DESIGN BASIS FOR AIR CONDITIONING AND VENTILATION SYSTEM FOR SUBSTATION AND CONTROL BUILDING HINDUSTAN PETROLEUM CORPORATION LTD.
|
|
- Brandon Ferguson
- 6 years ago
- Views:
Transcription
1 CONDITIONING AND VENTILATION FOR SUBSTATION AND CONTROL BUILDING HINDUSTAN PETROLEUM CORPORATION LTD. VISAKH REFINERY DHT PROJECT TEIL JOB NO.: 6261 DOCUMENT NO.: 6261-HVAC-PKG-300 TEIL SPECIFICATION NO.: For Bid Enquiry DVM AVP SJP Revised as per Client AMR SMW SVW Comments 0 For Bid Enquiry AMR / ARN SMW SVW Rev no. issue date Description Prepared by Checked by Approved by TOYO ENGINEERING INDIA LIMITED MUMBAI INDIA
2 DOC.No HVAC-PKG-300 DHT PROJECT Page 2 of 7 Sr. No. DESCRIPTION PAGE 1 General 3 2 Codes and Standards 3 3 Special requirements 3 4 Safety requirements 3 5 Design Basis for Air Conditioning System 4 6 Design Basis for Ventilation System 5 7 Air Conditioning & Ventilation System Equipments & Material 6
3 DOC.No HVAC-PKG-300 DHT PROJECT Page 3 of GENERAL This specification covers the minimum requirements for the design, engineering, manufacture, inspection, testing and supply of Air Conditioning & Ventilation system. In addition to concurrence to this specification following consideration to be taken: 1. Compliance with applicable national or overseas codes & standards as well as any statutory regulation in existence for a specific item. 2. All equipment shall be sourced from PMC s mandatory / recommended Vendor List. The supplied model shall have proven track record. 3. Facility for any known future expansion of plant capacity with a minimum of modifications or shutdown. 2.0 CODES AND STANDARDS The main codes, standards wherever applicable for each equipment or system are indicated in the technical specifications of respective systems. Other reference documents, as applicable, are also listed in these corresponding specifications wherein the requirements of various codes and standards are amended or supplemented for compliance by the Contractors. 3.0 SPECIAL REQUIREMENT 3.1 Contractor shall develop the system taking into consideration the requirements defined in Feed package, Specifications, Data sheets. 3.2 Equipment shall be complete in all respects and any item or feature not covered in the specification, but essential for proper operation shall be included by the Contractor. Also the plant shall conform in all respects to high standards of engineering design, state of art, reliability and continuous operation. 3.3 Package Equipment layouts shall be prepared taking into consideration various factors like requirement of operatability, approach, safety withdrawal space requirement, maintenance, foundation requirements etc. for convenient operation. 3.4 Selection, fabrication and installation of piping works shall meet the Piping requirements defined elsewhere in Feed Package. 3.5 Design, engineering, fabrication, testing of vessels / storage tank shall meet the specifications enclosed elsewhere in the Feed Package. 3.6 Electrical equipment and material shall be in accordance with the electrical specifications enclosed elsewhere in the feed Package. All equipment selected for hazardous area shall be certified by the Testing Authority as specified in Electrical specifications or equivalent international testing agency for the service and area in which it is to be used.
4 DOC.No HVAC-PKG-300 DHT PROJECT Page 4 of The controls / indicators which are required to be connected to remote control room (DCS) shall be terminated in a junction box (with terminal strip) or local panel (located at the edge of skid) as applicable. 3.8 Selection & Installation of Instrumentation & controls shall meet minimum requirements defined in the Instrument specification attached elsewhere in Feed Package. 4.0 SAFETY REQUIREMENTS 4.1 Operational hazards should be reduced to a minimum. Contractor shall use sound engineering judgment to complete an installation that will perform the required function without compromising this aim. 4.2 Electrical devices shall meet the requirements for the area classifications in which they are installed. 4.3 Couplings, gears and exposed rotating parts shall be provided with adequate guards of nonsparking type. Drive belts, if used, shall be antistatic type. 4.4 Piping shall be arranged in a manner so as to avoid tripping or headroom problem. Piping or tubing of insufficient mechanical strength for standing or hanging shall be protected from personnel traffic. 4.5 Requirements of noise limits and equipment vibration as defined in standard specification shall be met. 5.0 DESIGN BASIS FOR AIR CONDITIONING 5.1 Air Conditioning shall be provided for the Sub-Station-75 Building. Contractor shall develop the complete Air Conditioning system configuration and submit along with bid and also before starting the detailed engineering work for owner/pmc approval. 5.2 The air Conditioning System shall be air cooled based system for the Sub-Station-75 Building. 5.3 Air Conditioning unit shall be available for continuous and round the clock operation. All areas requiring air conditioning for 24 hrs. /day. Following redundancy shall be maintained in Air Conditioning System; a) Water cooled chiller - 100% standby. b) VAM No standby. c) Fresh Air Fan - 100% standby. d) Chemical Filter Unit - No standby. e) AHU Upto 3 nos AHU s, 1 no standby, for 4 no and above, 2 no standby. f) Chilled water pumps - 100% standby. g) Cooling water pumps - 100% standby. h) Exhaust fans No standby. i) Exhaust fans for Battery Room Minimum 1 no of fan as standby j) Supply air fans for Battery Room Minimum 1 no of fan as standby k) FRP Cooling Tower with Basin 100% Standby.
