SECTION A. Examination, preparation, and general installation procedures.

Size: px
Start display at page:

Download "SECTION A. Examination, preparation, and general installation procedures."

Transcription

1 SECTION PART 1 GENERAL 1.1 SECTION INCLUDES A. Examination, preparation, and general installation procedures. B. Cutting and patching. C. Cleaning and protection. D. Substantial Completion E. Final Completion F. Closeout procedures, including Contractor's Correction Punch List, except payment procedures. 1.2 REFERENCE STANDARDS A. NFPA Standard for Safeguarding Construction, Alteration, and Demolition Operations; SUBSTANTIAL COMPLETION A. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request. 1. Prepare and submit a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete. Additionally, attach a copy of work required for each room to the door entering the room. Subcontractor and Superintendent to initial as each Work item is completed. Attach supplemental lists as required. 2. Submit specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents. 3. Obtain and submit releases permitting Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases by applicable authorities having jurisdiction. 4. Terminate and remove temporary facilities from Project site, along with mockups, construction tools, and similar elements. 5. Submit changeover information related to Owner's occupancy, use, operation, and maintenance (including Operation & Maintenance Manuals). 6. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects. B. Inspection Procedures: Submit a written request for inspection for Substantial Completion a minimum of seven (7) days in advance of the requested Substantial Completion inspection date. On receipt of request, Architect may notify Contractor of unfulfilled requirements. On Technology and Millwork Upgrades to Double Jury Courtroom in the 7th Judicial Circuit Court Issued for Construction

2 date of inspection, Architect will conduct a review and either proceed with inspection or notify Contractor that the project is not Substantially Complete due to unfulfilled requirements. 1. Upon inspection the Architect and the Owner s representative will accompany the Contractor on a walk-through review of the Contractor s punch list. Should the Architect and/or the Owner s representative observe work which is incomplete or defective which is not included on the contractor s punch list, the Architect will prepare a supplemental punch list of items to be completed or corrected. 2. Architect will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Architect, that must be completed or corrected before certificate will be issued. 3. Results of the completed inspection will form the basis of requirements for establishing Final Completion. 1.4 FINAL COMPLETION A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following: 1. Submit a final Application for Payment according to Division 01 Section "Price and Payment Procedures". 2. Submit certified copy of Architect's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Contractor. The certified copy of the list shall state that the Work, including each item on the list has been completed or otherwise resolved for acceptance. Provide explanations for each proposed resolution to incomplete items. 3. Submit evidence of final, continuing insurance coverage complying with insurance requirements. 4. Submit pest-control final inspection report and warranty. 5. Instruct Owner's personnel in operation, adjustment, and maintenance of products, equipment, and systems. Submit demonstration and training videos. Obtain signed attendance sheets and submit them to the Architect. B. Inspection Procedures: Submit a written request for inspection for Final Completion, a minimum of (7) days in advance of the requested Final Completion Inspection Date. On receipt of request, Architect [and Construction Manager] may notify Contractor of unfulfilled requirements. On date of inspection, Architect [and Construction Manager] will conduct a review and either proceed with inspection or notify Contractor that the project is not Finally Complete due to unfulfilled requirements. 1. Upon Inspection the Architect and the Owner s representative will accompany the Contractor s superintendent on a walk-through review of the Substantial Completion punch list. 2. Architect will process the final Application for Payment after inspection providing all closeout documentation has been received and is acceptable, or the Architect will notify Contractor of construction and/or documentation that must be completed or corrected before final Application for Payment will be processed Issued for Construction

3 1.5 LIST OF INCOMPLETE ITEMS (PUNCH LIST) A. Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction. 1. Organize list of spaces in sequential order, starting with exterior areas first and proceeding from lowest floor to highest floor. 2. Organize items applying to each space by major element, including categories for ceiling, individual walls, floors, equipment, and building systems. 3. Indicate the subcontractor responsible for each item; provide spaces for subcontractor and superintendent to initial each item as Work is completed. 4. Include the following information at the top of each page: a. Project name. b. Date. 1.6 WARRANTIES c. Name of Architect. d. Name of Contractor. e. Page number. A. Submittal Time: Submit written warranties on request of Architect for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated. B. Partial Occupancy: Submit properly executed warranties within 15 days of completion of designated portions of the Work that are completed and occupied or used by Owner during construction period by separate agreement with Contractor. C. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual. 1. Bind warranties and bonds in heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch (215-by-280-mm) paper. 2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer. 3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor. D. Provide additional copies of each warranty to include in operation and maintenance manuals. PART 2 PRODUCTS 2.1 PATCHING MATERIALS A. General: Comply with requirements specified in other Sections. Issued for Construction

4 B. New Materials: As specified in product sections; match existing products and work for patching and extending work. C. Type and Quality of Existing Products: Determine by inspecting and testing products where necessary, referring to existing work as a standard. 1. If identical materials are unavailable or cannot be used, use materials that, when installed, will match the visual and functional performance of in-place materials. D. Product Substitution: For any proposed change in materials, submit request for substitution described in Section Product Requirements. 2.2 CLEANING PRODUCTS A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces. PART 3 EXECUTION 3.1 EXAMINATION A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent work. Start of work means acceptance of existing conditions. B. Verify that existing substrate is capable of structural support or attachment of new work being applied or attached. C. Examine and verify specific conditions described in individual specification sections. D. Take field measurements before confirming product orders or beginning fabrication, to minimize waste due to over-ordering or misfabrication. E. Verify that utility services are available, of the correct characteristics, and in the correct locations. F. Prior to Cutting: Examine existing conditions prior to commencing work, including elements subject to damage or movement during cutting and patching. After uncovering existing work, assess conditions affecting performance of work. Beginning of cutting or patching means acceptance of existing conditions. G. Compatibility: Before patching, verify compatibility with and suitability of substrates, including compatibility with in-place finishes or primers. H. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected. 3.2 PREPARATION A. Clean substrate surfaces prior to applying next material or substance. B. Seal cracks or openings of substrate prior to applying next material or substance. C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond. D. Temporary Support: Provide temporary support of Work to be cut Issued for Construction

