FTBA 2018 Construction Conference Major Projects Update

Size: px
Start display at page:

Download "FTBA 2018 Construction Conference Major Projects Update"

Transcription

1 FTBA 2018 Construction Conference Major Projects Update Bill Jones, P.E. FDOT District 7 Director of Transportation Development 1

2 2

3 3 FUNDED PROJECTS

4 Howard Frankland Bridge Industry Forum September

5 Howard Frankland Bridge $750 Million September 2018 December 2018 Fall 2019 ALL DATES TENTATIVE 5

6 6 Howard Frankland Bridge

7 7

8 8

9 9

10 10

11 11

12 12

13 13

14 14

15 Howard Frankland Bridge Contract Information Design-Build Procurement: 4 ATC meetings Ad to Award is 11 months Anticipated Contract Duration 4.5 years (Including 1960 Bridge Demo) 15

16 Howard Frankland Bridge Project Information No ROW required and limited utility coordination Adjacent project coordination with Gateway and I-275 Operational Improvement projects Geotech borings 58 in water and 23 along causeways Barge mooring and trestle restrictions Shore-to-Ship locations will require prior approval Construction activity work area limitations Marine life low noise corridors and no night-time in-water work Demo material disposal TBD 16

17 Howard Frankland Bridge HFB Major Quantities Asphalt: 155,000 TN Bridge: 2,700,000 SF Bridge Removal: 1,000,000 SF Embankment: 1,400,000 CY MSE Wall: 105,000 SF Sea Wall: 11,000 LF 17

18 Operational Improvement Projects on SR 60 and I-275 Industry Forum on March 8,

19 SR 60 Operational Improvement FPID: $3 Million April 23, 2018 September 2018 ALL DATES TENTATIVE Low-bid Design-Build No ROW required Old Tampa Bay Grand Hyatt 60 Skyway Park Dana Shores Neighborhood Adds 5 th southbound lane Includes shoulder reconstruction plus mainline mill and overlay 60 Tampa International Airport 19

20 I-275 Operational Improvement FPID: $27.5 Million April 30, 2018 December 2018 ALL DATES TENTATIVE No ROW required Utility relocations required Tampa International Airport International Plaza Lois Avenue Two bridge widenings One noise wall Constrained MOT and work zones To be completed prior to the 2021 Super Bowl in Tampa Old Tampa Bay Cypress Point Park Reo Street 60 Cypress Street Westshore Plaza Kennedy Boulevard Dale Mabry Highway 20

21 I-275 Operational Improvement FPID: Westshore Area Lane Additions and Transitions 21

22 Express Lane Transitions This is how express lanes will transition into the Westshore area after the new bridge is built. Westshore Area Lane Additions and Transitions 22

23 23 UNFUNDED PROJECTS

24 Tampa Interstate Study Supplemental Environmental Impact Statement (SEIS) Public Hearing, mid 2019 NEPA complete, Spring 2020 Original EIS commitments Transit accommodations Urban design guidelines 24

25 Approx. $1 Billion October 2021 ALL DATES TENTATIVE Westshore Area Interchange 25

26 26 Westshore Interchange Project Information Sections 4 and 5 to be let together 4-Level Interchange at I-275 / SR 60 Tampa International Airport vertical restrictions Structures 53 new bridges 18 widened bridges Extensive straddles and cantilevers 4,650 LF box culvert relocation ROW acquisition may overlap with construction Numerous utility relocations Westshore Area Interchange

27 Westshore Area Interchange Sections 4 / 5 Major Quantities Embankment: 6,500,000 CY Asphalt Pavement: 80,000 TN Concrete Pavement: 400,000 CY Sound/Noise Barrier: 18,500 SF Bridge: 2,000,000 SF MSE Wall: ~1,500,000 SF 27

28 28 Potential staging areas:

29 Downtown Interchange $775M-$1.55B December 2021 ALL DATES TENTATIVE 4 design options within SEIS 2 reconstruction options 2 elevated express lane viaduct options 29

30 Reconstruction Options Downtown Interchange 30

31 Elevated Express Lane Viaduct options Downtown Interchange 31

32 Downtown Interchange Downtown Interchange Project Information Urban Design Guidelines Tampa Heights Greenway 100+ contamination sites (Level 1 screening) Staging areas: South of Blake H.S., former jail site (Scott St.), and NE quadrant of I-4/I-275 interchange Avoid downtown TECO substation 32

33 Potential staging areas: Downtown Interchange 33

34 Downtown Interchange Downtown Interchange Major Quantities (Roadway) 34

35 Project Information: Bridges Downtown Interchange 35

36 I-275 North of Downtown Tampa TBD Fall 2020 ALL DATES TENTATIVE Project Typical Section TBD Working with community on a range of ideas for this corridor 36

37 Range of Options for I-275 North of Downtown Tampa I-275 Typical Sections 37

38 I-4 $750 Million Fall 2020 ALL DATES TENTATIVE PD&E Approval Anticipated - Summer 2018 Interstate widening with 2 express lanes/dir. I-4/I-75 Interchange work is limited will be included with I-75 improvements Design-Build procurement Anticipated construction duration - 4 years 38

39 I-4 Project Information I-4 Right-of-Way required acquisition may extend one year beyond NTP Bridges 20 widenings and 11 new Complex construction at I-4/Selmon Connector I-4 WB I-4 EB 39