5 DOC.No HVAC-PKG-300 DHT PROJECT Page 5 of Design Conditions: Outdoor design Conditions are as under (As per ISHRAE); Season Dry Bulb Temp.( 0 C) Wet Bulb Temp.( 0 C) Summer Monsoon Winter Daily range C 5.5 Min 10% margin over heat load calculation shall be considered for selecting capacity of Air Conditioning equipments. 5.6 Water cooled condensers shall be selected as per Basic Engineering Design Basis attached elsewhere. 5.7 For all air-conditioned buildings housing electronic equipment Chemical air filters are required to be installed in fresh air circuit. Inside quality of air shall be maintained as min ISA, G1 class within A/C area. For outdoor design conditions refer Basic Engineering Design Basis attached elsewhere. Minimum One air change per hour shall be considered for air conditioning. 5.8 Fresh Air arrangement for each building AC System; comprising of Bird Screen, Louvers, Volume Control Damper, motorised Fire Damper, Ducting, Chemical Filter with pre & fine dust filter (as per requirement), Centrifugal Fan shall be provided. 5.9 Fire Dampers shall be electrical motorised operated. Fire dampers shall be provided as per clean agent zoning. Relevant OISD norms shall be followed while deciding the location of fire dampers` Air Conditioning equipment shall be interlocked with gas/smoke detection and fire fighting system of the plant Safety factor shall be considered as minimum 12.5% in respect to Room sensible Heat and minimum 10% in respect of Room latent Heat Insulated supply air ducting shall be as per IS 655 / SMACNA complete with volume control damper, Splitter damper, guide Vanes, fire resistant flexible connection between Unit and ducting, air flow switch in main supply air ducts, duct supporting arrangement with anchor fasteners Duct mounted Electric strip finned heaters shall be provided complete with heating and safety thermostat with suitable inspection window for heater maintenance Self standing / wall mounted / audio/ visual annunciation panel for Package unit/ Air Heaters status and temperature / pressure instruments/controls as per standard Specifications.
6 DOC.No HVAC-PKG-300 DHT PROJECT Page 6 of Bidder to furnish the duct layout, while preparing duct layout purchaser s lighting layout and other relevant drawings shall be referred. Further any modification if required at site shall be done by Bidder to avoid interference, after taking proper approval 5.16 Bidder to furnish guaranteed power consumption for system. 6.0 DESIGN BASIS FOR VENTILATION S 6.1 All battery rooms shall have separate supply air fans and exhaust fans and fan motors shall be Ex.d type (gas group IIA/IIB/IIC). Minimum 12 air changes per hour of the room volume shall consider for ventilation of these rooms. Material of construction of Exhaust fans shall be suitable for fumes generated in Battery room. 6.2 For other rooms where ventilation is required like Clean Agent room in Control Building, minimum 12 air changes per hour of the room volume shall be considered for designing the exhaust system of the rooms. 6.3 Electrical (MCC Rooms) shall be ventilated. Minimum air changes to be considered for air quantity calculation shall be 12/hr. Air quantity shall also be calculated on the basis of 3 0 C temperature rise above ambient air (Taking care of the design temperature of the electrical equipment inside) and the higher of the two shall be provided. 6.4 Air intakes shall be located in non-hazardous and chemical fume free areas. 6.5 The system shall be provided with HDPE filters with frame work (minimum 90%, 10 microns), motorised CBRI certified fire dampers with frame in Supply air duct, control cable, power cable, interlocks to actuate audible alarm in case of fire, spring actuated counter weight operated pressure relief dampers with frame, bird screen, GSS air intake louvers with frame & bird protection screen, ducting with anodised aluminum grilles with aluminum angle frame, differential pressure measuring stn. across filters, manometers in space, associated civil, electrical, instrumentation, structural work & painting, inspection, performance testing. 6.6 The fans and motor noise level shall not exceed 85 dba at 1m distance from the equipment. 7.0 AIR CONDITIONING & VENTILATION EQUIPMENTS AND MATERIAL For details of Air Conditioning System & Ventilation system, refer following specifications; 6261-AA AA AA AA-340 Standard Engineering Specifications for Air conditioning system Standard Engineering Specifications for Air Handling Unit Standard Engineering Specifications for pressurization and Ventilation system Standard Engineering Specifications for Axial Fan
7 DOC.No HVAC-PKG-300 DHT PROJECT Page 7 of LIST OF SUGGESTED VENDOR 8.1 AIR CONDITIONING - CENTRAL Sub-vendors shall be as per Vendor List attached with this tender. 8.2 AIR CONDITIONING VAM Sub-vendors shall be as per Vendor List attached with this tender. 8.3 VENTILATION & PRESSURISATION Sub-vendors shall be as per Vendor List attached with this tender.
