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION Permit No. 175 Beaver Drive, P.O. Box 486 DuBois, PA 15801 Phone: 814-375-1111 Fax: 814-375-1117 Toll Free: 855-PENNSAF LOCATION OF PROPOSED

More information

3D Home Improvement and Inspection Services, Inc

3D Home Improvement and Inspection Services, Inc Property Inspection Report Cover Page ABC Disney Lane, Winter Garden FL, 34787 Inspection prepared for: John Doe Inspection Date: 7/15/2010 Time: 11:00 am Age: 6 Years Size: 3,378 LSF / 4,427 TSF Weather:

More information

The facility is approximately 439,350 square feet, located on a acre parcel on Wood Dale Road in Wood Dale, Illinois. 439,350 Square Feet

The facility is approximately 439,350 square feet, located on a acre parcel on Wood Dale Road in Wood Dale, Illinois. 439,350 Square Feet 1.0 DESIGN SPECIFICATIONS 1.1 Size of Building and Tract: The facility is approximately 439,350 square feet, located on a 21.86-acre parcel on Wood Dale Road in Wood Dale, Illinois. 1.2 Size of Building

More information

SECTION BASIC ELECTRICAL MATERIALS AND METHODS

SECTION BASIC ELECTRICAL MATERIALS AND METHODS SECTION 26 05 05 BASIC ELECTRICAL MATERIALS PART 1 - GENERAL 1.1 SUMMARY A. Section includes the limited scope construction materials and methods for application with electrical installations as follows:

More information

DeKalb County School District/Stadiums Avondale Stadium Final School Assessment Report May 20, 2016

DeKalb County School District/Stadiums Avondale Stadium Final School Assessment Report May 20, 2016 DeKalb County School District/Stadiums Avondale Stadium Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition Summary

More information

Continuing Certificate of Occupancy Pre-Inspection Checklist

Continuing Certificate of Occupancy Pre-Inspection Checklist Pre-Inspection Checklist INTRODUCTION: This pre-inspection checklist has been produced to assist you in preparing for a Continuing Certificate of Occupancy (CCO) inspection. The inspection criteria and

More information

Electric Service Standards

Electric Service Standards V: 1 of 6 A. Padmounted Requirements Complete requirements are contained in FPL specifications given to Customers for individual projects. Typical pad mounted transformer requirements include, but are

More information

MSBA Designer Services Contract Amendment for DBB v Page 1

MSBA Designer Services Contract Amendment for DBB v Page 1 7.5 Design Development Phase 7.5.1 Upon receipt of an Approval to proceed to the Design Development Phase, the Designer shall meet regularly and as necessary with the Owner, the OPM, and the Authority.

More information

Mount Vernon Elementary School Grades PK 5

Mount Vernon Elementary School Grades PK 5 Barbour County Schools Comprehensive Educational Facilities Plan 2010-2020 Mount Vernon Elementary School Grades PK 5 Blackwood Associates, Inc. / MSES consultants, Inc. / Roy Blizzard and Associates Mount

More information

SECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows:

SECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows: SECTION 16130 (Master Template Final-05) ELECTRICAL BOXES PART 1 GENERAL 1.01 SECTION INCLUDES A. Provide boxes for electrical equipment and wiring devices as follows: 1. Wall and ceiling outlet boxes.

More information

Design & Construction Standards, Revised January

Design & Construction Standards, Revised January PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is

More information

HURON PUBLIC WORKS BUILDING HURON, SOUTH DAKOTA BID NO R

HURON PUBLIC WORKS BUILDING HURON, SOUTH DAKOTA BID NO R HURON PUBLIC WORKS BUILDING HURON, SOUTH DAKOTA BID NO. 2017-26R Stone Group Architects Project No. 1731 ADDENDUM DATE: September 14, 2017 BID DATE: September 18, 2017 2:00 P.M. C.S.T. SCOPE OF THIS ADDENDUM:

More information

The following is required for a complete permit submittal for each unit.

The following is required for a complete permit submittal for each unit. P: (847)810-3502 OR (847)810-3503/3521, F: (847)615-4383 MULTI-FAMILY OR COMMERCIAL ADDITION OR ALTERATION PERMIT REQUIREMENTS The following is required for a complete permit submittal for each unit. MULTI-FAMILY

More information

TOWNSHIP OF LOGAN 125 MAIN STREET, PO BOX 314 BRIDGEPORT, NJ FAX

TOWNSHIP OF LOGAN 125 MAIN STREET, PO BOX 314 BRIDGEPORT, NJ FAX TOWNSHIP OF LOGAN 125 MAIN STREET, PO BOX 314 BRIDGEPORT, NJ 08014 856-467-3626--- FAX 856-467-9260 Application for Certificate of Occupancy for Change of Occupancy Pursuant to Chapter 119 of the Township