40 I-4 I-4 Major Quantities Asphalt Pavement: 450,000 TN Concrete Pavement: 17,000 SY Embankment: 5,500,000 CY Sound Barrier: 110,000 SF MSE Wall: 350,000 SF Bridges: 615,000 SF 40

41 I-75 North $1.7 Billion Summer 2021 ALL DATES TENTATIVE I-4 / I-75 Interchange Limits: From S of US 301 to N of Bruce B. Downs Blvd. Public Hearing Summer 2019 Interstate reconstruction/ widening with 2 express lanes/direction I-4/I-75 interchange reconfiguration/reconstruction Direct express lane ramps Significant local interchange improvements 41

42 I-75 North I-75 North Major Quantities Pavement type TBD: Asphalt: 570,000 TN, or Concrete: 3,700,000 SY Bridge: 5,000,000 SF Embankment: 17,000,000 CY MSE Wall: 1,000,000 SF 42

43 I-75 South $665 Million February 2021 ALL DATES TENTATIVE Limits: From Moccasin Wallow Rd. (S of Manatee Co. Line) to S of US 301 Public Hearing Summer 2019 Interstate reconstruction/widening with 2 express lanes/direction Significant local interchange improvements 43

44 I-75 South I-75 South Major Quantities Asphalt Pavement: 650,000 TN Bridge: 3,300,000 SF Embankment: 1,600,000 CY MSE Wall: 84,000 SF 44

45 I-275 Pinellas Corridor TBD$XX Million Fall?? ALL DATES TENTATIVE 45 Project Scope TBD Considering lane continuity, express lanes, and BRT on shoulder Project will likely include: Right of way for ponds Concrete pavement widening Shoulder reconstruction Bridge widening Noise walls

46 Questions? Bill Jones, P.E. FDOT District 7 Director of Transportation Development William.Jones@dot.state.fl.us

TAMPA BAY NEXT MAJOR PROJECTS UPDATE

TAMPA BAY NEXT MAJOR PROJECTS UPDATE TAMPA BAY NEXT MAJOR PROJECTS UPDATE Marshall Hampton, FDOT District Seven Tampa Bay Next Program Manager January 18, 2019 1 2 Program Overview Funding Priorities Fiscal Year 2018 2019 2020 2021 2022 2023

More information

Welcome. Tina Fischer. Collaborative Labs St. Petersburg College. North and West Hillsborough Community Working Group October 26, 2017

Welcome. Tina Fischer. Collaborative Labs St. Petersburg College. North and West Hillsborough Community Working Group October 26, 2017 Welcome North and West Hillsborough Community Working Group October 26, 2017 Tina Fischer Collaborative Labs St. Petersburg College Welcome to those viewing by webinar LISTENING OPTIONS Your listening

More information

Tampa Bay has a traffic problem. We re working on a comprehensive set of solutions.

Tampa Bay has a traffic problem. We re working on a comprehensive set of solutions. Tampa Bay has a traffic problem. We re working on a comprehensive set of solutions. Modernize infrastructure Prepare for the future Embrace collaboration and innovation The Program Includes: Interstate

More information

The Gateway Expressway FTBA Conference. February 2-3, 2017

The Gateway Expressway FTBA Conference. February 2-3, 2017 The Gateway Expressway FTBA Conference February 2-3, 2017 256996-1 SR 686 (Roosevelt Blvd.) at CR 611 (49th St. N) PD&E 256866-1 Segment 2A 256997-1 SR 686 (Roosevelt Blvd.) from 49th St. Bridge to north

More information

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS SECTION PAGE NO. SECTION TITLE NO. EXECUTIVE SUMMARY -------------------------------------------------------------------- ES-1 1.0 INTRODUCTION

More information

DRAFT AIR QUALITY TECHNICAL MEMORANDUM

DRAFT AIR QUALITY TECHNICAL MEMORANDUM AIR QUALITY TECHNICAL MEMORANDUM PROJECT DEVELOPMENT AND ENVIRONMENT STUDY STATE ROAD 60 GRADE SEPARATION OVER CSX RAILROAD Polk County, Florida Financial Project ID: 436559-1-22-01 Prepared for: Florida

More information

I-395 Reconstruction MDX SR Improvements I-95 Concrete Pavement Reconstruction

I-395 Reconstruction MDX SR Improvements I-95 Concrete Pavement Reconstruction I-395 Reconstruction MDX SR 83611 Improvements I-95 Concrete Pavement Reconstruction FTBA Conference February 10, 2016 Presentation Outline Project Overview I-395 Reconstruction MDX SR 83611 I-95 Pavement

More information

Draft Noise Study Report

Draft Noise Study Report Project Development & Environment Study I-75 (SR 93A) From Moccasin Wallow Road (CR 6) to South of US Highway 301 (SR 43) Draft Noise Study Report WPI Segment No.: 419235 2 Manatee & Hillsborough Counties

More information

I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions

I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions General Overview What is the I-65/I-70 North Split Reconstruction Project? The I-65/I-70 North Split Reconstruction Project

More information

DRAFT Geotechnical Technical Memorandum

DRAFT Geotechnical Technical Memorandum DRAFT Geotechnical Technical Memorandum US 19 (SR 55) Reevaluation from 66 th Avenue North to SR 690/118 th Avenue North Work Program Item Segment No. 435914-1 Project Development and Environment Study