STANDARD ENGINEERING SPECIFICATION FOR VENTILATION SYSTEM HINDUSTAN PETROLEUM CORPORATION LTD. VISAKH REFINERY DHT PROJECT
STANDARD ENGINEERING SPECIFICATION FOR VENTILATION SYSTEM HINDUSTAN PETROLEUM CORPORATION LTD. VISAKH REFINERY DHT PROJECT JOB NO. : 6261 DOCUMENT NO. : 6261- AA-320 TEIL SPECIFICATION NO. AA-320 1 04.10.2010
More informationB. System Design and Performance Requirements
15625 Water Chillers This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or in notes
More informationB. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing.
PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 230593 TESTING, ADJUSTING, AND BALANCING A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification
More informationYour partner for the right solution
Your partner for the right solution Project engineering of power stations Environment protection in energy sector Equipment supplying Supervision of installation of the equipment supplied Commissioning
More informationTYP. SINGLE PLY ROOFING ROOF SHEETING BROAN VENT CAP #10 x 1" GASKETED SMS TYP. 4 SIDES 8" FRAMED CURB HVAC SYSTEMS "BASIS OF DESIGN" ROOF INSULATION R-19 WALL INSULATION R-13 LIGHTING EFFIECNCY PER STANDARDS
More informationFiberglass Cooling Towers
Fiberglass Cooling Towers Available in sizes from 100 to 240 tons. FC Series 700 Fiberglass Cooling Tower Available in sizes from 170 to 240 tons. No other fiberglass cooling tower comes with as many high-quality
More informationCFFWA-20-1-U Chilled/Hot Water Universal Mount Fan Coil 2-Pipe Heat / Cool Fan Coil 60,000 BTUH
CFFWA-20-1-U Chilled/Hot Water Universal Mount Fan Coil 2-Pipe Heat / Cool Fan Coil 60,000 BTUH Rev. 1.3 HVAC Guide Specifications Chilled and Hot Water Universal Mount Fan Coil 2-Pipe Nominal Size: 60,000
More informationENGINEERING SERVICES
ICONS... ICONS ENGINEERING SERVICES Contact us at: Ph: (+91) 9704 038 648 E-mail: contactus@iconsengg.com Web: http:// ABOUT US A group of professionals imbibed with the power of knowledge thru many years
More informationB. Provide liquid-filled secondary substation transformers as indicated on drawings.
SECTION 26 12 13 PART 1 - GENERAL 1.01 WORK INCLUDED A. Comply with the provisions of Sections 26 05 00. B. Provide liquid-filled secondary substation transformers as indicated on drawings. 1.02 RELATED
More informationApplication of Advanced Energy Technologies
GLOBALCON 2002 Philadelphia, Pennsylvania March 27, 2002 Application of Advanced Energy Technologies Michael K. West, Ph.D., P.E. Building Systems Scientist Advantek Consulting, Inc. www.advantekinc.com
More informationMOBILE SUBSTATIONS TRAILER AND SKID. tgood.com. Energy, Fast!
MOBILE SUBSTATIONS TRAILER AND SKID tgood.com Energy, Fast! Global leader in E-House and prefabricated substation solutions PRODUCT OVERVIEW Custom configurable skid-mounted and trailer-mounted designs.
