BOND CONSTRUCTION UPDATE
|
|
- Scot Lynch
- 6 years ago
- Views:
Transcription
1 BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND 2013
2 CIBOLO VALLEY ELEMENTARY UPDATE SCUCISD BOND 2013 $ 34,000,000 Bond Allocation 900-1,200 Student Capacity 153,000 Square Feet Architects - O Neil Conrad Oppelt Architects Inc. & Pfluger & Associates General Contractor Bartlett Cocke Construction Management AG CM, Inc. March 31, 2015
3 CIBOLO VALLEY ELEMENTARY (GREEN VALLEY ROAD NEAR FM 1103 SITE) ES #8 CURRENT STATUS Brick installation ongoing on Pre-K/K grade wings and misc. interior areas Exterior CMU 99% complete; Interior CMU ongoing in restrooms, Pre-K/K MEP rough-ins continue in Pre-K/K HVAC Ductwork installation continues in Pre-K/K Window installation continues, 90% complete exterior Interior drywall continues throughout the building Interior painting continues in Areas A through D Floor tile installed in kitchen, and grouted Kitchen equipment installation ongoing Gymnasium equipment, pads, fans and lighting installed Boilers started up Ceiling Grid installation ongoing Irrigation installation started Millwork being delivered Elevator installation ongoing March/April Brick Veneer to continue on G Window and Storefront installation to complete Ceiling Grid installation continue Start up Chillers Irrigation and Landscape to continue Discovery Zone utilities, and flatwork Building E Discovery Zone structure to begin Restroom tile continue Plumbing Fixture installation to begin
4 CIBOLO VALLEY ELEMENTARY Perspective Views
5 CIBOLO VALLEY ELEMENTARY Front of School
6 CIBOLO VALLEY ELEMENTARY East Elevation (1103)
7 CIBOLO VALLEY ELEMENTARY nd Grade Wing
8 CIBOLO VALLEY ELEMENTARY Gymnasium
9 CIBOLO VALLEY ELEMENTARY Alley Between 1st/3rd Grade Wing & Pre-K/Kinder Wing Discovery Zone Alley
10 CIBOLO VALLEY ELEMENTARY CIBOLO VALLEY ES #8 SCHEDULE May Substantial Completion June SCUC Begins Moving In To Building August Project Complete
11 STEELE HIGH SCHOOL UPDATE SCUCISD BOND 2013 $ 25,000,000 Bond Allocation Three Story Academic Wing Addition 84,922 ft 2 Field House Addition 17,299 ft 2 Cafeteria Addition & Athletic Locker Room Renovation Architects - O Neil Conrad Oppelt Architects Inc. & Pfluger & Associates General Contractor Bartlett Cocke Construction Management AG CM, Inc. March 31, 2015
12 Steele High School Steele CURRENT STATUS Field House Exterior Brick Veneer nearly complete Field House interior walls being closed up Framing up walls and roughing-in MEP s at the Lower Level of the Academic Wing Academic Middle level Walls Framed Up and starting MEP Rough-Ins Academic Upper level Decking near complete Completed MEP Tie-Ins over the Spring Break Adding New Condenser Water Piping Between Cooling Towers and Chillers Cafeteria Brick veneer starting up April Continue MEP installation at Field House Academic Building will continue MEP Installation Start installing roof at the Academic building Waterproofing and brick veneer starting at Academic Wing Glass being installed at Field House, Cafeteria, and Academic Wing
13 Steele High School Academic Wing Academic Wing Rendering
14 Steele High School Academic Wing Academic Wing Decking Being Placed
15 Steele High School Academic Wing Academic Wing Mall Space
16 Steele High School Academic Wing Academic Wing Typical Science Classroom Framed Up
17 Steele High School Academic Wing Academic Wing Top Floor framing and rough ins starting up
18 Steele High School Field House Field House Rendering
19 Steele High School Field House Field House Exterior Brick Veneer Near Completion
20 Steele High School Field House Field House Locker Room Showers and Restrooms tiled and duct installed
21 Steele High School Cafeteria Expansion Cafeteria Expansion Duct and ceiling forms in place
22 Steele High School Schedule for Project: August General Contractor Selected September General Contractor begins Construction Substantial Completion Dates Academic Building Addition (Nov 2015) New Field House Building (July 2015) Renovation of Existing ROTC into Welding Shop (Feb 2016) Cafeteria Addition (June 2015) Changed from Nov 2015 Main Entry Renovations (Aug 2015) Renovation of PE Locker Rooms (Aug 2015) Feb Project Completion
23 DOBIE JUNIOR HIGH SCHOOL UPDATE SCUCISD BOND 2013 $ 10,000,000 Bond Allocation Proposed Site Improvements to Include New Drop-off Zone Proposed 8 New Classrooms / 1 New Science Lab Proposed New Kitchen Serving Lines Architect Marmon Mok General Contractor Krueger Construction Construction Management AG CM, Inc. March 31, 2015