More information

Dale Mabry Pedestrian Overpass Technical Feasibility Analysis. March 2017

Dale Mabry Pedestrian Overpass Technical Feasibility Analysis. March 2017 Dale Mabry Pedestrian Overpass Technical Feasibility Analysis March 2017 Overview Two Part Study: 1. Feasibility of Alternatives for a Pedestrian Overpass Across Dale Mabry Hwy Near I 275 2. Walk/Bike

More information

Tampa Bay Transportation Management Area (TMA) Leadership Group

Tampa Bay Transportation Management Area (TMA) Leadership Group Tampa Bay Transportation Management Area (TMA) Leadership Group Representing the MPOs in Pasco, Pinellas, & Hillsborough Counties Meeting Objectives Friday, May 11, 2018 9:30 a.m. - 12:30 p.m. Pasco County

More information

2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM

2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM 2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM A. District: 1 2 3 4 5 6 7 TPK C.O. B. Nomination Category: (Select only one category) Outstanding Major Project Outstanding

More information

I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017

I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017 I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017 State Project # 0064-965-264, P101, R201, C501, B616, B617, B618, B619, B620, B621, D601, D602 Federal # NHS-064-3(479),

More information

Pensacola Bay Bridge Replacement Design Build. Industry Forum. Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer

Pensacola Bay Bridge Replacement Design Build. Industry Forum. Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer Pensacola Bay Bridge Replacement Design Build Industry Forum Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer Project Location 2 GENERAL PROJECT INFORMATION Replacement of the structurally

More information

TRANSPORTATION HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA

TRANSPORTATION HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA 2008/09 $52.0 M 85% SELF-PERFORMED Widen 12 miles of Interstate 10 to six lanes including the reconstruction

More information

Value Engineering For Transportation Improvements. Interstate 4 from East of State Road 15/600 (US 17/92) to ½ Mile East of State Road 472

Value Engineering For Transportation Improvements. Interstate 4 from East of State Road 15/600 (US 17/92) to ½ Mile East of State Road 472 Value Engineering For Transportation Improvements Interstate 4 from East of State Road 15/600 (US 17/92) to ½ Mile East of State Road 472 Value Engineering Study Draft Report FM Number: 408464-2 Fed. Aid

More information

} SURVEY SR 429 STANDARD CLEARING & GRUBBING LIMITS OF FRICTION COURSE 8" 8" 8" 8" 12' VARIES 24'-36' VARIES VARIES * 4' SHLDR. PAVT.

} SURVEY SR 429 STANDARD CLEARING & GRUBBING LIMITS OF FRICTION COURSE 8 8 8 8 12' VARIES 24'-36' VARIES VARIES * 4' SHLDR. PAVT. } SURVEY SR 429 { CONST. SR 429 (WEKIVA PKWY) R/W (15 MIN.) 0'-10.4' R/W (15 MIN.) STANDARD CLEARING & GRUBBING 24'-36' 24'-48' 94' BORDER (2-30.) (2-30.) 94' BORDER 10' 4' 10' NATURAL GROUND, MAX. CUT

More information

TAMPA - HILLSBOROUGH COUNTY EXPRESSWAY AUTHORITY Committee / Board Meeting January 17, E. Twiggs Street, Suite 300 Tampa, FL AGENDA

TAMPA - HILLSBOROUGH COUNTY EXPRESSWAY AUTHORITY Committee / Board Meeting January 17, E. Twiggs Street, Suite 300 Tampa, FL AGENDA TAMPA - HILLSBOROUGH COUNTY EXPRESSWAY AUTHORITY Committee / Board Meeting January 17, 2017 1104 E. Twiggs Street, Suite 300 Tampa, FL 33602 AGENDA I. Operations & Maintenance Committee Bennett Barrow,

More information

Florida Department of TRANSPORTATION FTBA CONSTRUCTION CONFERENCE January 17-18, 2019 Hyatt Regency, Orlando FDOT WORK PROGRAM OVERVIEW

Florida Department of TRANSPORTATION FTBA CONSTRUCTION CONFERENCE January 17-18, 2019 Hyatt Regency, Orlando FDOT WORK PROGRAM OVERVIEW Florida Department of TRANSPORTATION 2019 FTBA CONSTRUCTION CONFERENCE January 17-18, 2019 Hyatt Regency, Orlando FDOT WORK PROGRAM OVERVIEW 1 Florida s Continued Growth Florida is currently home to nearly

More information

Tampa Bay Transportation Management Area (TMA) Leadership Group

Tampa Bay Transportation Management Area (TMA) Leadership Group Tampa Bay Transportation Management Area (TMA) Leadership Group Representing the MPOs in Pasco, Pinellas, & Hillsborough Counties Friday, February 8, 2019 9:30 a.m. - 12:00 p.m. Hillsborough Planning Commission

More information

DECEMBER P R O G R E S S R E P O R T

DECEMBER P R O G R E S S R E P O R T DECEMBER 201 2 P R O G R E S S R E P O R T The My 35 Plan is a dynamic document and will continue to be re-evaluated and updated by the Committee as needed. The My 35 Plan contains the ideas and recommendations

More information

CLA /10.54, PID Project Description:

CLA /10.54, PID Project Description: Project Description: The proposed project will consist of widening IR 70 to three lanes from Enon Road (SLM 06.75) to the US 68 interchange ramps (SLM 10.55). IR 70 is a component of the Strategic Highway

More information

Air Quality Analysis Technical Memorandum

Air Quality Analysis Technical Memorandum Air Quality Analysis Technical Memorandum Segment 2: State Road 400 (SR 400) / Interstate 4 (I-4) from West of SR 528 (Beachline Expressway) to West of SR 435 (Kirkman Road) Orange County (75280), Florida