More informationMechanical (HVAC)* * MasterFormat Specifications Division 23
40 Mechanical (HVAC)* The mechanical subcontractor (more commonly referred to as the heating, ventilation, and air conditioning, or HVAC, subcontractor) will furnish and install all equipment, ductwork,
More informationSECTION FIELD ERECTED INDUCED DRAFT COOLING TOWER
PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the contract including general and supplementary conditions and specifications section apply to this section. B. Related Sections:
More informationSECTION COOLING TOWER
PART 1 GENERAL 1.1 SECTION INCLUDES A. Mechanical induced draft Cooling Tower B. Controls C. Ladder and handrails 1.2 REFERENCES SECTION 23 65 00 COOLING TOWER A. ANSI/AFBMA 9 - Load Rating and Fatigue
More informationEhsan Soltani. Date of Birth: 1 Sep, 1980 Nationality: Iranian Marital Status: Married Mobile :(+98)
Ehsan Soltani Date of Birth: 1 Sep, 1980 Nationality: Iranian Marital Status: Married E-mail: ehsan.soltani@gmail.com Mobile :(+98) - 912-1501764 CAREER BRIEF: Having over 15 Years Work Experience in Iran
More informationPIP PCEPA003 Process Analyzer System Field Installation Guidelines
January 2016 Process Control PIP PCEPA003 Process Analyzer System Field Installation Guidelines PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry facilities,
More informationACBC Floor Mounted Active Beam
Floor Mounted Active Beam The Price Floor Mounted Active Beam,, is designed for occupant comfort. It provides high cooling and heating capacities while simultaneously supplying ventilation air from a DOAS
More informationCOOLING TECHNOLOGY INSTITUTE
PAPER NO: TP08-16 CATEGORY: DRY COOLING COOLING TECHNOLOGY INSTITUTE THE COST OF NOISE ROBERT GIAMMARUTI HUDSON PRODUCTS CORPORATION JESS SEAWELL COMPOSITE COOLING SOLUTIONS, LLC The studies and conclusions
More informationSECTION AIR DUCT CLEANING
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:
More informationNoise Control. Commercial, Industrial, and Environmental Products and Solutions.
Noise Control Commercial, Industrial, and Environmental Products and Solutions www.kineticsnoise.com Commercial Duct Silencers Kinetics Noise Control offers the design and engineering assistance to integrate
More informationKawasaki Gas Turbines-Americas Gas Turbines Power Generation Technology & Applications
Kawasaki Gas Turbines-Americas Gas Turbines Power Generation Technology & Applications Gas Turbine (GT) Technology Overview Gas Turbine Theory GT - Centrifugal Compressor FUEL INLET COMBUSTION CHAMBER
More informationMSC Guidelines for Review of Ventilation System Plans
K. B. FERRIE, CDR, Chief, Hull Division Purpose: This Plan Review Guideline (PRG) explains the requirements for seeking plan approval of ventilation systems from the Marine Safety Center (MSC) for most
More information5. AMCA 301 Method of Publishing Sound Ratings for Air Moving Devices. 6. AMCA 500 Test Methods for Louver, Dampers, and Shutters
PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is
More informationMobile Nitrogen Vaporizer Skid
A NEWSLETTER FROM CRYOGENIC INDUSTRIES WINTER 2013 Mobile Nitrogen Vaporizer Skid ryoquip Europe recently C designed and manufactured a mobile nitrogen ISO container vaporizer skid for large flow rate
More informationList of Enquiry Items for Enquiry BAP/PUR/FGD/EQS/2014/ E dt
List of Enquiry Items for Enquiry BAP/PUR/FGD/EQS/2014/4231581E dt 13.03.2014 Sl.No Material Code Description Unit Qty Destination 1. RFW301290000 EMERGENCY QUENCHING SYSTEM AT GGH INLET AS PER TECHNICAL
More informationElement D Services Heating, Ventilating, and Air Conditioning
PART 1 - GENERAL 1.01 OVERVIEW A. Provide a building temperature control/building automation system (BAS) for the space temperature control and monitoring of defined environmental conditions. General system
More informationDraft Indoor Air Quality Regulations
Department of Environment and Labour Occupational Health and Safety Division Draft Indoor Air Quality Regulations May, 2001 These draft regulations are being distributed for public comment. They do NOT
More informationIntroduction of the latest Technology of Energy Conservation