24 Dobie JH School Renovations & Additions Dobie New Front Entry Rendering (View from Dietz Rd.)
25 Dobie JH School Renovations & Additions Dobie New Front Entry Rendering (View From Borgfeld Rd.)
26 Dobie JH School Renovations & Additions Schedule for Renovations & Additions February General Contractor Selected March Construction Begins Substantial Completion Dates April Phase 1 May Phase 2 August Phase 3 August Project Completion
PROJECT UPDATE SEPTEMBER 11, 2014
PROJECT UPDATE SEPTEMBER 11, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT
More informationPROJECT UPDATE August 28, 2014
PROJECT UPDATE August 28, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT
More informationUpdate on FCPS Construction/Renovation Projects. December 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (06-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE As
More informationUpdate on FCPS Construction/Renovation Projects. June 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationGEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012
GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown
More informationLLANO ISD SCHOOL BOARD MEETING. January 2016
LLANO ISD SCHOOL BOARD MEETING January 2016 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationUpdate on FCPS Construction/Renovation Projects. July 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-26-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 39% COMPLETE As
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction August 2013 Leroy San Miguel Dr. Folks Middle School ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE
More informationUpdate on FCPS Construction/Renovation Projects. November 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 33% COMPLETE As
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction January 2016 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction December 2017 Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (01-22-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 29% COMPLETE SAMUEL
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction September 2015 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationGREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015
GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations
More informationProject Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope
Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope
More informationMARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD
MARCH 2018 2016 BOND & TIF PROJECT UPDATE Grapevine-Colleyville ISD GHS Agricultural Sciences Building Renovation Multipurpose Activity Centers Additions and Renovations to TES and GMS Cannon Elementary
More informationUpdate on FCPS Construction/Renovation Projects. September 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationNew Ringgold Middle School. Project Slideshow August 26, 2017
New Ringgold Middle School Project Slideshow August 26, 2017 Aerial Photo from West Provided by Hudson Group Taken 8.16.2017 Aerial Photo from North Provided by Hudson Group Taken 8.16.2017 Aerial Photo
More informationBoard Work Session Feasibility Study. January 9, 2017
Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking
More information6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After
Contents 1 Program Outline Gymnasium Restrooms Storage rooms IDF 2 Finish Outline Walls Flooring Ceiling Roof 3 MEP Outline Plumbing Mechanical Electrical 4 Communication and Security Guideline Communication
More informationMONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District
MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #103 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 25215» Total Man Hours on Project: 915333» Crafts On Project This Week: 23» OSHA Recordable Rate: 0 CURRENT CONSTRUCTION ACTIVITIES East Zone» Continued MEP Rough-In
More informationCEFPI Monthly Meeting
CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type
More informationG703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project
Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction January 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
More informationCoos Bay Best Bond Cost Breakdowns
Coos Bay Best Bond Cost Breakdowns Overview [For itemized breakdown by school, see following pages.] Harding: New 7 th /8 th grade school on Harding site, including second gym: $18,440,000 Demotion of
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction March 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Jim
More information3. 21st Century Learning A. Districtwide Flexible Learning $600,000 Subtotal $600,000
1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades $300,000 C. Tilden Entrance Upgrades $50,000 D. Door and Glass Improvements $500,000 E. Alert Systems $800,000
More informationYardmen Arena Expansion & Renovation Project Update
For Immediate Release 25, September,2017 Yardmen Arena Expansion & Renovation Project Update BELLEVILLE ON With 33 days until puck drop of the home opening game of the American Hockey League s Belleville
More informationCOMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry
GREATER ALBANY PUBLIC SCHOOLS Critical Facility Upgrades 2018 Progress Update Investments in Existing Capital Assets: Safe Warm - Dry Critical Facility Upgrades Goals Investing in existing capital assets
More informationUpdate on FCPS Construction/Renovation Projects. August 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationCONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO
CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005
More informationSEATON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationRAYMOND EDUCATION CAMPUS
INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report November 2018 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School
More informationMaterial Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5
Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00
More informationLemm Elementary. Restoring the Heart of the Community. Klein Independent School District
Lemm Elementary Restoring the Heart of the Community Target Date: August 2018 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main
More informationBARNARD ELEMENTARY SCHOOL
INITIAL YEAR BUILT 2002 BUILDING AREA 67,000 SF CURRENT PROGRAM CAPACITY 520 ENROLLMENT 2008 329 WARD 4 PROPOSED PROGRAM CAPACITY 450 Site Plan BARNARD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationMOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS
MOORESTOWN HIGH SCHOOL 06/22/15 08/28/15 Security vestibule at main entrance and transportation office; replacement of selected exterior doors; access controls at exterior doors 06/22/15 12/31/15 Upgrade
More informationTOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018
TOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018 The February 5, 2018 meeting of the Manchester Building Committee was held in the Manchester Room at the Town Hall. Manchester Building
More informationSTRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC
CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION
More informationRevised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi
Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts
More informationUpdate on FCPS Construction/Renovation Projects. August 2016
Update on FCPS Construction/Renovation Projects New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost:
More informationBRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING
PROPOSED MAIN ENTRY - EXTERIOR RENDERING EXISTING SITE AERIAL PHOTOGRAPH 6TH STREET NW PEDESTRIAN ACCESS School access to existing alley leads students through vehicular path CHAIN LINK ENCLOSED PARKING
More informationProject Status Update & Progress Report
UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update
More informationCORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting
CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan Community Information Meeting October 2017 AGENDA Meeting Objectives Draft Plan Overview School Improvements for specific site Feedback/Listening
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #105 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 24125» Total Man Hours on Project: 965963» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 CURRENT CONSTRUCTION ACTIVITIES East Zone» Continued MEP Rough-In
More informationDISCOVERY ELEMENTARY SCHOOL
DISCOVERY ELEMENTARY SCHOOL COMMUNITY UPDATE #11 April 2015 COMPLETED AND ONGOING CONSTRUCTION ACTIVITIES The north half of the Discovery Elementary School (DES) building referred to below encompasses
More informationLECKIE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationHOMOGENEOUS AREAS LIST Asbestos
Elementary Campus 1985 Elementary uilding Wing (17,600 sq. ft.) uilding 12" floor tile (white/beige) and mastic 3,200 Square Feet Troughout building 2' x 2' ceiling tiles 10,000 Square Feet Gym (4,700
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationVoorhees Replacement Facility Schedule Summary Classic WBS Layout 29-Sep-09 13:50 Activity Name Original Start Finish Duration Voorhees Replacement F 1136 17-Nov-06 31-Mar-11 Schematic Design 87 17-Nov-06
More informationLOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN
INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS
More informationMinuteman Regional Vocational Technical School
Minuteman Regional Vocational Technical School List of Recommendations L1 AAB compliance: Improvements to front entrance (concrete ramps, railings, etc.) Required by AAB cost trigger L2 AAB compliance:
More informationFrost Technical Center
Frost Technical Center 1955 Greenhouses Addition Various other additions and renovations Provide site security improvements Provide improved Admin area field of view to site entrance Provide security camera
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationUbuildit. Construction Project Budget for Date Prepared wholesale retail
Ubuildit Construction Project Budget for Date Prepared wholesale retail Buyer: Address: City/St: Living Area SF Frame Ground Floor 170 Living Area SF Frame 2nd Floor 0 189.666667 total veneer total veneer
More informationProgram Update. Chino Health Science Parking Lot
Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #110 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 22420» Total Man Hours on Project: 1081124» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 CURRENT CONSTRUCTION ACTIVITIES East Zone» Continued Hanging
More informationProgram Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement
Projects under Construction Data and Telecom Cabling-VPA, New Gym, & Physical Science Architect/Engineer: P2S Engineering Original Contract: $154,882 Construction Manager: Bernards Approved Change Orders:
More informationUpper Adams School District Facility Study Presentation Part 2 November 17, 2016
Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Providing a Client Oriented Approach to Architecture Crabtree, Rohrbaugh & Associates, Architects Agenda Part 1 Current