More information

Construction Cost Estimation Preparation Manual for Preliminary Design (English Units)

Construction Cost Estimation Preparation Manual for Preliminary Design (English Units) 10/16/2014 Construction Cost Estimation Preparation Manual for Preliminary Design (English Units) July 2002 Prepared by Construction Cost Estimating Unit Program Support Services 10/16/2014 Table of Contents

More information

Innovations in Utility Relocations- Case Studies in Cost and Time Savings

Innovations in Utility Relocations- Case Studies in Cost and Time Savings Innovations in Utility Relocations- Case Studies in Cost and Time Savings Janice Sands Ash, P.E. President The Ash Group, Inc. JOINT UTILITY RELOCATION PROJECTS Joint Utility Trench Projects (JUT) US 41

More information

2018 FTBA CONSTRUCTION CONFERENCE February 8-9, 2018 Hyatt Regency, Orlando FDOT WORK PROGRAM OVERVIEW

2018 FTBA CONSTRUCTION CONFERENCE February 8-9, 2018 Hyatt Regency, Orlando FDOT WORK PROGRAM OVERVIEW Florida Department of TRANSPORTATION 2018 FTBA CONSTRUCTION CONFERENCE February 8-9, 2018 Hyatt Regency, Orlando FDOT WORK PROGRAM OVERVIEW Presenter: Brian Blanchard, Assistant Secretary Engineering and

More information

Design-Build and Design-Bid-Build

Design-Build and Design-Bid-Build Design-Build and Design-Bid-Build Comparison of Overall Cost and Time Question: How does the total cost and time to deliver a $55,000,000 and 814 day design-build project compare to using design-bid-build

More information

Transportation Update

Transportation Update Transportation Update Projects Underway Norview Avenue About the Project: The Norview Avenue Interchange Improvement Project will eliminate the existing weave movement associated with the on- and off-ramps

More information

I-49 North Shreveport (I-220) To Arkansas State Line

I-49 North Shreveport (I-220) To Arkansas State Line I-49 North Shreveport (I-220) To Arkansas State Line Project Update: History and Current Status 2013 La. Transportation Conference Joe Umeozulu, P.E. Outline Brief General I-49 History I-49 North Funding

More information

Reconstruction Project Update

Reconstruction Project Update I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial

More information

Statewide Acceleration Transformation (SWAT)

Statewide Acceleration Transformation (SWAT) Presented to: AASHTO SCOE/SCOD Presented by: Marjorie Kirby Paul Hiers, P.E. Statewide Acceleration Transformation (SWAT) July 2017 PD&E Study Comply with the National Environmental Policy Act (NEPA) and

More information

Operational Analysis of Dulles Toll Road Ramps to Tysons. Board Transportation Committee Meeting September 17, 2013

Operational Analysis of Dulles Toll Road Ramps to Tysons. Board Transportation Committee Meeting September 17, 2013 Operational Analysis of Dulles Toll Road Ramps to Tysons Board Transportation Committee Meeting September 17, 2013 Seyed Nabavi Fairfax County Department of Transportation 1 Agenda Overview & Assumptions

More information

Shadow Lake Woods HOA

Shadow Lake Woods HOA A Regional Transportation Solution Shadow Lake Woods HOA November 22, 2016 WEKIVA PARKWAY Project Description $1.6 Billion Completion of Central Florida s Beltway 25-mile Toll Road Non-Toll Road Improvements:

More information

INTERACTIVE HIGHWAY SAFETY DESIGN MODEL (IHSDM)

INTERACTIVE HIGHWAY SAFETY DESIGN MODEL (IHSDM) INTERACTIVE HIGHWAY SAFETY DESIGN MODEL (IHSDM) TSITE 2016 Winter Meeting Nashville, TN February 25, 2016 AGENDA Project History IHSDM: Background & Overview IHSDM: Interstate 24 Model IHSDM: Interstate

More information

Florida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Four

Florida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Four DISTRICT FOUR PROJECT OVERVIEW Florida s Turnpike Enterprise continues to make significant project investments in District Four. In fiscal years 2014 and 2015, current Turnpike projects total over $127

More information

Highway Construction Program

Highway Construction Program Highway Construction Program Monthly Delivery Progress Report Watch List February 2017 This report focuses on Capital Highway Program projects, which have, or may have significant changes in scope, schedule,

More information

1.4 Analysis of Alignment Alternatives

1.4 Analysis of Alignment Alternatives Parkway is 20.94 miles, with 8.16 miles in Orange County, 7.37 miles in Lake County and 5.41 miles in Seminole County. SR 46 Reconstruction and Realignment, which would begin at the SR 46/US 441 interchange

More information

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb

More information

Project Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce

Project Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce Project Team D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce D6 Design Project Manager Ali Toghiani, P.E. CEI: AIM Engineering and Surveying Francis Chin,

More information

Contra Costa Transportation Authority STAFF REPORT February 15, 2017 Page 2 of 3 Background MTC is expected to seek authorization from the State Legis

Contra Costa Transportation Authority STAFF REPORT February 15, 2017 Page 2 of 3 Background MTC is expected to seek authorization from the State Legis Contra Costa Transportation Authority STAFF REPORT Meeting Date: February 15, 2017 Subject Summary of Issues Regional Measure 3 (RM3) Candidate Projects for Submittal to the Metropolitan Transportation