Introduction of the latest Technology of Energy Conservation --- To blue chip companies due to effective energy utilization --- September 15, 2015 Fuji Electric Co., Ltd. 1 Trends and prospects of the
More informationEnergy Recovery Ventilation Equipment
ANSI/AHRI Standard 1060 (I-P) 2014 Standard for Performance Rating of Airto-Air Exchangers for Energy Recovery Ventilation Equipment Approved by ANSI on May 15, 2015 IMPORTANT SAFETY DISCLAIMER AHRI does
More informationTable of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
More informationChapter 3.7: Cooling Towers
Part-I: Objective type questions and answers Chapter 3.7: Cooling Towers 1. The type of cooling towers with maximum heat transfer between air to water is. a) Natural draft b) Mechanical draft c) Both a
More informationContainment Booths. FOR MORE INFORMATION ON CONTAINMENT BOOTHS CALL +44 (0) OR
www.extract-technology.com ENGINEERED CONTAINMENT SOLUTIONS Containment Booths AT Extract Technology, we provide complete containment solutions based around an innovative range of Downflow Containment
More informationTender for HVAC work of Library Building At IIM Ahmedabad
Tender for HVAC work of Library Building At IIM Ahmedabad CoC, Specifications & Tender drawing Date of issue : 23/06/2017 Date of sub-mission : 18/07/2017 Tender No : IIMA/CCSP/024/2017-18 DATED-23/06/2017
More informationARRANGEMENT AND WORKING OF MULTIPORT FLOW SELECTOR VALVE IN PRODUCTION MANIFOLD:
GENERAL DESCRIPTION Crude oil well test manifold to be provide as Multiport Flow Selector (MPFS) technology. It provides a cost effective method for selecting and diverting well fluids from an individual
More information/ Hybrid Cooling Towers
/ Hybrid Cooling Towers Cooling Towers without visible plume / Cooling Technologies Balcke Hamon Dry Cooling Marley / Visible plume an avoidable problem / Every wet cooling tower generates a visible plume
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 12 2113 - LOUVER BLINDS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationLifting Appliances of Ships and Offshore Installations
CCS Rule Change Notice For: Lifting Appliances of Ships and Offshore Installations Version: May, 2016. RCN No.1 Effective date: 19 May, 2016 Beijing CONTENTS Chapter 3 CRANES, LIFTS, RAMPS AND SELF-LOADING
More informationThe following document can be provided to an Engineer, Contractor, or Owner to allow them to
MESAN series MXL Engineering Guide Specifications The following document can be provided to an Engineer, Contractor, or Owner to allow them to properly specify MESAN s MXL series Cooling Towers. 15XXX-
More informationBanyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL
SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationA/E Design Deliverable Checklist
A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic
More informationHIGH MAST CAMERA POLE ASSEMBLY GENERAL
10-3.24 HIGH MAST CAMERA POLE ASSEMBLY GENERAL The Contractor must furnish and install the following equipment for high mast camera pole assembly as described herein and as shown on the plans: 1. Camera
More informationPlanning for Biomed Facility Puts Energy Efficiency Under Microscope
Planning for Biomed Facility Puts Energy Efficiency Under Microscope Chilled beams, runaround-loop ERV system included May 19, 2014 By DAN VASTYAN, Common Ground, Manheim, Pa. HPAC Engineering Constructing
More informationA. This Section includes ceiling- and wall-mounted diffusers, registers, grilles and louvers.
SECTION 23 37 13 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply
More informationPerformance Efficiency Standard for Evaporative Cooling Equipment
Industry Recommendation / Code of Good Practice 9/12-2016 Performance Efficiency Standard for Evaporative Cooling Equipment First Edition Published on 11 October 2016 by,,, Belgium - The European Committee
More informationEC medium pressure axial fans.
EC medium pressure axial fans. The efficient system solution. The engineer s choice GreenTech EC technology in a new dimension. Thanks to these new new axial axial fans, fans, our our highly highly efficient
More informationINDIA HABITAT CENTRE New Delhi
INDIA HABITAT CENTRE New Delhi Tender For Renovation of Exhaust Air Ducting Works in Basements Date: January, 2014 Prepared by Sterling India Consulting Engineers New Delhi, India TABLE OF CONTENTS S.No.
