1 Riverbank Stabilization Techniques Workshop Merrimack River, Haverhill, MA Dwight R. Dunk, PWS Association of Massachusetts Wetland Scientists September 30, 2011
2 Introduction Project History Design Development Environmental Permitting
3 Project History 1996 bank stabilization design was advanced Used coir fascines and bank planting Construction problems led to abandoning this effort 2001 City partnered with Corps of Engineers Design used rock rip rap slope to 10-year flood elevation Discretionary EIR required because of habitat loss Project abandoned
4 Project History (Continued) May 2006 Mother s Day Storm caused erosion on southern bank and broke sewer interceptor discharging raw sewage in to the Merrimack River Mother s Day Storm caused about 10 feet of erosion on Riverside Avenue northern bank Problem 54 inch sewer in Riverside Avenue Erosion at Coffin Ave observed Problem - sewer, sewage pump station and related infrastructure in Coffin Avenue
5 Project History (Continued) Riverside Ave. washout Coffin Ave. washout
6 Project History (Continued) City of Haverhill applied for and received MEMA Flood Hazard Mitigation Grant to stabilize up to 1,800 linear feet of Merrimack River bank to protect public infrastructure. Approval received in December 2006
7 Eroded Conditions
8 Existing Conditions Analysis Topographic survey Field inspection by design staff Assess causes of erosion
9 Existing Conditions Analysis
10 Design Development Site Constraints: 54-inch Sewer Interceptor Riverside Avenue
11 Design Development (Continued) Reviewed previous bank stabilization plan documents Assessed pros and cons of each design Entirely rip rap slope Entirely soft slope Identified ways to protect and enhance habitat Evaluated agency acceptance of each option Identified preferred option
12 Design Development (Continued) Developed conceptual bank profiles and treatments Pre-Application Meeting - Met and conferred with agency staff (Corps of Engineers, MEPA, MassDEP, NHESP, Haverhill Conservation Commission Agent) Revised drawings and advanced to +60% design stage and pursue required permits and approvals Incorporated permit conditions into contract drawings and specifications
13 ~ 30% Design Drawing
14 Aquatic Plantings Stumps & Logs Erosion Control Matting Temporary Portable Dam Coir Fascines & Live Stakes Stone Toe
15 Planting Schedule
16 Techniques & Function Design elements and purpose 1. Stone toe slope foundation, support, and debris protection 2. Coir fascines slope stabilization, plant media and debris protection 3. Live stakes toe of slope vegetation and bank stabilization 4. Turf reinforcement matting slope stabilization during plant grow-in 5. Coarse woody debris in-river wave breaks and fish habitat 6. Rooted aquatic vegetation fish habitat and sediment trap 7. Slope vegetation slope stabilizations and habitat 8. Drainage scuppers direct runoff to river in stabilized channels rather than over bank flow
17 Designer s Challenges Landscaping projects are as much an art as science (or engineering). Challenge is to prepare plans that convey design intent and still allow for field modifications. 1. Riverbank is a dynamic landform existing conditions can and will change from topographic survey to construction start 2. Public bid projects designer doesn t dictate means and methods, rather prepares performance specifications 3. Balance needed - to protect static, man-made infrastructure and incorporate natural bank characteristics
18 Environmental Permitting Approvals included: Massachusetts GP Category 2 Approval Corps of Engineers MEPA Certificate Section 401 Water Quality Certification MassDEP Chapter 91 License MassDEP Order of Conditions - Haverhill Conservation Commission
19 Environmental Permitting (Continued) Key success factors: Pre-Application meeting with concept plan Incorporate comments from pre-application meeting and advance design to preliminary design stage Pursue MEPA review with preliminary design Incorporate comments on ENF into permitting plans, +60% design stage Communicate with agency staff throughout process
20 Bank Construction SumCo Eco Contracting was selected contractor There were changes during construction Method work with tides and avoid using temporary portable dam Sub-soil type - slope angle and improved drainage Synthetic Turf Reinforcement Matting (TRM) seasonal adjustment
21 Acknowledgements CDM Team: Lisa Gove, PE Project Manager John Olcott, RLA Lead Designer Ron Strand, PE Lead Engineer Joe Coan and Josh Coroa Landscape Designers Andrew Poyant Environmental Scientist Eric Dahlgren Resident Engineer City of Haverhill Paul Jessel Conservation Commission MEMA
Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)
Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department
More informationAppendix D - Evaluation of Interim Solutions