More information

Overview of Prior Studies

Overview of Prior Studies FLORIDA DEPARTMENT OF TRANSPORTATION PORT OF MIAMI TUNNEL STUDY Overview of Prior Studies This summary was provided on July 29, 2003 by Jeff V. Easley, PE, Vice President of Reynolds, Smith and Hills as

More information

Project Study Area. Presentation. July 8, 2008

Project Study Area. Presentation. July 8, 2008 Florida Department of Transportation Presentation for for the the South Side Community Plan #4 at at the the South South Shore Shore Regional Regional Library, Library, 15816 15816 Beth Beth Shields Shields

More information

BRIDGE GENERAL PLAN ESTIMATE OR PLANNING ESTIMATE X

BRIDGE GENERAL PLAN ESTIMATE OR PLANNING ESTIMATE X STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION BRIDGE GENERAL PLAN ESTIMATE OR PLANNING ESTIMATE X DPD-DSD-DIS (Rev 8/92) STRUCTURE BR. NO. RCVD BY ESTIMATING GROUP Wall 177 - Sta 177+00 to Sta 181+00

More information

SR 836 / I-395 and SR 5 / US 1 / Biscayne Boulevard Tunnel Concept Evaluation FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 6

SR 836 / I-395 and SR 5 / US 1 / Biscayne Boulevard Tunnel Concept Evaluation FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 6 SR 836 / I-395 and SR 5 / US 1 / Biscayne Boulevard Tunnel Concept Evaluation FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 6 October 2014 TABLE OF CONTENTS 1. Figure 1.A: Compendium of General Concerns

More information

SPAGHETTI BOWL. RTC Workshop April 20, 2018

SPAGHETTI BOWL. RTC Workshop April 20, 2018 SPAGHETTI BOWL RTC Workshop April 20, 2018 EIS TIMELINE PLANNING NEPA FINAL DESIGN & ROW CONSTRUCTION ALTERNATIVES UPDATES We will review changes to the Alternatives Alternative 1 Alternative 2 Alternative

More information

DESIGN BUILD LA 318 INTERCHANGE FUTURE I-49 SOUTH

DESIGN BUILD LA 318 INTERCHANGE FUTURE I-49 SOUTH DESIGN BUILD LA 318 INTERCHANGE FUTURE I-49 SOUTH Timothy Nickel, P.E. Project Management Administrator (225) 379-1110 Timothy.Nickel@la.gov Post Office Box 94245 Baton Rouge, LA 70804-9245 A Project within

More information

Air Quality Analysis Technical Memorandum

Air Quality Analysis Technical Memorandum Air Quality Analysis Technical Memorandum Segment 4: State Road 400 (SR 400)/Interstate 4 (I-4) from East of SR 15-600/US 17-92 (Seminole/Volusia County Line) to ½ Mile East of SR 472 Volusia County (79110),

More information

Surface Transportation Resiliency Planning in Hillsborough County, FL

Surface Transportation Resiliency Planning in Hillsborough County, FL Surface Transportation Resiliency Planning in Hillsborough County, FL Allison Yeh, AICP, LEED GA Hillsborough County, Florida 158 miles of coastline 4 th Largest Population in Florida (1.3 Million) 25%

More information

CITY OF SAFETY HARBOR ENGINEERING

CITY OF SAFETY HARBOR ENGINEERING CITY OF SAFETY HARBOR ENGINEERING The Engineering Department provides the city with technical services including design of construction and maintenance projects, review of development plans, field surveys,

More information

Final Recommendations Identification of Improvements, Strategies, and Solutions

Final Recommendations Identification of Improvements, Strategies, and Solutions Identification of Improvements, Strategies, and Solutions Prepared by: December 2015 TABLE OF CONTENTS 1. Introduction... 1 1 2. Freight Policy Recommendations... 2 1 3. Freight Infrastructure Recommendations...

More information

Value Engineering For Transportation Improvements. I-4 from 1 Mile East of State Road 434 to Volusia County Line

Value Engineering For Transportation Improvements. I-4 from 1 Mile East of State Road 434 to Volusia County Line Value Engineering For Transportation Improvements Interstate 4 from 1 Mile East of State Road 434 to Volusia County Line Value Engineering Study Draft Report FM Number: 242592-4 Fed. Aid Project: Project

More information

Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida

Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida November 7, 2014 SUBMITTED BY: Dewberry Bowyer-Singleton 520 South

More information

Maryland Transportation Authority (MDTA)

Maryland Transportation Authority (MDTA) Maryland Transportation Authority (MDTA) I-95 Major Deck and Superstructure Rehabilitation South of the Fort McHenry Tunnel Northeast Bridge Preservation Partnership Conference September 20, 2016 David

More information

APPENDIX A TIER 1 ANALYSIS

APPENDIX A TIER 1 ANALYSIS SPN H.004100 FEASIBILITY STUDY APPENDIX A TIER 1 ANALYSIS 040-012-042AH Appendices Lead Sheets PROVIDENCE STATE PROJECT. H.004100 The following worksheets analyze various project alternatives at various

More information

I-4 Beyond the Ultimate Project Development & Environment (PD&E) Reevaluation Study FROM WEST OF SR 528 (BEACHLINE EXPRESSWAY)

I-4 Beyond the Ultimate Project Development & Environment (PD&E) Reevaluation Study FROM WEST OF SR 528 (BEACHLINE EXPRESSWAY) I-4 Beyond the Ultimate Project Development & Environment (PD&E) Reevaluation Study FROM WEST OF SR 528 (BEACHLINE EXPRESSWAY) TO WEST OF SR 435 (KIRKMAN ROAD) ORANGE COUNTY, FLORIDA Financial Project