More informationFACILITIES MAINTENANCE WORKER
FACILITIES MAINTENANCE WORKER Summary Statement: Under supervision, is responsible for performing routine building maintenance tasks and assisting Building Maintenance Supervisor with the performance of
More informationModular Chiller Plants A GLOBAL LEADER IN ENERGY SOLUTIONS
Modular Chiller Plants A GLOBAL LEADER IN ENERGY SOLUTIONS A B O U T S tellar Energy is a global leader in the design, construction, fabrication, installation, and servicing of a range of energy systems,
More informationWe are now interested to do a project of Down Hill Conveyor System for our Indian customer : A New, 7 MTPA Iron Ore design
ISG/DHC-001 2 nd April 2010 ASSOCIATE`S CONVEYOR SYSTEM 1.SYNOPSIS: ASSISTANCE FOR DOWN HILL BHEL, Industrial System Group, Bangalore proposes to do DOWNHILL CONVEYOR SYSTEM for Indian Mining Industries,
More informationInnotech is a registered Trademark of Mass Electronics Pty Ltd Copyright 2013 Mass Electronics Pty Ltd
CHILLED WATER PRIMARY SECONDARY & THERMAL ENERGY STORAGE DIGITAL CONTROL SYSTEM FUNDAMENTALS Presented by : Ben Macdonald QLD Sales Manager Innotech Control Systems Australia www.innotech.com.au Innotech
More informationLarge University Central Chiller Plant Design Considerations
Carrier Engineering Newsletter Volume 5, Issue 3 Large University Central Chiller Plant Design Considerations Large campus chilled water plants have unique constraints and need careful evaluation for successful
More informationGeneral Specifications for HVAC System Cleaning
General Specifications for HVAC System Cleaning Part 1 Special Provisions 1.01 Qualification of the HVAC System Cleaning Contractor (A) Membership: The HVAC system cleaning contractor shall be a member
More informationDANVEST POWER UNIT. with special Low Load Unit for wind-diesel power stations
DANVEST POWER UNIT with special Low Load Unit for wind-diesel power stations Controls weak or isolated grids - and gives top power quality extremely low fuel consumption and maximum exploitation of renewable
More informationA GUIDE TO REACH SYSTEM RELIABILITY. Commercial HVAC Buyers Guide
A GUIDE TO REACH SYSTEM RELIABILITY Commercial HVAC Buyers Guide How to confidently select your HVAC contractor, compare options and quotes, and enjoy system reliability. If you are reading this document,
More informationIndustrial Application of Thermal Energy Harvesting
GE - Bently Nevada Industrial Application of Thermal Energy Harvesting Dr. Thomas Kafka GE Sensing & Inspection Technology GmbH Frankfurt, Germany 1 GE - Bently Nevada Content: Wireless data collection
More informationCOMMERCIAL LOAD ESTIMATING. Load Estimating Level 3: Block and Zone Loads. Technical Development Program
COMMERCIAL LOAD ESTIMATING Load Estimating Level 3: Block and Zone Loads Technical Development Program Technical Development Programs (TDP) are modules of technical training on HVAC theory, system design,
More informationThis document also describes the basis on which building permit fees should be calculated.
1/6 1.0 PURPOSE This specification outlines when a Building Permit is required pursuant to the Building Code Act and its Regulations. The Building Code Act prescribes that each municipality is responsible
More informationSECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number
MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number PART 1 GENERAL 01 02 03 04 SCOPE Furnish and install Manual Transfer Switches (MTS) and
More informationISO INTERNATIONAL STANDARD. Petroleum and natural gas industries Packaged reciprocating gas compressors
INTERNATIONAL STANDARD ISO 13631 First edition 2002-08-01 Petroleum and natural gas industries Packaged reciprocating gas compressors Industries du pétrole et du gaz naturel Unités de compresseurs alternatifs
More informationForced Draft Decarbonators. Degasification
Forced Draft Decarbonators Degasification Forced Draft Decarbonator When do you need it? What is it? How does it work? In Ion Exchange Demineralizer Systems, Forced Draft Decarbonators are located between
More informationTransform your HVAC performance. Good for your comfort, for the environment and for your bottom line
Transform your HVAC performance Good for your comfort, for the environment and for your bottom line TRANSFORMING YOUR HVAC SYSTEM IMPULS-e is a portfolio of solutions from Trane which uses advanced technology
More informationPAINT BOOTHS GENERAL PURPOSE
PAINT BOOTHS GENERAL PURPOSE 1 INDUSTRY-LEADING PRODUCTS With precise contamination control and premium angled ceiling hip lights, General Purpose Paint Booths from Global Finishing Solutions (GFS) enable
More informationSCOPE OF WORK FOR STEEL SHEDS OF FIRE WATER PUMP HOUSE & PRODUCT PUMP HOUSE
Doc No: 254624-400-SW-CIV-015 Rev: Page 1 of 7 SCOPE OF WORK FOR STEEL SHEDS OF FIRE WTER PUMP HOUSE & PRODUCT PUMP HOUSE Hindustan Petroleum Corporation Ltd Visakha Dispatch Station VR-TP rea, Naval Base
More informationASHRAE Chapter Meeting HVAC Noise & Vibration Control Specifications & Best Practices
ASHRAE Chapter Meeting HVAC Noise & Vibration Control Specifications & Best Practices Industrial Presented By OEM Architectural Noise & Vibration Control, Inc. 610-863-6300 www.brd-nonoise.com HVAC Marine
More informationPioneer Forced Draft Cooling Tower Specifications
Delta Cooling Towers, Inc. 41 Pine Street P.O. Box 315 Rockaway, New Jersey 07866-0315 Telephone 973.586.2201 Fax 973.586.2243 www.deltacooling.com sales@deltacooling.com Pioneer Forced Draft Cooling Tower
More informationCheck-List of General Building Services
Check-List of General Building Services AREAS Land Area 2 Acres Usage IT / ITES plus facilities Build up Area Office space 2,35,001 sq.ft. plus double basement of 1,03,374sq.ft. Floor Plate 30,000sq.ft
More informationA. Drawings and general provisions of the Contract, including General Conditions Specification Sections, apply to this section.