Appendix D - Evaluation of Interim Solutions D.1 Introduction The implementation of long-term improvements is projected to take 5 to 8 years. To reduce the number of years of flooding impacts, the partner
More informationCoal Combustion Facility Assessment Report. October 20, 2010
Coal Combustion Facility Assessment Report October 20, 2010 Introduction Stantec Consulting Services Inc. North American Consulting Firm 10,000 Engineers, Geologists, Architects, Scientists and Technicians
More informationCHAPTER 6 ADDITIONAL STANDARDS APPLYING TO SHORELAND AREAS AND PUBLIC WATERS
CHAPTER 6 ADDITIONAL STANDARDS APPLYING TO SHORELAND AREAS AND PUBLIC WATERS Section 1 Intent. 49 Section 2 Floodplain Requirements 49 Section 3 Water-Oriented Accessory Structures 50 Section 4 Stairways,
More informationAPPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports
APPENDIX H H.1 Guidance for Preparing and Reviewing CEQA Initial Studies Step 1: Consider the Project Characteristics as Provided by the Project Applicant Review the project application and draft plan
More informationPonds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.
POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made
More informationSOUTH FLORIDA WATER MANAGEMENT DISTRICT. Question 13: Wetlands
SOUTH FLORIDA WATER MANAGEMENT DISTRICT Question 13: Wetlands 1. The wetland responses and topographical data provided in the ADA for the 520- acre project site are conceptual in nature. The referenced
More informationCHAPTER 7. San Dieguito River Flooding Adaptation
CHAPTER 7 San Dieguito River Flooding Adaptation This chapter includes a range of adaptation measures to address vulnerabilities from flooding along the San Dieguito River, including the river valley,
More informationBethel Bank Stabilization
Bethel Bank Stabilization Condition of Improvements 30 December 2014 Bethel Bank Stabilization, Alaska (CWIS No. 012314, 075440) Authorization Public Law 99-662, under Section 202, 17 November 1986, as
More informationErosion & Sedimentation Control Policy
Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of
More informationE. STORMWATER MANAGEMENT
E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson
More informationS.O.P. No. HMD
Page: 1 of 9 PURPOSE: To establish (SOP) for submission requirements, review process and approval of applications for Non-vehicular Access Permits for the purpose of connection or discharge to any MassDOT
More informationElements of the Storm Water Management Plan. Storm Water Pollution Prevention Plan (SWPPP)
Elements of the Storm Water Management Plan Storm Water Pollution Prevention Plan (SWPPP) Small Construction Site Storm Water Management Rodney Hendrick Water Quality Specialist LSU Ag Center Plan Requirements
More informationSOS. City of Akron Combined Sewer Overflow (CSO) Long Term Control Plan. Separate Our Sewers Save Our Streams. Ohio OWEA Collection Systems Workshop
City of Akron Combined Sewer Overflow (CSO) Long Term Control Plan SOS Separate Our Sewers Save Our Streams Ohio OWEA Collection Systems Workshop Patrick Gsellman Genny Hanna Jim Hall Thursday, May 9,
More informationNew Castle County, DE. Floodplain Regulations
New Castle County, DE Floodplain Regulations John J. Gysling, PE CFM Department of Land Use New Castle County, DE February 26, 2009 Today s Presentation Floodplain Protection and Uses Terms and Definitions
More informationGOALS, OBJECTIVES, & POLICIES
ELEMENT 9 INFRASTRUCTURE ELEMENT STORM WATER MANAGEMENT SUB-ELEMENT Goal 1 To provide adequate stormwater management facilities and services to meet the present and future needs of the University and to
More informationConstructed Wetland Channel T-9
Description A constructed wetland channel is a conveyance BMP that is built, in part, to enhance stormwater quality. Constructed wetland channels use dense vegetation to slow down runoff and allow time
More informationNEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL
NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by
More informationSECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements
SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature
More informationConstructed Wetland Use in Nonpoint Source Control
Constructed Wetland Use in Nonpoint Source Control Description Constructed wetlands are excavated basins with irregular perimeters and undulating bottom contours into which wetland vegetation is purposely
More informationPreface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF)
Preface In 2008, the inter-agency Drainage Act & Section 28 Regulations Team (DART) was established by the Ministry of Natural Resources (MNR) and the Ministry of Agriculture, Food and Rural Affairs (OMAFRA)
More informationPART 1 GENERAL REQUIREMENTS
PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...