More information

Ohio Department of Transportation - Prebid Questions

Ohio Department of Transportation - Prebid Questions Project No. 120625 Sale Date - 12/14/2012 ATB-76747 - IR-90-7.56, PART 1;ATB-90-13.60, PART 2 12/11/2012 8:03:55 AM Per Addendum 5 Item 184 was reduced drastically. With over 35,000 LF of new guardrail

More information

Governor s Transportation Task Force. MEGAPROJECT NEEDS RPC Freight Roundtable Executive Director: Walter Brooks

Governor s Transportation Task Force. MEGAPROJECT NEEDS RPC Freight Roundtable Executive Director: Walter Brooks Governor s Transportation Task Force MEGAPROJECT NEEDS RPC Freight Roundtable Executive Director: Walter Brooks April 26, 2017 RPC Transportation Investments 2010-2015 Transit, $253.6M (20.3%) Safety &

More information

Project Streamlining Linking R/W with NEPA May 3, Nelson Castellanos Director- Office of Real Estates Services

Project Streamlining Linking R/W with NEPA May 3, Nelson Castellanos Director- Office of Real Estates Services Project Streamlining Linking R/W with NEPA May 3, 2012 Nelson Castellanos Director- Office of Real Estates Services Project Delivery Linear Process Project Planning NEPA Design R/W Construction Open to

More information

I-10 Master Plan Escambia and Santa Rosa Counties TPO Meetings. Tier II June 11 th & 13 th, 2012

I-10 Master Plan Escambia and Santa Rosa Counties TPO Meetings. Tier II June 11 th & 13 th, 2012 I-10 Master Plan Escambia and Santa Rosa Counties TPO Meetings Tier II June 11 th & 13 th, 2012 Agenda Introduction & Background Study Area Purpose & Need Project Status Tier Methodology & Tier I Evaluation

More information

I-90 Pavement Rehab VE Study

I-90 Pavement Rehab VE Study I-90 Pavement Rehab VE Study Using Value Analysis to Select Project Delivery Method Ken L. Smith, PE, CVS 360-570-4415 The week may have started with a bang But it ended with a success Do not drink and

More information

INTERCHANGE MODIFICATION REPORT

INTERCHANGE MODIFICATION REPORT INTERSTATE 75 AND STATE ROAD 884 (COLONIAL BOULEVARD) INTERCHANGE LEE COUNTY, FLORIDA INTERCHANGE MODIFICATION REPORT Prepared for: Florida Department of Transportation District One May 2017 Interchange

More information

ADA Training Design Case Studies MnDOT

ADA Training Design Case Studies MnDOT ADA Training Design Case Studies 2018 MnDOT 2 ADA Design Case Studies Overview TH 61 (Mounds Blvd) Mill & Overlay Lesson: Steep Slopes and Construction Limits Snelling Avenue Mill & Overlay Lesson: Strategies

More information

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0 SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605/SR-60 EA# 3101U0 October 9, 2017 Contents 1 Purpose of ICE Memo... 1 2 Background... 1 3 Existing Interchange Deficiencies... 1 4 Context Sensitive

More information

VDOT Major Projects Update

VDOT Major Projects Update VDOT Major Projects Update April 20, 2017 Agenda Introduction Peninsula Projects Southside Projects Harbor Crossing Questions/Comments 2 Summary Construction Execution Timeline I-64 Peninsula Seg. I PE

More information

Southern Beltway; US-22 to I-79 A CONSTRUCTION UPDATE JANUARY, 2018

Southern Beltway; US-22 to I-79 A CONSTRUCTION UPDATE JANUARY, 2018 Southern Beltway; US-22 to I-79 A CONSTRUCTION UPDATE JANUARY, 2018 Pittsburgh Traffic Congestion Pittsburgh s geography I-376 most congested traffic corridor outside NYC/LA Pittsburgh International Airport

More information

Construction Engineering and Inspection Services Pembroke Road from Dykes Road to Silver Shores Boulevard Broward County, FL

Construction Engineering and Inspection Services Pembroke Road from Dykes Road to Silver Shores Boulevard Broward County, FL Construction Engineering and Inspection Services to Silver Shores Boulevard Broward County, FL R L I N O. R 2 11 4 0 8 0 P 1 I. Experience and Qualifications with Roadway Construction a. Eisman & Russo

More information

IMPROVING I 81 IN MARYLAND

IMPROVING I 81 IN MARYLAND IMPROVING I 81 IN MARYLAND April 25, 2017 Stephen A. Bucy, P.E. Improving I 81 in Maryland Overview: Facts SHA s Comprehensive I 81 Strategy Current Phase 1 Widening Project Update Closing Improving I

More information

WELCOME. Public Meeting for I-35 / I-44 Interchange. October 6, 2015

WELCOME. Public Meeting for I-35 / I-44 Interchange. October 6, 2015 WELCOME Public Meeting for I-35 / I-44 Interchange October 6, 2015 TEAM INTRODUCTIONS PURPOSE OF THIS MEETING is to present the alternative alignments for the I-35/I-44 and I-35/NE 63rd Street Interchanges

More information

State Road (S.R.) 12 (Florida Arts Trail PD&E)