Page 1 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General Conditions Specification Sections, apply to this section. 1.2 SUMMARY A. The shade structure
More informationChilled Beams. The new system of choice?
Chilled Beams The new system of choice? Presented By: Kevin M. Pope P.E. Jason Leffingwell Hammel Green And Abrahamson, Inc. and Ken Bauer, P.E., LEED AP Butters-Fetting Co., Inc. History of Chilled Beams
More informationSPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM)
SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) Construction Criteria The unit costs for the Physical Fitness Center (Exercise Room) space type are based on the construction quality and design features in
More informationFenestration Components: Mechanical Summary. Water heater energy factor: Ef Fuel type: Gas Electric Other
This information must be on the drawing documents not attached to plans. The following Compliance statements must be on the drawings: 2009 International Energy Conservation Code Statement of acknowledgement
More informationGreat Ocean Rd Ice Creamery
Great Ocean Rd Ice Creamery BCA Section J - JV3 Compliance Report Revision: 01 Job No: 2171 Date: 7 July 2015 ADP Consulting Pty Ltd Level 10, 10 Queens Rd, Melbourne Vic 3004 www.adpconsulting.com.au
More informationCI/SfB (57.7) 1st edition
CI/SfB (57.7) 1st edition Vent-Axia Sentinel Multivent Wholehouse Mechanical Extract Ventilation System Ventilation Lo-Carbon Energy saving solutions Sentinel Multivent continuous mechanical extract ventilation,
More informationDESIGN SPECIFICATION FOR FOUNDATIONS
FOR HINDUSTAN PETROLEUM CORPORATION LTD. VISAKH REFINERY DHT PROJECT JOB NO. : 6261 DOCUMENT NO. : A-6261-110-006 TOTAL NO. OF PAGES: 11 (INCLUDING THIS PAGE) 0 16-11-2009 FOR APPROVAL
More informationFABRIC EXPANSION JOINTS. Technical Brochure
FABRIC EXPANSION JOINTS Technical Brochure FABRIC EXPANSION JOINTS Fabric expansion joints have found a wide range of applications, in all industry branches due to their adaptability for different conditions:
More informationDetailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content
Detailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content Purpose The purpose of this Detailed Requirements Document (DRD) is to provide
More informationCOMPLETE REVISION April Process Industry Practices Piping. PIP PNC00004 Piping Stress Analysis Criteria for ASME B31.
April 2012 Process Industry Practices Piping PIP PNC00004 Piping Stress Analysis Criteria for ASME B31.3 Metallic Piping PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost
More informationTM Series Cooling Tower Specification
1.0 Cooling Tower TM Series Cooling Tower Specification 1.1 General: Furnish and install factory-assembled, induced draft, counterflow cooling tower(s) with vertical air discharge conforming in all aspects
More informationTelecommunication Spaces
Telecommunication Spaces October 19, 2016 Page 1 Revision History Telecommunication Spaces Standard Effective Date Email Version Contact Phone OIT-TS strevena@csustan.edu 1.0 Stan Trevena 209.667.3137
More informationFull-Scope Commissioning for High-Quality Buildings
Full-Scope Commissioning for High-Quality Buildings Pieter L. van der Mersch, PE, QCxP University of Colorado Boulder 21 st National Conference on Building Commissioning AIA Quality Assurance The Building
More informationIndoor Air Quality Improvement in a School Building in Delhi
Indoor Air Quality Improvement in a School Building in Delhi Maija Virta #1, Suhaas Mathur #1 # Santrupti engineers Private Limited 1083, 35 th D Cross, 4 th T Block, Jayanagar, Bangalore 560041, India
More informationAIRCOOL VENTILATORS FURTHER INFORMATION
.................................................. CI/SfB (57.7) Xy Uniclass L7563 January 2015 FURTHER INFORMATION................................................................... Services Passivent
More informationREV. 9/08. Mounting Structure PRE-INSTALLATION GUIDE for Ergon Skybooms
REV. 9/08 Mounting Structure PRE-INSTALLATION GUIDE for Ergon Skybooms SKYTRON MOUNTING STRUCTURES for Ceiling Mounted Equipment Foreword Skytron s objective is to provide a program and guideline to assist
More informationInformation Delivery Manual (IDM)
Piping Engineering - Confluence http://idm.buildingsmart.no/confluence/display/idm/piping+engineering?decorator=printable 1 af 2 11-09-2011 19:21 Information Delivery Manual (IDM) Added by Jeffrey Wix,
More informationRetro-Commissioning for Existing Facilities