5 E. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations. F. Adjoining Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas. G. Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems are required to be removed, relocated, or abandoned, bypass such services/systems before cutting to minimize interruption to occupied areas. 3.3 GENERAL INSTALLATION A. Install products as specified in individual sections, in accordance with manufacturer's instructions and recommendations, and so as to avoid waste due to necessity for replacement. B. Make vertical elements plumb and horizontal elements level, unless otherwise indicated. C. Install equipment and fittings plumb and level, neatly aligned with adjacent vertical and horizontal lines, unless otherwise indicated. D. Make consistent texture on surfaces, with seamless transitions, unless otherwise indicated. E. Make neat transitions between different surfaces, maintaining texture and appearance. 3.4 CUTTING AND PATCHING A. Whenever possible, execute the work by methods that avoid cutting or patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay. 1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition. B. Perform whatever cutting and patching is necessary to: 1. Complete the work. 2. Fit products together to integrate with other work. 3. Provide openings for penetration of mechanical, electrical, and other services. 4. Match work that has been cut to adjacent work. 5. Repair areas adjacent to cuts to required condition. 6. Repair new work damaged by subsequent work. 7. Remove samples of installed work for testing when requested. 8. Remove and replace defective and non-conforming work. C. Execute work by methods that avoid damage to other work and that will provide appropriate surfaces to receive patching and finishing. In existing work, minimize damage and restore to original condition. D. Employ skilled and experienced installer to perform cutting for weather exposed and moisture resistant elements, and sight exposed surfaces. Issued for Construction

6 E. Cut rigid materials such as concrete and masonry using masonry saw or core drill. Pneumatic tools not allowed without prior approval. F. Restore work with new products in accordance with requirements of Contract Documents. G. Fit work air tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces. H. At penetrations of fire rated walls, partitions, ceiling, or floor construction, completely seal voids with fire rated material in accordance with Section , to full thickness of the penetrated element. I. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as possible. Provide materials and comply with installation requirements specified in other Sections. 1. Finish patched surfaces to match finish that existed prior to patching. On continuous surfaces, refinish to nearest intersection or natural break. For an assembly, refinish entire unit. 2. Match color, texture, and appearance. 3. Repair patched surfaces that are damaged, lifted, discolored, or showing other imperfections due to patching work. If defects are due to condition of substrate, repair substrate prior to repairing finish. 4. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate integrity of installation. 5. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing. a. Clean piping, conduit, and similar features before applying paint or other finishing materials. b. Restore damaged pipe covering to its original condition. 6. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance. a. Where patching occurs in a painted surface, apply primer and intermediate paint coats over the patch and apply final paint coat over entire unbroken surface containing the patch. Provide additional coats until patch blends with adjacent surfaces. 7. Ceilings: Patch, repair, or rehang in-place ceilings as necessary to provide an even-plane surface of uniform appearance. 8. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition Issued for Construction

7 3.5 PROGRESS CLEANING A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition. B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space. C. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust. D. Collect and remove waste materials, debris, and trash/rubbish from site periodically and dispose off-site; do not burn or bury. 3.6 PROTECTION OF INSTALLED WORK A. Protect installed work from damage by construction operations. B. Provide special protection where specified in individual specification sections. C. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage. D. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings. E. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials. F. Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer. G. Remove protective coverings when no longer needed; reuse or recycle plastic coverings if possible. 3.7 ADJUSTING A. Adjust operating products and equipment to ensure smooth and unhindered operation. 3.8 FINAL CLEANING A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations. B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions. 1. Use cleaning materials that are nonhazardous. 2. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces. 3. Remove all labels that are not permanent. Do not paint or otherwise cover fire test labels or nameplates on mechanical and electrical equipment. Issued for Construction

8 4. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned. 5. Clean filters of operating equipment. 6. Clean debris from roofs, gutters, downspouts, scuppers, overflow drains, area drains, drainage systems, and. 7. Clean site; sweep paved areas, rake clean landscaped surfaces. 8. Remove waste, surplus materials, trash/rubbish, and construction facilities from the site; dispose of in legal manner; do not burn or bury. 3.9 CLOSEOUT PROCEDURES A. Make submittals that are required by governing or other authorities. 1. Provide copies to Genesee County. B. Notify Architect/Engineer when work is considered ready for Architect/Engineer's Substantial Completion inspection. C. Submit written certification containing Contractor's Correction Punch List, that Contract Documents have been reviewed, work has been inspected, and that work is complete in accordance with Contract Documents and ready for Architect/Engineer's Substantial Completion inspection. D. Conduct Substantial Completion inspection and create Final Correction Punch List containing Architect/Engineer's and Contractor's comprehensive list of items identified to be completed or corrected and submit to Architect/Engineer. E. Correct items of work listed in Final Correction Punch List and comply with requirements for access to Genesee County-occupied areas. F. Notify Architect/Engineer when work is considered finally complete and ready for Architect/Engineer's Substantial Completion final inspection. G. Complete items of work determined by Architect/Engineer listed in executed Certificate of Substantial Completion. END OF SECTION Issued for Construction

Lantz-Boggio Architects, P.C LBA Project No

Lantz-Boggio Architects, P.C LBA Project No SECTION 01 7000- PART 1 GENERAL 1.01 SECTION INCLUDES A. Examination, preparation, and general installation procedures. B. Pre-installation meetings. C. Cutting and patching. D. Surveying for laying out

More information

Copyright 2010 AIA Georgia Institute of Technology Facilities Closeout Procedures. 2/15

Copyright 2010 AIA Georgia Institute of Technology Facilities Closeout Procedures. 2/15 SECTION 017700 - CLOSEOUT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following: 1.