More information

Meriter Heights Renovations Madison, Wisconsin

Meriter Heights Renovations Madison, Wisconsin Urban Design Submittal s 12 ebruary 2007 Owner Developer W. Mifflin St. STATE CAPITOL SQUARE Meriter Retirement Services, LLC 333 West Main Street 53703 W. Washington Ave. S. airchild St. STATE CAPITOL

More information

e a s t 2303 Dulles Station Blvd., Herndon, VA BASE BUILDING SPECS

e a s t 2303 Dulles Station Blvd., Herndon, VA BASE BUILDING SPECS DULLES STATION EST. e a s t 2000 2303 Dulles Station Blvd., Herndon, VA BASE BUILDING SPECS Narrative: 2303 Dulles Station Blvd (Dulles Station East) is a modern six story office building located in the

More information

Applying for Permits to build a new house in Linn County

Applying for Permits to build a new house in Linn County Planning & Development Linn County, Iowa Building Division Linn County Building Code Residential Guidelines Single Family Dwellings Page 1 of 4 Applying for Permits to build a new house in Linn County

More information

LEWIS ELEMENTARY SCHOOL

LEWIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Building Codes and Ordinances ARC 227

Building Codes and Ordinances ARC 227 Building Codes and Ordinances ARC 227 Week 6 Fire Resistive Construction 03.02.10 Instructor: Rick Staub, AIA Email: staub@pointonearchitects.com Phone: 860-434-7707 Fire Resistive Construction Passive

More information

DRAFT. Baker Center Special Campus Site Summary 64,153 SF. Introduction

DRAFT. Baker Center Special Campus Site Summary 64,153 SF. Introduction 1 Baker Center Special Campus Site Summary Address 3908 Avenue B Austin, TX 78751 Number of Permanent Campus Facilities 3 Original Year of Construction 1911 Total Campus Building Area (combined) 64,153

More information

STRUCTURAL ABBREVIATIONS S-001 GENERAL NOTES CONCRETE MASONRY NOTES DESIGN NOTES SOF NSWG-10 UAS SUPPORT FACILITY FY 2016 MILCON P-225

STRUCTURAL ABBREVIATIONS S-001 GENERAL NOTES CONCRETE MASONRY NOTES DESIGN NOTES SOF NSWG-10 UAS SUPPORT FACILITY FY 2016 MILCON P-225 GENERAL NOTES DESIGN NOTES (CONTINUED) FOUNDATION NOTES STRUCTURAL ABBREVIATIONS CONCRETE MASONRY NOTES DESIGN NOTES S-001 CONCRETE NOTES COLD-FORMED STEEL FRAMING NOTES PRE-ENGINEERED METAL BUILDING NOTES

More information

CANNING WAREHOUSE CANNERY DISTRICT BOZEMAN, MT

CANNING WAREHOUSE CANNERY DISTRICT BOZEMAN, MT CANNING WAREHOUSE CANNERY DISTRICT BOZEMAN, MT DESIGN DEVELOPMENT CQ + MA 100% DD Set 04-28-2015 Canning Warehouse CQ + MA 04-28-2015 Canning Warehouse EXISTING CONDITIONS CQ + MA 04-28-2015 Canning Warehouse

More information

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5 Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00

More information

TEXAS A&M ENGINEERING

TEXAS A&M ENGINEERING TEXAS A&M ENGINEERING 312 Jack K. Williams Administration Building I 3126 TAMU I College Station, Texas 77843-3126 M. Katherine Banks, Ph.D., P.E. Vice Chancellor and Dean of Engineering Director, Texas

More information

Planning for Biomed Facility Puts Energy Efficiency Under Microscope

Planning for Biomed Facility Puts Energy Efficiency Under Microscope Planning for Biomed Facility Puts Energy Efficiency Under Microscope Chilled beams, runaround-loop ERV system included May 19, 2014 By DAN VASTYAN, Common Ground, Manheim, Pa. HPAC Engineering Constructing

More information

Estimate Form for Bathroom Design and Installation

Estimate Form for Bathroom Design and Installation Estimate Form for Bathroom Design and Installation Name: Home Address: City: State: Phone (Home): Phone (Office): Phone (Office): Phone (Office): Phone (Jobsite): Jobsite Address: City: State: By: Hereafter

More information

Office of Design & Construction State University Plaza Albany, New York

Office of Design & Construction State University Plaza Albany, New York Instructions: Consultant should meet with the Campus and Fund at the work area(s) prior to completing this Checklist. At least two (2) meetings are required, one prior to Schematic Phase submission and

More information