More information901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL
SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL 901.1 DESCRIPTION Install, maintain and remove temporary erosion and pollution control devices as required during the construction of the project. BID
More informationCHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS
CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS 8.1 INTRODUCTION To minimize the detrimental effects of erosion and sedimentation, Henrico County requires that those individuals responsible for
More informationJEFFERSON COUNTY STORM WATER MANAGEMENT
JEFFERSON COUNTY STORM WATER MANAGEMENT B-210 Courthouse, Birmingham, Alabama 35203 Telephone: (205) 325-8741 Erosion and Sedimentation Control Measures for Commercial Projects (Plans Requirements) -All
More informationRichland County Department of Public Works Engineering (Land Development) Division
Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or
More informationSTONE OAK DAM: TO BREACH OR NOT TO BREACH, THAT IS THE QUESTION. TFMA Spring Conference 2013
STONE OAK DAM: TO BREACH OR NOT TO BREACH, THAT IS THE QUESTION TFMA Spring Conference May 23, 2013T F M A Spring Conference 2013 INTRODUCTIONS ALYSHA GIRARD, P.E., CFM Storm Water Program Manager City
More informationStandards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose
STANDARD FOR GRASSED WATERWAYS Definition A natural or constructed watercourse shaped or graded in earth materials and stabilized with suitable vegetation for the safe conveyance of runoff water. Purpose
More informationMODEL Stormwater Local Design Manual. City of Centerville
MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge
More informationPRINCESS ANNE DISTRICT STORMWATER PROJECTS
PRINCESS ANNE DISTRICT STORMWATER PROJECTS Topics o o o o o Sea Level Rise and the Southern Watersheds Ashville Park Sherwood Lakes Kingston Estates Drainage Operations & Maintenance in the Southern Watersheds
More informationApplication For Waste Regulation (Check all that apply)
Environmental Protection and Growth Management Department ENVIRONMENTAL ENGINEERING AND PERMITTING DIVISION 1 North University Drive, Mailbox #201 Plantation, Florida 33324 954-519-1483 FAX 954-519-1412
More informationVIDEO: Riparian Forest Buffers: The Link Between Land & Water
VIDEO: Riparian Forest Buffers: The Link Between Land & Water Introduction to Riparian Buffers Adapted from: Riparian Forest Buffers: The Link Between Land & Water. Maryland Cooperative Extension. Wye
More informationSTATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT
STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED LESTER PRAIRIE WASTEWATER TREATMENT FACILITY EXPANSION
More informationPUBLIC NOTICE. REPLY TO: Denver Regulatory Office 9307 South Wadsworth Blvd 30 DAY NOTICE Littleton, CO FAX (303)
PUBLIC NOTICE US Army Corps of Engineers Omaha District Application No: NWO-2017-01366-DEN Project: Douglas Lane Tributary Stabilization Project Applicant: Town of Castle Rock Waterway: Douglas Lane Tributary
More information10:00 AM, Wednesday, April 8, 2015
NOTICE OF MANDATORY PRE-BID CONFERENCE WILL BE HELD AT 10:00 AM, Wednesday, April 8, 2015 IN ROOM 16, CITY HALL BUILDING, 101 NORTH MAIN STREET WINSTON-SALEM, NORTH CAROLINA The purpose of this conference
More informationStandards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition
STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm
More informationSolutions to riverbank erosion: A summary of current shoreline stabilization techniques for the Gull River in Minden, Ontario.