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT)

1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT) 1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT) The use of an existing elevator during construction shall be strictly prohibited. Any deviation

More information

Specific requirements for individual units of work are included in the appropriate sections in Divisions 2 through 16.

Specific requirements for individual units of work are included in the appropriate sections in Divisions 2 through 16. SECTION 01 77 00 - PROJECT CLOSE-OUT PART 1 - GENERAL DESCRIPTION OF REQUIREMENTS: Definitions: Project close-out is the term used to describe certain collective project requirements, indicating completion

More information

FILED: NEW YORK COUNTY CLERK 05/04/ :16 PM

FILED: NEW YORK COUNTY CLERK 05/04/ :16 PM EXHIBIT P SECTION 01 73 10 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

SECTION CLOSEOUT PROCEDURES

SECTION CLOSEOUT PROCEDURES SECTION 017700 - PART 1 - GENERAL 1.1 SUMMARY A. Section includes requirements for contract closeout, including, but not limited to, the following: 1. Substantial Completion procedures. 2. Final Completion

More information

END OF SECTION SECTION FINAL CLEANING PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDE

END OF SECTION SECTION FINAL CLEANING PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDE d. Clean exposed hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Plumbing Contractor: Clean

More information

A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:

A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following: SECTION 01 73 00 - EXECUTION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following: SECTION 01700 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 RELATED DOCUMENTS 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

SECTION GENERAL REQUIREMENTS

SECTION GENERAL REQUIREMENTS SECTION 01005 GENERAL REQUIREMENTS PART 1 GENERAL 1.01 WORK COVERED BY CONTRACT DOCUMENTS A. Work of this Contract comprises the chiller and cooling tower replacement at Five Oaks Middle School which includes

More information

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of: 02070 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 STIPULATIONS A. The specifications sections " General Conditions of the Construction Contract ", "Special Conditions", and "Division 1 - General Requirements"

More information

SAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION

SAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION SECTION 02 41 14 SELECTIVE BUILDING DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Procedures for systematic removal of site improvements or portions of exterior and interior of buildings

More information

SECTION SUMMARY OF WORK

SECTION SUMMARY OF WORK SECTION 01010 - SUMMARY OF WORK PART 1 - GENERAL 1.01 SUMMARY OF WORK A. Work covers construction of the new Southeast Kentucky Regional Business Park Speculative Building #3, with associated site work.

More information

B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner.

B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner. SECTION 02 41 19 - SELECTIVE STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

155 North Beech, Casper, WY * (307) * (307) Fax INDEX

155 North Beech, Casper, WY * (307) * (307) Fax INDEX INSTRUCTION TO BIDDERS 155 North Beech, Casper, WY 82602 * (307) 265-0603 * (307) 266-5414 Fax PART 1: INSTRUCTION TO BIDDERS INDEX BIDDING DOCUMENTS. 2 CONTRACTOR APPLICATION FORM.2 EXAMINATION OF CONTRACT

More information

DIVISION 02 SELECTIVE DEMOLITION

DIVISION 02 SELECTIVE DEMOLITION DIVISION 02 SELECTIVE DEMOLITION SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building.

More information

1. Before selective demolition, Owner will remove the following items:

1. Before selective demolition, Owner will remove the following items: SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Demolition and removal of selected portions of building or structure. 2. Demolition and removal of selected

More information

DIVISION 2- EXISTING CONDITIONS

DIVISION 2- EXISTING CONDITIONS DIVISION 2- EXISTING CONDITIONS 024100- SELECTIVE DEMOLITION PART 1 - GENERAL: 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

A. The extent of Selective Demolition Work is that Work necessary, and required to facilitate the new construction indicated.

A. The extent of Selective Demolition Work is that Work necessary, and required to facilitate the new construction indicated. Project No. El611-0l SECTION 02 41 00 - SELECTIVE DEMOLITION PART1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

SECTION INTUMESCENT MASTIC FIREPROOFING

SECTION INTUMESCENT MASTIC FIREPROOFING PART 1 GENERAL 1.01 SUMMARY SECTION 07 81 23 - INTUMESCENT MASTIC FIREPROOFING A. Section Includes: 1. Intumescent Mastic Fireproofing for Application to Exposed Steel 2. Protection of Adjacent Surfaces

More information

EXECUTION REQUIREMENTS

EXECUTION REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes: Execution requirements. B. Related Requirements: 1. Specification Sections 2 through 49. PART 2 - PRODUCTS (Not Used). PART 3 - EXECUTION 3.1 SAFETY 01

More information

BuildingName The Description of the Project P DOCUMENTS

BuildingName The Description of the Project P DOCUMENTS ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

A New Barn for Brian & Julie Sims FM 2590 Canyon, TX. Gregg Bliss, Architect 1001 S.E. 3rd Ave. Amarillo, TX