State Road (S.R.) 12 (Florida Arts Trail PD&E) State Road (S.R.) 12 (Florida Arts Trail PD&E) from North Corry Street to S.R. 63 (U.S. 27) Gadsden County, Florida FPID Number: 433380-1-32-01 CRTPA Briefing September 2015 Today s Presentation Evolution

More information

Draft Location Hydraulic Report

Draft Location Hydraulic Report Project Development & Environment Study I-75 (SR 93A) From Moccasin Wallow Road (CR 6) to South of US Highway 301 (SR 43) Draft Location Hydraulic Report WPI Segment No.: 419235-2 Manatee & Hillsborough

More information

SR 29 Project Development & Environment Study. Presentation to SR 29 Stakeholders Advisory Committee. January 23, 2014

SR 29 Project Development & Environment Study. Presentation to SR 29 Stakeholders Advisory Committee. January 23, 2014 SR 29 Project Development & Environment Study Presentation to SR 29 Stakeholders Advisory Committee January 23, 2014 Purpose and Need Enhancing Economic Competitiveness Improving Emergency Evacuation Capabilities

More information

Tall Trees HOA Update

Tall Trees HOA Update A Regional Transportation Solution Tall Trees HOA Update June 9, 2016 Meeting Agenda I. Brief Section Update II. List of Community Concerns Received III. Responses to Each Concern IV. Recap Action Items

More information

LOCATION HYDRAULIC REPORT

LOCATION HYDRAULIC REPORT Draft LOCATION HYDRAULIC REPORT Florida Department of Transportation District One US 41 at Fruitville Road (CR 780) Intersection Improvements - PD&E STUDY Sarasota County, Florida Financial Project ID

More information

NJTPA Transportation Improvement Program Fiscal Years

NJTPA Transportation Improvement Program Fiscal Years Routes Name: CR 571 Mileposts: 4.85 DBNUM: N1127 County Route 571/County Route 527, Reconstruction, Toms River Township This project is for intersection improvements at CR 571 and CR 527 in Tom s River

More information

SR 50 PD&E Study

SR 50 PD&E Study SR50 Project Development & Environment Study Public Hearing November 1, 2011 SR 50 PD&E Study 427056-1-22-01 1 Purpose of the Public Hearing Afford persons the opportunity to express their views about

More information

Derry-Londonderry I-93 Exit 4A Public Officials/Information Meeting/NHDOT Design-Build Public Hearing

Derry-Londonderry I-93 Exit 4A Public Officials/Information Meeting/NHDOT Design-Build Public Hearing Derry-Londonderry 13065 - I-93 Exit 4A Public Officials/Information Meeting/NHDOT Design-Build Public Hearing July 25, 2018 Purpose of Meeting Purpose and Need Current Project Status Alternatives Overview

More information

Community Advisory Committee Meeting No. 2. June 22, 2006

Community Advisory Committee Meeting No. 2. June 22, 2006 Community Advisory Committee Meeting No. 2 June 22, 2006 Introductions The Study Team KDOT Wichita Partners Consultants CAC members Overview Today s Agenda Opinion Survey Study Status Starting Concept

More information

2050 VISION WORKSHOP

2050 VISION WORKSHOP I-75 PD&E Studies Project Development & Environment Studies From Moccasin Wallow Road to North of Fletcher Avenue Manatee and Hillsborough Counties 2050 VISION WORKSHOP Florida Department of Transportation

More information

Hillsborough MPO Surface Transportation Resiliency Planning

Hillsborough MPO Surface Transportation Resiliency Planning Hillsborough MPO Surface Transportation Resiliency Planning Allison Yeh, AICP, LEED GA NASEM_TRB Listening Session March 27, 2017 p l a n h i l l s b o r o u g h. o r g p l a n h i l l s b o r o u g h.

More information

I-64 Capacity Improvements Segment I Financial Plan Annual Update

I-64 Capacity Improvements Segment I Financial Plan Annual Update I-64 Capacity Improvements Segment I December 1, 2016 State Project # 0064-965-264, P101, R201, C501, B616, B617, B618, B619, B620, B621, D601, D602 Federal # NHS-064-3(479), NHA-064-3(479) UPC 104905

More information

AIR QUALITY TECHNICAL MEMORANDUM

AIR QUALITY TECHNICAL MEMORANDUM AIR QUALITY TECHNICAL MEMORANDUM AIR QUALITY TECHNICAL MEMORANDUM GOLDEN GLADES INTERCHANGE PD&E STUDY Miami-Dade County, Florida Financial Management Number: 428358-1-22-01 Efficient Transportation Decision

More information

FDOT PROJECT INFORMATION APPLICATION FORM

FDOT PROJECT INFORMATION APPLICATION FORM THIS FORM SHALL BE SUBMITTED FOR ALL PROJECTS NOT CURRENTLY IN THE FDOT WORK PROGRAM. FDOT PROJECT INFORMATION APPLICATION FORM DATE: APPLICANT: FDOT LIAISON: 1. MPO/TPO Project Priority Number: 2. Contact

More information

SR 9/I-95 Interchange at 45th Street PD&E Study Palm Beach County, Florida FPID No.: FAP No.: ETDM No.