Solutions to riverbank erosion: A summary of current shoreline stabilization techniques for the Gull River in Minden, Ontario. Report by: Michael Kosiw, Kennetha Parks, and Skyler Besley Report Completed:
More informationGUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK
PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the
More informationSECTION TRENCHING & BACKFILLING
SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications
More informationNOTICE OF PREPARATION
NOTICE OF PREPARATION Date: June 12, 2014 To: From: Subject: Governor s Office of Planning and Research/State Clearinghouse Unit, Responsible Agencies, Trustee Agencies, and Interested Parties Announcement
More informationNiagara Falls Storage Site Safety Measures During Remediation
Niagara Falls Storage Site Safety Measures During Remediation On-Site Worker Protection Community and Environmental Protection Transportation and Disposal Safety Fully enclosed Retrieval Facility Regular
More informationExtended Detention Basin Maintenance Plan for [[== Insert Project Name ==]]
Extended Detention Basin Plan for [[== Insert Project Name ==]] [[== Insert Date =]] Project Address and Cross Streets Assessor s Parcel No.: Property Owner: Phone No.: Designated Contact: Phone No.: Extended
More informationStormwater Local Design Manual For Houston County, Georgia
Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.
More informationPERFORMANCE STANDARDS AND MONITORING PROTOCOL FOR TIDAL WETLAND MITIGATION BANKS. October 28, 2016
PERFORMANCE STANDARDS AND MONITORING PROTOCOL FOR TIDAL WETLAND MITIGATION BANKS October 28, 2016 A. Tidal wetland mitigation banks shall conform to the following performance standards by the end of the
More informationSANTA ANA RIVER/ SAN TIMOTEO CREEK 1 LEVEE SYSTEM SAN BERNARDINO COUNTY, CALIFORNIA NLD SYSTEM ID #
SANTA ANA RIVER/ SAN TIMOTEO CREEK 1 LEVEE SYSTEM SAN BERNARDINO COUNTY, CALIFORNIA NLD SYSTEM ID # 3805030015 PERIODIC INSPECTION REPORT NO. 1 GENERALIZED EXECUTIVE SUMMARY FINAL SYSTEM RATING: UNACCEPTABLE
More informationUNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report
UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report Prepared for: Cameron McCarthy Landscape Architects LLP
More informationMaryland s Living Shorelines Program. Bhaskaran Subramanian February 27, 2015
Maryland s Living Shorelines Program Bhaskaran Subramanian February 27, 2015 1 Erosion & traditional approaches Living shorelines- what is it? Maryland s Living Shorelines program LS Law Products Funding-
More informationDesign Features of Constructed Wetlands for Nonpoint Source Treatment. September 1995
Design Features of Constructed Wetlands for Nonpoint Source Treatment September 1995 Brochure written by William W. Jones, School of Public and Environmental Affairs, Indiana University, Bloomington, Indiana.
More informationUMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist
UMD Storm Water Program Construction Requirements Greg Archer, MBA Environmental Compliance Specialist Phase 2 Regulatory Overview Dec. 1999 EPA issues Phase 2 Federal Register Municipalities (MS4) from
More informationTexas Department of Transportation Book 2 - Technical Provisions. IH 35E Managed Lanes Project. Attachment 4-3
Texas Department of Transportation Book 2 - Technical Provisions IH 35E Managed Lanes Project Attachment 4-3 Form 2448 IH 35E Managed Lanes Project Book 2 - Technical Provisions Attachment 4-3 Show Form
More informationTABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS...
TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... 4.17-1 4.17.0 Introduction... 4.17-1 4.17.1 Methodology... 4.17-2 4.17.2 Existing Conditions... 4.17-2 4.17.3 Impacts... 4.17-4 4.17.4 Applicant-Proposed
More informationEconomics of Implementing Two-stage Channels
2011 A Partnership of USDA NIFA & Land Grant Colleges and Universities Economics of Implementing Two-stage Channels GREAT LAKES REGION Jon Witter, Jessica D Ambrosio, Joe Magner, Andy Ward and Bruce Wilson
More informationFort Leonard Wood, Missouri. September 2013
Fort Leonard Wood, Missouri September 2013 1 Presenters Shannon Kelly, Physical Scientist Clean Water Act Program Manager Directorate of Public Works Environmental Division Environmental Compliance Branch
More informationCESAM-RD-C April 24, 2013 PUBLIC NOTICE NO. SAM AFM JOINT PUBLIC NOTICE SAM AFM U.S. ARMY CORPS OF ENGINEERS
DEPARTMENT OF THE ARMY U.S. ARMY ENGINEER DISTRICT, MOBILE DISTRICT P.O. BOX 2288 MOBILE, ALABAMA 36628-0001 CESAM-RD-C April 24, 2013 PUBLIC NOTICE NO. SAM-2012-00731-AFM JOINT PUBLIC NOTICE SAM-2012-0731-AFM
More informationKRISTOPHER J. KRZYSTON, CEI, CEM
PERMITTING IN NEW JERSEY KRISTOPHER J. KRZYSTON, CEI, CEM Kristopher J. Krzyston Rutgers graduate 1994 B.S. Environmental Planning Certificate in G.I.S. Assistant Division Manager Environmental Science
More informationNotice No Closing Date: May 12, 2017
Public Notice U.S. Army Corps of Engineers Pittsburgh District In Reply Refer to Notice No. below US Army Corps of Engineers, Pittsburgh District 1000 Liberty Avenue Pittsburgh, PA 15222-4186 Application
More informationPublic Notice ISSUED: August 11, 2015 EXPIRES: September 10, 2015
APPLICANT: John Deer Horicon Works Public Notice ISSUED: August 11, 2015 EXPIRES: September 10, 2015 REFER TO: MVP-2015-02020-JVD SECTION: 404 - Clean Water Act 1. APPLICATION FOR PERMIT TO discharge fill
More informationSCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS
SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS Version 2 June 2006 1. Purpose These Guidelines are supplementary
More informationTES Industrial Development SW ¼ SEC Lacombe County Outline Plan
TES Industrial Development Lacombe County Outline Plan 112849297 June 2012 am v:\1128\active\112849297\07_reports_studies\rpt_tes_20120508.doc i Table of Contents 1.0 INTRODUCTION... 1 1.1 PURPOSE... 1
More informationCHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR
GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section
More informationReducing Flood Risk in Toronto. David Kellershohn, M.Eng., P. Eng. Toronto Water, City of Toronto
Reducing Flood Risk in Toronto David Kellershohn, M.Eng., P. Eng. Toronto Water, City of Toronto Institute for Catastrophic Loss Reduction February 19, 2016 1 Agenda Reducing Flood Risk in Toronto 1) Overview
More informationVILLAGE OF BELLAIRE WATER QUALITY ACTION PLAN
VILLAGE OF BELLAIRE WATER QUALITY ACTION PLAN Elk-River-Chain-of-Lakes Gaps Analysis Project The Watershed Center Grand Traverse Bay Tip of the Mitt Watershed Council Michigan Department of Natural Resources
More informationKing County Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds
News Release Contact: Al Sanders 206-477-1016 August 31, 2015 Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds The Flood Control District
More informationCOON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432
PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:
More informationCONSTRUCTED WETLANDS: An Overview of the Technology
CONSTRUCTED WETLANDS: An Overview of the Technology Presentation For: Peconic River Remedial Alternatives Workshop December 12 & 13, 2000 ROUX ASSOCIATES, INC. Environmental Services and Management Presented
More informationAttachment D-1: Civil/Structural Scope of Work
Attachment D-1: Civil/Structural Scope of Work Project: Location: Targa Sound Renewable Fuels Project Tacoma, WA Prepared by: NORWEST ENGINEERING Consulting Engineers 4110 N.E. 122 nd Avenue, Portland,
More informationSTORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW
SUBCHAPTER 8 STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW 7:45-8.1 Purpose and scope of review Except for those projects expressly exempted by this chapter or waived by the Commission, the Commission