A New Barn for Brian & Julie Sims FM 2590 Canyon, TX. Gregg Bliss, Architect 1001 S.E. 3rd Ave. Amarillo, TX A New Barn for Brian & Julie Sims 21400 FM 2590 Canyon, TX Gregg Bliss, Architect 1001 S.E. 3rd Ave. Amarillo, TX 79102 806-372-2966 14-020 Division Section Title Pages PROCUREMENT AND CONTRACTING DOCUMENTS

More information

A. Section includes: removal of paving, pipes and utilities, and other site items as required by the project drawings.

A. Section includes: removal of paving, pipes and utilities, and other site items as required by the project drawings. SECTION 024113 - SITE DEMOLITION PART 1 -GENERAL 1.1 SUMMARY A. Section includes: removal of paving, pipes and utilities, and other site items as required by the project drawings. 1.2 SUBMITTALS A. Obtain

More information

SECTION SUMMARY

SECTION SUMMARY PART 1 GENERAL 1.01 PROJECT SECTION 01 1000 SUMMARY A. Project Name: BRIDGEWALK 2010 GENERAL RENOVATION. B. Owner's Name: Boulder Housing Partners. C. Architect's Name: Odell Architects. D. The Project

More information

SECTION SELECTIVE DEMOLITION

SECTION SELECTIVE DEMOLITION SECTION 024113- PART 1 - GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to the

More information

ReCote Finish System over Concrete

ReCote Finish System over Concrete Part 1 General 1.01 GENERAL A. The Master Wall ReCote Finish System for smooth precast and cast in place concrete consists of an acrylic primer and ReCote acrylic finish. When needed an acrylic modified

More information

Richmond Hill Primary Renovation SECTION SELECTIVE DEMOLITION

Richmond Hill Primary Renovation SECTION SELECTIVE DEMOLITION SECTION 024119 SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

TILE TILE

TILE TILE 09300 - TILE 09300-1 PART ONE: GENERAL 1.1 Description TILE 1.1.1 Work of this Section, as shown or specified, shall be provided by the Interior Contractor and shall be in accordance with the requirements

More information

SECTION ALTERATION PROJECT PROCEDURES

SECTION ALTERATION PROJECT PROCEDURES SECTION 013516 ALTERATION PROJECT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Requirements for protection of existing facilities during construction operations. 2. Demolition and removals

More information

ACTIVATE BOSTON MARKET & QDOBA

ACTIVATE BOSTON MARKET & QDOBA 35% SUBMITTAL 95% SUBMITTAL SOLICITATION ADDENDUM #1 1 TE OF I LLI N S OI ST A 16 MAR 2016 20 APR 2016 3 JUNE 2016 21 JULY 2016 E NS E CT TE LIC NORMAN J. BOCHENEK 001-010280 D A RC H I The Jenkins Group

More information

PROJECT MANUAL. for. NEW MEXICO STATE UNIVERSITY GERALD THOMAS HALL Fume Hood Replacement at the MAIN CAMPUS for LAS CRUCES, NEW MEXICO

PROJECT MANUAL. for. NEW MEXICO STATE UNIVERSITY GERALD THOMAS HALL Fume Hood Replacement at the MAIN CAMPUS for LAS CRUCES, NEW MEXICO PROJECT MANUAL for NEW MEXICO STATE UNIVERSITY GERALD THOMAS HALL Fume Hood Replacement at the MAIN CAMPUS for LAS CRUCES, NEW MEXICO FOR REVIEW ONLY NOT FOR CONSTRUCTION December 2016 SET NO. 6501 Americas

More information

SECTION MULTICOLOR INTERIOR FINISHING

SECTION MULTICOLOR INTERIOR FINISHING SECTION 09 94 19 MULTICOLOR INTERIOR FINISHING SPEC WRITER NOTE: Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section Includes:

More information

ITT at Daniel Webster College 3/2010 SECTION ITT AT DANIEL WEBSTER COLLEGE UNIVERSITY DRIVE NASHUA NEW HAMPSHIRE MARCH ARCHITECT:

ITT at Daniel Webster College 3/2010 SECTION ITT AT DANIEL WEBSTER COLLEGE UNIVERSITY DRIVE NASHUA NEW HAMPSHIRE MARCH ARCHITECT: SECTION 00001 ITT AT DANIEL WEBSTER COLLEGE UNIVERSITY DRIVE NASHUA NEW HAMPSHIRE MARCH 9 2010 ARCHITECT: DENNIS MIRES PA THE ARCHITECTS 697 UNION STREET MANCHESTER, NEW HAMPSHIRE 03104 603-625-4548 ITT

More information

SECTION HANDRAILS AND RAILINGS. A. Section Cast-In-Place Concrete; coordination with substrate.

SECTION HANDRAILS AND RAILINGS. A. Section Cast-In-Place Concrete; coordination with substrate. SECTION 05520 HANDRAILS AND RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES A. Welded stainless steel railing systems. 1.2 RELATED SECTIONS A. Section 03300 - Cast-In-Place Concrete; coordination with substrate.

More information

SECTION BASIC ELECTRICAL MATERIALS AND METHODS

SECTION BASIC ELECTRICAL MATERIALS AND METHODS SECTION 26 05 05 BASIC ELECTRICAL MATERIALS PART 1 - GENERAL 1.1 SUMMARY A. Section includes the limited scope construction materials and methods for application with electrical installations as follows:

More information

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection SECTION 13090 RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13090-1 LOW INTENSITY RADIATION PROTECTION

More information

University of New Hampshire Scholars' Repository

University of New Hampshire Scholars' Repository University of New Hampshire University of New Hampshire Scholars' Repository Division 07 Thermal and Moisture Protection Chapter 5 Technical Construction and Renovation Standards 1-25-2013 075423 - TPO

More information

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION SECTION 072700 VAPOR PERMEABLE AIR BARRIER LIQUID MEMBRANE PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. The Work of this Section, as shown or specified, shall be in accordance with the requirements of the

More information

ROOF BALLAST MATERIALS ARCHITECTURAL CONCRETE PAVING SLABS SRS LEVELING BLOCK SYSTEM INSTALLATION PART GENERAL 1.