More informationBALLOU SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE
More informationChino Valley Unified School District Monthly Construction Update
h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:
More informationIntroduction & Project Background
Introduction & Project Background Project Background is located in Pasadena, Maryland and is owned and maintained by Anne Arundel County School District. A new elementary school to replace the existing
More informationDeferred Maintenance Plan
Deferred Maintenance Plan 2012-2015 1/5/2012 1 Table of Contents Title Page Introduction 3 Wallace Hall Deferred Maintenance 4 Wallace Hall Building Assessment 6 Wilson Hall Deferred Maintenance 7 Wilson
More informationHOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #113 Douthit Hills Student Community, Clemson University Project Joe Jett
April 7, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Continued Finishing Drywall @ Building E. Continued Painting @ Bldg. E. Continued Wall Tile @ Bldg. E. Continued Installing Lights
More informationCONSTRUCTION COST BREAKDOWN THIS IS FORM CCB
CONSTRUCTION COST BREAKDOWN Property Owner s Name or Borrowers Name Brief Description of Project John Homeowner Build single family residence Property Address Property City Property Zip Code 4625 Jillbarr
More informationNALLE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationBiddeford School Department
Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6
More informationFACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture
FACILITY ASSESSMENT PRESENTATION 11 October 2017 SCHRADERGROUP architecture AGENDA 1. 1 Facility Assessment Review 2. 2 Prioritizing the Scope of Work with Associated Costs 3 Timeline of Work 3. 4 Procurement
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report September 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationArbor Heights Elementary School. Concrete for South Building Foundation Stem Walls
Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary
More informationBoard Report. Bond Program Update:
March 2014 Bond website: www.pcc.edu/bond Bond Program Update: Winter term is quickly coming to an end and as spring term approaches we have more buildings and areas opening for use for students and staff.
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction December 2013 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION
More informationFleet Elementary School
Fleet Elementary School Community Newsletter (January 2019) This is the January update on the status and progress of construction for the project. All monthly updates will also be posted to the project
More informationUNC Charlotte Science Building Project. Informational Meeting: May 3, 2018
UNC Charlotte Science Building Project Informational Meeting: May 3, 2018 Project Team Owner and Designers UNC Charlotte Donia Schauble Senior Project Manager - Design Jennifer Price Senior Construction
More informationCity High Middle School pre-design recommendations. March 29, 2017
City High Middle School pre-design recommendations March 29, 2017 City High Middle School table of contents 2 3 4 5 6 7 8 9 10 11 12 13 table of contents project description and purpose existing systems
More informationDAVIS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1943 BUILDING AREA 71,100 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 227 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan DAVIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-
More informationCollins Middle School
Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0
More informationSTUART-HOBSON MIDDLE SCHOOL
INITIAL YEAR BUILT 1927 BUILDING AREA 105,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 399 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan STUART-HOBSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationHartsville Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 8, 2012 Hartsville Area Schools - Building Evaluations School Name: West Hartsville Elementary Observed By: Cannon/Carter Principal:
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationCOOLIDGE SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1940 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1240 ENROLLMENT 2008 652 WARD 4 PROPOSED PROGRAM CAPACITY 1100 Site Plan COOLIDGE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationPOWELL ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1925 BUILDING AREA 38,500 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 319 WARD 4 PROPOSED PROGRAM CAPACITY 325 Site Plan POWELL - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-3
More informationSubject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3
MEMORANDUM To: Ashley Rosenthal Payne, Indianapolis Historic Preservation Commission Adrienne Schmetzer, Indiana Housing and Community Development Authority Architecture Preservation Interior Design Landscape
More informationSafety Update Crossing study is in final review stages. Facilities Update Construction Progress
Major Projects Update September 2017 Prepared by Business and Operations September 11, 2017 Transportation Update As of 9/6/17 we have 4,803 students registered for busing, up 643 from last month s update.
More informationAPPLICATION AND CERTIFICATE FOR PAYMENT
AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in
More informationDENNIS TOWNSHIP FEASIBILITY STUDY
DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT
More information