More informationSediment Basin. Fe= (Depends on soil type)
3.9 Sediment Control Description: A sediment basin is an embankment with a controlled outlet that detains stormwater runoff, resulting in the settling of suspended sediment. The basin provides treatment
More informationNatural Flood Management. Measures & Multiple Benefits. Steve Rose (JBA)
Natural Flood Management Measures & Multiple Benefits Steve Rose (JBA) Definitions Natural Flood Management - NFM (SEPA): A range of techniques that aim to reduce flooding by working with natural features
More informationInformation for File # PRH
Information for File # 2016-02602-PRH Applicant Corps Contact Tom Morley Paul Hauser Address 152 Baker Drive, Redwood Falls, MN 56283 E-Mail Paul.R.Hauser@usace.army.mil Phone 651-290-5357 Primary County
More informationVOLUME 1 TABLE OF CONTENTS
Santiago Hills Phase II Planned Community and East Orange Planned Community Area 1 Issue Date: 2, May 20055 VOLUME 1 TABLE OF CONTENTS SECTION 1: INTRODUCTION... 1-1 1.1 PROJECT DESCRIPTION... 1-1 1.2
More informationTexas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions
Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR050000 Storm Water Pollution Prevention Plan Worksheet Instructions The TCEQ Small Business and Local Government Assistance
More informationOverall Instructions
Farm Evaluation Survey Overall Instructions This Farm Evaluation Survey is prepopulated with member information you provide to the Coalition. If any information is incorrect, please indicate the correct
More informationU.S. ARMY CORPS OF ENGINEERS. Little Rock District
U.S. ARMY CORPS OF ENGINEERS Little Rock District SEDIMENT AND EROSION CONTROL GUIDELINES FOR PIPELINE PROJECTS Table of Contents 1.0 INTRODUCTION... - 1-2.0 PROJECTS IN WATERS OF THE UNITED STATES...
More informationReview of State and Federal Stormwater Regulations November 2007
Review of State and Federal Stormwater Regulations November 2007 By: James T. Spaulding, PE, CPESC Joseph M. Ducharme, Jr., PE TTG ENVIRONMENTAL CONSULTANTS, LLC 27 LOCKE ROAD, CONCORD, NH 03301-5301 TELEPHONE:
More informationProject Goals and Scoping
Prepared for: Boulder County, Colorado Flood Planning & Preliminary Design Services for South St. Vrain Creek Restoration at Hall Ranch and Scoping May 24, 2016 Meeting with General Public In association
More informationStream Watch Visual Survey Instructions
Stream Watch Visual Survey Instructions The Stream Watch Visual Survey is based on assessment parameters from the EPA's Rapid Bioassessment Protocol Habitat Assessment, Georgia Adopt a Stream Visual Survey,
More informationMechanical Site Preparation
Mechanical Site Preparation 1 Mechanical Site Preparation Introduction...3 CONTENTS The Benefits of Guidelines...3 Considerations...5 Design Outcomes To Maintain Soil Productivity...6 Planning...7 Planning
More informationEnvironmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department
2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote
More informationCharacteristics of Land Resources
Chapter Chapter 1 Characteristics of Land Resources The geology, soils and topography of Woodford County T he geology, soils and topography of an area are important to the community planning process for
More informationConstruction of Dariali HEPP. Reinstatement Plan
Construction of Dariali HEPP Reinstatement Plan 2016 Table of Content 1. Introduction... 3 2. Site Clean-up... 4 3. Headwork Site Reinstatement... 4 4. Reinstatement Of The Pipeline Corridor.9 5. Cable
More informationNovember 2,2006 CERTIFICATE OF THE SECRETARY OF ENVIRONMENTAL AFFIARS ON THE FINAL ENVIRONMENTAL IMPACT REPORT
MlTl ROMNEY Tel. (617) 626-1000 GOVERNOR Fax. (617) 626-1181 KERRY HEALEY hltp://www.mass.gavlenvir LIEUTENANTGOVERNOR ROBERT W. GOLLEDGE, JR November 2,2006 SECRETARY CERTIFICATE OF THE SECRETARY OF ENVIRONMENTAL
More informationCITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT
CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT Adopted by City Council: May 21, 2007 X:\General Eng\DESIGN STANDARDS\Engineering Design Standards