ROOF BALLAST MATERIALS ARCHITECTURAL CONCRETE PAVING SLABS SRS LEVELING BLOCK SYSTEM INSTALLATION PART GENERAL 1. 07555 - ROOF BALLAST MATERIALS ARCHITECTURAL CONCRETE PAVING SLABS SRS LEVELING BLOCK SYSTEM INSTALLATION PART 1.00 - GENERAL 1.01 SUMMARY: A. The work of this section consists of furnishing and installing

More information

SECTION RESILIENT SHEET FLOORING

SECTION RESILIENT SHEET FLOORING SECTION 09 65 16 RESILIENT SHEET FLOORING SPEC WRITER NOTE: Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1.

More information

Division 09 FINISHES TABLE OF CONTENTS

Division 09 FINISHES TABLE OF CONTENTS Division 09 FINISHES TABLE OF CONTENTS 09 1000 GENERAL... 3 A. RELATED SECTIONS... 3 B. MAINTENANCE OF FINISHES... 3 C. PUBLIC AREAS... 3 D. CUTTING AND PATCHING... 3 E. CLEANING... 3 F. RECOMMENDED FLOORING

More information

SECTION MODIFIED BITUMINOUS SHEET WATERPROOFING

SECTION MODIFIED BITUMINOUS SHEET WATERPROOFING SECTION 07 13 52 MODIFIED BITUMINOUS SHEET WATERPROOFING SPEC WRITER NOTE: Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section

More information

SECTION CUTTING AND PATCHING

SECTION CUTTING AND PATCHING SECTION 01 04 50 PART 1 - GENERAL 1.1 RELATED DOCUMENTS CUTTING AND PATCHING A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS PRODUCTION SPECIFICATIONS SECTION 03135 INSULATED CONCRETE FORMS PART 1 GENERAL 1.1 SECTION INCLUDES A. Insulated panel permanent concrete form system for: 1. Exterior structural wall panels. 2. Interior

More information

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS PRODUCTION SPECIFICATIONS SECTION 03135 INSULATED CONCRETE FORMS PART 1 GENERAL 1.1 SECTION INCLUDES A. Insulated panel permanent concrete form system for: 1. Exterior structural wall panels. 2. Interior

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

This Section includes surface preparation and field application of anti-graffiti coating systems for the following vertical and horizontal surfaces:

This Section includes surface preparation and field application of anti-graffiti coating systems for the following vertical and horizontal surfaces: 0 0 0 0 0 0 SECTION 0 ANTI- GRAFFITI COATINGS PART - GENERAL RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division Specification

More information

ACADEMIC SUCCESS CENTER THE COLLEGE AT BROCKPORT STATE UNIVERSITY OF NEW YORK PROJECT NO

ACADEMIC SUCCESS CENTER THE COLLEGE AT BROCKPORT STATE UNIVERSITY OF NEW YORK PROJECT NO SECTION 09 65 16 - RESILIENT SHEET FLOORING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION FLUID-APPLIED WATERPROOFING

SECTION FLUID-APPLIED WATERPROOFING SECTION 07140 FLUID-APPLIED WATERPROOFING PART 1 GENERAL 1.1 SUMMARY A. Section includes fluid applied rubberized asphalt and/or elastomeric membrane waterproofing; and surface dusting and/or protective

More information

A. Omega-Lite aluminum-faced composite panels, air and vapor barrier, attachments and sealants.

A. Omega-Lite aluminum-faced composite panels, air and vapor barrier, attachments and sealants. Section 07 42 13 Page 1 PART 1 GENERAL 1.1 SECTION INCLUDES A. Omega-Lite aluminum-faced composite panels, air and vapor barrier, attachments and sealants. 1.2 RELATED SECTIONS A. Section 06112 - Framing

More information

RENOVATE BUILDING 18-C FTFA SECTION GYPSUM BOARD 05/11

RENOVATE BUILDING 18-C FTFA SECTION GYPSUM BOARD 05/11 SECTION 09 29 00 GYPSUM BOARD 05/11 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text

More information

SECTION MOISTURE RESISTANT/WATER-PROOF FLOORING ADHESIVE FOR CONCRETE SLABS

SECTION MOISTURE RESISTANT/WATER-PROOF FLOORING ADHESIVE FOR CONCRETE SLABS SECTION 09699 MOISTURE RESISTANT/WATER-PROOF FLOORING ADHESIVE FOR CONCRETE SLABS PART 1 GENERAL 1.1 SECTION INCLUDES A. Testing and application of systems for the reduction of moisture resistant or water-proof

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 099600 - HIGH PERFORMANCE COATINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

ADDENDUM NO. 1. TO SCOPE OF WORK: Section 0220, Form 01004/5

ADDENDUM NO. 1. TO SCOPE OF WORK: Section 0220, Form 01004/5 ADDENDUM NO. 1 TO SCOPE OF WORK: Section 0220, Form 01004/5 PROJECT: Tankless Water Heaters Installation Glenn Edge and Rich Martin Apartments and Main Office Water Heater Replacement New Memorial Community

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 096519 - RESILIENT TILE FLOORING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION WELDED STEEL PICKET FENCE. 1. Fusion welded and rackable ornamental steel picket fence system.