Retro-Commissioning for Existing Facilities Tom Meyer Director, Technical Programs National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, Maryland 20877 (301) 977-3698 www.nebb.org
More informationCITY OF RICHMOND PINE CAMP COMMUNITY CENTER ROOF REPLACEMENT PROJECT RCS PROJECT NO
SECTION 01010 - SCOPE OF WORK PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. General provisions of Contract, General Conditions and Technical Specification Sections, apply to this Section. 1.02 PROJECT DESCRIPTION
More informationDIVISION 11 - EQUIPMENT FOOD SERVICE EQUIPMENT LABORATORY FUME HOODS. A. Design Considerations
DIVISION 11 - EQUIPMENT 11400 FOOD SERVICE EQUIPMENT A. Design Considerations 1. The A/E shall use the services of a food service equipment specialist in preparation of kitchen areas and other food preparation
More informationTrends and drivers in the Finnish ventilation and AC market
Trends and drivers in the Finnish ventilation and AC market Jarek Kurnitski, D.Sc. Docent Helsinki University of Technology Finnish Society of Indoor Air Quality and Climate, FiSIAQ 1 Contents Indoor climate
More informationBlackstone: flexible and environmentally friendly power plant
May-June 2002 Turbomachinery Blackstone: flexible and environmentally friendly power plant INTERNATIONAL Two single shaft combined cycle blocks - each with centrally-mounted generator and SSS Clutch Blackstone:
More informationOki (High Pressure Boiler Plant)
Bharat Heavy Electricals Limited 1717TC.1 Oki (High Pressure Boiler Plant) Tiruchirappalli 620014, TAMIL NADU, INDIA An ISO 9001 MATERIALS MANAGEMENT / CAPITAL EQUIPMENT Company ENQUIRY Phone: +91 431
More informationBUSWAY LOW VOLTAGE (POW-R-WAY III) SECTION SECTION 16466
BUSWAY LOW VOLTAGE (POW-R-WAY III) PART 1 GENERAL 1.01 1.02 SCOPE The Contractor shall furnish and install the busway system including all necessary fittings, hangers and accessories as specified herein
More informationDistrict Cooling Sustainable Design. Presented by George Berbari CEO of DC PRO Engineering
2016 District Cooling Presented by George Berbari CEO of DC PRO Engineering District Cooling Brief History & Future Central Chilled Water plants existed in the Middle East as early as the 1960 s. Few examples
More informationSampling. Stationary Portable. Sampling. Sewage Treatment. Municipal Sewerage Systems. Water Protection Control
Sampling Stationary Portable Sampling is an important factor for the compliance with required regulations and efficient operation. It forms the basis for continuous monitoring objectives and criteria,
More informationEnergy Conservation Best Know Methods Phil Naughton
Energy Conservation Best Know Methods Phil Naughton Why do we need energy reduction? Need for sustainable development Public pressure Customers and NGOs Legislative trends (EuP, Kyoto Protocol) Corporate
More informationNilan VPL Active heat recovery and cooling (air/air)
M a r k e t l e a d i n g c o m m e r c i a l a n d d o m e s t i c v e n t i l at i o n w i t h h e at r e c o v e r y Nilan 31-125 Active heat recovery and cooling (air/air) Nilan 31-125 Commercial ventilation
More informationGeothermal Power Plant
Geothermal Power Plant The Tokyo Electric Power Co., Inc., Japan Hachijo-jima Geothermal Power Plant 3,300kW 0A3-E-009 Outline All equipment and system except for the civil work and geothermal wells were
More informationC. ASSE 1013 Performance Requirements for Reduced Pressure Principle Backflow Preventers.
PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-23 71 19 (January 2008) Change 1-08/15 ---------------------------- Preparing Activity: USACE Superseding UFGS-23 71 19 (July 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationENVIRONMENTAL NOISE CONTROL FOR SEMICONDUCTOR MANUFACTURING FACILITIES
Presented at Inter-Noise 99 The 1999 Congress and Exposition on Noise Control Engineering December 8, 1999, Fort Lauderdale, Florida ENVIRONMENTAL NOISE CONTROL FOR SEMICONDUCTOR MANUFACTURING FACILITIES
More informationEvergreen Project Implementation Plan Instructions Low Income Housing Tax Credit Program
Evergreen Project Implementation Plan Instructions Low Income Housing Tax Credit Program The following table provides a brief description of the documentation that will be required of successful LIHTC
More informationPAINT BOOTHS LARGE EQUIPMENT
PAINT BOOTHS LARGE EQUIPMENT 1 THE FINISHING TOUCH A flawless paint finish can make a product stand out from the rest. With precise contamination control and excellent lighting, Large Equipment Booths
More information