More informationStorm Water and Sanitary Sewer
Public Works Department Summary Report on Planned Capital Improvements Storm Water and Sanitary Sewer Introduction Public Works has assembled this summary report to highlight major capital improvements
More informationTown of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL
CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with
More informationDEPARTMENT OF THE ARMY Wilmington District, Corps of Engineers 69 Darlington Avenue Wilmington, North Carolina April 24, 2017
DEPARTMENT OF THE ARMY Wilmington District, Corps of Engineers 69 Darlington Avenue Wilmington, North Carolina 28403-1343 April 24, 2017 Regional General Permit No. 2016-00163 (RGP 163) Name of Permittee:
More informationEnvironmental Information Worksheet
Environmental Information Worksheet Water System Owner (Attach additional sheets if necessary) Needs and Alternatives Provide a brief narrative that describes: Current drinking water system needs. Project
More informationThe Clean Water Act: Phase I
Nearly 40 percent of all surveyed bodies of water in the U.S. do not meet the Environmental Protection Agency s (EPA s) water quality standards because of untreated polluted runoff that is often discharged
More informationHolly Swartz and Jason Shirey
Chapter 105 General Permits for Stream and Wetland Impacts DEP Ch. 105 CONTACTS FOR BERKS COUNTY: Holly Swartz and Jason Shirey What DEP Regulates Under Chapter 105 Waters of the Commonwealth, which includes
More informationPublic Notice. Applicant: City of Dallas Project No.: SWF Date: April 18, Name: Chandler Peter Phone Number:
Public Notice Applicant: City of Dallas Project No.: SWF- 2014-00151 Date: April 18, 2014 The purpose of this public notice is to inform you of a proposal for work in which you might be interested. It
More informationLANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN
LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO. 0200-S3N-R2 AFIN 32-00042 OCTOBER 12, 2016 LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT
More informationBMP #: Infiltration Basin
Structural BMP Criteria BMP #: Infiltration Basin An Infiltration Basin is a shallow impoundment that stores and infiltrates runoff over a level, subtle, uncompacted, (preferably undisturbed area) with
More informationRevision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL
SLI Doc. No. 505573-3000-40EC-0003 01 5-Dec-2013 ii TABLE OF CONTENTS Page No. 1 INTRODUCTION... 1 2 CREST ELEVATIONS... 2 2.1 Cofferdams... 2 2.2 North Spur... 3 3 STABILITY ANALYSIS LOADING CASES AND
More informationItem Name Description Unit of Measure Mobilization Per WSDOT Lump Sum
Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of
More informationLiving Shorelines & Coastal Resiliency: A Consultants Perspective. Presented by: Bethany Bearmore, P.E. Louis Berger
Living Shorelines & Coastal Resiliency: A Consultants Perspective Presented by: Bethany Bearmore, P.E. Louis Berger Living Shorelines & Coastal Resiliency A Consultants Perspective 1. Why 2. Process 3.
More informationThe boxes of compliance
The boxes compliance (and why they matter.) The information presented here is accurate as March 2007 but may change in the future should regulations change or programs be revised. How Do You Deal With
More informationCOASTAL PROTECTION, LANDSCAPING AND INFRASTRUCTURAL WORKS IN MAURITIUS CASE NOYALE SITE ENVIRONMENTAL IMPACT ASSESSMENT REPORT CONTENTS
COASTAL PROTECTION, LANDSCAPING AND INFRASTRUCTURAL WORKS IN MAURITIUS CASE NOYALE SITE ENVIRONMENTAL IMPACT ASSESSMENT REPORT CONTENTS Chapter Description Page EXECUTIVE SUMMARY 1 INTRODUCTION 1-1 1.1
More informationSW-74 SERENOVA PRESERVE SITES 2, 3, 4, 8 MITIGATION PLAN
SW-74 SERENOVA PRESERVE SITES 2, 3, 4, 8 MITIGATION PLAN BACKGROUND INFORMATION Project SWIM? Aquatic Control? Exotic Control? Mitigation Bank? Type No No No No Mitigation Restoration and enhancement Type
More informationNorthern Frontier Northern Homeland
Northern Frontier Northern Homeland THE REPORT OF THE MACKENZIE VALLEY PIPELINE INQUIRY Volume Two Terms and Conditions Mr. Justice THOMAS R. BERGER ii NORTHERN FRONTIER, NORTHERN HOMELAND - Mackenzie
More information