SECTION WELDED STEEL PICKET FENCE. 1. Fusion welded and rackable ornamental steel picket fence system. PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Fusion welded and rackable ornamental steel picket fence system. B. Related sections: 1. Section 03310 Concrete Work for post support. 2. Section 09960

More information

A. Section includes Sprayed Fire-Resistive Materials: (SFRM) A. Pre-Installation Conference: Conduct conference at Project Site.

A. Section includes Sprayed Fire-Resistive Materials: (SFRM) A. Pre-Installation Conference: Conduct conference at Project Site. SECTION 078100 - APPLIED FIREPROOFING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Amendments to General Conditions and Division 01 Specification

More information

ALL DIMENSIONS FROM FINISHED FACE OF PARTITION TO FINISHED FACE OF PARTITION UNLESS OTHERWISE NOTED.

ALL DIMENSIONS FROM FINISHED FACE OF PARTITION TO FINISHED FACE OF PARTITION UNLESS OTHERWISE NOTED. ALL DIMENSIONS FROM FINISHED FACE OF PARTITION TO FINISHED FACE OF PARTITION UNLESS OTHERWISE NOTED. PARTITION CONSTRUCTION TO BE 3 5/8 METAL STUDS 24 ON CENTER WITH 5/8 TYPE X GYPSUM BOARDS BOTH SIDES.

More information

ASPIRE HEALTH PARTNERS. Project Specifications. Patient Tower Reroof 1800 Mercy Drive Orlando, Florida August 31, 2016

ASPIRE HEALTH PARTNERS. Project Specifications. Patient Tower Reroof 1800 Mercy Drive Orlando, Florida August 31, 2016 ASPIRE HEALTH PARTNERS Patient Tower Reroof 1800 Mercy Drive 32808 Project Specifications August 31, 2016 RS&H, Inc. 301 East Pine Street, Suite 350 32801 (407) 893.5800 RS&H Project # 504-0052-000 TABLE

More information

SECTION PENETRATION FIRESTOPPING PART 1- GENERAL PART 2- PRODUCTS 1.1 RELATED DOCUMENTS

SECTION PENETRATION FIRESTOPPING PART 1- GENERAL PART 2- PRODUCTS 1.1 RELATED DOCUMENTS SECTION 07 8413- PENETRATION FIRESTOPPING PART 1- GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION COMMON WORK RESULTS FOR ELECTRICAL

SECTION COMMON WORK RESULTS FOR ELECTRICAL PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

More information

HOTEL SANDFORD. C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated.

HOTEL SANDFORD. C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated. SECTION 024119 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information

SECTION EMBEDDED CMU/SPLIT FACE ARCHITECTURAL PRECAST/SITECAST CONCRETE. A. Site Cast or Tilt-Up CMU/Split Face Concrete Panels.

SECTION EMBEDDED CMU/SPLIT FACE ARCHITECTURAL PRECAST/SITECAST CONCRETE. A. Site Cast or Tilt-Up CMU/Split Face Concrete Panels. SECTION 03460 EMBEDDED CMU/SPLIT FACE ARCHITECTURAL PRECAST/SITECAST CONCRETE PART 1 GENERAL 1.1 SECTION INCLUDES A. Site Cast or Tilt-Up CMU/Split Face Concrete Panels. B. Shop/Plant Cast CMU/Split Face

More information

Section HIGH-TENSION Stretched-Fabric Wall Systems SoftWalls, Inc.

Section HIGH-TENSION Stretched-Fabric Wall Systems SoftWalls, Inc. P a g e 1 PART I. GENERAL 1.01 Scope A. Furnish and install SoftWalls HIGH-TENSION Acoustical & Tackable Stretch Fabric Systems B. Related Work Specified Elsewhere: 1.Preparation of a smooth, flat and

More information

SECTION A. Product Data: Manufacturer's data sheets on each product to be used, including:

SECTION A. Product Data: Manufacturer's data sheets on each product to be used, including: Page 1 of 7 SECTION 083925 MECHANICAL ROOM FLOOD DOORS AND FRAMES **Note to Specifier** This specification contains component and configuration options. Where indicated, choose the appropriate choice for

More information

SECTION A. Product Data: Manufacturer's data sheets on each product to be used, including:

SECTION A. Product Data: Manufacturer's data sheets on each product to be used, including: Page 1 of 8 SECTION 083919 WATERTIGHT DOORS **Note to Specifier** This specification contains component and configuration options. Where indicated, choose the appropriate choice for your specific project

More information

SECTION PROJECT CLOSEOUT

SECTION PROJECT CLOSEOUT PART 1 - GENERAL 1.01 SCOPE OF WORK A. This Section specifies administrative and procedural requirements for project closeout, including but not limited to: 1. Close-out procedures 2. Final cleaning 3.

More information

1. Decks, balconies, and sun porches 2. Walkways, ramps, and stairways 3. Patios and courtyards

1. Decks, balconies, and sun porches 2. Walkways, ramps, and stairways 3. Patios and courtyards SECTION 07185 TRAFFIC MEMBRANE PART 1 GENERAL 1.1 SECTION INCLUDES A. Traffic membrane, consisting of welded seam PVC waterproofing, over f following surfaces: 1. Decks, balconies, and sun porches 2. Walkways,

More information

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 07 Thermal and Moisture Protection 8400 Firestopping

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 07 Thermal and Moisture Protection 8400 Firestopping 1 General 1.1 The bidding requirements, contracting requirements, and applicable parts of Division 1 - General Requirements, as listed in the Table of Contents, shall be included in and made a part of

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 024116 - STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

CITY OF RICHMOND PINE CAMP COMMUNITY CENTER ROOF REPLACEMENT PROJECT RCS PROJECT NO

CITY OF RICHMOND PINE CAMP COMMUNITY CENTER ROOF REPLACEMENT PROJECT RCS PROJECT NO SECTION 01010 - SCOPE OF WORK PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. General provisions of Contract, General Conditions and Technical Specification Sections, apply to this Section. 1.02 PROJECT DESCRIPTION

More information

SECTION RESILIENT TILE FLOORING. A. Section includes vinyl composition floor tile and accessories indicated and as specified.