SR 9/I-95 Interchange at 45th Street PD&E Study Palm Beach County, Florida FPID No.: FAP No.: ETDM No. Palm Beach County, Florida Palm Beach Metropolitan Planning Organization April 217 Project Study Area LIMITS: SR 9/I-95: from S of 45th Street to N of 45th Street 45th Street: From Village Boulevard to

More information

NEPA and Design Public Hearings

NEPA and Design Public Hearings NEPA and Design Public Hearings Monday, December 5, 2016 Washington-Lee High School 1301 N. Stafford Street Arlington, VA 22201 Thursday, December 8, 2016 Mary Ellen Henderson Middle School 7130 Leesburg

More information

I-35/I-80/Iowa 141 Interchange IJR and NEPA A Practical Approach to Resolving a Decades-Old Traffic Operations Challenge

I-35/I-80/Iowa 141 Interchange IJR and NEPA A Practical Approach to Resolving a Decades-Old Traffic Operations Challenge I-35/I-80/Iowa 141 Interchange IJR and NEPA A Practical Approach to Resolving a Decades-Old Traffic Operations Challenge Client: AJR or IJR? This is a TO-MAY-TO This is a TO-MAH-TO Practical Design PRACTICAL

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions) FY 2018-2027 WIDE TRANSPORTATION IMPROVEMENT PROGRAM ADA Central, Contract 3 DBNUM: 15419 / UPC: 154190 This contract will bring projects into compliance with current ADA design requirements that could

More information

Engineering & Capital Improvements. Shore Acres Civic Association August 21 st, 2017

Engineering & Capital Improvements. Shore Acres Civic Association August 21 st, 2017 Engineering & Capital Improvements Shore Acres Civic Association August 21 st, 2017 40 th Avenue N Bridge 34 th Avenue NE Storm Drainage Improvements Resiliency Planning Continued Maintenance 40 th Avenue

More information

ANSWERS TO QUESTIONS RECEIVED THROUGH 11:00 A.M. ON JANUARY 4, 2019:

ANSWERS TO QUESTIONS RECEIVED THROUGH 11:00 A.M. ON JANUARY 4, 2019: ADDENDUM NO. PROJECT NO. 3-9-07 PAGE 2 ANSWERS TO QUESTIONS RECEIVED THROUGH :00 A.M. ON JANUARY, 209: Q# Plan sheet 2 has a note MAINTENANCE OF TRAFFIC (LOCAL ROADS) which relates to bid item 22 and calls

More information

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV Noise Technical Report 2015 Addendum NOISE TECHNICAL REPORT 2015 Addendum PREPARED FOR: Federal Highway Administration and Georgia Department of Transportation PREPARED BY: Parsons Brinckerhoff Project

More information

Chapter 6: Regional Transportation

Chapter 6: Regional Transportation Chapter 6: Regional Transportation Continued growth and development throughout the region magnifies the significance of connections to surrounding counties as economic and social interactions continue

More information

Port Region Freight Profile and Project List. EA Transportation Committee

Port Region Freight Profile and Project List. EA Transportation Committee Port Region Freight Profile and Project List EA Transportation Committee Regional Partnership 2 Transportation Task Force East Harris County Mfg s Assoc. (130+ plants) 11 Regional Mayors Port of Houston

More information

STORMWATER MANAGEMENT REPORT

STORMWATER MANAGEMENT REPORT STORMWATER MANAGEMENT REPORT STORMWATER MANAGEMENT REPORT GOLDEN GLADES INTERCHANGE PD&E STUDY Miami-Dade County, Florida Financial Management Number: 428358-1-22-01 Efficient Transportation Decision Making

More information

9.0 I-26 & I-526 Interchange Improvements

9.0 I-26 & I-526 Interchange Improvements 9.0 I-26 & I-526 Interchange Improvements The I-26 & I-526 System-to-System interchange currently consists of a combination of directional and loop ramps providing for all movements from one Interstate

More information

Value Engineering For Transportation Improvements. Interstate 4 from West of State Road 528 (Beachline) to West of State Road 435 (Kirkman Road)

Value Engineering For Transportation Improvements. Interstate 4 from West of State Road 528 (Beachline) to West of State Road 435 (Kirkman Road) Value Engineering For Transportation Improvements Interstate 4 from West of State Road 528 (Beachline) to West of State Road 435 (Kirkman Road) Value Engineering Study Draft Report FM Number: 242484-7

More information

JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018

JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018 JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018 On Maintenance of Traffic Details Sheet No. 46 there is a note that states I-49 Stage Construction is to be Completed Prior to Beginning Work on Hwy.

More information

PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today!

PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today! PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today! FEBRUARY 12, 2014 FTBA CONSTRUCTION CONFERENCE PROJECT PARTNERS Public Sponsors 90% Equity Partner Contractor 10% Equity Partner Operator Federal

More information

Public Works Capital Projects Management. Presented by: Joseph Cordts P. E., Portfolio Manager Capital Projects Management

Public Works Capital Projects Management. Presented by: Joseph Cordts P. E., Portfolio Manager Capital Projects Management Public Works Capital Projects Management Presented by: Joseph Cordts P. E., Portfolio Manager Capital Projects Management Overview Capital Projects Management (CPM) is responsible for management of the

More information

PREPARED TESTIMONY OF LEE LISECKI. Q. Please state your name, professional position, and business address.

PREPARED TESTIMONY OF LEE LISECKI. Q. Please state your name, professional position, and business address. Application 06-12-005 et al. Exhibit Date: August, 2008 PREPARED TESTIMONY OF LEE LISECKI Q. Please state your name, professional position, and business address. A. My name is Lee Lisecki. I am a principal

More information

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 1 Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 2 During this public meeting, we will explain the 75 th Street Corridor Improvement

More information