SECTION RESILIENT TILE FLOORING. A. Section includes vinyl composition floor tile and accessories indicated and as specified. SECTION 09 65 19 RESILIENT TILE FLOORING PART 1 - GENERAL 1.1 SUMMARY A. Section includes vinyl composition floor tile and accessories indicated and as specified. 1.2 SUBMITTALS A. Product Data: Submit

More information

SECTION Specification for Building Limes Specification For Building Sands from Natural Sources Methods of Tests for Paints.

SECTION Specification for Building Limes Specification For Building Sands from Natural Sources Methods of Tests for Paints. SECTION 09200 PART 1 - GENERAL 1.01 DESCRIPTION A. Extent of Work: The extent of lath and plaster work is shown on the drawings and in schedules and includes interior and exterior plaster work, and fibreglass

More information

SECTION ORNAMENTAL ALUMINUM RAILING

SECTION ORNAMENTAL ALUMINUM RAILING SECTION 05730 ORNAMENTAL ALUMINUM RAILING PART 1 GENERAL 1.1 SECTION INCLUDES A. Decorative Wire Rope Railing 1.2 RELATED SECTIONS A. Section 03300 Cast-In-Place Concrete: Placement of sleeves cast in

More information

SECTION PREHUNG WOOD DOORS. Display hidden notes to specifier. (Don't know how? Click Here)

SECTION PREHUNG WOOD DOORS. Display hidden notes to specifier. (Don't know how? Click Here) SECTION 08 14 00 PREHUNG WOOD DOORS Display hidden notes to specifier. (Don't know how? Click Here) Copyright 2014-2016 ARCAT, Inc. - All rights reserved PART 1 GENERAL 1.1 SECTION INCLUDES A. French Doors.

More information

SECTION A. Product Data: Manufacturer's data sheets on each product to be used, including:

SECTION A. Product Data: Manufacturer's data sheets on each product to be used, including: Page 1 of 7 SECTION 083925 MECHANICAL ROOM FLOOD DOORS AND FRAMES **Note to Specifier** This specification contains component and configuration options. Where indicated, choose the appropriate choice for

More information

The fire resistance required for doors in this building is 1 (one) hour resistance in compliance with the below general specifications:

The fire resistance required for doors in this building is 1 (one) hour resistance in compliance with the below general specifications: Query No.1 ; we need more specs. about fire resistant doors Answer to Query No. 1: The fire resistance required for doors in this building is 1 (one) hour resistance in compliance with the below general

More information

SECTION SECTIONAL OVERHEAD DOORS 522 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS. Display hidden notes to specifier. (Don't know how?

SECTION SECTIONAL OVERHEAD DOORS 522 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS. Display hidden notes to specifier. (Don't know how? SECTION 08360 SECTIONAL OVERHEAD DOORS 522 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Glazed Aluminum

More information

Kolorines Glass Mosaic Tiles Project Specification

Kolorines Glass Mosaic Tiles Project Specification Kolorines Glass Mosaic Tiles Project Specification SUGGESTED SPECIFICATION Glass Mosaic Tile Installation for Swimming Pools NOTES TO SPECIFIER: 1. Specify PremiumPlus Thin-Set mixed with CustomFlex Additive

More information

Lot C Walkway and Bridge Repair Project #23829

Lot C Walkway and Bridge Repair Project #23829 Lot C Walkway and Bridge Repair Project #23829 PREPARED BY: Moody Nolan, Inc. MKEC Engineering Consultants Inc. Division 00 through Division 33 Bid Documents, August 13, 2012 SPECIFICATIONS for Lot C

More information

SECTION Project Closeout Operation and Maintenance Data.

SECTION Project Closeout Operation and Maintenance Data. SECTION 01740 WARRANTIES PART 1 GENERAL NOTE TO SPECIFIER: Modify this section upon advice from the Board's legal counsel and M-DCPS Department of Facilities Design and Quality Control. 1.01 SUMMARY A.

More information

SECTION WARRANTIES

SECTION WARRANTIES SECTION 01740 WARRANTIES PART 1 GENERAL NOTE TO SPECIFIER: Modify this section upon advice from the Board's legal counsel and M-DCPS Department of Facilities Design and Quality Control. 1.01 SUMMARY A.

More information

SECTION RESILIENT ATHLETIC SURFACING. B. Related Sections: Section(s) related to this section include:

SECTION RESILIENT ATHLETIC SURFACING. B. Related Sections: Section(s) related to this section include: CONNOR PowerDrop Page 1 SECTION 09624 RESILIENT ATHLETIC SURFACING PART 1 - GENERAL 1.01 SUMMARY A. Section includes: Resilient athletic surfacing, including [recycled] [virgin] rubber flooring B. Related

More information

SECTION COMPOSITE WALL PANELS PART 1 GENERAL 1.01 SECTION INCLUDES

SECTION COMPOSITE WALL PANELS PART 1 GENERAL 1.01 SECTION INCLUDES SECTION 07 4243 - PART 1 GENERAL 1.01 SECTION INCLUDES A. Composite wall panel system consisting of aluminum-faced composite panels in a rainscreen application as part of the assembly described below.

More information

AIR CONDITIONING SYRACUSE JUNIOR HIGH SCHOOL

AIR CONDITIONING SYRACUSE JUNIOR HIGH SCHOOL PROJECT MANUAL FOR AIR CONDITIONING DAVIS SCHOOL DISTRICT 1450 S. 2000 W. Syracuse, UT 84075 January 2017 BLANK PAGE TABLE OF CONTENTS DIVISION 01 GENERAL CONDITIONS 01 1000 Summary 01 2900 Payment Procedures

More information

UPHOLSTERED WALL SYSTEM UPHOLSTERED WALL SYSTEM

UPHOLSTERED WALL SYSTEM UPHOLSTERED WALL SYSTEM 09951 - UPHOLSTERED WALL SYSTEM 09951-1 PART ONE: GENERAL 1.1 Description UPHOLSTERED WALL SYSTEM 1.1.1 Work of this Section, as shown or specified, shall be provided by the Interior Contractor and shall

More information

HPW Protocol Reference Manual

HPW Protocol Reference Manual 1 HPW Protocol Reference Manual Change Log: UPDATED BY DATE UPDATED VERSION UPDATE DETAILS 2 Table of Contents: HIGH PERFORMANCE WALL ASSEMBLY... 4 THERMAL SPECIFICATION... 4 REQUIREMENTS FOR HPW INSULATION...

More information

B. Store products in dry spaces protected from the weather, with ambient temperatures maintained between 50 and 90 deg F (10 and 32 deg C).

B. Store products in dry spaces protected from the weather, with ambient temperatures maintained between 50 and 90 deg F (10 and 32 deg C). SECTION 09651 - RESILIENT TILE FLOORING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

SECTION EXTERIOR SOLID PHENOLIC RAINSCREEN PANELS

SECTION EXTERIOR SOLID PHENOLIC RAINSCREEN PANELS SECTION 074233 EXTERIOR SOLID PHENOLIC RAINSCREEN PANELS PART 1 - GENERAL 1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

SECTION A. Product Data: Manufacturer's data sheets on each product to be used, including:

SECTION A. Product Data: Manufacturer's data sheets on each product to be used, including: Page 1 of 8 SECTION 083921 PEDESTRIAN FLOOD DOORS AND FRAMES **Note to Specifier** This specification contains component and configuration options. Where indicated, choose the appropriate choice for your

More information

SECTION RESINOUS FLOORING

SECTION RESINOUS FLOORING SECTION 09705 PART I - GENERAL 1.01 DESCRIPTION A. Scope: Work of this Section includes all materials and installation necessary to provide resinous flooring system with integral cove base and top finish

More information

TENOCHCA HALL - FAN COIL UNITS, RESTROOM AND FINISH RENOVATION PROJECT NO

TENOCHCA HALL - FAN COIL UNITS, RESTROOM AND FINISH RENOVATION PROJECT NO SECTION 26 05 00 - BASIC ELECTRICAL REQUIREMENTS PART 1 - GENERAL REQUIREMENTS 1.1 RELATED DOCUMENTS A. The general conditions and Division 1 are part of this section and the contract for this work and

More information

SECTION Arisfor WallGuard

SECTION Arisfor WallGuard 1.1 GENERAL A. is a three component polymerized cementitious protective coating that can be applied to a variety of vertical interior and exterior substrates including: stucco, exterior gypsum sheathing,

More information

PRINCE GEORGE S COUNTY COURTHOUSE

PRINCE GEORGE S COUNTY COURTHOUSE MODIFICATIONS TO SECURITY AREAS PRINCE GEORGE S COUNTY COURTHOUSE 14735 Main Street, Upper Marlboro, Maryland 20772 100% CONSTRUCTION DOCUMENT SET TECHNICAL SPECIFICATIONS August 4, 2014 GWWO Inc./Architects

More information

Project No Project Manual. INGHAM COUNTY PROBATE COURT OFFICE FILE STORAGE EXPANSION Lansing, Michigan

Project No Project Manual. INGHAM COUNTY PROBATE COURT OFFICE FILE STORAGE EXPANSION Lansing, Michigan Project No. 1607 Project Manual for INGHAM COUNTY PROBATE COURT OFFICE FILE STORAGE EXPANSION Lansing, Michigan January 1, 2017 Architect Straub Pettitt Yaste Architects 850 North Crooks, Suite 200 Clawson,

More information

CONCRETE TILE PAVERS

CONCRETE TILE PAVERS Section 32 14 13 CONCRETE TILE PAVERS (1995 MasterFormat Section 02780) Note: This guide specification for the U.S. is for the installation of concrete tile paving units whose thickness are less than the

More information

CONCRETE & STAINING TECHS SIMPLY WARRANTY

CONCRETE & STAINING TECHS SIMPLY WARRANTY THIS IS A WARRANTY AND NOT INSURANCE. THIS WARRANTY DOES NOT TAKE THE PLACE OF YOUR INSURANCE OR YOUR HOMEOWNERS INSURANCE. This warranty is on the task. If the Home is sold, each successor in title to

More information

ARCHITECTURAL GUIDE SPECIFICATIONS - DESCRIPTIVE

ARCHITECTURAL GUIDE SPECIFICATIONS - DESCRIPTIVE ARCHITECTURAL GUIDE SPECIFICATIONS - DESCRIPTIVE MANNINGTON COLORFIELDS SHEET RUBBER FLOORING Section 09 65 16 Sheet rubber Flooring (Thermoset Rubber) Created May 2012 Mannington Mills, Inc. P. O. Box

More information